Professional Documents
Culture Documents
Tip
PRINCE2 defines the term sponsor as the role that is the main
driving force behind a programme or project. The guidance uses the
term commission for the activity or authority to request the project.
The organization commissioning the project will usually provide the
project sponsor.
Definition: Portfolio
The totality of an organizations investment (or segment thereof) in
the changes required to achieve its strategic objectives.
Tip
Varied uses of terminology can be particularly confusing where
multiple best-practice methods are employed within the same
organization, and care must be taken to map or integrate the
methods.
The project approach is the way in which the work of the project is to be
delivered. It may rely on one or more delivery approaches, which are the
specialist approaches used by work packages to create the products.
Typical approaches include:
a waterfall approach where each of the delivery steps to create the
products takes place in sequence (e.g. in a construction project
where requirements gathering and design take place before building
begins) and the product is made available during or at the end of the
project
an agile approach often, but not exclusively, for software
development where requirements gathering, design, coding and
testing all take place iteratively through the project.
There are typically a number of delivery steps within the delivery
approach (e.g. the sprints within an agile approach or steps such as
study, design, build, test, etc. within a waterfall approach).
The application of PRINCE2 can be very different depending on which
delivery approach is used. For further guidance, see sections 9.3 and
16.5.
Key message
PRINCE2 Agile regards agile as a family of behaviours, concepts,
frameworks and techniques. For more information about using agile
and PRINCE2 together, see PRINCE2 Agile (AXELOS, 2015).
The traditional approach to measuring time, cost and quality may still
have its place but it does not necessarily tell the whole story. The best
way to summarize the project status at a point in time is to identify key
performance indicators (KPIs).
When designing KPIs, a balance should be struck between qualitative
and quantitative measures, leading and lagging indicators, and project
inputs and outputs. The number of KPIs should be balanced to create
only information that is necessary and sufficient.
Key message
Objectives are what the project needs to achieve, whereas KPIs are
the measures that indicate whether or not progress is being made
towards achieving the objectives.
Leading indicators
Measure progress towards events, and allow management to track
whether it is on course to achieve the expected performance. An
example would be the persistent failure of a supplier to meet quality
requirements early in the project.
The KPIs should be aligned with the quality expectations and
acceptance criteria defined in the project product description, and the
project tolerances (time, cost, quality, scope, benefits and risk) defined in
the PID.
One way to show project progress is through a project dashboard that
uses graphical representations such as pie charts and histograms to
display the status and trends of performance indicators. These can show
the status for quantitative KPIs and are easy to understand by relevant
stakeholders at all levels.