You are on page 1of 30

10 February 2014 1

Total Station
In-Built Programs
The instrument can perform some of the simple
surveying experiments, independently , such as..
Remote Elevation Measurement

Missing Line Measurement

Area Calculation

Data Collection
10 February 2014 2
Experimental Procedures

10 February 2014 3
Remote Elevation Measurement
To obtain elevation K
to the point at which
setting the target
Prism is not
possible, the REM
Program is useful.

Place the prism at any point on the ground in the same vertical plane of the target

10 February 2014 4
The procedure is as follows:

10 February 2014 5
10 February 2014 6
10 February 2014 7
MISSING LINE MEASUREMENT (MLM)

To obtain the measurement


for horizontal distance
(dHD), slope distance
(dSD), elevation (dVD) and
horizontal angle (HR)
between two target
prisms, the MLM
programme is useful.

The MLM mode has two modes


MLM-1 (A-B, A-C): Measurement is A-B, A-C, A-D, ..
MLM-2 (A-B, B-C): Measurement is A-B, B-C, C-D, ..

10 February 2014 8
The procedure for MLM 1 is as follows.

10 February 2014 9
10 February 2014 10
10 February 2014 11
The procedure for the MLM -2 is Completely same as MLM 1.

10 February 2014 12
Area Calculation
To calculate area of a
closed figure AREA
Programme is useful.
There are two
methods to calculate
the area of the figure.
Area calculation from
coordinate data file.
Area calculation from
measured data

10 February 2014 13
The procedure for the area calculation from measured data is as
follows.

10 February 2014 14
10 February 2014 15
To change the displayed area unit Press F3 (UNIT) key and select a unit by pressing F1 -
F4 keys
10 February 2014 16
Character of the Surveying
1.Field Work.
2.Office Work.

The field work consists of the measurement of angles,


distances and elevations and the keeping of a record of what
has been done in the form of field notes (DATA COLLECTION)

10 February 2014 17
Data Collection ..
Need..

For true representation of field conditions.


To plot the plans and sections with desired accuracy

10 February 2014 18
Types of Data Collection
Conventional Methods

Electronic Methods

10 February 2014 19
Data Collection.. TOTAL STATION
Electronic Method
(Microprocessor & Wave Propagation)

Stored into the Internal Memory


(Read ,Perform & Record)

10 February 2014 20
DATA COLLECTION..Modes
Distance Mode

Angle Mode

Coordinate Mode

10 February 2014 21
Data Collection..
Coordinate Mode (NEZ)..

Select the Instrument Station


(S W Corner)

10 February 2014 22
Data Collection..Cont..
Carrying out BM
Press Menu key
Goto page 2
input the instrument height and reflector height
Input the station coordinates as ( ex: 1000, 1000, 300 m).

10 February 2014 23
Data Collection..Cont..
Sight the prism held on B.M.

The difference in Z will be displayed

Depending on the line of sight, add/subtract accordingly


the difference in Z to the R.L. of the B.M. to get the R.L.
of the station point

10 February 2014 24
Data Collection..Cont..
RECORD
Press MENU key.
Create a file in coordinate (NEZ) mode.
Input occupied point data and Back sight data/
Direction.
Go to Side shots and orient the telescope towards the
prism held at various intermediate station points as per
the visibility.

10 February 2014 25
Data Collection..Cont..
Before going to shift the instrument, note down the last
point data as change point. A peg mark of identification
of the change point should be fixed.

Shift the instrument to the change point and set it there.

Input last point data as occupied point data. Again, after


input the instrument height and reflector height, orient
the telescope to the back sight station and continue the
process to other points.

10 February 2014 26
INSTRUCTIONS FOR OPERATION AND MAINTENANCE :

The following are the instructions to be followed for better results.

Instructions for Instrument Maintenance :

Always bring foot screws to the center of its run before


levelling it up.
Always see that both the locks are released before turning the
instrument.
Make sure that the clamps of the tripod are fixed firmly.
Hold the handle of the instrument before fixing and at the time
when it is to be removed for further shiftngs.

10 February 2014 27
Batteries should be discharged for every ten charging
completely, so that the life of the batteries will be increased.
Always cleans the lens with cloth after the days work is finished.
Make sure that the legs of tripod (bottom shoe) should be
cleaned daily.
Close the foot screws completely after the instrument is to be
changed its position.
Fix the instrument as per its position specified in the box and
close the box.

10 February 2014 28
Instructions for Operations Maintenance :

When ever we are working in Distance mode ( ) or Co-ordinate mode ( )


to come out press (Ang) button key (Esc-Escape key will not work).
Make sure that the measured filed is downloaded first to out PC and they
only it is to be deleted.
Always select the occ-point / BS point from the list only and then press
enter.
When ever Reflector Height is changed during side shot measurement
make sure that the changed height is edited properly before measuring.
Orientation is must after every shifting.
To make internal display unit on, press * (star) button and then press F1.
If it is required to change prism constant from 0 to -30, press * (star)
button and then press PSM/PPM and then change the prism constant by
pressing EDIT .
10 February 2014 29
THANK YOU

10 February 2014 30