MUNICIPALIDAD PROVINCIAL DE LA CONVENCION

GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

INFORME MENSUAL

DEL 01 AL 31 DE JULIO DEL 2015

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS DE LA I.E. N


51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"

Residente de Obra ARQ JORGE REYNALDO PALIZA JARA (7mo)

Inspector de Obra ING.


: JORGE W. PEZO VILLENA

2015
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS
GENERALIDADES
A) GENERALIDADES.

1. Nombre de la Obra.- "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,
PROVINCIA DE LA CONVENCIN CUSCO"
2. Unidad Gestora.- MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN.
3. Unidad Ejecutora.- MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN.
4. Secuencia Funcional.-
SECUENCIA FUNCIONAL 0112
PROGRAMA: 0090
PROD-PROY 2062364
ACT-AI-OBRA 4000038
FUNCION 0022
DIVIS-FUNC 0047
GRUP-FUNC 0104
META: 0001
FINALIDAD OO198481
RUBRO 0018
ESPEC.- GASTO 2.6.2.2.2.3

5. Ubicacin.-
Localidad. I.E.N51027 Provincia. LA CONVENCIN
Distrito. SANTA ANA Regin. CUSCO

6. Ao Presupuestal.- 2012

7. Datos Generales.-
Del Proyectista:
Nombres: WILBERT MEDINA BARZOLA
CIP/CAP: CIP. N 52689
Consultor de Obras: Reg. Nac. N C-1950

Del Residente (e):


Nombres: ARQ JORGE REYNALDO PALIZA JARA (7mo)
CIP/CAP: CAP. N 16257
DNI: 23805549
Telfono/Celular: RPC-997435348- MOV-975155092

Del Supervisor:
Nombres: ING. JORGE W. PEZO VILLENA
CIP/CAP: 36375
DNI: 23820454
Telfono/Celular: 984802350

8. Modalidad de Ejecucin.-
Administracin Directa.

9. Fuente de Financiamiento.-
Recursos Ordinarios
Canon y Sobrecanon

10. Presupuesto Original Aprobado.- S/. 9,892,391.35


Costo Directo S/. 8,307,447.15
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS
GENERALIDADES
Gastos Generales S/. 912,172.17
Gastos de Supervisin S/. 341,117.92
Gastos de Expediente S/. 229,616.33
Gastos de Liquidacin S/. 102,037.78
11. Presupuesto Adicional Aprobado.- S/. 1,523,757.14
Costo Directo S/. 1,290,126.92
Gastos Generales S/. 170,038.73
Gastos de Supervisin S/. 63,591.50
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS
GENERALIDADES
12. Presupuesto Segunda Adicional Aprobado S/. 1,865,967.56
Costo Directo S/. 1,536,828.59
Gastos Generales S/. 206,879.96
Gastos de Supervisin S/. 75,567.01
Gastos de Expediente S/. 8,743.81
Gastos de Liquidacin S/. 37,948.19
13. presupuesto total aprobado S/. 13,282,116.05
13. Valorizacin Fsica de Corte de Obra (DEL 12 DE ENERO AL 31 DE ENERO DEL 2015)

a. Valorizacin del Mes Informado. S/. %


Valorizacin estructuras segn Presupuesto Aprobado : S/. 2,937.83 0.02%
Valorizacin arquitectura segn Presupuesto Aprobado : S/. 1,342.20 0.01%
Valorizacin Instal. Sanitarias segn Presupuesto Aprobado : S/. 0.00 0.00%
Valorizacin Instal. electricas segn Presupuesto Aprobado : S/. 0.00 0.00%
Valorizacin de Implementos y Equipamiento : S/. 0.00 0.00%
Valorizacin de Capacitacion y Asistencia Tcnica : S/. 0.00 0.00%
Costo directo : S/. 4,280.03 0.03%
Gastos Generales: S/. 474.53 0.00%
Gastos de Supervisin: S/. 173.33 0.00%
Gastos de Expediente Tecnico S/. 0.00 0.00%
Gastos de Liquidacin: S/. 0.00 0.00%
Total Valorizacin : S/. 4,927.89 0.04%

b. Valorizacin Acumulada. S/. %


Valorizacin estructuras segn Presupuesto Aprobado : S/. 4,050,831.07 30.50%
Valorizacin arquitectura segn Presupuesto Aprobado : S/. 3,013,562.88 22.69%
Valorizacin Instal. Sanitarias segn Presupuesto Aprobado : S/. 327,711.41 2.47%
Valorizacin Instal. electricas segn Presupuesto Aprobado : S/. 381,031.21 2.87%
Valorizacin de Implementos y Equipamiento : S/. 386,355.69 2.91%
Valorizacin de Capacitacion y Asistencia Tcnica : S/. 0.00 0.00%
Costo directo : S/. 8,159,492.26 61.43%
Gastos Generales: S/. 904,643.49 6.81%
Gastos de Supervisin: S/. 330,438.98 2.49%
Gastos de Expediente Tecnico S/. 84,000.00 0.63%
Gastos de Liquidacin: S/. 0.00 0.00%
Total Valorizacin : S/. 9,478,574.74 71.36%

14. Ejecucin Financiera : S/. %


Ejecucin acumulada aos 2008 - 2014 - 2015: Junio S/. 12,154,962.05 91.51%
Ejecucin Julio 2015: S/. 95,169.64 0.72%
Ejecucin acumulada a Julio 2015 : S/. 12,250,131.69 92.23%
Saldo al 31 de Mayo del 2015 : S/. 1,031,984.36 7.77%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

B.- SUSTENTO DOCUMENTARIO DE OBRA:

1. Aprobacin del Expediente Tcnico.


RESOLUCION DE ALCALDIA N 628-2012-A-OSG-MPLC

2. Aprobacin del Adicional N 1.


RESOLUCION DE ALCALDIA N 338-2014-A-OSG-MPLC

3. Presentacion de 2da adicional Reformulado


RESOLUCION DE ALCALDIA N 711-2014-A-OSG-MPLC

4. Acta de entrega del Terreno.


Folio 02 del cuaderno 01 de Octubre 2012.

5. Acta de Inicio de Obra.


Folio 03 del Cuaderno 01 de Octubre 2012.

6. Declaratoria de Viabilidad.
RESOLUCION DIRECTORAL N 003-2011-EF/68.01 Formato SNIP 16
MONTO: S/. 9516321.00

7. Acta de Reinicio de Obra.


Folio 1436 del Cuaderno 12 de Enero 2015.

8. Cdigo del Banco de Proyectos.


86920
MUNICIPALIDAD PROVINCIAL DE LA CO
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

FICHA TECNICA

DEL 01 AL 31 DE JULIO DEL 2015


DATOS GENERALES
UBICACIN NOMBRE DEL PROYECTO:
DPTO: CUSCO
PROV: LA CONVENCION "MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA C
DIST: SANTA ANA PROVINCIA DE LA CONVENCIN CUSCO"
LOC: QUILLABAMBA
PERFIL EXPEDIENTE TECNICO

CODIGO SNIP 86920 RES. APROB. RESOLUCION DE ALCALDIA N 628-2012-A-OSG-MPLC

MONTO S/. 9,516,321.00 MONTO. S/. 9,892,391.35


FECHA 6/12/2019 FECHA. 11/17/2012
1 RA AMPLIACION DE PLAZO Y PRESUPUESTAL
RES. APROB. RESOLUCION DE ALCALDIA N 338-2014-A-OSG-MPLC
MONTO. S/. 1,523,757.14
FECHA. 7/7/2014
2 DA AMPLIACION DE PLAZO Y PRESUPUESTAL
RES. APROB. RESOLUCION DE ALCALDIA N 711-2014-A-OSG-MPLC
MONTO. S/. 1,865,967.56
FECHA. 12/16/2014
CADENA FUNCIONAL 2012
SEC. FUNC. FUNCION PROGRAMA ACT. PROYECTO COMPONENTE META FINALIDAD
0112 22 90
CADENA FUNCIONAL 2013
SEC. FUNC. FUNCION PROGRAMA ACT. PROYECTO COMPONENTE META FINALIDAD
0112 22 90 66
CADENA FUNCIONAL 2014
SEC. FUNC. FUNCION PROGRAMA ACT. PROYECTO COMPONENTE META FINALIDAD
0112 22 90 66
INFORMACION DE AGENTES

N RESPONSABLE DE OBRA
MUNICIPALIDAD PROVINCIAL DE LA CO
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

FICHA TECNICA
3 ING.JORGE W. PEZO VILLENA
4 ARQ. JORGE REYNALDO PALIZA JARA
PLAZO EJECUCION
FECHA DE INICIO: 10/1/2012 FECHA DE REINICIO: 1/12/2015 FECHA DE CONCLUSION:
METAS: PRESUPUESTO :
ESTRUCTURAS S/. 5,530,147.48
ARQUITECTURA S/. 3,592,008.84
INSTALACIONES SANITARIAS S/. 356,339.19
INSTALACIONES ELECTRICAS S/. 425,131.80
IMPLEMENTACION Y EQUIPAMIENTO S/. 1,338,239.86
CAPACITACION Y ASISTENCIA TECNICA A LA PLANA DOCENTE S/. 48,700.00
COSTO DIRECTO S/. 11,290,567.17
GASTOS GENERALES S/. 1,251,785.99
SUPERVISION S/. 457,239.67
EXPEDIENTE TECNICO S/. 229,616.33
GASTOS DE LIQUIDACION S/. 52,906.89
PRESUPUESTO TOTAL MODIFICADO S/. 13,282,116.05
MUNICIPALIDAD PROVINCIAL DE LA CO
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

FICHA TECNICA

ESUMEN INFORME MENSUAL


AVANCE FISICO CON RESPECTO AL PRESUPUESTO TOTAL
PROGRAMADO EJECUTADO SEGN
MES MAYORES METRADOS PARTIDAS NUEVAS DEDUCTIVOS EJECUTADO
EXPEDIENTE TECNICO

VALORIZ. % VALORIZ. % VALORIZ. % VALORIZ. % VALORIZ. % VALORIZ. %


AO 2014
DIC-14 12,536,906.05 94.39% 8,967,529.30 67.52%
ENE-15 450,000.00 3.39% 16,247.10 0.12% - - 0.00% - - 16,247.10 0.12%
FEB-15 154,000.00 1.16% 110,309.33 0.83% - - 0.00% - - 110,309.33 0.83%
MARZO-17 141,210.00 1.06% 156,655.73 1.18% - - 0.00% - - 156,655.73 1.18%

TOTAL 13,282,116.05 100.00% 9,250,741.46 69.65% - - 0.00% - - 283,212.16 2.13%

CURVA AVANCE FISICO


120.0% 100.00%
90.00%
100.0% Column T
80.00%
Column S 70.00%
80.0%
60.00%
60.0% 50.00%
40.00%
40.0% 30.00%
120.0% 100.00%

Column T
MUNICIPALIDAD PROVINCIAL DE LA CO
90.00%
100.0% 80.00%
GERENCIA DE INFRAESTRUCTURA
80.0%
Column S DIVISION DE OBRAS70.00%
60.00%
60.0% FICHA TECNICA 50.00%
40.00%
40.0% 30.00%
20.00%
20.0% 10.00%
0.00%
0.0% AO 2014
AO 2014 DIC-14 ENE-15 FEB-15 MARZO-17

OCURRENCIAS

SE DEJA TRABAJOS A NIVEL DE EJECUCION DE ACCESOS SE REALIZO EL CORTE DE

.
OVINCIAL DE LA CONVENCION
DE INFRAESTRUCTURA
ISION DE OBRAS

HA TECNICA

31 DE JULIO DEL 2015


TOS GENERALES
DEL PROYECTO: UNIDAD EJECUTORA

GERENCIA DE INFRAESTRUCTURA-DIVISION DE OBRAS


DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,
CONVENCIN CUSCO" MODALIDAD: ADMINISTRACION DIRECTA

ENTE TECNICO VARIACION VIABILIDAD PLAZO EJECUCION

ACUMULADO 3.95% 365 DIAS CALENDARIOS

MONTO:

E PLAZO Y PRESUPUESTAL VARIACION VIABILIDAD PLAZO EJECUCION


ACUMULADO 19.96% 304 DIAS CALENDARIO
S/. 11,416,148.49

E PLAZO Y PRESUPUESTAL VARIACION VIABILIDAD PLAZO EJECUCION


ACUMULADO 39.57% 153 DIAS CALENDARIO
S/. 13,282,116.05

RMACION DE AGENTES

CARGO ESPECIALIDAD COLEGIATURA RESOLUCION


OVINCIAL DE LA CONVENCION
DE INFRAESTRUCTURA
ISION DE OBRAS

HA TECNICA
Inspector de Obra Ing. Civil
Residente de Obra Arquitecto
PLAZO EJECUCION
5/31/2015 TIEMPO DE EJECUCION 5 MESES FECHA DE TERMINO REAL:
ESTRUCTURA DE PRESUPUESTO EXP. TEC.
PRESUPUESTO TOTAL PRESUPUESTO TOTAL
Costo Directo 11,290,567.17 Costo Directo 11,290,567.17
Gastos Generales 11.09 % 1,251,785.99 Gastos Generales 1,251,785.99
Gastos de Inspeccin 4.05% 457,239.67 Gastos de Inspeccin 457,239.67
Expediente Tcnico 1.73% 229,616.33 Expediente Tcnico 229,616.33
Gastos de Liquidacin 0.47 % 52,906.89 Gastos de Liquidacin 52,906.89
TOTAL S/. S/. 13,282,116.05 TOTAL S/. S/. 13,282,116.05
OVINCIAL DE LA CONVENCION
DE INFRAESTRUCTURA
ISION DE OBRAS

HA TECNICA

L PRESUPUESTO TOTAL AVANCE FINANCIERO

EJECUTADO PROGRA
EJECUTADO ACUMULADO AVANCE FINANCIERO EJECUTADO
ACUMUL. M. ACUM.

% % VALORIZ. % % ACUMUL. MONTO % % ACUMUL.


84.21%
67.52% 94.39% 352,399.47 2.65% 86.86%
67.64% 97.78% 16,247.10 0.12% 0.12% 30,426.00 0.23% 87.09%
68.47% 98.94% 126,556.43 0.95% 0.95% 98,324.00 0.74% 87.83%
69.65% 100.00% 283,212.16 2.13% 2.13% 200,000.00 1.51% 89.34%

2.13% - 0.00% 0.00% 681,149.47 5.13% 5.13%


Nota: Los Gastos financieros estan a base al compromiso de gastos

CURVA DE AVANCE FISICO VS AVANCE FINANCIERO


100.00%
90.00%
80.00%
70.00% Column W

60.00%
Polynomial (Column W)
50.00%
40.00% Column AB

30.00%
100.00%
OVINCIAL DE LA CONVENCION
90.00%
80.00%
DE INFRAESTRUCTURA
ISION DE OBRAS70.00% Column W

60.00%
Polynomial (Column W)

HA TECNICA 50.00%
40.00% Column AB

30.00%
20.00%
10.00%
0.00%
AO 2014 DIC-14 ENE-15 FEB-15 MARZO-17

ACCIONES

SE REALIZO EL CORTE DE OBRA CON PRESENCIA DE LOS INGENIEROS RESPONSABLES ,AUTORIDADES Y HABITANTES DE LA COMUNIDAD DE YOYATO
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA

DIVISION DE OBRAS

Descripcin de la Obra en Ejecucin.-

Descripcin de los trabajos ejecutados:

- Las actividades a realizarse en este mes son:Rasqueteo y desmanchado de muro para Pintado de Auditorium , como tambien se ha
ejecutado los dados de sostenimiento de las montantes de evacuacion de aguas pluviales, los cuales tambien se ha tarrajeado con C:A
cm , asu vez se ha enchapado con piso ceramico 30x30 anbientes como los SSHH de Auditorium,Direccion Antigua,y Lavoratorio del
Pabellon N06,tambien se han ejecuta trabajos de instalaciones sanitarias en tamque elevado, como tambien se coloco las tuberias de
bajada pvc -sap 4"para lluvias (montantes), como tambien se ha realizado la implementacion de los centros de computo tamto de pr
y secundaria con sus respectivos escritorios.

Avance Fisico Valorizado:

AVANCE FISICO ACUMULADO ANTERIOR 9,473,646.85 71.33%


AVANCE FISICO ACTUAL 4,927.89 0.04%
AVANCE FISICO ACUMULADO 9,478,574.74 71.36%
SALDO 3,803,541.32 28.64%

Avance Financiero Valorizado:

AVANCE FINANCIERO ACUMULADO ANTERIOR 12,154,962.05 91.51%


AVANCE FINANCIERO ACTUAL 95,169.64 0.72%
AVANCE FINANCIERO ACUMULADO 12,250,131.69 92.23%
SALDO 1,031,984.36 7.77%

Relacin de Maquinaria y Equipo utilizado en la obra.-

TOTAL OBSERVACION
ITEM EQUIPO DESCRIPCION DEL EQUIPO PLACA O SERIE
HM COMB ES
0.00 0.00
VEHICULO

PESADOS

###
S

###

SUB TOTAL 0.00 0.00

Descripcin de los Recursos Humanos.

CARGO CANTIDAD
INSPECTOR 1.00
RESIDENTE 1.00
ASISTENTE TCNICO 1.00
ASISTENTE ADMINISTRATIVO 1.00
TOPOGRAFO 0.00
ALMACENERO 0.00
MAESTRO DE OBRA I 0.00
GUARDIAN 1.00
OPERARIO 1.00
OFICIALES 0.00
PEONES 2.00

Descripcin de los plazos:


o Fecha de Inicio de obra : 01 de Octubre del 2012
o Fecha de Reinicio de obra : 12 de Enero 2015.
Planillas de Metrados.-

PARTIDAS EJECUTADAS DEL PROYECTO


o y desmanchado de muro para Pintado de Auditorium , como tambien se ha
evacuacion de aguas pluviales, los cuales tambien se ha tarrajeado con C:A E=1.5
nbientes como los SSHH de Auditorium,Direccion Antigua,y Lavoratorio del
ones sanitarias en tamque elevado, como tambien se coloco las tuberias de
en se ha realizado la implementacion de los centros de computo tamto de primaria

11416148.49
e Enero 2015.
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
CONCLUSIONES Y RECOMENDACIONES
.
21. Conclusiones y Recomendaciones.-

Observaciones:
La Obra empezo con deficiencias al inicio del ao, comco hay un cambio de gobierno local, el inicio de una obra es lenta, por que el personal que se toma son

gente nueva, no esta al tanto de la ejecucion de la obra.


De acuerdo a las disposiciones del Gerente de Obras, el personal de obra estuvo en el ordenamiento de los materiales de obra, ya que anteriormente el
Residente de Obra dejo en un desorden total, sin tener en cuenta que esta obra es de continuidad,
Hay muchas deficiencias en el ejecucion de la Obra, por disposicion de la Gerencia de Obra se tuvo que tomar un grupo de tecnico para el Infor de Corte, en la
cual detalladamente presentaran lo real que se gasto el presupuesto total y en que se gastaron los adicionales que fueron dos.

Se esta elaborando el Expediente Modificado N03 el cual sera presentado a la Supervision para evaluacion y aprobacion respectiva posteriorme sera remitido a
la Oficina de Programacion de Inversiones para registro respectivo.

Recomendaciones:

Se presento a la oficina de Abastecimiento una serie de requerimientos correspondientes a insumos y servicios para la culminacion de la Obra

, en la cual se presento retardos en la adquisiocion y contratacion de servicios los cuales afectaron el normal avance fisico de las partidas programadas.

CONCLUSIONES:

Para el presente informe de corte se lleg a un Avance Fsico de 71.17 % Por las razones anteriormente citadas.

El avance financiero tambien es de S/. 12,109,162.05 porcentualmente haciende a 91.17%

Para el logro optimo de la ejecucion de una obra debe haber un mayor apoyo por parte del departamento de logstica y como tambin de las dems reas
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS
RESUMEN DE VALORIZACION DE AVANCE DE OBRA N 32 DEL MES DE JUlIO 2015

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

AVANCE ACUMULADO
PRESUPUESTO
ITEM VALORIZACION ANTERIOR ACTUAL ACUMULADO
S/. VALORIZADO % VALORIZADO % VALORIZADO %
1 ESTRUCTURAS 5,530,147.48 4,047,893.24 73.20% 2,937.83 0.05% 4,050,831.07 73.25%

2 ARQUITECTURA 3,592,008.84 3,012,220.68 83.86% 1,342.20 0.04% 3,013,562.88 83.90%

3 INSTALACIONES SANITARIAS 356,339.19 327,711.41 91.97% 0.00 0.00% 327,711.41 91.97%

4 INSTALACIONES ELECTRICAS 425,131.80 381,031.21 89.63% 0.00 0.00% 381,031.21 89.63%

5 IMPLEMENTACION Y EQUIPAMIENTO 1,338,239.86 386,355.69 28.87% 0.00 0.00% 386,355.69 28.87%

CAPACITACION Y ASISTENCIA TECNICA A LA PLANA


6 48,700.00 0.00 0.00% 0.00 0.00% 0.00 0.00%
DOCENTE
COSTO DIRECTO 11,290,567.17 8,155,212.23 72.23% 4,280.03 0.04% 8,159,492.26 72.27%
GASTOS GENERALES 1,251,785.99 904,168.96 474.53 904,643.49
SUPERVISION 457,239.67 330,265.65 173.33 330,438.98
EXPEDIENTE TECNICO 229,616.33 84,000.00 0.00 84,000.00
GASTOS DE LIQUIDACION 52,906.89 0.00 0.00 0.00
PRESUPUESTO TOTAL MODIFICADO 13,282,116.05 9,473,646.85 71.33% 4,927.89 0.04% 9,478,574.74 71.36%
INCIAL DE LA CONVENCIN
AESTRUCTURA PBLICA
ON DE OBRAS
E DE OBRA N 32 DEL MES DE JUlIO 2015

NTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SALDO

VALORIZADO %
1,479,316.41 26.75%

578,445.96 16.10%

28,627.78 8.03%

44,100.59 10.37%

951,884.17 71.13%

48,700.00 100.00%

3,131,074.91 27.73%
347,142.50
126,800.69
145,616.33
52,906.89
3,803,541.31 28.64%
Und.
Item Descripcin partida

01.00.00 ESTRUCTURAS

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.01 CONSTRUCCIONES PROVISIONALES

01.01.01.01 CARTEL DE OBRA 2.40X3.60 PZA


01.01.01.02 ALMACEN OFICINA Y CASETA DE GUARDIANIA MES
01.01.01.01 CERCO PROVICIONAL DE CALAMINA H =2,00 m M
01.01.01.02 CONSTRUCCION DE ALMACEN PROVICIONAL M2
01.01.02 INSTALACIONES PROVISIONALES
01.01.02.01 AGUA PARA LA CONSTRUCCION GLB
01.01.03 TRABAJOS PRELIMINARES
01.01.03.01 LIMPIEZA DE TERRENO MANUAL M2

01.01.04 REMOCIONES

01.01.04.01 DESMONTAJE DE PUERTAS PZA


01.01.04.02 DESMONTAJE DE VENTANAS PZA
01.01.04.03 DESMONTAJE DE VENTANAS - PUERTAS UND
01.01.04.04 DESMONTAJE DE APARATOS SANITARIOS UND
01.01.04.05 DESMONTAJE TECHO ETERNIT/CALAMINA M2

01.01.05 DEMOLICIONES

01.01.05.01 DEMOLICION MUROS DE ADOBE m3


01.01.05.02 DEMOLICION MUROS DE LADRILLO KK CABEZA M2
01.01.05.03 DEMOLICION DE LOSA ALIGERADA H=0.20M M2
01.01.05.04 ROTURA DE LOSA EN VOLADIZO m3
01.01.05.05 DEMOLICION COLUMNAS Y VIGAS DE CONCRETO m3
01.01.05.06 DEMOLICION DE PISO DE CONCRETO INC.F.P. LOSA DEPORTIVA M2
01.01.05.07 DEMOLICION DE SOBRECIMIENTOS m3
01.01.05.08 DEMOLICION DE CIMIENTOS DE CONCRETO m3
01.01.05.09 DEMOLICION DE CIMIENTOS DE MURO DE ADOBE m3
01.01.05.10 DEMOLICION DE ESCALERAS m3
01.01.05.11 DEMOLICION DE GRADAS DE CONCRETO m3
01.01.05.12 DEMOLICION DE BEBEDERO Y URINARIO DE CONCRETO M
01.01.05.13 DEMOLICION DE CERCO PERIMETRICO MURO DE LADRILLO SOGA M
01.01.05.14 PICADO DE CERAMICO M2
01.01.05.15 RASQUETEO Y DESMANCHADO DE MURO PARA PINTADO M2
01.01.05.16 ACARREO INTERNO, MAT.PROCEDENTE DE DEMOLICION. m3
01.01.05.17 ELIMINACION DE DEMOLICIONES m3
01.01.05.18 DEMOLICION DE MUROS DE LADRILLO KK SOGA M2

01.01.06 MOVILIZACIN DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS

01.01.06.01 MOVILIZACION , MAQUINARIAS Y HERRAMIENTAS GLB

01.01.07 TRAZO, NIVELES Y REPLANTEO

01.01.07.01 TRAZO Y REPLANTEO PRELIMINAR M2


01.01.07.02 REPLANTEO DURANTE EL PROCESO M2

01.02 SEGURIDAD Y SALUD

01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALU GLB

01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL und


01.02.03 EQUIPO DE PROTECCION COLECTIVA GLB
01.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB
01.02.05 CAPACITACION EN SEGURIDAD Y SALUD GLB
01.02.06 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN EL TRA GLB
02.00.00 ESTRUCTURAS

02.01.00 MOVIMIENTO DE TIERRAS

02.01.01 EXCAVACIONES

02.01.01.01 EXCAVACION MASIVA C/MAQU1NA m3


02.01.01.02 EXCAV.ZANJAS Y ZAPATA Rt<2kg/cm2 h=1.5m m3
02.01.01.03 EXCAVACION DE ZANJA PARA CISTERNA RT<2kg/cm2 m3
02.01.01.04 EXCAVACION DE TERRENO NATURAL EN PATIOS Y VEREDAS m3
02.01.01.05 EXCAVACION DE ZANJA PARA BUZON DE INSPECCION m3
02.01.02 CORTES
02.01.02.01 CORTE A MAQUINA m3

02.01.03 RELLENOS

02.01.03.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3

02.01.04 NIVELACION INTERIOR Y APISONADO

02.01.04.01 CONFORMACION DE TERRENO HASTA NIVEL DE SUBRASANTE M2


02.01.04.02 AFIRMADO DE 3" EN INTERIORES,PATIOS Y VEREDAS M2
02.01.04.03 NIVELACION INTERIOR Y APISONADO PARA F.PISO, PATIO Y VEREDAS M2

02.01.05 EL1MINACIO DE MATERIAL EXCEDENTE

02.01.05.01 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES m3


02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3

02.02 OBRAS DE CONCRETO SIMPLE

02.02.01 CIMIENTOS CORRIDOS

02.02.01.01 CIMIENTOS CORRIDOS 1:10 + 30 % P.G. fe >=100Kg/cm2 M3


02.02.01.02 SOLADO PARA ZAPATAS e=2", 1:12 CEM/HORM M2
02.02.01.03 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M2

02.02.02 SOBRECM1ENTO|

02.02.02.01 SOBRECIMIENTO, CONCRETO 1:8 + 25% P.M. Fe >=100Kg/cm2 m3


02.02.02.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2

02.02.03 BASE DE CONCRETO

02.02.03.01 BASE DE CONCRETO 1:8 + 25% P.M. m3


02.02.03.02 BASE DE CONCRETO, ENCOF. Y DESENCOF. M2

02.02.04 SARDINEL

02.02.04.01 SARDINEL, CONCRETO h=0.50M, fc= 175 Kg/cm2 Acabado 1:2 m3


02.02.04.02 SARDINEL, ENCOFRADO Y DESENCOFRADO M2

02.02.05 OTROS CONCRETOS CIMPLE


02.02.05.01 SUBZAPATA MEZCLA 1:10 + 30 % P.G. (fc=100 kg/cm2) m3
02.02.05.02 FALSO PISO MEZCLA 1:8 e=4" M2

02.03 OBRAS DE CONCRETO ARMADO

02.03.01 CIMIENTOS REFORZADOS

02.03.01.01 CIMIENTOS REFORZ. CONCRETO F'c = 210 kg/cm2 m3


02.03.01.02 CIMIENTOS REFORZ. ACERO Fy=4,200 kg/cm2 KG

02.03.02 ZAPATAS |

02.03.02.01 ZAPATAS.- CONCRETO 210 kg/cm2 m3


02.03.02.02 ZAPATAS.- ACERO Fy=4200 kg/cm2 KG

02.03.03 VIGAS DE CIMENTACION

02.03.03.01 VIGAS DE CIMENT.- CONC. 210 kg/cm2 m3


02.03.03.02 VIGAS DE CIMENT.- ENCOF. Y DESENCOF M2
02.03.03.03 VIGAS DE CIMENT.- ACERO Fy=4,200 kg/cm2 KG

02.03.04 SOBRECIMIENTOS REFORZADOS

02.03.04.01 SOBREC. REF. CONCRETO 1:8+25% P.M. m3


02.03.04.02 SOBREC. REF. ENCOFRADO Y DESENCOFRADO M2
02.03.04.03 SOBREC. REF.- ACERO Fy=4,200 kg/cm2 KG
02.03.05 MUROS REFORADOS
02.03.05.01 MUROS DE CONTENC.- CONCRETO 210 kg/cm2 m3
02.03.05.02 MUROS DE CONTENC.- ENCOF. Y DESENCOFRADO [DOS CARAS) M2
02.03.05.03 MUROS DE CONT.- ACERO Fy=4,200 kg/cm2 KG

02.03.06 COLUMNAS Y PLACAS

02.03.06.01 COLUMNAS.- CONCRETO 210 kg/cm2 - 2 pisos m3


02.03.06.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.06.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG

02.03.07 VIGAS

02.03.07.01 VIGAS.- CONCRETO 210 kg/cm2 - 2 PISOS M3


02.03.07.02 VIGAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.07.03 VIGAS.- ACERO Fy=4200 kg/cm2 KG

02.03.08 LOSA MACIZA |

02.03.08.01 LOSAS MACIZAS.- CONC.210kg/cm2-2 PISOS M3


02.03.08.02 LOSAS MACIZAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.08.03 LOSAS MACIZAS.- ACERO Fy=4,200 kg/cm2 KG

02.03.09 LOSA ALIGERADA

02.03.09.01 LOSA ALIGERADA - CONCRETO 210 kg/cm2 - 2 PISOS m3


02.03.09.02 LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADO M2
02.03.09.03 LOSA ALIGERADA.- ACERO Fy=4,200 kg/cm2 KG
02.03.09.04 LOSA ALIGERADA.- LADR. HUECO 15x30x30 und
02.03.09.05 LOSA ALIGERADA.- PLASTOFORMO DE 3.00x0.15x0.30m und

02.03.10 ESCALERAS

02.03.10.01 ESCALERAS.-CONCRETO 210kg/cm2 m3


02.03.10.02 ESCALERAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.10.03 ESCALERAS.- ACERO Fy=4200 kg/cm2 KG
02.03.11 GRADAS 1

02.03.11.01 GRADAS EN PISO, CONCRETO F'c=175 kg/cm2. M2


02.03.11.02 GRADAS EN PISO, ENCOFRADO Y DESENCOFRADO M2
02.03.11.03 GRADAS EN PISO, ACERO Fy=4,200 kg/cm2 KG

02.03.12 CISTERNAS SUBTERRANEAS

02.03.12.01 CISTERNA, CONCRETO F'c=210 kg/cm2. m3


02.03.12.02 CISTERNA, ENCOFRADO Y DESENCOFRADO M2
02.03.12.03 CISTERNA, ACERO Fy=4200 kg/cm2 KG

02.03.13 TANQUE ELEVADO

02.03.13.01 TANQUES ELEVADOS.- CONCRETO 210 kR/cm2 m3


02.03.13.02 TANQUES ELEVADOS.- ENCOFRADO Y DESENCOFR M2
02.03.13.03 TANQUES ELEVADOS.- ACERO Fy=4,200 kg/cm2 KG

02.03.14 BUZON DE INSPECCION PARA DRENAJE

02.03.14.01 BUZON DE INSPECCION.- CONCRETO 210 kg/cm2 m3


02.03.14.02 BUZON DE INSPECCION.- ENCOFRADO Y DESENCOFRADO M2
02.03.14.03 BUZON DE INSPECCION.- ACERO Fy=4,200 kg/cm2 kg

02.03.15 DADOS DE CONCRETO

02.03.15.01 DADOS DE CONCRETO 1:8 + 25% P.M. m3


02.03.15.02 DADOS DE CONCRETO, ENCOF. Y DESENCOF. M2

02.03.16 CANALETAS

02.03.16.01 CANALETAS PARA AGUAS PLUVIALES fc=175 GRADERIAS M

02.03.17 GRADERIAS

02.03.17.01 RELLENO CON PIEDRA SELECCIONADA m3


02.03.17.02 CIMIENTOS CONCRETO CICLOPEO 1:10 + 40 % P.G. M3
02.03.17.03 CONCRETO CICLOPEO fc= 100Kg/cm2 + 50% P.G. M3
02.03.17.04 CONCRETO 175 kg/cm2 m3
02.03.17.05 ENCOFRADO Y DESENCOFRADO M2
02.03.17.06 CONCRETO 210 kg/cm2 GRADERIAS m3
02.03.17.07 GRADERIAS.- ACERO Fy=4,200 kg/cm2 kg

02.03.18 FALSA COLUMNA DE 0.25X0.20 (DADO DE CONCRETO)

02.03.18.01 COLUMNAS - CONCRETO 175 kg/cm2 Falsa Columna m3


02.03.18.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.18.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG

02.04 ESTRUCTURAS METALICAS Y COBERTURAS

02.04.01 TENSORES - VIGUETAS

02.04.01.01 TENSORES DE AC LISO 3/4" INCL. UNIONES M


02.04.01.02 VIGUETA-VM | M
02.04.01.03 CORREAS METALICAS DE 2"X6"X2MM M
02.04.01.04 VIGUETAS METALICAS DE 2"X2"X2MM M

02.04.02 TIJERALES

02.04.02.01 TIJERAL METALICO CON ANGULOS T-l (13.00m.) und


02.04.02.02 TIJERAL METALICO CON ANGULOS T-2 (9.50 m.) und
02.04.02.03 TIJERAL METALICO CON ANGULOS T-3 (4.20m.) und
02.04.02.04 TIJERAL METALICO CON ANGULOS T-4 (5.00m.) und
02.04.02.05 TIJERAL METALICO CON ANGULOS T-5 (5.40m.) und
02.04.02.06 TIJERAL METALICO CON ANGULOS T-6 (2.80m.) und
02.04.02.07 TIJERAL METALICO CON ANGULOS T-7 (6.00 m.) und
02.04.02.08 TIJERAL METALICO CON ANGULOS T-8 (6.60m.) und
02.04.02.09 TIJERAL METALICO CON ANGULOS T-9 (8.75m.) und
02.04.02.10 TIJERAL METALICO T-10 (L=6.65m, h=1.20m) DE TUBO und

RECTANGULAR

02.04.03 APOYOS

02.04.03.01 APOYO MOVIL und


02.04.03.02 APOYO FIJO VIGUETAS SOBRE TIMPANO und

02.04.04 COBERTURA

02.04.04.01 COBERTURA C/LAMINA TERMOACUST1CA TIPO TEJA C/ALMA M2


02.04.04.02 CUMBRERA TERMOACUSTICA C/ALMA ACERO ROJO/BLANCO M
02.04.04.03 COBERTURA DE ONDULINE CLASS1C M2
02.04.04.04 COBERTURA CLASS1C M

02.05,01 ESTRUCTURAS DE MADERA

02.05.01 VIGAS Y SUJETADORES

02.05.01.01 VIGAS Y SUJETADORES DE MADERA P2


03.00.00 ARQUITECTURA
03.01 MUROS Y TABIQUES DE ALBAILERIA
03.01.01 MURO DE LADRILLO KKTIPO IV CABEZA M: 1:1:4 E=1.5 cm (*) M2
03.01.02 MURO DE LADRILLO KK TIPO IV SOGA M: 1:1:4 E=1.5 cm (*) M2
03.01.03 MURO DE LADRILLO KK TIPO IV CANTO M: 1:1:4 E=1.5 cm (*) M2
03.01.04 TABIQUERIA DRYWALL INTERIOR E= O.lOm M2
03.01.05 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS KG

03.02 REVOQUES Y REVESTIIENTOS

03.02.01 TARRAJEO EN MUROS INTERIORES C:A 1:5 E=1.5 CM. M2


03.02.02 TARRAJEO EN MUROS EXTERIORES C:A 1: 5, E= 1.50 CM M2
03.02.03 TARRAJEO DE COLUMNAS C:A 1:5 E=1.5 CM. M2
03.02.04 TARRAJEO DE VIGAS C:A 1: 5, E=1.50 CM M2
03.02.05 TARRAJEO SEMIPULIDO DE BORDES BOLEADOS MEZCLA C:A 1:4 E= 1.5 CM M
03.02.06 TARRAJEO CEMENTO PULIDO CON OCRE ROJO M2
03.02.07 TARRAJEO CEMENTO PULIDO M2
03.02.08 TARRAJEO CON IMPERMEABILIZANTE (TANQUE LEVADO Y CISTERNA) M2
03.02.09 TARRAJEO CON IMPERMEABILIZANTE EN CONFORMACION DE M2
03.02.10 VESTIDURA DE DERRAMES (1:5) M
03.02.11 REVEST.CEMENTO PULIDO EN GRADAS M
03.02.12 BRUNAS SEGUN DETALLE (lxl cm) M
03.02.13 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2
03.02.14 REVESTIDO DE GRADAS C:A, 1:3 e=1.5cm C/PERFIL DE ALUMINIO DE 1 1/2" M

03.03 CIELO RASOS


03.03.01 CIELO RASO CON MEZCLA C:A 1:5 M2

03.03.02 FALSO CIELO RASOS

03.03.02.01 FALSO C/RASO C/PLANCHA FIBROCEMENTO 1.22x2.44x6mm M2


03.03.02.02 CIELO BALDOSA ACUSTICA ACABADO PVC C/LANA DE VIDRIO M2
03.03.03 CIELO RASO CON YESO M2
03.04 PISOS Y PAVIMENTOS
03.04.01 CONTRAPISOS
03.04.01.01 CONTRAPISO DE 40 mm M2
03.04.01.02 CONTRAPISO DE 48 mm PARA RECIBIR VIN1LICO M2
03.04.01.03 CONTRAPISO PULIDO DE 2 M2
03.04.01.04 CONTRAPISO CON IMPERMEABILIZANTE E=2 TECHO M2

03.04.02 PISOS

03.04.02.01 PISO CERAMICO 30 x 30 SERIE COLOR - NACIONAL M2


03.04.02.02 PISO LOSETA VENECIANA 30x30 COLOR CLARO M2
03.04.02.03 PISO LOSETA VINILICA DE ALTO TRANSITO e=3.2mm M2
03.04.02.04 MACHIHEMBRADO MAD.l"x4" DURMIENTE 2"x3"x4" 1er Piso M2
03.04.02.05 PISO DE ALFOMBRA DE FIBRA VEGETAL M2
03.04.02.06 PISO DE COLORES INICIAL e= 0.20 M2

03.04.03 PISOS DE CONCRETO

03.04.03.01 PISO DE CEMENTO PULIDO Y BRUADO E=3" S/COLOREAR M2


03.04.03.02 VEREDA CONCRETO 175 kg/cm2 E=4" FROT.Y BRUADO M2
03.04.03.03 RAMPAS DE CONCRETO 175 kg/cm2 E=5" BRUADO S/D1SEO M2
03.04.03.04 CONCRETO F'C=175 KG/CM2 E= 5" ACAB. SEMIPULUDO (LOSA DEPORTIVA) M2
03.04.03.05 ACERO DE REFUERZO Fy=4200 kg/cm2 LOSA DE CONCRETO kg
03.04.03.06 MALLAS DE ACERO 1/4" PARA PISOS DE CONCRETO kS

03.04.04 ACABADO DE CONCRETO EN PISOS

03.04.04.01 ACABADO DE CEMENTO PULIDO E=2cm MEZCLA 1:2 M2

03.05 ZOCALOS Y CONTRAZOCALOS

03.05.01 ZOCALOS

03.05.01.01 ZOCALO DE CERAMICO 30x30 H=1.80m M2


03.05.01.02 ZOCALO DE CERAMICO 30x20 M2

03.05.02 CONTRAZOCALOS

03.05.02.01 CONTRAZOCALO DE LOSETA VENECIANA 10x30 CLARO M


03.05.02.02 CONTR.S/COLOREAR H=20 cm MZ 1:2 e=1.5 cm M
03.05.02.03 CONTRAZOCALO DE CERAMICO DE 10X30CM CLARO M

03.06 COBERTURA (Cubierta)

03.06.01 CUB.DE LADR.PASTELERO ASENTADO CON BARRO e=2"C/FRAGUA M2


03.06.02 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2

03.07 CARPINTERIA DE MADERA

03.07.01 PUERTAS

03.07.01.01 PUERTA CEDRO MACHIMBRADA C/V1SOR-AULA 2004 M2


03.07.01.02 PUERTA CEDRO ENCAJONADO E= 1 1/2 M2
03.07.02 VENTANAS

03.07.02.01 VENTANA CEDRO C/SEG.Y 1/2", SIERRA 01 Y 02 PISOS M2

03.07.03 MUEBLES

03.07.03.01 TICERO DE MADERA CEDRO (L=5 m) BARNIZADO und


03.08 CARPINTERIA METALICA Y HERRERIA
03.08.01 VENTANAS DE FIERRO
03.08.01.01 VENTANA.C/S PERF. 1 1/2"X1 1/2"X3/168" ,FIJA M2
03.08.01.02 DIVICIONES METALICAS E=1/16" M2

03.08.02 PUERTAS DE FIERRO


03.08.02.01 PUERTA METALICA LAC E=1/16" M2
03.08.02.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" M2
03.08.02.03 PUERTA METALICA C/PERFILES 3/16" M2
03.08.03 BARANDAS
03.08.03.01 BARANDAS PARA PUENTES , MUROS, RAMPAS Y PASARELAS M
03.08.04 PASAMANOS
03.08.04.01 PASAMANO DE TUBO FG DE 2" EN ESCALERA M

03.08.05 ESCALERAS
03.08.05.01 CANTONERA DE FIERRO EN ESCALERA M
03.08.05.02 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO M
03.08.05.03 ESCALERA METALICA DE CARACOL und

03.08.06 CERCOS
03.08.06.01 CERCO DE FIERRO TIPO REJA (H= 3.00 ) M

03.08.07 ELEMENTOS METALICOS ESPECIALES


03.08.07.01 MARCO Y TAPA DE FIERRO 0.60X0.60M und
03.08.07.02 MARCO Y TAPA DE FIERRO .80X.80M P/TQUE CISTERNA APOYADO 6M3 und

03.09 CERRAJERA

03.09.01 BISAGRAS
03.09.01.01 BISAGRAS CAPUCHINAS ACERO ALUMINIZADO 3 1/2" EN PUERTAS Y VENTANA PZA
03.09.01.02 BISAGRA DE ACERO ALUMINIZADO DE 2.5" PESADA EN PUERTA/VENTANAS (S PZA
03.09.01.03 BISAGRA DE ACERO ALUMINIZADO DE 2.5" EN ESTANTERIA PZA
03.09.01.04 BISAGRA CAPUCHINAS ACERO ALUMINIZADO 4" EN PUERTAS PZA

03.09.02 CERRADURA
03.09.02.01 CERRADURA DOS GOLPES EN PUERTA PZA
03.09.02.02 CERRADURA LGO PARA PUERTA EXTERIOR PZA

03.09.03 ACCESORIOS CIERRE


03.09.03.01 CERROJO DE 2" ALUMINIZADO PARA PUERTA PZA
03.09.03.02 CERROJO "SAPITO" SEGURIDAD BAT.VENTANA PZA
03.09.03.03 CANDADO TIPO FORTE 60 MM. PZA

03.09.04 VIDRIO CRISTALES Y SIMILARES


03.09.04.01 VIDRIOS SEMIDOBLES IMPORTADO P2
03.09.04.02 VIDRIO TEMPLADO DE 6MM P2
03.09.04.03 VIDRIO TRIPLE DE BRONCE DE 6 MM SISTEMA NOVA INC COLOCACION P2
03.10 PINTURA

03.10.01 PINTURA DE CIELOS RASOS, VIGAS, COLUMNAS Y PAREDES


03.10.01.01 PINTURA OLEO MATE BLANCO HUMO MUROS EXT. M2
03.10.01.02 PINTURA OLEO MATE ALABASTRO COL.VIG, DERRAM. M2
03.10.01.03 PINTURA OLEO MATE MARFIL MUROS M2
03.10.01.04 PINTURA LATEX 2 MANOS BLANCO CIELO RASO M2
03.10.01.05 PINTURA DE PIZARRA EN MUROS M2

03.10.02 PINTURA DE PUERTAS Y VENTANAS


03.10.02.01 PINT.ANTICOR.Y ESMALTE 2 MANOS-PTA/VENT. M2
03.10.02.02 PINTURA BARNIZ EN CARP.DE MADERA M2

03.10.03 PINTURA DE CONTRAZOCALOS Y BARANDAS


03.10.03.01 PINTURA ANTICORROSIVA Y ESM. EN BARANDAS M
03.10.03.02 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=0.20 M
03.10.03.03 PINTURA DEMARCACION DE LOSA DEPORTIVA und

03.11 VARIOS, LIMPIEZA Y JARDINERA

03.11.01 CANALETA DE FIERRO GALVANIZADO REGILLA M


03.11.02 TAPAJUNTA METALICA EN PISOS M
03.11.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) M
03.11.04 PIZARRA CEMENTO 5.0x1.20 SIN TISERO PZA
03.11.05 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" M
03.11.06 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1/2" M
03.11.07 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR M
03.11.08 JUNTA DE DILATACION CON ESPUMA PLASTICA+JEBE MICROPOROSO M
03.11.09 LIMPIEZA FINAL DE LA OBRA GLB

03.12 OTROS

03.12.01 ASTA DE BANDERA TIPICO PZA


03.12.02 LOSA C.A.e=10cm.ANCHO 55cm.ACAB.C.PUL. PARA ASIENTOS EN DUCHAS M
03.12.03 LOSA C.A. PARA MESA DE LABORATORIO M
03.12.04 MESA C.A. REVESTIDO CON MAYOLICA PARA MESA DE LABORATORIO M2
03.12.05 ARCO Y TABLERO FULBITO-BASKET(MET-MAD) und
03.12.06 TUBOS C.VOLEY,INC.RED Y DADOS CONCRETO JGO
03.12.07 TOBOGAN H=1.85M (JUEGO INFANTIL) und
03.12.08 MESA DE NIOS und
03.12.09 JUEGO NIOS TIPO A und
03.12.10 JUEGO NIOS TIPO B und
03.12.11 JUEGO NIOS TIPO C und
03.12.12 JUEGO NIOS TIPO D und
03.12.13 COLUMPIO METALICOS L=3.10m (JUEGO INFANTIL) CON 03 ASIENTO und
03.12.14 BUTACAS und
03.12.15 CONFORMACION DE TALUD PARA JARDINERIA M2
03.12.16 SEMBRADO DE GRASS NATURAL INC. TIERRA DE CHACRA E= 0.10m M2
03.12.17 PISO BLANDO (JUEGOS INFANTILES) E= 6" M2
03.12.18 ANGULAR METALICO DE 1 1/2" X1 1/2" EN PISO PARA VEREDAS M
03.12.19 GARGOLAS und
03.12.20 PUERTAS EN SSHH DE MELAMINA CON PERFIL DE ALUMINIO und
03.12.21 PROTECTOR METALICO P/VENTANAS EN AULAS SEGUN DISENO M2
04.00.00 INSTALACIONES SANITARIAS

04.01 APARATOS SANITARIOS Y ACCESORIOS

04.01.01 LAVATORIO MANATIAL TREBOL O SIMILAR PZA


04.01.02 LAVATORIO SOBREPONER SONET BLANCO PZA
04.01.03 INODORO DE LOSA VITRIFICADA TREBOL O SIMILAR PZA
04.01.04 INODORO DE TAZA MILENIUM PZA
04.01.05 INODORO CON FLUXOMETRO PZA
04.01.06 INODORO TANQUE BAJO LOSA NIOS PZA
04.01.07 URINARIO CON FLUXOMETRO PZA
04.01.08 LAVADERO ACERO INOXIDABLE PZA
04.01.09 SARDINEL EN DUCHA REVESTIDA C/CERAMICO M
04.01.10 PAPELERA DE LOSA BLANCA DE 15X15 CM und
04.01.11 DUCHA SIMPLE CON GRIFERIA PZA
04.01.12 GRIFERIA PARA BEBEDERO und
04.01.13 BEBEDERO CORRIDO DE CONCRETO REVEST.C/MAYOLICA 15x15 M
04.01.14 COLOCACION DE ACCESORIOS SANITARIOS und
04.01.15 COLOCACION DE APARATOS SANITARIOS und

04.02 SISTEMA DE AGUA FRIA Y CONTRA1NCENDIOS

04.02.01 OBRAS PRELIMINARES

04.02.01.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3


04.02.01.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES m3
04.02.01.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3

04.02.02 SALIDAS DE AGUA FRIA

04.02.02.01 SALIDA DE AGUA FRIA CON TUBERIA PVC SAP 2 1/2" PTO
04.02.02.02 SALIDAD DE AGUA FRIA CON TUBERIA PVC SAP 11/4" PTO
04.02.02.03 SALIDAD DE AGUA FRIA CON TUBERIA DE PVC SAP 1" PTO
04.02.02.04 SALIDAD DE AGUA FRIA CON TUBERIA PVC SAP 3/4 PTO
04.02.02.05 SALIDA DE AGUA FRIA - PVC SAP 1/2 PTO
04.02.02.06 SALIDAD DE AGUA FRIA CON TUBERIA FG 2" PTO

04.02.03 RED DE TUBERIAS

04.02.03.01 TUBERIA PVC SAP CLASE 10 - 2 1/2" M


04.02.03.02 TUBERIA PVC CLASE 10 - 2" M
04.02.03.03 TUBERIA PVC CLASE 10 -1 1/2" M
04.02.03.04 TUBERIA PVC CLASE 10 - 1 1/4" M
04.02.03.05 TUBERIA PVC CLASE 10-1" M
04.02.03.06 TUBERIA PVC CLASE 10 - 3/4" M
04.02.03.07 TUBERIA PVC CLASE 10 -1/2" M
04.02.03.08 TUBERIA DE FGDO 2" M

04.02.04 VALVULAS

04.02.04.01 VALVULA DE COMPUERTA DE BRONCE 1 1/4" und


04.02.04.02 VALVULA DE COMPUERTA DE BRONCE 1" und
04.02.04.03 VALVULA DE COMPUERTA DE BRONCE 3/4" und
04.02.04.04 VALVULA DE COMPUERTA DE BRONCE 1/2" und
04.02.04.05 VALVULA GLOBO 1/2" und
04.02.04.06 VALVULA GLOBO 1" und
04.02.04.07 VALVULA DE COMPUERTA DE BRONCE 2" und

04.02.05 ACCESORIOS

04.02.05.01 CODO PVC AGUA C- 10 -1/2" x 90 PZA


04.02.05.02 CODO PVC AGUA C-10 3/4" X90 PZA
04.02.05.03 CODO PVC AGUA C-10 1" X90 PZA
04.02.05.04 CODO PVC AGUA C-10 1 1/4" X 90 PZA
04.02.05.05 CODO PVC AGUA C-10 1 1/2" X90 PZA
04.02.05.06 CODO PVC AGUA C-10 2" X90 PZA
04.02.05.07 TEE PVC -SAP 1/2" PZA
04.02.05.08 TEE PVC -SAP 3/4" PZA
04.02.05.09 TEE PVC SAP 1" PZA
04.02.05.10 TEE PVC SAP 1 1/4" PZA
04.02.05.11 TEE PVC-SAP 1 1/2" PZA
04.02.05.12 TEE PVC SAP 2" PZA
04.02.05.13 REDUCCION PVC PARA AGUA FRIA 3/4" x 1/2" PZA
04.02.05.14 REDUCCION PVC PARA AGUA FRIA 1 1/4" x 3/4" PZA
04.02.05.15 REDUCCION PVC PARA AGUA FRIA 1 1/4" x 1" PZA
04.02.05.16 REDUCCION PVC PARA GAU FRIA 1 /12" X 1" PZA
04.02.05.17 REDUCCION PVC PARA AGUA FRIA 1 1/2" X 1 1/4" PZA
04.02.05.18 REDUCCION PVC PARA AGUA FRIA 2" x 3/4" PZA
04.02.05.19 REDUCCION PVC PARA AGUA FRIA 2" x 1 1/4" PZA
04.0205.20 REDUCCION PVC PARA AGUA FRIA 2" x 1 1/2 PZA
04.02.05.21 REDUCCION PVC PARA AGUA FRIA 11/2" X 1/2" PZA
04.02.05.22 ACCESORIOS CISTERNA YT-E 20M3-10M3 und
04.02.05.23 CAJA DE MADERA PARA VALVULA PZA
04.02.05.24 ACCESORIOS CISTERNA 180M3 und
04.02.05.25 CODO DE FG DE 1/2"X90 PZA
04.02.05.26 REDUCCION PVC PARA AGUA FRIA 1" x 3/4" PZA

04.02.06 VARIOS

04.02.06.01 LLAVE DE RIEGO C/GRIFO DE Vi' EN CAJUELA CONCRETO F'c 140 und
04.02.06.02 EMPALME A RED EXISTENTE, AGUA und
04.02.06.03 EMPALME A CISTERNA EXISTENTE und
04.02.06.04 CAJA DE VALVULA BYPASS DE CONCRETO und
04.02.06.05 CAJA DE REBOSE C/REJILLA DE FIERRO und
04.02.06.06 EQUIPO DE BOMBEO , 2 ELECTROBOMBAS 2.0 HP und
04.02.06.07 EQUIPO DE BOMBEO. 2 BOMBAS DE AGUA FRIA und
04.02.06.08 EQUIPO DE BOMBEO, ELECTROBOMBAS 1.4HP UND
04.02.06.09 REBOSE DE CISTERNA Y TANQUE E. DE FoGo Y 2" und
04.02.06.10 REBOSE DE CISTERNA DE FoGo Y 3" und
04.02.06.11 REBOSE DE CISTERNA DE FoGo 0 4" und
04.02.06.12 REBOSE DE TANQUE ALTO DE FoGo Y 2" und
04.02.06.13 ABRAZADERA DE FIJACION DE TUBO (Mx Y3") PZA
04.02.06.14 ABRAZADERA DE FIJACION DE TUBO PZA

04.03 SISTEMA DE DREANJE PLUVIAL

04.03.01 TUBERIA DE BAJADA PVC-SAP 4" P/LLUVIAS M


04.03.02 CANALETA DE FIERRO GALVANIZADO M
04.03.03 CANALETA CONC.175 P/EVAC.PLUVIAL e=.10m h=.30m (X-X) SIN M
04.03.04 CANALETA CONC.175 P/EVAC.PLUV1AL CON REJILLA (Y-Y) M
04.03.05 EXCAVACION DE ZANJA EN TERRENO NORMAL m3
04.03.06 PERFILADO DEFONDO DE ZANJA M2
04.03.07 CAMA DE ARENA m3
04.03.08 RELLENO COMPACTADO CON MATERIAL PROPIO m3
04.03.09 INSTALACION DE TUBERIA PVC SAL DE 315MM M

04.04 DESAGE Y VENTILACION

04.04.01 OBRAS PRELIMINARES

04.04.01.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3


04.04.01.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES m3
04.04.01.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3

04.04.02 SALIDAS DE DESAGE

04.04.02.01 SALIDA DE DESAGE DE 2" EN PVC PTO


04.04.02.02 SALIDA DE DESAGE DE 3" EN PVC PTO
04.04.02.03 SALIDA DE DESAGE DE 4" EN PVC PTO
04.04.02.04 SALIDA PARA VENTILACION PTO

04.04.03 TUBERIAS

04.04.03.01 TUBERIA PVC-SAP 2" RED EXTERIOR M


04.04.03.02 TUBERIA PVC-SAP 3" RED EXTERIOR M
04.04.03.03 TUBERIA PVC-SAP 4" RED EXTERIOR M
04.04.03.04 TUBERIA PVC-SAP 6" RED EXTERIOR M
04.04.03.05 TUBERIA DE FGDO 2" M
04.04.03.06 TUBERIA PVC-SAL 4" M
04.04.03.07 TUBERIA PVC-SAL 3" M
04.04.03.08 TUBERIA PVC-SAL 2" M

04.04.04 ACCESORIOS

04.04.04.01 REGISTRO DE BRONCE 4" und


04.04.04.02 REGISTRO DE BRONCE 3" und
04.04.04.03 REGISTRO DE BRONCE 2" und
04.04.04.04 SUMIDERO DE BRONCE 2" und
04.04.04.05 SOMBRERO PARA VENTILACION EN PVC und
04.04.04.06 CODO PVC SAL 2" x 90 PZA
04.04.04.07 CODO PVC SAL 3"X 90 PZA
04.04.04.08 CODO PVC SAL 2" x 45 PZA
04.04.04.09 CODO PVC SAL 4" x 45 PZA
04.04.04.10 TEE PVC SAL 2" x 2" PZA
04.04.04.11 TEE PVC SAL 3" x 3" PZA
04.04.04.12 TEE PVC SAL 4" x 2" PZA
04.04.04.13 YEE PVC SAL DESAGE 2" x 2" PZA
04.04.04.14 YEE PVC SAL DESAGE 3" X 2" PZA
04.04.04.15 YEE PVC SAL DESAGE 4" X 2" PZA
04.04.04.16 YEE PVC SAL DESAGE 4" X 3" PZA
04.04.04.17 YEE PVC SAL DESAGE 4" X 4" PZA
04.04.04.18 REDUCCION PVC DESAGE SAL 3" x 2" PZA
04.04.04.19 TRAMPA "P" DE PVC SAL PARA DESAGE 2" PZA
04.04.04.20 ACCESORIOS PARA DESAGE EN SISTERNA Y TE und
04.04.04.21 CODO PVC SAL 4" x 90 PZA
04.04.04.22 TEE PVC SAL 4 x 3" PZA
04.04.04.23 CODO PVC SAL 3"X 45 PZA

04.04.05 CAJAS DE REGISTRO

04.04.05.01 CAJA DE REG.ALB.10"x20" C/TAPA CONCRETO und


04.04.05.02 CAJA DE REG.ALB.12"x24" C/TAPA CONCRETO und
04.04.05.03 CAJADE REG. ALB 18" x 20" VC/TAPA CONCRETO und
04.04.05.04 CAJA DE REG.ALB.24"x24" C/TAPA CONCRETO und
04.04.05.05 BUZON STANDAR DE D=1.20m H=1.40m und

04.04.06 VARIOS

04.04.06.01 CAJA SUMIDERO CON REJILLA DE FIERRO und


04.04.06.02 EMPALME A RED EXISTENTE, DESAGE und
05.00.00 INSTLACIONES ELECTRICAS

05.01 OBRAS PRELIMINARES

05.01.01 PICADO Y RESANE DE PISO Y VEREDA DE CONCRETO M2


05.01.02 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3
05.01.03 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT.ELEC.SANIT). m3
05.01.04 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3
05.01.05 CONEXION A RED EXISTENTE und

05.02 SALIDA PARA ALUMBRADO, TOMACORRIENTES, FUERZAS

SEALES DEBILES

05.02.01 SALIDA DE TECHO (CENTRO DE LUZ) PTO


05.02.02 SALIDA PARA BRAQUETE (PARED) PTO
05.02.03 SALIDA PARA TOMACORRIENTE DOBLE PTO
05.02.04 SALIDA TRIFASICA PARA ELECTROBOMBA PTO
05.02.05 SALIDA DE TELEFONO y/o INTERCOMUNICADORES PTO
05.02.06 SALIDA PARA RED DATA (COMPUTO) PTO
05.02.07 SALIDA PARA TIMBRE PTO
05.02.08 SALIDA PARA VENTILADORES PTO

05.03 CANALIZACION Y/O TUBERIAS

05.03.01 TUBERIA PVC-P 65mm M


05.03.02 TUBERIA PVC-P35mm M
05.03.03 TUBERIA PVC-P 25mm M

05.04 CAJAS

05.04.01 CAJA DE PASE FG 4x4xl.5" und


05.04.02 CAJA DE PASE FG 6x6x3" und
05.04.03 CAJA DE PASE FG 12X12X6" und
05.04.04 CAJA PASE FG 6" x 6" x 2 1/2" und
05.04.05 CAJA PASE FG 6" x 6" x 6" und
05.04.06 CAJA DE PASE FG 4X4X2" und
05.05 TABLEROS Y CUCHILLAS (LLAVES)
05.05.01 T.G.AUT. 8-3X40,2-3X60. 2-2X40,4- 2X30 ,2-3X30 1-RESERVA und
05.05.02 TA. AUT. 4- 2 X 15A, 2- 2 X 20A und
05.05.03 TAB.AUT. 3-2X20, 4-2X15A und
05.05.04 TAB.AUT. 1-2X20, 2-2X15A und
05.05.05 TAB.AUT. 3-2X20, 6-2X15A und
05.05.06 TAB.AUT. 1-2X30,1-2X20,1-2X15A und
05.05.07 TAB.AUT. 1-2X20,2-2X15A und
05.05.08 TAB.AUT. 1-3X30, 3-2X20, 2-2X15A und
05.05.09 TAB.AUT. 2-2xl5A und
05.05.10 TAB. AUT. 3 - 2 x 15 A und
05.05.11 TAB AUT. 5- 2 x 20A TD1- UPS und
05.05.12 TAB. AUT. 3 - 2 x 20A TD2 - UPS und
05.05.13 TAB. AUT. CONTROL LUCES 8.2 X 15A und
05.05.14 TAB AUT. CONTROL ELECTROBOMBAS 2 X 20A und

05.06 CONEXIONES A RED EXTERNA Y MEDIDORES

05.06.01 AL1MENTADOR CAB. N2XH (3- 1X95 +1X50 +lX35)mm2 M


05.06.02 ALIMENTADOR CAB. N2XH (3-1x25 +1x25+ Ixl0)mm2 M
05.06.03 ALIMENTADOR CAB. N2XH (3-1x16 +1x16+ Ixl0)mm2 M
05.06.04 ALIMENTADOR CAB. N2XH (3-1x10 +1x10+ Ixl0)mm2 M
05.06.05 ALIMENTADOR CAB. N2XH (3-1x4 +1x4+ Ixl0)mm2 M
05.06.06 ALIMENTADOR CAB. N2XH (2-1x6 + Ixl0)mm2 M
05.06.07 ALIMENTADOR CAB. N2XH (2-1x4 + Ixl0)mm2 M
05.06.08 ALIMENTADOR CAB. N2XH 2- 1x6 mm2 M
05.06.09 ALIMENTADOR CAB. N2XH 2- 1x4 mm2 M
05.06.10 ALIMENTADOR SOL NH-70 2-lxl.5mm2/20mm PVC M
05.06.11 CABLE COBRE DESNUDO Ixl0mm2, Y 20mm PVC-P M

05.07 INSTALACION PARARRAYOS

05.07.01 PARARRAYO C/D1SPOSIT.DE CEBADO C/03P/T1ERRA.EN POSTE (2004) und

05.08 INSTALACION DEL SISTEMA PUESTA A TIERRA

05.08.01 POZO PUESTA A TIERRA P-l und


05.08.02 POZO PUESTA A TIERRA P-2 ( R<5 Ohms) und

05.09 ARTEFACTOS

05.09.01 ARTEF.FLUORESCENTE 3/36W (SIM.BE JOSFEL) C/SOPORTE und


05.09.02 ARTEF.FLUORESCENTE 2/18W (SIM.BE JOSFEL) C/SOPORTE und
05.09.03 ARTEFACTO FLUORESCENTE CIRCULAR DE 32W und
05.09.04 SUMINISTRO E INST. ARTEFACTO 2 LAMPARAS FLUORCENTE COMPACTA 18W und
05.09.05 SUMINISTRO E INST. LUMINARIA INCANDECENTE und
05.09.06 FAROLA JP 250 LAMPARA HG 125W und
05.09.07 EQUIPO DE ILUMINACION DE MERGENCIA BATERIA PZA
05.09.08 DETECTOR DE HUMO PZA
05.09.09 LUMINARIA CON BRAZO Y GLOBO und

05.10 OTROS

05.10.01 CONSTRUCCION DE SUBESTACIONES und


05.10.02 SUMINISTRO E INSTALACION DE POSTES DE ALUMBRADO und
05.10.03 CAMPANILLA DE TIMBRE DE 6" CON TRANF 220/12V und
05.10.04 CAMPANILLA DE TIMBRE DE 8" CON TRANF 220/12V und
06.00.00 IMPLEMENTACION Y EQUIPAMIENTO
06.01.00 ADQUISICION DE EQUIPOS Y MOBILIARIOS GLB
06.02.00 ADQUISICION DE TEXTOS GLB
07.00.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE
07.01.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE GLB

COSTO DIRECTO
GASTOS GENERALES
SUPERVISION
EXPEDIENTE TECNICO
GASTOS DE LIQUIDACION
PRESUPUESTO TOTAL MODIFICADO
1

Metrado P.U. Parcial ANTERIOR ACTUAL


S/. S/. Metrado Parcial % Metrado

1.00 577.16 577.16 1.00 577.16 100.00% 0.00


12.00 250.00 3,000.00 12.00 3,000.00 100.00% 0.00
80.00 44.28 3,542.40 75.00 3,321.00 93.75% 0.00
168.00 37.24 6,256.32 152.90 5,694.00 91.01% 0.00

1.00 900.00 900.00 1.00 900.00 100.00% 0.00

7,718.43 0.51 3,936.40 6,007.87 3,064.01 77.84% 0.00

73.00 3.55 259.15 73.00 259.15 100.00% 0.00


110.00 5.69 625.90 110.00 625.90 100.00% 0.00
5.00 5.69 28.45 5.00 28.45 100.00% 0.00
20.00 4.74 94.80 20.00 94.80 100.00% 0.00
2,130.43 1.67 3,557.82 2,130.43 3,557.82 100.00% 0.00

554.97 40.93 22,714.92 554.97 22,714.92 100.00% 0.00


1,433.55 5.11 7,325.44 1,433.55 7,325.44 100.00% 0.00
705.34 5.11 3,604.29 705.34 3,604.29 100.00% 0.00
158.00 39.68 6,269.44 149.92 5,948.83 94.89% 0.00
188.71 185.69 35,041.56 188.71 35,041.56 100.00% 0.00
1,161.87 23.15 26,897.29 1,161.87 26,897.29 100.00% 0.00
72.03 138.99 10,011.45 51.25 7,123.24 71.15% 0.00
324.92 138.99 45,160.63 222.60 30,939.17 68.51% 0.00
176.10 25.58 4,504.64 176.10 4,504.64 100.00% 0.00
16.67 83.17 1,386.44 16.67 1,386.44 100.00% 0.00
58.50 21.44 1,254.24 50.34 1,079.29 86.05% 0.00
16.18 12.55 203.06 16.18 203.06 100.00% 0.00
295.47 43.58 12,876.58 295.47 12,876.58 100.00% 0.00
186.96 3.35 626.32 186.95 626.28 99.99% 0.00
2,514.10 1.39 3,494.60 2,282.27 3,172.36 90.78% 231.83
1,245.81 12.55 15,634.92 1,081.56 13,573.58 86.82% 0.00
3,162.60 22.39 70,810.61 3,162.60 70,810.61 100.00% 0.00
12.63 5.11 64.54 0.00 0.00 0.00% 0.00

1.00 12,000.00 12,000.00 1.00 12,000.00 100.00% 0.00

7,429.62 1.52 11,293.02 4,301.04 6,537.58 57.89% 0.00


7,429.62 1.52 11,293.02 5,283.31 8,030.63 71.11% 0.00

1.00 4,000.00 4,000.00 0.94 3,760.00 94.00% 0.00


180.00 203.14 36,565.20 176.00 35,752.64 97.78% 0.00
1.00 1,150.00 1,150.00 1.00 1,150.00 100.00% 0.00
1.00 750.00 750.00 1.00 750.00 100.00% 0.00
1.00 3,820.00 3,820.00 1.00 3,820.00 100.00% 0.00
1.00 1,010.00 1,010.00 1.00 1,010.00 100.00% 0.00

491.64 14.30 7,030.45 439.89 6,290.43 89.47% 0.00


2,170.01 27.88 60,499.88 1,918.57 53,489.73 88.41% 0.00
93.81 27.88 2,615.42 93.81 2,615.42 100.00% 0.00
1,466.48 28.42 41,677.36 122.45 3,480.03 8.35% 0.00
5.95 28.42 169.10 0.00 0.00 0.00% 0.00

981.71 10.05 9,866.19 868.11 8,724.51 88.43% 17.73

1465.17 26.17 38,343.50 1,213.61 31,760.17 82.83% 0.00

2,383.71 45.82 109,221.59 1,327.71 60,835.67 55.70% 0.00


5,612.53 9.57 53,711.91 3,459.30 33,105.50 61.64% 0.00
3,157.11 2.12 6,693.07 2,446.07 5,185.67 77.48% 0.00

3,969.68 16.73 66,412.75 2,313.06 38,697.49 58.27% 6.90


4,940.64 23.60 116,599.10 3,855.19 90,982.48 78.03% 45.00

748.08 213.61 159,797.47 693.50 148,138.54 92.70% 0.00


426.99 19.61 8,373.27 426.99 8,373.27 100.00% 0.00
1,924.58 73.40 141,264.17 510.94 37,503.00 26.55% 0.00

168.89 227.79 38,471.45 143.11 32,599.03 84.74% 0.00


1,116.63 24.79 27,681.26 727.64 18,038.20 65.16% 0.00

0.00 224.69 0.00 2.30 0.00


0.00 28.97 0.00 29.81 0.00

823.84 384.26 316,568.76 429.47 165,028.14 52.13% 0.00


273.88 21.09 5,776.13 273.88 5,776.13 100.00% 0.00
182.42 189.34 34,539.40 174.32 33,005.75 95.56% 0.00
2,866.85 22.82 65,421.52 2,316.90 52,871.66 80.82% 0.00

134.74 486.60 65,564.48 134.74 65,564.48 100.00% 0.00


2,465.91 4.83 11,910.35 2,465.91 11,910.35 100.00% 0.00

756.80 499.59 378,089.71 355.89 177,799.09 47.03% 0.00


7,229.05 4.83 34,916.31 7,229.05 34,916.31 100.00% 0.00

54.51 500.34 27,273.53 54.51 27,273.53 100.00% 0.00


293.17 31.13 9,126.38 293.17 9,126.38 100.00% 0.00
3,231.71 4.83 15,609.16 3,231.71 15,609.16 100.00% 0.00

111.75 237.59 26,550.68 96.15 22,844.28 86.04% 0.00


1,245.38 26.26 32,703.68 1,084.71 28,484.48 87.10% 0.00
3,660.03 4.83 17,677.94 2,820.52 13,623.11 77.06% 0.00

346.91 500.34 173,572.95 246.04 123,103.65 70.92% 0.00


1,433.18 33.18 47,552.91 1,094.00 36,298.92 76.33% 0.00
13,297.14 4.83 64,225.19 10,280.63 49,655.44 77.31% 0.00

420.64 542.21 228,075.21 420.64 228,075.21 100.00% 0.00


3,957.91 35.10 138,922.64 3,957.91 138,922.64 100.00% 0.00
56,657.98 4.83 273,658.04 55,788.93 269,460.53 98.47% 0.00

501.91 513.70 257,831.17 501.91 257,831.17 100.00% 0.00


4,063.69 41.34 167,992.94 4,063.69 167,992.94 100.00% 0.00
46,420.70 4.83 224,211.98 46,420.70 224,211.98 100.00% 0.00

25.65 505.34 12,961.97 25.65 12,961.97 100.00% 0.00


148.92 30.69 4,570.35 148.92 4,570.35 100.00% 0.00
647.40 4.83 3,126.94 647.40 3,126.94 100.00% 0.00

232.01 438.05 101,631.98 214.08 93,777.74 92.27% 0.00


2,534.76 31.43 79,667.51 2,380.38 74,815.34 93.91% 0.00
18,025.50 4.83 87,063.17 15,257.06 73,691.60 84.64% 0.00
21,114.86 2.51 52,998.30 188.00 471.88 0.89% 0.00
2,096.27 27.67 58,003.79 1,479.40 40,935.00 70.57% 0.00

68.42 516.28 35,323.88 54.09 27,925.59 79.06% 0.00


295.26 44.35 13,094.78 290.78 12,896.09 98.48% 0.00
2,561.76 4.83 12,373.30 2,561.76 12,373.30 100.00% 0.00
37.23 132.73 4,941.54 33.95 4,506.18 91.19% 3.28
32.55 20.45 665.65 32.55 665.65 100.00% 0.00
236.66 4.83 1,143.07 184.59 891.57 78.00% 0.00

18.32 514.10 9,418.31 18.32 9,418.31 100.00% 0.00


57.48 25.26 1,451.94 57.48 1,451.94 100.00% 0.00
1,010.05 4.83 4,878.54 1,010.05 4,878.54 100.00% 0.00

4.61 520.10 2,397.66 0.00 0.00 0.00% 4.61


35.74 28.02 1,001.43 0.00 0.00 0.00% 35.74
326.82 4.83 1,578.54 26.73 129.11 8.18% 300.09

2.21 534.71 1,181.71 0.00 0.00 0.00% 0.00


12.06 30.89 372.53 0.00 0.00 0.00% 0.00
96.77 4.96 479.98 0.00 0.00 0.00% 0.00

0.36 224.69 80.89 0.00 0.00 0.00% 0.00


3.84 28.97 111.24 0.00 0.00 0.00% 0.00

231.00 53.88 12,446.28 231.00 12,446.28 100.00% 0.00

14.50 67.46 978.17 0.00 0.00 0.00% 0.00


2.41 177.41 427.56 0.00 0.00 0.00% 0.00
1.36 182.31 247.94 0.00 0.00 0.00% 0.00
14.73 394.15 5,805.83 6.79 2,676.28 46.10% 1.44
107.27 30.94 3,318.93 97.17 3,006.44 90.58% 10.10
12.05 534.71 6,443.26 12.05 6,443.26 100.00% 0.00
894.96 4.96 4,439.00 894.96 4,439.00 100.00% 0.00

46.19 461.03 21,294.98 42.40 19,547.67 91.79% 0.00


368.13 35.10 12,921.36 282.06 9,900.31 76.62%
3,747.83 4.83 18,102.02 3,038.57 14,676.29 81.08%

91.00 16.75 1,524.25 0.00 0.00 0.00%


1,173.43 36.33 42,630.71 0.00 0.00 0.00%
12,345.96 34.69 428,281.35 4,052.92 140,595.79 32.83%
2,895.64 34.03 98,538.63 0.00 0.00 0.00%

1.00 4,181.19 4,181.19 1.00 4,181.19 100.00%


1.00 3,080.23 3,080.23 0.00 0.00 0.00%
2.00 1,576.33 3,152.66 2.00 3,152.66 100.00%
2.00 1,994.93 3,989.86 2.00 3,989.86 100.00%
2.00 2,015.13 4,030.26 2.00 4,030.26 100.00%
1.00 7,539.53 7,539.53 1.00 7,539.53 100.00%
6.00 4,030.80 24,184.80 6.00 24,184.80 100.00%
5.00 3,490.35 17,451.75 3.00 10,471.05 60.00%
2.40 2,978.70 7,148.88 2.40 7,148.88 100.00%
3.00 480.80 1,442.40 3.00 1,442.40 100.00%

11.00 62.65 689.15 11.00 689.15 100.00%


28.00 51.85 1,451.80 28.00 1,451.80 100.00%

0.00 80.30 0.00 0.00


0.00 46.97 0.00 310.00
4,201.03 96.11 403,760.99 2,909.54 279,635.89 69.26%
318.61 67.12 21,385.10 21.85 1,466.57 6.86%

0.00 5.10 0.00 0.00 0.00

4,042.92 104.07 420,746.68 3,545.17 368,945.84 87.69%


1,151.59 59.68 68,726.89 1,151.59 68,726.89 100.00%
9.00 47.42 426.78 0.00 0.00 0.00%
38.02 127.36 4,842.23 22.49 2,864.33 59.15%
1,147.74 6.49 7,448.83 890.26 5,777.79 77.57%

5,868.57 14.03 82,336.04 5,868.57 82,336.04 100.00%


5,818.48 16.25 94,550.30 4,081.68 66,327.30 70.15% 57.71
6,740.82 21.72 146,410.61 4,117.42 89,430.36 61.08% 37.02
3,461.74 25.43 88,032.05 3,442.00 87,530.06 99.43% 19.17
38.40 9.55 366.72 8.00 76.40 20.83% 0.00
191.50 16.82 3,221.03 0.00 0.00 0.00% 0.00
112.80 14.03 1,582.58 0.00 0.00 0.00% 0.00
112.42 19.52 2,194.44 41.00 800.32 36.47% 29.88
11.76 21.81 256.49 9.45 206.10 80.35% 0.00
2,032.55 7.23 14,695.34 2,032.55 14,695.34 100.00% 0.00
70.14 24.02 1,684.76 34.14 820.04 48.67% 36.00
6,397.93 3.05 19,513.69 6,397.93 19,513.69 100.00% 0.00
776.20 12.83 9,958.65 655.60 8,411.35 84.46% 0.00
25.95 27.73 719.59 0.00 0.00 0.00% 0.00
0.00 23.17 0.00 0.00 0.00

3,530.84 28.82 101,758.81 3,530.84 101,758.81 100.00% 0.00


298.37 220.40 65,760.75 202.03 44,527.41 67.71% 0.00
2,238.20 52.55 117,617.41 565.04 29,692.85 25.25% 0.00

4,066.21 23.29 94,702.03 4,066.21 94,702.03 100.00% 0.00


38.11 25.76 981.71 38.11 981.71 100.00% 0.00
7.77 33.75 262.24 0.00 0.00 0.00% 0.00
73.84 35.13 2,594.00 0.00 0.00 0.00% 0.00

7,681.36 71.80 551,521.65 6,158.19 442,158.04 80.17% 47.08


71.54 66.17 4,733.80 0.00 0.00 0.00% 0.00
22.83 76.70 1,751.06 0.00 0.00 0.00% 0.00
30.03 65.16 1,956.75 24.05 1,567.10 80.09% 0.00
365.46 46.89 17,136.42 0.00 0.00 0.00% 0.00
14.00 55.03 770.42 0.00 0.00 0.00% 0.00

2,040.69 41.53 84,749.86 2,040.69 84,749.86 100.00% 0.00


2,476.52 53.45 132,369.99 1,755.82 93,848.58 70.90% 6.92
109.69 66.65 7,310.84 109.69 7,310.84 100.00% 0.00
1,080.00 67.55 72,954.00 1,077.62 72,793.23 99.78% 2.38
1,921.92 4.96 9,532.72 1,921.92 9,532.72 100.00% 0.00
5,181.54 4.96 25,700.44 554.30 2,749.33 10.70% 0.00

36.14 13.80 498.73 0.00 0.00 0.00% 0.00

755.58 60.76 45,909.04 621.89 37,786.04 82.31% 0.00


161.51 60.76 9,813.35 161.51 9,813.35 100.00% 0.00

2,188.85 20.31 44,455.54 2,188.85 44,455.54 100.00% 0.00


1,872.51 6.69 12,527.09 1,487.00 9,948.03 79.41% 0.00
664.17 34.04 22,608.35 101.20 3,444.85 15.24% 0.00

13.83 43.98 608.24 0.00 0.00 0.00% 0.00


13.83 4.33 59.88 0.00 0.00 0.00% 0.00

283.38 240.31 68,099.05 278.37 66,895.09 98.23% 0.00


10.23 420.00 4,296.60 0.00 0.00 0.00% 0.00
986.02 146.55 144,501.23 858.00 125,739.90 87.02% 0.00

37.00 129.37 4,786.69 0.00 0.00 0.00% 0.00

40.49 378.69 15,333.16 40.49 15,333.16 100.00% 0.00


205.99 146.31 30,138.40 26.75 3,913.79 12.99% 0.00

6.72 167.64 1,126.54 0.00 0.00 0.00% 0.00


21.24 384.07 8,157.65 8.44 3,241.55 39.74% 0.00
6.48 218.65 1,416.85 2.57 561.93 39.66% 0.00

201.05 60.69 12,201.72 135.00 8,193.15 67.15% 0.00

52.00 60.41 3,141.32 0.00 0.00 0.00% 52.00

264.00 40.98 10,818.72 246.00 10,081.08 93.18% 18.00


13.60 142.08 1,932.29 0.00 0.00 0.00% 0.00
1.00 1,335.86 1,335.86 0.00 0.00 0.00% 1.00

249.56 526.71 131,445.75 249.56 131,445.75 100.00% 0.00

4.00 219.93 879.72 0.00 0.00 0.00% 0.00


1.00 288.38 288.38 0.00 0.00 0.00% 0.00

1270 11.45 14,541.50 1,002.00 11,472.90 78.90% 0.00


244.00 6.95 1,695.80 0.00 0.00 0.00% 0.00
48.00 6.95 333.60 0.00 0.00 0.00% 0.00
16.00 13.70 219.20 0.00 0.00 0.00% 0.00

121.00 68.32 8,266.72 96.00 6,558.72 79.34% 0.00


3.00 58.32 174.96 0.00 0.00 0.00% 0.00

124.00 8.75 1,085.00 82.00 717.50 66.13% 0.00


620.00 9.08 5,629.60 460.00 4,176.80 74.19% 0.00
3.00 40.00 120.00 0.00 0.00 0.00% 0.00

0.00 8.93 0.00 3,850.00 0.00


207.61 19.43 4,033.86 0.00 0.00 0.00% 0.00
8,503.20 22.00 187,070.40 7,471.27 164,367.94 87.86% 0.00
6,395.84 8.12 51,934.22 3,232.64 26,249.04 50.54% 67.61
8,116.59 9.90 80,354.24 6,230.29 61,679.87 76.76% 620.64
5,803.39 9.90 57,453.56 5,803.39 57,453.56 100.00% 0.00
3,864.48 9.95 38,451.58 2,704.83 26,913.06 69.99% 1,159.65
105.64 18.09 1,911.03 58.46 1,057.54 55.34% 0.00

384.01 9.80 3,763.30 0.00 0.00 0.00% 0.00


16.23 12.59 204.34 3.00 37.77 18.48% 0.00

5.10 3.84 19.58 0.00 0.00 0.00% 0.00


799.25 2.15 1,718.39 799.25 1,718.39 100.00% 0.00
2.00 125.81 251.62 0.00 0.00 0.00% 0.00

418.77 54.61 22,869.03 0.00 0.00 0.00% 0.00


58.94 34.77 2,049.34 50.00 1,738.50 84.83% 0.00
87.02 43.00 3,741.86 21.00 903.00 24.13% 0.00
37.00 162.44 6,010.28 0.00 0.00 0.00% 0.00
4,311.63 9.79 42,210.86 2,500.00 24,475.00 57.98% 0.00
917.31 5.45 4,999.34 620.00 3,379.00 67.59% 0.00
132.68 24.46 3,245.35 0.00 0.00 0.00% 0.00
17.19 13.90 238.94 0.00 0.00 0.00% 0.00
1.00 700.00 700.00 0.00 0.00 0.00% 0.00

1.00 763.37 763.37 1.00 763.37 100.00% 0.00


27.06 175.64 4,752.82 21.66 3,804.36 80.04% 0.00
12.20 182.97 2,232.23 0.00 0.00 0.00% 0.00
54.18 429.41 23,265.43 16.90 7,257.03 31.19% 0.00
4.00 2,187.06 8,748.24 0.00 0.00 0.00% 0.00
2.00 417.29 834.58 0.00 0.00 0.00% 0.00
5 828.51 4,142.55 3.00 2,485.53 60.00% 0.00
4.00 989.33 3,957.32 0.00 0.00 0.00% 0.00
1.00 2,689.33 2,689.33 0.50 1,344.67 50.00% 0.00
1.00 2,839.33 2,839.33 0.50 1,419.67 50.00% 0.00
1.00 3,022.23 3,022.23 0.50 1,511.12 50.00% 0.00
1.00 1,922.23 1,922.23 0.50 961.12 50.00% 0.00
1.00 868.88 868.88 0.50 434.44 50.00% 0.00
330 221.46 73,081.80 0.00 0.00 0.00% 0.00
1,220.81 1.60 1,953.30 1,206.51 1,930.42 98.83% 14.30
1,070.81 23.42 25,078.33 626.11 14,663.50 58.47% 0.00
232.98 15.01 3,497.03 0.00 0.00 0.00% 0.00
689.80 27.73 19,128.15 0.00 0.00 0.00% 0.00
6.00 34.24 205.44 6.00 205.44 100.00% 0.00
36.00 250.00 9,000.00 36.00 9,000.00 100.00% 0.00
137.25 120.00 16,470.00 137.25 16,470.00 100.00% 0.00

10.00 220.00 2,200.00 10.00 2,200.00 100.00% 0.00


4.00 220.00 880.00 4.00 880.00 100.00% 0.00
22.00 560.00 12,320.00 22.00 12,320.00 100.00% 0.00
9.00 350.00 3,150.00 7.00 2,450.00 77.78% 0.00
5.00 560.00 2,800.00 1.00 560.00 20.00% 0.00
7.00 350.00 2,450.00 7.00 2,450.00 100.00% 0.00
2.00 570.00 1,140.00 2.00 1,140.00 100.00% 0.00
7.00 360.00 2,520.00 2.00 720.00 28.57% 0.00
23.00 77.97 1,793.31 0.00 0.00 0.00% 0.00
14.00 46.49 650.86 0.00 0.00 0.00% 0.00
16.00 77.46 1,239.36 16.00 1,239.36 100.00% 0.00
14.00 13.70 191.80 14.00 191.80 100.00% 0.00
26.41 245.84 6,492.63 26.41 6,492.63 100.00% 0.00
15.00 22.92 343.80 15.00 343.80 100.00% 0.00
65.00 22.92 1,489.80 23.00 527.16 35.38% 0.00

136.80 14.34 1,961.71 136.32 1,954.83 99.65% 0.48


136.80 11.15 1,525.32 127.14 1,417.61 92.94% 5.28
15.82 23.60 373.35 15.82 373.35 100.00% 0.00

2.00 74.25 148.50 1.00 74.25 50.00% 0.00


7.00 61.30 429.10 6.00 367.80 85.71% 0.00
3.00 57.95 173.85 2.00 115.90 66.67% 0.00
7.00 56.40 394.80 6.00 338.40 85.71% 0.00
70.00 47.40 3,318.00 65.00 3,081.00 92.86% 0.00
4.00 163.22 652.88 3.00 489.66 75.00% 0.00

5.33 12.90 68.76 3.00 38.70 56.28% 0.00


125.00 11.10 1,387.50 125.00 1,387.50 100.00% 0.00
61.00 9.89 603.29 61.00 603.29 100.00% 0.00
237.00 9.85 2,334.45 236.90 2,333.47 99.96% 0.00
190.22 9.44 1,795.68 190.22 1,795.68 100.00% 0.00
195.20 8.57 1,672.86 195.20 1,672.86 100.00% 0.00
219.00 7.96 1,743.24 219.00 1,743.24 100.00% 0.00
30.98 29.26 906.47 18.00 526.68 58.10% 0.00

3.00 125.19 375.57 1.00 125.19 33.33% 2.00


2.00 111.19 222.38 2.00 222.38 100.00% 0.00
15.00 95.19 1,427.85 15.00 1,427.85 100.00% 0.00
2.00 79.19 158.38 2.00 158.38 100.00% 0.00
3.00 63.19 189.57 3.00 189.57 100.00% 0.00
1.00 93.76 93.76 1.00 93.76 100.00% 0.00
4.00 321.19 1,284.76 0.00 0.00 0.00% 0.00

146.00 8.24 1,203.04 146.00 1,203.04 100.00% 0.00


54.00 9.04 488.16 54.00 488.16 100.00% 0.00
36.00 11.04 397.44 36.00 397.44 100.00% 0.00
32.00 12.04 385.28 29.00 349.16 90.63% 0.00
10.00 12.04 120.40 10.00 120.40 100.00% 0.00
21.00 17.04 357.84 21.00 357.84 100.00% 0.00
42.00 10.54 442.68 42.00 442.68 100.00% 0.00
60.00 10.54 632.40 60.00 632.40 100.00% 0.00
14.00 10.54 147.56 14.00 147.56 100.00% 0.00
15.00 10.54 158.10 15.00 158.10 100.00% 0.00
8.00 10.54 84.32 8.00 84.32 100.00% 0.00
4.00 10.54 42.16 4.00 42.16 100.00% 0.00
65.00 8.24 535.60 65.00 535.60 100.00% 0.00
5.00 10.04 50.20 5.00 50.20 100.00% 0.00
3.00 10.04 30.12 3.00 30.12 100.00% 0.00
14.00 10.84 151.76 14.00 151.76 100.00% 0.00
3.00 10.54 31.62 3.00 31.62 100.00% 0.00
1.00 13.04 13.04 1.00 13.04 100.00% 0.00
4.00 13.04 52.16 1.00 13.04 25.00% 3.00
8.00 13.04 104.32 8.00 104.32 100.00% 0.00
2.00 10.84 21.68 1.00 10.84 50.00% 0.00
1.00 3,786.46 3,786.46 1.00 3,786.46 100.00% 0.00
9.00 36.27 326.43 6.00 217.62 66.67% 0.00
1.00 1,551.46 1,551.46 1.00 1,551.46 100.00% 0.00
37.00 24.06 890.22 10.00 240.60 27.03% 0.00
10.00 12.04 120.40 10.00 120.40 100.00% 0.00

4.00 174.60 698.40 2.00 349.20 50.00% 0.00


1.00 51.19 51.19 1.00 51.19 100.00% 0.00
2.00 57.04 114.08 1.00 57.04 50.00% 0.00
2.00 206.66 413.32 2.00 413.32 100.00% 0.00
2.00 136.39 272.78 0.00 0.00 0.00% 0.00
1.00 4,588.36 4,588.36 1.00 4,588.36 100.00% 0.00
1.00 3,038.36 3,038.36 0.80 2,430.69 80.00% 0.00
1.00 2,735.07 2,735.07 0.80 2,188.06 80.00% 0.00
2.00 59.24 118.48 1.30 77.01 65.00% 0.00
2.00 66.74 133.48 1.30 86.76 65.00% 0.00
2.00 85.19 170.38 1.30 110.75 65.00% 0.00
2.00 52.24 104.48 1.30 67.91 65.00% 0.00
2.00 12.90 25.80 1.30 16.77 65.00% 0.00
8.00 12.43 99.44 4.30 53.45 53.75% 0.00

338.70 17.25 5,842.58 321.30 5,542.43 94.86% 0.00


689.39 71.64 49,387.90 558.46 40,008.07 81.01% 0.00
70.70 69.61 4,921.43 70.70 4,921.43 100.00% 0.00
535.46 243.21 130,229.23 535.46 130,229.23 100.00% 0.00
78.00 25.58 1,995.24 0.00 0.00 0.00% 0.00
337.50 1.02 344.25 0.00 0.00 0.00% 0.00
19.50 87.97 1,715.42 0.00 0.00 0.00% 0.00
78.00 26.17 2,041.26 0.00 0.00 0.00% 0.00
150.00 80.04 12,006.00 0.00 0.00 0.00% 0.00

263.53 14.34 3,779.02 263.53 3,779.02 100.00% 0.00


240.94 11.15 2,686.48 240.94 2,686.48 100.00% 0.00
23.13 23.60 545.87 18.67 440.61 80.72% 0.00

62.00 67.59 4,190.58 58.00 3,920.22 93.55% 0.00


7.00 67.59 473.13 7.00 473.13 100.00% 0.00
53.00 67.59 3,582.27 40.00 2,703.60 75.47% 0.00
45.00 43.82 1,971.90 45.00 1,971.90 100.00% 0.00

168.70 13.62 2,297.69 168.70 2,297.69 100.00% 0.00


233.15 16.71 3,895.94 233.15 3,895.94 100.00% 0.00
378.18 18.90 7,147.60 378.18 7,147.60 100.00% 0.00
59.60 33.71 2,009.12 59.60 2,009.12 100.00% 0.00
14.05 29.26 411.10 7.00 204.82 49.82% 0.00
30.00 19.07 572.10 30.00 572.10 100.00% 0.00
20.00 18.94 378.80 9.00 170.46 45.00% 0.00
25.00 13.79 344.75 18.00 248.22 72.00% 0.00

36.00 40.64 1,463.04 36.00 1,463.04 100.00% 0.00


3.00 36.64 109.92 3.00 109.92 100.00% 0.00
7.00 32.64 228.48 7.00 228.48 100.00% 0.00
28.00 22.64 633.92 28.00 633.92 100.00% 0.00
38.00 11.73 445.74 24.00 281.52 63.16% 0.00
109.00 10.62 1,157.58 109.00 1,157.58 100.00% 0.00
120.00 12.62 1,514.40 120.00 1,514.40 100.00% 0.00
81.00 10.62 860.22 81.00 860.22 100.00% 0.00
36.00 10.62 382.32 36.00 382.32 100.00% 0.00
39.00 10.62 414.18 39.00 414.18 100.00% 0.00
5.00 12.62 63.10 5.00 63.10 100.00% 0.00
46.00 16.12 741.52 46.00 741.52 100.00% 0.00
43.00 14.12 607.16 43.00 607.16 100.00% 0.00
9.00 16.12 145.08 9.00 145.08 100.00% 0.00
48.00 18.12 869.76 44.00 797.28 91.67% 0.00
33.00 19.12 630.96 33.00 630.96 100.00% 0.00
35.00 19.12 669.20 35.00 669.20 100.00% 0.00
13.00 10.12 131.56 13.00 131.56 100.00% 0.00
38.00 107.06 4,068.28 38.00 4,068.28 100.00% 0.00
2.00 226.16 452.32 1.50 339.24 75.00% 0.00
17.00 13.18 224.06 17.00 224.06 100.00% 0.00
18.00 20.18 363.24 18.00 363.24 100.00% 0.00
6.00 15.18 91.08 6.00 91.08 100.00% 0.00

1.00 169.38 169.38 1.00 169.38 100.00% 0.00


38.00 183.10 6,957.80 38.00 6,957.80 100.00% 0.00
2.00 204.46 408.92 2.00 408.92 100.00% 0.00
3.00 218.18 654.54 3.00 654.54 100.00% 0.00
1.00 1,395.32 1,395.32 1.00 1,395.32 100.00% 0.00

1.00 81.07 81.07 0.50 40.54 50.01% 0.00


1.00 43.32 43.32 1.00 43.32 100.00% 0.00

16.00 57.39 918.24 16.00 918.24 100.00% 0.00


345.60 14.34 4,955.90 277.20 3,975.05 80.21% 0.00
172.80 11.15 1,926.72 133.74 1,491.20 77.40% 0.00
218.00 23.60 5,144.80 185.40 4,375.44 85.05% 0.00
1.00 32.32 32.32 0.00 0.00 0.00% 0.00

399.00 101.00 40,299.00 399.00 40,299.00 100.00% 0.00


31.00 105.40 3,267.40 31.00 3,267.40 100.00% 0.00
191.00 129.56 24,745.96 101.00 13,085.56 52.88% 90.00
4.00 267.75 1,071.00 3.00 803.25 75.00% 0.00
8.00 56.19 449.52 0.00 0.00 0.00% 0.00
70.00 96.22 6,735.40 14.00 1,347.08 20.00% 56.00
9.00 68.62 617.58 3.00 205.86 33.33% 3.00
2.00 67.26 134.52 0.00 0.00 0.00% 0.00

67.00 21.91 1,467.97 67.00 1,467.97 100.00% 0.00


710.79 12.61 8,963.06 632.00 7,969.52 88.92% 0.00
1,388.85 11.28 15,666.23 1,284.10 14,484.65 92.46% 0.00

31.00 15.28 473.68 31.00 473.68 100.00% 0.00


4.00 21.85 87.40 4.00 87.40 100.00% 0.00
2.00 48.69 97.38 2.00 97.38 100.00% 0.00
8.00 37.19 297.52 6.00 223.14 75.00% 0.00
2.00 45.69 91.38 2.00 91.38 100.00% 0.00
18.00 15.28 275.04 18.00 275.04 100.00% 0.00

5.00 2,522.78 12,613.90 5.00 12,613.90 100.00% 0.00


6.00 612.78 3,676.68 6.00 3,676.68 100.00% 0.00
1.00 596.39 596.39 1.00 596.39 100.00% 0.00
1.00 446.98 446.98 1.00 446.98 100.00% 0.00
1.00 686.39 686.39 1.00 686.39 100.00% 0.00
2.00 416.39 832.78 1.00 416.39 50.00% 0.00
1.00 416.98 416.98 1.00 416.98 100.00% 0.00
1.00 646.39 646.39 1.00 646.39 100.00% 0.00
2.00 371.39 742.78 2.00 742.78 100.00% 0.00
1.00 416.39 416.39 1.00 416.39 100.00% 0.00
1.00 536.39 536.39 1.00 536.39 100.00% 0.00
2.00 446.39 892.78 1.00 446.39 50.00% 0.00
1.00 732.78 732.78 1.00 732.78 100.00% 0.00
2.00 462.78 925.56 1.00 462.78 50.00% 0.00

7.50 182.69 1,370.18 5.00 913.45 66.67% 0.00


54.59 83.51 4,558.81 54.59 4,558.81 100.00% 0.00
708.79 67.31 47,708.65 708.79 47,708.65 100.00% 0.00
21.70 57.20 1,241.24 10.00 572.00 46.08% 0.00
348.83 48.15 16,796.16 348.83 16,796.16 100.00% 0.00
151.28 41.94 6,344.68 90.00 3,774.60 59.49% 0.00
294.92 39.82 11,743.71 181.00 7,207.42 61.37% 0.00
517.53 34.65 17,932.41 424.04 14,692.99 81.94% 0.00
10.00 32.60 326.00 5.00 163.00 50.00% 0.00
106.00 10.68 1,132.08 73.00 779.64 68.87% 0.00
22.00 10.01 220.22 20.00 200.20 90.91% 0.00

1.00 8,194.73 8,194.73 1.00 8,194.73 100.00% 0.00

7.00 830.05 5,810.35 7.00 5,810.35 100.00% 0.00


3.00 1,125.15 3,375.45 3.00 3,375.45 100.00% 0.00

198.00 175.85 34,818.30 134.00 23,563.90 67.68% 0.00


108.00 105.96 11,443.68 108.00 11,443.68 100.00% 0.00
26.00 95.96 2,494.96 20.00 1,919.20 76.92% 0.00
12.00 99.96 1,199.52 7.00 699.72 58.33% 0.00
79.00 70.96 5,605.84 23.00 1,632.08 29.11% 0.00
50.00 466.35 23,317.50 49.00 22,851.15 98.00% 0.00
7.00 165.27 1,156.89 0.00 0.00 0.00% 7.00
4.00 125.27 501.08 3.00 375.81 75.00% 1.00
49.00 466.65 22,865.85 0.00 0.00 0.00% 0.00

1.00 542.56 542.56 0.00 0.00 0.00% 0.00


50.00 1,039.78 51,989.00 29.00 30,153.62 58.00% 0.00
3.00 88.46 265.38 0.00 0.00 0.00% 0.00
3.00 98.46 295.38 0.00 0.00 0.00% 0.00

1.00 1,000,000.00 1,000,000.00 0.27 267,647.97 26.76% 0.00


1.00 338,239.86 338,239.86 0.00 0.00 0.00% 0.00

1.00 48,700.00 48,700.00 0.00 0.00 0.00% 0.00


11,290,567.17 7,657,841.09 67.83%
1,251,785.99
457,239.67
229,616.33
52,906.89
13,282,116.05
ACTUAL ACUMULADO SALDO
Parcial % Metrado Parcial % Metrado Parcial

0.00 0.00 1.00 577.16 100.00% 0.00 0.00


0.00 0.00 12.00 3000 100.00% 0.00 0.00
0.00 0.00 75.00 3321 93.75% 5.00 221.40
0.00 0.00 152.90 5694 91.01% 15.10 562.32

0.00 0.00% 1.00 900.00 100.00% 0.00 0.00

0.00 0.00% 6,007.87 3,064.01 77.84% 1,710.56 872.39

0.00 0.00% 73.00 259.15 100.00% 0.00 0.00


0.00 0.00% 110.00 625.90 100.00% 0.00 0.00
0.00 0.00% 5.00 28.45 100.00% 0.00 0.00
0.00 0.00% 20.00 94.80 100.00% 0.00 0.00
0.00 0.00% 2,130.43 3,557.82 100.00% 0.00 0.00

0.00 0.00% 554.97 22,714.92 100.00% 0.00 0.00


0.00 0.00% 1,433.55 7,325.44 100.00% 0.00 0.00
0.00 0.00% 705.34 3,604.29 100.00% 0.00 0.00
0.00 0.00% 149.92 5,948.83 94.89% 8.08 320.61
0.00 0.00% 188.71 35,041.56 100.00% 0.00 0.00
0.00 0.00% 1,161.87 26,897.29 100.00% 0.00 0.00
0.00 0.00% 51.25 7,123.24 71.15% 20.78 2,888.21
0.00 0.00% 222.60 30,939.17 68.51% 102.32 14,221.46
0.00 0.00% 176.10 4,504.64 100.00% 0.00 0.00
0.00 0.00% 16.67 1,386.44 100.00% 0.00 0.00
0.00 0.00% 50.34 1,079.29 86.05% 8.16 174.95
0.00 0.00% 16.18 203.06 100.00% 0.00 0.00
0.00 0.00% 295.47 12,876.58 100.00% 0.00 0.00
0.00 0.00% 186.95 626.28 99.99% 0.01 0.03
322.24 9.22% 2,514.10 3,494.60 100.00% 0.00 0.00
0.00 0.00% 1,081.56 13,573.58 86.82% 164.25 2,061.34
0.00 0.00% 3,162.60 70,810.61 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 12.63 64.54

0.00 0.00% 1.00 12,000.00 100.00% 0.00 0.00

0.00 0.00% 4,301.04 6,537.58 57.89% 3,128.58 4,755.44


0.00 0.00% 5,283.31 8,030.63 71.11% 2,146.31 3,262.39

0.94 3,760.00 94.00% 0.06 240.00


0.00 0.00%
0.00 0.00% 176.00 35,752.64 97.78% 4.00 812.56
0.00 0.00% 1.00 1,150.00 100.00% 0.00 0.00
0.00 0.00% 1.00 750.00 100.00% 0.00 0.00
0.00 0.00% 1.00 3,820.00 100.00% 0.00 0.00
0.00 0.00% 1.00 1,010.00 100.00% 0.00 0.00

0.00 0.00% 439.89 6,290.43 89.47% 51.75 740.03


0.00 0.00% 1,918.57 53,489.73 88.41% 251.44 7,010.15
0.00 0.00% 93.81 2,615.42 100.00% 0.00 0.00
0.00 0.00% 122.45 3,480.03 8.35% 1,344.03 38,197.33
0.00 0.00% 0.00 0.00 0.00% 5.95 169.10

178.19 1.81% 885.84 8,902.69 90.23% 95.87 963.49

0.00 0.00% 1,213.61 31,760.17 82.83% 251.56 6,583.33

0.00 0.00% 1,327.71 60,835.67 55.70% 1,056.00 48,385.92


0.00 0.00% 3,459.30 33,105.50 61.64% 2,153.23 20,606.41
0.00 0.00% 2,446.07 5,185.67 77.48% 711.04 1,507.40

115.44 0.17% 2,319.96 38,812.93 58.44% 1,649.72 27,599.82


1,062.00 0.91% 3,900.19 92,044.48 78.94% 1,040.45 24,554.62

0.00 0.00% 693.50 148,138.54 92.70% 54.58 11,658.83


0.00 0.00% 426.99 8,373.27 100.00% 0.00 0.00
0.00 0.00% 510.94 37,503.00 26.55% 1,413.64 103,761.18

0.00 0.00% 143.11 32,599.03 25.78 5,872.43


0.00 0.00% 727.64 18,038.20 65.16% 388.99 9,643.06

0.00 0.00% 429.47 165,028.14 52.13% 394.37 151,540.62


0.00 0.00% 273.88 5,776.13 100.00% 0.00 0.00
0.00 0.00% 174.32 33,005.75 95.56% 8.10 1,533.65
0.00 0.00% 2,316.90 52,871.66 80.82% 549.95 12,549.86

0.00 0.00% 134.74 65,564.48 100.00% 0.00 0.00


0.00 0.00% 2,465.91 11,910.35 100.00% 0.00 0.00

0.00 0.00% 355.89 177,799.09 47.03% 400.91 200,290.63


0.00 0.00% 7,229.05 34,916.31 0.00 0.00

0.00 0.00% 54.51 27,273.53 100.00% 0.00 0.00


0.00 0.00% 293.17 9,126.38 100.00% 0.00 0.00
0.00 0.00% 3,231.71 15,609.16 100.00% 0.00 0.00

0.00 0.00% 96.15 22,844.28 86.04% 15.60 3,706.40


0.00 0.00% 1,084.71 28,484.48 87.10% 160.67 4,219.19
0.00 0.00% 2,820.52 13,623.11 77.06% 839.51 4,054.83

0.00 0.00% 246.04 123,103.65 70.92% 100.87 50,469.30


0.00 0.00% 1,094.00 36,298.92 76.33% 339.18 11,253.99
0.00 0.00% 10,280.63 49,655.44 77.31% 3,016.51 14,569.74

0.00 0.00% 420.64 228,075.21 100.00% 0.00 0.00


0.00 0.00% 3,957.91 138,922.64 100.00% 0.00 0.00
0.00 0.00% 55,788.93 269,460.53 98.47% 869.05 4,197.51

0.00 0.00% 501.91 257,831.17 100.00% 0.00 0.00


0.00 0.00% 4,063.69 167,992.94 100.00% 0.00 0.00
0.00 0.00% 46,420.70 224,211.98 100.00% 0.00 0.00

0.00 0.00% 25.65 12,961.97 100.00% 0.00 0.00


0.00 0.00% 148.92 4,570.35 100.00% 0.00 0.00
0.00 0.00% 647.40 3,126.94 100.00% 0.00 0.00

0.00 0.00% 214.08 93,777.74 17.93 7,854.24


0.00 0.00% 2,380.38 74,815.34 93.91% 154.38 4,852.16
0.00 0.00% 15,257.06 73,691.60 84.64% 2,768.44 13,371.57
0.00 0.00% 188.00 471.88 0.89% 20,926.86 52,526.42
0.00 0.00% 1,479.40 40,935.00 616.87 17,068.79

0.00 0.00% 54.09 27,925.59 79.06% 14.33 7,398.29


0.00 0.00% 290.78 12,896.09 98.48% 4.48 198.69
0.00 0.00% 2,561.76 12,373.30 100.00% 0.00 0.00
435.35 8.81% 37.23 4,941.54 100.00% 0.00 0.00
0.00 0.00% 32.55 665.65 100.00% 0.00 0.00
0.00 0.00% 184.59 891.57 78.00% 52.07 251.50

0.00 0.00% 18.32 9,418.31 100.00% 0.00 0.00


0.00 0.00% 57.48 1,451.94 100.00% 0.00 0.00
0.00 0.00% 1,010.05 4,878.54 100.00% 0.00 0.00

2,397.66 100.00% 4.61 2,397.66 100.00% 0.00 0.00


1,001.43 100.00% 35.74 1,001.43 100.00% 0.00 0.00
1,449.43 91.82% 326.82 1,578.54 100.00% 0.00 0.00

0.00 0.00% 0.00 0.00 0.00% 2.21 1,181.71


0.00 0.00% 0.00 0.00 0.00% 12.06 372.53
0.00 0.00% 0.00 0.00 0.00% 96.77 479.98

0.00 0.00% 0.00 0.00 0.00% 0.36 80.89


0.00 0.00% 0.00 0.00 0.00% 3.84 111.24

0.00 0.00% 231.00 12,446.28 100.00% 0.00 0.00

0.00 0.00% 0.00 0.00 0.00% 14.50 978.17


0.00 0.00% 0.00 0.00 0.00% 2.41 427.56
0.00 0.00% 0.00 0.00 0.00% 1.36 247.94
567.58 9.78% 8.23 3,243.85 55.87% 6.50 2,561.98
312.49 9.42% 107.27 3,318.93 100.00% 0.00 0.00
0.00 0.00% 12.05 6,443.26 100.00% 0.00 0.00
0.00 0.00% 894.96 4,439.00 100.00% 0.00 0.00

0.00 0.00% 42.40 19,547.67 91.79% 3.79 1,747.30


0.00 0.00% 282.06 9,900.31 76.62% 86.07 3,021.06
0.00 0.00% 3,038.57 14,676.29 81.08% 709.26 3,425.73

0.00 0.00% 0.00 0.00 0.00% 91.00 1,524.25


0.00 0.00% 0.00 0.00 0.00% 1,173.43 42,630.71
0.00 0.00% 4,052.92 140,595.79 32.83% 8,293.04 287,685.56
0.00 0.00% 0.00 0.00 2,895.64 98,538.63

0.00 0.00% 1.00 4,181.19 100.00% 0.00 0.00


0.00 0.00% 0.00 0.00 0.00% 1.00 3,080.23
0.00 0.00% 2.00 3,152.66 100.00% 0.00 0.00
0.00 0.00% 2.00 3,989.86 100.00% 0.00 0.00
0.00 0.00% 2.00 4,030.26 100.00% 0.00 0.00
0.00 0.00% 1.00 7,539.53 100.00% 0.00 0.00
0.00 0.00% 6.00 24,184.80 100.00% 0.00 0.00
0.00 0.00% 3.00 10,471.05 60.00% 2.00 6,980.70
0.00 0.00% 2.40 7,148.88 100.00% 0.00 0.00
0.00 0.00% 3.00 1,442.40 100.00% 0.00 0.00

0.00 0.00% 11.00 689.15 100.00% 0.00 0.00


0.00 0.00% 28.00 1,451.80 100.00% 0.00 0.00

0.00 0.00% 2,909.54 279,635.89 69.26% 1,291.49 124,125.10


0.00 0.00% 21.85 1,466.57 6.86% 296.76 19,918.53

0.00 0.00% 3,545.17 368,945.84 87.69% 497.75 51,800.84


0.00 0.00% 1,151.59 68,726.89 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 9.00 426.78
0.00 0.00% 22.49 2,864.33 59.15% 15.53 1,977.90
0.00 0.00% 890.26 5,777.79 77.57% 257.48 1,671.05

0.00 0.00% 5,868.57 82,336.04 0.00 0.00


937.79 0.99% 4,139.39 67,265.09 71.14% 1,679.09 27,285.21
804.07 0.55% 4,154.44 90,234.44 61.63% 2,586.38 56,176.17
487.49 0.55% 3,461.17 88,017.55 99.98% 0.57 14.50
0.00 0.00% 8.00 76.40 20.83% 30.40 290.32
0.00 0.00% 0.00 0.00 0.00% 191.50 3,221.03
0.00 0.00% 0.00 0.00 112.80 1,582.58
583.26 26.58% 70.88 1,383.58 63.05% 41.54 810.86
0.00 0.00% 9.45 206.10 80.35% 2.31 50.38
0.00 0.00% 2,032.55 14,695.34 100.00% 0.00 0.00
864.72 51.33% 70.14 1,684.76 100.00% 0.00 0.00
0.00 0.00% 6,397.93 19,513.69 100.00% 0.00 0.00
0.00 0.00% 655.60 8,411.35 120.60 1,547.30
0.00 0.00% 0.00 0.00 0.00% 25.95 719.59
0.00 0.00% 3,530.84 101,758.81 0.00 0.00
0.00 0.00% 202.03 44,527.41 67.71% 96.34 21,233.34
0.00 0.00% 565.04 29,692.85 25.25% 1,673.16 87,924.56

0.00 0.00% 4,066.21 94,702.03 100.00% 0.00 0.00


0.00 0.00% 38.11 981.71 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 7.77 262.24
0.00 0.00% 0.00 0.00 0.00% 73.84 2,594.00

3,380.34 0.61% 6,205.27 445,538.39 80.78% 1,476.09 105,983.26


0.00 0.00% 0.00 0.00 0.00% 71.54 4,733.80
0.00 0.00% 0.00 0.00 0.00% 22.83 1,751.06
0.00 0.00% 24.05 1,567.10 80.09% 5.98 389.66
0.00 0.00% 0.00 0.00 0.00% 365.46 17,136.42
0.00 0.00% 0.00 0.00 0.00% 14.00 770.42

0.00 0.00% 2,040.69 84,749.86 100.00% 0.00 0.00


369.87 0.28% 1,762.74 94,218.45 71.18% 713.78 38,151.54
0.00 0.00% 109.69 7,310.84 100.00% 0.00 0.00
160.77 0.22% 1,080.00 72,954.00 100.00% 0.00 0.00
0.00 0.00% 1,921.92 9,532.72 0.00 0.00
0.00 0.00% 554.30 2,749.33 10.70% 4,627.24 22,951.11

0.00 0.00% 0.00 0.00 0.00% 36.14 498.73

0.00 0.00% 621.89 37,786.04 82.31% 133.69 8,123.00


0.00 0.00% 161.51 9,813.35 100.00% 0.00 0.00

0.00 0.00% 2,188.85 44,455.54 100.00% 0.00 0.00


0.00 0.00% 1,487.00 9,948.03 79.41% 385.51 2,579.06
0.00 0.00% 101.20 3,444.85 562.97 19,163.50

0.00 0.00% 0.00 0.00 0.00% 13.83 608.24


0.00 0.00% 0.00 0.00 0.00% 13.83 59.88

0.00 0.00% 278.37 66,895.09 5.01 1,203.95


0.00 0.00% 0.00 0.00 0.00% 10.23 4,296.60
0.00 0.00% 858.00 125,739.90 87.02% 128.02 18,761.33

0.00 0.00% 0.00 0.00 0.00% 37.00 4,786.69

0.00 0.00% 40.49 15,333.16 100.00% 0.00 0.00


0.00 0.00% 26.75 3,913.79 12.99% 179.24 26,224.60

0.00 0.00% 0.00 0.00 0.00% 6.72 1,126.54


0.00 0.00% 8.44 3,241.55 39.74% 12.80 4,916.10
0.00 0.00% 2.57 561.93 39.66% 3.91 854.92

0.00 0.00% 135.00 8,193.15 67.15% 66.05 4,008.57

3,141.32 100.00% 52.00 3,141.32 100.00% 0.00 0.00

737.64 6.82% 264.00 10,818.72 100.00% 0.00 0.00


0.00 0.00% 0.00 0.00 0.00% 13.60 1,932.29
1,335.86 100.00% 1.00 1,335.86 100.00% 0.00 0.00

0.00 0.00% 249.56 131,445.75 100.00% 0.00 0.00

0.00 0.00% 0.00 0.00 0.00% 4.00 879.72


0.00 0.00% 0.00 0.00 0.00% 1.00 288.38

0.00 0.00% 1,002.00 11,472.90 78.90% 268.00 3,068.60


0.00 0.00% 0.00 0.00 0.00% 244.00 1,695.80
0.00 0.00% 0.00 0.00 0.00% 48.00 333.60
0.00 0.00% 0.00 0.00 0.00% 16.00 219.20

0.00 0.00% 96.00 6,558.72 79.34% 25.00 1,708.00


0.00 0.00% 0.00 0.00 0.00% 3.00 174.96

0.00 0.00% 82.00 717.50 66.13% 42.00 367.50


0.00 0.00% 460.00 4,176.80 74.19% 160.00 1,452.80
0.00 0.00% 0.00 0.00 0.00% 3.00 120.00

0.00 0.00% 0.00 0.00 0.00% 207.61 4,033.86


0.00 0.00% 7,471.27 164,367.94 87.86% 1,031.93 22,702.46
548.99 1.06% 3,300.25 26,798.03 51.60% 3,095.59 25,136.19
6,144.34 7.65% 6,850.93 67,824.21 84.41% 1,265.66 12,530.03
0.00 0.00% 5,803.39 57,453.56 100.00% 0.00 0.00
11,538.52 30.01% 3,864.48 38,451.58 100.00% 0.00 0.00
0.00 0.00% 58.46 1,057.54 55.34% 47.18 853.49

0.00 0.00% 0.00 0.00 0.00% 384.01 3,763.30


0.00 0.00% 3.00 37.77 18.48% 13.23 166.57

0.00 0.00% 0.00 0.00 0.00% 5.10 19.58


0.00 0.00% 799.25 1,718.39 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 2.00 251.62

0.00 0.00% 0.00 0.00 0.00% 418.77 22,869.03


0.00 0.00% 50.00 1,738.50 84.83% 8.94 310.84
0.00 0.00% 21.00 903.00 24.13% 66.02 2,838.86
0.00 0.00% 0.00 0.00 0.00% 37.00 6,010.28
0.00 0.00% 2,500.00 24,475.00 57.98% 1,811.63 17,735.86
0.00 0.00% 620.00 3,379.00 67.59% 297.31 1,620.34
0.00 0.00% 0.00 0.00 0.00% 132.68 3,245.35
0.00 0.00% 0.00 0.00 0.00% 17.19 238.94
0.00 0.00% 0.00 0.00 0.00% 1.00 700.00

0.00 0.00% 1.00 763.37 100.00% 0.00 0.00


0.00 0.00% 21.66 3,804.36 80.04% 5.40 948.46
0.00 0.00% 0.00 0.00 0.00% 12.20 2,232.23
0.00 0.00% 16.90 7,257.03 31.19% 37.28 16,008.40
0.00 0.00% 0.00 0.00 0.00% 4.00 8,748.24
0.00 0.00% 0.00 0.00 0.00% 2.00 834.58
0.00 0.00% 3.00 2,485.53 60.00% 2.00 1,657.02
0.00 0.00% 0.00 0.00 0.00% 4.00 3,957.32
0.00 0.00% 0.50 1,344.67 50.00% 0.50 1,344.67
0.00 0.00% 0.50 1,419.67 50.00% 0.50 1,419.67
0.00 0.00% 0.50 1,511.12 50.00% 0.50 1,511.12
0.00 0.00% 0.50 961.12 50.00% 0.50 961.12
0.00 0.00% 0.50 434.44 50.00% 0.50 434.44
0.00 0.00% 0.00 0.00 0.00% 330.00 73,081.80
22.88 1.17% 1,220.81 1,953.30 100.00% 0.00 0.00
0.00 0.00% 626.11 14,663.50 58.47% 444.70 10,414.83
0.00 0.00% 0.00 0.00 0.00% 232.98 3,497.03
0.00 0.00% 0.00 0.00 0.00% 689.80 19,128.15
0.00 0.00% 6.00 205.44 100.00% 0.00 0.00
0.00 0.00% 36.00 9,000.00 100.00% 0.00 0.00
0.00 0.00% 137.25 16,470.00 100.00% 0.00 0.00

0.00 0.00% 10.00 2,200.00 100.00% 0.00 0.00


0.00 0.00% 4.00 880.00 100.00% 0.00 0.00
0.00 0.00% 22.00 12,320.00 100.00% 0.00 0.00
0.00 0.00% 7.00 2,450.00 77.78% 2.00 700.00
0.00 0.00% 1.00 560.00 20.00% 4.00 2,240.00
0.00 0.00% 7.00 2,450.00 100.00% 0.00 0.00
0.00 0.00% 2.00 1,140.00 100.00% 0.00 0.00
0.00 0.00% 2.00 720.00 28.57% 5.00 1,800.00
0.00 0.00% 0.00 0.00 0.00% 23.00 1,793.31
0.00 0.00% 0.00 0.00 0.00% 14.00 650.86
0.00 0.00% 16.00 1,239.36 100.00% 0.00 0.00
0.00 0.00% 14.00 191.80 100.00% 0.00 0.00
0.00 0.00% 26.41 6,492.63 100.00% 0.00 0.00
0.00 0.00% 15.00 343.80 100.00% 0.00 0.00
0.00 0.00% 23.00 527.16 35.38% 42.00 962.64

6.88 0.35% 136.80 1,961.71 100.00% 0.00 0.00


58.87 3.86% 132.42 1,476.48 96.80% 4.38 48.84
0.00 0.00% 15.82 373.35 100.00% 0.00 0.00

0.00 0.00% 1.00 74.25 50.00% 1.00 74.25


0.00 0.00% 6.00 367.80 85.71% 1.00 61.30
0.00 0.00% 2.00 115.90 66.67% 1.00 57.95
0.00 0.00% 6.00 338.40 85.71% 1.00 56.40
0.00 0.00% 65.00 3,081.00 92.86% 5.00 237.00
0.00 0.00% 3.00 489.66 75.00% 1.00 163.22

0.00 0.00% 3.00 38.70 56.28% 2.33 30.06


0.00 0.00% 125.00 1,387.50 100.00% 0.00 0.00
0.00 0.00% 61.00 603.29 100.00% 0.00 0.00
0.00 0.00% 236.90 2,333.47 99.96% 0.10 0.98
0.00 0.00% 190.22 1,795.68 100.00% 0.00 0.00
0.00 0.00% 195.20 1,672.86 100.00% 0.00 0.00
0.00 0.00% 219.00 1,743.24 100.00% 0.00 0.00
0.00 0.00% 18.00 526.68 58.10% 12.98 379.79

250.38 66.67% 3.00 375.57 100.00% 0.00 0.00


0.00 0.00% 2.00 222.38 100.00% 0.00 0.00
0.00 0.00% 15.00 1,427.85 100.00% 0.00 0.00
0.00 0.00% 2.00 158.38 100.00% 0.00 0.00
0.00 0.00% 3.00 189.57 100.00% 0.00 0.00
0.00 0.00% 1.00 93.76 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 4.00 1,284.76

0.00 0.00% 146.00 1,203.04 100.00% 0.00 0.00


0.00 0.00% 54.00 488.16 100.00% 0.00 0.00
0.00 0.00% 36.00 397.44 100.00% 0.00 0.00
0.00 0.00% 29.00 349.16 90.63% 3.00 36.12
0.00 0.00% 10.00 120.40 100.00% 0.00 0.00
0.00 0.00% 21.00 357.84 100.00% 0.00 0.00
0.00 0.00% 42.00 442.68 100.00% 0.00 0.00
0.00 0.00% 60.00 632.40 100.00% 0.00 0.00
0.00 0.00% 14.00 147.56 100.00% 0.00 0.00
0.00 0.00% 15.00 158.10 100.00% 0.00 0.00
0.00 0.00% 8.00 84.32 100.00% 0.00 0.00
0.00 0.00% 4.00 42.16 100.00% 0.00 0.00
0.00 0.00% 65.00 535.60 100.00% 0.00 0.00
0.00 0.00% 5.00 50.20 100.00% 0.00 0.00
0.00 0.00% 3.00 30.12 100.00% 0.00 0.00
0.00 0.00% 14.00 151.76 100.00% 0.00 0.00
0.00 0.00% 3.00 31.62 100.00% 0.00 0.00
0.00 0.00% 1.00 13.04 100.00% 0.00 0.00
39.12 75.00% 4.00 52.16 100.00% 0.00 0.00
0.00 0.00% 8.00 104.32 100.00% 0.00 0.00
0.00 0.00% 1.00 10.84 50.00% 1.00 10.84
0.00 0.00% 1.00 3,786.46 100.00% 0.00 0.00
0.00 0.00% 6.00 217.62 66.67% 3.00 108.81
0.00 0.00% 1.00 1,551.46 100.00% 0.00 0.00
0.00 0.00% 10.00 240.60 27.03% 27.00 649.62
0.00 0.00% 10.00 120.40 100.00% 0.00 0.00

0.00 0.00% 2.00 349.20 50.00% 2.00 349.20


0.00 0.00% 1.00 51.19 100.00% 0.00 0.00
0.00 0.00% 1.00 57.04 50.00% 1.00 57.04
0.00 0.00% 2.00 413.32 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 2.00 272.78
0.00 0.00% 1.00 4,588.36 100.00% 0.00 0.00
0.00 0.00% 0.80 2,430.69 80.00% 0.20 607.67
0.00 0.00% 0.80 2,188.06 80.00% 0.20 547.01
0.00 0.00% 1.30 77.01 65.00% 0.70 41.47
0.00 0.00% 1.30 86.76 65.00% 0.70 46.72
0.00 0.00% 1.30 110.75 65.00% 0.70 59.63
0.00 0.00% 1.30 67.91 65.00% 0.70 36.57
0.00 0.00% 1.30 16.77 65.00% 0.70 9.03
0.00 0.00% 4.30 53.45 53.75% 3.70 45.99

0.00 0.00% 321.30 5,542.43 94.86% 17.40 300.15


0.00 0.00% 558.46 40,008.07 81.01% 130.93 9,379.83
0.00 0.00% 70.70 4,921.43 100.00% 0.00 0.00
0.00 0.00% 535.46 130,229.23 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 78.00 1,995.24
0.00 0.00% 0.00 0.00 0.00% 337.50 344.25
0.00 0.00% 0.00 0.00 0.00% 19.50 1,715.42
0.00 0.00% 0.00 0.00 0.00% 78.00 2,041.26
0.00 0.00% 0.00 0.00 0.00% 150.00 12,006.00

0.00 0.00% 263.53 3,779.02 100.00% 0.00 0.00


0.00 0.00% 240.94 2,686.48 100.00% 0.00 0.00
0.00 0.00% 18.67 440.61 80.72% 4.46 105.26

0.00 0.00% 58.00 3,920.22 93.55% 4.00 270.36


0.00 0.00% 7.00 473.13 100.00% 0.00 0.00
0.00 0.00% 40.00 2,703.60 75.47% 13.00 878.67
0.00 0.00% 45.00 1,971.90 100.00% 0.00 0.00

0.00 0.00% 168.70 2,297.69 100.00% 0.00 0.00


0.00 0.00% 233.15 3,895.94 100.00% 0.00 0.00
0.00 0.00% 378.18 7,147.60 100.00% 0.00 0.00
0.00 0.00% 59.60 2,009.12 100.00% 0.00 0.00
0.00 0.00% 7.00 204.82 49.82% 7.05 206.28
0.00 0.00% 30.00 572.10 100.00% 0.00 0.00
0.00 0.00% 9.00 170.46 45.00% 11.00 208.34
0.00 0.00% 18.00 248.22 72.00% 7.00 96.53

0.00 0.00% 36.00 1,463.04 100.00% 0.00 0.00


0.00 0.00% 3.00 109.92 100.00% 0.00 0.00
0.00 0.00% 7.00 228.48 100.00% 0.00 0.00
0.00 0.00% 28.00 633.92 100.00% 0.00 0.00
0.00 0.00% 24.00 281.52 63.16% 14.00 164.22
0.00 0.00% 109.00 1,157.58 100.00% 0.00 0.00
0.00 0.00% 120.00 1,514.40 100.00% 0.00 0.00
0.00 0.00% 81.00 860.22 100.00% 0.00 0.00
0.00 0.00% 36.00 382.32 100.00% 0.00 0.00
0.00 0.00% 39.00 414.18 100.00% 0.00 0.00
0.00 0.00% 5.00 63.10 100.00% 0.00 0.00
0.00 0.00% 46.00 741.52 100.00% 0.00 0.00
0.00 0.00% 43.00 607.16 100.00% 0.00 0.00
0.00 0.00% 9.00 145.08 100.00% 0.00 0.00
0.00 0.00% 44.00 797.28 91.67% 4.00 72.48
0.00 0.00% 33.00 630.96 100.00% 0.00 0.00
0.00 0.00% 35.00 669.20 100.00% 0.00 0.00
0.00 0.00% 13.00 131.56 100.00% 0.00 0.00
0.00 0.00% 38.00 4,068.28 100.00% 0.00 0.00
0.00 0.00% 1.50 339.24 75.00% 0.50 113.08
0.00 0.00% 17.00 224.06 100.00% 0.00 0.00
0.00 0.00% 18.00 363.24 100.00% 0.00 0.00
0.00 0.00% 6.00 91.08 100.00% 0.00 0.00

0.00 0.00% 1.00 169.38 100.00% 0.00 0.00


0.00 0.00% 38.00 6,957.80 100.00% 0.00 0.00
0.00 0.00% 2.00 408.92 100.00% 0.00 0.00
0.00 0.00% 3.00 654.54 100.00% 0.00 0.00
0.00 0.00% 1.00 1,395.32 100.00% 0.00 0.00

0.00 0.00% 0.50 40.54 50.01% 0.50 40.54


0.00 0.00% 1.00 43.32 100.00% 0.00 0.00

0.00 0.00% 16.00 918.24 100.00% 0.00 0.00


0.00 0.00% 277.20 3,975.05 80.21% 68.40 980.86
0.00 0.00% 133.74 1,491.20 77.40% 39.06 435.52
0.00 0.00% 185.40 4,375.44 85.05% 32.60 769.36
0.00 0.00% 0.00 0.00 0.00% 1.00 32.32

0.00 0.00% 399.00 40,299.00 100.00% 0.00 0.00


0.00 0.00% 31.00 3,267.40 100.00% 0.00 0.00
11,660.40 47.12% 191.00 24,745.96 100.00% 0.00 0.00
0.00 0.00% 3.00 803.25 75.00% 1.00 267.75
0.00 0.00% 0.00 0.00 0.00% 8.00 449.52
5,388.32 80.00% 70.00 6,735.40 100.00% 0.00 0.00
205.86 33.33% 6.00 411.72 66.67% 3.00 205.86
0.00 0.00% 0.00 0.00 0.00% 2.00 134.52

0.00 0.00% 67.00 1,467.97 100.00% 0.00 0.00


0.00 0.00% 632.00 7,969.52 88.92% 78.79 993.54
0.00 0.00% 1,284.10 14,484.65 92.46% 104.75 1,181.58

0.00 0.00% 31.00 473.68 100.00% 0.00 0.00


0.00 0.00% 4.00 87.40 100.00% 0.00 0.00
0.00 0.00% 2.00 97.38 100.00% 0.00 0.00
0.00 0.00% 6.00 223.14 75.00% 2.00 74.38
0.00 0.00% 2.00 91.38 100.00% 0.00 0.00
0.00 0.00% 18.00 275.04 100.00% 0.00 0.00

0.00 0.00% 5.00 12,613.90 100.00% 0.00 0.00


0.00 0.00% 6.00 3,676.68 100.00% 0.00 0.00
0.00 0.00% 1.00 596.39 100.00% 0.00 0.00
0.00 0.00% 1.00 446.98 100.00% 0.00 0.00
0.00 0.00% 1.00 686.39 100.00% 0.00 0.00
0.00 0.00% 1.00 416.39 50.00% 1.00 416.39
0.00 0.00% 1.00 416.98 100.00% 0.00 0.00
0.00 0.00% 1.00 646.39 100.00% 0.00 0.00
0.00 0.00% 2.00 742.78 100.00% 0.00 0.00
0.00 0.00% 1.00 416.39 100.00% 0.00 0.00
0.00 0.00% 1.00 536.39 100.00% 0.00 0.00
0.00 0.00% 1.00 446.39 50.00% 1.00 446.39
0.00 0.00% 1.00 732.78 100.00% 0.00 0.00
0.00 0.00% 1.00 462.78 50.00% 1.00 462.78

0.00 0.00% 5.00 913.45 66.67% 2.50 456.73


0.00 0.00% 54.59 4,558.81 100.00% 0.00 0.00
0.00 0.00% 708.79 47,708.65 100.00% 0.00 0.00
0.00 0.00% 10.00 572.00 46.08% 11.70 669.24
0.00 0.00% 348.83 16,796.16 100.00% 0.00 0.00
0.00 0.00% 90.00 3,774.60 59.49% 61.28 2,570.08
0.00 0.00% 181.00 7,207.42 61.37% 113.92 4,536.29
0.00 0.00% 424.04 14,692.99 81.94% 93.49 3,239.43
0.00 0.00% 5.00 163.00 50.00% 5.00 163.00
0.00 0.00% 73.00 779.64 68.87% 33.00 352.44
0.00 0.00% 20.00 200.20 90.91% 2.00 20.02

0.00 0.00% 1.00 8,194.73 100.00% 0.00 0.00

0.00 0.00% 7.00 5,810.35 100.00% 0.00 0.00


0.00 0.00% 3.00 3,375.45 100.00% 0.00 0.00

0.00 0.00% 134.00 23,563.90 67.68% 64.00 11,254.40


0.00 0.00% 108.00 11,443.68 100.00% 0.00 0.00
0.00 0.00% 20.00 1,919.20 76.92% 6.00 575.76
0.00 0.00% 7.00 699.72 58.33% 5.00 499.80
0.00 0.00% 23.00 1,632.08 29.11% 56.00 3,973.76
0.00 0.00% 49.00 22,851.15 98.00% 1.00 466.35
1,156.89 100.00% 7.00 1,156.89 100.00% 0.00 0.00
125.27 25.00% 4.00 501.08 100.00% 0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 49.00 22,865.85

0.00 0.00% 0.00 0.00 0.00% 1.00 542.56


0.00 0.00% 29.00 30,153.62 58.00% 21.00 21,835.38
0.00 0.00% 0.00 0.00 0.00% 3.00 265.38
0.00 0.00% 0.00 0.00 0.00% 3.00 295.38

0.00 0.00% 0.27 267,647.97 26.76% 0.73 732,352.03


0.00 0.00% 0.00 0.00 0.00% 1.00 338,239.86

0.00 0.00% 0.00 0.00 0.00% 1.00 48,700.00


57,791.66 0.51% 7,715,632.76 68.34% 3,574,934.36

67.86
0.51
68.37
SALDO
%

0.00%
0.00%
6.25%
8.99%

0.00%
1
22.16%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
5.11%
0.00%
0.00%
28.85%
31.49%
0.00%
0.00%
13.95%
0.00%
0.00%
0.00%
0.00%
13.18%
0.00%
100.00%

0.00%

42.11%
28.89%

6.00%

2.22%
0.00%
0.00%
0.00%
0.00%

10.53%
11.59%
0.00%
91.65%
100.00%

9.77%

17.17%

44.30%
38.36%
22.52%

41.56%
21.06%

7.30%
0.00%
73.45%

15.26%
34.84%

47.87%
0.00%
4.44%
19.18%

0.00%
0.00%

52.97%
0.00%

0.00%
0.00%
0.00%

13.96%
12.90%
22.94%

29.08%
23.67%
22.69%

0.00%
0.00%
1.53%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

7.73%
6.09%
15.36%
99.11%
29.43%

20.94%
1.52%
0.00%
0.00%
0.00%
22.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

100.00%
100.00%
100.00%

100.00%
100.00%

0.00%

100.00%
100.00%
100.00%
44.13%
0.00%
0.00%
0.00%

8.21%
23.38%
18.92%

100.00%
100.00%
67.17%
100.00%

0.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
40.00%
0.00%
0.00%

0.00%
0.00%

30.74%
93.14%

12.31%
0.00%
100.00%
40.85%
22.43%

0.00%
28.86%
38.37%
0.02%
79.17%
100.00%
100.00%
36.95%
19.64%
0.00%
0.00%
0.00%
15.54%
100.00%
0.00%
32.29%
74.75%

0.00%
0.00%
100.00%
100.00%

19.22%
100.00%
100.00%
19.91%
100.00%
100.00%

0.00%
28.82%
0.00%
0.00%
0.00%
89.30%

100.00%

17.69%
0.00%

0.00%
20.59%
84.76%

100.00%
100.0%

1.77%
100.00%
12.98%

100.00%

0.00%
87.01%

100.00%
60.26%
60.34%

32.85%

0.00%

0.00%
100.00%
0.00%

0.00%

100.00%
100.00%

21.10%
100.00%
100.00%
100.00%

20.66%
100.00%

33.87%
25.81%
100.00%

100.00%
12.14%
48.40%
15.59%
0.00%
0.00%
44.66%

100.00%
81.52%

100.0%
0.00%
100.00%

100.00%
15.17%
75.87%
100.00%
42.02%
32.41%
100.00%
100.00%
100.00%

0.00%
19.96%
100.00%
68.81%
100.00%
100.00%
40.00%
100.00%
50.00%
50.00%
50.00%
50.00%
50.00%
100.00%
0.00%
41.53%
100.00%
100.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
22.22%
80.00%
0.00%
0.00%
71.43%
100.00%
100.00%
0.00%
0.00%
0.00%
0.00%
64.62%

0.00%
3.20%
0.00%

50.00%
14.29%
33.33%
14.29%
7.14%
25.00%

43.72%
0.00%
0.00%
0.04%
0.00%
0.00%
0.00%
41.90%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%

0.00%
0.00%
0.00%
9.38%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
50.00%
0.00%
33.33%
0.00%
72.97%
0.00%

50.00%
0.00%
50.00%
0.00%
100.00%
0.00%
20.00%
20.00%
35.00%
35.00%
35.00%
35.00%
35.00%
46.25%

5.14%
18.99%
0.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%

0.00%
0.00%
19.28%

6.45%
0.00%
24.53%
0.00%

0.00%
0.00%
0.00%
0.00%
50.18%
0.00%
55.00%
28.00%

0.00%
0.00%
0.00%
0.00%
36.84%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8.33%
0.00%
0.00%
0.00%
0.00%
25.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

50.01%
0.00%

0.00%
19.79%
22.60%
14.95%
100.00%

0.00%
0.00%
0.00%
25.00%
100.00%
0.00%
33.33%
100.00%

0.00%
11.08%
7.54%

0.00%
0.00%
0.00%
25.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
50.00%
0.00%
50.00%

33.33%
0.00%
0.00%
53.92%
0.00%
40.51%
38.63%
18.06%
50.00%
31.13%
9.09%

0.00%

0.00%
0.00%

32.32%
0.00%
23.08%
41.67%
70.89%
2.00%
0.00%
0.00%
100.00%

100.00%
42.00%
100.00%
100.00%

73.24%
100.00%

100.00%
31.66%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
01.00.00 ESTRUCTURAS

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.01 CONSTRUCCIONES PROVISIONALES

01.01.01.01 CARTEL DE OBRA 2.40X3.60 PZA 1.00 577.16 577.16 1.00 577.16
01.01.01.02 ALMACEN OFICINA Y CASETA DE GUARDIANIA MES 12.00 250.00 3,000.00 12.00 3,000.00
01.01.01.01 CERCO PROVICIONAL DE CALAMINA H =2,00 m M 80.00 44.28 3,542.40 80.00 3,542.40
01.01.01.02 CONSTRUCCION DE ALMACEN PROVICIONAL M2 168.00 37.24 6,256.32 168.00 6,256.32
01.01.02 INSTALACIONES PROVISIONALES
01.01.02.01 AGUA PARA LA CONSTRUCCION GLB 1.00 900.00 900.00 1.00 900.00
01.01.03 TRABAJOS PRELIMINARES
01.01.03.01 LIMPIEZA DE TERRENO MANUAL M2 7,718.43 0.51 3,936.40 6,007.87 3,064.01
01.01.04 REMOCIONES

01.01.04.01 DESMONTAJE DE PUERTAS PZA 73.00 3.55 259.15 73.00 259.15


01.01.04.02 DESMONTAJE DE VENTANAS PZA 110.00 5.69 625.90 117.00 665.73
01.01.04.03 DESMONTAJE DE VENTANAS - PUERTAS UND 5.00 5.69 28.45 5.00 28.45
01.01.04.04 DESMONTAJE DE APARATOS SANITARIOS UND 20.00 4.74 94.80 20.00 94.80
01.01.04.05 DESMONTAJE TECHO ETERNIT/CALAMINA M2 2,130.43 1.67 3,557.82 2,130.43 3,557.82
01.01.05 DEMOLICIONES

01.01.05.01 DEMOLICION MUROS DE ADOBE m3 554.97 40.93 22,714.92 554.97 22,714.92


01.01.05.02 DEMOLICION MUROS DE LADRILLO KK CABEZA M2 1,433.55 5.11 7,325.44 1,433.55 7,325.44
01.01.05.03 DEMOLICION DE LOSA ALIGERADA H=0.20M M2 705.34 5.11 3,604.29 705.34 3,604.29
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
01.01.05.04 ROTURA DE LOSA EN VOLADIZO m3 158.00 39.68 6,269.44 149.92 5,948.83
01.01.05.05 DEMOLICION COLUMNAS Y VIGAS DE CONCRETO m3 188.71 185.69 35,041.56 188.87 35,071.27
01.01.05.06 DEMOLICION DE PISO DE CONCRETO INC.F.P. LOSA DEPORTIVA M2 1,161.87 23.15 26,897.29 1,161.87 26,897.29
01.01.05.07 DEMOLICION DE SOBRECIMIENTOS m3 72.03 138.99 10,011.45 51.25 7,123.24
01.01.05.08 DEMOLICION DE CIMIENTOS DE CONCRETO m3 324.92 138.99 45,160.63 222.60 30,939.17
01.01.05.09 DEMOLICION DE CIMIENTOS DE MURO DE ADOBE m3 176.10 25.58 4,504.64 176.10 4,504.64
01.01.05.10 DEMOLICION DE ESCALERAS m3 16.67 83.17 1,386.44 16.67 1,386.44
01.01.05.11 DEMOLICION DE GRADAS DE CONCRETO m3 58.50 21.44 1,254.24 52.31 1,121.48
01.01.05.12 DEMOLICION DE BEBEDERO Y URINARIO DE CONCRETO M 16.18 12.55 203.06 16.18 203.06
01.01.05.13 DEMOLICION DE CERCO PERIMETRICO MURO DE LADRILLO SOGA M 295.47 43.58 12,876.58 295.47 12,876.58
01.01.05.14 PICADO DE CERAMICO M2 186.96 3.35 626.32 187.13 626.89
01.01.05.15 RASQUETEO Y DESMANCHADO DE MURO PARA PINTADO M2 2,514.10 1.39 3,494.60 3,821.03 5,311.23
01.01.05.16 ACARREO INTERNO, MAT.PROCEDENTE DE DEMOLICION. m3 1,245.81 12.55 15,634.92 1,081.56 13,573.58
01.01.05.17 ELIMINACION DE DEMOLICIONES m3 3,162.60 22.39 70,810.61 3,172.09 71,023.10
01.01.05.18 DEMOLICION DE MUROS DE LADRILLO KK SOGA M2 12.63 5.11 64.54 0.00 0.00
01.01.06 MOVILIZACIN DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS

01.01.06.01 MOVILIZACION , MAQUINARIAS Y HERRAMIENTAS GLB 1.00 12,000.00 12,000.00 1.00 12,000.00
01.01.07 TRAZO, NIVELES Y REPLANTEO

01.01.07.01 TRAZO Y REPLANTEO PRELIMINAR M2 7,429.62 1.52 11,293.02 6,301.04 9,577.58


01.01.07.02 REPLANTEO DURANTE EL PROCESO M2 7,429.62 1.52 11,293.02 6,783.31 10,310.63
01.02 SEGURIDAD Y SALUD
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial

01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALU GLB


1.00 4,000.00 4,000.00 0.94 3,760.00
01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 180.00 203.14 36,565.20 180.00 36,565.20
01.02.03 EQUIPO DE PROTECCION COLECTIVA GLB 1.00 1,150.00 1,150.00 1.00 1,150.00
01.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 750.00 750.00 1.00 750.00
01.02.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 3,820.00 3,820.00 1.00 3,820.00
01.02.06 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN EL TRA GLB 1.00 1,010.00 1,010.00 1.00 1,010.00
02.00.00 ESTRUCTURAS

02.01.00 MOVIMIENTO DE TIERRAS

02.01.01 EXCAVACIONES

02.01.01.01 EXCAVACION MASIVA C/MAQU1NA m3 491.64 14.30 7,030.45 439.89 6,290.43


02.01.01.02 EXCAV.ZANJAS Y ZAPATA Rt<2kg/cm2 h=1.5m m3 2,170.01 27.88 60,499.88 1,918.57 53,489.73
02.01.01.03 EXCAVACION DE ZANJA PARA CISTERNA RT<2kg/cm2 m3 93.81 27.88 2,615.42 93.81 2,615.42
02.01.01.04 EXCAVACION DE TERRENO NATURAL EN PATIOS Y VEREDAS m3 1,466.48 28.42 41,677.36 126.39 3,592.00
02.01.01.05 EXCAVACION DE ZANJA PARA BUZON DE INSPECCION m3 5.95 28.42 169.10 0.00 0.00
02.01.02 CORTES
02.01.02.01 CORTE A MAQUINA m3 981.71 10.05 9,866.19 885.84 8,902.69
02.01.03 RELLENOS

02.01.03.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3 1465.17 26.17 38,343.50 1,213.61 31,760.17
02.01.04 NIVELACION INTERIOR Y APISONADO

02.01.04.01 CONFORMACION DE TERRENO HASTA NIVEL DE SUBRASANTE M2 2,383.71 45.82 109,221.59 1,327.71 60,835.67
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.01.04.02 AFIRMADO DE 3" EN INTERIORES,PATIOS Y VEREDAS M2 5,612.53 9.57 53,711.91 3,459.30 33,105.50
02.01.04.03 NIVELACION INTERIOR Y APISONADO PARA F.PISO, PATIO Y VEREDAS M2 3,157.11 2.12 6,693.07 2,446.07 5,185.67
02.01.05 ELIMINACIO DE MATERIAL EXCEDENTE

02.01.05.01 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES m3 3,969.68 16.73 66,412.75 2,332.40 39,021.05
02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 4,940.64 23.60 116,599.10 3,929.69 92,740.68
02.02 OBRAS DE CONCRETO SIMPLE

02.02.01 CIMIENTOS CORRIDOS

02.02.01.01 CIMIENTOS CORRIDOS 1:10 + 30 % P.G. fe >=100Kg/cm2 M3 748.08 213.61 159,797.47 693.50 148,138.54
02.02.01.02 SOLADO PARA ZAPATAS e=2", 1:12 CEM/HORM M2 426.99 19.61 8,373.27 426.99 8,373.27
02.02.01.03 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M2 1,924.58 73.40 141,264.17 510.94 37,503.00
02.02.02 SOBRECM1ENTO|

02.02.02.01 SOBRECIMIENTO, CONCRETO 1:8 + 25% P.M. Fe >=100Kg/cm2 m3 168.89 227.79 38,471.45 143.11 32,599.03
02.02.02.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 1,116.63 24.79 27,681.26 727.64 18,038.20
02.02.03 BASE DE CONCRETO

02.02.03.01 BASE DE CONCRETO 1:8 + 25% P.M. m3 0.00 224.69 0.00


02.02.03.02 BASE DE CONCRETO, ENCOF. Y DESENCOF. M2 0.00 28.97 0.00
02.02.04 SARDINEL

02.02.04.01 SARDINEL, CONCRETO h=0.50M, fc= 175 Kg/cm2 Acabado 1:2 m3 823.84 384.26 316,568.76 429.47 165,028.14
02.02.04.02 SARDINEL, ENCOFRADO Y DESENCOFRADO M2 273.88 21.09 5,776.13 273.88 5,776.13
02.02.05 OTROS CONCRETOS CIMPLE
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.02.05.01 SUBZAPATA MEZCLA 1:10 + 30 % P.G. (fc=100 kg/cm2) m3 182.42 189.34 34,539.40 174.32 33,005.75
02.02.05.02 FALSO PISO MEZCLA 1:8 e=4" M2 2,866.85 22.82 65,421.52 2,316.90 52,871.66
02.03 OBRAS DE CONCRETO ARMADO

02.03.01 CIMIENTOS REFORZADOS

02.03.01.01 CIMIENTOS REFORZ. CONCRETO F'c = 210 kg/cm2 m3 134.74 486.60 65,564.48 134.74 65,564.48
02.03.01.02 CIMIENTOS REFORZ. ACERO Fy=4,200 kg/cm2 KG 2,465.91 4.83 11,910.35 2,465.91 11,910.35
02.03.02 ZAPATAS |

02.03.02.01 ZAPATAS.- CONCRETO 210 kg/cm2 m3 756.80 499.59 378,089.71 355.89 177,799.09
02.03.02.02 ZAPATAS.- ACERO Fy=4200 kg/cm2 KG 7,229.05 4.83 34,916.31 7,229.05 34,916.31
02.03.03 VIGAS DE CIMENTACION

02.03.03.01 VIGAS DE CIMENT.- CONC. 210 kg/cm2 m3 54.51 500.34 27,273.53 54.51 27,273.53
02.03.03.02 VIGAS DE CIMENT.- ENCOF. Y DESENCOF M2 293.17 31.13 9,126.38 293.17 9,126.38
02.03.03.03 VIGAS DE CIMENT.- ACERO Fy=4,200 kg/cm2 KG 3,231.71 4.83 15,609.16 3,231.71 15,609.16
02.03.04 SOBRECIMIENTOS REFORZADOS

02.03.04.01 SOBREC. REF. CONCRETO 1:8+25% P.M. m3 111.75 237.59 26,550.68 96.15 22,844.28
02.03.04.02 SOBREC. REF. ENCOFRADO Y DESENCOFRADO M2 1,245.38 26.26 32,703.68 1,084.71 28,484.48
02.03.04.03 SOBREC. REF.- ACERO Fy=4,200 kg/cm2 KG 3,660.03 4.83 17,677.94 2,820.52 13,623.11
02.03.05 MUROS REFORADOS
02.03.05.01 MUROS DE CONTENC.- CONCRETO 210 kg/cm2 m3 346.91 500.34 173,572.95 246.04 123,103.65
02.03.05.02 MUROS DE CONTENC.- ENCOF. Y DESENCOFRADO [DOS CARAS) M2 1,433.18 33.18 47,552.91 1,094.00 36,298.92
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.03.05.03 MUROS DE CONT.- ACERO Fy=4,200 kg/cm2 KG 13,297.14 4.83 64,225.19 10,280.63 49,655.44
02.03.06 COLUMNAS Y PLACAS

02.03.06.01 COLUMNAS.- CONCRETO 210 kg/cm2 - 2 pisos m3 420.64 542.21 228,075.21 420.64 228,075.21
02.03.06.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2 3,957.91 35.10 138,922.64 3,957.91 138,922.64
02.03.06.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 56,657.98 4.83 273,658.04 55,788.93 269,460.53
02.03.07 VIGAS

02.03.07.01 VIGAS.- CONCRETO 210 kg/cm2 - 2 PISOS M3 501.91 513.70 257,831.17 502.82 258,298.63
02.03.07.02 VIGAS.- ENCOFRADO Y DESENCOFRADO M2 4,063.69 41.34 167,992.94 4,074.78 168,451.41
02.03.07.03 VIGAS.- ACERO Fy=4200 kg/cm2 KG 46,420.70 4.83 224,211.98 46,470.89 224,454.40
02.03.08 LOSA MACIZA |

02.03.08.01 LOSAS MACIZAS.- CONC.210kg/cm2-2 PISOS M3 25.65 505.34 12,961.97 25.65 12,961.97
02.03.08.02 LOSAS MACIZAS.- ENCOFRADO Y DESENCOFRADO M2 148.92 30.69 4,570.35 148.92 4,570.35
02.03.08.03 LOSAS MACIZAS.- ACERO Fy=4,200 kg/cm2 KG 647.40 4.83 3,126.94 647.40 3,126.94
02.03.09 LOSA ALIGERADA

02.03.09.01 LOSA ALIGERADA - CONCRETO 210 kg/cm2 - 2 PISOS m3 232.01 438.05 101,631.98 214.08 93,777.74
02.03.09.02 LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADO M2 2,534.76 31.43 79,667.51 2,380.38 74,815.34
02.03.09.03 LOSA ALIGERADA.- ACERO Fy=4,200 kg/cm2 KG 18,025.50 4.83 87,063.17 15,257.06 73,691.60
02.03.09.04 LOSA ALIGERADA.- LADR. HUECO 15x30x30 und 21,114.86 2.51 52,998.30 188.00 471.88
02.03.09.05 LOSA ALIGERADA.- PLASTOFORMO DE 3.00x0.15x0.30m und 2,096.27 27.67 58,003.79 1,479.40 40,935.00
02.03.10 ESCALERAS
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.03.10.01 ESCALERAS.-CONCRETO 210kg/cm2 m3 68.42 516.28 35,323.88 54.09 27,925.59
02.03.10.02 ESCALERAS.- ENCOFRADO Y DESENCOFRADO M2 295.26 44.35 13,094.78 290.78 12,896.09
02.03.10.03 ESCALERAS.- ACERO Fy=4200 kg/cm2 KG 2,561.76 4.83 12,373.30 2,561.76 12,373.30
02.03.11 GRADAS 1

02.03.11.01 GRADAS EN PISO, CONCRETO F'c=175 kg/cm2. M2 37.23 132.73 4,941.54 43.84 5,818.88
02.03.11.02 GRADAS EN PISO, ENCOFRADO Y DESENCOFRADO M2 32.55 20.45 665.65 32.55 665.65
02.03.11.03 GRADAS EN PISO, ACERO Fy=4,200 kg/cm2 KG 236.66 4.83 1,143.07 184.59 891.57
02.03.12 CISTERNAS SUBTERRANEAS

02.03.12.01 CISTERNA, CONCRETO F'c=210 kg/cm2. m3 18.32 514.10 9,418.31 18.32 9,418.31
02.03.12.02 CISTERNA, ENCOFRADO Y DESENCOFRADO M2 57.48 25.26 1,451.94 57.48 1,451.94
02.03.12.03 CISTERNA, ACERO Fy=4200 kg/cm2 KG 1,010.05 4.83 4,878.54 1,010.05 4,878.54
02.03.13 TANQUE ELEVADO

02.03.13.01 TANQUES ELEVADOS.- CONCRETO 210 kR/cm2 m3 4.61 520.10 2,397.66 4.61 2,397.66
02.03.13.02 TANQUES ELEVADOS.- ENCOFRADO Y DESENCOFR M2 35.74 28.02 1,001.43 35.74 1,001.43
02.03.13.03 TANQUES ELEVADOS.- ACERO Fy=4,200 kg/cm2 KG 326.82 4.83 1,578.54 326.82 1,578.54
02.03.14 BUZON DE INSPECCION PARA DRENAJE

02.03.14.01 BUZON DE INSPECCION.- CONCRETO 210 kg/cm2 m3 2.21 534.71 1,181.71 0.00 0.00
02.03.14.02 BUZON DE INSPECCION.- ENCOFRADO Y DESENCOFRADO M2 12.06 30.89 372.53 0.00 0.00
02.03.14.03 BUZON DE INSPECCION.- ACERO Fy=4,200 kg/cm2 kg 96.77 4.96 479.98 0.00 0.00
02.03.15 DADOS DE CONCRETO
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.03.15.01 DADOS DE CONCRETO 1:8 + 25% P.M. m3 0.36 224.69 80.89 0.73 164.14
02.03.15.02 DADOS DE CONCRETO, ENCOF. Y DESENCOF. M2 3.84 28.97 111.24 7.03 203.67
02.03.16 CANALETAS

02.03.16.01 CANALETAS PARA AGUAS PLUVIALES fc=175 GRADERIAS M 231.00 53.88 12,446.28 293.05 15,789.53
02.03.17 GRADERIAS

02.03.17.01 RELLENO CON PIEDRA SELECCIONADA m3 14.50 67.46 978.17 0.00 0.00
02.03.17.02 CIMIENTOS CONCRETO CICLOPEO 1:10 + 40 % P.G. M3 2.41 177.41 427.56 0.00 0.00
02.03.17.03 CONCRETO CICLOPEO fc= 100Kg/cm2 + 50% P.G. M3 1.36 182.31 247.94 0.00 0.00
02.03.17.04 CONCRETO 175 kg/cm2 m3 14.73 394.15 5,805.83 8.23 3,243.85
02.03.17.05 ENCOFRADO Y DESENCOFRADO M2 107.27 30.94 3,318.93 107.27 3,318.93
02.03.17.06 CONCRETO 210 kg/cm2 GRADERIAS m3 12.05 534.71 6,443.26 12.05 6,443.26
02.03.17.07 GRADERIAS.- ACERO Fy=4,200 kg/cm2 kg 894.96 4.96 4,439.00 894.96 4,439.00
02.03.18 FALSA COLUMNA DE 0.25X0.20 (DADO DE CONCRETO)

02.03.18.01 COLUMNAS - CONCRETO 175 kg/cm2 Falsa Columna m3 46.19 461.03 21,294.98 43.59 20,095.38
02.03.18.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2 368.13 35.10 12,921.36 285.06 10,005.61
02.03.18.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 3,747.83 4.83 18,102.02 3,038.57 14,676.29
02.04 ESTRUCTURAS METALICAS Y COBERTURAS

02.04.01 TENSORES - VIGUETAS

02.04.01.01 TENSORES DE AC LISO 3/4" INCL. UNIONES M 91.00 16.75 1,524.25 0.00 0.00
02.04.01.02 VIGUETA-VM | M 1,173.43 36.33 42,630.71 0.00 0.00
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.04.01.03 CORREAS METALICAS DE 2"X6"X2MM M 12,345.96 34.69 428,281.35 4,052.92 140,595.79
02.04.01.04 VIGUETAS METALICAS DE 2"X2"X2MM M 2,895.64 34.03 98,538.63 0.00 0.00
02.04.02 TIJERALES

02.04.02.01 TIJERAL METALICO CON ANGULOS T-l (13.00m.) und 1.00 4,181.19 4,181.19 1.00 4,181.19
02.04.02.02 TIJERAL METALICO CON ANGULOS T-2 (9.50 m.) und 1.00 3,080.23 3,080.23 0.00 0.00
02.04.02.03 TIJERAL METALICO CON ANGULOS T-3 (4.20m.) und 2.00 1,576.33 3,152.66 2.00 3,152.66
02.04.02.04 TIJERAL METALICO CON ANGULOS T-4 (5.00m.) und 2.00 1,994.93 3,989.86 2.00 3,989.86
02.04.02.05 TIJERAL METALICO CON ANGULOS T-5 (5.40m.) und 2.00 2,015.13 4,030.26 2.00 4,030.26
02.04.02.06 TIJERAL METALICO CON ANGULOS T-6 (2.80m.) und 1.00 7,539.53 7,539.53 1.00 7,539.53
02.04.02.07 TIJERAL METALICO CON ANGULOS T-7 (6.00 m.) und 6.00 4,030.80 24,184.80 6.00 24,184.80
02.04.02.08 TIJERAL METALICO CON ANGULOS T-8 (6.60m.) und 5.00 3,490.35 17,451.75 3.00 10,471.05
02.04.02.09 TIJERAL METALICO CON ANGULOS T-9 (8.75m.) und 2.40 2,978.70 7,148.88 2.40 7,148.88
02.04.02.10 TIJERAL METALICO T-10 (L=6.65m, h=1.20m) DE TUBO und 3.00 480.80 1,442.40 3.00 1,442.40
RECTANGULAR

02.04.03 APOYOS

02.04.03.01 APOYO MOVIL und 11.00 62.65 689.15 11.00 689.15


02.04.03.02 APOYO FIJO VIGUETAS SOBRE TIMPANO und 28.00 51.85 1,451.80 28.00 1,451.80
02.04.04 COBERTURA

02.04.04.01 COBERTURA C/LAMINA TERMOACUST1CA TIPO TEJA C/ALMA M2 0.00 80.30 0.00
02.04.04.02 CUMBRERA TERMOACUSTICA C/ALMA ACERO ROJO/BLANCO M 0.00 46.97 0.00
02.04.04.03 COBERTURA DE ONDULINE CLASS1C M2 4,201.03 96.11 403,760.99 2,909.54 279,635.89
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
02.04.04.04 COBERTURA CLASS1C M 318.61 67.12 21,385.10 21.85 1,466.57
02.05,01 ESTRUCTURAS DE MADERA

02.05.01 VIGAS Y SUJETADORES

02.05.01.01 VIGAS Y SUJETADORES DE MADERA P2 0.00 5.10 0.00


COSTO DIRECTO 5,530,147.48 4,047,893.24
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% 0.00 0.00 0.00 1.00 577.16 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00 12.00 3,000.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00 80.00 3,542.40 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00 168.00 6,256.32 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 1.00 900.00 100.00% 0.00 0.00 0.00%

77.84% 0.00 0.00 0.00% 6,007.87 3,064.01 77.84% 1,710.56 872.39 22.16%

100.00% 0.00 0.00 0.00% 73.00 259.15 100.00% 0.00 0.00 0.00%
106.36% 0.00 0.00 0.00% 117.00 665.73 106.36% -7.00 -39.83 -6.36%
100.00% 0.00 0.00 0.00% 5.00 28.45 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 20.00 94.80 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2,130.43 3,557.82 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 554.97 22,714.92 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1,433.55 7,325.44 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 705.34 3,604.29 100.00% 0.00 0.00 0.00%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
94.89% 0.00 0.00 0.00% 149.92 5,948.83 94.89% 8.08 320.61 5.11%
100.08% 0.00 0.00 0.00% 188.87 35,071.27 100.08% -0.16 -29.71 -0.08%
100.00% 0.00 0.00 0.00% 1,161.87 26,897.29 100.00% 0.00 0.00 0.00%
71.15% 0.00 0.00 0.00% 51.25 7,123.24 71.15% 20.78 2,888.21 28.85%
68.51% 0.00 0.00 0.00% 222.60 30,939.17 68.51% 102.32 14,221.46 31.49%
100.00% 0.00 0.00 0.00% 176.10 4,504.64 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 16.67 1,386.44 100.00% 0.00 0.00 0.00%
89.42% 0.00 0.00 0.00% 52.31 1,121.48 89.42% 6.19 132.76 10.58%
100.00% 0.00 0.00 0.00% 16.18 203.06 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 295.47 12,876.58 100.00% 0.00 0.00 0.00%
100.09% 0.00 0.00 0.00% 187.13 626.89 100.09% -0.17 -0.57 -0.09%
151.98% 0.00 0.00 0.00% 3,821.03 5,311.23 151.98% -1,306.93 -1,816.63 -51.98%
86.82% 0.00 0.00 0.00% 1,081.56 13,573.58 86.82% 164.25 2,061.34 13.18%
100.30% 0.00 0.00 0.00% 3,172.09 71,023.10 100.30% -9.49 -212.48 -0.30%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.63 64.54 100.00%

100.00% 0.00 0.00 0.00% 1.00 12,000.00 100.00% 0.00 0.00 0.00%

84.81% 1,128.58 1,715.44 15.19% 7,429.62 11,293.02 100.00% 0.00 0.00 0.00%
91.30% 646.31 982.39 8.70% 7,429.62 11,293.02 100.00% 0.00 0.00 0.00%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

240.00 1.00 4,000.00 100.00% 0.00 0.00 0.00%


94.00% 0.06 6.00%
100.00% 0.00 0.00 0.00% 180.00 36,565.20 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 1,150.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 750.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 3,820.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 1,010.00 100.00% 0.00 0.00 0.00%

89.47% 0.00 0.00 0.00% 439.89 6,290.43 89.47% 51.75 740.03 10.53%
88.41% 0.00 0.00 0.00% 1,918.57 53,489.73 88.41% 251.44 7,010.15 11.59%
100.00% 0.00 0.00 0.00% 93.81 2,615.42 100.00% 0.00 0.00 0.00%
8.62% 0.00 0.00 0.00% 126.39 3,592.00 8.62% 1,340.09 38,085.36 91.38%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.95 169.10 100.00%

90.23% 0.00 0.00 0.00% 885.84 8,902.69 90.23% 95.87 963.49 9.77%

82.83% 0.00 0.00 0.00% 1,213.61 31,760.17 82.83% 251.56 6,583.33 17.17%

55.70% 0.00 0.00 0.00% 1,327.71 60,835.67 55.70% 1,056.00 48,385.92 44.30%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
61.64% 0.00 0.00 0.00% 3,459.30 33,105.50 61.64% 2,153.23 20,606.41 38.36%
77.48% 0.00 0.00 0.00% 2,446.07 5,185.67 77.48% 711.04 1,507.40 22.52%

58.76% 0.00 0.00 0.00% 2,332.40 39,021.05 58.76% 1,637.28 27,391.69 41.24%
79.54% 0.00 0.00 0.00% 3,929.69 92,740.68 79.54% 1,010.95 23,858.42 20.46%

92.70% 0.00 0.00 0.00% 693.50 148,138.54 92.70% 54.58 11,658.83 7.30%
100.00% 0.00 0.00 0.00% 426.99 8,373.27 100.00% 0.00 0.00 0.00%
26.55% 0.00 0.00 0.00% 510.94 37,503.00 26.55% 1,413.64 103,761.18 73.45%

84.74% 0.00 0.00 0.00% 143.11 32,599.03 25.78 5,872.43 15.26%


65.16% 0.00 0.00 0.00% 727.64 18,038.20 65.16% 388.99 9,643.06 34.84%

0.00
0.00

52.13% 0.00 0.00 0.00% 429.47 165,028.14 52.13% 394.37 151,540.62 47.87%
100.00% 0.00 0.00 0.00% 273.88 5,776.13 100.00% 0.00 0.00 0.00%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
95.56% 0.00 0.00 0.00% 174.32 33,005.75 95.56% 8.10 1,533.65 4.44%
80.82% 0.00 0.00 0.00% 2,316.90 52,871.66 80.82% 549.95 12,549.86 19.18%

100.00% 0.00 0.00 0.00% 134.74 65,564.48 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2,465.91 11,910.35 100.00% 0.00 0.00 0.00%

47.03% 0.00 0.00 0.00% 355.89 177,799.09 47.03% 400.91 200,290.63 52.97%
100.00% 0.00 0.00 0.00% 7,229.05 34,916.31 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 54.51 27,273.53 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 293.17 9,126.38 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3,231.71 15,609.16 100.00% 0.00 0.00 0.00%

86.04% 0.00 0.00 0.00% 96.15 22,844.28 86.04% 15.60 3,706.40 13.96%
87.10% 0.00 0.00 0.00% 1,084.71 28,484.48 87.10% 160.67 4,219.19 12.90%
77.06% 0.00 0.00 0.00% 2,820.52 13,623.11 77.06% 839.51 4,054.83 22.94%

70.92% 0.00 0.00 0.00% 246.04 123,103.65 70.92% 100.87 50,469.30 29.08%
76.33% 0.00 0.00 0.00% 1,094.00 36,298.92 76.33% 339.18 11,253.99 23.67%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
77.31% 0.00 0.00 0.00% 10,280.63 49,655.44 77.31% 3,016.51 14,569.74 22.69%

100.00% 0.00 0.00 0.00% 420.64 228,075.21 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3,957.91 138,922.64 100.00% 0.00 0.00 0.00%
98.47% 0.00 0.00 0.00% 55,788.93 269,460.53 98.47% 869.05 4,197.51 1.53%

100.18% 0.00 0.00 0.00% 502.82 258,298.63 100.18% -0.91 -467.47 -0.18%
100.27% 0.00 0.00 0.00% 4,074.78 168,451.41 100.27% -11.09 -458.46 -0.27%
100.11% 0.00 0.00 0.00% 46,470.89 224,454.40 100.11% -50.19 -242.42 -0.11%

100.00% 0.00 0.00 0.00% 25.65 12,961.97 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 148.92 4,570.35 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 647.40 3,126.94 100.00% 0.00 0.00 0.00%

92.27% 0.00 0.00 0.00% 214.08 93,777.74 17.93 7,854.24 7.73%


93.91% 0.00 0.00 0.00% 2,380.38 74,815.34 93.91% 154.38 4,852.16 6.09%
84.64% 0.00 0.00 0.00% 15,257.06 73,691.60 84.64% 2,768.44 13,371.57 15.36%
0.89% 0.00 0.00 0.00% 188.00 471.88 0.89% 20,926.86 52,526.42 99.11%
70.57% 0.00 0.00 0.00% 1,479.40 40,935.00 616.87 17,068.79 29.43%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
79.06% 0.00 0.00 0.00% 54.09 27,925.59 79.06% 14.33 7,398.29 20.94%
98.48% 0.00 0.00 0.00% 290.78 12,896.09 98.48% 4.48 198.69 1.52%
100.00% 0.00 0.00 0.00% 2,561.76 12,373.30 100.00% 0.00 0.00 0.00%

117.75% 0.00 0.00 0.00% 43.84 5,818.88 117.75% -6.61 -877.35 -17.75%
100.00% 0.00 0.00 0.00% 32.55 665.65 100.00% 0.00 0.00 0.00%
78.00% 0.00 0.00 0.00% 184.59 891.57 78.00% 52.07 251.50 22.00%

100.00% 0.00 0.00 0.00% 18.32 9,418.31 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 57.48 1,451.94 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1,010.05 4,878.54 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 4.61 2,397.66 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 35.74 1,001.43 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 326.82 1,578.54 100.00% 0.00 0.00 0.00%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.21 1,181.71 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.06 372.53 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 96.77 479.98 100.00%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
202.92% 0.00 0.00 0.00% 0.73 164.14 202.92% -0.37 -83.25 -102.92%
183.09% 0.00 0.00 0.00% 7.03 203.67 183.09% -3.19 -92.43 -83.09%

126.86% 0.00 0.00 0.00% 293.05 15,789.53 126.86% -62.05 -3,343.25 -26.86%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.50 978.17 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.41 427.56 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.36 247.94 100.00%
55.87% 0.00 0.00 0.00% 8.23 3,243.85 55.87% 6.50 2,561.98 44.13%
100.00% 0.00 0.00 0.00% 107.27 3,318.93 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 12.05 6,443.26 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 894.96 4,439.00 100.00% 0.00 0.00 0.00%

94.37% 0.00 0.00 0.00% 43.59 20,095.38 94.37% 2.60 1,199.60 5.63%
77.43% 0.00 0.00 0.00% 285.06 10,005.61 77.43% 83.07 2,915.76 22.57%
81.08% 0.00 0.00 0.00% 3,038.57 14,676.29 81.08% 709.26 3,425.73 18.92%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.00 1,524.25 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,173.43 42,630.71 100.00%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
32.83% 0.00 0.00 0.00% 4,052.92 140,595.79 32.83% 8,293.04 287,685.56 67.17%
0.00% 0.00 0.00 0.00% 0.00 0.00 2,895.64 98,538.63 100.00%

100.00% 0.00 0.00 0.00% 1.00 4,181.19 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,080.23 100.00%
100.00% 0.00 0.00 0.00% 2.00 3,152.66 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 3,989.86 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 4,030.26 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 7,539.53 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 6.00 24,184.80 100.00% 0.00 0.00 0.00%
60.00% 0.00 0.00 0.00% 3.00 10,471.05 60.00% 2.00 6,980.70 40.00%
100.00% 0.00 0.00 0.00% 2.40 7,148.88 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3.00 1,442.40 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 11.00 689.15 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 28.00 1,451.80 100.00% 0.00 0.00 0.00%

0.00
0.00
69.26% 0.00 0.00 0.00% 2,909.54 279,635.89 69.26% 1,291.49 124,125.11 30.74%
ROVINCIAL DE LA CONVENCIN
NFRAESTRUCTURA PBLICA
RA N 32 - DEL 01 AL 31 DE JULIO DEL 2015

ANTERIOR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
6.86% 0.00 0.00 0.00% 21.85 1,466.57 6.86% 296.76 19,918.53 93.14%

0.00
73.20% 2,937.83 0.05% 0.00 4,050,831.07 73.25% 1,479,316.32 26.75%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.00.00 ARQUITECTURA
03.01 MUROS Y TABIQUES DE ALBAILERIA
03.01.01 MURO DE LADRILLO KK TIPO IV CABEZA M: 1:1:4 E=1.5 cm (*) M2 4,042.92 104.07 420,746.68 3,545.17 368,945.84
03.01.02 MURO DE LADRILLO KK TIPO IV SOGA M: 1:1:4 E=1.5 cm (*) M2 1,151.59 59.68 68,726.89 1,151.59 68,726.89
03.01.03 MURO DE LADRILLO KK TIPO IV CANTO M: 1:1:4 E=1.5 cm (*) M2 9.00 47.42 426.78 0.00 0.00
03.01.04 TABIQUERIA DRYWALL INTERIOR E= O.lOm M2 38.02 127.36 4,842.23 22.49 2,864.33
03.01.05 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS KG 1,147.74 6.49 7,448.83 890.26 5,777.79
03.02 REVOQUES Y REVESTIIENTOS

03.02.01 TARRAJEO EN MUROS INTERIORES C:A 1:5 E=1.5 CM. M2 5,868.57 14.03 82,336.04 5,925.22 83,130.84
03.02.02 TARRAJEO EN MUROS EXTERIORES C:A 1: 5, E= 1.50 CM M2 5,818.48 16.25 94,550.30 4,261.47 69,248.89
03.02.03 TARRAJEO DE COLUMNAS C:A 1:5 E=1.5 CM. M2 6,740.82 21.72 146,410.61 4,267.34 92,686.62
03.02.04 TARRAJEO DE VIGAS C:A 1: 5, E=1.50 CM M2 3,461.74 25.43 88,032.05 3,476.67 88,411.72
03.02.05 TARRAJEO SEMIPULIDO DE BORDES BOLEADOS MEZCLA C:A 1:4 E= 1.5 CM M 38.40 9.55 366.72 8.00 76.40
03.02.06 TARRAJEO CEMENTO PULIDO CON OCRE ROJO M2 191.50 16.82 3,221.03 0.00 0.00
03.02.07 TARRAJEO CEMENTO PULIDO M2 112.80 14.03 1,582.58 0.00 0.00
03.02.08 TARRAJEO CON IMPERMEABILIZANTE (TANQUE LEVADO Y CISTERNA) M2 112.42 19.52 2,194.44 70.88 1,383.58
03.02.09 TARRAJEO CON IMPERMEABILIZANTE EN CONFORMACION DE M2 11.76 21.81 256.49 9.45 206.10
03.02.10 VESTIDURA DE DERRAMES (1:5) M 2,032.55 7.23 14,695.34 2,255.53 16,307.48
03.02.11 REVEST.CEMENTO PULIDO EN GRADAS M 70.14 24.02 1,684.76 70.14 1,684.76
03.02.12 BRUNAS SEGUN DETALLE (lxl cm) M 6,397.93 3.05 19,513.69 6,397.93 19,513.69
03.02.13 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 776.20 12.83 9,958.65 655.60 8,411.35
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.02.14 REVESTIDO DE GRADAS C:A, 1:3 e=1.5cm C/PERFIL DE ALUMINIO DE 1 1/2" M 25.95 27.73 719.59 0.00 0.00
03.03 CIELO RASOS

03.03.01 CIELO RASO CON MEZCLA C:A 1:5 M2 0.00 23.17 0.00
03.03.02 FALSO CIELO RASOS

03.03.02.01 FALSO C/RASO C/PLANCHA FIBROCEMENTO 1.22x2.44x6mm M2 3,530.84 28.82 101,758.81 3,756.24 108,254.84
03.03.02.02 CIELO BALDOSA ACUSTICA ACABADO PVC C/LANA DE VIDRIO M2 298.37 220.40 65,760.75 202.03 44,527.41
03.03.03 CIELO RASO CON YESO M2 2,238.20 52.55 117,617.41 565.04 29,692.85
03.04 PISOS Y PAVIMENTOS
03.04.01 CONTRAPISOS
03.04.01.01 CONTRAPISO DE 40 mm M2 4,066.21 23.29 94,702.03 4,066.21 94,702.03
03.04.01.02 CONTRAPISO DE 48 mm PARA RECIBIR VIN1LICO M2 38.11 25.76 981.71 38.11 981.71
03.04.01.03 CONTRAPISO PULIDO DE 2 M2 7.77 33.75 262.24 0.00 0.00
03.04.01.04 CONTRAPISO CON IMPERMEABILIZANTE E=2 TECHO M2 73.84 35.13 2,594.00 0.00 0.00
03.04.02 PISOS

03.04.02.01 PISO CERAMICO 30 x 30 SERIE COLOR - NACIONAL M2 7,681.36 71.80 551,521.65 6,909.51 496,102.73
03.04.02.02 PISO LOSETA VENECIANA 30x30 COLOR CLARO M2 71.54 66.17 4,733.80 0.00 0.00
03.04.02.03 PISO LOSETA VINILICA DE ALTO TRANSITO e=3.2mm M2 22.83 76.70 1,751.06 214.12 16,423.38
03.04.02.04 MACHIHEMBRADO MAD.l"x4" DURMIENTE 2"x3"x4" 1er Piso M2 30.03 65.16 1,956.75 24.05 1,567.10
03.04.02.05 PISO DE ALFOMBRA DE FIBRA VEGETAL M2 365.46 46.89 17,136.42 0.00 0.00
03.04.02.06 PISO DE COLORES INICIAL e= 0.20 M2 14.00 55.03 770.42 0.00 0.00
03.04.03 PISOS DE CONCRETO
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.04.03.01 PISO DE CEMENTO PULIDO Y BRUADO E=3" S/COLOREAR M2 2,040.69 41.53 84,749.86 2,053.29 85,273.13
03.04.03.02 VEREDA CONCRETO 175 kg/cm2 E=4" FROT.Y BRUADO M2 2,476.52 53.45 132,369.99 1,817.00 97,118.65
03.04.03.03 RAMPAS DE CONCRETO 175 kg/cm2 E=5" BRUADO S/D1SEO M2 109.69 66.65 7,310.84 153.20 10,210.70
03.04.03.04 CONCRETO F'C=175 KG/CM2 E= 5" ACAB. SEMIPULUDO (LOSA DEPORTIVA) M2 1,080.00 67.55 72,954.00 1,080.00 72,954.00
03.04.03.05 ACERO DE REFUERZO Fy=4200 kg/cm2 LOSA DE CONCRETO kg 1,921.92 4.96 9,532.72 1,921.92 9,532.72
03.04.03.06 MALLAS DE ACERO 1/4" PARA PISOS DE CONCRETO kg 5,181.54 4.96 25,700.44 554.30 2,749.33
03.04.04 ACABADO DE CONCRETO EN PISOS

03.04.04.01 ACABADO DE CEMENTO PULIDO E=2cm MEZCLA 1:2 M2 36.14 13.80 498.73 0.00 0.00
03.05 ZOCALOS Y CONTRAZOCALOS

03.05.01 ZOCALOS

03.05.01.01 ZOCALO DE CERAMICO 30x30 H=1.80m M2 755.58 60.76 45,909.04 621.89 37,786.04
03.05.01.02 ZOCALO DE CERAMICO 30x20 M2 161.51 60.76 9,813.35 161.51 9,813.35
03.05.02 CONTRAZOCALOS

03.05.02.01 CONTRAZOCALO DE LOSETA VENECIANA 10x30 CLARO M 2,188.85 20.31 44,455.54 2,188.85 44,455.54
03.05.02.02 CONTR.S/COLOREAR H=20 cm MZ 1:2 e=1.5 cm M 1,872.51 6.69 12,527.09 1,487.00 9,948.03
03.05.02.03 CONTRAZOCALO DE CERAMICO DE 10X30CM CLARO M 664.17 34.04 22,608.35 101.20 3,444.85
03.06 COBERTURA (Cubierta)

03.06.01 CUB.DE LADR.PASTELERO ASENTADO CON BARRO e=2"C/FRAGUA M2 13.83 43.98 608.24 0.00 0.00
03.06.02 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 13.83 4.33 59.88 0.00 0.00
03.07 CARPINTERIA DE MADERA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.07.01 PUERTAS

03.07.01.01 PUERTA CEDRO MACHIMBRADA C/V1SOR-AULA 2004 M2 283.38 240.31 68,099.05 278.37 66,895.09
03.07.01.02 PUERTA CEDRO ENCAJONADO E= 1 1/2 M2 10.23 420.00 4,296.60 0.00 0.00
03.07.02 VENTANAS

03.07.02.01 VENTANA CEDRO C/SEG.Y 1/2", SIERRA 01 Y 02 PISOS M2 986.02 146.55 144,501.23 858.00 125,739.90
03.07.03 MUEBLES

03.07.03.01 TICERO DE MADERA CEDRO (L=5 m) BARNIZADO und 37.00 129.37 4,786.69 0.00 0.00
03.08 CARPINTERIA METALICA Y HERRERIA
03.08.01 VENTANAS DE FIERRO
03.08.01.01 VENTANA.C/S PERF. 1 1/2"X1 1/2"X3/168" ,FIJA M2 40.49 378.69 15,333.16 40.49 15,333.16
03.08.01.02 DIVICIONES METALICAS E=1/16" M2 205.99 146.31 30,138.40 26.75 3,913.79
03.08.02 PUERTAS DE FIERRO
03.08.02.01 PUERTA METALICA LAC E=1/16" M2 6.72 167.64 1,126.54 0.00 0.00
03.08.02.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" M2 21.24 384.07 8,157.65 8.44 3,241.55
03.08.02.03 PUERTA METALICA C/PERFILES 3/16" M2 6.48 218.65 1,416.85 2.57 561.93
03.08.03 BARANDAS
03.08.03.01 BARANDAS PARA PUENTES , MUROS, RAMPAS Y PASARELAS M 201.05 60.69 12,201.72 194.60 11,810.27
03.08.04 PASAMANOS
03.08.04.01 PASAMANO DE TUBO FG DE 2" EN ESCALERA M 52.00 60.41 3,141.32 52.00 3,141.32
03.08.05 ESCALERAS
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.08.05.01 CANTONERA DE FIERRO EN ESCALERA M 264.00 40.98 10,818.72 264.00 10,818.72
03.08.05.02 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO M 13.60 142.08 1,932.29 0.00 0.00
03.08.05.03 ESCALERA METALICA DE CARACOL und 1.00 1,335.86 1,335.86 1.00 1,335.86
03.08.06 CERCOS
03.08.06.01 CERCO DE FIERRO TIPO REJA (H= 3.00 ) M 249.56 526.71 131,445.75 249.56 131,445.75
03.08.07 ELEMENTOS METALICOS ESPECIALES
03.08.07.01 MARCO Y TAPA DE FIERRO 0.60X0.60M und 4.00 219.93 879.72 0.00 0.00
03.08.07.02 MARCO Y TAPA DE FIERRO .80X.80M P/TQUE CISTERNA APOYADO 6M3 und 1.00 288.38 288.38 3.00 865.14
03.09 CERRAJERA

03.09.01 BISAGRAS
03.09.01.01 BISAGRAS CAPUCHINAS ACERO ALUMINIZADO 3 1/2" EN PUERTAS Y VENTANA PZA 1270 11.45 14,541.50 1,002.00 11,472.90
03.09.01.02 BISAGRA DE ACERO ALUMINIZADO DE 2.5" PESADA EN PUERTA/VENTANAS (S PZA 244.00 6.95 1,695.80 0.00 0.00
03.09.01.03 BISAGRA DE ACERO ALUMINIZADO DE 2.5" EN ESTANTERIA PZA 48.00 6.95 333.60 0.00 0.00
03.09.01.04 BISAGRA CAPUCHINAS ACERO ALUMINIZADO 4" EN PUERTAS PZA 16.00 13.70 219.20 0.00 0.00
03.09.02 CERRADURA
03.09.02.01 CERRADURA DOS GOLPES EN PUERTA PZA 121.00 68.32 8,266.72 96.00 6,558.72
03.09.02.02 CERRADURA LGO PARA PUERTA EXTERIOR PZA 3.00 58.32 174.96 0.00 0.00
03.09.03 ACCESORIOS CIERRE
03.09.03.01 CERROJO DE 2" ALUMINIZADO PARA PUERTA PZA 124.00 8.75 1,085.00 82.00 717.50
03.09.03.02 CERROJO "SAPITO" SEGURIDAD BAT.VENTANA PZA 620.00 9.08 5,629.60 460.00 4,176.80
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.09.03.03 CANDADO TIPO FORTE 60 MM. PZA 3.00 40.00 120.00 0.00 0.00
03.09.04 VIDRIO CRISTALES Y SIMILARES
03.09.04.01 VIDRIOS SEMIDOBLES IMPORTADO P2 0.00 8.93 0.00
03.09.04.02 VIDRIO TEMPLADO DE 6MM P2 207.61 19.43 4,033.86 0.00 0.00
03.09.04.03 VIDRIO TRIPLE DE BRONCE DE 6 MM SISTEMA NOVA INC COLOCACION P2 8,503.20 22.00 187,070.40 8,587.79 188,931.38
03.10 PINTURA

03.10.01 PINTURA DE CIELOS RASOS, VIGAS, COLUMNAS Y PAREDES


03.10.01.01 PINTURA OLEO MATE BLANCO HUMO MUROS EXT. M2 6,395.84 8.12 51,934.22 10,898.53 88,496.04
03.10.01.02 PINTURA OLEO MATE ALABASTRO COL.VIG, DERRAM. M2 8,116.59 9.90 80,354.24 7,899.90 78,209.01
03.10.01.03 PINTURA OLEO MATE MARFIL MUROS M2 5,803.39 9.90 57,453.56 7,337.92 72,645.41
03.10.01.04 PINTURA LATEX 2 MANOS BLANCO CIELO RASO M2 3,864.48 9.95 38,451.58 5,490.52 54,630.65
03.10.01.05 PINTURA DE PIZARRA EN MUROS M2 105.64 18.09 1,911.03 58.46 1,057.54
03.10.02 PINTURA DE PUERTAS Y VENTANAS
03.10.02.01 PINT.ANTICOR.Y ESMALTE 2 MANOS-PTA/VENT. M2 384.01 9.80 3,763.30 0.00 0.00
03.10.02.02 PINTURA BARNIZ EN CARP.DE MADERA M2 16.23 12.59 204.34 3.00 37.77
03.10.03 PINTURA DE CONTRAZOCALOS Y BARANDAS
03.10.03.01 PINTURA ANTICORROSIVA Y ESM. EN BARANDAS M 5.10 3.84 19.58 0.00 0.00
03.10.03.02 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=0.20 M 799.25 2.15 1,718.39 799.25 1,718.39
03.10.03.03 PINTURA DEMARCACION DE LOSA DEPORTIVA und 2.00 125.81 251.62 2.00 251.62
03.11 VARIOS, LIMPIEZA Y JARDINERA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.11.01 CANALETA DE FIERRO GALVANIZADO REGILLA M 418.77 54.61 22,869.03 195.10 10,654.41
03.11.02 TAPAJUNTA METALICA EN PISOS M 58.94 34.77 2,049.34 50.00 1,738.50
03.11.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) M 87.02 43.00 3,741.86 21.00 903.00
03.11.04 PIZARRA CEMENTO 5.0x1.20 SIN TISERO PZA 37.00 162.44 6,010.28 0.00 0.00
03.11.05 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" M 4,311.63 9.79 42,210.86 2,500.00 24,475.00
03.11.06 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1/2" M 917.31 5.45 4,999.34 620.00 3,379.00
03.11.07 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR M 132.68 24.46 3,245.35 0.00 0.00
03.11.08 JUNTA DE DILATACION CON ESPUMA PLASTICA+JEBE MICROPOROSO M 17.19 13.90 238.94 0.00 0.00
03.11.09 LIMPIEZA FINAL DE LA OBRA GLB 1.00 700.00 700.00 0.00 0.00
03.12 OTROS

03.12.01 ASTA DE BANDERA TIPICO PZA 1.00 763.37 763.37 3.00 2,290.11
03.12.02 LOSA C.A.e=10cm.ANCHO 55cm.ACAB.C.PUL. PARA ASIENTOS EN DUCHAS M 27.06 175.64 4,752.82 21.66 3,804.36
03.12.03 LOSA C.A. PARA MESA DE LABORATORIO M 12.20 182.97 2,232.23 0.00 0.00
03.12.04 MESA C.A. REVESTIDO CON MAYOLICA PARA MESA DE LABORATORIO M2 54.18 429.41 23,265.43 16.90 7,257.03
03.12.05 ARCO Y TABLERO FULBITO-BASKET(MET-MAD) und 4.00 2,187.06 8,748.24 4.00 8,748.24
03.12.06 TUBOS C.VOLEY,INC.RED Y DADOS CONCRETO JGO 2.00 417.29 834.58 0.00 0.00
03.12.07 TOBOGAN H=1.85M (JUEGO INFANTIL) und 5 828.51 4,142.55 3.00 2,485.53
03.12.08 MESA DE NIOS und 4.00 989.33 3,957.32 0.00 0.00
03.12.09 JUEGO NIOS TIPO A und 1.00 2,689.33 2,689.33 0.50 1,344.67
03.12.10 JUEGO NIOS TIPO B und 1.00 2,839.33 2,839.33 0.50 1,419.67
03.12.11 JUEGO NIOS TIPO C und 1.00 3,022.23 3,022.23 0.50 1,511.12
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
03.12.12 JUEGO NIOS TIPO D und 1.00 1,922.23 1,922.23 0.50 961.12
03.12.13 COLUMPIO METALICOS L=3.10m (JUEGO INFANTIL) CON 03 ASIENTO und 1.00 868.88 868.88 0.50 434.44
03.12.14 BUTACAS und 330 221.46 73,081.80 0.00 0.00
03.12.15 CONFORMACION DE TALUD PARA JARDINERIA M2 1,220.81 1.60 1,953.30 1,416.65 2,266.64
03.12.16 SEMBRADO DE GRASS NATURAL INC. TIERRA DE CHACRA E= 0.10m M2 1,070.81 23.42 25,078.33 1,108.09 25,951.49
03.12.17 PISO BLANDO (JUEGOS INFANTILES) E= 6" M2 232.98 15.01 3,497.03 0.00 0.00
03.12.18 ANGULAR METALICO DE 1 1/2" X1 1/2" EN PISO PARA VEREDAS M 689.80 27.73 19,128.15 0.00 0.00
03.12.19 GARGOLAS und 6.00 34.24 205.44 6.00 205.44
03.12.20 PUERTAS EN SSHH DE MELAMINA CON PERFIL DE ALUMINIO und 36.00 250.00 9,000.00 36.00 9,000.00
03.12.21 PROTECTOR METALICO P/VENTANAS EN AULAS SEGUN DISENO M2 137.25 120.00 16,470.00 137.25 16,470.03
COSTO DIRECTO 3,592,008.84 3,012,220.68
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

87.69% 0.00 0.00 0.00% 3,545.17 368,945.84 87.69% 497.75 51,800.84 12.31%
100.00% 22.49 1,342.20 1.95% 1,174.08 70,069.09 101.95% -22.49 -1,342.20 -1.95%
0.00% 0.00 0.00 0.00% 0.00 0.00 9.00 426.78 100.00%
59.15% 0.00 0.00 0.00% 22.49 2,864.33 59.15% 15.53 1,977.90 40.85%
77.57% 0.00 0.00 0.00% 890.26 5,777.79 77.57% 257.48 1,671.05 22.43%

100.97% 0.00 0.00 0.00% 5,925.22 83,130.84 -56.65 -794.80 -0.97%


73.24% 0.00 0.00 0.00% 4,261.47 69,248.89 73.24% 1,557.01 25,301.41 26.76%
63.31% 0.00 0.00 0.00% 4,267.34 92,686.62 63.31% 2,473.48 53,723.99 36.69%
100.43% 0.00 0.00 0.00% 3,476.67 88,411.72 100.43% -14.93 -379.67 -0.43%
20.83% 0.00 0.00 0.00% 8.00 76.40 20.83% 30.40 290.32 79.17%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 191.50 3,221.03 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 112.80 1,582.58 100.00%
63.05% 0.00 0.00 0.00% 70.88 1,383.58 63.05% 41.54 810.86 36.95%
80.35% 0.00 0.00 0.00% 9.45 206.10 80.35% 2.31 50.38 19.64%
110.97% 0.00 0.00 0.00% 2,255.53 16,307.48 110.97% -222.98 -1,612.15 -10.97%
100.00% 0.00 0.00 0.00% 70.14 1,684.76 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 6,397.93 19,513.69 100.00% 0.00 0.00 0.00%
84.46% 0.00 0.00 0.00% 655.60 8,411.35 120.60 1,547.30 15.54%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.95 719.59 100.00%

0.00

106.38% 0.00 0.00 0.00% 3,756.24 108,254.84 -225.40 -6,496.03 -6.38%


67.71% 0.00 0.00 0.00% 202.03 44,527.41 67.71% 96.34 21,233.34 32.29%
25.25% 0.00 0.00 0.00% 565.04 29,692.85 25.25% 1,673.16 87,924.56 74.75%

100.00% 0.00 0.00 0.00% 4,066.21 94,702.03 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 38.11 981.71 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.77 262.24 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 73.84 2,594.00 100.00%

89.95% 0.00 0.00 0.00% 6,909.51 496,102.73 89.95% 771.85 55,418.92 10.05%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 71.54 4,733.80 100.00%
937.91% 0.00 0.00 0.00% 214.12 16,423.38 937.91% -191.29 -14,672.32 -837.91%
80.09% 0.00 0.00 0.00% 24.05 1,567.10 80.09% 5.98 389.66 19.91%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 365.46 17,136.42 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 770.42 100.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.62% 0.00 0.00 0.00% 2,053.29 85,273.13 100.62% -12.60 -523.28 -0.62%
73.37% 0.00 0.00 0.00% 1,817.00 97,118.65 73.37% 659.52 35,251.34 26.63%
139.67% 0.00 0.00 0.00% 153.20 10,210.70 139.67% -43.51 -2,899.86 -39.67%
100.00% 0.00 0.00 0.00% 1,080.00 72,954.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1,921.92 9,532.72 0.00 0.00 0.00%
10.70% 0.00 0.00 0.00% 554.30 2,749.33 10.70% 4,627.24 22,951.11 89.30%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.14 498.73 100.00%

82.31% 0.00 0.00 0.00% 621.89 37,786.04 82.31% 133.69 8,123.00 17.69%
100.00% 0.00 0.00 0.00% 161.51 9,813.35 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 2,188.85 44,455.54 100.00% 0.00 0.00 0.00%
79.41% 0.00 0.00 0.00% 1,487.00 9,948.03 79.41% 385.51 2,579.06 20.59%
15.24% 0.00 0.00 0.00% 101.20 3,444.85 562.97 19,163.50 84.76%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.83 608.24 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.83 59.88 100.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

98.23% 0.00 0.00 0.00% 278.37 66,895.09 5.01 1,203.95 1.77%


0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.23 4,296.60 100.00%

87.02% 0.00 0.00 0.00% 858.00 125,739.90 87.02% 128.02 18,761.33 12.98%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.00 4,786.69 100.00%

100.00% 0.00 0.00 0.00% 40.49 15,333.16 100.00% 0.00 0.00 0.00%
12.99% 0.00 0.00 0.00% 26.75 3,913.79 12.99% 179.24 26,224.60 87.01%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.72 1,126.54 100.00%
39.74% 0.00 0.00 0.00% 8.44 3,241.55 39.74% 12.80 4,916.10 60.26%
39.66% 0.00 0.00 0.00% 2.57 561.93 39.66% 3.91 854.92 60.34%

96.79% 0.00 0.00 0.00% 194.60 11,810.27 96.79% 6.45 391.45 3.21%

100.00% 0.00 0.00 0.00% 52.00 3,141.32 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 264.00 10,818.72 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.60 1,932.29 100.00%
100.00% 0.00 0.00 0.00% 1.00 1,335.86 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 249.56 131,445.75 100.00% 0.00 0.00 0.00%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 879.72 100.00%
300.00% 0.00 0.00 0.00% 3.00 865.14 300.00% -2.00 -576.76 -200.00%

78.90% 0.00 0.00 0.00% 1,002.00 11,472.90 78.90% 268.00 3,068.60 21.10%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 244.00 1,695.80 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.00 333.60 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 219.20 100.00%

79.34% 0.00 0.00 0.00% 96.00 6,558.72 79.34% 25.00 1,708.00 20.66%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 174.96 100.00%

66.13% 0.00 0.00 0.00% 82.00 717.50 66.13% 42.00 367.50 33.87%
74.19% 0.00 0.00 0.00% 460.00 4,176.80 74.19% 160.00 1,452.80 25.81%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 120.00 100.00%

0.00
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 207.61 4,033.86 100.00%
100.99% 0.00 0.00 0.00% 8,587.79 188,931.38 100.99% -84.59 -1,860.98 -0.99%

170.40% 0.00 0.00 0.00% 10,898.53 88,496.04 170.40% -4,502.69 -36,561.82 -70.40%
97.33% 0.00 0.00 0.00% 7,899.90 78,209.01 97.33% 216.69 2,145.23 2.67%
126.44% 0.00 0.00 0.00% 7,337.92 72,645.41 126.44% -1,534.53 -15,191.85 -26.44%
142.08% 0.00 0.00 0.00% 5,490.52 54,630.65 142.08% -1,626.04 -16,179.07 -42.08%
55.34% 0.00 0.00 0.00% 58.46 1,057.54 55.34% 47.18 853.49 44.66%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 384.01 3,763.30 100.00%
18.48% 0.00 0.00 0.00% 3.00 37.77 18.48% 13.23 166.57 81.52%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.10 19.58 100.0%
100.00% 0.00 0.00 0.00% 799.25 1,718.39 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 251.62 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
46.59% 0.00 0.00 0.00% 195.10 10,654.41 46.59% 223.67 12,214.62 53.41%
84.83% 0.00 0.00 0.00% 50.00 1,738.50 84.83% 8.94 310.84 15.17%
24.13% 0.00 0.00 0.00% 21.00 903.00 24.13% 66.02 2,838.86 75.87%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.00 6,010.28 100.00%
57.98% 0.00 0.00 0.00% 2,500.00 24,475.00 57.98% 1,811.63 17,735.86 42.02%
67.59% 0.00 0.00 0.00% 620.00 3,379.00 67.59% 297.31 1,620.34 32.41%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 132.68 3,245.35 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.19 238.94 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 700.00 100.00%

300.00% 0.00 0.00 0.00% 3.00 2,290.11 300.00% -2.00 -1,526.74 -200.00%
80.04% 0.00 0.00 0.00% 21.66 3,804.36 80.04% 5.40 948.46 19.96%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.20 2,232.23 100.00%
31.19% 0.00 0.00 0.00% 16.90 7,257.03 31.19% 37.28 16,008.40 68.81%
100.00% 0.00 0.00 0.00% 4.00 8,748.24 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 834.58 100.00%
60.00% 0.00 0.00 0.00% 3.00 2,485.53 60.00% 2.00 1,657.02 40.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 3,957.32 100.00%
50.00% 0.00 0.00 0.00% 0.50 1,344.67 50.00% 0.50 1,344.67 50.00%
50.00% 0.00 0.00 0.00% 0.50 1,419.67 50.00% 0.50 1,419.67 50.00%
50.00% 0.00 0.00 0.00% 0.50 1,511.12 50.00% 0.50 1,511.12 50.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
50.00% 0.00 0.00 0.00% 0.50 961.12 50.00% 0.50 961.12 50.00%
50.00% 0.00 0.00 0.00% 0.50 434.44 50.00% 0.50 434.44 50.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 330.00 73,081.80 100.00%
116.04% 0.00 0.00 0.00% 1,416.65 2,266.64 116.04% -195.84 -313.35 -16.04%
103.48% 0.00 0.00 0.00% 1,108.09 25,951.49 103.48% -37.28 -873.16 -3.48%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 232.98 3,497.03 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 689.80 19,128.15 100.00%
100.00% 0.00 0.00 0.00% 6.00 205.44 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 36.00 9,000.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 137.25 16,470.03 100.00% 0.00 -0.03 0.00%
83.86% 1,342.20 0.04% 3,013,562.88 83.90% 578,445.96 16.10%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.00.00 INSTALACIONES SANITARIAS

04.01 APARATOS SANITARIOS Y ACCESORIOS

04.01.01 LAVATORIO MANATIAL TREBOL O SIMILAR PZA 10.00 220.00 2,200.00 10.00 2,200.00
04.01.02 LAVATORIO SOBREPONER SONET BLANCO PZA 4.00 220.00 880.00 4.00 880.00
04.01.03 INODORO DE LOSA VITRIFICADA TREBOL O SIMILAR PZA 22.00 560.00 12,320.00 28.00 15,680.00
04.01.04 INODORO DE TAZA MILENIUM PZA 9.00 350.00 3,150.00 7.00 2,450.00
04.01.05 INODORO CON FLUXOMETRO PZA 5.00 560.00 2,800.00 5.00 2,800.00
04.01.06 INODORO TANQUE BAJO LOSA NIOS PZA 7.00 350.00 2,450.00 7.00 2,450.00
04.01.07 URINARIO CON FLUXOMETRO PZA 2.00 570.00 1,140.00 2.00 1,140.00
04.01.08 LAVADERO ACERO INOXIDABLE PZA 7.00 360.00 2,520.00 2.00 720.00
04.01.09 SARDINEL EN DUCHA REVESTIDA C/CERAMICO M 23.00 77.97 1,793.31 0.00 0.00
04.01.10 PAPELERA DE LOSA BLANCA DE 15X15 CM und 14.00 46.49 650.86 0.00 0.00
04.01.11 DUCHA SIMPLE CON GRIFERIA PZA 16.00 77.46 1,239.36 24.00 1,859.04
04.01.12 GRIFERIA PARA BEBEDERO und 14.00 13.70 191.80 21.00 287.70
04.01.13 BEBEDERO CORRIDO DE CONCRETO REVEST.C/MAYOLICA 15x15 M 26.41 245.84 6,492.63 26.41 6,492.63
04.01.14 COLOCACION DE ACCESORIOS SANITARIOS und 15.00 22.92 343.80 15.00 343.80
04.01.15 COLOCACION DE APARATOS SANITARIOS und 65.00 22.92 1,489.80 23.00 527.16
04.02 SISTEMA DE AGUA FRIA Y CONTRA1NCENDIOS

04.02.01 OBRAS PRELIMINARES

04.02.01.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3 136.80 14.34 1,961.71 137.16 1,966.87
04.02.01.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES m3 136.80 11.15 1,525.32 132.78 1,480.50
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.02.01.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 15.82 23.60 373.35 15.82 373.35
04.02.02 SALIDAS DE AGUA FRIA

04.02.02.01 SALIDA DE AGUA FRIA CON TUBERIA PVC SAP 2 1/2" PTO 2.00 74.25 148.50 1.00 74.25
04.02.02.02 SALIDAD DE AGUA FRIA CON TUBERIA PVC SAP 11/4" PTO 7.00 61.30 429.10 6.00 367.80
04.02.02.03 SALIDAD DE AGUA FRIA CON TUBERIA DE PVC SAP 1" PTO 3.00 57.95 173.85 2.00 115.90
04.02.02.04 SALIDAD DE AGUA FRIA CON TUBERIA PVC SAP 3/4 PTO 7.00 56.40 394.80 6.00 338.40
04.02.02.05 SALIDA DE AGUA FRIA - PVC SAP 1/2 PTO 70.00 47.40 3,318.00 65.00 3,081.00
04.02.02.06 SALIDAD DE AGUA FRIA CON TUBERIA FG 2" PTO 4.00 163.22 652.88 3.00 489.66
04.02.03 RED DE TUBERIAS

04.02.03.01 TUBERIA PVC SAP CLASE 10 - 2 1/2" M 5.33 12.90 68.76 3.00 38.70
04.02.03.02 TUBERIA PVC CLASE 10 - 2" M 125.00 11.10 1,387.50 125.00 1,387.50
04.02.03.03 TUBERIA PVC CLASE 10 -1 1/2" M 61.00 9.89 603.29 61.00 603.29
04.02.03.04 TUBERIA PVC CLASE 10 - 1 1/4" M 237.00 9.85 2,334.45 236.90 2,333.47
04.02.03.05 TUBERIA PVC CLASE 10-1" M 190.22 9.44 1,795.68 190.22 1,795.68
04.02.03.06 TUBERIA PVC CLASE 10 - 3/4" M 195.20 8.57 1,672.86 195.20 1,672.86
04.02.03.07 TUBERIA PVC CLASE 10 -1/2" M 219.00 7.96 1,743.24 219.00 1,743.24
04.02.03.08 TUBERIA DE FGDO 2" M 30.98 29.26 906.47 18.00 526.68
04.02.04 VALVULAS

04.02.04.01 VALVULA DE COMPUERTA DE BRONCE 1 1/4" und 3.00 125.19 375.57 3.00 375.57
04.02.04.02 VALVULA DE COMPUERTA DE BRONCE 1" und 2.00 111.19 222.38 2.00 222.38
04.02.04.03 VALVULA DE COMPUERTA DE BRONCE 3/4" und 15.00 95.19 1,427.85 15.00 1,427.85
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.02.04.04 VALVULA DE COMPUERTA DE BRONCE 1/2" und 2.00 79.19 158.38 2.00 158.38
04.02.04.05 VALVULA GLOBO 1/2" und 3.00 63.19 189.57 3.00 189.57
04.02.04.06 VALVULA GLOBO 1" und 1.00 93.76 93.76 1.00 93.76
04.02.04.07 VALVULA DE COMPUERTA DE BRONCE 2" und 4.00 321.19 1,284.76 0.00 0.00
04.02.05 ACCESORIOS

04.02.05.01 CODO PVC AGUA C- 10 -1/2" x 90 PZA 146.00 8.24 1,203.04 146.00 1,203.04
04.02.05.02 CODO PVC AGUA C-10 3/4" X90 PZA 54.00 9.04 488.16 54.00 488.16
04.02.05.03 CODO PVC AGUA C-10 1" X90 PZA 36.00 11.04 397.44 36.00 397.44
04.02.05.04 CODO PVC AGUA C-10 1 1/4" X 90 PZA 32.00 12.04 385.28 29.00 349.16
04.02.05.05 CODO PVC AGUA C-10 1 1/2" X90 PZA 10.00 12.04 120.40 10.00 120.40
04.02.05.06 CODO PVC AGUA C-10 2" X90 PZA 21.00 17.04 357.84 21.00 357.84
04.02.05.07 TEE PVC -SAP 1/2" PZA 42.00 10.54 442.68 42.00 442.68
04.02.05.08 TEE PVC -SAP 3/4" PZA 60.00 10.54 632.40 60.00 632.40
04.02.05.09 TEE PVC SAP 1" PZA 14.00 10.54 147.56 14.00 147.56
04.02.05.10 TEE PVC SAP 1 1/4" PZA 15.00 10.54 158.10 15.00 158.10
04.02.05.11 TEE PVC-SAP 1 1/2" PZA 8.00 10.54 84.32 8.00 84.32
04.02.05.12 TEE PVC SAP 2" PZA 4.00 10.54 42.16 4.00 42.16
04.02.05.13 REDUCCION PVC PARA AGUA FRIA 3/4" x 1/2" PZA 65.00 8.24 535.60 65.00 535.60
04.02.05.14 REDUCCION PVC PARA AGUA FRIA 1 1/4" x 3/4" PZA 5.00 10.04 50.20 5.00 50.20
04.02.05.15 REDUCCION PVC PARA AGUA FRIA 1 1/4" x 1" PZA 3.00 10.04 30.12 3.00 30.12
04.02.05.16 REDUCCION PVC PARA GAU FRIA 1 /12" X 1" PZA 14.00 10.84 151.76 14.00 151.76
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.02.05.17 REDUCCION PVC PARA AGUA FRIA 1 1/2" X 1 1/4" PZA 3.00 10.54 31.62 3.00 31.62
04.02.05.18 REDUCCION PVC PARA AGUA FRIA 2" x 3/4" PZA 1.00 13.04 13.04 1.00 13.04
04.02.05.19 REDUCCION PVC PARA AGUA FRIA 2" x 1 1/4" PZA 4.00 13.04 52.16 4.00 52.16
04.0205.20 REDUCCION PVC PARA AGUA FRIA 2" x 1 1/2 PZA 8.00 13.04 104.32 8.00 104.32
04.02.05.21 REDUCCION PVC PARA AGUA FRIA 11/2" X 1/2" PZA 2.00 10.84 21.68 1.00 10.84
04.02.05.22 ACCESORIOS CISTERNA YT-E 20M3-10M3 und 1.00 3,786.46 3,786.46 1.00 3,786.46
04.02.05.23 CAJA DE MADERA PARA VALVULA PZA 9.00 36.27 326.43 6.00 217.62
04.02.05.24 ACCESORIOS CISTERNA 180M3 und 1.00 1,551.46 1,551.46 1.00 1,551.46
04.02.05.25 CODO DE FG DE 1/2"X90 PZA 37.00 24.06 890.22 10.00 240.60
04.02.05.26 REDUCCION PVC PARA AGUA FRIA 1" x 3/4" PZA 10.00 12.04 120.40 10.00 120.40
04.02.06 VARIOS

04.02.06.01 LLAVE DE RIEGO C/GRIFO DE Vi' EN CAJUELA CONCRETO F'c 140 und 4.00 174.60 698.40 2.00 349.20
04.02.06.02 EMPALME A RED EXISTENTE, AGUA und 1.00 51.19 51.19 1.00 51.19
04.02.06.03 EMPALME A CISTERNA EXISTENTE und 2.00 57.04 114.08 3.00 171.12
04.02.06.04 CAJA DE VALVULA BYPASS DE CONCRETO und 2.00 206.66 413.32 4.00 826.64
04.02.06.05 CAJA DE REBOSE C/REJILLA DE FIERRO und 2.00 136.39 272.78 2.00 272.78
04.02.06.06 EQUIPO DE BOMBEO , 2 ELECTROBOMBAS 2.0 HP und 1.00 4,588.36 4,588.36 1.00 4,588.36
04.02.06.07 EQUIPO DE BOMBEO. 2 BOMBAS DE AGUA FRIA und 1.00 3,038.36 3,038.36 0.80 2,430.69
04.02.06.08 EQUIPO DE BOMBEO, ELECTROBOMBAS 1.4HP UND 1.00 2,735.07 2,735.07 0.80 2,188.06
04.02.06.09 REBOSE DE CISTERNA Y TANQUE E. DE FoGo Y 2" und 2.00 59.24 118.48 3.30 195.49
04.02.06.10 REBOSE DE CISTERNA DE FoGo Y 3" und 2.00 66.74 133.48 3.30 220.24
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.02.06.11 REBOSE DE CISTERNA DE FoGo 0 4" und 2.00 85.19 170.38 29.88 2,545.48
04.02.06.12 REBOSE DE TANQUE ALTO DE FoGo Y 2" und 2.00 52.24 104.48 3.30 172.39
04.02.06.13 ABRAZADERA DE FIJACION DE TUBO (Mx Y3") PZA 2.00 12.90 25.80 3.30 42.57
04.02.06.14 ABRAZADERA DE FIJACION DE TUBO PZA 8.00 12.43 99.44 47.30 587.94
04.03 SISTEMA DE DREANJE PLUVIAL

04.03.01 TUBERIA DE BAJADA PVC-SAP 4" P/LLUVIAS M 338.70 17.25 5,842.58 394.58 6,806.51
04.03.02 CANALETA DE FIERRO GALVANIZADO M 689.39 71.64 49,387.90 558.46 40,008.07
04.03.03 CANALETA CONC.175 P/EVAC.PLUVIAL e=.10m h=.30m (X-X) SIN M 70.70 69.61 4,921.43 70.70 4,921.43
04.03.04 CANALETA CONC.175 P/EVAC.PLUV1AL CON REJILLA (Y-Y) M 535.46 243.21 130,229.23 535.46 130,229.23
04.03.05 EXCAVACION DE ZANJA EN TERRENO NORMAL m3 78.00 25.58 1,995.24 0.00 0.00
04.03.06 PERFILADO DEFONDO DE ZANJA M2 337.50 1.02 344.25 0.00 0.00
04.03.07 CAMA DE ARENA m3 19.50 87.97 1,715.42 0.00 0.00
04.03.08 RELLENO COMPACTADO CON MATERIAL PROPIO m3 78.00 26.17 2,041.26 0.00 0.00
04.03.09 INSTALACION DE TUBERIA PVC SAL DE 315MM M 150.00 80.04 12,006.00 0.00 0.00
04.04 DESAGE Y VENTILACION

04.04.01 OBRAS PRELIMINARES

04.04.01.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3 263.53 14.34 3,779.02 263.53 3,779.02
04.04.01.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES m3 240.94 11.15 2,686.48 240.94 2,686.48
04.04.01.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 23.13 23.60 545.87 18.67 440.61
04.04.02 SALIDAS DE DESAGE

04.04.02.01 SALIDA DE DESAGE DE 2" EN PVC PTO 62.00 67.59 4,190.58 58.00 3,920.22
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.04.02.02 SALIDA DE DESAGE DE 3" EN PVC PTO 7.00 67.59 473.13 7.00 473.13
04.04.02.03 SALIDA DE DESAGE DE 4" EN PVC PTO 53.00 67.59 3,582.27 40.00 2,703.60
04.04.02.04 SALIDA PARA VENTILACION PTO 45.00 43.82 1,971.90 45.00 1,971.90
04.04.03 TUBERIAS

04.04.03.01 TUBERIA PVC-SAP 2" RED EXTERIOR M 168.70 13.62 2,297.69 168.70 2,297.69
04.04.03.02 TUBERIA PVC-SAP 3" RED EXTERIOR M 233.15 16.71 3,895.94 233.15 3,895.94
04.04.03.03 TUBERIA PVC-SAP 4" RED EXTERIOR M 378.18 18.90 7,147.60 382.18 7,223.21
04.04.03.04 TUBERIA PVC-SAP 6" RED EXTERIOR M 59.60 33.71 2,009.12 59.60 2,009.12
04.04.03.05 TUBERIA DE FGDO 2" M 14.05 29.26 411.10 7.00 204.82
04.04.03.06 TUBERIA PVC-SAL 4" M 30.00 19.07 572.10 30.00 572.10
04.04.03.07 TUBERIA PVC-SAL 3" M 20.00 18.94 378.80 9.00 170.46
04.04.03.08 TUBERIA PVC-SAL 2" M 25.00 13.79 344.75 18.00 248.22
04.04.04 ACCESORIOS

04.04.04.01 REGISTRO DE BRONCE 4" und 36.00 40.64 1,463.04 38.00 1,544.32
04.04.04.02 REGISTRO DE BRONCE 3" und 3.00 36.64 109.92 3.00 109.92
04.04.04.03 REGISTRO DE BRONCE 2" und 7.00 32.64 228.48 7.00 228.48
04.04.04.04 SUMIDERO DE BRONCE 2" und 28.00 22.64 633.92 28.00 633.92
04.04.04.05 SOMBRERO PARA VENTILACION EN PVC und 38.00 11.73 445.74 24.00 281.52
04.04.04.06 CODO PVC SAL 2" x 90 PZA 109.00 10.62 1,157.58 109.00 1,157.58
04.04.04.07 CODO PVC SAL 3"X 90 PZA 120.00 12.62 1,514.40 120.00 1,514.40
04.04.04.08 CODO PVC SAL 2" x 45 PZA 81.00 10.62 860.22 81.00 860.22
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.04.04.09 CODO PVC SAL 4" x 45 PZA 36.00 10.62 382.32 36.00 382.32
04.04.04.10 TEE PVC SAL 2" x 2" PZA 39.00 10.62 414.18 39.00 414.18
04.04.04.11 TEE PVC SAL 3" x 3" PZA 5.00 12.62 63.10 5.00 63.10
04.04.04.12 TEE PVC SAL 4" x 2" PZA 46.00 16.12 741.52 46.00 741.52
04.04.04.13 YEE PVC SAL DESAGE 2" x 2" PZA 43.00 14.12 607.16 43.00 607.16
04.04.04.14 YEE PVC SAL DESAGE 3" X 2" PZA 9.00 16.12 145.08 9.00 145.08
04.04.04.15 YEE PVC SAL DESAGE 4" X 2" PZA 48.00 18.12 869.76 44.00 797.28
04.04.04.16 YEE PVC SAL DESAGE 4" X 3" PZA 33.00 19.12 630.96 33.00 630.96
04.04.04.17 YEE PVC SAL DESAGE 4" X 4" PZA 35.00 19.12 669.20 35.00 669.20
04.04.04.18 REDUCCION PVC DESAGE SAL 3" x 2" PZA 13.00 10.12 131.56 13.00 131.56
04.04.04.19 TRAMPA "P" DE PVC SAL PARA DESAGE 2" PZA 38.00 107.06 4,068.28 38.00 4,068.28
04.04.04.20 ACCESORIOS PARA DESAGE EN SISTERNA Y TE und 2.00 226.16 452.32 3.50 791.56
04.04.04.21 CODO PVC SAL 4" x 90 PZA 17.00 13.18 224.06 17.00 224.06
04.04.04.22 TEE PVC SAL 4 x 3" PZA 18.00 20.18 363.24 18.00 363.24
04.04.04.23 CODO PVC SAL 3"X 45 PZA 6.00 15.18 91.08 6.00 91.08
04.04.05 CAJAS DE REGISTRO

04.04.05.01 CAJA DE REG.ALB.10"x20" C/TAPA CONCRETO und 1.00 169.38 169.38 1.00 169.38
04.04.05.02 CAJA DE REG.ALB.12"x24" C/TAPA CONCRETO und 38.00 183.10 6,957.80 51.00 9,338.10
04.04.05.03 CAJADE REG. ALB 18" x 20" VC/TAPA CONCRETO und 2.00 204.46 408.92 2.00 408.92
04.04.05.04 CAJA DE REG.ALB.24"x24" C/TAPA CONCRETO und 3.00 218.18 654.54 3.00 654.54
04.04.05.05 BUZON STANDAR DE D=1.20m H=1.40m und 1.00 1,395.32 1,395.32 1.00 1,395.32
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
04.04.06 VARIOS

04.04.06.01 CAJA SUMIDERO CON REJILLA DE FIERRO und 1.00 81.07 81.07 0.50 40.53
04.04.06.02 EMPALME A RED EXISTENTE, DESAGE und 1.00 43.32 43.32 1.00 43.32
COSTO DIRECTO 356,339.19 327,711.41
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% 0.00 0.00 0.00% 10.00 2,200.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 4.00 880.00 100.00% 0.00 0.00 0.00%
127.27% 0.00 0.00 0.00% 28.00 15,680.00 127.27% -6.00 -3,360.00 -27.27%
77.78% 0.00 0.00 0.00% 7.00 2,450.00 77.78% 2.00 700.00 22.22%
100.00% 0.00 0.00 0.00% 5.00 2,800.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 7.00 2,450.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 1,140.00 100.00% 0.00 0.00 0.00%
28.57% 0.00 0.00 0.00% 2.00 720.00 28.57% 5.00 1,800.00 71.43%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 1,793.31 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 650.86 100.00%
150.00% 0.00 0.00 0.00% 24.00 1,859.04 150.00% -8.00 -619.68 -50.00%
150.00% 0.00 0.00 0.00% 21.00 287.70 150.00% -7.00 -95.90 -50.00%
100.00% 0.00 0.00 0.00% 26.41 6,492.63 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 15.00 343.80 100.00% 0.00 0.00 0.00%
35.38% 0.00 0.00 0.00% 23.00 527.16 35.38% 42.00 962.64 64.62%

100.26% 0.00 0.00 0.00% 137.16 1,966.87 100.26% -0.36 -5.16 -0.26%
97.06% 0.00 0.00 0.00% 132.78 1,480.50 97.06% 4.02 44.82 2.94%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 15.82 373.35 100.00% 0.00 0.00 0.00%

50.00% 0.00 0.00 0.00% 1.00 74.25 50.00% 1.00 74.25 50.00%
85.71% 0.00 0.00 0.00% 6.00 367.80 85.71% 1.00 61.30 14.29%
66.67% 0.00 0.00 0.00% 2.00 115.90 66.67% 1.00 57.95 33.33%
85.71% 0.00 0.00 0.00% 6.00 338.40 85.71% 1.00 56.40 14.29%
92.86% 0.00 0.00 0.00% 65.00 3,081.00 92.86% 5.00 237.00 7.14%
75.00% 0.00 0.00 0.00% 3.00 489.66 75.00% 1.00 163.22 25.00%

56.28% 0.00 0.00 0.00% 3.00 38.70 56.28% 2.33 30.06 43.72%
100.00% 0.00 0.00 0.00% 125.00 1,387.50 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 61.00 603.29 100.00% 0.00 0.00 0.00%
99.96% 0.00 0.00 0.00% 236.90 2,333.47 99.96% 0.10 0.98 0.04%
100.00% 0.00 0.00 0.00% 190.22 1,795.68 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 195.20 1,672.86 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 219.00 1,743.24 100.00% 0.00 0.00 0.00%
58.10% 0.00 0.00 0.00% 18.00 526.68 58.10% 12.98 379.79 41.90%

100.00% 0.00 0.00 0.00% 3.00 375.57 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 222.38 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 15.00 1,427.85 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 2.00 158.38 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3.00 189.57 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 93.76 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 1,284.76 100.00%

100.00% 0.00 0.00 0.00% 146.00 1,203.04 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 54.00 488.16 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 36.00 397.44 100.00% 0.00 0.00 0.00%
90.63% 0.00 0.00 0.00% 29.00 349.16 90.63% 3.00 36.12 9.38%
100.00% 0.00 0.00 0.00% 10.00 120.40 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 21.00 357.84 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 42.00 442.68 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 60.00 632.40 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 14.00 147.56 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 15.00 158.10 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 8.00 84.32 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 4.00 42.16 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 65.00 535.60 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 5.00 50.20 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3.00 30.12 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 14.00 151.76 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 3.00 31.62 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 13.04 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 4.00 52.16 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 8.00 104.32 100.00% 0.00 0.00 0.00%
50.00% 0.00 0.00 0.00% 1.00 10.84 50.00% 1.00 10.84 50.00%
100.00% 0.00 0.00 0.00% 1.00 3,786.46 100.00% 0.00 0.00 0.00%
66.67% 0.00 0.00 0.00% 6.00 217.62 66.67% 3.00 108.81 33.33%
100.00% 0.00 0.00 0.00% 1.00 1,551.46 100.00% 0.00 0.00 0.00%
27.03% 0.00 0.00 0.00% 10.00 240.60 27.03% 27.00 649.62 72.97%
100.00% 0.00 0.00 0.00% 10.00 120.40 100.00% 0.00 0.00 0.00%

50.00% 0.00 0.00 0.00% 2.00 349.20 50.00% 2.00 349.20 50.00%
100.00% 0.00 0.00 0.00% 1.00 51.19 100.00% 0.00 0.00 0.00%
150.00% 0.00 0.00 0.00% 3.00 171.12 150.00% -1.00 -57.04 -50.00%
200.00% 0.00 0.00 0.00% 4.00 826.64 200.00% -2.00 -413.32 -100.00%
100.00% 0.00 0.00 0.00% 2.00 272.78 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 4,588.36 100.00% 0.00 0.00 0.00%
80.00% 0.00 0.00 0.00% 0.80 2,430.69 80.00% 0.20 607.67 20.00%
80.00% 0.00 0.00 0.00% 0.80 2,188.06 80.00% 0.20 547.01 20.00%
165.00% 0.00 0.00 0.00% 3.30 195.49 165.00% -1.30 -77.01 -65.00%
165.00% 0.00 0.00 0.00% 3.30 220.24 165.00% -1.30 -86.76 -65.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
1494.00% 0.00 0.00 0.00% 29.88 2,545.48 1494.00% -27.88 -2,375.10 -1394.00%
165.00% 0.00 0.00 0.00% 3.30 172.39 165.00% -1.30 -67.91 -65.00%
165.00% 0.00 0.00 0.00% 3.30 42.57 165.00% -1.30 -16.77 -65.00%
591.25% 0.00 0.00 0.00% 47.30 587.94 591.25% -39.30 -488.50 -491.25%

116.50% 0.00 0.00 0.00% 394.58 6,806.51 116.50% -55.88 -963.93 -16.50%
81.01% 0.00 0.00 0.00% 558.46 40,008.07 81.01% 130.93 9,379.83 18.99%
100.00% 0.00 0.00 0.00% 70.70 4,921.43 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 535.46 130,229.23 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.00 1,995.24 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.50 344.25 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.50 1,715.42 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.00 2,041.26 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 150.00 12,006.00 100.00%

100.00% 0.00 0.00 0.00% 263.53 3,779.02 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 240.94 2,686.48 100.00% 0.00 0.00 0.00%
80.72% 0.00 0.00 0.00% 18.67 440.61 80.72% 4.46 105.26 19.28%

93.55% 0.00 0.00 0.00% 58.00 3,920.22 93.55% 4.00 270.36 6.45%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 7.00 473.13 100.00% 0.00 0.00 0.00%
75.47% 0.00 0.00 0.00% 40.00 2,703.60 75.47% 13.00 878.67 24.53%
100.00% 0.00 0.00 0.00% 45.00 1,971.90 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 168.70 2,297.69 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 233.15 3,895.94 100.00% 0.00 0.00 0.00%
101.06% 0.00 0.00 0.00% 382.18 7,223.21 101.06% -4.00 -75.61 -1.06%
100.00% 0.00 0.00 0.00% 59.60 2,009.12 100.00% 0.00 0.00 0.00%
49.82% 0.00 0.00 0.00% 7.00 204.82 49.82% 7.05 206.28 50.18%
100.00% 0.00 0.00 0.00% 30.00 572.10 100.00% 0.00 0.00 0.00%
45.00% 0.00 0.00 0.00% 9.00 170.46 45.00% 11.00 208.34 55.00%
72.00% 0.00 0.00 0.00% 18.00 248.22 72.00% 7.00 96.53 28.00%

105.56% 0.00 0.00 0.00% 38.00 1,544.32 105.56% -2.00 -81.28 -5.56%
100.00% 0.00 0.00 0.00% 3.00 109.92 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 7.00 228.48 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 28.00 633.92 100.00% 0.00 0.00 0.00%
63.16% 0.00 0.00 0.00% 24.00 281.52 63.16% 14.00 164.22 36.84%
100.00% 0.00 0.00 0.00% 109.00 1,157.58 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 120.00 1,514.40 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 81.00 860.22 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% 0.00 0.00 0.00% 36.00 382.32 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 39.00 414.18 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 5.00 63.10 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 46.00 741.52 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 43.00 607.16 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 9.00 145.08 100.00% 0.00 0.00 0.00%
91.67% 0.00 0.00 0.00% 44.00 797.28 91.67% 4.00 72.48 8.33%
100.00% 0.00 0.00 0.00% 33.00 630.96 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 35.00 669.20 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 13.00 131.56 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 38.00 4,068.28 100.00% 0.00 0.00 0.00%
175.00% 0.00 0.00 0.00% 3.50 791.56 175.00% -1.50 -339.24 -75.00%
100.00% 0.00 0.00 0.00% 17.00 224.06 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 18.00 363.24 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 6.00 91.08 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 1.00 169.38 100.00% 0.00 0.00 0.00%
134.21% 0.00 0.00 0.00% 51.00 9,338.10 134.21% -13.00 -2,380.30 -34.21%
100.00% 0.00 0.00 0.00% 2.00 408.92 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3.00 654.54 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 1,395.32 100.00% 0.00 0.00 0.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

49.99% 0.00 0.00 0.00% 0.50 40.53 49.99% 0.50 40.54 50.01%
100.00% 0.00 0.00 0.00% 1.00 43.32 100.00% 0.00 0.00 0.00%
91.97% 0.00 0.00% 327,711.41 91.97% 28,627.78 8.03%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
05.00.00 INSTALACIONES ELECTRICAS

05.01 OBRAS PRELIMINARES

05.01.01 PICADO Y RESANE DE PISO Y VEREDA DE CONCRETO M2 16.00 57.39 918.24 33.71 1,934.62
05.01.02 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3 345.60 14.34 4,955.90 281.57 4,037.71
05.01.03 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT.ELEC.SANIT). m3 172.80 11.15 1,926.72 133.74 1,491.20
05.01.04 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 218.00 23.60 5,144.80 185.40 4,375.44
05.01.05 CONEXION A RED EXISTENTE und 1.00 32.32 32.32 0.00 0.00
05.02 SALIDA PARA ALUMBRADO, TOMACORRIENTES, FUERZAS

SEALES DEBILES

05.02.01 SALIDA DE TECHO (CENTRO DE LUZ) PTO 399.00 101.00 40,299.00 399.00 40,299.00
05.02.02 SALIDA PARA BRAQUETE (PARED) PTO 31.00 105.40 3,267.40 31.00 3,267.40
05.02.03 SALIDA PARA TOMACORRIENTE DOBLE PTO 191.00 129.56 24,745.96 197.00 25,523.32
05.02.04 SALIDA TRIFASICA PARA ELECTROBOMBA PTO 4.00 267.75 1,071.00 3.00 803.25
05.02.05 SALIDA DE TELEFONO y/o INTERCOMUNICADORES PTO 8.00 56.19 449.52 0.00 0.00
05.02.06 SALIDA PARA RED DATA (COMPUTO) PTO 70.00 96.22 6,735.40 70.00 6,735.40
05.02.07 SALIDA PARA TIMBRE PTO 9.00 68.62 617.58 6.00 411.72
05.02.08 SALIDA PARA VENTILADORES PTO 2.00 67.26 134.52 0.00 0.00
05.03 CANALIZACION Y/O TUBERIAS

05.03.01 TUBERIA PVC-P 65mm M 67.00 21.91 1,467.97 67.00 1,467.97


05.03.02 TUBERIA PVC-P35mm M 710.79 12.61 8,963.06 632.00 7,969.52
05.03.03 TUBERIA PVC-P 25mm M 1,388.85 11.28 15,666.23 1,284.10 14,484.65
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
05.04 CAJAS

05.04.01 CAJA DE PASE FG 4x4xl.5" und 31.00 15.28 473.68 38.00 580.64
05.04.02 CAJA DE PASE FG 6x6x3" und 4.00 21.85 87.40 4.00 87.40
05.04.03 CAJA DE PASE FG 12X12X6" und 2.00 48.69 97.38 2.00 97.38
05.04.04 CAJA PASE FG 6" x 6" x 2 1/2" und 8.00 37.19 297.52 6.00 223.14
05.04.05 CAJA PASE FG 6" x 6" x 6" und 2.00 45.69 91.38 2.00 91.38
05.04.06 CAJA DE PASE FG 4X4X2" und 18.00 15.28 275.04 18.00 275.04
05.05 TABLEROS Y CUCHILLAS (LLAVES)
05.05.01 T.G.AUT. 8-3X40,2-3X60. 2-2X40,4- 2X30 ,2-3X30 1-RESERVA und 5.00 2,522.78 12,613.90 5.00 12,613.90
05.05.02 TA. AUT. 4- 2 X 15A, 2- 2 X 20A und 6.00 612.78 3,676.68 6.00 3,676.68
05.05.03 TAB.AUT. 3-2X20, 4-2X15A und 1.00 596.39 596.39 1.00 596.39
05.05.04 TAB.AUT. 1-2X20, 2-2X15A und 1.00 446.98 446.98 1.00 446.98
05.05.05 TAB.AUT. 3-2X20, 6-2X15A und 1.00 686.39 686.39 1.00 686.39
05.05.06 TAB.AUT. 1-2X30,1-2X20,1-2X15A und 2.00 416.39 832.78 1.00 416.39
05.05.07 TAB.AUT. 1-2X20,2-2X15A und 1.00 416.98 416.98 1.00 416.98
05.05.08 TAB.AUT. 1-3X30, 3-2X20, 2-2X15A und 1.00 646.39 646.39 1.00 646.39
05.05.09 TAB.AUT. 2-2xl5A und 2.00 371.39 742.78 2.00 742.78
05.05.10 TAB. AUT. 3 - 2 x 15 A und 1.00 416.39 416.39 1.00 416.39
05.05.11 TAB AUT. 5- 2 x 20A TD1- UPS und 1.00 536.39 536.39 1.00 536.39
05.05.12 TAB. AUT. 3 - 2 x 20A TD2 - UPS und 2.00 446.39 892.78 1.00 446.39
05.05.13 TAB. AUT. CONTROL LUCES 8.2 X 15A und 1.00 732.78 732.78 1.00 732.78
05.05.14 TAB AUT. CONTROL ELECTROBOMBAS 2 X 20A und 2.00 462.78 925.56 1.00 462.78
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
05.06 CONEXIONES A RED EXTERNA Y MEDIDORES

05.06.01 AL1MENTADOR CAB. N2XH (3- 1X95 +1X50 +lX35)mm2 M 7.50 182.69 1,370.18 5.00 913.45
05.06.02 ALIMENTADOR CAB. N2XH (3-1x25 +1x25+ Ixl0)mm2 M 54.59 83.51 4,558.81 54.59 4,558.81
05.06.03 ALIMENTADOR CAB. N2XH (3-1x16 +1x16+ Ixl0)mm2 M 708.79 67.31 47,708.65 1,008.79 67,901.66
05.06.04 ALIMENTADOR CAB. N2XH (3-1x10 +1x10+ Ixl0)mm2 M 21.70 57.20 1,241.24 10.00 572.00
05.06.05 ALIMENTADOR CAB. N2XH (3-1x4 +1x4+ Ixl0)mm2 M 348.83 48.15 16,796.16 348.83 16,796.16
05.06.06 ALIMENTADOR CAB. N2XH (2-1x6 + Ixl0)mm2 M 151.28 41.94 6,344.68 200.00 8,388.00
05.06.07 ALIMENTADOR CAB. N2XH (2-1x4 + Ixl0)mm2 M 294.92 39.82 11,743.71 181.00 7,207.42
05.06.08 ALIMENTADOR CAB. N2XH 2- 1x6 mm2 M 517.53 34.65 17,932.41 424.04 14,692.99
05.06.09 ALIMENTADOR CAB. N2XH 2- 1x4 mm2 M 10.00 32.60 326.00 5.00 163.00
05.06.10 ALIMENTADOR SOL NH-70 2-lxl.5mm2/20mm PVC M 106.00 10.68 1,132.08 73.00 779.64
05.06.11 CABLE COBRE DESNUDO Ixl0mm2, Y 20mm PVC-P M 22.00 10.01 220.22 20.00 200.20
05.07 INSTALACION PARARRAYOS

05.07.01 PARARRAYO C/D1SPOSIT.DE CEBADO C/03P/T1ERRA.EN POSTE (2004) und 1.00 8,194.73 8,194.73 1.00 8,194.73
05.08 INSTALACION DEL SISTEMA PUESTA A TIERRA

05.08.01 POZO PUESTA A TIERRA P-l und 7.00 830.05 5,810.35 7.00 5,810.35
05.08.02 POZO PUESTA A TIERRA P-2 ( R<5 Ohms) und 3.00 1,125.15 3,375.45 3.00 3,375.45
05.09 ARTEFACTOS

05.09.01 ARTEF.FLUORESCENTE 3/36W (SIM.BE JOSFEL) C/SOPORTE und 198.00 175.85 34,818.30 134.00 23,563.90
05.09.02 ARTEF.FLUORESCENTE 2/18W (SIM.BE JOSFEL) C/SOPORTE und 108.00 105.96 11,443.68 108.00 11,443.68
05.09.03 ARTEFACTO FLUORESCENTE CIRCULAR DE 32W und 26.00 95.96 2,494.96 20.00 1,919.20
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
05.09.04 SUMINISTRO E INST. ARTEFACTO 2 LAMPARAS FLUORCENTE COMPACTA 18W und 12.00 99.96 1,199.52 7.00 699.72
05.09.05 SUMINISTRO E INST. LUMINARIA INCANDECENTE und 79.00 70.96 5,605.84 23.00 1,632.08
05.09.06 FAROLA JP 250 LAMPARA HG 125W und 50.00 466.35 23,317.50 64.00 29,846.40
05.09.07 EQUIPO DE ILUMINACION DE MERGENCIA BATERIA PZA 7.00 165.27 1,156.89 16.00 2,644.32
05.09.08 DETECTOR DE HUMO PZA 4.00 125.27 501.08 4.00 501.08
05.09.09 LUMINARIA CON BRAZO Y GLOBO und 49.00 466.65 22,865.85 0.00 0.00
05.10 OTROS

05.10.01 CONSTRUCCION DE SUBESTACIONES und 1.00 542.56 542.56 0.00 0.00


05.10.02 SUMINISTRO E INSTALACION DE POSTES DE ALUMBRADO und 50.00 1,039.78 51,989.00 31.00 32,233.18
05.10.03 CAMPANILLA DE TIMBRE DE 6" CON TRANF 220/12V und 3.00 88.46 265.38 0.00 0.00
05.10.04 CAMPANILLA DE TIMBRE DE 8" CON TRANF 220/12V und 3.00 98.46 295.38 0.00 0.00
COSTO DIRECTO 425,131.80 381,031.21
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

210.69% 0.00 0.00 0.00% 33.71 1,934.62 210.69% -17.71 -1,016.38 -110.69%
81.47% 0.00 0.00 0.00% 281.57 4,037.71 81.47% 64.03 918.19 18.53%
77.40% 0.00 0.00 0.00% 133.74 1,491.20 77.40% 39.06 435.52 22.60%
85.05% 0.00 0.00 0.00% 185.40 4,375.44 85.05% 32.60 769.36 14.95%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 32.32 100.00%

100.00% 0.00 0.00 0.00% 399.00 40,299.00 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 31.00 3,267.40 100.00% 0.00 0.00 0.00%
103.14% 0.00 0.00 0.00% 197.00 25,523.32 103.14% -6.00 -777.36 -3.14%
75.00% 0.00 0.00 0.00% 3.00 803.25 75.00% 1.00 267.75 25.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 449.52 100.00%
100.00% 0.00 0.00 0.00% 70.00 6,735.40 100.00% 0.00 0.00 0.00%
66.67% 0.00 0.00 0.00% 6.00 411.72 66.67% 3.00 205.86 33.33%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 134.52 100.00%

100.00% 0.00 0.00 0.00% 67.00 1,467.97 100.00% 0.00 0.00 0.00%
88.92% 0.00 0.00 0.00% 632.00 7,969.52 88.92% 78.79 993.54 11.08%
92.46% 0.00 0.00 0.00% 1,284.10 14,484.65 92.46% 104.75 1,181.58 7.54%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

122.58% 0.00 0.00 0.00% 38.00 580.64 122.58% -7.00 -106.96 -22.58%
100.00% 0.00 0.00 0.00% 4.00 87.40 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 97.38 100.00% 0.00 0.00 0.00%
75.00% 0.00 0.00 0.00% 6.00 223.14 75.00% 2.00 74.38 25.00%
100.00% 0.00 0.00 0.00% 2.00 91.38 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 18.00 275.04 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 5.00 12,613.90 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 6.00 3,676.68 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 596.39 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 446.98 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 686.39 100.00% 0.00 0.00 0.00%
50.00% 0.00 0.00 0.00% 1.00 416.39 50.00% 1.00 416.39 50.00%
100.00% 0.00 0.00 0.00% 1.00 416.98 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 646.39 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 2.00 742.78 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 416.39 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 1.00 536.39 100.00% 0.00 0.00 0.00%
50.00% 0.00 0.00 0.00% 1.00 446.39 50.00% 1.00 446.39 50.00%
100.00% 0.00 0.00 0.00% 1.00 732.78 100.00% 0.00 0.00 0.00%
50.00% 0.00 0.00 0.00% 1.00 462.78 50.00% 1.00 462.78 50.00%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

66.67% 0.00 0.00 0.00% 5.00 913.45 66.67% 2.50 456.73 33.33%
100.00% 0.00 0.00 0.00% 54.59 4,558.81 100.00% 0.00 0.00 0.00%
142.33% 0.00 0.00 0.00% 1,008.79 67,901.66 142.33% -300.00 -20,193.01 -42.33%
46.08% 0.00 0.00 0.00% 10.00 572.00 46.08% 11.70 669.24 53.92%
100.00% 0.00 0.00 0.00% 348.83 16,796.16 100.00% 0.00 0.00 0.00%
132.21% 0.00 0.00 0.00% 200.00 8,388.00 132.21% -48.72 -2,043.32 -32.21%
61.37% 0.00 0.00 0.00% 181.00 7,207.42 61.37% 113.92 4,536.29 38.63%
81.94% 0.00 0.00 0.00% 424.04 14,692.99 81.94% 93.49 3,239.43 18.06%
50.00% 0.00 0.00 0.00% 5.00 163.00 50.00% 5.00 163.00 50.00%
68.87% 0.00 0.00 0.00% 73.00 779.64 68.87% 33.00 352.44 31.13%
90.91% 0.00 0.00 0.00% 20.00 200.20 90.91% 2.00 20.02 9.09%

100.00% 0.00 0.00 0.00% 1.00 8,194.73 100.00% 0.00 0.00 0.00%

100.00% 0.00 0.00 0.00% 7.00 5,810.35 100.00% 0.00 0.00 0.00%
100.00% 0.00 0.00 0.00% 3.00 3,375.45 100.00% 0.00 0.00 0.00%

67.68% 0.00 0.00 0.00% 134.00 23,563.90 67.68% 64.00 11,254.40 32.32%
100.00% 0.00 0.00 0.00% 108.00 11,443.68 100.00% 0.00 0.00 0.00%
76.92% 0.00 0.00 0.00% 20.00 1,919.20 76.92% 6.00 575.76 23.08%
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
58.33% 0.00 0.00 0.00% 7.00 699.72 58.33% 5.00 499.80 41.67%
29.11% 0.00 0.00 0.00% 23.00 1,632.08 29.11% 56.00 3,973.76 70.89%
128.00% 0.00 0.00 0.00% 64.00 29,846.40 128.00% -14.00 -6,528.90 -28.00%
228.57% 0.00 0.00 0.00% 16.00 2,644.32 228.57% -9.00 -1,487.43 -128.57%
100.00% 0.00 0.00 0.00% 4.00 501.08 100.00% 0.00 0.00 0.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.00 22,865.85 100.00%

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 542.56 100.00%
62.00% 0.00 0.00 0.00% 31.00 32,233.18 62.00% 19.00 19,755.82 38.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 265.38 100.00%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 295.38 100.00%
89.63% 0.00 0.00% 381,031.21 89.63% 44,100.60 10.37%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
06.00.00 IMPLEMENTACION Y EQUIPAMIENTO
06.01.00 ADQUISICION DE EQUIPOS Y MOBILIARIOS GLB 1.00 1,000,000.00 1,000,000.00 0.39 386,355.69
06.02.00 ADQUISICION DE TEXTOS GLB 1.00 338,239.86 338,239.86 0.00 0.00
COSTO DIRECTO 1,338,239.86 386,355.69

0.37765769
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

38.64% 0.00 0.00 0.00% 0.39 386,355.69 38.64% 0.61 613,644.31 61.36%
0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 338,239.86 100.00%
28.87% 0.00 0.00% 386,355.69 28.87% 951,884.17 71.13%
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
SUB GERENCIA DE INFRAESTRUCTURA PBLICA
VALORIZACION DE AVANCE DE OBRA N 32 - DEL 01 AL

OBRA : "MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE JULIO DEL 2015

Und. Metrado P.U. Parcial ANTERIOR


Item Descripcin partida
S/. S/. Metrado Parcial
07.00.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE
07.01.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE GLB 1.00 48,700.00 48,700.00 0.00 0.00
COSTO DIRECTO 48,700.00 0.00
1
ONVENCIN
RA PBLICA
EL 01 AL 31 DE JULIO DEL 2015

OR ACTUAL ACUMULADO SALDO


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 48,700.00 100.00%
0.00% 0.00 0.00% 0.00 0.00% 48,700.00 100.00%
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
01.00.00 ESTRUCTURAS
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
01.01.01 CONSTRUCCIONES PROVISIONALES
01.01.01.01 CARTEL DE OBRA 2.40X3.60 PZA
01.01.01.02 ALMACEN OFICINA Y CASETA DE GUARDIANIA MES
01.01.01.01 CERCO PROVICIONAL DE CALAMINA H =2,00 m M

01.01.01.02 CONSTRUCCION DE ALMACEN PROVICIONAL M2

01.01.02 INSTALACIONES PROVISIONALES


01.01.02.01 AGUA PARA LA CONSTRUCCION GLB
01.01.03 TRABAJOS PRELIMINARES
01.01.03.01 LIMPIEZA DE TERRENO MANUAL M2
01.01.04 REMOCIONES
01.01.04.01 DESMONTAJE DE PUERTAS PZA
01.01.04.02 DESMONTAJE DE VENTANAS PZA
01.01.04.03 DESMONTAJE DE VENTANAS - PUERTAS UND
01.01.04.04 DESMONTAJE DE APARATOS SANITARIOS UND
01.01.04.05 DESMONTAJE TECHO ETERNIT/CALAMINA M2
01.01.05 DEMOLICIONES
01.01.05.01 DEMOLICION MUROS DE ADOBE m3
01.01.05.02 DEMOLICION MUROS DE LADRILLO KK CABEZA M2
01.01.05.03 DEMOLICION DE LOSA ALIGERADA H=0.20M M2
01.01.05.04 ROTURA DE LOSA EN VOLADIZO m3
01.01.05.05 DEMOLICION COLUMNAS Y VIGAS DE CONCRETO m3
01.01.05.06 DEMOLICION DE PISO DE CONCRETO INC.F.P. LOSA DEPORTIVA M2
01.01.05.07 DEMOLICION DE SOBRECIMIENTOS m3
01.01.05.08 DEMOLICION DE CIMIENTOS DE CONCRETO m3
01.01.05.09 DEMOLICION DE CIMIENTOS DE MURO DE ADOBE m3
01.01.05.10 DEMOLICION DE ESCALERAS m3
01.01.05.11 DEMOLICION DE GRADAS DE CONCRETO m3
01.01.05.12 DEMOLICION DE BEBEDERO Y URINARIO DE CONCRETO M
01.01.05.13 DEMOLICION DE CERCO PERIMETRICO MURO DE LADRILLO SOGA M
01.01.05.14 PICADO DE CERAMICO M2
01.01.05.15 RASQUETEO Y DESMANCHADO DE MURO PARA PINTADO M2
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.

01.01.05.16 ACARREO INTERNO, MAT.PROCEDENTE DE DEMOLICION. m3


01.01.05.17 ELIMINACION DE DEMOLICIONES m3
01.01.05.18 DEMOLICION DE MUROS DE LADRILLO KK SOGA M2
01.01.06 MOVILIZACIN DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS
01.01.06.01 MOVILIZACION , MAQUINARIAS Y HERRAMIENTAS GLB
01.01.07 TRAZO, NIVELES Y REPLANTEO
01.01.07.01 TRAZO Y REPLANTEO PRELIMINAR M2

01.01.07.02 REPLANTEO DURANTE EL PROCESO M2

01.02 SEGURIDAD Y SALUD


ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE
01.02.01 GLB
SEGURIDAD Y SALUD EN EL TRABAJO

01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL und

01.02.03 EQUIPO DE PROTECCION COLECTIVA GLB


01.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB
01.02.05 CAPACITACION EN SEGURIDAD Y SALUD GLB
01.02.06 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN GLB
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACIONES
02.01.01.01 EXCAVACION MASIVA C/MAQU1NA m3
02.01.01.02 EXCAV.ZANJAS Y ZAPATA Rt<2kg/cm2 h=1.5m m3
02.01.01.03 EXCAVACION DE ZANJA PARA CISTERNA RT<2kg/cm2 m3
02.01.01.04 EXCAVACION DE TERRENO NATURAL EN PATIOS Y VEREDAS m3
02.01.01.05 EXCAVACION DE ZANJA PARA BUZON DE INSPECCION m3
02.01.02 CORTES
02.01.02.01 CORTE A MAQUINA m3
02.01.03 RELLENOS
02.01.03.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3
02.01.04 NIVELACION INTERIOR Y APISONADO
02.01.04.01 CONFORMACION DE TERRENO HASTA NIVEL DE SUBRASANTE M2
02.01.04.02 AFIRMADO DE 3" EN INTERIORES,PATIOS Y VEREDAS M2
02.01.04.03 NIVELACION INTERIOR Y APISONADO PARA F.PISO, PATIO Y VEREDAS M2
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
02.01.05 ELIMINACIO DE MATERIAL EXCEDENTE
02.01.05.01 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES m3
02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3
02.02 OBRAS DE CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS
02.02.01.01 CIMIENTOS CORRIDOS 1:10 + 30 % P.G. fe >=100Kg/cm2 M3
02.02.01.02 SOLADO PARA ZAPATAS e=2", 1:12 CEM/HORM M2
02.02.01.03 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M2
02.02.02 SOBRECMIENTO
02.02.02.01 SOBRECIMIENTO, CONCRETO 1:8 + 25% P.M. Fe >=100Kg/cm2 m3
02.02.02.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2
02.02.03 BASE DE CONCRETO
02.02.03.01 BASE DE CONCRETO 1:8 + 25% P.M. m3
02.02.03.02 BASE DE CONCRETO, ENCOF. Y DESENCOF. M2
02.02.04 SARDINEL
02.02.04.01 SARDINEL, CONCRETO h=0.50M, fc= 175 Kg/cm2 Acabado 1:2 m3
02.02.04.02 SARDINEL, ENCOFRADO Y DESENCOFRADO M2
02.02.05 OTROS CONCRETOS CIMPLE
02.02.05.01 SUBZAPATA MEZCLA 1:10 + 30 % P.G. (fc=100 kg/cm2) m3
02.02.05.02 FALSO PISO MEZCLA 1:8 e=4" M2
02.03 OBRAS DE CONCRETO ARMADO
02.03.01 CIMIENTOS REFORZADOS
02.03.01.01 CIMIENTOS REFORZ. CONCRETO F'c = 210 kg/cm2 m3
02.03.01.02 CIMIENTOS REFORZ. ACERO Fy=4,200 kg/cm2 KG
02.03.02 ZAPATAS
02.03.02.01 ZAPATAS.- CONCRETO 210 kg/cm2 m3
02.03.02.02 ZAPATAS.- ACERO Fy=4200 kg/cm2 KG
02.03.03 VIGAS DE CIMENTACION
02.03.03.01 VIGAS DE CIMENT.- CONC. 210 kg/cm2 m3
02.03.03.02 VIGAS DE CIMENT.- ENCOF. Y DESENCOF M2
02.03.03.03 VIGAS DE CIMENT.- ACERO Fy=4,200 kg/cm2 KG
02.03.04 SOBRECIMIENTOS REFORZADOS
02.03.04.01 SOBREC. REF. CONCRETO 1:8+25% P.M. m3
02.03.04.02 SOBREC. REF. ENCOFRADO Y DESENCOFRADO M2
02.03.04.03 SOBREC. REF.- ACERO Fy=4,200 kg/cm2 KG
02.03.05 MUROS REFORADOS
02.03.05.01 MUROS DE CONTENC.- CONCRETO 210 kg/cm2 m3
02.03.05.02 MUROS DE CONTENC.- ENCOF. Y DESENCOFRADO [DOS CARAS) M2
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
02.03.05.03 MUROS DE CONT.- ACERO Fy=4,200 kg/cm2 KG
02.03.06 COLUMNAS Y PLACAS
02.03.06.01 COLUMNAS.- CONCRETO 210 kg/cm2 - 2 pisos m3
02.03.06.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.06.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG
02.03.07 VIGAS
02.03.07.01 VIGAS.- CONCRETO 210 kg/cm2 - 2 PISOS M3
02.03.07.02 VIGAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.07.03 VIGAS.- ACERO Fy=4200 kg/cm2 KG
02.03.08 LOSA MACIZA
02.03.08.01 LOSAS MACIZAS.- CONC.210kg/cm2-2 PISOS M3
02.03.08.02 LOSAS MACIZAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.08.03 LOSAS MACIZAS.- ACERO Fy=4,200 kg/cm2 KG
02.03.09 LOSA ALIGERADA
02.03.09.01 LOSA ALIGERADA - CONCRETO 210 kg/cm2 - 2 PISOS m3
02.03.09.02 LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADO M2
02.03.09.03 LOSA ALIGERADA.- ACERO Fy=4,200 kg/cm2 KG
02.03.09.04 LOSA ALIGERADA.- LADR. HUECO 15x30x30 und
02.03.09.05 LOSA ALIGERADA.- PLASTOFORMO DE 3.00x0.15x0.30m und
02.03.10 ESCALERAS
02.03.10.01 ESCALERAS.-CONCRETO 210kg/cm2 m3
02.03.10.02 ESCALERAS.- ENCOFRADO Y DESENCOFRADO M2
02.03.10.03 ESCALERAS.- ACERO Fy=4200 kg/cm2 KG
02.03.11 GRADAS 1
02.03.11.01 GRADAS EN PISO, CONCRETO F'c=175 kg/cm2. M2
02.03.11.02 GRADAS EN PISO, ENCOFRADO Y DESENCOFRADO M2
02.03.11.03 GRADAS EN PISO, ACERO Fy=4,200 kg/cm2 KG
02.03.12 CISTERNAS SUBTERRANEAS
02.03.12.01 CISTERNA, CONCRETO F'c=210 kg/cm2. m3
02.03.12.02 CISTERNA, ENCOFRADO Y DESENCOFRADO M2
02.03.12.03 CISTERNA, ACERO Fy=4200 kg/cm2 KG
02.03.13 TANQUE ELEVADO
02.03.13.01 TANQUES ELEVADOS.- CONCRETO 210 kR/cm2 m3
02.03.13.02 TANQUES ELEVADOS.- ENCOFRADO Y DESENCOFR M2
02.03.13.03 TANQUES ELEVADOS.- ACERO Fy=4,200 kg/cm2 KG
02.03.14 BUZON DE INSPECCION PARA DRENAJE
02.03.14.01 BUZON DE INSPECCION.- CONCRETO 210 kg/cm2 m3
02.03.14.02 BUZON DE INSPECCION.- ENCOFRADO Y DESENCOFRADO M2
02.03.14.03 BUZON DE INSPECCION.- ACERO Fy=4,200 kg/cm2 kg
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
02.03.15 DADOS DE CONCRETO
02.03.15.01 DADOS DE CONCRETO 1:8 + 25% P.M. m3

02.03.15.02 DADOS DE CONCRETO, ENCOF. Y DESENCOF. M2


02.03.16 CANALETAS
02.03.16.01 CANALETAS PARA AGUAS PLUVIALES fc=175 GRADERIAS M
02.03.17 GRADERIAS
02.03.17.01 RELLENO CON PIEDRA SELECCIONADA m3
02.03.17.02 CIMIENTOS CONCRETO CICLOPEO 1:10 + 40 % P.G. M3
02.03.17.03 CONCRETO CICLOPEO fc= 100Kg/cm2 + 50% P.G. M3
02.03.17.04 CONCRETO 175 kg/cm2 m3
02.03.17.05 ENCOFRADO Y DESENCOFRADO M2
02.03.17.06 CONCRETO 210 kg/cm2 GRADERIAS m3
02.03.17.07 GRADERIAS.- ACERO Fy=4,200 kg/cm2 kg
02.03.18 FALSA COLUMNA DE 0.25X0.20 (DADO DE CONCRETO)
02.03.18.01 COLUMNAS - CONCRETO 175 kg/cm2 Falsa Columna m3

02.03.18.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2

02.03.18.03 ACERO DE REFUERZO Fy=4200 kg/cm2 KG


02.04 ESTRUCTURAS METALICAS Y COBERTURAS
02.04.01 TENSORES - VIGUETAS
02.04.01.01 TENSORES DE AC LISO 3/4" INCL. UNIONES M
02.04.01.02 VIGUETA-VM | M
02.04.01.03 CORREAS METALICAS DE 2"X6"X2MM M
02.04.01.04 VIGUETAS METALICAS DE 2"X2"X2MM M
02.04.02 TIJERALES
02.04.02.01 TIJERAL METALICO CON ANGULOS T-l (13.00m.) und
02.04.02.02 TIJERAL METALICO CON ANGULOS T-2 (9.50 m.) und
02.04.02.03 TIJERAL METALICO CON ANGULOS T-3 (4.20m.) und
02.04.02.04 TIJERAL METALICO CON ANGULOS T-4 (5.00m.) und
02.04.02.05 TIJERAL METALICO CON ANGULOS T-5 (5.40m.) und
02.04.02.06 TIJERAL METALICO CON ANGULOS T-6 (2.80m.) und
02.04.02.07 TIJERAL METALICO CON ANGULOS T-7 (6.00 m.) und
02.04.02.08 TIJERAL METALICO CON ANGULOS T-8 (6.60m.) und
02.04.02.09 TIJERAL METALICO CON ANGULOS T-9 (8.75m.) und
02.04.02.10 TIJERAL METALICO T-10 (L=6.65m, h=1.20m) DE TUBO und
RECTANGULAR
MUNICIPALIDAD PROVINCIA
GERENCIA DE INFRAEST
DIRECCION DE

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
02.04.03 APOYOS
02.04.03.01 APOYO MOVIL und
02.04.03.02 APOYO FIJO VIGUETAS SOBRE TIMPANO und
02.04.04 COBERTURA
02.04.04.01 COBERTURA C/LAMINA TERMOACUST1CA TIPO TEJA C/ALMA M2
02.04.04.02 CUMBRERA TERMOACUSTICA C/ALMA ACERO ROJO/BLANCO M
02.04.04.03 COBERTURA DE ONDULINE CLASS1C M2
02.04.04.04 COBERTURA CLASS1C M
02.05,01 ESTRUCTURAS DE MADERA
02.05.01 VIGAS Y SUJETADORES
02.05.01.01 VIGAS Y SUJETADORES DE MADERA P2
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
0.00
0.00
0.00 07/03/2015
0.00
0.00 07/07/2015

0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00
0.00 04/05/2015
0.00 05/05/2015
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 05/05/2015
0.00 04/05/2015
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

1,128.58
1.00 1,128.58 1,128.58 07/07/2015
646.31
1.00 646.31 646.31 04/07/2015

0.06
0.06 0.06 12/07/2015
0.00
0.00 07/11/2015
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00
0.00 27/05/2015

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00
0.00 19/05/2015
0.00
0.00 19/05/2015
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
UBICACIN DE PARTIDA
EJECUTADA

AUDITORIUM

ALMACEN -AUDITORIUM

AUDITORIUM
AUDITORIUM
UBICACIN DE PARTIDA
EJECUTADA

AUDITORIUM
AUDITORIUM

REPLANTEO

TAMQUE ELEVADO

PERSONAL DE OBRA
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA

TAMQ. ELEVADO NUEVO

SSHH N02

SSHH N02
UBICACIN DE PARTIDA
EJECUTADA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
03.00.00 ARQUITECTURA
03.01 MUROS Y TABIQUES DE ALBAILERIA
03.01.01 MURO DE LADRILLO KK TIPO IV CABEZA M: 1:1:4 E=1.5 cm (*) M2
03.01.02 MURO DE LADRILLO KK TIPO IV SOGA M: 1:1:4 E=1.5 cm (*) M2

03.01.03 MURO DE LADRILLO KK TIPO IV CANTO M: 1:1:4 E=1.5 cm (*) M2


03.01.04 TABIQUERIA DRYWALL INTERIOR E= O.lOm M2
03.01.05 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS KG
03.02 REVOQUES Y REVESTIIENTOS
03.02.01 TARRAJEO EN MUROS INTERIORES C:A 1:5 E=1.5 CM. M2
03.02.02 TARRAJEO EN MUROS EXTERIORES C:A 1: 5, E= 1.50 CM M2
03.02.03 TARRAJEO DE COLUMNAS C:A 1:5 E=1.5 CM. M2
03.02.04 TARRAJEO DE VIGAS C:A 1: 5, E=1.50 CM M2
03.02.05 TARRAJEO SEMIPULIDO DE BORDES BOLEADOS MEZCLA C:A 1:4 E= 1. M
03.02.06 TARRAJEO CEMENTO PULIDO CON OCRE ROJO M2
03.02.07 TARRAJEO CEMENTO PULIDO M2
03.02.08 TARRAJEO CON IMPERMEABILIZANTE (TANQUE LEVADO Y CISTERNA) M2
03.02.09 TARRAJEO CON IMPERMEABILIZANTE EN CONFORMACION DE M2
03.02.10 VESTIDURA DE DERRAMES (1:5) M
03.02.11 REVEST.CEMENTO PULIDO EN GRADAS M
03.02.12 BRUNAS SEGUN DETALLE (lxl cm) M
03.02.13 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2
03.02.14 REVESTIDO DE GRADAS C:A, 1:3 e=1.5cm C/PERFIL DE ALUMINIO DE 1 M
03.03 CIELO RASOS
03.03.01 CIELO RASO CON MEZCLA C:A 1:5 M2
03.03.02 FALSO CIELO RASOS
03.03.02.01 FALSO C/RASO C/PLANCHA FIBROCEMENTO 1.22x2.44x6mm M2
03.03.02.02 CIELO BALDOSA ACUSTICA ACABADO PVC C/LANA DE VIDRIO M2
03.03.03 CIELO RASO CON YESO M2
03.04 PISOS Y PAVIMENTOS
03.04.01 CONTRAPISOS
03.04.01.01 CONTRAPISO DE 40 mm M2
03.04.01.02 CONTRAPISO DE 48 mm PARA RECIBIR VIN1LICO M2
03.04.01.03 CONTRAPISO PULIDO DE 2 M2
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
03.04.01.04 CONTRAPISO CON IMPERMEABILIZANTE E=2 TECHO M2
03.04.02 PISOS
03.04.02.01 PISO CERAMICO 30 x 30 SERIE COLOR - NACIONAL M2
03.04.02.02 PISO LOSETA VENECIANA 30x30 COLOR CLARO M2
03.04.02.03 PISO LOSETA VINILICA DE ALTO TRANSITO e=3.2mm M2
03.04.02.04 MACHIHEMBRADO MAD.l"x4" DURMIENTE 2"x3"x4" 1er Piso M2
03.04.02.05 PISO DE ALFOMBRA DE FIBRA VEGETAL M2
03.04.02.06 PISO DE COLORES INICIAL e= 0.20 M2
03.04.03 PISOS DE CONCRETO
03.04.03.01 PISO DE CEMENTO PULIDO Y BRUADO E=3" S/COLOREAR M2
03.04.03.02 VEREDA CONCRETO 175 kg/cm2 E=4" FROT.Y BRUADO M2
03.04.03.03 RAMPAS DE CONCRETO 175 kg/cm2 E=5" BRUADO S/D1SEO M2
03.04.03.04 CONCRETO F'C=175 KG/CM2 E= 5" ACAB. SEMIPULUDO (LOSA DEPOR M2
03.04.03.05 ACERO DE REFUERZO Fy=4200 kg/cm2 LOSA DE CONCRETO kg
03.04.03.06 MALLAS DE ACERO 1/4" PARA PISOS DE CONCRETO kg
03.04.04 ACABADO DE CONCRETO EN PISOS
03.04.04.01 ACABADO DE CEMENTO PULIDO E=2cm MEZCLA 1:2 M2
03.05 ZOCALOS Y CONTRAZOCALOS
03.05.01 ZOCALOS
03.05.01.01 ZOCALO DE CERAMICO 30x30 H=1.80m M2
03.05.01.02 ZOCALO DE CERAMICO 30x20 M2
03.05.02 CONTRAZOCALOS
03.05.02.01 CONTRAZOCALO DE LOSETA VENECIANA 10x30 CLARO M
03.05.02.02 CONTR.S/COLOREAR H=20 cm MZ 1:2 e=1.5 cm M
03.05.02.03 CONTRAZOCALO DE CERAMICO DE 10X30CM CLARO M
03.06 COBERTURA (Cubierta)
03.06.01 CUB.DE LADR.PASTELERO ASENTADO CON BARRO e=2"C/FRAGUA M2
03.06.02 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2
03.07 CARPINTERIA DE MADERA
03.07.01 PUERTAS
03.07.01.01 PUERTA CEDRO MACHIMBRADA C/V1SOR-AULA 2004 M2
03.07.01.02 PUERTA CEDRO ENCAJONADO E= 1 1/2 M2
03.07.02 VENTANAS
03.07.02.01 VENTANA CEDRO C/SEG.Y 1/2", SIERRA 01 Y 02 PISOS M2
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
03.07.03 MUEBLES
03.07.03.01 TICERO DE MADERA CEDRO (L=5 m) BARNIZADO und
03.08 CARPINTERIA METALICA Y HERRERIA
03.08.01 VENTANAS DE FIERRO
03.08.01.01 VENTANA.C/S PERF. 1 1/2"X1 1/2"X3/168" ,FIJA M2
03.08.01.02 DIVICIONES METALICAS E=1/16" M2
03.08.02 PUERTAS DE FIERRO
03.08.02.01 PUERTA METALICA LAC E=1/16" M2
03.08.02.02 PUERTA INGRESO PRINCIPAL C/PERFILES 3/16" M2
03.08.02.03 PUERTA METALICA C/PERFILES 3/16" M2
03.08.03 BARANDAS
03.08.03.01 BARANDAS PARA PUENTES , MUROS, RAMPAS Y PASARELAS M
03.08.04 PASAMANOS
03.08.04.01 PASAMANO DE TUBO FG DE 2" EN ESCALERA M
03.08.05 ESCALERAS
03.08.05.01 CANTONERA DE FIERRO EN ESCALERA M
03.08.05.02 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO M
03.08.05.03 ESCALERA METALICA DE CARACOL und
03.08.06 CERCOS
03.08.06.01 CERCO DE FIERRO TIPO REJA (H= 3.00 ) M
03.08.07 ELEMENTOS METALICOS ESPECIALES
03.08.07.01 MARCO Y TAPA DE FIERRO 0.60X0.60M und
03.08.07.02 MARCO Y TAPA DE FIERRO .80X.80M P/TQUE CISTERNA APOYADO 6M3 und

03.09 CERRAJERA
03.09.01 BISAGRAS
03.09.01.01 BISAGRAS CAPUCHINAS ACERO ALUMINIZADO 3 1/2" EN PUERTAS Y PZA
03.09.01.02 BISAGRA DE ACERO ALUMINIZADO DE 2.5" PESADA EN PUERTA/VENTA PZA
03.09.01.03 BISAGRA DE ACERO ALUMINIZADO DE 2.5" EN ESTANTERIA PZA
03.09.01.04 BISAGRA CAPUCHINAS ACERO ALUMINIZADO 4" EN PUERTAS PZA
03.09.02 CERRADURA
03.09.02.01 CERRADURA DOS GOLPES EN PUERTA PZA
03.09.02.02 CERRADURA LGO PARA PUERTA EXTERIOR PZA
03.09.03 ACCESORIOS CIERRE
03.09.03.01 CERROJO DE 2" ALUMINIZADO PARA PUERTA PZA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
03.09.03.02 CERROJO "SAPITO" SEGURIDAD BAT.VENTANA PZA
03.09.03.03 CANDADO TIPO FORTE 60 MM. PZA
03.09.04 VIDRIO CRISTALES Y SIMILARES
03.09.04.01 VIDRIOS SEMIDOBLES IMPORTADO P2
03.09.04.02 VIDRIO TEMPLADO DE 6MM P2
03.09.04.03 VIDRIO TRIPLE DE BRONCE DE 6 MM SISTEMA NOVA INC COLOCACION P2
03.10 PINTURA
03.10.01 PINTURA DE CIELOS RASOS, VIGAS, COLUMNAS Y PAREDES
03.10.01.01 PINTURA OLEO MATE BLANCO HUMO MUROS EXT. M2
03.10.01.02 PINTURA OLEO MATE ALABASTRO COL.VIG, DERRAM. M2
03.10.01.03 PINTURA OLEO MATE MARFIL MUROS M2
03.10.01.04 PINTURA LATEX 2 MANOS BLANCO CIELO RASO M2
03.10.01.05 PINTURA DE PIZARRA EN MUROS M2
03.10.02 PINTURA DE PUERTAS Y VENTANAS
03.10.02.01 PINT.ANTICOR.Y ESMALTE 2 MANOS-PTA/VENT. M2
03.10.02.02 PINTURA BARNIZ EN CARP.DE MADERA M2
03.10.03 PINTURA DE CONTRAZOCALOS Y BARANDAS
03.10.03.01 PINTURA ANTICORROSIVA Y ESM. EN BARANDAS M
03.10.03.02 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=0.2 M
03.10.03.03 PINTURA DEMARCACION DE LOSA DEPORTIVA und
03.11 VARIOS, LIMPIEZA Y JARDINERA
03.11.01 CANALETA DE FIERRO GALVANIZADO REGILLA M
03.11.02 TAPAJUNTA METALICA EN PISOS M
03.11.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) M
03.11.04 PIZARRA CEMENTO 5.0x1.20 SIN TISERO PZA
03.11.05 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" M
03.11.06 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1/2" M
03.11.07 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR M
03.11.08 JUNTA DE DILATACION CON ESPUMA PLASTICA+JEBE MICROPOROSO M
03.11.09 LIMPIEZA FINAL DE LA OBRA GLB
03.12 OTROS
03.12.01 ASTA DE BANDERA TIPICO PZA
03.12.02 LOSA C.A.e=10cm.ANCHO 55cm.ACAB.C.PUL. PARA ASIENTOS EN DU M
03.12.03 LOSA C.A. PARA MESA DE LABORATORIO M
03.12.04 MESA C.A. REVESTIDO CON MAYOLICA PARA MESA DE LABORATORIO M2
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
03.12.05 ARCO Y TABLERO FULBITO-BASKET(MET-MAD) und
03.12.06 TUBOS C.VOLEY,INC.RED Y DADOS CONCRETO JGO
03.12.07 TOBOGAN H=1.85M (JUEGO INFANTIL) und
03.12.08 MESA DE NIOS und
03.12.09 JUEGO NIOS TIPO A und
03.12.10 JUEGO NIOS TIPO B und
03.12.11 JUEGO NIOS TIPO C und
03.12.12 JUEGO NIOS TIPO D und
03.12.13 COLUMPIO METALICOS L=3.10m (JUEGO INFANTIL) CON 03 ASIENTO und
03.12.14 BUTACAS und
03.12.15 CONFORMACION DE TALUD PARA JARDINERIA M2
03.12.16 SEMBRADO DE GRASS NATURAL INC. TIERRA DE CHACRA E= 0.10m M2
03.12.17 PISO BLANDO (JUEGOS INFANTILES) E= 6" M2
03.12.18 ANGULAR METALICO DE 1 1/2" X1 1/2" EN PISO PARA VEREDAS M
03.12.19 GARGOLAS und
03.12.20 PUERTAS EN SSHH DE MELAMINA CON PERFIL DE ALUMINIO und
03.12.21 PROTECTOR METALICO P/VENTANAS EN AULAS SEGUN DISENO M2
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
22.49
4.00 3.00 12.00 02/07/2015
1.00 10.49 10.49 02/07/2015
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00
0.00 22/04/2015

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00
0.00 0.00
0.00 0.00
0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
UBICACIN DE PARTIDA
EJECUTADA

PABELLON N04 BIBLIOTECA


PABELLON N04 BIBLIOTECA
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA

TAMQUE CISTERNA
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
04.00.00 INSTALACIONES SANITARIAS
04.03 SISTEMA DE DREANJE PLUVIAL
04.03.01 TUBERIA DE BAJADA PVC-SAP 4" P/LLUVIAS M
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00
0.00 06/06/2015
UBICACIN DE PARTIDA
EJECUTADA

SSHH N04
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
05.00.00 INSTALACIONES ELECTRICAS
05.01 OBRAS PRELIMINARES
05.01.01 PICADO Y RESANE DE PISO Y VEREDA DE CONCRETO M2
05.01.02 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3
05.01.03 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT.ELEC.SANIT). m3
05.01.04 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3
05.01.05 CONEXION A RED EXISTENTE und
05.02 SALIDA PARA ALUMBRADO, TOMACORRIENTES, FUERZAS
SEALES DEBILES
05.02.01 SALIDA DE TECHO (CENTRO DE LUZ) PTO
05.02.02 SALIDA PARA BRAQUETE (PARED) PTO
05.02.03 SALIDA PARA TOMACORRIENTE DOBLE PTO
05.02.04 SALIDA TRIFASICA PARA ELECTROBOMBA PTO
05.02.05 SALIDA DE TELEFONO y/o INTERCOMUNICADORES PTO
05.02.06 SALIDA PARA RED DATA (COMPUTO) PTO
05.02.07 SALIDA PARA TIMBRE PTO
05.02.08 SALIDA PARA VENTILADORES PTO
05.03 CANALIZACION Y/O TUBERIAS
05.03.01 TUBERIA PVC-P 65mm M
05.03.02 TUBERIA PVC-P35mm M
05.03.03 TUBERIA PVC-P 25mm M
05.04 CAJAS
05.04.01 CAJA DE PASE FG 4x4xl.5" und
05.04.02 CAJA DE PASE FG 6x6x3" und
05.04.03 CAJA DE PASE FG 12X12X6" und
05.04.04 CAJA PASE FG 6" x 6" x 2 1/2" und
05.04.05 CAJA PASE FG 6" x 6" x 6" und
05.04.06 CAJA DE PASE FG 4X4X2" und
05.05 TABLEROS Y CUCHILLAS (LLAVES)
05.05.01 T.G.AUT. 8-3X40,2-3X60. 2-2X40,4- 2X30 ,2-3X30 1-RESERVA und
05.05.02 TA. AUT. 4- 2 X 15A, 2- 2 X 20A und
05.05.03 TAB.AUT. 3-2X20, 4-2X15A und
05.05.04 TAB.AUT. 1-2X20, 2-2X15A und
05.05.05 TAB.AUT. 3-2X20, 6-2X15A und
05.05.06 TAB.AUT. 1-2X30,1-2X20,1-2X15A und
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
05.05.07 TAB.AUT. 1-2X20,2-2X15A und
05.05.08 TAB.AUT. 1-3X30, 3-2X20, 2-2X15A und
05.05.09 TAB.AUT. 2-2xl5A und
05.05.10 TAB. AUT. 3 - 2 x 15 A und
05.05.11 TAB AUT. 5- 2 x 20A TD1- UPS und
05.05.12 TAB. AUT. 3 - 2 x 20A TD2 - UPS und
05.05.13 TAB. AUT. CONTROL LUCES 8.2 X 15A und

05.05.14 TAB AUT. CONTROL ELECTROBOMBAS 2 X 20A und

05.06 CONEXIONES A RED EXTERNA Y MEDIDORES


05.06.01 AL1MENTADOR CAB. N2XH (3- 1X95 +1X50 +lX35)mm2 M
05.06.02 ALIMENTADOR CAB. N2XH (3-1x25 +1x25+ Ixl0)mm2 M
05.06.03 ALIMENTADOR CAB. N2XH (3-1x16 +1x16+ Ixl0)mm2 M
05.06.04 ALIMENTADOR CAB. N2XH (3-1x10 +1x10+ Ixl0)mm2 M
05.06.05 ALIMENTADOR CAB. N2XH (3-1x4 +1x4+ Ixl0)mm2 M
05.06.06 ALIMENTADOR CAB. N2XH (2-1x6 + Ixl0)mm2 M
05.06.07 ALIMENTADOR CAB. N2XH (2-1x4 + Ixl0)mm2 M
05.06.08 ALIMENTADOR CAB. N2XH 2- 1x6 mm2 M
05.06.09 ALIMENTADOR CAB. N2XH 2- 1x4 mm2 M
05.06.10 ALIMENTADOR SOL NH-70 2-lxl.5mm2/20mm PVC M
05.06.11 CABLE COBRE DESNUDO Ixl0mm2, Y 20mm PVC-P M
05.07 INSTALACION PARARRAYOS
05.07.01 PARARRAYO C/D1SPOSIT.DE CEBADO C/03P/T1ERRA.EN POSTE (2004) und
05.08 INSTALACION DEL SISTEMA PUESTA A TIERRA
05.08.01 POZO PUESTA A TIERRA P-l und
05.08.02 POZO PUESTA A TIERRA P-2 ( R<5 Ohms) und
05.09 ARTEFACTOS
05.09.01 ARTEF.FLUORESCENTE 3/36W (SIM.BE JOSFEL) C/SOPORTE und
05.09.02 ARTEF.FLUORESCENTE 2/18W (SIM.BE JOSFEL) C/SOPORTE und
05.09.03 ARTEFACTO FLUORESCENTE CIRCULAR DE 32W und
05.09.04 SUMINISTRO E INST. ARTEFACTO 2 LAMPARAS FLUORCENTE COMPACTA 18W und
05.09.05 SUMINISTRO E INST. LUMINARIA INCANDECENTE und
05.09.06 FAROLA JP 250 LAMPARA HG 125W und
05.09.07 EQUIPO DE ILUMINACION DE MERGENCIA BATERIA PZA
05.09.08 DETECTOR DE HUMO PZA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
05.09.09 LUMINARIA CON BRAZO Y GLOBO und
05.10 OTROS
05.10.01 CONSTRUCCION DE SUBESTACIONES und
05.10.02 SUMINISTRO E INSTALACION DE POSTES DE ALUMBRADO und
05.10.03 CAMPANILLA DE TIMBRE DE 6" CON TRANF 220/12V und
05.10.04 CAMPANILLA DE TIMBRE DE 8" CON TRANF 220/12V und
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA
UBICACIN DE PARTIDA
EJECUTADA
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS

"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ M


OBRA :
PROVINCIA DE LA CONVENCIN CUSCO"
CODIGO SNIP:86920
FECHA DE INICIO: 01 de OCTUBRE del 2012
VALORIZACION DEL 01 AL 31 DE MAYO DEL 2015
CUADRO METRADOS DE PARTIDAS EJECUTADOS DEL MES MAYO 2015

Item Descripcin partida N VECES


Und.
06.00.00 IMPLEMENTACION Y EQUIPAMIENTO
06.01.00 ADQUISICION DE EQUIPOS Y MOBILIARIOS GLB

06.02.00 ADQUISICION DE TEXTOS GLB


07.00.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE
07.01.00 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANTA DOCENTE GLB
ENCIN
BLICA

1027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA,


NCIN CUSCO"

OS DEL MES MAYO 2015

Metrado
SUB TOTAL TOTAL FECHA
LARGO ANCHO ALTURA
0.00 0.00
0.00
0.00 29/06/2015
0.00 0.00
0.00 0.00
0.00 0.00
UBICACIN DE PARTIDA
EJECUTADA

LABORATORIO DE COMPUTO
MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

IMPLEMENTACION DEL CENTRO DE COMPUTO DEL NIVEL PRIMARIO

SE OBSERVA OTRA VISTA DEL CENTRO DE COMPUTO DEL NIVEL PRIMARIO


MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SE OBSERVA IIMPLEMENTACION DEL CENTRO DE COMPUTO DEL NIVEL SECUNDARIO


MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SE OBSERVA OTRA VISTA DE LA IMPLEMENTACION DEL CENTRO DE COMPUTO


DEL NIVEL SECUNDARIO
MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SE OBSERVA EL TAMQUE ELEVADO EXISTENTE TERMINADO Y EN FUNCIONAMIENTO


MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SE OBSERVA OTRA VISTA DEL TAMQUE ELEVADO EXISTENTE EN FUNCIONAMIENTO

SE OBSERVA LAS ELECTROBOMBAS EN FUNCIONAMIENTO DEL TAMQUE


ELEVADO EXISTENTE
MUNICIPALIDAD PROVINCIAL DE LA CONVENCION
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PANEL FOTOGRAFICO
"MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS
DE LA I.E. N 51027 JUAN DE LA CRUZ MONTES SALAS
SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

SE OBSERVA EL TABLERO DE DEL SISTEMA ELECTRICO DE CONTROL


DE LA ELECTROBOMBA DEL TAMQUE ELEVADO EXISTENTE
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

PLANILLA DE METRADOS POR CADA


PARTIDA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

VALORIZACION MENSUAL DE OBRA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CRONOGRAMA COMPARADO PROYECTADO


Vs. EJECUTADO

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

PLANILLA DE PERSONAL COMPROMETIDA A


LA OBRA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

MANIFIESTO DE GASTOS

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CUADRO DE MANIFIESTO POR ESPECIFICA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CUADRO DE MOVIMIENTO DIARIO DE


ALMACEN

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CUADRO RESUMEN (INGRESOS-EGRESOS)

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

SALDO VALORIZADO DE MATERIALES

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

REPROGRAMACION DE EJECUCION FISICA Y


FINANCIERA EN DIAGRAMA DE GANTT.

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CONTROL DE EQUIPO MECANICO

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

CONTROLES DE CALIDAD

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

PANEL FOTOGRAFICO

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

COPIAS DE CUADERNO DE OBRA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

COPIAS DE PARTE DIARIO DE MAQUINARIA

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

NOTAS DE ENTRADA DE ALMACEN

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIVISION DE OBRAS

INFORME MENSUAL DEL MES DE JULIO

COPIAS DE NOTA DE SALIDA DE ALMACEN

"MEJORAMIENTO DE LA OFERTA DE SERVICIOS


EDUCATIVOS DE LA I.E. N 51027 JUAN DE LA CRUZ
MONTES SALAS SANTA ANA, PROVINCIA DE LA
CONVENCIN CUSCO"
REPROGRAMACION DE EJECUCION FISICA Y FINANCIERA EN DIAGRAMA DE BARRAS DE GANTT.
OBRA MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS - SANTA ANA, PROVINCIA LA CONVENCION

EJECUTOR MUNICIPALIMUNICIPALIDAD PROVINCIAL DE LA CONVENCION


UBICACIN CUSCO - LADISTRITO DE SANTA ANA -PROVINCIA DE LA CONVENCION-REGION CUSCO
2015
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
SEM001 SEM002 SEM003 SEM004 SEM005 SEM006 SEM007 SEM008 SEM009 SEM010 SEM011 SEM012 SEM013 SEM014 SEM015 SEM016 SEM017 SEM018 SEM019 SEM020 SEM021 SEM022 SEM023 SEM024 SEM025 SEM026 SEM027 SEM028 SEM029 SEM030 SEM031 SEM032 SEM033 SEM034 SEM035 SEM036 SEM037 SEM038 SEM039 SEM040 SEM041 SEM042
N UND METRADO Precio (S/.) Precio (S/.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

01 ESTRUCTURAS 5,705.01
01.01 Obras provisionales y Trabajos Preliminares 5,705.01
01.01.03 Trabajos Preliminares 4,054.50
2,027.25 2,027.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.03.01 LIMPIEZA DE TERRENO MANUAL M2 7,950.00 0.51 4,054.50
X X
0.00 0.00 0.00 51.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.04.02 DESMONTAJE DE VENTANAS PZA 9.00 5.69 51.21
X

01.01.05 Demoliciones 1,599.30


0.00 0.00 0.00 32.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.05.11 DEMOLICION DE GRADAS DE CONCRETO m3 1.53 21.44 32.80
X
0.00 0.00 0.00 756.52 756.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.05.15 RASQUETEO Y DESMANCHADO DE MURO PARA PINTADO M2 1,088.52 1.39 1,513.04
X X
19.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.05.16 ACARREO INTERNO, MAT.PROCEDENTE DE DEMOLICION. m3 1.53 12.55 19.20
X
0.00 34.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.05.17 ELIMINACION DE DEMOLICIONES m3 1.53 22.39 34.26
X

02 ESTRUCTURAS 4,548.99
02.01 Movimiento de Tierras 708.89
02.01.01 Excavaciones 111.97
EXCAVACION DE TERRENO NATURAL EN PATIOS Y 0.00 0.00 0.00 0.00 111.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.01.04 m3 3.94 28.42 111.97
VEREDAS X

02.01.05 Eliminacion de Material Excedente 596.92


ACARREO INTERNO, MATERIAL PROCEDENTE DE 0.00 0.00 0.00 0.00 65.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.05.01 m3 3.94 16.73 65.92
EXCAVACIONES X
0.00 0.00 0.00 0.00 265.50 265.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.05.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 22.50 23.60 531.00
X X

02.03 Obras de Concreto Armado 3,840.10


02.03.07 Vigas 1,171.78
0.00 0.00 0.00 0.00 233.74 233.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.07.01 VIGAS.- CONCRETO 210 kg/cm2 - 2 PISOS M3 0.91 513.70 467.47
X X
0.00 0.00 0.00 0.00 229.23 229.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.07.02 VIGAS.- ENCOFRADO Y DESENCOFRADO M2 11.09 41.34 458.46
X X
0.00 0.00 0.00 0.00 0.00 245.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.07.03 VIGAS.- ACERO Fy=4200 kg/cm2 KG 50.90 4.83 245.85
X

02.03.11 Gradas 877.35


0.00 0.00 0.00 0.00 438.68 438.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.11.01 GRADAS EN PISO, CONCRETO F'c=175 kg/cm2. M2 6.61 132.73 877.35
X X

02.03.15 Dados de Concreto 36.02


0.00 0.00 0.00 0.00 0.00 24.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.15.01 DADOS DE CONCRETO 1:8 + 25% P.M. m3 0.11 224.69 24.72
X
0.00 0.00 0.00 0.00 11.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.15.02 DADOS DE CONCRETO, ENCOF. Y DESENCOF. M2 0.39 28.97 11.30
X

02.03.16 Canaletas 1,231.16


0.00 0.00 0.00 0.00 0.00 0.00 615.58 615.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.16.01 CANALETAS PARA AGUAS PLUVIALES f'c=175 M 22.85 53.88 1,231.16
X X

02.03.18 Falsa Columna 0.25 x 0.20 (Dado de Concreto) 523.79


0.00 0.00 0.00 0.00 0.00 0.00 244.35 244.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.18.01 COLUMNAS - CONCRETO 175 kg/cm Falsa Columna m3 1.06 461.03 488.69
X X
0.00 0.00 0.00 0.00 0.00 0.00 35.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.18.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO M2 1.00 35.10 35.10
X

03 ARQUITECTURA 413,496.69
3.01 Muros y Tabiques de Albailera 2,591.78
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 647.95 647.95 647.95 647.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.01 TABIQUERIA DRYWALL INTERIOR E= 0.10m M2 20.35 127.36 2,591.78
X X X X

03.02 Revoques y Revestimientos 7,151.75


0.00 264.93 264.93 264.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01 TARRAJEO EN MUROS INTERIORES C:A 1:5 E=1.5 CM. M2 56.65 14.03 794.80
X X X

TARRAJEO EN MUROS EXTERIORES C:A 1: 5 , E= 1.50 0.00 0.00 661.27 661.27 661.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 M2 122.08 16.25 1,983.80
CM X X X
0.00 0.00 0.00 1,183.42 1,183.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.03 TARRAJEO DE COLUMNAS C:A 1:5 E=1.5 CM. M2 108.97 21.72 2,366.83
X X
0.00 0.00 0.00 0.00 394.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.04 TARRAJEO DE VIGAS C:A 1: 5 , E=1.50 CM M2 15.50 25.43 394.17
X
0.00 0.00 0.00 0.00 1,612.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.10 VESTIDURA DE DERRAMES (1:5) M 222.98 7.23 1,612.15
X

3.03 Cielo Rasos 6,495.74


03.03.02 Falso Cielo Rasos 6,495.74
FALSO C/RASO C/PLANCHA FIBROCEMENTO 0.00 0.00 0.00 0.00 2,165.25 2,165.25 2,165.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03.02.01 M2 225.39 28.82 6,495.74
1.22x2.44x6mm X X X

03.04 Pisos y Pavimentos 80,457.97


03.04.02 Pisos 74,657.83
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,558.71 14,558.71 14,558.71 14,558.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.02.01 PISO CERAMICO 30 x 30 SERIE COLOR - NACIONAL M2 811.07 71.80 58,234.83
X X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,105.75 4,105.75 4,105.75 4,105.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.02.03 PISO LOSETA VINILICA DE ALTO TRANSITO e=3.2mm M2 214.12 76.70 16,423.00
X X X X

03.04.03 Pisos de Concreto 5,800.14


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,450.10 1,450.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.03.02 VEREDA CONCRETO 175 kg/cm2 E=4" FROT.Y BRUADO M2 54.26 53.45 2,900.20
X X

RAMPAS DE CONCRETO 175 kg/cm2 E=5" BRUADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,899.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.03.03 M2 43.51 66.65 2,899.94
S/DISEO X

03.08 Carpintera Metlica y Herrera 6,972.90


03.08.03 Barandas 4,175.47
BARANDAS PARA PUENTES , MUROS, RAMPAS Y 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,391.82 1,391.82 1,391.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.08.03.01 M 68.80 60.69 4,175.47
PASARELAS X X X

03.08.05 Escaleras 1,932.29


0.00 0.00 0.00 0.00 0.00 0.00 0.00 966.15 966.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.08.05.02 ESCALERA GATO, TUBO F.G. 1 1/2" Y 1" TQE. ELEVADO M 13.60 142.08 1,932.29
X x

03.08.07 Elementos Metalicos Especiales 865.14


MARCO Y TAPA DE FIERRO .80x.80m P/TQUE CISTERNA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 865.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.08.07.02 und 3.00 288.38 865.14
APOYADO 6M3 X

03.09 Cerrajera 36,308.30


03.09.04 Vidrio Cristales y Similares 36,308.30
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,344.62 1,344.62 1,344.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.09.04.01 VIDRIO TEMPLADO DE 6mm P2 207.61 19.43 4,033.86
REPROGRAMACION DE EJECUCION FISICA Y FINANCIERA EN DIAGRAMA DE BARRAS DE GANTT.
OBRA MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS - SANTA ANA, PROVINCIA LA CONVENCION

EJECUTOR MUNICIPALIMUNICIPALIDAD PROVINCIAL DE LA CONVENCION


UBICACIN CUSCO - LADISTRITO DE SANTA ANA -PROVINCIA DE LA CONVENCION-REGION CUSCO
2015
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
SEM001 SEM002 SEM003 SEM004 SEM005 SEM006 SEM007 SEM008 SEM009 SEM010 SEM011 SEM012 SEM013 SEM014 SEM015 SEM016 SEM017 SEM018 SEM019 SEM020 SEM021 SEM022 SEM023 SEM024 SEM025 SEM026 SEM027 SEM028 SEM029 SEM030 SEM031 SEM032 SEM033 SEM034 SEM035 SEM036 SEM037 SEM038 SEM039 SEM040 SEM041 SEM042
N UND METRADO Precio (S/.) Precio (S/.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
03.09.04.01 VIDRIO TEMPLADO DE 6mm P2 207.61 19.43 4,033.86
X X X

VIDRIOS TRIPLE DE BRONCE DE 6mm SISTEMA NOVA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,068.61 8,068.61 8,068.61 8,068.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.09.04.02 P2 1,467.02 22.00 32,274.44
INC. COLOCACION X X X X

03.09 Pintura 104,531.25


03.09.04 Pintura de Cielos Razos Vigas , Columnas y Paredes 103,353.00
0.00 0.00 0.00 0.00 0.00 0.00 12,339.51 12,339.51 12,339.51 12,339.51 12,339.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.01.01 PINTURA OLEO MATE BLANCO HUMO MUROS EXT. M2 7,598.22 8.12 61,697.55
X X X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,461.60 3,461.60 3,461.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.01.02 PINTURA OLEO MATE ALABASTRO COL.VIG, DERRAM. M2 1,048.97 9.90 10,384.80
X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,797.96 3,797.96 3,797.96 3,797.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.01.03 PINTURA OLEO MATE MARFIL MUROS M2 1,534.53 9.90 15,191.85
X X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,359.60 5,359.60 5,359.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.01.04 PINTURA LATEX 2 MANOS BLANCO CIELO RASO M2 1,615.96 9.95 16,078.80
X X X

03.10.03 Pintura de Contrazocalos y Barandas 1,178.25


0.00 0.00 0.00 0.00 0.00 0.00 463.32 463.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.03.01 PINTURA ANTICORROSIVA Y ESM. EN BARANDAS M 241.31 3.84 926.63
X X
0.00 0.00 0.00 0.00 0.00 0.00 251.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.10.03.03 PINTURA DEMARCACION DE LOSA DEPORTIVA und 2.00 125.81 251.62
X

03.11 Varios, Limpieza y Jardinera 20,638.11


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,984.53 4,984.53 4,984.53 4,984.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.11.01 CANALETA DE FIERRO GALVANIZADO REGILLA M 365.10 54.61 19,938.11
X X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.11.09 LIMPIEZA FINAL DE LA OBRA GLB 1.00 700.00 700.00

03.12 Otros 148,348.89


0.00 0.00 0.00 0.00 0.00 0.00 1,526.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.01 ASTA DE BANDERA TIPICO PZA 2.00 763.37 1,526.74
X
0.00 0.00 0.00 0.00 2,916.08 2,916.08 2,916.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.05 ARCO Y TABLERO FULBITO-BASKET(MET-MAD) und 4.00 2,187.06 8,748.24
X X X
0.00 0.00 0.00 0.00 0.00 0.00 0.00 834.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.06 TUBOS C.VOLEY,INC.RED Y DADOS CONCRETO JGO 2.00 417.29 834.58
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,978.66 1,978.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.08 MESA DE NIOS und 4.00 989.33 3,957.32
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 4,755.73 0.00 0.00
03.12.14 BUTACAS und 330.00 321.46 109,381.80
X X X X X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 174.40 174.40 174.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.15 CONFORMACION DE TALUD PARA JARDINERIA M2 327.00 1.60 523.20
X X X

SEMBRADO DE GRASS NATURAL INC. TIERRA DE CHACRA 0.00 0.00 0.00 0.00 1,036.34 1,036.34 1,036.34 1,036.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.16 M2 177.00 23.42 4,145.34
E= 0.10m X X X X

ANGULAR METALICO DE 11/2"X11/2" EN PISO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,436.64 2,436.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.18 M 175.74 27.73 4,873.27
P/VEREDAS X X

0.00 0.00 0.00 0.00 0.00 0.00 1,625.00 1,625.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.20 PUERTA SS.HH. MELAMINE CON PERFIL DE ALUMINIO und 13.00 250.00 3,250.00
X X

PROTECTOR METALICO P/VENTANAS EN AULAS SEGUN 0.00 0.00 0.00 0.00 0.00 2,777.10 2,777.10 2,777.10 2,777.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.12.21 M2 92.57 120.00 11,108.40
DISEO X X X X

04 Instalaciones Sanitarias 21,886.17


04.01 Aparatos Sanitarios y Accesorios 7,455.58
0.00 0.00 0.00 1,680.00 1,680.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03 INODORO DE LOSA VITRIFICADA TREBOL O SIMILAR PZA 6.00 560.00 3,360.00
X X

0.00 0.00 0.00 0.00 746.67 746.67 746.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.05 INODORO CON FLUXOMETRO PZA 4.00 560.00 2,240.00
X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 570.00 570.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.07 URINARIO CON FLUXOMETRO PZA 2.00 570.00 1,140.00
X X

0.00 0.00 0.00 0.00 0.00 0.00 309.84 309.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.11 DUCHA SIMPLE CON GRIFERIA PZA 8.00 77.46 619.68
X X

0.00 0.00 0.00 0.00 0.00 47.95 47.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.12 GRIFERIA PARA BEBEDERO und 7.00 13.70 95.90
X X

04.02 Sistema de Agua Fra y Contraincendio 8,027.11


04.02.05 Accesorios 1,551.46
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 517.15 517.15 517.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.05.24 ACCESORIOS CISTERNA 180M3 und 1.00 1,551.46 1,551.46
X X X

04.02.06 Varios 6,475.65


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 114.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.03 EMPALME A CISTERNA EXISTENTE und 2.00 57.04 114.08
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 413.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.04 CAJA DE VALVULA BYPASS DE CONCRETO und 2.00 206.66 413.32
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 272.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.05 CAJA DE REBOSE C/REJILLA DE FIERRO und 2.00 136.39 272.78
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,294.18 2,294.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.06 EQUIPO DE BOMBEO , 2 ELECTROBOMBAS 2.0 HP und 1.00 4,588.36 4,588.36
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 118.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.09 REBOSE DE CISTERNA Y TANQUE E. DE FoGo 2" und 2.00 59.24 118.48
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 133.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.10 REBOSE DE CISTERNA DE FoGo 3" und 2.00 66.74 133.48
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 170.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.11 REBOSE DE CISTERNA DE FoGo 4" und 2.00 85.19 170.38
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 104.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.12 REBOSE DE TANQUE ALTO DE FoGo 2" und 2.00 52.24 104.48
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.13 ABRAZADERA DE FIJACION DE TUBO (Mx 3") PZA 2.00 12.90 25.80
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 267.25 267.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06.14 ABRAZADERA DE FIJACION DE TUBO PZA 43.00 12.43 534.49
X X

04.03 Sistema de Drenaje Fluvial 5,794.28


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,448.57 1,448.57 1,448.57 1,448.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.01 TUBERIA DE BAJADA PVC-SAP 4" P/LLUVIAS M 335.90 17.25 5,794.28
X X X X

04.04 Desague y Ventilacin 609.20


04.04.03 Tuberias 75.60
0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.80 37.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03.03 TUBERIA PVC-SAP 4" RED EXTERIOR M 4.00 18.90 75.60
X X

04.04.04 Accesorios 533.60


0.00 0.00 0.00 0.00 0.00 0.00 0.00 81.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04.01 REGISTRO DE BRONCE 4" und 2.00 40.64 81.28
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.16 226.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04.20 ACCESORIOS PARA DESAGUE EN SISTERNA Y TE und 2.00 226.16 452.32
X X

05 Instalaciones Elctricas 30,255.00


05.01 Obras Preliminares 1,213.10
REPROGRAMACION DE EJECUCION FISICA Y FINANCIERA EN DIAGRAMA DE BARRAS DE GANTT.
OBRA MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS - SANTA ANA, PROVINCIA LA CONVENCION

EJECUTOR MUNICIPALIMUNICIPALIDAD PROVINCIAL DE LA CONVENCION


UBICACIN CUSCO - LADISTRITO DE SANTA ANA -PROVINCIA DE LA CONVENCION-REGION CUSCO
2015
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
SEM001 SEM002 SEM003 SEM004 SEM005 SEM006 SEM007 SEM008 SEM009 SEM010 SEM011 SEM012 SEM013 SEM014 SEM015 SEM016 SEM017 SEM018 SEM019 SEM020 SEM021 SEM022 SEM023 SEM024 SEM025 SEM026 SEM027 SEM028 SEM029 SEM030 SEM031 SEM032 SEM033 SEM034 SEM035 SEM036 SEM037 SEM038 SEM039 SEM040 SEM041 SEM042
N UND METRADO Precio (S/.) Precio (S/.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 508.19 508.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.01 PICADO Y RESANE DE PISO Y VEREDA DE CONCRETO M2 17.71 57.39 1,016.38
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.02 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT.-ELECT. m3 4.37 14.34 62.67
X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 134.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.04 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 5.68 23.60 134.05
X

05.02 Salida para Alumbrado, Tomacorrientes, Fuerza y Seales Debiles 9,650.86


0.00 388.68 388.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.03 SALIDA PARA TOMACORRIENTE DOBLE PTO 6.00 129.56 777.36
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 535.50 535.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.04 SALIDA TRIFASICA PARA ELECTROBOMBA PTO 4.00 267.75 1,071.00
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 224.76 224.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.05 SALIDA DE TELEFONO y/o INTERCOMUNICADORES PTO 8.00 56.19 449.52
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,367.70 3,367.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.06 SALIDA PARA RED DATA (COMPUTO) PTO 70.00 96.22 6,735.40
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 308.79 308.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.07 SALIDA PARA TIMBRE PTO 9.00 68.62 617.58
X X

05.04 Cajas 106.96


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 106.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.01 CAJA DE PASE FG 4x4x1.5" und 7.00 15.28 106.96
X
REPROGRAMACION DE EJECUCION FISICA Y FINANCIERA EN DIAGRAMA DE BARRAS DE GANTT.
OBRA MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS - SANTA ANA, PROVINCIA LA CONVENCION

EJECUTOR MUNICIPALIMUNICIPALIDAD PROVINCIAL DE LA CONVENCION


UBICACIN CUSCO - LADISTRITO DE SANTA ANA -PROVINCIA DE LA CONVENCION-REGION CUSCO
2015
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
SEM001 SEM002 SEM003 SEM004 SEM005 SEM006 SEM007 SEM008 SEM009 SEM010 SEM011 SEM012 SEM013 SEM014 SEM015 SEM016 SEM017 SEM018 SEM019 SEM020 SEM021 SEM022 SEM023 SEM024 SEM025 SEM026 SEM027 SEM028 SEM029 SEM030 SEM031 SEM032 SEM033 SEM034 SEM035 SEM036 SEM037 SEM038 SEM039 SEM040 SEM041 SEM042
N UND METRADO Precio (S/.) Precio (S/.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

05.05 Tableros y cuchillas (Llaves) 925.56


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.78 462.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.05.14 TAB AUT. CONTROL ELECTROBOMBAS 2 X 20A und 2.00 462.78 925.56
X X

05.06 Conexiones a Red Externa y Medidores 4,613.40


0.00 0.00 0.00 922.68 922.68 922.68 922.68 922.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.06.06 ALIMENTADOR CAB. N2XH (2-1x6 + 1x10)mm2 M 110.00 41.94 4,613.40
X X X X X

05.09 Artefactos 8,482.68


0.00 0.00 0.00 2,331.75 2,331.75 2,331.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.09.06 FAROLA JP 250 LAMPARA HG 125W und 15.00 466.35 6,995.25
X X X

0.00 0.00 0.00 743.72 743.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.09.07 EQUIPO DE ILUMINACION DE MERGENCIA BATERIA PZA 9.00 165.27 1,487.43
X X

05.10 Otros 5,262.44


0.00 0.00 0.00 180.85 180.85 180.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.10.01 CONSTRUCCION DE SUBESTACIONES und 1.00 542.56 542.56
X X X

SUMINISTRO E INSTALACION DE POSTES DE 0.00 0.00 1,386.37 1,386.37 1,386.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.10.02 und 4.00 1,039.78 4,159.12
ALUMBRADO X X X

0.00 0.00 0.00 132.69 132.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.10.03 CAMPANILLA DE TIMBRE DE 6" CON TRANF 220/12V und 3.00 88.46 265.38
X X

0.00 0.00 0.00 295.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.10.04 CAMPANILLA DE TIMBRE DE 8" CON TRANF 220/12V und 3.00 98.46 295.38
X

06 IMPLEMENTACION Y EQUIPAMIENTO 253,393.59


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 8,735.74 0.00 0.00 0.00
06.01 ADQUISICION DE EQUIPOS Y MOBILIRIOS GLB 1.00 247,113.30 218,393.59
X X X X X X X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,375.00 4,375.00 4,375.00 4,375.00 4,375.00 4,375.00 4,375.00 4,375.00 0.00 0.00
06.02 ADQUISICION DE TEXTOS GLB 1.00 35,000.00 35,000.00
X X X X X X X X

07 CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANA DOCENTE 48,700.00


CAPACITACION Y ASISTENCIA TECNICA PARA LA PLANA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,411.11 5,411.11 5,411.11 5,411.11 5,411.11 5,411.11 5,411.11 5,411.11 5,411.11 0.00
07.01 GLB 1.00 48,700.00 48,700.00
DOCENTE X X X X X X X X X

08 PARTIDAS COMPLEMENTARIAS 100,212.33


08.01 Implementacion de Audio y Video en el Auditoriun 45,430.00
08.01.01 Audio 19,000.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 211.11 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.01 CAJAS ACUSTICAS (PARLANTES) und 4.00 950.00 3,800.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 138.89 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.02 CONSOLA O MEZCLADORA PROFESIONAL DE AUDIO und 1.00 2,500.00 2,500.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.03 ECUALIZADOR GRAFICO und 1.00 1,800.00 1,800.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 80.56 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.04 AMPLIFICADOR-MEZCLADORA und 1.00 1,450.00 1,450.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.05 MICROS INALAMBRICOS und 3.00 1,200.00 3,600.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 122.22 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.06 MICROS CON CABLE und 10.00 220.00 2,200.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 77.78 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.07 PEDESTALES PARA MICROFONOS und 10.00 140.00 1,400.00
X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.08 CONECCION MEDUSA DE 30 m ORIGINAL und 1.00 2,250.00 2,250.00
X X X X X X X X X X X X X X X X X X

08.01.02 Tv y Video Luces y Decoracion de Escenario y Efectos en Auditorium 26,430.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 0.00 0.00 0.00 0.00 0.00
08.01.02.01 DVD FULL HD CON USB- HDMI und 1.00 280.00 280.00
X X X X X X X X X X X X X X X X X X X

PROYECTOR PROFESIONAL PARA USO CONTINUO CON 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 173.68 0.00 0.00 0.00 0.00 0.00
08.01.02.02 und 1.00 3,300.00 3,300.00
LENTE MOTORIZADO EXTERNO 18 OZ X X X X X X X X X X X X X X X X X X X

ECRAN - PANTALLA DE PROYECCIN MOTORIZADA DE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 131.58 0.00 0.00 0.00 0.00 0.00
08.01.02.03 und 1.00 2,500.00 2,500.00
180 X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 0.00 0.00 0.00 0.00 0.00
08.01.02.04 RACK PARA PROYECTOR und 1.00 950.00 950.00
X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 57.89 0.00 0.00 0.00 0.00 0.00
08.01.02.05 CONTROLADOR DE LUCES DE 24 CANALES DMX und 1.00 1,100.00 1,100.00
X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 157.89 0.00 0.00 0.00 0.00 0.00
08.01.02.06 Le-172 LED JUEGO DE LUCES DOUBLE FLOWER und 4.00 750.00 3,000.00
X X X X X X X X X X X X X X X X X X X

CAON SEGUIDOR DE ESCENARIO (CABEZA MOVIL DE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 236.84 0.00 0.00 0.00 0.00 0.00
08.01.02.07 und 1.00 4,500.00 4,500.00
575 W) X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 35.79 0.00 0.00 0.00 0.00 0.00
08.01.02.08 MQUINA DE HUMO und 1.00 680.00 680.00
X X X X X X X X X X X X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02.09 LQUIDO FLUIDO PARA MQUINA DE HUMO gal 1.00 120.00 120.00
X X X X X X X X X X X X X X X

DECORACION DE ESCENARIO CON MADERAMEN 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,500.00 2,500.00 2,500.00 2,500.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02.10 glb 1.00 10,000.00 10,000.00
ENCHAPADA X X X X

08.02 Pintura de Estructuras Metalicas y de Concreto 30,320.10


08.02.01 Pintura de Estructuras Metalicas 6,428.80
0.00 0.00 0.00 0.00 0.00 0.00 1,543.89 1,543.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.01 PINTURA DE CERCO METALICO DE INICIAL M2 209.91 14.71 3,087.78
X X

PINTURA DE REJAS METALICAS DE CANAL DE 0.00 0.00 0.00 0.00 0.00 0.00 1,643.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.02 M2 174.42 9.42 1,643.04
EVACUACION DE AGUAS PLUVIALES X

PINTURA EN PUERTAS METALICAS DE INGRESO A LA I. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,697.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.03 M2 115.43 14.71 1,697.98
E X

08.02.02 Pintura de Estructuras de Concreto 23,891.30


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,009.70 1,009.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.01 PINTURA EN POSTES DE ALUMBRADO EXTERIOR M2 137.28 14.71 2,019.39
X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 877.87 877.87 877.87 877.87 877.87 877.87 877.87 877.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.02 PINTURA MURAL DECORATIVAS -PREVENCION M2 101.87 68.94 7,022.92
X X X X X X X X

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,969.80 2,969.80 2,969.80 2,969.80 2,969.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.03 PINTURA INTERIOR Y EXTERIOR EN AUDITORIUM M2 1,815.28 8.18 14,848.99
X X X X X

08.03 Trabajos de Proteccion de Ventanas y Puertas 9,462.23


08.03.01 Trabajos de Proteccion de Ventanas 4,958.30
PROTECCION CON MALLA MOSQUITERO PARA VENTANA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,652.77 1,652.77 1,652.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01.01 M2 213.72 23.20 4,958.30
- SELVA X X X
|
08.03.02 Trabajos de Proteccion de Puertas 4,503.93
PROTECCION METALICA DE SEGURIDAD EN PUERTAS DE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,501.31 1,501.31 1,501.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01 M2 10.63 423.70 4,503.93
LABORATORIOS X X X

08.04 Trabajos de Instalacion de Transformador 15,000.00


08.04.01 Instalaciones de Transformador y Alimentador Externo 15,000.00
GLB 1.00 15,000.00 15,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64 1,363.64
08.04.01.01 INSTALACION Y ADECUACION DEL TRANSFORMADOR
X X X X X X X X X X X
REPROGRAMACION DE EJECUCION FISICA Y FINANCIERA EN DIAGRAMA DE BARRAS DE GANTT.
OBRA MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS - SANTA ANA, PROVINCIA LA CONVENCION

EJECUTOR MUNICIPALIMUNICIPALIDAD PROVINCIAL DE LA CONVENCION


UBICACIN CUSCO - LADISTRITO DE SANTA ANA -PROVINCIA DE LA CONVENCION-REGION CUSCO
2015
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
SEM001 SEM002 SEM003 SEM004 SEM005 SEM006 SEM007 SEM008 SEM009 SEM010 SEM011 SEM012 SEM013 SEM014 SEM015 SEM016 SEM017 SEM018 SEM019 SEM020 SEM021 SEM022 SEM023 SEM024 SEM025 SEM026 SEM027 SEM028 SEM029 SEM030 SEM031 SEM032 SEM033 SEM034 SEM035 SEM036 SEM037 SEM038 SEM039 SEM040 SEM041 SEM042
N UND METRADO Precio (S/.) Precio (S/.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
ML 300.00 24.04 7,212.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 480.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.01.02 ALIMENT. (3x1x16)mm2 TW Externo
X X X X X X X X X X X X X X X

2,046.45 2,715.12 2,701.25 10,797.99 20,380.64 14,736.77 31,210.04 30,657.59 25,945.87 51,253.47 53,822.99 40,676.45 40,179.18 19,790.76 24,761.89 25,303.17 15,562.46 17,712.22 15,894.25 15,894.25 15,894.25 15,894.25 15,894.25 15,894.25 16,542.20 16,542.20 16,542.20 16,542.20 15,413.45 18,383.25 18,383.25 19,746.89 32,033.00 32,025.00 29,055.20 29,055.20 25,499.64 24,641.22 24,641.22 15,905.48 6,774.75 1,363.64

COSTO DIRECTO 884,709.78 4,761.57 48,616.65 139,066.97 154,469.39 83,339.74 63,577.00 64,872.89 66,881.09 102,188.13 108,251.26 48,685.08

GASTOS GENERALES 233,437.00 1,256.38 12,827.85 36,693.81 40,757.85 21,989.79 16,775.25 17,117.18 17,647.05 26,963.07 28,562.87 12,845.91
SUPERVISION 110,879.72 596.76 6,093.07 17,429.11 19,359.48 10,444.88 7,968.04 8,130.45 8,382.13 12,807.13 13,567.01 6,101.65
EXPEDIENTE TECNICO 15,140.33 81.49 831.99 2,379.90 2,643.49 1,426.22 1,088.01 1,110.19 1,144.56 1,748.78 1,852.54 833.16
LIQUIDACION 52,906.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL PRESUPUESTO 1,297,073.72 6,696.20 68,369.57 195,569.79 217,230.20 117,200.63 89,408.30 91,230.71 94,054.84 143,707.10 152,233.68 68,465.80

EJECUCION ACUMULADA MENSUALIZADA


MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS
CRONOGRAMA COMPARADO Vs EJECUTADO

OBRA :
"MEJORAMIENTO DE LA OFERTA DE SERVICIO EDUCATIVO N 51027 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

CODIGO SNIP: 86920

PROGRAMADO EJECUTADO
MES

AVANCE FISICO % AVANCE ACUMULADO % AVANCE FISICO % AVANCE ACUMULADO


AO 2014 8,967,529.30 67.52% 8,967,529.30
ENERO 6,696.20 0.05% 8,974,225.50 67.57% 16,247.10 0.12% 8,983,776.40
FEBRERO 68,369.57 0.51% 9,042,595.07 68.08% 110,309.33 0.83% 9,094,085.73
MARZO 195,569.79 1.47% 9,238,164.86 69.55% 156,655.73 1.18% 9,250,741.45
ABRIL 217,230.20 1.64% 9,455,395.07 71.19% 72,238.32 0.54% 9,322,979.77
MAYO 117,200.63 0.88% 9,572,595.70 72.07% 129,554.28 0.98% 9,452,534.05
JUNIO 89,408.30 0.67% 9,662,004.00 72.74% 21,112.79 0.16% 9,473,646.84
JULIO 91,230.71 0.69% 9,753,234.71 73.43% 4,927.89 0.04% 9,478,574.73
MUNICIPALIDAD PROVINCIAL DE LA CONVENCIN
GERENCIA DE INFRAESTRUCTURA PBLICA
DIRECCION DE OBRAS
CRONOGRAMA COMPARADO Vs EJECUTADO

7 JUAN DE LA CRUZ MONTES SALAS SANTA ANA, PROVINCIA DE LA CONVENCIN CUSCO"

EJECUTADO

%
67.52%
67.64%
68.47%
69.65%
70.19%
71.17%
71.33%
71.36%