GROUP MEMBERS:- Matric.

No
1 NURUL HIDAYAH BT. NORHAMIDI 1612942
2 HANIF BIN MOHAMAD NOOR 1616467
3 SHUHADA MULIANI BT. AHMAD RASA’ARIM 1613862
4 MUHAMMAD NABIL SHAUQI BIN SUAIB 1614969
LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)

The cold water, disposal and sanitary


installation shall be supplied and delivered
to site and installed by the Contractor in
accordance with relevant Authorities. The
work shall be carried out by Plumbers
suitably registered with Pusat Khidmat
Kontraktor

COLD WATER PLUMBING

Excavate trench for pipe maximum


depth not exceeding 0.50m
commencing from formation level and
get out, part return, fill in and ram
and deposit and spread in making up
level where directed within the site
and remainder load and cart away.

Trench for 50mm diameter Galvanized Iron m 21 44.84 941.64


A
(G.I.) pipe

Class ‘D’ UPVC Pipe as described


complete with necessary accessories

B 32mm Diameter pipe chased in brick wall m 72 8.93 642.96

C 25mm Diameter pipe chased in brick wall m 144 7.92 1,140.48

To Collection RM 2,725.08
Page No. 1/1
LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)
(Cont'd)

Class ‘D’ UPVC Pipe as described


complete with necessary accessories
(Cont'd)

A 20mm Diameter pipe chased in brick wall m 184 4.04 743.36

B 15mm Diameter pipe chased in brick wall m 54 6.44 347.76

Galvanized Iron (G.I.) Pipe as


described complete with necessary
accessories

80mm Diameter pipe laid and jointed in m 10 78.47 784.70


C
trench

75mm Diameter pipe laid and jointed in m 3 66.38 199.14


D
trench

50mm Diameter pipe laid and jointed in m 17 44.84 762.28


E
trench

SUNDRIES

Brasswork to B.S. 1010

50mm Diameter stop valve including nos 3 20.73 62.19


F
jointing to pipe

50mm Diameter Double check valve nos 12 49.67 596.04


G
including jointing to pipe
To Collection RM 3,495.47

Page No. 1/2


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)
(Cont'd)

Brasswork to B.S. 1010 (Cont'd)

50mm Diameter Lockable valve including nos 3 44.97 134.91


A
jointing to pipe

PIPE FITTINGS

Supply and fix the following UPVC pipe


fittings or other approved equivalent;
complete with all fixing accessories

Equal Elbow
B 25mm Diameter nos 408 3.41 1,391.28

C 20mm Diameter nos 108 3.49 376.92

D 15mm Diameter nos 48 2.98 143.04

Reducing Elbow
E 50mm to 25mm Diameter nos 12 3.97 47.64

F 25mm to 20mm Diameter nos 36 4.32 155.52

G 20mm to 15mm Diameter nos 36 5.07 182.52

Equal tee
H 25mm Diameter nos 12 5.53 66.36

I 20mm Diameter nos 24 4.23 101.52

Tee Socket
J 20mm Diemater nos 48 4.05 194.40
To Collection RM 2,794.11

Page No. 1/3


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)
(Cont'd)

Supply and fix the following UPVC pipe


fittings or other approved equivalent;
complete with all fixing accessories
(Cont'd)

P-Trap
A 3-Inch PVC DWV Trap white colour nos 36 19.85 714.60

COLD WATER SERVICES

Water storage tank

nos 1 35,000.00 35,000.00


Supply and install 5000mm x 3000mm x
2000mm High FRP 30m3 cold water
complete with 100mm diameter ventilation
pipe with mosquito netting, 75mm
B diameter G.I. type 'B' overflow and scour
pipe, 25mm diameter G.I. type 'B' warning
pipe, 760mm x 760mm access panel
complete with 600mm x 300mm aluminium
ladder and water indicator
To Collection RM 35,714.60

Page No. 1/4


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)
(Cont'd)

COLD WATER SERVICES (Cont'd)

Pump set

nos 1 -
Variable speed hydropneumatics including
2 nos booster pump sets; 20 IGPM at 105 ft.
head; 2.5 HP at 2900 R.P.M complete with
A
pressure tank and other necessary works to
complete the installation in accordance to
the Engineer's drawing and specification

Testing

item 1 -
On completion of the installation of cold
water services, test all piping, fittings etc
for water tightness, make good all defects
B
and leave everything in perfect working
order to the entire satisfaction of the
Architect and Local Authorities
To Collection RM 0.00

Page No. 1/5


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 1 - PLUMBING


INSTALLATION (ALL PROVISIONAL)
(Cont'd)

COLLECTION

Page No. 1/1 2,725.08

Page No. 1/2 3,495.47

Page No. 1/3 2,794.11

Page No. 1/4 35,714.60

Page No. 1/5 -


To Collection RM 44,729.26

Page No. 1/6


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 2 – SANITARY FITTINGS


(ALL PROVISIONAL)

Supply and fix the following fittings or


other approved equivalent; complete
with all fixing accessories including
chasing into walls, plugging, screwing
and connection to soil and waste and
cold-water system; fixed strictly with
the manufacturer's instructions and
specifications: -

Water Closet
Pedestal Water Closet set excluding cistem, nos 24 210.33 5,047.92
A
claytan as specified

Wash Basin
nos 24 83.33 1,999.92
560mm 406mm Wash basin in white
complete with 13mm chromium plated tap
B blank, tap hole stopper, 32mm ‘’P’’ trap
including 38mm seal waste fitting with
chain and plug and painted bracket support

Sink
Single bowl and single drainer stainless nos 12 83.33 999.96
C steel size 900mm x 450mm x 169mm lay
on type.

Tap
D 12mm Chromium plated bib tap nos 24 92.00 2,208.00
To Collection RM 10,255.80

Page No. 2/1


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 2 – SANITARY WARES


AND FITTINGS (ALL PROVISIONAL)
(Cont'd)

Supply and fix the following fittings or


other approved equivalent; complete
with all fixing accessories including
chasing into walls, plugging, screwing
and connection to soil and waste and
cold-water system; fixed strictly with
the manufacturer's instructions and
specifications: - (Cont'd)

Shower
nos 24 9.87 236.88
100mm Diameter chromium plated shower
A rose and arm with swivel joint complete
with 13mm chrome plated stopcock
To Collection RM 236.88

Page No. 2/2


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

ELEMENT NO. 2 – SANITARY WARES


AND FITTINGS (ALL PROVISIONAL)
(Cont'd)

COLLECTION

Page No. 2/1 10,255.80

Page No. 2/2 236.88


To Collection RM 10,492.68

Page No. 2/3


LOW RISE APARTMENT PROJECT, KUCHING SARAWAK
BILL NO. 1: MAIN BLOCK
Description Unit Qty Rate RM

SUMMARY

ELEMENT NO. 1 - PLUMBING 44,729.26


INSTALLATATION (ALL PROVISIONAL)

ELEMENT NO. 2 – SANITARY WARES 10,492.68


AND FITTINGS (ALL PROVISIONAL)
To Collection RM 55,221.94