DAILY ACTIVITY REPORT (MECHANICAL- CPP)

SL NO. PACKAGE EQUIPMENT CENTRE

1 CHP PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

CONVEYOR 2A &2B

CONVEYOR 3A &3B
CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE

2 BOILER & ESP BOILER -I

STRUCTURAL

PRESSURE PART

ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART

ROTATING EQUIPMENTS
HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP

LP PIPING RAW WATER PUMP HOUSE

3
CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

FIRE FIGHTING SYSTEM

LDO SYSTEM

PIPE RACK
FABRICATION &ERECTION OF
PIPING

COOLING FANS ,GEAR BOXES,PROPELLER


4 TOWER SHAFT & STRUCTURALS

DISTRIBUTION PIPE LINES

DRIFT ELIMINATORS & SPLASH


GUARDS

DECK RAILING WORK.

5 TG BUILDING STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER
AUXILLARIES

FABRICATION &ERECTION OF
PIPING

LUBE OIL SYSTEM

AC DUCTING WORK

ASH SILO STRUCTURAL


6
ERECTION OF EMBEDED PLATES &
OPENING

ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE


WATER
7 TREATMENT STRUCTURAL
PLANT

EQUIPMENT ERECTION

FABRICATION &ERECTION OF
PIPING

CHEMICAL HOUSE

WATER RESERVOIR

MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 27
(HAZEMAG)
2 THERMAX 283
3 GPR 16
4 APT 14
5 SUVENDU SAHU 6
JOSEPH
6 8
CONSTRUCTIONS
(MECHANICAL- CPP) DATE-23.08.13
PLANNED FOR
ACTIVITY AT SITE REMARK
TOMORROW

Hoppers, railings &


Final welding monorail beam chutes for feeder breaker
completed. Vertical bracing Same to continue awaited at site. Party has
erection &welding in progress been followed up.

Side Sheeting work & final All matreials received at


welding in progress Same to continue site

16 TON materials not


despatched by party
Boom extension of 80T crane has despite of repeated
been takenup for the dismantling reminders. HAZEMAG has
Same to continue
of TP-2 damaged columns for the been chased up to
rework. despatch the rework
materials post release of
payment.

Bracket & Idler erection work in Same to continue


progress

Erection & final welding of Floor


beams at Trussel TR-3 completed
&fixing of chequered plates is in Same to continue
progress. Erection of walkway is in
progress. Gallery welding is in
progress.

Civil foundation work yet


No activity to be completed
Trussel fabrication
completed & gallery to
be received.party not
despatching further
Approach of road to be materials despite of
made for Marching the
Iand dressing work in progress. repeated reminders.
Crane for errection of Rigorous followup
Trussel. required as party is not
able to provide any
evidence of work in
progress.

Material not received at


No activity site

Civil work yet to be


No activity completed

All fabrication scraps


being cut for use &house
Final painting work in progress. keeping work to
continue. Painting work
to continue.

Completed

Completed

Completed

Completed
Shifting of fire wood to Same to continue
combustion bed in progress.

Completed

Insulation work of MDC hopper


,pipelines & SA air duct is in Same to continue
progress.

No activity

Erection & welding of 13 M floor Same to continue


platform in progress.

Rectification work found not to be


satisfactory & rework to be done. Hydro test to be carried
Erection of non integral piping out .
support in progress.

ID fan foundation modification in


progress & foundation work for PA Same to continue
& SA FAN in progress.
Bed ash cooler outlet duct pre Balance Erection work
assembly taken up. Fabrication Same to continue awaiting completion of
work of SA fan delivery line in
fan foundation.
progress

Erection &welding of secondary Same to continue Same as above


air ducting work in progress .

Welding work at ID FAN ducting in


progress. Erection of economiser
casing in progress.Connecting duct Same to continue
from boiler to economiser work in
progress.

MDC welding in progress. Same to continue


Insulation work to start
No activity after hydro test.

Emitting electrode erection in


progress. Hopper erection
completed & welding is in Same to continue
progress.

Pipe assembly for raw water pump clearing of raw water


outlet is in progress. Shifting & pump house area for
Assembly of 2 Nos of raw water starting of vertical pump
pump is in progress. erection.
Fabrication & welding of purlin
support completed. Erection of Erection of Purlin
purlin has been taken up.

Allignment of columns
completed . Erection of of purlin Sheeting work to start.
extended portion completed.

No activity as monitoring basin


work yet to start.

Erection of Pipe supports for


instrument air pipe line in
progress. Welding of flanges to Same to continue
pipes is in progress .Corner
flashing (Sheeting work)
completed.

Follow up on for cables &


conduits of fire sensors at
No activity No activity TG Building 10.5M
control room roof.

Civil foundation work to


No activity No activity start.fabricated tank
awaited at site

Fabrication of racks between


clarified water pump house
&main rack, in progress. Doubling Same to continue
with welding on pipe rack in
progress.
400mm ACW pipe painting
wrapping in progress. Fabrication Same to continue
of pipe supports for CW Pump
inlet is in progress.

Civil work yet to be


completed &
No activity No activity mobilisation to be
started by Paltech

No activity No activity same as above

No activity No activity same as above

Fixing of hand railing work in Same to continue


progress.

Erection &welding of supporting


beams for staircase in progress. Same to continue
Welding of staircase headroom
completed & ready for erection .

No activity

No activity

Expansion of tubing in progress & Same to continue


dome welding completed.
Condensate float tank has been Positioning & alignment All other available
of condensate float tank equipments have been
erected &kept in 15.5M floor. to be completed. placed in position.

Fabrication of boiler feed pump Same to continue


delivery line in progress.

Fabrication of lube oil


No activity pipe line to be taken up.

Insulation work of 10.5 M control


room roof in progress.Erection of Same to continue
AC duct in progress.

Fixing of staircase gratings &


Same to continue
handrails is in progress.

All insert plates & edge angles for


openings have been fixed in No activity
position.

No activity

No activity
Completed

Erection of remaining
small pumps to be taken
No activity No activity up during erection of
panels

DM Water production
No activity for boiler-II internal
hydro test.

Purlin erection to start


No activity No activity after gable wall
completion.
Hand railing work in progress. Same to continue