Professional Documents
Culture Documents
SR.NO. MAN POWER REQ. NOS. MAN POWER RATE/NOS TOTAL COST (INR) REMARKS
Lime Stone Truck Tippler foundation strengthening work by This work is required to accomplish
2 100 TT1 dismantling and re-grouting work. with civil dept.
Belt conveyor tippler trolley rail aligning & welding work. The
8 100 BC2 existing rail supports strengthening work, by providing extra
supports.
200 TCR1 Maintenance work for tertiary crusher side liner plates and
18 discharge chute.
300 RM1 Raw Mill inlet mounting flange inspection followed by required
22 bolt tightening work.
300 RM1 Inspection of all bolts of Raw mill diaphragm, shell liner bolts &
23 girth gear followed by required tightening work.
300 RM1 Internal inspection of raw mill diaphragm liners and required
25 bolt tightening work.
300 LQ1, 2 Cleaning of all oil filters and strainers alongwith arresting oil
27 &3 leakages from oil lines.
Bag House Inspection for alignment of both screw conveyors 300SC1 & 2 ,
30 all the hanging bearing & its greasing point.
400 BE-1 Inspection of condition for belt, belt joint, buckets and bucket
33 bolts. Also discharge chute tounge plate gap inspection.
300CP1-2 Sorting out the problems of dryer during the visit of Service
36 Engineer. Although the refrigerant (R410A) level is Ok.
Belt conveyor tippler trolley rail aligning & welding work. The
8 100 BC2 existing rail supports strengthening work, by providing extra
supports.
9 Misc. 100TT1 side, handrail damaged; required repairing work.
Temporary fixing of a de-watering pump behind the spillage
10 Misc. conveyor 100SX1 at L/S crusher floor level.
11 Misc. Fixing of a de-watering at 100BC1 tail end side.
Belt conveyor 100BC2 open platform area, hand rail fixing
12 Misc. work.
L/S STOCK PILE TO RAW MILL FEED AREA
Under ground tunnel belt replacement and jointing work after
13 100 BC3 removal of jointed piece of rubber belt.
200 TCR1 Maintenance work for tertiary crusher side liner plates and
19 discharge chute.
20 200 TCR1 All V-belt replacement work by new spare V-belts.
Fixing of toe guards at Raw Material Hopper floor level along
21 Misc. with handrailing.
300 RM1 Raw Mill torsion shaft bolt tightness and coupling greasing
25 work.
300 RM1 Inspection of all bolts of Raw mill diaphragm, shell liner bolts &
26 girth gear followed by required tightening work.
Removal of collected grease from Raw Mill girth gear guard by
27 300 RM1 taping it from the point. Fixing of a 4'' ball valve for grease
removal work.
300 RM1 Internal inspection of raw mill diaphragm liners and required
28 bolt tightening work.
Both the trunion bearings pre-jacking oil line checking and
29 300 LQ1 & 2 required maintenance work. (This is due to unhealthy pressure
comes at sometime)
300 LQ1, 2 Cleaning of all oil filters and strainers alongwith arresting oil
30 &3 leakages from oil lines.
Bag House Inspection for alignment of both screw conveyors 300SC1 & 2 ,
33 all the hanging bearing & its greasing point.
Bag House discharge air slide, required to connect to CA fan
34 Bag House suction line for venting the air slide & screw conveyors 300SC1
&2.
400 BE-1 Inspection of condition for belt, belt joint, buckets and bucket
36 bolts. Also discharge chute tounge plate gap inspection.