1 6/14/2017
2 6/17/2017
3 11/18/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Trunion lubrication pump for 300LQ2 heat exchanger dismatled and cleaning work done.
Trunion lubrication pump for 300LQ1 heat exchanger dismatled and cleaning work done.
Both the trunion lubricating pump 300LQ1 &2 oil filters and strainers cleaning and fixing
work done.
TS (300LQ1-2)
REMARKS
Completed
Completed
1 8/17/2017
2 11/28/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Completed.
2 8/11/2017
3 11/11/2017
4 11/18/2017
5 11/29/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Raw mill main gear box 10 liters oil (ISO VG-320) top-up done.
Raw mill main gear box FLS pump both the oil filter and strainer cleaning and fixing work done.
Raw mill main gear box and auxillary gear box all sealing arrangement greaseing work done.
LS1)
REMARKS
Completed
Completed
1 7/19/2017
2 8/17/2017
23-08-17 to 30-
3 08-17
4 9/5/2017
5 9/20/2017
6 9/21/2017
04-10-2017 to
7 06-10-17
8 10/18/2017
9 10/23/2017
10 11/9/2017
11 11/22/2017
12 11/26/2017
13 11/27/2017
14 12/8/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Raw mill hot air re-circulation duct modification work (Project Work) done as per need of
Plant head to enhance the out-put of raw mill. Fabrication and fixing of new damaper 75
mm dia to the modified duct.
Raw mill inlet trunion mounting flange all bolts ( M20x75 mm Grade 8.9 = 12 Nos.)
replacement & required bolt tightening work done.
Raw mill inlet fresh air damper repairing and re-installation work done.
Raw mill girth gear grease barrel has been replaced by new grease barrel.
Raw mill all shell liner and diaphragm bolts tightening work done.
Raw mill inlet trunion mounting flange bolts total = 07 nos broken and all these bolts
replacement & required bolt tightening work done.
Raw mill inlet trunion mounting flange bolts total = 03 nos broken and all these bolts
replacement & required bolt tightening work done.
Raw mill girth gear grease barrel has been replaced by new grease barrel at morning 07:45
AM.
Raw mill diaphragm liner bolts 03 nos. fixing and tag welding work done. Diaphragm liner
bolts tighteness done.
Raw mill grinding chamber liner bolt 01-no fixing and bolt tightening work done.
Raw mill inlet trunion mounting flange all bolts tighteness done and 01 no bolt has been
replacement & required bolt tightening work done.
Raw mill girth gear guard sealing felt arrangement slipped from the position, re-fixing work
done. Also the bolts for grinding chamber door tightening done fixing with gland rope.
D.
AL
(300RM1)
REMARKS
Completed
Completed
Completed
Completed
Completed
Completed
1 6/25/2017
2 12/2/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Reject belt feeding skirt board and rubber has been modified to prevent spillage of material.
Raw mill reject belt conveyor 300BC1 all pulleys (head, tail & snub) bearing greasing work done.
R (300BC1)
REMARKS
1 11/30/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
HISTORY SHEET FOR SCREW CONVEYOR & RVF (300SC1 & RVF5-
SR.NO. DATE DESCRIPTION OF WORK
Bag house screw conveyor 300SC1, NDE bearing and block got
1 6/20/2017 damage. Complete set up (SN513) has been replaced by new spare.
Bag house screw conveyor 300SC1 NDE shaft sealing work done to
2 7/27/2017 prevent spillage of material.
Bag house screw conveyor 300SC1 all hanging bearings were checked
and found out two nos wear out. These two nos liners have been
3 8/21/2017 replced by new ones. All the 300RVF5 to 8 sprockets tightening and
required maintenance work done.
Bag house screw conveyor 300SC1, both the bearings ( Inlet & Outlet)
4 11/17/2017 shaft sealing area gland packing inserted.
Bag house rotary vane feeders 300RVF5 to 8 ( total 04 nos) all
5 11/21/2017 sprockets (drive & driven), chain and guard tighteness done.
Bag house chamber no-05, existing rotary vane feeder 300RVF5 has
6 11/26/2017 been replaced by new RVF of higher capacity.
Bag house screw conveyor 300SC1 all inspection door sealing and
7 11/27/2017 locking arrangement done.
LTD.
EPAL
Completed
Completed
Completed
HISTORY SHEET FOR SCREW CONVEYOR & RVF (300SC2 & RVF10
SR.NO. DATE DESCRIPTION OF WORK
Bag house screw conveyor 300SC2, both the bearings ( Inlet & Outlet) shaft
1 11/17/2017 sealing area gland packing inserted.
Bag house screw conveyor 300SC2 NDE shaft sealing work done to prevent
2 7/27/2017 spillage of material.
Bag house screw conveyor 300SC1 all hanging bearings were checked and found
3 8/21/2017 out two nos wear out. These two nos liners have been replced by new ones. All
the 300RVF5 to 8 sprockets tightening and required maintenance work done.
Bag house rotary vane feeders 300RVF5 to 8 ( total 04 nos) all sprockets (drive &
4 11/21/2017 driven), chain and guard tighteness done. Two nos. RVF geared motor oil level
maintained.
Bag house screw conveyor 300SC2 all inspection door sealing and locking
5 11/27/2017 arrangement done.
(300SC2 & RVF10-13)
REMARKS
Completed
Completed
1 6/14/2017
2 6/16/2017
3 10/14/2017
4 10/18/2017
5 10/23/2017
6 10/27/2017
7 11/23/2017
8 11/27/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Bag house inlet draft point which was changed from original position to a new point for
process point of view. But due to draft problem it again set to the original position.
Bag house chamber no-8 all bags inspection done and damaged 95 bags has been
replaced by new one.
Bag house chamber no-5 all bags inspection done and damaged 50 bags has been
replaced by new one.
Bag house chamber no-6 all bags inspection done and damaged 105 bags has been
replaced by new one.
Bag house all puppet valve for chamber nos 5 to 8 & 10 to 13, puppet bolts tighteness
done. Also inspection of bags done.
Bag house FRL-unit clearing and oil level maintaining work done.
L
300DC1)
REMARKS
Completed.
Completed.
1 11/19/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
1 6/21/2017
2 6/25/2017
3 10/3/2017
4 11/17/2017
5 11/18/2017
UNITED CEMENT PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Blending silo bucket elevator 400BE1 maintenance platform fixing work at tail end drum.
Blending silo bucket elevator 400BE1 existing damage belt joint has been replaced and tail
drum lifted up by an amount 300 mm. Accordingly, the boot casing has also been modified.
Blending silo all lifting bucket bolts tighteness and belt-joint inspection done, found
satisfactory.
Blending silo all lifting bucket bolts tighteness and belt-joint inspection done, found
satisfactory. Fluid Coupling oil-46 grade two litres filled up and level maintained.
Blending silo bucket elevator tail drum NDE side old grease replenishment and filling new
grease along with sealing work.
LEVATOR (400BE1)
REMARKS
Completed
Completed
Completed
Completed
Blending Silo top dust collector 400DC1 existing solenoid valves 5 in nos. (out of 6) has
2 7/5/2017 been replaced by new spares together with E&I department. As there were purging
problem in existing one.
Blending Silo top dust collector 400DC1 fan all existing V-belts (03 nos) has been
3 6/26/2017 replaced by new spares. Both the bearing cleaning and greasing work done. Impeller
coating cleaning also done.
Blending Silo top dust collector 400DC1 fan shaft NDE side bearing re-locating and
4 11/17/2017 both bearing check-nut tightening and greasing work done.
L
COLLECTOR (400DC1)
REMARKS
Completed.