MERCURY FITTINGS (P) LTD - UNIT 1

NPD Weekly Review HELD ON 03-01-2017 BETWEEN 2.30 PM to 03.30PM


NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 To Follow Resourcing parts of TCL (3 Part No.)

Drawing changesin CUMMINS to be followed for


Part no:
2
S-923 E ( Material issue)
1779903 (Design issue)

3 JK Tyre to be followed for Bussiness VTR

4 Toshiba to be enquired for NPD activity

Timing plan for APQP to be prepared and CAPA to


5 Engg. Team
be done if applicable

9
MERCURY FITTINGS (P) LTD - UNIT 1
NPD Weekly Review HELD ON 03-01-2017 BETWEEN 2.30 PM to 03.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

10

11

12

13

14

15

16

17
MERCURY FITTINGS (P) LTD - UNIT 1
NPD Weekly Review HELD ON 03-01-2017 BETWEEN 2.30 PM to 03.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

18

19

20

21

22

23
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 09-12-2016 BETWEEN 2.30 PM to 06.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS
25 th of every
1 Sales meeting to be conducted Kishore Closed
month

2 Value for customer wise trend Kishore From next month Closed

TATA CUMMINS Elbow drawing issue to be followed


3 Kishore 14.12.16 Open
and Completed

Process and product auidit NC to be addressed to


4 QMS and QMS should follow and close with Target Varun/Ravi 27.12.16 Closed
date

5 In-house rejection value to be verified Ravi 14.12.16 Open

Production plan to be monitored by sales and


6 weekly plan will be released from sales to Kishore 14.12.16 Open
Production by every Friday

7 Remaining slide to be updated Banu 14.12.16 Open

8 Suggestion team to be monitored Velmurugan 14.12.16 Open

Rejection (development part list ) Customer name to


9 Velmurugan 14.12.16 Open
be included
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 09-12-2016 BETWEEN 2.30 PM to 06.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

Existing Cycle time improvement to be verified with


10 Velmurugan/Dhanaraj 27.12.16 Open
NPD

11 Target to be included in auto part developed Dhanaraj 14.12.16 Open

12 Good to b removed in changes within 3 months Dhanaraj 14.12.16 Open

13 Repeated absenteesim to be highlighted Vinodha 14.12.16 Open

SOP parts to be included in presentation make it is


14 Dhanaraj 14.12.16 Open
as 1st Slide

NPD constrain regarding other departments make it


15 Dhanaraj 14.12.16 Open
as last slide

Repeated failure for 3 months from MFI-1 & 2 to be


16 Banu 30.11.16 In-progress
addressed to VTR

17 Setter efficency to be improved Velmurugan 30.11.16 In-progress


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 09-12-2016 BETWEEN 2.30 PM to 06.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

18 Time study for setting hours to be discussed Velmurugan 30.11.16 In-progress

Approved customer drawing to be given before 15th


19 Kishore 15.11.16 In-progress
of month (Part no:3910265)

20 RFQ status to be added in slide Kishore 15.11.16 Open

21 Maintenance cost to be verified Thayanithi 15.11.16 Closed

22 Target to be revised for maintenance cost Thayanithi 15.11.16 Closed

Preventive maintenance target vs actual to be


23 Thayanithi 15.11.16 Closed
added in slide
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 08-11-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Zinc-nickel coating new source to be identified Prabhakar 30.11.16 Not needed

2 Customer wise sales trend Kishore 15.11.16 Closed

3 COPQ value to be added Ravi 15.11.16 Closed

Continual improvement price to be addressed (if


4 All department 15.11.16 Closed
applicable)

Repeated failure for 3 months from MFI-1 & 2 to be


5 Banu 30.11.16 In-progress
addressed to VTR

6 Setter efficency to be improved Velmurugan 30.11.16 In-progress

7 Suggestion scheme to be motivated Varun 30.11.16 Closed

8 Suggeation team to be formed Velmurugan 30.11.16 Closed


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 08-11-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

9 Time study for setting hours to be discussed Velmurugan 30.11.16 In-progress

Approved customer drawing to be given before 15th


10 Kishore 15.11.16 In-progress
of month (Part no:3910265)

11 COPQ value to be corrected (Sales without tax) Velmurugan 15.11.16 Closed

12 NPD slide to be re-checked Dhanaraj 15.11.16 Closed

13 NPD Improvement plan slide to be modified Dhanaraj 15.11.16 Closed

Development part approval status pendind details to


14 Dhanaraj 15.11.16 Closed
be added in slide

15 RFQ status to be added in slide Kishore 15.11.16 Open

16 Maintenance cost to be verified Thayanithi 15.11.16 Open


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 08-11-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

17 Target to be revised for maintenance cost Thayanithi 15.11.16 Open

Preventive maintenance target vs actual to be


18 Thayanithi 15.11.16 Open
added in slide

19 HR Slide 2months to be reviewed Vinodha Next month Closed

24

24

25

26
27
28
29
30
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 14-10-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Management CAPA need to be prepared Kishore 21.10.16 Open

Proper communication between department


2 Kishore/Ravi 21.10.16 Closed
regarding customer complaint

3 Failure need to be included in PPT Banumathy 21.10.16 Closed

4 Supplier rating to be shared with QMS Banumathy 21.10.16 Closed

5 Axis value to be altered to show maximum deflecion Ravi 21.10.16 Closed

Banumathy /
6 No decimal value 21.10.16 Closed
Velmurugan

New part development PPM to be altered and


7 Velmurugan 21.10.16 Closed
analyzed

8 Audit to be planned for process capability Ravi 21.10.16 Open


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 14-10-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

9 Sundramoorthy to be trained Velmurugan 21.10.16 In-progress

10 Target to be fixed for Break down maintenance Thayanithi 21.10.16 Closed

11 Maintenance to be planned for 2nd shift Thayanithi 28.10.16 Closed

12 Maintenance cumulative cost gragh to be prepared Thayanithi 21.10.16 Closed

13 PPAP not approved 1st time graph to be prepared Sudhakar 21.10.16 Closed

14

15

16
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 14-10-2016 BETWEEN 2.00 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

17

18

19
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 13-09-2016 BETWEEN 3.30 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Trend for Ongoing development parts Sudhakar 27..09.16 Closed

2 Trend for Developed parts to Production Sudhakar 27..09.16 Closed

3 Status of 162 position gauge Sudhakar 27..09.16 In-progress

4 Discussion regarding BR7410Z Pocess flow Ravi 27..09.16 Closed

5 Format to be introduced for line stoppage Ravi 27..09.16 In-progress

Pareto chart to be prepared for maintenance cost


6 Thayanathi 27..09.16 Closed
with all the causes clearly

7 Plan vs actual tend for preventive maintenance Thayanathi 27..09.16 Closed

8 MTBF & MTTR to be prepared Thayanathi 27..09.16 Closed


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 13-09-2016 BETWEEN 3.30 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

9 Setting Incomplete to be removed Velmurugan 27..09.16 Closed

10 Card closing to be focused Banu 27..09.16 Open

11 Stalin to be given target Banu 27..09.16 Open

12 Categorywise for top absentees Vinodha 27..09.16 Closed

13 Late coming target to be revised as 24 Vinodha 27..09.16 Closed

14 Late coming to be monitored carefully Vinodha 27..09.16 Closed

15 Discussion regarding house keeping with GM Vinodha 27..09.16 Closed

16 Train the trainers class need to be conucted Vinodha 30.09.16 Closed


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 13-09-2016 BETWEEN 3.30 PM to 05.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

17

18

19
MERCURY FITTINGS (P) LTD - UNIT 1
Management Review HELD ON 30-08-2016 BETWEEN 2.00 PM to 06.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Contigency for special and critical process Velmurugan 15.09.16 Closed

2 QMS CAPA need to be corrected Varun 08.09.16 Closed

Neel Auto & KJ Forging to be added in auto


3 Sudhakar 15.09.16 Open
customer

4 AVTEC Rating to be changed Kishore 08.09.16 Open

5 Discussion with GM regarding COPQ Velmurugan / Ravi 08.09.16 Open

Target to be changed for No. of components newly


6 Sudhakar 08.09.16 Closed
developed

Auto component Cumulative graph need to be


7 Sudhakar 08.09.16 Closed
added

8 Production CAPA need to be altered Velmurugan / Varun 15.09.16 Closed


MERCURY FITTINGS (P) LTD - UNIT 1
Management Review HELD ON 30-08-2016 BETWEEN 2.00 PM to 06.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

Supplier rejection and their intrest towards business


9 Ravi 15.09.16 Open
need to be communicated to MD

10 CAPA for Supplier rejection Ravi 08.09.16 Open

11 To verify the Zero trends Varun 15.09.16 Open

Audit (process,product) Selection details need to be


12 Ravi 08.09.16 Open
addressed

13 Cycle time improvement to be initiated Velmurugan 15.09.16 Open

14 Call out for Maintenance breakdown to be added Thayanithi 08.09.16 Open

15 Overall contigency plan for rain to be prepared Velmurugan / Thayanithi 15.09.16 Open

16 Maintenance cost need to be addressed properly Thayanithi 08.09.16 Open


MERCURY FITTINGS (P) LTD - UNIT 1
Management Review HELD ON 30-08-2016 BETWEEN 2.00 PM to 06.30PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

Method for training the operators need to discuss


17 Velmurugan 15.09.16 Open
with GM

18 Tamil version of policy need to be corrected Varun 15.09.16 Open

19 Maintenance class to be conducted Vinodha 08.09.16 Open


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 20-01-2017 BETWEEN 10.30 AM to 12.00AM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Sheeba alternative to be identified Dhanaraj/Varun Next month Open

2 Ashok Leyland name change to be followed Kishore 25.01.17 closed

3 No. of P.M should not be maintained 100% Thiyanithi closed

12 month data for machine wise breakdown to be


4 Thiyanithi 25.01.17 closed
included

Root cause to be identified for display failure in


5 Thiyanithi 25.01.17 closed
CNC (Discuss with FANUC)

Maintenance cost saving improvement to be


6 Thiyanithi 25.01.17 cloesd
planned

7 Maintenance cost to be verified (More attention) Thiyanithi 25.01.17 closed

8 Continual improvement to be prepared All Department Open

Frequency for process validation to be done twice in


9 Velmurugan 25.01.17 Open
a year
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 20-01-2017 BETWEEN 10.30 AM to 12.00AM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

10 Layer process audit scheme to be planned Velmurugan 25.01.17 Open

11 PPAP approved graph to be altered Dhanaraj 25.01.17 closed

SOP parts to be included in presentation make it is


12 Dhanaraj 14.12.16 closed
as 1st Slide

13 5s Daily score to be implemented Varun 25.01.17 Open

Purchase Presentation should include 2 months


14 Banu 25.01.17 Open
data (Feb presentation)

15

16

17
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 20-01-2017 BETWEEN 10.30 AM to 12.00AM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

18

19

20

21
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 11-04-2017 BETWEEN 2.00 PM to 4.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 MTBF & MTTR Minutes to be verified in graphs Thiyanithi 17.04.17 Open

2 CNC-10 MTBF Value to be re-checked Thiyanithi 17.04.17 Open

3 Breakdown details to be listed for 6 months in MOP slide Thiyanithi 17.04.17 Open

4 Series value to be altered in the presentation Ravi 17.04.17 Open

5 Discuss UOM for COPQ with Ramavallaban Varun/Anbu 17.04.17 Open

6 Card closing to be discussed every week Velmurugan /Banu 17.04.17 Open

7 The Stacker M/C to be Repaired Thiyanithi 20.04.17 Open

8 To Provide Wooden or Plastic Pallet for CNC M/C Thiyanithi 17.04.17 Open

9 Blower M/C To be purchased Thiyanithi 17.04.17 Open


MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 11-04-2017 BETWEEN 2.00 PM to 4.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

10 Sales / HR MOP was not reviewed Kishore / Sudha Next Month Open

11 Sheeba alternative to be identified Dhanaraj/Anbu Next month Open

12 Continual improvement to be prepared All Department Open

13 Frequency for process validation to be done twice in a year Velmurugan 25.01.17 Open

14 Layer process audit scheme to be planned Velmurugan 25.01.17 Open

15 5s Daily score to be implemented Varun/Anbu 25.01.17 Open

Purchase Presentation should include 2 months data (Feb


16 Banu 25.01.17 Open
presentation)

17
MERCURY FITTINGS (P) LTD - UNIT 1
Monthly Review HELD ON 11-04-2017 BETWEEN 2.00 PM to 4.00PM
NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

18

19

20

21
MERCURY FITTINGS (P) LTD - UNIT 1

Monthly Review HELD ON 24-05-2017 BETWEEN 2.00 PM to 5.00PM

NO. AGENDA OF THE MEETING

Sales value Slide to be mentioned whether it is inclusive of


1
Taxes

2 Sales Target to be revised

3 CAPA for 3117053,3121023 Failure

4 Setting time to be Increased

5 Master for Air Gauge to be replaced.

ISO Certificate for Primetech,Precision pro,Laser point to be


6
provided.

7 RFQ Detail vs Committed NPD part status to be provided.

CNC 3 vs CNC 4 Machine history with Breakdown details to be


8
provided.

9 DG & EB Unit to be provided with 12 month details.

10 Customer PPM to be rechecked.

Control Plan focus to be prioritized in Product Audit Non


11
conformity parts.
Meeting regarding customer relationship to be held with MF4
12
noting the importance.

13 Continual Improvement to be Prepared.

14 Recruitment Plan to be revised and Prepared.

15 Overall absentism to be made in No of days.

16 Absentism data's to be corelated.

17 Motiation calendar to be prepared.


18 Frequency for process validation to be done twice in a year

19 Blower M/C To be purchased

20 Card closing to be discussed every week

21
ITTINGS (P) LTD - UNIT 1

24-05-2017 BETWEEN 2.00 PM to 5.00PM

RESPONSIBILITY TARGET DATE STATUS

kishore Next Month Open

Anbu/Seetharam Next Month Open

Kishore 27.05.17 Open

Velmurugan 01.06.17 Open

Ravi 01.06.17 Open

Banumathi 01.06.17 Open

Sudhakar Next Month Open

Dhayanithi Next Month Open

Dhayanithi Next Month Open

Ravi 27.05.17 Open

Sudhakar 01.06.17 Open

Ravi 01.06.17 Open

All Departments Next Month Open

Ganesan Next Month Open

Ganesan Next Month Open

Ganesan 01.06.17 Open

Ganesan 01.06.17 Open


Velmurugan 25.01.17 Open

Thiyanithi 17.04.17 Open

Velmurugan /Banu 17.04.17 Open


MERCURY FITTINGS (P) LTD - UNIT 1

Monthly Review HELD ON 20-06-2017 BETWEEN 2.00 PM to 5.00PM


NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE

Mr.Ganesan - HR Department Absent

Mr. Ravi - Quality Department Absent


Time period to be added in Maintenance Cost
1 Thayanithi 24.6.17
history slide
Month detail in Maintenance cost details
2 Thayanithi 30.06.17
slide to be added
No of new product development approved
3 Thayanithi Next Month
status to be added.
List of pending Npd parts which are yet to
4 Sudhakar 30.06.17
approve to be added.
Contol plan updation details to be provided
5 Sudhakar 30.06.17
( Target/Actual )
6 Control Plan updation to be prioritized. Sudhakar 30.06.17

7 Sales Target to be revised Anbu /Seetharam 30.06.17


May-17 slides which were not updated to be
8 Banumathi 30.06.17
completed .
Delivery performance for May-17 to be
9 Velmurugan 24.6.17
rechecked
Target for Setting rejection to be defined /
10 Velmurugan 30.06.17
Setting rejection to be neglected.
11 Purchase Trend value to be corrected. Banumathi 30.06.17

12 ITR value to be corrected. Banumathi 30.06.17

13 M/C Problem to be discussed Velmurugan 24.6.17

14 Master for Air Gauge to be replaced. Ravi 01.06.17


RFQ Detail vs Committed NPD part status to
15 Sudhakar Next Month
be provided.
Control Plan focus to be prioritized in Product
16 Sudhakar 01.06.17
Audit Non conformity parts.
Meeting regarding customer relationship to be
17 Ravi 01.06.17
held with MF4 noting the importance.
18 Recruitment Plan to be revised and Prepared. Ganesan Next Month
19 Overall absentism to be made in No of days. Ganesan Next Month

20 Absentism data's to be corelated. Ganesan 01.06.17

21 Motivation calendar to be prepared. Ganesan 01.06.17


Frequency for process validation to be done
22 Velmurugan 25.01.17
twice in a year
23 Blower M/C To be purchased Thiyanithi 17.04.17
5.00PM
STATUS

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open

Open
Open

Open

Open

Open

Open
MERCURY FITTINGS (P) LTD - UNIT 1

MANAGEMENT REVIEW HELD ON 24-08-2017 BETWEEN 3.00 PM to 6.00PM

NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Time period to be added in Maintenance Cost history slide Thayanithi 24.6.17 close

1 No of new product development approved status to be added. Sudhakar Next Month close

2 List of pending Npd parts which are yet to approve to be added. Sudhakar 30.06.17 close

3 Contol plan updation details to be provided ( Target/Actual ) Sudhakar 30.06.17 close

4 Control Plan updation to be prioritized. Sudhakar 30.06.17 close

1 Sales Target to be revised without tax Anbu /Seetharam 30.09.17 Open

6 May-17 slides which were not updated to be completed . Banumathi 30.06.17 close

7 Delivery performance for May-17 to be rechecked Velmurugan 24.6.17 close

Target for Setting rejection to be defined / Setting rejection to be


8 Velmurugan 30.06.17 close
neglected.

9 Purchase Trend value to be corrected. Banumathi 30.06.17 close

10 ITR value to be corrected. Banumathi 30.06.17 close

Meeting regarding customer relationship to be held with MF4 noting the


11 Ravi 01.06.17 close
importance.

12 NC to be closed Concerned Dept 02.09.17 Open

APQP to be followed for High volume parts and overview on APQP to be


13 NPD Team 15.09.17 Open
studied

14 Cummins scorecard to be discussed with Deepak Kishore 08.09.17 Open

List for Cusomer satisfaction feedback based on volume to be prepared


15 Kishore 08.09.17 Open
and Analyzed

16 COPQ dtails to be included with shortage of parts. Velmurugan / Ravi 11.09.17 Open

17 Continual Improvement to be prioritized over High volume parts All Dept 30.09.17 Open

18 Frequency for process validation to be done twice in a year Velmurugan 25.01.17 Open

19 Blower M/C To be purchased Thiyanithi 17.04.17 Open


Mercury Fittings Pvt Ltd,. Chennai - 58
Meeting Held on 09.09.17
S.No Points Discussed

Time Plan for Control Plan,Gauges , details & Implementation of SCL to


1
be submitted

Time Plan for Control Plan , Gauges , details &Implementation of TVS


2
to be submitted

Time Plan for Control Plan , Gauges , details &Implementation of Avtec


3
to be submitted

Time Plan for Control Plan, Gauges , details & Implementation of Neel
4
Auto to be submitted

Time Plan for Control Plan , Gauges , details &Implementation of Tata


5
cummins to be submitted

6 Follow up Status to be Reviewed on daily basis

7 Necessary support for Control Plan Implementation to be provided.


Ltd,. Chennai - 58
n 09.09.17
Responsibility Target Date

Gowtham 13.09.17

Prabhakar 13.09.17

Gowtham 13.09.17

Prabhakar 13.09.17

Sudhakar 14.09.17

Anbu / Seetharam 14.09.17

Murugavel / Velmurugan 11.09.17


Review - Minutes of Meeting - 13.09.17
Sl.No Points Discussed Responsibility Target date Status

Time plan to be followed and Displayed on Monthly Review based


1 NPD Team Next Month Open.
on Objective,(Blank - 3 weeks, Forging - 6weeks)

2 Time plan display to be based on Responsibility NPD Team Next Month Open.

3 Diamler Pending Status of NPD parts to be Closely monitored. Sudhakar 19/09/17 Open.

4 Plan vs Actual NPD parts to be reconfigured with actual datas. Sridhar Next Month Open.

5 PPAP FTR data to be corrected Sridhar Next Month Open.

6 Control plan Responsibility assigned to Arasappan to take charge. velmurugan 14.09.17 Open.

7 PPAP VS Start of Production slide to be prepared Effective Sridhar Next Month Open.

Reason for Control plan changes to be communicated to NPD


8 Sundaramoorthy 15/09/17 Open.
Team
MERCURY FITTINGS (P) LTD - UNIT 1

MONTHLY REVIEW HELD ON 11-09-2017 BETWEEN 2.30 PM to 6.00PM

NO. AGENDA OF THE MEETING RESPONSIBILITY TARGET DATE STATUS

1 Sales value (without Tax) new slide to be prepared. Kishore Next Month Open

2 Cum.Sales slide to be altered. Kishore Next Month Open

3 CAPA to be addressed Appropriately and Effectively All Dept 30.09.17 Open

4 Customer wise Trend (plan vs Actuall) to be prepared. Kishore Next Month Open

5 Customer feedback to be received . Kishore 16.09.17 Open

6 Punching to be considered with alternate to Engraving. Velmurugan, Murugavel 5/10/2017 Open

7 Presentation to be submitted to the QMS 2 Days prior to the Meeting All Dept Next Month Open

8 Tool grinding shall be addresssed color based on Grinding frequencies Velmurugan 5/10/2017 Open

9 Setter Effficiency metrics to be discussed Velmurugan 5/10/2017 Open

10 NPD team to Effectively follow PPAP lot rejection. Sridhar / Sudhakar 30.09.17 Open

11 Prod,. Value to look for reliable metrics Velmurugan / EDP 30.09.17 Open

12 Unit 4 Rejection to be accounted for ., Banumathi / Ravi 30.09.17 Open

13 Critical spare list for LMW M/C to be Effectively prepared. Dayanithi 16.09.17 Open

14 Birthday celebration shall be revisit on behalf of Dept Heads. Ganesan 20.09.17 Open

15 Sales Target to be revised without tax Anbu /Seetharam 30.09.17 Open

APQP to be followed for High volume parts and overview on APQP to be


16 NPD Team 15.09.17 Open
studied

17 Cummins scorecard to be discussed with Deepak Kishore 08.09.17 Open

18 Continual Improvement to be prioritized over High volume parts All Dept 30.09.17 Open

19 Frequency for process validation to be done twice in a year Velmurugan 25.01.17 Open

20 Blower M/C To be purchased Thiyanithi 17.04.17 Open


Mercury Fittings Pvt Ltd,. Chennai - 58
ISO/TS 16949 - 2009 Auditor Observation Points Held on 20
S.No Agenda of Audit Points
Ashok Leyland Nissan to rename as Ashok Leyland
1
Wherever required

Discussion to be held with Mr. Vetriselvan of DNV about


2
the transition Scheme and Corporate benefits.

Tata cummins Supplier Quality Manual to be identified if


3
any,.

CSR Requirements to be stringently Followed as per


4
IATF Rule

5 Supplier Audit to be strengthened

Training on Control plan, FMEA and PPAP need to be


6
provided.

7 Process and product Audit to be Dynamically covered

Data collection to be segrerated on basis of Auto and Non


8
Auto Parts.
Customer Complaint Analysis to be made with Escape
9
point of view.

Weekly production plan to be Effectively carried and


10
followed.

Delivery Failures to be prioritized and Effective CAPA to


11
be Implemented

12 Targets for Productivity ,cost and Time to be Effected.

Skill to be Deployed on the basis of Job responsibility


13
Effectively.
Effective calendar to be prepared and list of participant to
14 be defined at the time of Calendar preparation on Need
Identification basis.
Operator Skill to be Addressed and Training to be given
15
based on Production Output.

Special process like Heat Treatment, Plating Auditor


16
competency to be attained by Training.

Core tools Training to be given to Technical Staffs


17
Involved.

Daily Preventive Maintenance to be Followed and


18
reviewed.

19 Tracer Tag to be Effectively Implemented and followed.

Eye Testing Certificate for all Visual Inspection Quality


20
person to be addressed.

Adequate Lighting inall Areas to be Ensured and Lux


21
Meter to be Calibrated.

FG O-ring Assembled parts to be Identified and Shelf


22
Life to be determined .

HR to Determine the process of Recruiting various level


23
Manpower and to be verified with Top Management.

24 Premium Freight charge Data to be Monitored.

D&Q Rating Methodolgy to be studied and various


25
Responsibility to be Allocated for respective Datas.

HR , QMS, Quality and Purchase to undergo Training


26
with new regulation of IATF Standard.

Trailing New supplier data to be evidenced and


27
controlled.

DC data and ERP due date variation in Purchase to be


28
corrected.
29 Supplier selection to be Effectively carried out.

Finished Goods stock to be Corelated with Existing


30
Physical stock Datas.

Permissible Error to be Identified & recorded in External


31
Calibration Certificates.

Manpower to be devised for Control Plan Implementation


32
from Production to NPD.

Gauge and Instruments of Supplier and Customer to be


33
ensured
MSA -Attribute Study Process to be Planned as six month
34
.
All external Instruments Calibration (Manufacture or
35
Lab) to be ensured with the accredation body logo

TS Audit Non Conformity are to be taken the corretion


36
and Corrective Action
Fittings Pvt Ltd,. Chennai - 58
or Observation Points Held on 20 Sep - 22 Sep-17
Responsibility Target Date Status
NPD, QMS, Sales,
03.10.17 Open
Production and Quality

Seetharam / Anbu 13.10.17 Open

Sudhakar 13.10.17 Open

Sudhakar / Ravi 13.10.17 Open

Ravi 20.10.17 Open

Ganesan 14.10.17 Open

Ravi 20.10.17 Open

All Departments 20.10.17 Open

Ravi 20.10.17 Open

C.Velmurugan 13.10.17 Open

B.kishore 3.10.17 Open

Sudhakar 13.10.17 Open

C.Velmurugan / Ganesan 20.10.17 Open


Ganesan 3.10.17 Open

C.Velmurugan / Ganesan 13.10.17 Open

Ganesan 21/11/17 Open

Ganesan 21/11/17 Open

Thiyanithi 3.10.17 Open

Ravi / C.Velmurugan /
3.10.17 Open
Banumathi

Ganesan 3.10.17 Open

Thiyanithi 13.10.17 Open

Sales Team 13.10.17 Open

Ganesan 20.10.17 Open

Banu 3.10.17 Open

Banu 20.10.17 Open

Ganesan 20.10.17 Open

Ravi / Sudhakar / Banu 3.10.17 Open

Banu / EDP 20.10.17 Open


NPD 13.10.17 Open

Sales Team 3.10.17 Open

Ravi/Shankar 13.10.17 Open

NPD 3.10.17 Open

Ravi/Shankar 21/11/17 Open

Ravi/Shankar 3.10.17 Open

Ravi/Shankar 21/11/17 Open

MR 21/11/17 Open
MERCURY FITTINGS UNIT - I
NPD REVIEW HELD ON 04.10.17 BETWEEN 10.00AM TO 11.00 AM
VELMURUGAN .K, SEETHARAM, ANBU, SUDHAKAR,
PARTICIPANTS
PRABAKAR, SRITHAR, GOWTHAM.

NO. POINTS DISCUSSED RESPONSIBILITY TARGET DATE STATUS

Product Development sales Target Fixed as 6%


1 Velmurugan .K - OPEN
Growth

Role & Responsibility of each Team mate to be


2 Seetharam / Sudhakar 17/10/17 OPEN
prepared and Submitted

3 Non moving parts status to be followed. Sudhakar 15/10/17 Open

4 Non moving parts list to be submitted Seetharam 5/10/2017 Closed

Control plan changes to be assigned with


5 responsible person and parts to be ensured as Sudhakar 15/10/17 Open
per control plan while operation.

6 Metrics on weekly objective to be discuused Sudhakar 5/10/2017 Open


Weekly review to be held on Every Wednesday
7 Effectivly.
- - -

Format for Approval of Process change to be


8 prepared
Seetharam 7/10/2017 Closed

9 Training on core tools, matrix to be prepared. Anbu 7/10/2017 Open


MERCURY FITTINGS UNIT - I
NPD REVIEW HELD ON 04.10.17 BETWEEN 11.00AM TO 11.50 AM
VELMURUGAN .K, SEETHARAM, ANBU, VELMURUGAN.
PARTICIPANTS
C, BANUMATHI, RAVI

NO. POINTS DISCUSSED RESPONSIBILITY TARGET DATE STATUS

Rejected part Details to be visually analyzed Velmurugan .C, Ravi,


1 - OPEN
daily Banumathi

Implementation date and venue to be finalized


2 Ravi 7/10/2017 OPEN
for review

Redbin to be Identified seperately for both the


3 Velmurugan, C 15/10/17 Open
production shifts

6
7

9
MERC
URY
FITTIN
GS
UNIT - SALES REVIEW HELD ON 04.10.17 BETWEEN 12.00PM TO 1.00 PM
I
VELMURUGAN .K, SEETHARAM, ANBU,VELMURUGAN.
PARTICIPANTS C, BANUMATHI, RAJESHWARAN, KISHORE,
DEVAPRAKASAM, VENKATACHALAM .

NO. POINTS DISCUSSED RESPONSIBILITY TARGET DATE STATUS

Responsibility for sub contractor follow up to be Velmurugan .K /


1 20/10/17 OPEN
assigned ( To discuss with MD) Banumathi

RAJESHWARAN,
KISHORE,
2 Non active parts list follow up to be done 17/10/17 OPEN
DEVAPRAKASAM,
VENKATACHALAM .

RAJESHWARAN,
KISHORE,
3 Customer visits to be plannned 15/10/17 Open
DEVAPRAKASAM,
VENKATACHALAM .

4 Sales SOP to be followed as stated. All Dept, 5/10/2017 Open

6
7

9
Mercury Fittings Pvt Ltd,. Chennai - 58
Meeting Held on 10.10.17
S.No Points Discussed

Last Month MOM Minitus status to be shown


1
brfore start of review

To be plan weekly Meeting for Subcontractor and


2
supplier

To set the cutoff for forgings in every month of


3
first week of the firm commitement

Manpower shortage to fill full the in production


4
for roller operation

To be train the alternate manpower for critical


5
jobs

Inhouse Rejection to be analyzed and do the


6 action plan for rejection reduction PPM (From
3886 PPM to 1200 PPM)

8 To be Prepare the SOP for Jaws Manufacturing

To be analyse the setting efficience and to


9
improve the production hours

10 Take video complete setting hours

Any lession learn from previous mistakes to


11 show the One point Lession for daily in
Production area
Daily PM to add the chuck bar status in
12
Preventive check list

Production Efficiency to be analyze daily basis


13
for Machine wise

14 Seperatly tracking and reviewed for NPD parts

15 To remove the cost of poor quality

16 To put the rejection and rework cost for part wise

To rise the SPQR for rework and rejection


17
problems for sub contractors

Process to be validate latest For part no:-


18
BFF25/FEROUL

19 Data To be need the power cost interms of sales

20 To be introduce JH pillar activites

21 To workout the power cost saving projects

To collect the CAPA for delivery failure for sub


22
contractors and suppliers
Card closing in card from . T o take action and
23
close the all cards

24 To put the NPD cards are seperately

To take action for customer drawing issue like


25
practically dimension are not meet

To put the effort for last one year pending for


26 waiting of customer feed back and take
necessary action
Need clear data for cost savings for part no:-
27 22343137-C
Ltd,. Chennai - 58
on 10.10.17
Responsibility Target Date status

All dept Month

Banu 14.10.17

Banu Next Month

HR 23.10.17

Velmurugan 23.10.17

Velmurugan 23.10.17

Velmurugan 16.10.17

Velmurugan 23.10.17

Velmurugan 17.10.17

Velmurugan 16.10.17
Thiyanithi 16.10.17

Velmurugan Next Month

Sudhakar /
Next Month
Velmurugan

Velmurugan Next Month

Velmurugan 23.10.17

Ravi/Banu 23.10.17

Ravi/Velmurugan 21.10.17

Thiyanithi 16.10.17

Velmurugan.K/Anbu Next Month

Thiyanithi 23.10.17

Banu 17.10.17
Banu/Velmurugan/R
Next Month
avi

Sudhakar Next Month

Sudhakar 23.10.17

Sudhakar 23.10.17

Sudhakar 23.10.17
Mercury Fittings Pvt Ltd,. Chennai - 58
Meeting Held on 10.10.17
S.No Points Discussed
Last Month MOM Minitus status to be shown
1
brfore start of review

To be plan weekly Meeting for Subcontractor and


2
supplier

To set the cutoff for forgings in every month of


3
first week of the firm commitement

Manpower shortage to fill full the in production


4
for roller operation

To be train the alternate manpower for critical


5
jobs

Inhouse Rejection to be analyzed and do the


6 action plan for rejection reduction PPM (From
3886 PPM to 1200 PPM)

8 To be Prepare the SOP for Jaws Manufacturing

To be analyse the setting efficience and to


9
improve the production hours

10 Take video complete setting hours

Any lession learn from previous mistakes to


11 show the One point Lession for daily in
Production area
Daily PM to add the chuck bar status in
12
Preventive check list

Production Efficiency to be analyze daily basis


13
for Machine wise

14 Seperatly tracking and reviewed for NPD parts

15 To remove the cost of poor quality

16 To put the rejection and rework cost for part wise

To rise the SPQR for rework and rejection


17
problems for sub contractors

Process to be validate latest For part no:-


18
BFF25/FEROUL

19 Data To be need the power cost interms of sales

20 To be introduce JH pillar activites

21 To workout the power cost saving projects

To collect the CAPA for delivery failure for sub


22
contractors and suppliers
Card closing in card from . To take action and
23
close the all cards

24 To put the NPD cards are seperately

To take action for customer drawing issue like


25
practically dimension are not meet

To put the effort for last one year pending for


26 waiting of customer feed back and take
necessary action
Need clear data for cost savings for part no:-
27 22343137-C

Responsibility for sub contractor follow up to be


assigned ( To discuss with MD)

Non active parts list follow up to be done

Customer visits to be plannned

Sales SOP to be followed as stated.

Redbin to be Identified seperately for both the


production shifts
Product Development sales Target Fixed as 6%
Growth
Role & Responsibility of each Team mate to be
prepared and Submitted

Non moving parts status to be followed.

Non moving parts list to be submitted


Control plan changes to be assigned with
responsible person and parts to be ensured as
per control plan while operation.
Metrics on weekly objective to be discuused

Weekly review to be held on Every Wednesday


Effectivly.
Format for Approval of Process change to be
prepared

Training on core tools, matrix to be prepared.


Pvt Ltd,. Chennai - 58
ld on 10.10.17
Responsibility Target Date Status

All dept Month


Closed

Banu 14.10.17
Open

Banu Next Month


Open

HR 23.10.17
Closed

Velmurugan 23.10.17
Open

Velmurugan 23.10.17
on going

Velmurugan 16.10.17
Open

Velmurugan 23.10.17
on going

Velmurugan 17.10.17
Closed

Velmurugan 16.10.17
Open
Thiyanithi 16.10.17
Closed

Velmurugan Next Month


Open

Sudhakar / Velmurugan Next Month


Closed

Velmurugan Next Month


Open

Velmurugan 23.10.17
Closed

Ravi/Banu 23.10.17
Closed

Ravi/Velmurugan 21.10.17
Closed

Thiyanithi closed
Closed

Velmurugan.K/Anbu Next Month


Open

Thiyanithi 23.10.17
Open

Banu 17.10.17
Open
Banu/Velmurugan/Ravi Next Month
Open

Sudhakar Next Month


Closed

Sudhakar 23.10.17
Open

Sudhakar 23.10.17
open

Sudhakar 23.10.17
Closed
Velmurugan .K /
20/10/17 OPEN
Banumathi
RAJESHWARAN,
KISHORE,
17/10/17 OPEN
DEVAPRAKASAM,
VENKATACHALAM .

RAJESHWARAN,
KISHORE,
15/10/17 Open
DEVAPRAKASAM,
VENKATACHALAM .

All Dept, 5/10/2017 Open

Velmurugan, C 15/10/17 Open

Velmurugan .K - OPEN
Seetharam / Sudhakar 17/10/17 OPEN

Sudhakar 15/10/17 Open

Seetharam 5/10/2017 Closed

Sudhakar 15/10/17 Open

Sudhakar 5/10/2017 Open

- - -

Seetharam 7/10/2017 Closed

Anbu 7/10/2017 Closed


Mercury Fittings Pvt Ltd,. Chennai - 58
NPD Review Meeting Held on 20.10.17 at 2.30PM to 5.00 PM
S.No Points Discussed Responsibility Target Date

Resposibility and Target on development parts to


1 Sudhakar Month
be assigned.

Plan, revisit date and completion date to be


2 Sudhakar 14.10.17
mentioned in the Development status

Customer expected date to be included in part


3 Sudhakar Next Month
Development status slide

Development status tracking Format to be


4 Sudhakar 23.10.17
upgraded from Murugavel

PPAP FTR slide to include Plan ,completion and


5 Sudhakar 23.10.17
PSW status .

Development progress tracking to identify from


6 k.Velmurugan 23.10.17
the base of feasibility commitment.

Active part list comparision to be provided with


7 Sudhakar 16.10.17
respect to Non moving and Development parts.
Status

Close

Close

Close

Close

Close

open

on going
Mercury Fittings Pvt Ltd,. Chennai - 58
Sales Review Meeting Held on 21.10.17
S.No Points Discussed
MF Unit 4 commitment and Quantity to be
1
revised and allocate to Unit 3

List of Cards waiting for Inspection to be


2
submitted

3 commitment to receive from MF 3

MOQ for Auto parts to be planned to 500No's


4
based on volume
Ltd,. Chennai - 58
g Held on 21.10.17
Responsibility Target Date Satus

Rajeswaran Month
Open

Anbu 14.10.17
Open

Murugavel Next Month


close
Kishore ,
Rajeshwaran,
23.10.17
Devaprakasam,
Venkatachalam Open
Mercury Fittings Pvt Ltd,. Chennai - 58
NPD Review Meeting Held on 17.11.17 at 2.30PM to 6.00 PM
S.No Points Discussed Responsibility Target Date

With Tax Slide to be remove from our Mop


1 kishore Next Month
Presentation

To Analyse the delivery failure based Auto and


2 kishore Next Month
Non auto customer in using pie chart

To Form the CFT team regarding NAPL Delivery


3 Velmurugan.K 25.11.17
and quality issue.

One day before to inform what customer


4 Suntharamoorthi Next Month
requirements,From PPC to Production supervisor

Any development Parts monitoring to meet the


target after to sign the CFT team in Target Next NPD part
5 CFT team
productivity,Processes Capability and cost form devolopement
(F/7.1/10)
Next month Manpower requirement to be
6 communicate the Personal Dept before 25th of Velmurugan.C 25.11.17
every month based on Plant capacity
To Communicate the Mr.Paranthaman to attend
7 the next week Sales review meeting due to Rajeshwar/Banu 20.11.17
forging issue

8 To update the MFI-2 delivery performance in ppt Banu 25.11.17

9 To take the Action for card closing Banu 30.11.17

Velumurugan.K
10 To finailized the weekly purchase review 23.11.17
& Banu

Velmurugan.C/Ravi/
11 To address the rejection in all stages Next Month
Banu

Slide to change the term for supplier to


12 Banu Next Month
subcontractor

Requirement Plan Vs Actul to be update the


13 Sudha 28.11.17
actual data