Professional Documents
Culture Documents
D
ue to the combined actions of vibration with pitting cor- were found to be leaking. The tube sections that had separated
rosion tube failure occurred by a mechanism known as were used to perform fractography.
corrosion fatigue. Vibration on its own should not cause The tubes were also split longitudinally in halves to view
any mechanical problems provided it is below the material fatigue the inside surfaces and to determine the extent of pitting dam-
limit. Case histories are presented that describe a variety of flow- age (Fig. 1). Visual observation of the broken piece revealed
induced vibration-related failures in tubular heat exchangers. small pits on the inside surface. Some pits were visible on the
outside surface as well. The tube exterior also had indicated
Introduction. Many types of heat exchanger failures are ran- baffle marks as can be clearly seen in Fig. 2. A spark emission
domly faced in the petrochemical, chemical, utility, engergy and spectrometer was used to identify the tube alloy composition
petroleum industries.1 Some common failures in heat exchangers and it was found to conform to the SA 214 tube specification.
are: assembly errors, manufacturing defects, improper design, An optical macrograph of the inner surface revealed corrosion
pipe and tubing imperfections, welding,2 fabrication,3 improper in progress. Pits were clearly visible after cleaning the surface as
materials, improper operating conditions, pitting, stress-corrosion can be seen in Fig. 3.
cracking,4 corrosion fatigue, thermal fatigue,5 general corrosion, Further observation of the fracture surface revealed two pits
crevice corrosion,6 design errors, fouling,7 selective leaching/ that were found at the origin of a fatigue crack. Fig. 4 clearly
dealloying8 and erosion corrosion.9 This article will constrict shows two macrographs showing two pits and the fracture beach
the readers to one failure phenomenon in heat exchangers that is
flow-induced fatigue. TABLE 1. Heat-exchanger data
Case 1. The cooler has been in service for at least six years. Shell side Tube side
The earliest leak was recorded after only two years in service Operating pressure, bar 4.5 37.7
and was plugged. The tube side did not reveal any signs of cor-
Operating temp., C 38/44 90/45
rosion. Shell-side inspection could not be performed due to the
fact that this is a fixed-head heat exchanger. Tube leakage was Material SA516-60 SA214 ERW tube
again suspected within three weeks after the repairs. Recently, Service fluid Fresh cooling water Hydrocarbons
it was noticed that there was a considerable rise in the cooling
water pipeline skin temperature connected to the cooler. Skin Tube O.D., mm 19.05
temperatures of both the inlet and outlet pipeline surfaces were Tube length, m 6.0
found to be the same. In addition, it was also observed that HE and tube configuration Horizontal and straight tubes
cooling water flow was blocked by increased hydrocarbon leak-
age into the shell side. During shutdown, the heat-exchanger
tubes were replaced with seamless SA 179 and baffle material
remained typical carbon steel. The inspection team managed
to perform magnetic flux leakage (MFL) on the heat-exchanger
tubing. Major affected tubes were located immediately at the
hydrocarbon inlet as can be seen from MFL results (Fig. 1). The
heat-exchanger operating parameters and relevant tube informa-
tion are provided in Table 1.
marks indicating fatigue. The pits did not appear to be deep. Fig.
5 shows optical micrographs in the etched condition. No trans-
granular, intergranular or grain abnormality can be observed.
Industrial Videoscope
Water-Jacketed Injector
for High-Temperature
Applications
Computational Fluid
Dynamics (CFD) Manufacturing quality and flexibility.
Need a simple quill or multi-nozzle injector? Insertion length of a
few inches or several feet? 25# or 2500# class flange? High-pressure,
high-temperature and/or corrosion-resistant construction? Special
design features like a water-jacket, air purge or easy retraction for
maintenance? Tell us what you need and well design and manufacture
to your specifications and meet B31.1, B33.3 and CRN (Canadian
Registration Number) requirements.
Design validation with process modeling.
Let us simulate the injection environment to identify potential
problems. We can model gas flow, droplet trajectory and velocity,
atomization, heat transfer, thermal stresses, vibration and more
to ensure optimal performance.
CFD shows the change in drop size based
on nozzle placement in the duct.
D32 Proven track record.
(m) Weve manufactured hundreds of injectors for water wash, slurry
220 backflush, feed and additive injection, SNCR and SCR NOx control,
desuperheating and more. Customers include Jacobs Engineering,
Foster Wheeler Corp, Shaw Group, Conoco Phillips Co, Shell, Valero
165 Nozzle spraying
Z = 0.6 m in-line with duct and dozens more.
Emission impos
30
I MAY 2010 HYDROCARBON
www.hoerbiger.com
PROCESSING
MAINTENANCE/RELIABILITY SPECIALREPORT
tion; while the tubes at the upper location are not prevented from
vibration like the lower tubes. Fig. 6 shows a 3D image and FE
analysis to establish a rationale of the situation.
These findings presented were supported by the IRIS test
performed. Their conclusive finding was that the upper tubes
had suffered the most (Fig. 7). This, in itself, had supported the
FIG. 7 IRIS results showing the affected tube locations.
proposed finding of the failed tube locations. This investigation
instigated plant personnel to review the heat exchanger and ones
of similar design.
Due to process requirements, other than materials, the design was
Case 2. The heat exchanger in this case (Fig. 8) has gone through changed to being horizontal with duplex stainless-steel tube.
design changes since its commissioning 20 years ago, this is because Since the process is not corrosive, its inspection was set to low.
of plant expansion and increased process demands. Only six years Still, for the first time one of them was inspected and cleaned. The
ago, the heat exchanger was vertical with cupper nickel tubes. original standby was placed in service in its place. After being in
If not:
sible.
Try HOERBIGERs new BCD packing ring
combining high sealing efficiency with
extended lifetime.
service for about two years to date, it was taken out and cleaned
using a novel method of hydrokinetic hydrojetting. While per-
H2O Failed tube and H2O
location of failure forming the cleaning, the top row (fifth tube from the north) at
the gas inlet had leaked. Almost at the same time, other coolers
installed in other parts of the plant had also leaked. Cooler inspec-
tion indicated a leak from one tube, again in the top row, but this
time the fifth tube from the right in the top row. This tube was
Cycle plugged and seal welded at both ends and the cooler was placed
Cycle gas
gas back in service. The phenomenon is that both units failed in the
16.756 m
same locations; right beneath the second baffle plate.
Material: Tube: duplex (2205) SS-SA-789-S31803
Shell-baffels: Carbon steel
FIG. 8 Schematics of the heat exchanger in question showing the Process medium: Shell-water
location of failure.
Tube-cycle gas
Time-in-service: 20 yearsHE setup was vertical and the
tube material was cupper nickel. From
2000 to present, HE setup horizontal and
tube material is duplex SS-2205.
Shell: Carbon steel.
Setup/number of tubes/length: horizontal-one pass / 2.040
tubes, 1.6764 mm.
FIG. 10 Tube showing failure in the second baffle plate from the
cycle gas outlet.
32
I MAY 2010 HYDROCARBON PROCESSING
MAINTENANCE/RELIABILITY SPECIALREPORT
apparent in the region exactly under the second baffle plate. Figs. Al-Anizi, Erosion in the tube entrance region of an air-cooled heat exchanger,
International Journal of Impact Engineering, V. 32, n. 9, September 2006, p. 1440.
9, 10 and 11 clearly show the phenomena. Fig. 12 shows photos
of the affected section and a view of the inner surface indicating
no sign of corrosion. Dr. Ali Babakr has served as a Senior Corrosion Engineer cum
Failure Analysis Advisor for Saudi Basic Industries Corporation
Discussion. There is no doubt that the failure was the result (SABIC), Jubail, Saudi Arabia since 2008. Currently, he serves as a
Consultant for an Engineering firm in the USA. He holds PhD and
of thinning induced by movement/vibration. The movement/ MS degrees in Metallurgy from the University of Idaho, and B.S.
vibration was the result of the water inlet flow. A failure scenario Materials Chemistry from the Huston-Tillotson University, Austin, Texas. He also has
can be proposed: interest in semiconductors and magnetic materials manufacture and applications.
Excessive inlet flow created movement of the upper-right He has authored several papers to address the mitigation of corrosion and other
materials degradation problems. Email: alibabakr@yahoo.com
tubes. Tube movement was excited by the space that already exists
between the tubes and the baffle plate. The tube movement action
resulted in localized tube thinning. The reason why this particular Toyin Ashiru obtained his Ph.D. in industrial metallurgy from
location was the most affected was because water was directed first the University of Birmingham, UK; and B.Sc. (honors) in materials
to these locations by the impingement plate. science from the University of Sussex, UK. He has about 25 years
This was not evident while in operation. The failure took place of teaching, research and industrial experiences in corrosion and
metallurgy. Currently, Dr. Ashiru is senior staff engineer in the mate-
when hydrokinetic hydrojetting was performed, that particular rial and corrosion section of SABIC Technology Center, Jubail. Dr. Ashiru has patents
location under the baffle plate was so thinned that it could not on processes he developed for mitigating corrosion-related problems. He published
handle the pressure during cleaning. Indicative of that is the more than 100 papers in learned journals and conference proceedings. Dr. Ashiru is
failure shape. The burst is to the outside rather than inside. Since a member of various professional associations and has served as the editor-in-chief
or as an editorial board member of some technical journals.
this is a flow-induced failure, the most affected tube sites will be
around the upper-right and left locations.
Christian van der Westhuizen has more than 26 years of industrial experi-
It seems that the plant(s) demand had increased accumulating ence mainly focused in the petrochemical industry. He managed his own metallurgical
the load on these. The most evident approach to minimizing this consulting company in South Africa and afterwards worked for companies in Saudi
problem is by reducing cooling water flowrate. This in turn will Arabia as well as the United Kingdom. Mr. van der Westhuizens experience lies mainly
jeopardize plant demand. Hence, it is empirical to accommodate in failure analysis, welding, corrosion mitigation and material selection. At present he is
the company metallurgist for Davy Process Technology in London and is a professionally
this problem by unit redesign to minimize the effect of cooling registered chartered engineer as well as chartered scientist in the UK. Mr. van der West-
water inlet. It would be impractical to only address the space huizen has written over 15 papers and presented them at various international confer-
preset in the baffle plate. To eliminate flow-induced vibration, a ences and has been involved as chairman is several technology exchange meetings.
reduction in the flow is vital for the current situation. In addition,
it would not be feasible to change tube metallurgy since the failure
is not related to material compatibility.
Tentative conclusions:
Thinning was the result of increased flowrates.
The failures were due to flow-induced vibration that led to MIST ELIMINATORSU
-i`i>`ix
i>viiiVii}ii}>`v>LV>}i>
LITERATURE CITED
ii`iv>Vii
1 Metals handbok. Fatigue Failures, vol. 10, 8th ed., ASM International. 1975, RANDOM PACKINGSU>}iivVi`
>`>V}V`}i>i`}>`>``i
p. 95.
i>V>`>V>ii>>>>Liii
2
>vii}iVii`
Otegui, J. L. and P. G. Fazzini, Failure analysis of tubetubesheet welds in
cracked gas heat exchangers, Engineering Failure Analysis V. 11, n. 6, INTERNALSU
i]>>```>vv>]
L>}>}>`Li>iV>V}>`
December 2004, p. 903. Li`i >`>}ivVi>v`>]
3 Naumann, F. K. and F. Spies, Boiler tube cracked during bending, ASM >L>`ii>VLLiV
-v>LV>iiVi>>i>>V
failure analysis library, ASM International, Materials Park, Ohio (1996).
4 Pola, A., Gelfi, M., Depero, L. E. and R. Roberti, Study of annealing tem- STRUCTURED PACKINGSUVVvii
i>Vi`>V}Vii`vL
perature effect on stress-corrosion cracking of aluminum brass heat-exchang- 8]x9iV>`}V>>V-ii
-
iV>i}>i`V}]`>}]i>}>`V}
ers tubes by microdiffraction experiments, Engineering Failure Analysis, i/>i
-iVivviVii
V. 15, n. 1, January-March 2008, p. 54. v>
- 8}>i>`}ivvViVi>V}
>LiVi>}v>>v
5 Becker, W. T., Thermal fatigue in a vaporizer handbook of case histories, >V}ii>iVvi`>>t