Assessment of Hydro-Turbine Generator Shaft Overview
Hydro Tasmania Power Station operates six horizontal Machined groove 1
shaft hydro- turbine generators each with two Pelton wheel runners installed. Three of the turbine shafts have shrunk-on runners while the remaining three have bolted runners. Historically, cracking occurred in the shafts under the runner hubs. During overhauls the cracks were removed by grinding and this left circumferential machine grooves on the shafts. NDT inspections have indicated that the extent of the cracking in the shrunk-on runners was significantly Machined groove 2 more severe than in the bolted runners. Quest Reliability LLC was hired to perform a stress analysis, Figure 1 FEA model of the shaft critical crack size computations and a vibration analysis on a shaft at the Tarraleah Power Station.
The project consisted of several parts. The first part
included a three dimensional finite element analysis (FEA) including the worst of the identified grooves. The model included the loading due to the shrink fit, the centrifugal load applied by the spinning runners, the torque applied on the shaft due to the runners, and the total assembly self weight. The stresses from this analysis were extracted and used as primary stress input in a critical crack size computation and fatigue life estimates. Finally, a natural frequency analysis was performed using the FEA model to provide guidance regarding safe operational speeds of the shaft. Figure 2 Applied loads on the model
www.QuestIntegrity.com Quest Integrity Rev.06-15
Results
The assessment was carried out using guidelines
given in BS7910:2005 and the conclusions reached were as follows:
The fracture mechanics assessment showed that
the shaft assembly could withstand a significant crack depth around the shaft before failure.
However, a fatigue crack growth analysis based on
mean fatigue crack growth properties found that a Figure 3 Axial stress due to combined loads, 6mm deep crack would likely put the shaft near the stress scale -75MPa to 75MPa. end of life in about 12 years.
Assuming lower bound (worst case) fatigue crack
growth properties, the remaining life was calculated as 6 years.
The stress analysis also included a natural
frequency evaluation to ensure that the rotation of the assembly would not interfere with the natural frequency. The 40.69Hz natural frequency of the structure, much higher than the 13.92Hz maximum rotational speed, implies that there should be limited excitation at the natural frequency under normal operation. Figure 4 First mode or natural frequency of assembly. Non-deformed shape in grey.