WORK BREAKDOWN

STRUCTURE FOR BIMP


PIPELINE PROJECT

Name
Luqman bin Osman

Matric Number
MK1622030T

Course
Master of Oil and Gas Engineering

Subject
KOGE 11203 Project Management and Economics in Oil and Gas

Lecturer
En. Zakaria Aris
% Work
WBS Task Name Duration Resource Names Cost
Complete
1 BIMP PIPELINE PROJECT 70 days SM Anissuzaman 0% RM0.00
1.1 PROJECT INITIATION 10 days SM Anissuzaman 0% RM0.00
1.1.1 Project charter 2 days SM Anissuzaman 0% RM0.00
1.1.2 Formation of PMT 3 days Luqman 0% RM0.00
1.1.3 Kick-Off meeting 1 day Luqman,SM Anissuzaman 0% RM0.00
1.1.4 Project needs & requirement 4 days Luqman 0% RM0.00
1.1.5 Permit to work 7 days Munirah 0% RM0.00
1.1.6 Permit to operate 7 days Munirah 0% RM0.00
1.1.7 Acquiring ROW 10 days Kennedy 0% RM0.00
1.1.8 Technical requirement 10 days Helfi 0% RM0.00
1.2 PROJECT PLANNING 30 days SM Anissuzaman 0% RM0.00
1.2.1 PRD 3 days Luqman 0% RM0.00
1.2.1.1 PRD development 2 days Luqman 0% RM0.00
1.2.1.2 PRD presentation and challenge session 1 day Luqman 0% RM0.00
1.2.1.3 Final review 3 days Luqman 0% RM0.00
1.2.1.4 Approval of PRD 1 day Luqman 0% RM0.00
1.2.2 QAQC 12 days Kennedy 0% RM0.00
1.2.2.1 Develop quality plan 4 days Kennedy 0% RM0.00
1.2.2.2 Review 4 days Kennedy 0% RM0.00
1.2.2.3 Approval 4 days Kennedy 0% RM0.00
1.2.3 HSE 12 days Sani 0% RM0.00
1.2.3.1 Develop HSE plan 4 days Sani 0% RM0.00
1.2.3.2 Review 4 days Sani 0% RM0.00
1.2.3.3 Approval 4 days Sani 0% RM0.00
1.2.4 CONSTRUCTION 12 days Helfi 0% RM0.00
1.2.4.1 Develop Construction execution plan 4 days Helfi 0% RM0.00
1.2.4.2 Review 4 days Helfi 0% RM0.00
1.2.4.3 Approval 4 days Helfi 0% RM0.00
1.3 CONTRACTOR SELECTION AND AWARD 15 days Luqman,SM Anissuzaman 0% RM0.00
1.3.1 Submit ITB to contractor 1 day Luqman 0% RM0.00
1.3.2 Contractor interview 2 days Luqman 0% RM0.00
1.3.3 Contractor final evaluation 5 days Luqman 0% RM0.00
1.3.4 Approval of selected contractor 4 days Luqman 0% RM0.00
1.3.5 Contract award 2 days Luqman 0% RM0.00
1.4 PROCUREMENT 30 days Munirah,SM Anissuzaman 0% RM0.00
1.4.1 Finalize the BOM 2 days Munirah 0% RM0.00
1.4.2 Get quotation for BOM material 4 days Munirah 0% RM0.00
1.4.2.1 Get quotation for key item 2 days Munirah 0% RM0.00
1.4.2.2 Get quotation for non key item 2 days Munirah 0% RM0.00
1.4.3 Purchasing 15 days Munirah 0% RM0.00
1.4.3.1 Issue PO for key item 4 days Munirah 0% RM0.00
1.4.3.2 Issue PO for non-key item 4 days Munirah 0% RM0.00

1|Page
1.4.4 Receiving material 3 days Munirah 0% RM0.00
receive and do material inspection for both key
1.4.4.1 2 days Munirah 0% RM0.00
and non-key item
1.4.5 Storage of material 2 days Helfi 0% RM0.00
1.4.6 Payment Issue 7 days Munirah 0% RM0.00
Luqman,Helfi,Kennedy,SM
1.5 CONSTRUCTION AND TESTING 30 days 0% RM0.00
Anissuzaman
1.5.1 Clearing and grading 12 days Kennedy 0% RM0.00
1.5.1.1 Install silt fence 3 days Kennedy 0% RM0.00
1.5.1.2 Survey / stake the ROW 4 days Kennedy 0% RM0.00
1.5.1.3 Remove tree, rock and debris from the ROW 6 days Kennedy 0% RM0.00
1.5.2 Stringing 7 days Helfi 0% RM0.00
1.5.2.1 Inspect pipe 2 days Helfi 0% RM0.00
1.5.2.2 Apply coating 3 days Helfi 0% RM0.00
1.5.2.3 Transport pipe to ROW 6 days Helfi 0% RM0.00
1.5.3 Trenching 5 days Kennedy 0% RM0.00
1.5.3.1 Erect temporary support 2 days Kennedy 0% RM0.00
1.5.3.2 Excavation 3 days Kennedy 0% RM0.00
1.5.4 Welding 15 days Luqman 0% RM0.00
1.5.4.1 Pipe laying 2 days Luqman 0% RM0.00
1.5.4.2 Fit-up 2 days Luqman 0% RM0.00
1.5.4.3 Pipe welding 7 days Luqman 0% RM0.00
1.5.4.4 NDT 3 days Luqman 0% RM0.00
1.5.5 Backfilling 2 days Kennedy 0% RM0.00
1.5.5.1 Screen backfill and remove large rocks 2 days Kennedy 0% RM0.00
1.5.6 Pre-commissioning 7 days Luqman 0% RM0.00
1.5.6.1 Flushing 2 days Luqman 0% RM0.00
1.5.6.2 Blowing 2 days Luqman 0% RM0.00
1.5.6.3 Hydrotest 3 days Luqman 0% RM0.00

2|Page