Critical Path Method
Activity Immediate Predecessor Duration in Weeks
A ----- 5
B ----- 11
C ------ 8
Example 1
D C 7
E A 9
F A,B,D 4
G C 12
H C 5
I E,F,G 10
J F,G 5
K H 5
L H 9
M J,K 3
N L 6
Network Diagram Example 1
E(9)
2 5
I(10)
A(5) D1 D2
4 7 9
H(5) L(9)
Network Diagram Example 1
Determine Critical Path……
5
20
E(9)
2 5
A(5) D1 I(10)
D2
15 20 25 30
0 B(11) J(5)
F(4)
1 3 6 8 10
G(12)
D(7) K(5)
N(6)
C(8)
4 7 9
8 H(5) L(9)
13 22
Network Diagram Example 1
Conditions for CPM:
Determine Critical Path……
20 (i) ESi=LCi
11 (ii) ESj=LCj
20
5 E(9) (iii) ESj-Esi=LCj-Lci=Dij
2 5
A(5) D1 I(10)
D2
16 27 30
0
15 25 30
0
B(11) F(4)
J(5)
1 3 6 8 10
20
G(12) 20
D(7) K(5)
N(6)
C(8)
8
4 7 9
8 H(5) L(9)
13 27
13 22
Floats in Critical Path
Activity Earliest Earliest Latest Duration Total Free
Start Start Start (Dij) Float Float
(ESi) (ESj) (Lci) (TFij) (FFij) Total Float
A 0 5 11 5 6 0 = LCj – Esi - Dij
B 0 15 16 11 5 4
C 0 8 8 8 0 0
D 8 15 16 7 1 0
Free Float
E 5 20 20 9 6 6 = ESj – ESi - Dij
F 15 20 20 4 1 1
G 8 20 20 12 0 0
H 8 13 15 5 2 0
I 20 30 30 10 0 0
J 20 25 27 5 2 0
K 13 25 27 5 9 7
L 13 22 24 9 2 0
M 25 30 30 3 2 2
N 22 30 30 6 2 2
D1 5 15 16 0 11 10
D2 20 20 20 0 0 0
PROJECT EVALUATION REVIEW TECHNIQUE
The time estimate if the
• Optimistic Time Estimate (a) execution goes extremely
good
2
• And the variance of the project completion time = ∑ σi
2
Where σ i is the variance of the ith critical activity in the critical path
C= Due date then What is the probability of completing the project within due
date.
(x-µ)
Beta distribution is approximated to standard normal distribution z =
σ
x is the actual project completion time
µ is the expected project completion time
σ is the standard deviation of the expected project completion time
Where P (x<C) represents the probability that the project will be completed on or before the C time
units
(C-µ) (C-µ)
∑ P (x-µ) < = P z<
σ σ σ
PERT example 1
Activity Time Estimates
Optimistic Most Likely Pessimistic
1-2 3 6 15
1-6 2 5 14
2-3 6 12 30
2-4 2 5 8
3-5 5 11 17
4-5 3 6 15
6-7 3 9 27
5-8 1 4 25
7-8 4 19 22
(6) (17)
22
17
11
6 6 7
(11)
PERT example 1 contd..
• Probability of completing the project on or before 35 months
• Sum of variances of the critical activities i.e. 1-2, 2-3,3-5,5-8
2 2 2 2 2
σ = σ 1-2 + σ 2-3 + σ 3-5 + σ 5-8
0.5
• Hence: σ = (40) = 6.325 months
= P[ z<= -0.6324 ]
= 1-P[ z<= -0.6324 ]
= 1-0.7357 = 0.2643