OBJECTIVE.
Reduced absenteeism
ACTIVITIES
Excavation work Painting
Concrete work Chipping and Grouting
Steel Rest Floor & Falls Ceiling
Installation/Erection Loading and Unloading
Shuttering & Electrical works
Deshuttering Panel Installing
Pre Cast Installation Cable Pulling
Water Proofing Testing &
Welding, Cutting and Commissioning.
Grinding. Shut down & tapping.
Substation Energize
HAZARDS & RISK
Physical Hazards Loading & Unloading
Mechanical Hazards Electricity Hazards.
Chemical Hazards Health Hazard
Biological Hazards Risk-Damage to
Ergonomically person & Property
Hazards
Environmental
Hazards
Slip, Tripp & Fall
Fire & Explosion
IMPLEMENTATION.
Safe system of work Proactive and reactive-
a. -Hazard Identification a. Regular & periodic
& Risk Assessment Inspection
b. -Job Hazard Analysis b. Safe system of work
c. PTWC (permit to work c. Tour & Survey with site
certificate) management
d. Check List d. Performance
HSE monitoring
Instruction, Information e. Accident investigation
and training
a. Induction, Daily TBT
&Specific training-
fire, fall protection etc.
IMPLEMENTATION
Reporting & Recordkeeping Environmental Management system.
a. Accident/incident, Near miss, First Aid a. Identify Aspect & Impact, Waste storage &
and Weekly & Monthly safety disposal, Segregation Hazardous & non
hazardous, Emissions, controlling-
reporting & keeping. Spillage, noise and dust control
Daily observation, Performance Encouraging and Motivation
monitoring and Monthly HSE a. QHSE Reward Procedure implemented (
Evaluation. Monthly ceremony conducted)
a. Unsafe Act & Condition, near miss. Legal & client Requirement Compliance
Safety Recommendation concern HSE Third Party Certification, TUV and
Operating and Driving SAG License.
a. Correction, corrective and preventive a. Local Municipality (Baldiya Clearance.)
action.
Site Emergency Evacuation plan. Hierarchy theory implemented in order to
a. Assembly Area, Locate exit Eliminating and controlling hazards & risk.
way, Emergency Equipment, Assign
Responder person, First Aider and
Rescue Team.
-
RISK ASSESSMENT & PERMIT
Risk Assessment
Hierarchy Theory
applied
Identify the hazard
Who might be harmed
Evaluate the risk
(High, medium & Low)
Record finding and
controlling
Review.
-
HSE INSTRUCTION, INFORMATION AND
TRAINING
Fire
Equip.
- Training
harness
Training
Body
Full
Induct
TBT
ion
PROACTIVE AND REACTIVE-
Record Keeping.
-
Reporting
Mailing, WSR, Practically Safety Recommendation for corrective & preventive action as
per site safety Daily Observing unsafe Act & Condition
SITE EMERGENCY EVACUATION PLAN.
EMERGENCY RESPONSE PERSON AND CONTACT NUMBER(PE-130)
COMMUNICATIO
INCIDENT CO- RESPONDER/ FIRST AID FIRE FIGHTING
N
ORDINATOR RESCUE TEAM TEAM TEAM
TEAM
Md. Usman
Nabil Ahmad Nabil Ahmad Md. Akid Admin Md. Nasir
2 Imtiaz
(0553995482) (0553995482) 0544827894 (0598125277)
(Fabricator)
Md. Akid/Sadiq
Md. Nishad Admin
3
(0502968925) 0544827894
0554946778
Muslim Khan
Md. Samshad
(0595001930)
Nabil Ahmad (HSE
4Ambulance 997 Off.)
Fire/Civil Defence 998 (0553995482)
Local Police 999
Mr. Amjad (SM)
5
(0542368080)
Incident
witness COMPANY
Safety officer
First Aid Room at nearest Site Manager
place
All Safety
Nearest officer at site
(site security
Police Station
Hospital
also)
Hazardous Liquid
spillage kit & Waste
Segregation Bins
provided in Different
Location
Documentation EMS -
Environmental Check List
& Waste Disposal Log
MOTIVATION AND ENCOURAGING
QHSE Reward
Assessment form
As per OSHAS 1801-2017 Procedure SP4 3 1 Legal Other req and Eval of Compliance
HIERARCHY THEORY
Applied Hierarchy of control at site
such as Isolation
mechanical and
electrical Interlock
Guard, Adjustable
Guard in
equipment and
enclosed dusty
area.
ADMINISTRATIVE CONTROL
Tag out Lock out & Safety
Signage like
mandatory, danger and
warning signage provided in
deferent location.
PPE is last controlling system, while hazards could not eliminate or first applied engineering control then PPE
used for protection from hazards.
SAFETY STATISTICS
Achieved- Total number of safe man
hours: more than 300000