NEW BUDGETS
PRJ - N - 1 Additional Budget for 8.2 MW Used Diesel Generator - - 245,000 245,000
PRJ - N - 2 New sea water Reverse Osmosis Plant 1,500 157,500 157,500
Construction of Water bore hole for new Sea Water Reverse Osmosis Plant 1,000ft.
PRJ - N - 3 - - 60,000 60,000
(4 Nos.).
Additional amount for procurement, Installation and commissioning of (Pressure
PRJ - N - 4 480 50,400 50,400
swing Adsorption) PSA Plant
PRJ - N - 5 Additional Budget for the optimization of Cooling Tower-4/5. - - 15,000 15,000