CHECK LIST FOR MV PANELS

LOCATION: Panel Name

GRID REFERENCE: Panel detail


Contract No:
DRAWING NO.: Incomer Breaker rating:

REFERENCE IRE NO.: Type:


Date :

REFERENCE ITP NO.: Q11017-0100D-LPS-STA-PK2-QMS-ITP-00003

Approved
No. Activities Remarks
YES NO
A. PRE INSTALLATION INSPECTION
1 Installation Checks As per ITP & QCS 2014 S2P2 clause 2.1.4
2 Ensure drawings were approved and proceed to start the works.
Ensure all materials used at site have material submittal approval and inspected and
3
approved by the Engineer Thru Material Inspection Request.
B INSTALLATION CHECK LIST
1 Check the works area is clean and safe
2 Check the nameplate detail of individual feeders and check with SLD.
3 Check the panel location as per drawing.
5 Check visually any damage in Panels and Individual feeders
6 Check IN ROOM - clearance between other electrical panels is as per QCS
provision is sufficient space to allow for doors to open fully without fouling other items of
7
equipment or other open doors
Check no components shall be located within the assembly at a height greater than
8
2000 mm or less than 500 mm above finished floor level
9 check the control supply MCB breakers / fuses rating match with drawing
10 Check neutral for control supply removable and properly tighted
11 Check inside panels, bus bar chambers are free from debris, clear from loose bolts, nuts
12 Check the size of bus bars are as per drawing
Ensure size neutral bar is to be continuous through all sections. Neutral bus is to be
13
insulated and separate from earth bus
Ensure Earth bus is to extend full length of board, firmly fixed to each section in
14
accordance with the Regulations and Standards.
15 Main incomer is provided with surge protectors as per QGEWC specification
16 Check mechanical interlocks are provided( if applicable)
17 Check incomer/ out doing breakers rating are as per drawing
Check the door handles / breaker handles are free from damage and check keys are
18
provided for feeders
19 Check mechanical operation(ON/OFF ) of breakers are operating properly.
Check ACBs are interchangeable ( for withdrawable breaker have same rating + same
20
phases)
21 Check ACB/VCB are easy to drawab from cradle
23 Check all the relays /meters are mounted properly with out loose connection.
24 Check the panel earthing properly connected to main earth
Ensure the panel bus bar interconnections between the feeders with proper tightening
25
and marked.
Ensure the panel interconnections between the comportments with properly bolted
26
and gasket provided
27 Check Phase to Phase & Phase to earth clearances in the main bus bar.
28 Check type of cable entry ( top entry / bottom entry )
29 Ensure cable load shouldnt be dumped on gland plate of panel
30 Check the cable glands are properly earthed using proper lugs.
31 Check all dummy gland hole are closed.
32 Check spare terminal connectors are provided.
33 Check the cable feruling in control cable.
34 Check all the terminals are tightened properly
35 Check the panel earth link provided between compartments.
36 Check CT secondary are properly shorted
37 Check all doors are properly earthed using flexible cable.
38 Check the tightness of all control wires, terminal blocks
39 Check compartment provided with a heater with proper switch
40 Check the panel identification for I/C & O/G feeders. .
Check Doors and covers giving access to potentially live conductors provided
41
with prominent warning labels, in English and Arabic
42 Ensure identification to be provided for all meters lamps, relays.
43 Ensure live parts are properly covered and cannot access.
44 Work area is clean and proper Housekeeping is maintained.

Remarks _________________________________________________________________________
Sub
ORGANIZATION L&P GSIC JV KEO
contractor
NAME
SIGNATURE
DATE
Doc No: Q11017-0100D-LPS-GEN-PKS-QMS-FRM-00047A
CHECK LIST FOR ELECTRICAL PANELS - MCC PANEL

LOCATION: MCC Panel No

GRID REFERENCE: Panel detail


Contract No:
DRAWING NO.: Incomer Breaker rating:

REFERENCE IRE NO.: Type:


Date :

REFERENCE ITP NO.: Q11017-0100D-LPS-STA-PK2-QMS-ITP-00003

Approved
No. Activities Remarks
YES NO
A. PRE INSTALLATION INSPECTION
1 Installation Checks As per ITP & QCS 2014 S2P2 clause 2.1.4
2 Ensure drawings were approved and proceed to start the works.
Ensure all materials used at site have material submittal approval and inspected and
3
approved by the Engineer Thru Material Inspection Request.
B INSTALLATION CHECK LIST
1 Check the works area is clean and safe
2 Check the nameplate detail of individual feeders and check with SLD.
3 Check the panel location as per drawing.
5 Check visually any damage in Panels and Individual feeders
6 Check IN ROOM - clearance between other electrical panels is as per QCS
provision is sufficient space to allow for doors to open fully without fouling other items of
7
equipment or other open doors
Check no components shall be located within the assembly at a height greater than
8
2000 mm or less than 500 mm above finished floor level
9 check the control supply MCB breakers / fuses rating match with drawing
10 Check neutral for control supply removable and properly tighted
11 Check inside panels, bus bar chambers are free from debris, clear from loose bolts, nuts
12 Check the size of bus bars are as per drawing
Ensure size neutral bar is to be continuous through all sections. Neutral bus is to be
13
insulated and separate from earth bus
Ensure Earth bus is to extend full length of board, firmly fixed to each section in
14
accordance with the Regulations and Standards.
15 Main incomer is provided with surge protectors as per QGEWC specification
16 Check mechanical interlocks are provided( if applicable)
17 Check incomer/ out doing breakers rating are as per drawing
Check the door handles / breaker handles are free from damage and check keys are
18
provided for feeders
19 Check mechanical operation(ON/OFF ) of breakers are operating properly.
Check ACBs are interchangeable ( for withdrawable breaker have same rating + same
20
phases)
21 Check ACB/VCB are easy to drawab from cradle
22 Check the type of starter is correct as per drawing
23 Check OLR setting is correct
24 Ensure OUT GOING feeders having proper rating of terminal blocks
25 Check the control cable wiring (for starters ) is proeper with dressing .
26 Check the gland pate cutout location match with cable entry.
27 Check all the relays /meters are mounted properly with out loose connection.
28 Check the panel earthing properly connected to main earth
Ensure the panel bus bar interconnections between the feeders with proper tightening
29
and marked.
Ensure the panel interconnections between the comportments with properly bolted
30
and gasket provided
31 Check Phase to Phase & Phase to earth clearances in the main bus bar.
32 Ensure cable load shouldnt be dumped on gland plate of panel
33 Check the cable glands are properly earthed using proper lugs.
34 Check all dummy gland hole are closed.
35 Check spare terminal connectors are provided.
36 Check the cable feruling in control cable.
37 Check all the terminals are tightened properly
38 Check the panel earth link provided between compartments.
39 Check CT secondary are properly shorted
40 Check all doors are properly earthed using flexible cable.
41 Check the tightness of all control wires, terminal blocks
42 Check compartment provided with a heater with proper switch
43 Check the panel identification for I/C & O/G feeders. .
Check Doors and covers giving access to potentially live conductors provided
44
with prominent warning labels, in English and Arabic
45 Ensure identification to be provided for all meters lamps, relays.
46 Ensure live parts are properly covered and cannot access.
47 Work area is clean and proper Housekeeping is maintained.

Remarks _________________________________________________________________________
Sub
ORGANIZATION L&P GSIC JV KEO
contractor
NAME
SIGNATURE
DATE
Doc No: Q11017-0100D-LPS-GEN-PKS-QMS-FRM-00047B
CHECK LIST FOR VFD

LOCATION: VFD details

GRID REFERENCE: Income From


Contract No:
DRAWING NO.: Service Area

REFERENCE IRE NO.:


Date :

REFERENCE ITP NO.: Q11017-0100D-LPS-STA-PK2-QMS-ITP-00003

Approved
No. Activities Remarks
YES NO
A. PRE INSTALLATION INSPECTION
1 Installation Checks As per ITP & QCS 2014 S2P2 clause 2.1.4
2 Ensure drawings were approved and proceed to start the works.
Ensure all materials used at site have material submittal approval and inspected and
3
approved by the Engineer Thru Material Inspection Request.
B INSTALLATION CHECK LIST
1 Checks works carried out as per approved drawings.
2 Check visually any damage in VFD panel
3 Check IN ROOM - clearance between other electrical panels is as per QCS
Ensure VFD is plumb and line
4 Earthing is provided properly
check the control supply MCB breakers / fuses rating match with drawing
5 Check cables are properly dressed in incomer and out going side
6 Check provision for BMS is provided
7 Cable Glands have proper earthing connection.
8 Cable tray have proper earthing and connected to main earth.
9 Ensure live parts of bus bars are properly insulated
Crimped lugs is provided with of the insulated type without conductor exposure
10
between the crimp and wire insulation
11 Danger label is visible
12 Cable properly Dressed
13 Cable marker Provided
14 Work area is clean and proper Housekeeping is maintained.
15
16
17

ORGANIZATION Sub contractor L&P JV GSIC JV KEO


NAME
SIGNATURE
DATE
Doc No: Q11017-0100D-LPS-GEN-PKS-QMS-FRM-00047C