DAILY ACTIVITY REPORT (MECHANICAL- CPP)

SL NO. PACKAGE EQUIPMENT CENTRE

1 CHP PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

CONVEYOR 2A &2B

CONVEYOR 3A &3B
CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE

2 BOILER & ESP BOILER -I

STRUCTURAL

PRESSURE PART

ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH

FLUE GAS PATH


FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART

ROTATING EQUIPMENTS

HOT AIR DUCTING


COLD AIR DUCTING

FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP

LP PIPING RAW WATER PUMP HOUSE

3
CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE


UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

FIRE FIGHTING SYSTEM

LDO SYSTEM

PIPE RACK

FABRICATION &ERECTION OF
PIPING
COOLING FANS ,GEAR BOXES,PROPELLER
4 TOWER SHAFT & STRUCTURALS

DISTRIBUTION PIPE LINES

DRIFT ELIMINATORS & SPLASH


GUARDS

DECK RAILING WORK.

5 TG BUILDING STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER

AUXILLARIES

FABRICATION &ERECTION OF
PIPING
LUBE OIL SYSTEM

AC DUCTING WORK

ASH SILO STRUCTURAL


6
ERECTION OF EMBEDED PLATES &
OPENING

ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

WATER
7 TREATMENT STRUCTURAL
PLANT

EQUIPMENT ERECTION
FABRICATION &ERECTION OF
PIPING

CHEMICAL HOUSE

MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 26
(HAZEMAG)
2 THERMAX 265
3 GPR 16
4 APT 14
5 SUVENDU SAHU 6
JOSEPH
6 10
CONSTRUCTIONS
(MECHANICAL- CPP) DATE-22.08.13
PLANNED FOR
ACTIVITY AT SITE REMARK
TOMORROW

Hoppers, railings &


Final welding monorail beam chutes for feeder breaker
in progress. Vertical bracing Same to continue awaited at site.Party has
erection &welding in progress been followed up.

Side Sheeting work & final All matreials received at


welding in progress Same to continue site

16 TON materials not


despatched by party
Boom extension of 80T crane despite of repeated
has been takenup for the reminders. HAZEMAG has
Same to continue
dismantling of TP-2 damaged been chased up to
columns for the rework. despatch the rework
materials post release of
payment.

Idler erection work in progress Same to continue

Erection & final welding of


Floor beams at Trussel TR-3 Same to continue
completed.Erection of walkway
is in progress.

Civil foundation work yet


No activity to be completed
Trussel fabrication
completed & gallery to
be received.party not
despatching further
Approach of road to be materials despite of
made for Marching the
Iand dressing work in progress. repeated reminders.
Crane for errection of Rigorous followup
Trussel. required as party is not
able to provide any
evidence of work in
progress.

Material not received at


No activity site

Civil work yet to be


No activity completed

All fabrication scraps being


Completed cut for use &house keeping
work to continue.

Completed

Completed

Completed

Completed

Shifting of fire wood to


combustion bed in progress.All
the manhole door closed & Same to continue
damper of ID fan opening work
in progress.
Completed

Insulation work of MDC


hopper ,pipelines & SA air duct Same to continue
is in progress.

No activity

Erection & welding of 13 M


floor platform in progress. Same to continue
Welding of bed material &lime
stone outlet chute completed.

Rectification work of detected


lekages in progress & overall
inspection done.Erection of Hydro test to be carried out .
non integral piping support in
progress.

ID fan foundation modification


in progress & foundation work Same to continue
for PA & SA FAN in progress.

Erection of seal air ducting Balance Erection work


work completed. Fabrication awaiting completion of
work of SA fan delivery line in fan foundation.
progress
Erection &welding of
secondary air ducting work in Same to continue Same as above
progress .

Welding work at ID FAN


ducting in progress. Erection of
economiser casing in Same to continue
progress.Connecting duct from
boiler to economiser work in
progress.

MDC welding in progress. Same to continue


Insulation work to start
No activity after hydro test.

Emitting electrode erection in


progress. Hopper erection Same to continue
completed & welding is in
progress.

Pipe assembly for raw water


pump outletis in clearing of raw water pump
progress.Shifting & Assembly house area for starting of
of 2 Nos of raw water pump is vertical pump erection.
in progress.

Purlins unloading has


No activity Erection of Purlin been completed.

Allignment of columns
completed . Fabrication of Erection of Purlin & Start of Purlins unloading has
purlin extended portion is in sheeting work. been completed.
progress.
No activity as monitoring basin
work yet to start.

Erection of Pipe supports for


instrument air pipe line in
progress. Welding of flanges to Same to continue
pipes is in progress .Corner
flashing (Sheeting work) in
progress.

Follow up on for cables &


conduits of fire sensors at
No activity No activity TG Building 10.5M
control room roof.

Civil foundation work to


No activity No activity start.fabricated tank
awaited at site

Fabrication of racks between


clarified water pump house
&main rack, in progress. Same to continue
Doubling with welding on pipe
rack in progress.

400mm ACW pipe painting


wrapping in progress. Same to continue
Fabrication of pipe supports for
CW Pump inlet is in progress.
Civil work yet to be
completed &
No activity No activity mobilisation to be
started by Paltech

No activity No activity same as above

No activity No activity same as above

Fixing of hand railing work in Same to continue


progress.

Erection &welding of
supporting beams for staircase
in progress. Welding of Same to continue
staircase headroom completed
& ready for erection .

No activity

No activity

Expansion of tubing in progress Same to continue


& dome welding completed.

Erection of Condensate float As the float tank is fouling All other available
tank to be taken up. Clearing of with one beam,the beam to equipments have been
area for crane positioning in be removed and wall below placed in position.
progress the beam to be dismantled

Fabrication of boiler feed Same to continue


pump delivery line in progress.
No activity

Insulation work of 10.5 M


control room roof in Same to continue
progress.Erection of AC duct in
progress.

Fixing of staircase gratings &


handrails is in progress. Same to continue

All insert plates & edge angles


for openings have been fixed in No activity
position.

No activity

No activity

Completed

Erection of remaining
small pumps to be taken
No activity No activity up during erection of
panels
DM Water production for
No activity boiler-II internal hydro test.

Purlin erection to start


No activity No activity after gable wall
completion.