DAILY ACTIVITY REPORT (MEC

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B
1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE


BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL
PRESSURE PART

ROTATING EQUIPMENTS

2 BOILER & ESP

HOT AIR DUCTING

COLD AIR DUCTING


FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP
TG TO BOILER INTERCONNECTION

RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE


COMPRESSOR HOUSE

3 LP PIPING FIRE FIGHTING SYSTEM

LDO SYSTEM

PIPE RACK
FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS

DECK RAILING WORK.

STRUCTURAL
TURBINE

TURBOGENERATOR

5 TG BUILDING
CONDENSER

AUXILLARIES

FABRICATION & ERECTION OF PIPING

LUBE OIL SYSTEM


AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL

EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 28
(HAZEMAG)
2 THERMAX 205
3 GPR 22
4 APT 21
5 SUVENDU SAHU 6
JOSEPH
6 12
CONSTRUCTIONS

7 ION EXCHANGE 4
REPORT (MECHANICAL- CPP) DATE-07.10.13
ACTIVITY AT SITE

Erection of feeder breaker platform assembly in progress. .

Sheeting work & Final welding completed .

Erection of diagonal beams connecting main columns


started & is in progress.Rework on the main columns of
Transfer Tower-2 completed . Fabrication & welding of
staircase column completed. Alignment work completed
and welding in progress. Tie members of Main Column
structures being erected. Rework on the foundation is in
progress.

Column grouting work completed.


Erection & Welding of handrailing is in progress. Grouting
of all the columns completed.

Foundation work 3B is in progress. Erection of gallery of


3A completed.

Erection of bottom section of 4 nos of Columns of TR-6


was completed. Erection of tie beam of TR-6 is in
process.Erection of 2 column of TR-5 completed.

Assembly work of Structures & final welding completed.

Casting of half portion of 17.0 M slab completed.


Final painting work in progress.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation work at SA FAN duct is in progress.Insulation of


outlet duct of ESP connecting to ID FAN is in progress.
Insulation of remaining pipes in furnace is in
progress.Insulation of PA duct started. Insulation of by
pass ducts from BAC started.

No activity

Final painting work in progress. Erection of monorail


support structure & monorail for ID FAN completed &
welding is in progress. Assembly of monorail support
structure & monorail for PA FAN is in progress.
Fixing of net in pent house for insulation. Welding of
supporting structures in progress. Erection of steam vent
support completed. Erection & welding of IBD Vent
completed. Refractory work in furnace zone started.

Erection of ID FAN-3 completed & alignment is in progress.


ID FAN-4 foundation modification completed & erection of
its fan casing is in progress. Erection & alignment of rotor
of PA FAN-3 & 4 completed. Erection of rotor of SA FAN-3
& SA FAN-4 completed & alingnment is in progress.

Erection & welding of PA Duct connecting to windbox


completed . Ducting from PA line to MDC is in
progress.Ducting from PA AIR line to Wind box is in
progress .Erection of PA FAN to APH connecting duct
completed & final welding is in progress. Erection of duct
connecting APH to ESP completed & welding started.

Erection & welding of secondary air duct fitting work in


progress .
Refractory work inside furnace zone started.Welding work
at ID FAN ducting in progress. Erection of economiser
casing completed & Welding of economiser casing
completed.

MDC welding in progress. Erection & welding of MDC


Bypass to ash seperator completed. Fixing of ceramic
cyclones pipes in MDC completed.Erection of MDC bypass
line taken up. Erection of air slide in MDC is in progress.

Insulation work to be taken up.

Assembly of pent house structure is in progress. Emitting


electrode erection completed. Assembly & welding of
1st,3rd fields Hopper completed. Erection of 2nd & 4th
field hopper completed final welding of hopper is in
progress. Erection of chequered plates on the roof
completed.Pent house roof sheeting work is in progress.
Fabrication of Connecting walkway is in progress. fixing of
anchor plates on TG building for walkway is in progress.

Erection of pump started under the supervision of mather


&platt Engineers.

No activity

Erection of cooling water pump(CW) base frame


completed. Fabrication of reducer for cooling water inlet is
in progress. Positioning of monorail beam inside pump
house is in progress.

No activity as monitoring basin Civil work yet to start.


Erection of pipe rack support connecting to main pipe rack
completed. Fabrication of Pipelines in progress. Erection
of compresed air pipe near boiler is in progress & doubling
of pipes on pipe rack is under process.

Fire fighting pumps have reached transporters


Godown.GPR informed and freight clearance by GPR is
awaited

Civil foundation work has started.

Fabrication of remaining cable rack completed & erection


is in progress. Final welding of pipe rack connecting beams
completed. Fabrication of columns & connecting beam for
pipe rack connecting from main pipe rack to DM Plant
completed.
Wrapping coating of 1400NB Pipes for CW line is under
progress. Assembly &welding of 1400 NB pipe near
cooling tower is in progress.Fabrication of bend for ACW
line completed & erection is in progress. Alignment of
1400NB pipe near cooling tower completed final welding
is in progress. Fabrication & erection of 80 NB DM make
up line is in progress.

All materials shited close to Cooling Tower

No activity

No activity

Railing work at staircase completed .

Fixing of handrailing in staircase is in progress. Erection &


final welding of head room for staircase completed. Roof
sheeting of staircase head room completed & side
sheeting to start.
Shifting of turbine assembly materials to the TG Deck is in
progress. TG Sole plate placed on TG Deck. Turbine
exhaust hood erected in position & final welding with
condenser neck to complete. Grinding and Blue matching
of generator front & rear bearing pedestal completed.
Erection of lower casing of high pressure zone completed
& alignment processis in progress .Placing of packing
plates under turbine sole plate was done.

Insertion of generator rotor &fixing it in position was


completed with proper supervision of BHEL
Representatives.

No activity

No activity

Fabrication of boiler feed pump delivery line in progress.


Fabrication & assembly of pipe connecting condensate
float tank from 15.5 M Floor is in progress.

Fabrication & Erection of lube oil pipe line & pipe supports
is in progress.
Insulation work of 10.5 M control room roof completed.
Erection of AC duct & rapping of insulation is in progress.

Final welding is in progress & fixing of gratings completed.


Fixing of Handrailing work is in progress.

No activity

No activity

No activity

Completed

Erection of agitator pump with its assembly in acid


preparation tanks is in progress.Assembly of pipes in MGF
near cooling tower is in progress.Erection of level gauge
on DM tank-1 was completed.Erection of pump in
nutrilization pit will be completed.
Pipe connecting sludge transfer pump in
progress.Fabrication & erection of connecting pipe from
raw water to clarifier taken up.

Erection of purlins completed & levelling completed.


Fixing of flanges to puddle pipes in acid preparation tank
completed.

No activity
DATE-07.10.13
PLANNED FOR REMARK
TOMORROW

Hoppers, railings & chutes for feeder


Same to continue breaker awaited at site. Party has been
followed up.

No activity Transfer Chutes awaited at Site

Same to continue

Follow up on for Short Post and


stringers for inclined ramp.
Welding of handrailing will be Idler frames & Idler not received at
coninued. site.

Civil foundation work yet to be


completed

Trussel fabrication completed & gallery


to be received.party not despatching
Erection of connecting beams further materials despite of repeated
of TR-6 to continue. Erection of reminders. Rigorous followup required
TR-5 to continue. as party is not able to provide any
evidence of work in progress.

Erection work to start after


transfer house -2 erection
completion.

Civil work to continue. Civil work yet to be completed


All fabrication scraps being cut
for use & house keeping work
to continue. Painting work to
continue.
Same to continue

Same to continue
welding of supporting
structures for pipes to Refractory work started.
continue. Refractory work to
continue.

Same to continue

Balance Erection work awaiting


Same to continue completion of fan foundation.

Same to continue
Same to continue

Same to continue

Same to continue
Same to continue

Erection work to continue.

No activity

Erection of monorail beams to Alignment of base frame to be taken


start. after erection of suction line to pump.
Final Alignment pipe rack
support connecting to main
pipe rack & erection of
connecting beam Pipe fittings awaited at site.
completed.Erection of
compressed air line in pipe
rack to continue.

Cables & conduits of fire sensors at TG


Fixing of Fire Sensor Cables Building 10.5M control room roof have
and Conduits to continue.
reached Site

Civil foundation work


Same to continue started.fabricated tank received at
site.

Erection & welding of cable


rack supports to be continued.
Erection of columns for DM
plant.
Same to continue

Civil work yet to be completed &


mobilisation to be started by
Same to continue Paltech.Paltech to mobilise site by
15/9/13.

Shifting to continue same as above

Shifting to continue same as above

West side railing work of cooling tower


staircase to be taken up after
completion of deck railing.

Fixing of handrailing to
continue.
Erection Work In progress with
Same to Continue. supervision of BHEL Representatives.

Generator rotor insertion to


start.

No activity

All other available equipments have


No activity been placed in position.

Approval given by IBR for all pressure


No activity line erection & welding.

Same to continue
Materials indented for supply of
Same to continue cooling water to A.C.Units

Handrailing work to continued.

No activity

Pipe assembly work to be


continued. Erection of pipe
support inside DM plant to
start.
Same to Continue

No activity