Hoja: 1
Fecha: 16/11/2017
PRESUPUESTO GENERAL
1. OBRAS PRELIMINARES
1- INST001 INSTALACION DE FAENAS Y MOVILIZACION GLB 1.00 4,968.81 4,968.81
2- LETR004 LETRERO DE OBRA (LONA PVC) 2.00X1.50 M2 PZA 1.00 761.52 761.52
3- REPL001 REPLANTEO Y TRZADO DE ALAMCENAMIENTO M2 2,400.00 12.32 29,568.00
4- REPL009 REPLANTEO Y TRAZADO DE EJE ML 307.00 8.91 2,735.37
Subtotal 1. OBRAS PRELIMINARES 38,033.70
2. OBRA DE TOMA
5- EXCA010 EXCAVACION CON MAQUINARIA 0-2 M SIN AGOTAMIENTO M3 37.78 38.17 1,442.06
6- EXCA014 EXCAVACIN Y RETIRO DE ROCA BLANDA C/MAQUINARIA M3 104.50 83.37 8,712.17
7- HORM004 HORMIGON CICLOPEO 50% P.D. PARA ESTRUCTURA HIDRAULICA M3 192.07 987.60 189,688.33
8- REJI015 REJILLA METLICA LINEAL ML 6.00 1,459.03 8,754.18
Subtotal 2. OBRA DE TOMA 208,596.74
3. CANAL DE TRANSPORTE
9- EXCA007 EXCAVACION MANUAL 0-2 M S/AGOTAMIENTO T. SEMIDURO M3 22.50 82.44 1,854.90
10- RELL007 RELLENO Y COMPACTADO C/COMPACTADOR MANUAL M3 189.00 75.04 14,182.56
11- HORM014 HORMIGON SIMPLE FCK=20MPA M3 38.06 2,702.33 102,850.68
12- EMPI001 SOLADO DE PIEDRA M2 169.15 75.86 12,831.72
13- JUNT011 JUNTA DE DILATACIN ML 111.60 105.15 11,734.74
14- ACER006 ACERO DE REFUERZO KG 196.14 20.61 4,042.45
15- HORM006 PILARES DE HC 60% PIEDRA DESPLAZADORA M3 7.54 734.43 5,537.60
16- HORM006 ATRANCOS PARA CANAL HC 60% PIEDRA DESPLAZ. M3 1.03 734.43 756.46
Subtotal 3. CANAL DE TRANSPORTE 153,791.11
4. DESARENADOR
17- HORM014 HORMIGON SIMPLE FCK=20MPA M3 9.61 2,702.33 25,969.39
18- COMP005 COMPUERTA DE LIMPIEZA EN DESARENADOR PZA 1.00 7,953.42 7,953.42
19- EMPI001 SOLADO DE PIEDRA M2 23.11 75.86 1,753.12
20- ACER006 ACERO DE REFUERZO KG 7.46 20.61 153.75
Subtotal 4. DESARENADOR 35,829.68
5. ALMACENAMIENTO
21- MEJ001 CORTE Y NIVELACION DEL TERRENO M3 123.66 118.35 14,635.16
22- EXCA026 EXCAVACION MANUAL 0-1 M. EN TERRENO COLUVIAL M3 60.82 68.70 4,178.33
23- HORM004 HORMIGON CICLOPEO 50% P.D. PARA ESTRUCTURA HIDRAULICA M3 562.37 987.60 555,396.61
24- CESP004 CAPA BASE DE ARENA FINA M3 102.65 225.18 23,114.73
25- HORM016 HORMIGON SIMPLE LOSA M3 205.30 1,682.25 345,365.93
26- JUNT011 JUNTA DE DILATACIN ML 758.80 29.37 22,285.96
BENITO ALVARO LAURA ACUA
Hoja: 2
Fecha: 16/11/2017
PRESUPUESTO GENERAL
6. OBRAS COMPLEMENTARIAS
37- PLAC004 PLAQUETA DE ENTREGA DE OBRA 0,60 X 0,40 M FIERRO PZA 1.00 793.36 793.36
Subtotal 6. OBRAS COMPLEMENTARIAS 793.36
8. MITIGACIN AMBIENTAL
39- MIT105 MITIGACION AMBIENTAL GLB 1.00 70,469.65 70,469.65
Subtotal 8. MITIGACIN AMBIENTAL 70,469.65
COSTO TOTAL DEL PROYECTO 1,883,060.78