Question No : 1

In making investment decisions, the senior management in your company prefers to use a rate that equates the present
value of cash inflows with the present value of cash outflows. This rate is also called:

Choice 1 Discount Rate

Choice 2 Benefit Cost Ratio

Choice 3 Internal Rate of Return

Choice 4 Net Present Value

Correct Choice : 3

Justification :

Internal Rate of Return (IRR)

 Discount Rate on an investment which makes Present value of cash inflows = Present value of cash outflows
 Project Selection Criterion: Select a project with higher IRR.

Example: There are 2 projects. Project A has an IRR of 15% and will be completed in 5 years. Project B has an IRR of
10% and will be completed in 1 year. Which project will you select?
Answer: Project A will be selected. The fact that project B has a smaller duration than project A does not matter because
time is already taken into account in IRR calculations.

Reference: PMstudy.com comments


Question No : 2

You are completing a NASA project for the launch of a weather forecasting satellite. The satellite is being tested for a
specific quality metric: Performance under Strong Winds. For which processes are quality metrics used?

Choice 1 Perform Quality Assurance and Plan Quality

Choice 2 Plan Quality and Control Quality

Choice 3 Control Quality, Plan Quality, and Perform Quality Assurance

Choice 4 Perform Quality Assurance and Control Quality

Correct Choice : 4

Justification :
Quality metrics are used in the Perform Quality Assurance and Control Quality processes.

Reference: PMBOK® Guide - Fifth Edition, page 232, figure 8-3

PMstudy.com comments: Quality metrics form an output of Plan Quality Management process
Question No : 3

As a project manager, you are in the process of creating a list of all the project team members, their roles, and
communication information. This information should reside in:

Choice 1 Project plan

Choice 2 Project team directory

Choice 3 Performance reports

Choice 4 Responsibility assignment matrix

Correct Choice : 2

Justification :
Project team directory is a documented list of project team members, their project roles, and communication information.

Reference: PMBOK® Guide - Fifth Edition, page 556


Question No : 4

You are a procurements manager and are responsible for managing complex procurement contracts. In this context, which
of the following is the most effective means of handling complex communications?

Choice 1 Formal oral

Choice 2 Formal written

Choice 3 Informal written

Choice 4 Informal oral

Correct Choice : 2

Justification :
The best way to manage complex communications, such as in contracts, is through formal written communication.

Reference: PMstudy.com comments


Question No : 5

In managing risks for your project, you examine the extent to which the uncertainty of each project element affects the
objective being examined when all other uncertain elements are held at baseline values. This helps to:

Choice 1 Get a qualitative analysis of the risk.

Choice 2 Determine which risks may have impact on the project.

Choice 3 Translate the uncertainties at a detailed level into potential impact on objectives expressed at the level of the total
project.

Choice 4 Determine the implication of choosing one alternative over the other.

Correct Choice : 2

Justification :
Sensitivity analysis helps to determine which risks have the most potential impact on the project. It helps to understand
how the variations in project`s objectives correlate with variations in different uncertainties. Conversely, it examines the
extent to which the uncertainty of each project element affects the objective being studied when all other uncertain
elements are held at their baseline values.

Reference: PMBOK® Guide - Fifth Edition, page 338


Question No : 6

You are in the process of selecting an appropriate type of contract for your project. In this context, which of the following
statements related to fixed price, cost reimbursable, and time and material contracts is NOT correct?

Choice 1 In a fixed-price contract, the product is well defined.

Choice 2 In a cost reimbursable contract, the risk of the seller is low.

Choice 3 In a time and material contract, the risk of the buyer is low.

Choice 4 In a time and material contract, the type of payment is based on unit rates for work done. The unit rate for work
done is fixed, but the total cost increases with time.

Correct Choice : 3

Justification :
Contract Type Selection

Fixed Price Cost Reimbursable Time and Material


Definition of product Well-defined Not well-defined Not well-defined
Risk of buyer Low High High
Risk of seller High Low Low
Unit rate of payment fixed,
Payment for actual cost
Type of payment Fixed total price but the cost increases with
+ fee for seller profit
time

Reference: PMstudy.com study notes


Question No : 7

What are common updates made throughout the Project Stakeholder Management processes?

Choice 1 Project Documents, Project Management Plan, Enterprise Environmental Factors

Choice 2 Project Documents, Organizational Process Assets, Project Management Plan

Choice 3 Organizational Process Assets, Issue Log, Stakeholder Register

Choice 4 Organizational Process Assets, Stakeholder Management Plan, Issue Log

Correct Choice : 2

Justification :
Project documents such as the Stakeholder Register, Project Schedule, Issue Log, and Change Log may be updated
throughout the Project Stakeholder Management processes. Various organizational process assets such as project status
reports, lessons learned documentation, and project records (e.g., correspondence, memos, meeting minutes) may also be
updated. Finally, various components of the Project Management Plan, such as the Stakeholder Management Plan,
Communications Management Plan, Human Resource Management Plan and potentially other subsidiary plans, may need
to be updated due to stakeholder management activities.

Option 1: Enterprise Environmental Factors (e.g., organizational culture or structure, government or industry standards) are
not typically updated throughout the Project Stakeholder Management processes, but they may be used; so you will see
Enterprise Environmental Factors as an input in the Identify Stakeholders and Plan Stakeholder Management processes,
but not and output.

Options 3 and 4: Although these are all correct, option 2 is more inclusive. You should choose the most inclusive response
when there are multiple correct options.

Reference: PMstudy.com comments


Question No : 8

Your company manufactures car batteries. A research team discovers that there is a manufacturing flaw in the batteries,
25,000 of which are already sold. This flaw can cause fatal accidents, although no such accidents have been reported yet.
Recalling all the batteries sold would cost the company as much as $ 25 million. What first step is your company going to
take on this issue?

Choice 1 Recall all batteries for repair

Choice 2 Do nothing - there are no reported accidents till now

Choice 3 Strengthen the contingency reserves of the company to handle financial implications arising out of future
accidents occurring due to malfunction of the batteries

Choice 4 Ensure that the manufacturing defect is rectified in subsequent production

Correct Choice : 1

Justification :
Option 1: This is the correct answer as it is ethical to recall the batteries immediately on discovering the manufacturing flaw
in spite of the high cost involved and probability of accident occurrence.

Option 2 and Option 3: These are not recommended, because they are unethical actions; they presuppose inaction till
accidents happen.

Option 4: This is not recommended. This is certainly a step that the company should take--- but not the first.

Reference: PMstudy.com comments


Question No : 9

You are a project manager in XYZ Company, which has a projectized organizational structure. In this context, which of the
following statements is incorrect?

Choice 1 Team members are often co-located.

Choice 2 There is a "home" for project team members after a project is completed.

Choice 3 You have a great deal of authority and independence.

Choice 4 Organizational units (or departments) either report directly to you or provide support services to the various
projects.

Correct Choice : 2

Justification :
One disadvantage of a projectized organization is that there is "no home" for the project team members once the project is
completed. All the remaining answer options mentioned are features of a projectized organization.

Reference: PMstudy.com comments


Question No : 10

You are in the Direct and Manage Project Work process. Which of the following is NOT a result?

Choice 1 Deliverables

Choice 2 Project management plan updates

Choice 3 Product management plan

Choice 4 Change requests

Correct Choice : 3

Justification :
Please refer to PMBOK® Guide - Fifth Edition, page 79 (figure 4-6)

Reference: PMBOK® Guide - Fifth Edition, page 79

PMstudy.com comments: PMBOK® Guide does not define product management plan
Question No : 11

In projects, expert judgment will often be used throughout the Project Integration processes. Which of the following does
not provide expert judgment?

Choice 1 Professional and technical associations

Choice 2 Competitors

Choice 3 Consultants

Choice 4 Other units within the organization

Correct Choice : 2

Justification :
Expert judgment is available from many sources, including but not limited to:

- Other units within the organization


- Consultants
- Stakeholders, including customers or sponsors
- Professional and technical associations
- Industry groups
- Subject matter experts

Reference: PMBOK® Guide Fifth Edition, page 122

PMstudy.com comments: Competitors are not reliable sources of expert judgment.


Question No : 12

An activity has an optimistic estimate of 10 days, pessimistic estimate of 16 days, and most likely estimate of 13 days.
What is the PERT estimate for the task?

Choice 1 13 days

Choice 2 10 days

Choice 3 16 days

Choice 4 Cannot be determined with available information

Correct Choice : 1

Justification :
In a normal distribution, the PERT duration (also called mean)
= {Pessimistic + (4 x Most Likely) + Optimistic}/6
= {16 + (4 x 13) + 10}/6
= 13

Reference: PMstudy.com study notes


Question No : 13

Which of the following projects described below will you select?

Choice 1 Project A with opportunity cost of $100,000 and investment of $1,000,000.

Choice 2 Project B with opportunity cost of $200,000 and investment of $500,000.

Choice 3 Project C with opportunity cost of $300,000 and investment of $3,500,000.

Choice 4 Cannot be determined from the above options.

Correct Choice : 4

Justification :
Opportunity cost and investment are not project selection criteria. So, we cannot use these to make a decision.

Reference: PMstudy.com comments


Question No : 14

In your project, you are preparing a process improvement plan for the manufacture of a new drug. You include process
configuration, as part of the process improvement plan. The use of process configuration advances this objective through:

Choice 1 Description of the process and start and end of processes

Choice 2 Graphic depiction of processes, with interfaces identified, used to facilitate analysis

Choice 3 Process metric to maintain control over status of process

Choice 4 Improvement of process activities

Correct Choice : 2

Justification :
Process configuration is a graphic depiction of processes, with identified interfaces, used to facilitate analysis.

Reference: PMBOK® Guide - Fifth Edition, page 241


Question No : 15

In your previous project, the project manager gave a lot of autonomy to the team members, which led to anarchy. The
management style followed by the project manager was:

Choice 1 Directing

Choice 2 Laissez faire

Choice 3 Delegating

Choice 4 Democratic

Correct Choice : 2

Justification :
The project manager usually follows different leadership styles as listed below:

• Autocratic: Makes decisions himself/herself; allows team members little involvement and discussion before a decision is
made.

• Directing: Instruct people what tasks will be performed and when and how they should be performed.

• Laissez Faire: Does not interfere; team is left unsupervised which may lead to anarchy.

• Democratic: Allows team to discuss issues and reach decisions, although still guides and advises.

• Delegating: Delegates to team members, particularly if competent to handle tasks.

• Coaching: Issues instructions and then supports and monitors.

• Discussing: Two-way communication and discussion with team members.

• Facilitating: Coordinates inputs from several sources before making a decision.

• Supportive: Provides positive assistance and encouragement; maintains and presents a positive outlook during times of
uncertainty; listens and encourages.

• Participatory: Involve others; same as Democratic style.

• Task-Oriented: Enforces task completion by deadlines.

• Team-Based: Emphasizes teamwork and working well together.

• Assertive: Confronts issues and displays confidence; establishes authority with respect.

Reference: PMstudy.com study notes

Question No : 16

In accordance with the communications management plan, you have been providing the Sponsor with status updates on a
daily basis but now the Chief Financial Officer has been coming to your desk every week to request a status update on the
project. What should the project manager do?

Choice 1 Update the communications management plan

Choice 2 Re-examine the stakeholder registry

Choice 3 Ask the Chief Financial Officer to talk to the Sponsor to get status updates

Choice 4 Continue providing the Sponsor with the status updates and ignore the Chief Financial Officer

Correct Choice : 1

Justification :
The best course of action would be to update the communications management plan to provide updates to the Sponsor
and the Chief Financial Officer.
Question No : 17

Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce threats to
project objectives. The output of Plan Risk Responses process may be:

Choice 1 Expert judgment

Choice 2 Project management plan updates

Choice 3 Risk management plan

Choice 4 Risk register

Correct Choice : 2

Justification :
Project documents updates and project management plan updates are outputs of Plan Risk Responses process.

Reference: PMBOK® Guide - Fifth Edition, page 342 (figure 11-18)

PMstudy.com comments:

Option 1: This is a technique used in the Identify Risks, Perform Quantitative Risk Analysis, Perform Qualitative Risk
Analysis, and Plan Risk Responses processes.
Option 3: This is an output of the Plan Risk Management process.
Option 4: This is an output of the Identify Risks process.
Question No : 18

In your company, you are in the process of deciding whether to buy a product or to make it in-house. Which of the following
statements about make-or-buy analysis are correct?

A. Make-or-buy analysis is part of the Conduct Procurements process that can be used to determine whether a particular
product can be produced cost effectively by the performing organization.
B. A make-or-buy analysis should consider all related costs.
C. Budget constraints may influence make-or-buy decisions.
D. Buy-side of the analysis includes both the actual out-of-pocket costs to purchase the product, as well as the indirect
costs of supporting the purchasing process.

Choice 1 B, C and D

Choice 2 A, C and D

Choice 3 B, C and A

Choice 4 A, B and D

Correct Choice : 1

Justification :
Make-or-buy analysis is part of the Plan Procurement Management process. It is a general management technique used to
determine whether particular work can best be accomplished by the project team or outsourced.

Reference: PMBOK® Guide - Fifth Edition, page 365


Question No : 19

You have just started working on a project to construct a new toll highway that has been recently approved by the
government. You are aware that some local residents are opposed to the construction of the highway and a group of them
have been lobbying against it. Some seem to be concerned with the noise from the traffic on the highway, others with the
potential that they may need to relocate due to the highway’s planned location. Which of the following would be considered
valid stakeholders that should be identified and managed in your project?

Choice 1 Residents of the city

Choice 2 Government employees

Choice 3 Lobbying group

Choice 4 All of the above are stakeholders

Correct Choice : 4

Justification :
Stakeholders include all individuals and groups who are involved in, could impact, or be impacted by the project. All of
these are valid stakeholders. Residents who live in (and near) the city will be impacted by the new highway. Government
employees have already been involved in decision-making and would likely be providing further input and approvals
needed throughout the project. The group of local residents lobbying against the highway should also be identified and
their expectations considered. Even though they are negatively impacted by the project, they should still be identified as
stakeholders and managed throughout the project.

Reference: PMstudy.com comments


Question No : 20

You are constructing a railway track, which will pass through a less populated area. All necessary government and
regulatory approvals have been obtained for the project. You are aware that due to the motion of the train, there is a very
low probability of houses in the vicinity developing cracks. In this context, you should:

Choice 1 Stop the project

Choice 2 Do nothing, since the probability of adverse consequences is minimal

Choice 3 Inform the local people about the possibility of damage to their houses and preventive measures

Choice 4 Teach people how to rebuild their houses with concrete

Correct Choice : 3

Justification :
According to PMI Code of Ethics and Professional Conduct, a certificant should assume:

a. Responsibility to provide accurate and truthful communications.

b. Responsibility to comply with laws, regulations, and ethical standards governing professional practice in the
state/province and/or country while providing project management services.

Option 3: This is the correct answer. Although the probability of damage to the houses is low, it is ethical to inform the local
people and provide them all necessary assistance.

Option 1: Stopping of the project is an extreme reaction, because all approvals have already been obtained.
Option 2: This is unethical and violates the PMI Code of Ethics and Professional Conduct.
Option 4: Teaching them to rebuild houses with concrete is beyond the scope of the project.

Reference: PMI Code of Ethics and Professional Conduct


Question No : 21

You are working as a coordinator in an organization where decisions are primarily made by the senior management. The
structure of the organization you are working in is:

Choice 1 Weak Matrix

Choice 2 Balanced Matrix

Choice 3 Functional

Choice 4 Strong Matrix

Correct Choice : 1

Justification :
Weak matrix organizations maintain many of the characteristics of a functional organization, and the role of the project
manager is more of a coordinator or expeditor.

Reference: PMBOK® Guide - Fifth Edition, page 23

PMstudy.com comments: In a weak matrix organization, project manager plays the role of a coordinator or expeditor and
all decisions are primarily made by the top/senior management.
Question No : 22

You are involved in a project for manufacturing ball bearings. You notice that the quality of the ball bearings produced has
deviated from the parameters specified in project management plan. In order to bring it in line with the specifications, you
initiate measures, which are referred to as:

Choice 1 Corrective action

Choice 2 Change requests

Choice 3 Defect repair

Choice 4 Preventive action

Correct Choice : 1

Justification :
Corrective action is an intentional activity that realigns the performance of the project work with the project management
plan.

Reference: PMBOK® Guide - Fifth Edition, page 81


Question No : 23

You are a project manager for a $50 million project that is highly complex and involves more than 100 people. To
successfully execute the project, you decide to break it down into smaller manageable units. Which of the following
processes will you use?

Choice 1 Control Scope

Choice 2 Collect Requirements

Choice 3 Define Scope

Choice 4 Create WBS

Correct Choice : 4

Justification :
Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable
components.

Reference: PMBOK® Guide - Fifth Edition, page 125


Question No : 24

Which of the following statements about the creation of duration estimates is incorrect?

Choice 1 Mathematical analyses like CPM, GERT, and PERT indicate the dates on which the activity can be scheduled,
given resource limits and other constraints.

Choice 2 Duration compression techniques, including fast tracking and crashing can help in decreasing the project
schedule.

Choice 3 WBS classification allows for useful activity ordering and sorting.

Choice 4 The duration of the project is the sum of the duration of all the tasks in the project.

Correct Choice : 4

Justification :
The duration of the project should be calculated after drawing a network diagram and determining the critical path. The
duration of the project is the length of the critical path and not the sum of the duration of all the tasks in the project.

Reference: PMstudy.com study notes


Question No : 25

You have been managing a project to build a new Baseball complex and are three months into the construction. You notice
some variances and would like to forecast a new EAC. You hope to get approval to adjust the Cost Performance Baseline
by submitting the new EAC and justification through the Integrated Change Control process. Calculate the To-complete
performance index of your project, based on this new EAC, when the actual cost of your project is $200,000, cost variance
of your project is $25,000 and the budget at completion of your project is $350,000.

Choice 1 1.125

Choice 2 -1.4

Choice 3 1

Choice 4 -1

Correct Choice : 1

Justification :

CV = EV - AC
EV = CV + AC
= $25,000 + $200,000
= $225,000

CPI = EV / AC
= $225,000 / $200,000
= 1.125

EAC = BAC / CPI


= $350,000 / 1.125
= $311,111.11

TCPI = (BAC - EV) / (EAC - AC)


= ($350,000 - $225,000) / ($311,111.11 - $200,000)
= $125,000 / $111,111
= 1.125
Question No : 26

As a project manager, you want to ensure that appropriate quality standards and operational definitions are used for your
products. In this context, which of the following tools or techniques would you use to achieve this objective?

A. Quality audit
B. Process analysis
C. Quality control measurements
D. All quality planning tools and techniques

Choice 1 Only A

Choice 2 A and B

Choice 3 A, B and D

Choice 4 All of the above

Correct Choice : 3

Justification :
Quality control measurements are an input (not tool and technique) for Perform Quality Assurance. All the remaining are
valid tools for the Perform Quality Assurance process. The Perform Quality Assurance process uses the tools and
techniques of the Plan Quality Management and the Control Quality processes.

Reference: PMBOK® Guide - Fifth Edition, pages 243 (figure 8-8) and 245
Question No : 27

You have a portfolio architect in your project, who has been with the company for 30 years. She commands a lot of respect
and recognition from others and is very self-confident. From a Maslow`s hierarchy of needs perspective, she has reached
the phase of:

Choice 1 Self-actualization

Choice 2 Social

Choice 3 Physiological

Choice 4 Self-esteem

Correct Choice : 4

Justification :
Please refer to the below diagram:

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, pages 195 and 196
Question No : 28

Work performance reports are the physical or electronic representation of work performance information compiled in
project documents intended to generate decisions or raise issues, actions, or awareness. Which of the following is NOT a
common format for work performance reports?

Choice 1 S-curves

Choice 2 Control charts

Choice 3 Tables

Choice 4 Histograms

Correct Choice : 2

Justification :
Common formats for work performance reports include bar charts, S-curves, histograms, and tables. Control charts are a
tool used in the Control Quality process.

Reference: PMstudy.com comments


Question No : 29

In your new project the objective is to develop a new drug. After doing financial analysis, your finance manager provided
you with these statistics:

30% probability of success with benefits of $700,000


70% probability of failure with loss of $300,000

Based on this information, you:

Choice 1 Suggest that the project should proceed.

Choice 2 Suggest that the project should be stopped.

Choice 3 Communicate to your senior management that you cannot take a decision whether to proceed with the project or
not.

Choice 4 Start working on the project and ask your finance manager for additional information.

Correct Choice : 3

Justification :
Expected Value of the project
= Expected Value of success (0.30 x $700,000) + Expected value of Failure [0.70 x (- $300,000)]
= $210,000 - $210,000
=0

Since the Expected Value is "0", you cannot take a decision whether to continue with the project or not.

Reference: PMstudy.com comments


Question No : 30

Which of the following tools are used in the Control Procurements process?

A. Payment systems
B. Performance reporting
C. Inspections and audits
D. Procurement audits

Choice 1 B, C, and D

Choice 2 Only B

Choice 3 Only C

Choice 4 A, B, and C

Correct Choice : 4

Justification :
`Procurement audits` is not a tool used in the Control Procurements process. It is a tool for the Close Procurements
process. All the other options are tools and techniques used in the Control Procurements process.

Reference: PMBOK® Guide - Fifth Edition, page 356 (figure 12-1)


Question No : 31

Which one of the following is not an input to the Manage Stakeholder Engagement process?

Choice 1 Project Management Plan

Choice 2 Change Log

Choice 3 Communications Management Plan

Choice 4 Organizational Process Assets

Correct Choice : 1

Justification :
In the Manage Stakeholder Engagement process, the Project Management Plan is not listed as an input, but instead two of
its subsidiary plans – the Stakeholder Management Plan and the Communications Management Plan – are listed. The
Stakeholder Management Plan provides information on how to manage and keep stakeholders involved in the project. The
Communications Management Plan includes information on managing stakeholder expectations in terms of their
informational needs. These are the main plans needed to Manage Stakeholder Engagement.

Reference: PMBOK® Guide - Fifth Edition, page 404 (figure 13-8)

PMstudy.com comments: Option 2: The Change Log has information about changes that stakeholders need to be aware
of, so it is a valid input here.

Option 4: Organizational Process Assets used here might include stakeholder communication requirements, change and
issue control procedures, and relevant historical information from previous projects.
Question No : 32

You are doing a project under cost-reimbursable contract where the target price was $1,200,000. Your project is nearing
completion and CPI is currently 1.3. You are concerned that you will be losing money by billing for less. In this context, you
should:

Choice 1 Tell your buyer about the CPI as it stands today and explain the reasons for the deviation from the plan.

Choice 2 Invoice for $1,500,000 because there are chances for costs being higher in a subsequent project.

Choice 3 Tell the bad news to the buyer and suggest charging more from the customer.

Choice 4 Add some extra features to cause "customer delight".

Correct Choice : 1

Justification :
As per PMI Code of Ethics and Professional Conduct, you should assume:
a. Responsibility to maintain and satisfy the scope and objectives of professional services, unless otherwise directed by the
customer

Option 1: This is the correct answer, because it is ethical to inform the buyer about the CPI as it stands.

Option 2: This is unethical because you are over-invoicing for the project.

Option 3: This does not reflect the correct position. Since CPI is 1.3, you have extra money, and there is no need to ask the
buyer for extra funding.

Choice 4: This is also called "gold plating." We should never deliver more than what is undertaken and as approved in the
project scope.

Reference: PMstudy.com study notes


Question No : 33

The dictionary meaning of authority is "power to influence or command thought, opinion, or behavior.” Your authority as a
project manager is greatly dependent on:

Choice 1 Support from functional managers

Choice 2 Support from senior management

Choice 3 Your influencing and leadership skills

Choice 4 Organizational structure

Correct Choice : 4

Justification :
Please refer to PMBOK® Guide - Fifth Edition, page 22 (table 2-1)

Reference: PMBOK® Guide - Fifth Edition, page 22

PMstudy.com comments: The most important factor for determining the authority of a project manager is the organizational
structure. Depending on the organizational structure, the project manager may have high to almost total authority (as in a
Projectized organization), little or none (as in a Functional organization).
Question No : 34

The customer communicates a request for a change in your project plan. What should be your first step towards
addressing the change request?

Choice 1 Talk with team members to understand implications of the change.

Choice 2 Communicate the change to the management to get their inputs.

Choice 3 Open up a change control.

Choice 4 Implement the change and communicate to the customer.

Correct Choice : 1

Justification :
Any time the customer requests for a change, you should:

1. Understand what kind of change is requested and talk with team members to assess the implication of the change.
2. Open up a change control if there is a formal change control mechanism.
3. Communicate the change to the management, and inform the customer about the impact of the change (e.g. increase in
sizing, schedule, etc.).
4. Implement the change, if it is accepted.

Reference: PMstudy.com comments


Question No : 35

Decomposition is a valuable tool for Create WBS process. However, decomposition may not be possible for a deliverable
or subcomponent if:

Choice 1 The deliverable or subcomponent is very complicated

Choice 2 The deliverable or subcomponent is already being produced

Choice 3 The deliverable or subcomponent will be accomplished far into the future

Choice 4 The deliverable is a service

Correct Choice : 3

Justification :
Decomposition may not be possible for a deliverable or subcomponent that will be accomplished far into the future.

Reference: PMBOK® Guide - Fifth Edition, page 131


Question No : 36

You are in the process of developing the project schedule to determine start and finish dates for project activities. Which of
the following tools would NOT be used for this purpose?

Choice 1 Critical path method

Choice 2 Schedule compression

Choice 3 Scheduling tool

Choice 4 Schedule baseline

Correct Choice : 4

Justification :
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements and schedule
constrains to create the project schedule.

Schedule baseline is an output for this process. The tools and techniques specified in the other options are used in the
Develop Schedule process.

Reference: PMBOK® Guide - Fifth Edition, page 173, figure 6-16


Question No : 37

Given the following information, determine the EV of your project.

AC = $120,000
PV = $125,000
CV = -$10,000

Choice 1 $130,000

Choice 2 $110,000

Choice 3 $90,000

Choice 4 $120,000

Correct Choice : 2

Justification :
The formula to calculate CV is EV - AC, so when given both CV and AC, you can use this formula as a basis for solving for
EV.

CV = EV - AC
EV = CV + AC
EV = -$10,000 + $120,000
EV = $110,000

Reference: PMstudy.com comments


Question No : 38

Your company manufactures bearings for the automobile industry. You have historical information on the identified errors
and defects, and you would like to use this information to determine future performance. An appropriate tool which you can
use is:

Choice 1 Scatter diagram

Choice 2 Statistical sampling

Choice 3 Control chart

Choice 4 Trend analysis

Correct Choice : 4

Justification :
Trend Analysis. An analytical technique that uses mathematical models to forecast future outcomes based on historical
results.

Reference: PMBOK® Guide - Fifth Edition, page 566


Question No : 39

You are the project manager of a complicated construction project, which involves building highways in the state of North
Carolina. You have several groups working with you in the project. To plan resources for this project and determine
connection between activities you should preferably use:

Choice 1 Staffing pool description

Choice 2 Staffing management plan

Choice 3 Responsibility assignment matrix (RAM)

Choice 4 Organization matrix

Correct Choice : 3

Justification :
RAM is used to illustrate the connections between activities or work packages and project team members. On larger
projects, RAMs can be developed at various levels. For example, a high-level RAM can define what a project team group
or unit is responsible for within each component of the WBS, while lower level RAMs are used within the group to
designate roles, responsibilities, and levels of authority for specific activities.

Reference: PMBOK® Guide - Fifth Edition, page 262


Question No : 40

The processes used in Project Communications Management are:

Choice 1 Plan Communications Management, Manage Communications, and Control Communications.

Choice 2 Plan Communications Management, Control Communications, and Integrated Change Control.

Choice 3 Plan Communications Management, Administrative Closure, Control Communications, and Manage
Communications.

Choice 4 Control Communications, Manage Communications, and Administrative Closure.

Correct Choice : 1

Justification :
Plan Communications Management, Manage Communications, and Control Communications are the processes used in
Project Communications Management.

Reference: PMBOK® Guide - Fifth Edition, page 288 (figure 10-1)

PMstudy comments: Integrated Change Control is done as part of the Monitoring and Controlling process. Administrative
closure is done as part of the Closing process.
Question No : 41

In your project, you have just conducted a risk data quality assessment to evaluate the degree to which the data about
risks is useful for risk management. What is your next step?

Choice 1 Perform a structured review of project plans and assumptions, both at the total project and detailed scope levels.

Choice 2 Develop checklists to identify risks based on historical information and knowledge that has been accumulated
from previous similar projects.

Choice 3 Conduct planning meetings to develop the risk management plan.

Choice 4 Conduct interviews to quantify the probability and impact of risks on project activities.

Correct Choice : 4

Justification :
Risk data quality assessment is a tool for Perform Qualitative Risk Analysis.

Option 4: This is the correct answer. It refers to "Interviewing" which is a tool and technique for Perform Quantitative Risk
Analysis. Perform Quantitative Risk Analysis is conducted after Perform Qualitative Risk Analysis.
Option 1: This refers to Documentation Reviews which is a tool for Identify Risks. Identify Risks is conducted before
Perform Qualitative Risk Analysis.
Option 2: This refers to Checklist Analysis which is a tool for Identify Risks. Identify Risks is conducted before Perform
Qualitative Risk Analysis.
Option 3: This refers to "Meetings" which is a tool for Plan Risk Management process. Plan Risk Management process is
conducted before Perform Qualitative Risk Analysis process.

Reference: PMstudy.com comments


Question No : 42

You have just signed a contract with a seller. Due to funding issues, your management decides to terminate the contract.
For this purpose, you will:

Choice 1 Go back to procurement planning to determine what to procure and when.

Choice 2 Choose from other potential sellers.

Choice 3 Follow procedures as listed in contract closure.

Choice 4 Initiate procedures listed in contract change control system to define the process by which the contract may be
identified.

Correct Choice : 3

Justification :
Early termination of a contract is a special case of procurement closure that can result from a mutual agreement of both
parties, from the default of one party, or for convenience of the buyer if provided for in the contract.

Reference: PMBOK® Guide - Fifth Edition, page 387


Question No : 43

Which of the following processes is Information Management Systems a tool for?

Choice 1 Plan Stakeholder Management

Choice 2 Manage Stakeholder Engagement

Choice 3 Identify Stakeholders

Choice 4 Control Stakeholder Engagement

Correct Choice : 4

Justification :
Information Management Systems are used to collect, store, manage, and distribute information in various methods and
formats (e.g., hard copy, electronic, tables, spreadsheets, presentations, graphical). Standard tools are used by the project
manager to capture, store, and distribute information to stakeholders about project cost, schedule, and other performance
data. The project manager consolidates information from several systems and distributes reports to project stakeholders.

Reference: PMBOK® Guide - Fifth Edition, pages 392 (figure 13-1) and 412

PMstudy.com comments: Information Management Systems is also used in the Manage Communications and Control
Communications processes which also involve gathering and reporting project information to stakeholders as planned.
Question No : 44

The seller`s project is undertaken on contract and you are an employee of the seller. Since you had worked earlier with
ABC Bank, the buyer, you happen to be aware of the evaluation criteria used in ABC Bank to select sellers. You
understand that this could be a potential conflict of interest situation. How do you propose to act?

Choice 1 Do nothing and continue to work as before

Choice 2 Take appropriate person in ABC Bank into confidence and discuss this issue with her

Choice 3 Disclose the evaluation criteria to your (seller) organization and help their business growth

Choice 4 Remove yourself from the project

Correct Choice : 2

Justification :
Option 2: This is the correct answer. Since the evaluation criteria are proprietary information of ABC Bank, it is important
for you to discuss the matter directly with the appropriate person in the ABC Bank.

Option 1: This introduces conflict of interest as to whether to act or not in favor of your current employer.

Option 3: This is unethical, because proprietary information of the buyer should not be disclosed.

Option 4: This is an extreme step that could be taken only if required after talking to the buyer.

Reference: PMstudy.com comments


Question No : 45

Your director has appointed you as a portfolio manager in the company. Your responsibility as a portfolio manager is to:

Choice 1 Select and support projects or program investments

Choice 2 Manage groups of projects in a coordinated way

Choice 3 Create a unique product, service, or result

Choice 4 Ensure that customer requirements are satisfied through progressive elaboration of projects

Correct Choice : 1

Justification :
A portfolio refers to projects, programs, subportfolios, and operations managed as a group to achieve strategic objectives.

Reference: PMBOK® Guide - Fifth Edition, page 9

PMstudy.com comments: Project portfolio management refers to the selection and support of projects or program
investments. These investments in projects and programs are guided by the organization`s strategic plan and available
resources.

Option 2 refers to programs. Options 3 and 4 refer to projects.


Question No : 46

You are the project manager for a project, which is being managed under a contract. You receive a change request from
the buyer involving a government regulation. What should you do FIRST?

Choice 1 Talk with team members to understand implications of the change.

Choice 2 Communicate the change to the management to get their inputs.

Choice 3 Open up a change control.

Choice 4 Implement the change and communicate to the customer.

Correct Choice : 3

Justification :
Since the change request pertains to a government regulation and the project is being managed as part of a contract, it is
mandatory to implement the change. The first step towards that is to activate the change control mechanism.

Reference: PMstudy.com comments


Question No : 47

As part of decomposing, you break down the project work that needs to be accomplished in the near term at a low level of
WBS. However, the work planned in the future is broken down at a relatively high level of WBS. This technique is called :

Choice 1 Procrastination

Choice 2 Delaying tactics

Choice 3 Futuristic planning

Choice 4 Rolling wave planning

Correct Choice : 4

Justification :
Rolling Wave Planning: An iterative planning technique in which the work to be accomplished in the near term is planned in
detail, while the work in the future is planned at a higher level.

Reference: PMBOK® Guide - Fifth Edition, page 560


Question No : 48

You are the project manager in the public works department, which awards contracts for constructing roads. Before
selecting the sellers, you must advertise in local newspapers. This is an example of:

Choice 1 Best practices in the industry

Choice 2 External dependency

Choice 3 Discretionary dependencies

Choice 4 Mandatory dependencies

Correct Choice : 4

Justification :
Mandatory dependencies are those that are contractually required or inherent in the nature of the work. Mandatory
dependencies often involve physical limitations, such as on a construction project where it is impossible to erect the
superstructure until after the foundation has been built, or on an electronics project, where a prototype must be built before
it can be tested.

Reference: PMBOK® Guide - Fifth Edition, page 157

PMstudy.com comments: The use of “must” in the sentence suggests that this is a mandatory dependency.
Question No : 49

In your project, you are aggregating the estimated costs of individual activities to establish an authorized cost baseline. For
this purpose, which of the following will NOT be used as an input?

Choice 1 Resource calendars

Choice 2 Scope baseline

Choice 3 Cost baseline

Choice 4 Basis of estimates

Correct Choice : 3

Justification :
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish
an authorized cost baseline. Cost baseline is an output, not an input, of the Determine Budget process.

Reference: PMBOK® Guide - Fifth Edition, page 208 (figure 7-6)


Question No : 50

In your project, you would like to generate ideas that can be linked to form organized patterns of thought about a problem.
Which one of the following techniques would you use?

Choice 1 Force field analysis

Choice 2 Affinity diagrams

Choice 3 Nominal group techniques

Choice 4 Brainstorming

Correct Choice : 2

Justification :
Affinity diagrams are used to generate ideas that can be linked to form organized patterns of thought about a problem.

Reference: PMBOK® Guide - Fifth Edition, page 245


Question No : 51

In your software project, you have a programmer, who constantly professes to know all about project management and
keeps challenging his superiors. The programmer is playing the role of:

Choice 1 Aggressor

Choice 2 Conflict maximizer

Choice 3 Devil`s Advocate

Choice 4 Dominator

Correct Choice : 4

Justification :

Roles that undermine project management implementation

The Aggressor
- Criticizes everybody and everything on project management
- Deflates the status and ego of other team members
- Always acts aggressively

The Dominator
- Always tries to take over
- Professes to know everything about project management
- Tries to manipulate people
- Will challenge those in charge for a leadership role

The Devil’s Advocate


- Finds fault in all areas of project management
- Refuses to support project management unless threatened
- Acts more of a devil than an advocate
Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, page 181
Question No : 52

Which of the following is not an organizational process asset that can influence the Control Communications process?

Choice 1 Report templates

Choice 2 Policies, standards, and procedures that define communications

Choice 3 Specific communication technologies available

Choice 4 The project`s budget

Correct Choice : 4

Justification :
The organizational process assets that may influence the Control Communications process include, but are not limited to:

• Report templates;
• Policies, standards, and procedures that define communications;
• Specific communication technologies available;
• Allowed communication media;
• Record retention policies; and
• Security requirements.

Reference: PMBOK® Guide - Fifth Edition, page 306

PMstudy.com comments: The project`s budget is a constraint, and not part of organizational process assets. (Please note
that scope, cost and time are the triple constraints for any project.)
Question No : 53

You are evaluating the probabilities of risks and costs or rewards for each logical path of events and future decisions. You
create a diagram that describes a decision under consideration and the implications of choosing one or another of the
available alternatives. The diagram you have created can be referred to as:

Choice 1 Simulation diagram

Choice 2 Fishbone diagram

Choice 3 Decision tree

Choice 4 Influence diagram

Correct Choice : 3

Justification :
Decision tree analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple
options in the presence of uncertainty.

Reference: PMBOK® Guide - Fifth Edition, page 536


Question No : 54

Which of the following is a major component in a procurement Agreement?

A. Incentives
B. Penalties
C. Warranty
D. Identified project manager

Choice 1 B, C and D

Choice 2 All of the above

Choice 3 B and C

Choice 4 A, B and C

Correct Choice : 4

Justification :
The major components in a contract document will vary, but will sometimes include the following: Incentives, penalties,
pricing, place of delivery, warranty, etc.

Reference: PMBOK® Guide - Fifth Edition, pages 377 and 378


Question No : 55

You are the project manager for a project that involves developing a very important product for the company. While
executing the project plan, you notice that there are a lot of disagreements and conflicts occurring among project team
members, specifically regarding approved changes to the product. You review the Change and Issue Logs to gather some
information about what the conflicts could be about. After doing this, what should be your NEXT step?

Choice 1 Allow the team members to work through their disagreements without your involvement

Choice 2 Ask a senior team member to help the other members resolve their issues

Choice 3 Meet with all team members, listen to each perspective, and facilitate conflict management and consensus toward
project objectives

Choice 4 Have each team member discuss how he/she believes the changes should be made

Correct Choice : 3

Justification :
While the project is in executing phase, it is not uncommon for there to be conflict and disagreement among project team
members. The role of the project manager is to effectively manage stakeholders and promote appropriate stakeholder
engagement. It is therefore important for the project manager to have strong interpersonal and management skills.
Examples of interpersonal skills include building trust, resolving conflict, active listening, and overcoming resistance to
change. Examples of management skills include facilitating consensus toward project objectives, influencing others to
support the project, negotiating agreements to satisfy the project needs, and modifying organizational behavior to accept
the project outcomes.

Option 1: The team has already been trying to work out disagreements without success so the project manager must now
step in.

Option 2: The project manager is ultimately responsible for managing the project team members; this should not be
delegated to other team members who may themselves be involved in conflicts.

Option 4: This may be a valid exercise after the project manager explores option 3 if the issues are primarily about how the
changes to the product should be made.
Question No : 56

You observe that two technical team members have been arguing constantly. You would like to ensure that personality
clashes do not endanger your project. To resolve this issue, you should use:

Choice 1 Leading and influencing skills

Choice 2 Communication skills

Choice 3 Negotiation skills

Choice 4 Problem solving skills

Correct Choice : 4

Justification :
Problem solving skills include problem definition and decision-making. Problems may be technical (differences of opinion
about the best way to design a product), managerial (a functional group is not performing according to plan), or
interpersonal (personality or style clashes).

Reference: PMstudy.com comments


Question No : 57

Your project sponsor has specified that you have to complete your project within 3 months with a funding limit of $250,000.
This is an example of:

Choice 1 Authoritative project management

Choice 2 Constraint

Choice 3 Assumption

Choice 4 Laissez-faire management

Correct Choice : 2

Justification :
Constraint is a limiting factor that affects the execution of a project or process. Constraints identified with the project scope
statement list and describe the specific internal or external restrictions or limitations associated with the project scope that
affect the execution of the project, for example, a predefined budget or any imposed dates or schedule milestones that are
issued by the customer or performing organization.

Reference: PMBOK® Guide Fifth Edition, page 124

PMstudy.com comments: Here, the project sponsor has imposed two constraints: a) completion time of 3 months and b)
funding limit of $250,000.
Question No : 58

In your current role as a project manager, you track, review, and regulate the progress of your project. Which of the
following would you not use to perform these activities?

Choice 1 Project management plan

Choice 2 Performance reports

Choice 3 Organizational process assets

Choice 4 Approved change requests

Correct Choice : 4

Justification :
Monitor and Control Project Work is the process of tracking, reviewing, and reporting the progress to meet the performance
objectives defined in the project management plan. Approved change requests is not an input to this process.

Reference: PMBOK® Guide - Fifth Edition, page 86


Question No : 59

Your company exhibited a car model in two international auto expos and obtained feedback from the global automobile
industry, auto magazines, and others. The company decided to go ahead with the designing and manufacturing of the car,
taking into consideration the feedback received. Which of the following methods did your company use to make this
decision?

Choice 1 Observation technique

Choice 2 Prototype

Choice 3 Requirement documentation

Choice 4 Requirement traceability matrix

Correct Choice : 2

Justification :
Prototype is a method of obtaining early feedback on requirements by providing a working model of the expected product
before actually building it. Since a prototype is tangible, it allows stakeholders to experiment with a model of the final
product rather than being limited to discussing abstract representations of their requirements.

Reference: PMBOK® Guide - Fifth Edition, page 116

PMstudy.com comments:
Option 1: Observation technique provides a direct way of viewing individuals in their environment and how they perform
their jobs and tasks to carry out the processes
Option 3: Requirement documentation describes how individual requirements meet the business needs for the project.
Option 4: Requirement traceability matrix gives high level requirement to more detailed requirement.
Question No : 60

Based on the following, construct a project schedule network diagram and determine the duration of the critical path.

Your project has a total of five tasks. At the beginning of the project you can simultaneously begin tasks A and C. Task A
has a duration of 3 days, and task C has a duration of 4 days. When task A completes, task B can begin. Task B has a
duration of 5 days. Task C is followed by task D, which is estimated at 6 days. Once task B is done, you can start task E.
The duration of task E is 4 days. Task D is a predecessor to Task E. What is the duration of the critical path?

Choice 1 12 days

Choice 2 15 days

Choice 3 18 days

Choice 4 14 days

Correct Choice : 4

Justification :
The project schedule network diagram can be represented as shown below.
Reference: PMstudy.com comments
Question No : 61

In your project, you are estimating schedule activity costs. You decide to use the bottom-up estimating technique. In this
context, which of the following statements about Bottom-up Estimates is incorrect?

Choice 1 Determines the cost of individual scope requirements in the scope statement

Choice 2 Provides detailed costs at lowest levels that are rolled up to higher levels for reporting and tracking purposes

Choice 3 Is a method of estimating a component of work

Choice 4 Provide cost and accuracy, which is influenced by the size and complexity of the individual schedule activity or
work package

Correct Choice : 1

Justification :
Bottom-up estimating is a method of estimating a component of work. The cost of individual work packages or activities is
estimated to the greatest level of specified detail. The detailed cost is then summarized or "rolled up" to higher levels for
subsequent reporting and tracking purposes.

Reference: PMBOK® Guide - Fifth Edition, page 205

PMstudy.com comments: Scope requirements are not used for bottom-up estimating
Question No : 62

You are managing a project to design and implement a process to manufacture components for internal combustion
engines used in the automobile industry. You notice that in the past couple of days too many defects have been observed.
You would like to find out whether the process is stable or unusual events are occurring in your manufacturing process. For
this purpose, you should use:

Choice 1 Inspection

Choice 2 Pareto charts

Choice 3 Statistical sampling

Choice 4 Control charts

Correct Choice : 4

Justification :
Control charts are used to determine whether or not a process is stable or has predictable performance. Control charts can
be used to monitor various types of output variables. Although used most frequently to track repetitive activities required for
producing manufactured lots.

Reference: PMBOK® Guide - Fifth Edition, page 238


Question No : 63

In your project, you are determining project roles, responsibilities, and reporting relationships. Which of the following is not
an input to this process?

Choice 1 Enterprise environmental factors

Choice 2 Organizational process assets

Choice 3 Activity resource requirements

Choice 4 Project organization charts

Correct Choice : 4

Justification :
Plan Human Resource Management is the process of identifying and documenting project roles, responsibilities, required
skills, reporting relationships, and creating a staffing management plan. Inputs to this process are activity resource
requirements, enterprise environmental factors, and organizational process assets. However, project organization charts
are an output.

Reference: PMBOK® Guide - Fifth Edition, pages 257, 260, and 265
Question No : 64

In your project, you have created a list of identified risks and potential responses. You should document this information in
the:

Choice 1 Risk management plan

Choice 2 Risk database

Choice 3 Project plan

Choice 4 Risk register

Correct Choice : 4

Justification :
The risk register is a document in which the results of risk analysis and risk response planning are recorded.

Reference: PMBOK® Guide - Fifth Edition, page 327


Question No : 65

You will use the Conduct Procurements process to receive bids or proposals and apply the selection criteria for selecting a
provider. Which of the following tools and techniques can be used for the Conduct Procurements process?

Choice 1 Procurement negotiations, bidder conferences, and independent estimates

Choice 2 Procurement negotiations, contract types, and bidder conferences

Choice 3 Procurement negotiations, make-or-buy analysis, and independent estimates

Choice 4 Performance reporting, advertising, and independent estimates

Correct Choice : 1

Justification :
Procurement negotiations, bidder conferences, advertising, and independent estimates are some of the tools and
techniques used in the Conduct Procurements process.

Reference: PMBOK® Guide - Fifth Edition, page 371 (figure 12-4)


Question No : 66

You are managing a large software development project which involves an external customer. According to the Scope
Management Plan, the customer is expected to be verifying product deliverables when completed throughout the project.
This is especially important due to the complexity of the product requirements. You have sent a few of the software
modules to the customer for deliverable acceptance as scheduled; however, she appears to be busy and is slow
responding to emails and voice mails. The project is starting to fall behind and product acceptance risk has increased.
What should be your NEXT step?

Choice 1 Schedule a meeting with the customer to discuss the issue and explore ways of increasing current engagement

Choice 2 Ask the project sponsor to contact the customer and discuss the impact to the project

Choice 3 Ask the customer to provide another contact to verify the deliverables

Choice 4 Provide the customer with extra time to verify the modules and change the project schedule accordingly

Correct Choice : 1

Justification :
It is the project manager’s responsibility to effectively manage all stakeholder engagement throughout the project life cycle.
Any issues that arise should be addressed promptly to limit negative impact to the project. At this point, the next step is to
try to deal with the issue with the customer first by using appropriate management and interpersonal skills.

Option 2: The option of involving the project sponsor can be explored if option 1 is not effective.

Option 3: This is also not an immediate next step but can be explored later if the sponsor decides that her schedule cannot
accommodate the demands of the project.

Option 4: Allowing extra time for the customer to verify the scope could have significant impact to the project schedule and
other parts of the project management plan, so this would not be the best choice at this time.

Reference: PMstudy.com comments


Question No : 67

You are a project manager in an IT company. You have recently received an offer as a project manager in a construction
company offering a 25% salary hike. You have excellent technical knowledge in the IT field, but do not have much
exposure to the construction industry. In this context,

Choice 1 You should attend training classes related to the construction industry to get more technical expertise in the field.

Choice 2 You should not take up the assignment, because you will lose out on the experience and skills gained in the IT
field.

Choice 3 You should take up the assignment, because project management skills required in the construction company are
similar to those required in the IT field.

Choice 4 You should try to get more information about project management in the construction industry and then make an
informed decision about whether to take up the new opportunity.

Correct Choice : 3

Justification :
According to PMI, project management skills span across industries and the knowledge gained in one industry can be used
in other industries. A project manager need not be technically qualified in any specific industry to succeed.

Reference: PMstudy.com comments


Question No : 68

At what stage of the project are factors like probability of successfully completing the project, cost of changes, and cost of
error correction, the highest?

Choice 1 Beginning

Choice 2 End

Choice 3 Executing

Choice 4 Beginning and end

Correct Choice : 2

Justification :
The cost of making changes and correcting errors typically increases substantially as the project approaches completion.

Reference: PMBOK® Guide - Fifth Edition, page 40

PMstudy.com notes:
Question No : 69

As a project manager, you know that project plan development is an important element to manage projects. Develop
Project Management Plan is done as part of:

Choice 1 Initiating

Choice 2 Planning

Choice 3 Executing

Choice 4 Controlling

Correct Choice : 2

Justification :
Develop Project Management Plan process is taken up as part of the Planning Process Group. Please refer table 3-1
(page 61) and figure A1-7 (page 428).

Reference: PMBOK® Guide - Fifth Edition, pages 61 and 428


Question No : 70

As a project manager, you are interested in creating a detailed project scope statement to clearly define what work will be
performed and what work is going to be excluded. Which of the following will NOT be a part of this project scope
statement?

Choice 1 Project exclusions

Choice 2 Work breakdown structure (WBS)

Choice 3 Project deliverables

Choice 4 Project assumptions and constraints

Correct Choice : 2

Justification :
The detailed project scope statement, either directly, or by reference to other documents, includes the following: product
scope description, acceptance criteria, deliverable, project exclusion, constraints, and assumptions. However, it does not
include WBS, which is created in the Create WBS process.

Reference: PMBOK® Guide - Fifth Edition, pages 123 and 124


Question No : 71

Please refer to the diagram below:

What is the slack for Task 2?

Choice 1 3 days

Choice 2 2 days

Choice 3 - 4 days

Choice 4 4 days

Correct Choice : 4

Justification :
The two paths for this project are:

Task 1→ Task 2→ Task 5

Task 1→ Task 3→ Task 4→ Task 5

The lengths of the paths are:


Task 1→ Task 2→ Task 5 : 17 days

Task 1→ Task 3→ Task 4→ Task 5 : 21 days

So, the critical path is of 21 days duration.

Slack in Task 2
= 21 - 17 days
= 4 days

Reference: PMstudy.com study notes


Question No : 72

Your sponsor has asked you to use payback period as a selection criterion to select amongst 5 competing projects. In this
context, which of the following statements related to payback period is incorrect?

Choice 1 Payback period is the number of years required to get back the initial investment in the project.

Choice 2 Payback period takes the discount rate into account to determine the best possible option.

Choice 3 Payback period is a project selection criterion widely used in conjunction with NPV and IRR to determine the most
suitable project.

Choice 4 The initial investment in the project will not impact the selection criteria when payback period is used for project
selection.

Correct Choice : 2

Justification :

Payback Period

 Number of years required for an organization to recapture an initial investment.


 Discount rate is not taken into account in calculations for payback period.
 Project Selection Criterion: Select a project with lower payback period.

Example: There are 2 projects. Project A has an investment of $500,000 and a payback period of 3 years. Project B has an
investment of $300,000 and a payback period of 5 years. Using the payback period criterion, which project will you select?
Answer: Project A will be selected. The fact that project B has a smaller investment than project A will not impact the
selection.
Question No : 73

You are working as a research assistant studying the growth of bacteria under different environmental conditions. Based
on your experiments, you conclude that the longevity of bacteria increases as the temperature increases. What type of
diagram can you use to illustrate your observation?

Choice 1 Control chart

Choice 2 Run chart

Choice 3 Scatter diagram

Choice 4 Histogram

Correct Choice : 3

Justification :
A scatter diagram shows the relationship between two variables.

Reference: PMBOK® Guide - Fifth Edition, page 238

PMstudy.com comments: We are talking about two variables in the question, i.e., (a) temperature - the independent
variable and b) longevity of bacteria - the dependent variable. The relationship between these two variables can be
illustrated using a scatter diagram. This tool allows the quality team to study and identify the possible relationship between
changes observed in two variables. Dependent variables versus independent variables are plotted. The closer the points
are to a diagonal line, the more closely they are related.
Question No : 74

As a project manager, you realize the importance of team development for human resource management. Which of the
following is NOT a tool for the Develop Project Team process?

Choice 1 Interpersonal skills

Choice 2 Pre-assignment

Choice 3 Training

Choice 4 Ground rules

Correct Choice : 2

Justification :
Pre-assignment refers to the project team members selected in advance and is one of the tools and techniques used for
the Acquire Project Team process.

Reference: PMBOK® Guide - Fifth Edition, page 270


Question No : 75

In your project, the risk calculations show that there is a risk of overrunning the project scope and schedule targets to
levels that are beyond the threshold limits determined in the project. To bring the level of risk to a level acceptable to your
organization, you should:

Choice 1 Consider using contingency reserves

Choice 2 Decrease the project scope and increase the project schedule

Choice 3 Talk with your sponsor about cancelling the project

Choice 4 Do additional risk response planning

Correct Choice : 1

Justification :
Contingency reserves are needed to bring the risk of overrunning stated project objectives to a level acceptable to the
organization.

Reference: PMBOK® Guide - Fifth Edition, page 341


Question No : 76

In your project, the procurement statement of work (SOW) describes the procurement item in sufficient detail to allow
prospective sellers to determine if they are capable of providing the product. In this context, the details of the procurement
items` descriptions:

Choice 1 May vary, based on the nature of the item or needs of the buyer.

Choice 2 Should be at the level of work breakdown structures.

Choice 3 Should be at the activity level.

Choice 4 Should be at the level required in the proposal.

Correct Choice : 1

Justification :
The Procurement statement of work describes the procurement item in sufficient detail to allow prospective sellers to
determine if they are capable of providing the products, services, or results. Sufficient detail can vary based on the nature
of the item, the needs of the buyer, or the expected contract form.

Reference:PMBOK® Guide - Fifth Edition, page 367


Question No : 77

During which process would the project manager most often need to use skills that influence others to support the project
and facilitate consensus toward project objectives?

Choice 1 Identify Stakeholders

Choice 2 Manage Stakeholder Engagement

Choice 3 Plan Stakeholder Management

Choice 4 Control Stakeholder Engagement

Correct Choice : 2

Justification :
These are examples of Management Skills which are tools for Manage Stakeholder Engagement.

Reference: PMBOK® Guide - Fifth Edition, page 408

PMstudy.com comments: While the project is being executed, it is the project manager’s responsibility to ensure that all
stakeholders are involved as needed to meet the project objectives. This can be accomplished through effective
Management Skills.
Question No : 78

Your company has recently been awarded a contract by the government to reconstruct houses devastated by an
earthquake. In this context, the government`s role will impact your:

Choice 1 Project scope baseline

Choice 2 Business case and Business need

Choice 3 Project charter

Choice 4 Project management plan

Correct Choice : 3

Justification :
Option 3: Since the government is an external agency, and this is a "recently awarded" project as mentioned in the
question, hence inputs (e.g. contract) from the government will help the project manager in creation of the project charter
for the performing organization.
Option 1: Scope Baseline includes the Scope Statement, WBS and WBS Dictionary. So, this will be created later on after
the project charter is finalized.
Option 2: Business Need/Business case for the project should be already established because the government has
contracted out the work to your company.
Option 4: Project management plan is a planning document which will be created after the project charter is finalized.

Reference: PMstudy.com comments


Question No : 79

A project manager is responsible for managing project costs and human resources. Factors like cost and staffing level for a
project:

Choice 1 Increase with duration of the project

Choice 2 Decrease with duration of the project

Choice 3 Are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close

Choice 4 Cannot be determined, as they are specific to the project

Correct Choice : 3

Justification :
Refer PMBOK® Guide - Fifth Edition, page 39 (figure 2-8).

Reference: PMBOK® Guide - Fifth Edition, page 39

PMstudy.com Comments:
Question No : 80

You are managing a small project with five team members working part-time. At the beginning of every week, you orally
allocate work to all the team members. This is an example of:

Choice 1 Work Authorization System

Choice 2 Improper planning because team members do not know in advance what needs to be done at what time

Choice 3 Project time management plan

Choice 4 Project flexible time management plan

Correct Choice : 1

Justification :
A work authorization system is a collection of formal documented procedures that defines how project work will be
authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper
sequence.

Reference: PMBOK® Guide - Fifth Edition, page 567

PMstudy.com comments: The primary mechanism is typically a written authorization to begin work on a specific activity or
work package. Depending on the size of the project, the design of a work authorization system would vary. For example,
on many smaller projects, verbal authorizations will be adequate.
Question No : 81

In your project, you are preparing the requirements management plan to define and document stakeholders` needs to meet
the project`s objectives. Which of the following is not a component of the requirements management plan?

Choice 1 Traceability structure

Choice 2 WBS

Choice 3 Requirements prioritization process

Choice 4 Product metrics

Correct Choice : 2

Justification :
Components of the requirements management plan can include, but are not limited to... requirements prioritization
process, product metrics that will be used and the rationale for using them; and traceability structure to reflect which
requirement attributes will be captured on the traceability matrix.

Reference: PMBOK® Guide - Fifth Edition, page 110

PMstudy.com comments: Create WBS process happens after the Requirements Management Plan is created.
Question No : 82

The Trustees of a Race Track have appointed you as the Project Manager for a $400 million redevelopment project. They
expect the project to be completed before the Race Date exactly 3 Years from Project Start Date. Which of the following
parameters will help in determining the probability of finishing on time?

Choice 1 PERT value

Choice 2 CPM

Choice 3 Standard deviation

Choice 4 Variance

Correct Choice : 3

Justification :
Standard deviation is a measure that determines the probability of getting a result.
Hence, it is a good indicator of the probability of completing the task on time.

Reference: PMstudy.com study notes


Question No : 83

You are the project manager for a project where your team must travel to the work site by foot. The walk is 100 miles, and
is the first task on the project schedule. The total amount budgeted for this task is $4,000. If the team is scheduled to walk
20 miles per day, they should reach the work site at the end of day 5. At the end of the second day, you realize the team
has only traveled 30 miles, and you have spent $2,000. Based on this, what is the SPI for your project, and the projected
TCPI.

Choice 1 0.8, 1.4

Choice 2 0.75, 1.4

Choice 3 0.75, 1.2

Choice 4 Cannot be determined with the given information

Correct Choice : 2

Justification :

Given:
BAC = $4,000
AC = $2,000
PV = $1,600 ($4,000 / 5 days = $800 / day x 2 days = $1,600)
EV = $1,200 ($4,000 / 100 = $40 / mile; 30 miles x $40 / mile)

SPI = EV/PV = $1,200 / $1,600 = 0.75 (or 30 miles / 40 miles = 0.75)

TCPI = (BAC – EV) / (BAC – AC) = ($4,000-$1,200) / ($4,000-2,000) = $2,800 / $2,000 = 1.4

Reference: PMstudy.com comments


Question No : 84

After joining as a stand-in project manager for an ongoing project, you are informed by the team that certain features are
being added to the deliverable which was not asked for by the customer, to earn customer appreciation. In this situation:

Choice 1 You are concerned, because the project team is gold-plating

Choice 2 You are happy, because the project will `exceed customer expectations`

Choice 3 You are worried that this is going to increase the project size

Choice 4 You are undecided about the increase in the quality metrics of the project

Correct Choice : 1

Justification :
You should be concerned because the project team is gold-plating, which is not a recommended project management
practice.

Please note that `adding extra functionality beyond project scope` is not recommended by PMI, since a project is supposed
to deliver what is defined in its scope. Similarly, one cannot request for additional sizing for the project because the
customer had never asked for the additional requirements.

Reference: PMstudy.com comments


Question No : 85

Among the various conflict resolution modes (Confrontation, Compromise, Withdrawal, Forcing, and Smoothing), which
conflict resolution mode is most preferred or least preferred by project managers (answer format: most preferred, least
preferred)?

Choice 1 Compromise, Withdrawal

Choice 2 Confrontation, Withdrawal

Choice 3 Confrontation, Forcing

Choice 4 Smoothing, Withdrawal

Correct Choice : 2

Justification :
The most preferred conflict resolution techniques adopted by project managers (in descending order of preference) are as
follows:

1. Confrontation
2. Compromise
3. Smoothing
4. Forcing
5. Withdrawal

Blake and Mouton have delineated five modes for handling conflicts as listed below:

 Withdrawal: Retreating or withdrawal from a potential disagreement.

 Smoothing: De-emphasizing or avoiding areas of differences and emphasizing areas of agreement.


 Compromising: Bargaining and searching for solutions that bring some degree of satisfaction to the parties in a
dispute. Characterized by a ‘’give and take’’ attitude.

 Forcing: Exerting one’s viewpoint at the potential expense of another. Often characterized by competitiveness and
a win-lose situation.

 Confrontation: Facing the conflict directly, which involves a problem solving approach, whereby affected parties
work through their disagreements.

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, pages 304, 305 and 306
Question No : 86

As a project manager, you are creating a risk management plan to describe how risk management will be structured and
performed on the project. Which of the following would the risk management plan not include?

Choice 1 Budgeting

Choice 2 Methodology

Choice 3 Trigger condition

Choice 4 Risk categories

Correct Choice : 3

Justification :
Trigger condition is an event or situation that indicates that a risk is about to occur.

Reference: PMBOK® Guide - Fifth Edition, page 566

PMstudy.com comments: Please note that trigger conditions are not discovered in the Plan Risk Management process and
are not included in the risk management plan. All the other options are included in the risk management plan
(PMBOK®Guide - Fifth Edition, pages 316 and 317).
Question No : 87

As the project manager for a critical project in your organization, you must ensure that your team has the newest available
technology, so you are procuring 25 custom desktop computers, printers, and updated software for the project team
members. You will select a vendor and conduct negotiations with the vendor you determine best able to provide the
customized computers as required. What is a key output of this process?

Choice 1 Source selection criteria

Choice 2 Procurement negotiations

Choice 3 Procurement management plan

Choice 4 Agreements

Correct Choice : 4

Justification :
You are currently in the Conduct Procurements process and one of the key output of this process is the Agreement.

Option 1: Source selection criteria is an output of the Plan Procurement Management process.

Option 2: Procurement negotiations is a tool for the Conduct Procurements process, its not an output.

Option 3: The Procurement management plan in an output of the Plan Procurement Management process.

Reference:PMBOK® Guide - Fifth Edition, page 356 (figure 12-1)


Question No : 88

Issue resolution is necessary to address obstacles that can prevent the team from achieving its goals. In order to manage
and resolve issues that arise during project execution, you develop an Issue Log and assign each issue to a team member
to ensure there is accountability for resolving specific issues by a target date. The Issue Log is generated and updated in
which Project Stakeholder Management process(es)?

Choice 1 Manage Stakeholder Engagement

Choice 2 Control Stakeholder Engagement

Choice 3 Manage Stakeholder Expectations

Choice 4 Manage Stakeholder Engagement and Control Stakeholder Engagement

Correct Choice : 4

Justification :
The question asks where the Issue Log is generated and updated. The Issue Log is an output of the Manage Stakeholder
Engagement process. It is also an input to the Control Stakeholder Engagement process so it is used and updated there as
well.

Reference: PMBOK® Guide - Fifth Edition, pages 392 (figure 13-1), 408 and 411

PMstudy.com comments:

Options 1 and 2: These are correct options, but it is important to read all options and go with the most inclusive option.

Option 3: Manage Stakeholder Expectations is not a valid PMI process name.


Question No : 89

Which of the following is not the responsibility of a Project Management Professional?

Choice 1 Making decisions and taking actions

Choice 2 Fulfilling the commitments that you undertake

Choice 3 Ignoring errors and omissions

Choice 4 Upholding the Code of Ethics and Professional Conduct

Correct Choice : 3

Justification :
It is the responsibility of a project management professional to take ownership of the decisions you make or fail to make,
the actions you take or fail to take, and the consequences that result from these actions. When errors or omissions are
made, the certificant should not ignore them, but should take ownership and make suitable corrections.

Reference: PMstudy.com comments


Question No : 90

Project performance must be monitored and measured regularly to identify variances from the plan. Which of the following
processes does not belong to the Monitoring and Controlling Process Group?

Choice 1 Validate Scope

Choice 2 Control Risks

Choice 3 Control Communications

Choice 4 Perform Quality Assurance

Correct Choice : 4

Justification :
Perform Quality Assurance is a process in the Executing Process group.

Reference: PMBOK® Guide - Fifth Edition, page 61, table 3-1


Question No : 91

To know who will approve the changes in your project deliverables and documentation, you should refer to:

Choice 1 Change control system

Choice 2 Project plan

Choice 3 Organization chart

Choice 4 Resource assignment matrix

Correct Choice : 1

Justification :
Change control system is a set of procedures that describes how modifications to the project deliverables and
documentation are managed and controlled.

Reference: PMBOK® Guide - Fifth Edition, page 531


Question No : 92

Which of the following cannot be considered a benefit of a well-constructed scope statement?

Choice 1 Provides a documented basis for making future project decisions

Choice 2 Develops common understanding of project scope among stakeholders

Choice 3 Provides knowledge of project justification, deliverables, and objectives

Choice 4 Provides a basis for time and cost estimates

Correct Choice : 4

Justification :
Work breakdown structure (which is a component of the scope baseline, an output from Create WBS process) helps in
providing a basis for time and cost estimates.

Options 1, 2, and 3 are benefits of a well-constructed scope statement.

Reference: PMstudy.com comments


Question No : 93

You are responsible for Quality Audit in an Ongoing Project. The Audit has an optimistic estimate of ten days, pessimistic
estimate of sixteen days, and most likely estimate of thirteen days. Assuming a normal distribution, what is the probability
that the Audit will be completed within 10 to 16 days?

Choice 1 99.99 %

Choice 2 99.73 %

Choice 3 95.46 %

Choice 4 68.26%

Correct Choice : 2

Justification :
Please refer to the following Six Sigma exhibit:

In a normal distribution, the PERT duration (also called mean)


{Pessimistic + (4* Most Likely) + Optimistic} / 6
= {16 + (4 * 13) + 10}/6
= 13 days

1 Standard Deviation (sigma)


= (Pessimistic - Optimistic) / 6
= (16 - 10) / 6
= 1 day

If the task has to be completed within 10 days to 16 days, then the probability of completion within the time frame is
99.73% (3 sigma) as shown in the Six Sigma exhibit.

Reference: PMstudy.com study notes


Question No : 94

You have calculated the projected cost performance that is required to be achieved with the remaining resources in order
to meet a specified management goal. This projected cost performance is also known as:

Choice 1 Performance measurement document

Choice 2 To-complete performance index

Choice 3 Cost baseline

Choice 4 Cost performance index

Correct Choice : 2

Justification :
The To-complete performance index (TCPI) is a measure of the cost performance that is required to be achieved with the
remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the
outstanding work to the remaining budget.

Reference: PMBOK® Guide - Fifth Edition, page 221


Question No : 95

In your project, you recommend a specific technique to identify a problem, discover the underlying causes that lead to it,
and develop preventive actions. The recommended technique is:

Choice 1 Trend analysis

Choice 2 Process analysis

Choice 3 Risk analysis

Choice 4 Root cause analysis

Correct Choice : 4

Justification :
Root cause analysis is a specific technique used to identify a problem, discover the underlying causes that lead to it, and
develop preventive actions.

Reference: PMBOK® Guide - Fifth Edition, page 247


Question No : 96

You are the project manager of a high priority project, which will require more than 1,000 team members. During human
resource planning, you would like to apply proven principles to shorten the time needed to create a human resource plan
and make it effective. In this context, you will benefit if you consult an expert in the field of:

Choice 1 Networking and team formation

Choice 2 Human resource theory

Choice 3 Organizational theory

Choice 4 Cost management

Correct Choice : 3

Justification :
Organizational theory provides information regarding the way in which people, teams, and organizational units behave.
Effective use of this information can shorten the amount of time, cost, and effort needed to create the Plan Human
Resource Management process outputs and improve planning efficiency.

Reference: PMBOK® Guide - Fifth Edition, page 263


Question No : 97

Project Risk Management helps in maximizing the likelihood and impact of positive events, and minimizing the likelihood
and impact of negative events in the project. In this context, Plan Risk Responses process:

Choice 1 Helps in defining how to conduct the risk management activities

Choice 2 Develops procedures and techniques to enhance opportunities and to reduce threats to project objectives

Choice 3 Determines which risks may affect the project and documents their characteristics

Choice 4 Monitors residual risks, identifies new risks, and evaluates risk process effectiveness

Correct Choice : 2

Justification :
Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce threats to
project objectives.

Reference: PMBOK® Guide - Fifth Edition, page 309

PMstudy.com comments:

Option 1: This defines the Plan Risk Management process.


Option 3: This defines the Identify Risks process.
Option 4: This defines the Control Risks process.
Question No : 98

In your project, the seller is worried that the CPIF contract is reaching the point of total assumption. What is meant by
thepoint of total assumption?

Choice 1 Point where share ratio becomes irrelevant

Choice 2 Point where risk registers need to be updated

Choice 3 Point where buyer assumes all the risk

Choice 4 Point where seller decides not to do the project any more

Correct Choice : 1

Justification :
Point of total assumption refers to the point where the costs have to be incurred by the seller herself when they have
exceeded the ceiling limits stipulated in the contract. Hence, share ratio ceases to be relevant.

Reference: PMstudy.com study notes


Question No : 99

You are working with your team to execute a project which involves implementation of 50 new Base Transceiver Station
(BTS) towers throughout remote areas of the country in order to improve wireless communication services. The project
involves many internal and external stakeholders which you have been managing throughout. Current schedule
performance is 1.3 and cost performance is 1.1 and there are no pressing issues that require escalations at this time. The
sponsor is a very high-level executive in the company who fully supports the project. However, he seems quite nervous
these days and has showed up at the past two team status meetings during which he diverted the team discussion away
from the usual agenda to issues that did not involve the project team. What is the best NEXT step for you to pursue?

Choice 1 Speak with the sponsor separately to discuss his present concerns and offer to provide any other required
information outside of the team status meetings.

Choice 2 Since the sponsor is a high-level executive, you should allow him to attend the meeting and address his concerns
there.

Choice 3 Ask the sponsor not to attend any more meetings.

Choice 4 Ask the sponsor to submit his issues prior to the meeting so you can add them to the Issue Log and the meeting
agenda.

Correct Choice : 1

Justification :
The project sponsor is a very valuable stakeholder to the project since he/she is accountable for enabling project success.
Some sponsors may be over- or under-involved in projects which could adversely impact the project’s objectives. In this
case, the sponsor is causing some distraction for the project team members by attending team meetings and bringing up
issues that should not be part of the regular status meeting. The project manager should first have a discussion with the
project sponsor to understand his present concerns and offer options for him to get any information he needs instead of
attending regular team status meetings. It is the project manager’s responsibility to manage stakeholders to ensure the
project’s success and to also ensure that they are all engaged when appropriate.

Option 2: Although the sponsor is a senior manager, he does not need to attend regular team status meetings, but rather
should be involved when issues need to be escalated, or when required for authorizing changes, phase-end reviews, very
high risks, etc.

Option 3: The sponsor does not usually need to attend team meetings but this option is a bit drastic. There are times when
the sponsor may want to check in and provide support to the project team so he may occasionally attend a meeting. Also it
would not be a good idea for the project manager to ask the sponsor not to attend any more meetings as the authority of
the sponsor is usually above that of the project manager.

Option 4: It’s always best to include all issues to be discussed in the meeting on an agenda; however, that’s not the real
problem in this situation and the issues being brought up by the sponsor are not relevant to this meeting.

Reference: PMstudy.com comments


Question No : 100

You have joined a company as a project manager, and although you maintain the professional conduct expected of you, it
is not reciprocated by the other employees. The BEST course of action for you would be to:

Choice 1 Maintain the same conduct

Choice 2 Change your behavior and be one among the other employees

Choice 3 Complain to the higher authority

Choice 4 Ignore others` behavior

Correct Choice : 1

Justification :
As a project manager, you are expected to behave as befitting a professional project management certificant, even when
such conduct is not reciprocated by your colleagues. This is one of the major tenets of the Code of Ethics and Professional
Conduct prescribed by PMI.

Reference: PMstudy.com comments


Question No : 101

As a project manager, you are aware that project management process groups are linked by their objectives. Planning
process group outputs including the project management plan become inputs for project implementation. In this context,
which of the following statements is inaccurate?

Choice 1 Process groups are non-overlapping activities that occur with varying intensity throughout the project.

Choice 2 If the project is divided into phases, the process groups interact within a project phase and may also cross over to
other phases.

Choice 3 Not all processes will be needed on all projects and not all of the interactions will apply to all the projects or
process groups.

Choice 4 Among the process groups and their processes, the process outputs are related and have an impact on the other
process groups.

Correct Choice : 1

Justification :
The Process Groups are seldom either discrete or one-time events; they are overlapping activities that occur throughout
the project. The output of one process generally becomes an input to another process or is a deliverable of the project,
subproject, or project phase.

Reference: PMBOK® Guide - Fifth Edition, page 51

PMstudy comments: Also, please refer to PMBOK® Guide - Fifth Edition, page 78, table 4-1.
Question No : 102

Perform Integrated Change Control process requires coordinating changes across knowledge areas. When a proposed
schedule change occurs, which of the following will not be affected?

Choice 1 Cost

Choice 2 Quality

Choice 3 Staffing

Choice 4 Communications

Correct Choice : 4

Justification :
A proposed schedule change will often affect cost, risk, quality, and staffing. Usually, communications are not impacted if
there is a schedule change in the project.

Reference: PMstudy.com comments


Question No : 103

You are the project manager for an initiative to release a new product in the market. But because of government
regulations, you will have to make some changes to the requirements documentation and the WBS. The changes made in
the requirements documentation are reflected in the:

Choice 1 Project document updates

Choice 2 Work breakdown structure

Choice 3 Project plan

Choice 4 Project charter

Correct Choice : 1

Justification :
Project Document updates: If approved change requests result from the Create WBS process, then the requirements
documentation may need to be updated to include approved changes.

Reference: PMBOK® Guide - Fifth Edition, page 132


Question No : 104

Of the following documents, all of which are updated during the Control Schedule process, which is NOT a part of the
project management plan?

Choice 1 Schedule baseline

Choice 2 Cost baseline

Choice 3 Schedule management plan

Choice 4 Schedule data

Correct Choice : 4

Justification :
Elements of the project management plan that may be updated include, but are not limited to, schedule baseline, schedule
management plan, and cost baseline. Schedule data is the project document that gets updated as an output to the Control
Schedule process.

Reference: PMBOK® Guide - Fifth Edition, page 191

PMstudy.com comments: Schedule data is a project document, but all baselines/plans are part of the project management
plan.
Question No : 105

Resource calendars provide information on a specific resource or a category of resources. They show how a project team
member might be unavailable (on vacation or in a training program) or how a labor contract can limit certain workers to
certain days of the week. Resource calendars are valuable inputs to:

Choice 1 Develop an approximation of the monetary resources needed to complete project activities.

Choice 2 Aggregate the estimated costs of individual activities or work packages to establish an authorized cost baseline.

Choice 3 Manage the actual changes when and as they occur.

Choice 4 Monitor work performance against funds expended.

Correct Choice : 2

Justification :
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish
an authorized cost baseline. Resource calendars are inputs to this process.

Reference: PMBOK® Guide - Fifth Edition, page 208 (figure 7-6)

PMstudy.com comments: Option 1 refers to the Estimate Costs process; options 3 and 4 refer to the Control Costs
process.
Question No : 106

`Cost of quality` includes all costs incurred over the life of the product by investing in meeting requirements. In this context,
which of the following is NOT a ‘cost of quality’?

Choice 1 Opportunity costs

Choice 2 Cost of poor quality

Choice 3 External failure costs

Choice 4 Appraisal costs

Correct Choice : 1

Justification :
Cost of quality includes all costs incurred over the life of the product by investment in preventing non-conformance to
requirements, appraising the product or service for conformance to requirements, and failing to meet requirements
(rework). Failure costs are often categorized into internal (found by the project) and external (found by the customer).
Failure costs are also called cost of poor quality.

Reference: PMBOK® Guide - Fifth Edition, page 235

PMstudy.com comments: Opportunity costs are not included in the cost of quality.
Question No : 107

You are the project manager in an organization, so all your team members report to you. Managing a team is always a
challenge and a project manager needs to focus on:

Choice 1 Communication

Choice 2 Observation

Choice 3 Influence

Choice 4 Assessment

Correct Choice : 1

Justification :
Team management involves a combination of skills with special emphasis on communication, conflict management,
negotiation, and leadership.

Reference: PMBOK® Guide - Fifth Edition, page 280


Question No : 108

If there is a fire, the risk response plan developed is to use a fire extinguisher. If the fire extinguisher cannot take care of
the fire, you call in a fire engine – calling in the fire engine is an example of:

Choice 1 Secondary risk

Choice 2 Residual risk

Choice 3 Fallback Plan

Choice 4 Work around

Correct Choice : 3

Justification :
Several risk response strategies are available… A fallback plan can be developed for implementation if the selected
strategy turns out not to be fully effective or if an accepted risk occurs.

Reference: PMBOK® Guide - Fifth Edition, page 343


Question No : 109

The following is the data for a CPIF project you are managing:

Target cost is $100,000;


Actual cost is $80,000
Target fee is $20,000;
Maximum fee is $25,000;
Sharing ratio is 60:40.

What should be the final price of the contract?

Choice 1 $100,000

Choice 2 $108,000

Choice 3 $105,000

Choice 4 $92,000

Correct Choice : 3

Justification :
Target cost (TC) = $100,000
Target fee (TF) = $20,000
Maximum fee = $25,000
Sharing ratio = 60:40
Actual fee (AF) = {(TC - AC) * SSR} + TF = {($100,000 - $80,000) * 40%} + $20,000 = $20,000 * 40% + $20,000 = $28,000

Although the actual fee is more than the maximum fee, the maximum fee ($25,000) only is payable.

So, final price = AC + AF = $ 80,000 + $ 25,000 = $ 105,000


Question No : 110

Which of the following statements about project stakeholders is not correct?

Choice 1 Stakeholders influence over the final characteristics of the product is usually highest at the beginning of a project.

Choice 2 Stakeholders may passively or actively detract from the success of the project.

Choice 3 Stakeholder identification is a continuous process throughout the entire project life cycle.

Choice 4 Stakeholders’ levels of responsibility and authority remain the same throughout the project’s life cycle.

Correct Choice : 4

Justification :
Stakeholders have varying levels of responsibility and authority on a project, but this can change throughout the project life
cycle; so option 4 is the “not correct” statement.

Option 1: The ability of stakeholders to influence the final characteristics of the project’s product (without significantly
impacting cost), is highest at the beginning of the project and generally decreases throughout the project life cycle.

Options 2 and 3: These are both correct statements as per the PMBOK® Guide -Fifth Edition, page 31.

Reference: PMstudy.com comments


Question No : 111

You realize that you are not able to concentrate on your work due to an actual or potential conflict of interest situation.
Which out of the following should you NOT do, in this context?

Choice 1 Disclose the facts to the affected stakeholders

Choice 2 Prepare a mitigation plan

Choice 3 Seek stakeholders` consent to proceed further

Choice 4 Engage in decision-making activities related to the conflict of interest situation

Correct Choice : 4

Justification :
When you realize that you are in an actual or a potential conflict of interest situation, you should immediately withdraw from
engaging in decision-making activities. Decisions taken in such situations might go against the interests of your current
project and the employer company.

Reference: PMstudy.com comments


Question No : 112

You are the project manager of a new project, tasked with construction of a bridge on the River Nile in Egypt. While
initiating the project, you should:

Choice 1 Create a scope management plan to document project scope definition, verification, and control

Choice 2 Develop a project management plan

Choice 3 Determine specific activities that need to be performed to produce various project deliverables

Choice 4 Develop a project charter

Correct Choice : 4

Justification :
Project Charter is a document issued by the project initiator or sponsor that formally authorizes the existence of a project
and provides the project manager with the authority to apply organizational resources to project activities.

Reference: PMBOK® Guide - Fifth Edition, page 553

PMstudy.com comments: Initiating process group consists of the processes that facilitate the formal authorization to start a
new project or a project phase. The activities stated in the first 3 options are undertaken after the project is initiated.

Option 1 refers to Define Scope, Validate Scope, and Control Scope; Option 2 refers to Develop Project Management Plan;
and Option 3 refers to Define Activities. All these are processes are related to the Planning Process Group and are
performed after the processes related to the Initiating Process Group.
Question No : 113

You are in the initiating phase of your project and are involved with creation of the project charter. Which of the following
statements relating to the project charter is NOT correct?

Choice 1 Includes or references the business need and product description.

Choice 2 Provides authority to the project manager.

Choice 3 Formally authorizes a project.

Choice 4 Authorized only by the project sponsor.

Correct Choice : 4

Justification :
Projects are initiated by an entity external to the project such as a sponsor, program or project management office (PMO)
staff person, or a portfolio governing body chairperson or authorized representative. The project initiator or sponsor should
be at the level that is appropriate to procure funding and commit resources to the project.

Reference: PMBOK® Guide - Fifth Edition, page 68


Question No : 114

You are managing a complicated software development project with several deliverables. To be effective and to be alert to
potential future problems, you monitor the status of completion of the project deliverables. This information will be available
to you in the:

Choice 1 Work performance measurements

Choice 2 Project baseline changes

Choice 3 Work performance information

Choice 4 Earned value techniques

Correct Choice : 3

Justification :
Work performance information includes information about project progress, such as which deliverables have started, their
progress, which deliverables have finished, or which have been accepted.

Reference: PMBOK® Guide - Fifth Edition, page 136


Question No : 115

Please refer to the diagram below:

Task 1→ Task 3→ Task 4→ Task 5 is the critical path. What is the late finish date for Task 2?

Choice 1 15 days

Choice 2 17 days

Choice 3 13 days

Choice 4 3 days

Correct Choice : 2

Justification :
The length of the critical path is: (3 + 6 + 8 + 4) = 21 days.

So, the late finish for Task 2


= Critical path - time for Task 5
= 21 - 4 = 17 days
Question No : 116

As the project manager in a software company, you are determining the possible costs to complete project activities. This
is done as part of:

Choice 1 Variance analysis

Choice 2 Estimate Costs

Choice 3 Determine Budget

Choice 4 Control Costs

Correct Choice : 2

Justification :
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project
activities. Cost trade-offs and risks should be considered, such as make versus buy, buy versus lease, and the sharing of
resources in order to achieve optimal costs for the project.

Reference: PMBOK® Guide - Fifth Edition, pages 200 and 201


Question No : 117

You are trying to determine the cost and schedule trade-off which will be most appropriate for determining the ride quality
of a car. You classify factors like tire pressure, suspension, height of vehicle, etc., which have to be optimized to improve
ride quality. A tool you can use to facilitate making the decision is:

Choice 1 Cost of quality

Choice 2 Cause-and-effect diagrams

Choice 3 Design of experiments

Choice 4 Network diagrams

Correct Choice : 3

Justification :
Design of Experiments (DOE) is a statistical method for identifying which factors may influence specific variables of a
product or process under development or in production.

Reference: PMBOK® Guide - Fifth Edition, page 239

PMstudy.com comments: The technique can also be applied to project management issues, such as cost and schedule
trade-offs. For example, senior engineers will cost more than junior engineers but can also be expected to complete the
assigned work in less time.
Question No : 118

As part of your project, you were involved with improving the competencies and interaction of team members to enhance
project performance. What should you do next?

Choice 1 Manage conflicts if they arise

Choice 2 Create organization charts with appropriate position descriptions

Choice 3 Interact with others in the organization in a constructive way to understand political and interpersonal factors

Choice 4 Create a staffing management plan

Correct Choice : 1

Justification :
Develop Project Team is a process to improve the competencies and interaction of team members to enhance project
performance.

In the Manage Project Team process you manage conflicts if they arise. This follows the Develop Project Team process.
Organization charts, position descriptions, and networking are tools for the Plan Human Resource Management process.
Staffing management plan is an output of the Plan Human Resource Management process.

Since the Plan Human Resource Management process precedes the Develop Project Team process, options 2, 3 and 4
are not correct.

Reference: PMstudy.com comments


Question No : 119

You have created an Excel spreadsheet that shows cumulative cost at any particular point of time in the project duration.
Your director wants to review the project costs and you decide to make a presentation. Cumulative costs plotted against
time is shown in the slide as a:

Choice 1 S-curve

Choice 2 Histogram

Choice 3 Control chart

Choice 4 Pareto diagram

Correct Choice : 1

Justification :
S-curve is a graphic display of cumulative costs, labor hours, percentage of work, or other quantities, plotted against time.
The name derives from the S-like shape of the curve.

Reference: PMstudy.com comments


Question No : 120

Which of the following elements of the organizational process assets is necessary to be updated in the Control
Procurements process?

A. Procurement audits
B. Correspondence
C. Payment schedules and requests
D. Seller performance evaluation documentation

Choice 1 B, C and D

Choice 2 Only B

Choice 3 Only C

Choice 4 All of the above

Correct Choice : 1

Justification :
Elements of the organizational process assets that may be updated include, but are not limited to: correspondence,
payment schedules and requests, seller performance evaluation documentation

Reference: PMBOK® Guide - Fifth Edition, page 386

PMstudy.com comments: Procurement Audit is a tool for Close Procurements process


Question No : 121

As part of your duties as a project manager, you make sensitive company data available to a vendor. In this context, which
of the following precautions should you take?

Choice 1 Insist that the vendor signs a non-disclosure agreement after you release the sensitive information.

Choice 2 Make sure that the vendor receives all the sensitive information in time.

Choice 3 Ensure that the vendor signs a non-disclosure agreement before you release the sensitive information.

Choice 4 Monitor the vendor in order to prevent her from sharing the information with her competitors.

Correct Choice : 3

Justification :
PMI Code of Ethics and Professional Conduct requires a project manager not to disclose sensitive or confidential
information. But, at times, an organization has a legitimate need to disclose confidential information to vendors,
governmental agencies, or others. When disclosing confidential or sensitive information, it is the responsibility of the project
manager to ensure that proper nondisclosure agreements are signed prior to the disclosure of the sensitive information.

Reference: PMstudy.com comments


Question No : 122

In your project, you are coordinating people and resources as well as integrating and performing activities of the project in
accordance with the project management plan. This is performed during:

Choice 1 Initiating Process Group

Choice 2 Executing Process Group

Choice 3 Planning Process Group

Choice 4 Monitoring Process Group

Correct Choice : 2

Justification :
The Executing Process Group consists of those processes performed to complete the work defined in the project
management plan to satisfy the project specifications. This Process Group involves coordinating people and resources,
managing stakeholder expectations, as well as integrating and performing the activities of the project in accordance with
the project management plan.

Reference: PMBOK® Guide - Fifth Edition, page 444


Question No : 123

Ideally, when should a project manager be assigned to a project?

Choice 1 As soon as a project is authorized

Choice 2 Soon after the scope statement is finalized

Choice 3 When the WBS is completed

Choice 4 At any time during the project life cycle, depending on requirements

Correct Choice : 1

Justification :
A project manager is identified and assigned as early in the project as is feasible.

Reference: PMBOK® Guide - Fifth Edition, page 67


Question No : 124

In your project, you are subdividing major project deliverables into smaller, more manageable components. This will be
done as part of :

Choice 1 Create WBS

Choice 2 Scope verification

Choice 3 Work authorization system

Choice 4 Product analysis

Correct Choice : 1

Justification :
Decomposition is a technique used for dividing and subdividing the project scope and project deliverables into smaller,
more manageable parts. (Decomposition is done as part of the Create WBS process.)

Reference: PMBOK® Guide Fifth Edition, page 128


Question No : 125

Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources.
In this context, the non-work schedule activities that are added in the critical chain method to manage uncertainty are
referred to as:

Choice 1 Duration buffers

Choice 2 Resource leveling

Choice 3 Reverse resource leveling

Choice 4 Crashing

Correct Choice : 1

Justification :
The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty.

Reference: PMBOK® Guide - Fifth Edition, page 178


Question No : 126

In your project, you are using project files, records, and closed contracts to determine the cost of many categories of
resources. This will help you to estimate the cost of the resources needed to complete the project activities. This
information is available to you as a part of:

Choice 1 Activity list

Choice 2 Estimating publications

Choice 3 Historical information

Choice 4 Code of accounts

Correct Choice : 3

Justification :
Historical information: Documents and data on prior projects, including project files, records, correspondence, closed
contracts, and closed projects.

Reference: PMBOK® Guide - Fifth Edition, page 542


Question No : 127

Which of the following statements about "Quality" and "Grade" is correct?

A. Grade is a rank given to entities having the same functional use but different technical characteristics.
B. Low quality product may be of high grade.
C. Low grade product may be of high quality.
D. It is a problem if the product is of high quality and low grade.

Choice 1 A and B

Choice 2 Only B

Choice 3 All of the Above

Choice 4 A, B and C

Correct Choice : 4

Justification :
Grade is a category assigned to deliverables having the same functional use but different technical characteristics. While a
quality level that fails to meet quality requirements is always a problem, low grade may not be.

Reference: PMBOK® Guide - Fifth Edition, page 228


Question No : 128

Which of the following activities does a project manager NOT perform during the Manage Project Team process?

Choice 1 To observe and converse to stay in touch with the work and attitudes of project team members

Choice 2 To perform appraisals to clarify roles and responsibilities, develop training plans, etc.

Choice 3 To negotiate for assignment of appropriate project members to the team.

Choice 4 To manage conflicts which leads to increased creativity and better decision making

Correct Choice : 3

Justification :
Option 3 (negotiation) is a tool and technique for the Acquire Project Team process. Option 1 (observation and
conversation), Option 2 (project performance appraisals) and Option 4 (conflict management) are tools and techniques for
the Manage Project Team process.

Reference: PMBOK® Guide - Fifth Edition, page 257 (figure 9-1)

PMstudy.com comments: Manage Project Team process involves tracking team member performance, providing feedback,
resolving issues, and managing changes to enhance project performance. The project management team observes team
behavior, manages conflict, resolves issues, and appraises team member performance.
As a result of managing the project team, the human resource plan is updated, change requests are submitted, issues are
resolved, inputs are provided for performance appraisals, and lessons learned are added to the organization`s database.
Question No : 129

Utility function is a commonly used technique to determine risk tolerance levels. Some project managers are more averse
to risk than others. Which of the following is NOT a commonly used classification for risk tolerance?

Choice 1 Risk averter

Choice 2 Risk seeker

Choice 3 Risk mitigator

Choice 4 Neutral risk taker

Correct Choice : 3

Justification :
The three commonly used classifications for risk tolerance are risk averter or avoider, risk taker or seeker and the neutral
risk taker (risk averse, risk seeking, risk neutral).
Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, page 746
Question No : 130

ABC Inc recently signed a contract for nuclear waste disposal from nuclear power plants in your state. During project
implementation, some employees of ABC Inc were exposed to a high level of nuclear radiation. ABC Inc now wants to get
out of the agreement. The only means for either party to exit the contract is by:

Choice 1 Getting validation from the U.S. FDA that nuclear waste is dangerous

Choice 2 Determining that the contract violates applicable law

Choice 3 Establishing that the company will be under financial difficulties due to labor issues if the project continues

Choice 4 Declaring the contract null and void

Correct Choice : 2

Justification :
Regardless of the document’s complexity, a contract is a mutually binding legal agreement that obligates the seller to
provide the specified products, services, or results, and obligates the buyer to compensate the seller. A contract is a legal
relationship subject to remedy in the courts.

Reference: PMBOK® Guide - Fifth Edition, page 377

The only way that either party can get out of a signed contract is if the contract violates applicable law. ABC Inc has not
violated the law of the land.
Question No : 131

You are working as a project manager in a company; you get to know that a person managing another project of your
company has furnished false reports about his PMP experience and credentials. What should you do in this context?

Choice 1 Report violation of the PMP code of conduct to PMI.

Choice 2 Report violation of the PMP code of conduct to PMI only if found true after verifying the facts.

Choice 3 Report violation of the PMP code of conduct to PMI and then verify the facts.

Choice 4 Report the violation to your manager.

Correct Choice : 2

Justification :
Reporting violations of the PMP code of conduct is one of the primary responsibilities of a project management
professional. If and when one gets to know that a violation of the PMP code of conduct has occurred, she should verify the
facts, if found true, must notify the PMI.

Reference: PMstudy.com comments


Question No : 132

ABC company has recently launched a new model of their car in the market and the market response has been
overwhelming. Sales have gone up to a level much higher than what the company anticipated. To cater to the increased
market demand, the company plans to start a project to create a new assembly line for the cars. Who, according to you, is
the user for this project?

Choice 1 Project manager and project management team

Choice 2 Person who may buy the car in the future

Choice 3 Project sponsor who provides funding

Choice 4 Assembly line worker who is going to work on the new assembly line being created

Correct Choice : 4

Justification :
Customers are the persons or organizations who will approve and manage the project’s product, service, or result.
Users are the persons or organizations who will use the project’s product, service, or result.

Reference: PMBOK® Guide - Fifth Edition, page 32

PMstudy.com comments: Here the assembly line worker will use the project`s product, i.e., the new assembly line being
created. So, he is user of the project.
Question No : 133

In the project execution phase, deliverables are produced. While monitoring and controlling project work, you track, review,
and regulate the progress to meet the performance objectives. In this context, what is NOT performed in the Monitor and
Control Project Work process?

Choice 1 Comparing expected project performance against the project plan

Choice 2 Monitoring implementation of approved changes as they occur

Choice 3 Providing information to support status reporting, progress measurement, and forecasting

Choice 4 Providing forecasts to update current cost and current schedule information

Correct Choice : 1

Justification :
The Monitor and Control Project Work process is concerned with comparing actual project performance against the project
management plan.

Reference: PMBOK® Guide - Fifth Edition, page 88


Question No : 134

Your project is very critical for the company and must be completed within six months. The project charter has been
signed, but the scope statement is not yet prepared. The management asks you to go ahead with the project without the
scope statement being approved. What should you do?

Choice 1 Refuse to work on the project, because the management is not following standard project management practices.

Choice 2 To save time, you should start the project with inputs from the project charter.

Choice 3 Meet the management and explain the problems you may face if you start a project without a scope statement.

Choice 4 Escalate the issue to the project sponsor and issue a risk memo.

Correct Choice : 3

Justification :
Option 3: This is the best available alternative. Without the scope statement, you do not have a good understanding of the
project justification, product, or project deliverables and project objectives. Also, you do not have all the inputs for the
scope definition and for the creation of work breakdown structure (WBS). The best option is to talk to the management
about the problems likely to be faced if you start a project without a scope statement.

Option 1: This is an extreme step and is not recommended


Option 2: This will pose problems. For example, you will not be able to create a WBS without the help of a scope
statement.
Option 4: This is an extreme measure and is not recommended.

Reference: PMstudy.com comments


Question No : 135

In which of the following processes is decomposition used as a tool?

Choice 1 Define Activities

Choice 2 Sequence Activities

Choice 3 Estimate Activity Resources

Choice 4 Estimate Activity Durations

Correct Choice : 1

Justification :
Decomposition is a tool used in the Define Activities process.

Reference: PMBOK® Guide - Fifth Edition, page 143, figure 6-1


Question No : 136

You have recently taken over a new project. While studying the project information, you find out that cost variances are
very severe. To provide a realistic basis for performance measurement, what should you recommend?

Choice 1 Issue budget updates

Choice 2 Revise the cost baseline

Choice 3 Adjust schedule activity budget

Choice 4 Close the project

Correct Choice : 2

Justification :
In some cases, cost variances can be so severe that a revised cost baseline is needed to provide a realistic basis for
performance measurement.

Reference: PMBOK® Guide - Fifth Edition, page 226


Question No : 137

Which of the following should be determined during the Plan Quality Management process, so the cost of quality will
include the number of tests, expected scrap, etc.?

Choice 1 Sample frequency

Choice 2 Sample size

Choice 3 Sample time

Choice 4 Sample frequency and Sample size

Correct Choice : 4

Justification :
Sample frequency and sizes should be determined during the Plan Quality Management process, so the cost of quality will
include the number of tests, expected scrap, etc.

Reference: PMBOK® Guide - Fifth Edition, page 240


Question No : 138

Ten members were assigned in advance to your project. In this context, which of the following cannot be a reason for this
pre-assignment?

Choice 1 Specific people were promised as part of a competitive proposal.

Choice 2 Suitable people volunteered to work on the project.

Choice 3 Staff assignments were defined in the project charter.

Choice 4 The project was dependent on the expertise of the pre-assigned persons

Correct Choice : 2

Justification :
When project team members were selected in advance, they would be considered pre-assigned. This situation could occur
if the project was the result of specific people being promised as part of a competitive proposal, if the project was
dependent upon the expertise of particular persons, or if some staff assignments were defined within the project charter.

Reference: PMBOK® Guide - Fifth Edition, page 270


Question No : 139

The Plan Risk Responses process helps the project manager to develop options and actions to enhance opportunities and
to reduce threats to project objectives. The output from the Plan Risk Responses is updates to the risk register, which
should be:

Choice 1 At the level of detail of work packages in the WBS

Choice 2 At the level of detail whereby actions can be taken

Choice 3 Able to identify and document residual risks and secondary risks

Choice 4 Used for periodic risk reviews to identify risk ratings and prioritization

Correct Choice : 2

Justification :
The risk register should be written to a level of detail that corresponds with the priority ranking and the planned response.
Often, the high and moderate risks are addressed in detail.

Reference: PMBOK® Guide - Fifth Edition, page 347


Question No : 140

The scope of your project is very well defined and you have completed all the work described in the contract to your
satisfaction, but you think your buyer is not happy with the work. What should you do?

Choice 1 Go through arbitration proceedings to ensure that disputes are resolved

Choice 2 Talk with senior management about changing the scope of the project to accommodate requirements that would
satisfy the customer

Choice 3 Ask the customer for input and get her advice on changes that need to be made

Choice 4 Move to contract close-out

Correct Choice : 4

Justification :
As stated in the question, the scope of your project is very well defined, and you have completed all the work described in
the contract. You should now move towards contract close-out. Also note that while `you think` that your buyer is not
happy, there is no mention of the buyer explicitly stating that she is dissatisfied.

Reference: PMstudy.com study notes


Question No : 141

You are managing a team of twenty members; you realize that some of your team members are showing less-than-
desirable customer service attitude. In this context, which of the following will be the most appropriate action?

Choice 1 Warn those team members of the consequences of their attitude.

Choice 2 Inform the senior management about those team members.

Choice 3 Influence those team members to adhere to company expectations about customer service

Choice 4 Replace those team members.

Correct Choice : 3

Justification :
A project manager has a great amount of influence on her team members. It is her responsibility to coach and influence the
team members who do not posses right attitudes, to conform to the standards of the conduct expected by her organization.

Reference: PMstudy.com comments


Question No : 142

At the end of the closing process group,

Choice 1 It is verified that the defined processes are completed within all the process groups to close the project or project
phase.

Choice 2 It is determined that the product will be successful in the market.

Choice 3 The project management plan is written off by the project sponsor.

Choice 4 The new change requests are initiated as required.

Correct Choice : 1

Justification :
The Closing Process Group, when completed, verifies that the defined processes are completed within all of the Process
Groups to close the project or a project phase, as appropriate, and formally establishes that the project or project phase is
complete.

Reference: PMBOK® Guide - Fifth Edition, page 57


Question No : 143

You have recently appointed a project manager to handle a critical project in your organization. You want to give her the
authority to apply organizational resources to project activities. Which document should you use?

Choice 1 Resource authorization document

Choice 2 Work Breakdown Structure

Choice 3 Project charter

Choice 4 Project scope description

Correct Choice : 3

Justification :
The project charter provides the project manager with the authority to plan and execute the project...This understanding will
better allow for efficient resources allocation to project activities.

Reference: PMBOK® Guide - Fifth Edition, page 67


Question No : 144

You have undertaken a project under contract, where you are supposed to create an anti-virus software product for a
customer in ten months. You follow the software development life-cycle which includes analysis, high-level design, low-
level design, coding, testing, and rollout, with a deliverable at the end of each phase. Your customer has defined the scope
very well, and said that he is going to review your product after ten months. In this case, you should:

Choice 1 Insist that the customer verify the deliverables at the end of each phase

Choice 2 Ask your senior management to review the deliverables at the end of each phase to ensure that the deliverables
satisfy customer requirements

Choice 3 Complete the product as per specifications and provide the completed product to the customer as requested

Choice 4 Provide project deliverables to the customer at the end of each phase, even if the customer does not review them

Correct Choice : 1

Justification :
The verified deliverables obtained from the Control Quality process are reviewed with the customer or sponsor to ensure
that they are completed satisfactorily and have received formal acceptance of the deliverables by the customer or
sponsor.

Reference: PMBOK® Guide - Fifth Edition, page 134

PMstudy.com comments: It is important to ensure that the customer does formal scope verification after project
deliverables are completed. Otherwise, there is a high probability that the customer will complain of non-conformance with
requirements.
Question No : 145

Activity attributes extend the description of the activities in the activity list. Which of the following require activity attributes
as input?

A. Sequence Activities
B. Define Activities
C. Estimate Activity Resources
D. Estimate Activity Durations

Choice 1 B, C and D

Choice 2 A, C and D

Choice 3 A, B and D

Choice 4 A, B and C

Correct Choice : 2

Justification :
Activity attributes are outputs from the Define Activities process and inputs for Sequence Activities, Estimate Activity
Resources, Estimate Activity Durations, and Develop Schedule processes.

Reference: PMBOK® Guide - Fifth Edition, page 143 (figure 6 - 1)

PMstudy.com comments: Activity List and Activity attributes are created in the Define Activities process.
Question No : 146

In your project, you have determined the planned quantity of work to be performed. Luckily, a similar project was
successfully completed three months ago, and historical information from that project is readily available. To get a cost
estimate for your project, you multiply the planned quantity of work in your project with the cost per unit obtained from the
previous project. This is a classic example of:

Choice 1 Analogous estimating

Choice 2 Determining resource cost rates

Choice 3 Bottom-up estimating

Choice 4 Parametric estimating

Correct Choice : 4

Justification :
Parametric estimating uses a statistical relationship between historical data and other variables (e.g., square footage in
construction) to calculate a cost estimate for project work.

Reference: PMBOK® Guide - Fifth Edition, page 205


Question No : 147

A flow chart is a diagram, which shows how various elements of a system relate and includes tools like "cause and effect
diagrams" and "flowcharting." As a project manager, you find "cause and effect diagrams" a useful tool for:

Choice 1 Showing the relationship between two variables

Choice 2 Identifying which factors may influence specific variables of a product or process under development or in
production

Choice 3 Determining whether or not a process is stable or has predictable performance

Choice 4 Illustrating how various factors might be linked to potential problems or effects

Correct Choice : 4

Justification :
Option 4: This is the correct answer. Cause and effect diagrams, also called Ishikawa diagrams or fishbone diagrams
illustrate how various factors might be linked to potential problems or effects.

Reference: PMBOK® Guide - Fifth Edition, page 236

PMstudy.com comments:

Option 1: This refers to scatter diagrams, which shows the relationship between two variables
Option 2: This refers to Design of Experiment (DOE), which identifies which factors may influence specific variables of a
product or process under development or in production.
Option 3: This refers to Control Charts, which are used to determine whether or not a process is stable or has predictable
performance.
Question No : 148

Your project has two hundred and fifty people from five different countries working to create a software solution to be
deployed across fifteen countries. One of your project leads continually misses project deadlines and undermines your
authority in front of other team members. In a stakeholder meeting, you want to settle a particular conflict with this project
lead quickly and exert your authority. What conflict management technique would you use?

Choice 1 Confronting

Choice 2 Forcing

Choice 3 Withdrawing

Choice 4 Avoiding

Correct Choice : 2

Justification :
Forcing is a conflict management technique where you exert your viewpoint at the expense of the viewpoints of others and
is used if you have the authority and have to settle conflicts quickly.

Reference: PMstudy.comments
Question No : 149

In your project, you are about to complete the Plan Risk Responses process. Completion of certain tasks marks the end of
the process. Which one of the following is NOT that task?

Choice 1 People have been identified to take responsibility for each agreed-to and funded risk response.

Choice 2 High priority risks are addressed in detail in the risk register.

Choice 3 Low priority risks are included in the risk mitigation plan if they occur.

Choice 4 Negative risks have been considered for avoidance, transference or mitigation.

Correct Choice : 3

Justification :
Risks judged to be of low priority are included in a watch list for periodic monitoring.

Reference: PMBOK® Guide - Fifth Edition, page 347


Question No : 150

A contract which includes features of cost reimbursable and fixed price types of contract is a:

Choice 1 Fixed price plus incentive fee contract

Choice 2 Cost plus award fee contract

Choice 3 Time and material contract

Choice 4 Cost plus fixed fee contract

Correct Choice : 3

Justification :
Time and material contracts are a hybrid type of contractual arrangements that contain aspects of both cost-reimbursable
and fixed-price contracts.

Option 1: This type of contract involves fixed-price features which allow for deviation from performance, with financial
incentives tied to achieving agreed metrics.
Option 2: In this type of contract, the seller is reimbursed for all legitimate costs, but the majority of the fee is only earned
based on the satisfaction of certain broad subjective performance criteria defined and incorporated into the contract.
Option 4: In this type of contract, the seller is reimbursed for all allowable costs for performing the contract work, and
receives a fixed fee payment calculated as a percentage of the initial estimated project costs.

Reference:PMBOK® Guide - Fifth Edition, pages 363 and 364


Question No : 151

You are managing a team consisting of members from four different countries; you realize that some cultural differences
among your team members are hampering the progress of your project. In this context, what should you do?

Choice 1 Conduct team building activities in which most of the team members can participate actively.

Choice 2 Train your team members on project objectives.

Choice 3 Train your team members on the broad objectives of your organization.

Choice 4 Provide training to your team members regarding cultural diversities among different countries along with training
on project objectives and the company culture.

Correct Choice : 4

Justification :
When working with team members of different countries, to ensure that cultural diversities do not hamper the progress of
the project, the project manager must provide training to her team members regarding cultural diversities among various
countries, project goals, and the ethics and culture of the company.

Reference: PMstudy.com comments


Question No : 152

You recently joined ABC bank as a project manager. Although the project is within budget and doing well, recently there
have been several change requests. The outgoing project manager was using twelve project management processes
during the project execution. Given this information, which of the following could be the most likely cause of frequent
change requests?

Choice 1 The new project manager was appointed for a very critical project and proper training was not provided.

Choice 2 All stakeholders were not identified.

Choice 3 New methods of communication like email and SMS were not used as part of project communication
management.

Choice 4 Very few project management processes were used by the outgoing project manager.

Correct Choice : 2

Justification :
We should try to find out the reason for the problem. The question clearly states that recently there have been several
change requests. The root cause of the problems is that all stakeholders are not identified.

Training (option 1), communication methods (option 3) or the number of project management processes (option 4) cannot
be contributing factors to the increase in change requests. However, if some stakeholders are not identified (option 2),
there is a possibility that some requirements of those stakeholders are left out. This is the most important reason for
increase in change requests.

Reference: PMstudy.com comments


Question No : 153

A non-governmental agency authorizes a project to provide potable water systems, latrines and sanitation education to
low-income communities. The need for the project arose due to:

Choice 1 Market need

Choice 2 Business need

Choice 3 Social need

Choice 4 Legal requirement

Correct Choice : 3

Justification :
The business case is created as a result of... social need (e.g., a non-governmental organization in a developing country
authorizing a project to provide potable water systems, latrines and sanitation education to communities suffering from high
rates of cholera).

Reference: PMBOK® Guide - Fifth Edition, page 69


Question No : 154

Items at the lowest level of a Work Breakdown Structure are called:

Choice 1 Work Packages

Choice 2 WBS Dictionaries

Choice 3 Work Components

Choice 4 WBS, Work Components, Work Packages or WBS Dictionaries - depending on the context in which the term is
used

Correct Choice : 1

Justification :
The planned work is contained within the lowest level of WBS components, which are called work packages.

Reference: PMBOK® Guide - Fifth Edition, page 126


Question No : 155

You are the project manager on a Software Creation Project. If the number of critical paths in the project increases, but the
duration of the project remains the same, what should the project manager do?

Choice 1 Perform crashing to complete project on time

Choice 2 Fast track the project

Choice 3 Perform additional risk planning

Choice 4 Decrease the scope of the project

Correct Choice : 3

Justification :
If the number of critical paths increases in the project, delay in any one of the critical paths has the potential to delay the
project. The risk of the project (in meeting the project schedule) increases; hence additional risk planning has to be
performed.

Reference: PMstudy.com comments


Question No : 156

Your project is in the execution stage. NPV of your project is -$200,000 and IRR is 5%. CPI is 1.2 and SPI is 0.8. What is
the recommended action?

Choice 1 Cancel the project since NPV is negative

Choice 2 Cancel the project since IRR is very low

Choice 3 Crash your project

Choice 4 Try to improve the NPV

Correct Choice : 3

Justification :
Option 3 is the most recommended action. CPI is greater than 1 and SPI is less than 1. Since SPI is less than 1, this
means that project is behind schedule; hence it is recommended to crash the project to bring it on schedule.

Please note that crashing may increase costs. Since your project has CPI greater than 1, cost will not be a concern.

Options 1, 2, and 4 are not recommended actions. NPV and IRR are project selection criteria (selection of projects is done
in the initiation stage). Since this project is already in the execution phase, NPV and IRR should not be considered.

Reference: PMstudy.com comments


Question No : 157

A description of how a project management team should implement the overall intention and direction of an organization
with regard to quality (as articulated by top management) is available in:

Choice 1 Operational definitions

Choice 2 Quality management plan

Choice 3 Checklists

Choice 4 Quality policy

Correct Choice : 2

Justification :
The quality management plan describes how the project management team plans to meet the quality requirements set for
the project. The performing organization`s quality policy, as endorsed by senior management, sets the organization`s
intended direction on implementing its quality management approach.

Reference: PMBOK® Guide - Fifth Edition, pages 234 and 241


Question No : 158

You have recently taken over as project manager. In your initial meeting, you first notice that there is too much conflict
among the project team members, which harms productivity and working relationships. In this context, which of the
following would not be a technique you would use to reduce conflict in your team?

Choice 1 Establish team ground rules

Choice 2 Establish group norms

Choice 3 Minimize differences of opinion among team members

Choice 4 Better manage the communication channels

Correct Choice : 3

Justification :
Team ground rules, group norms, and solid project management practices like communication planning and role definition
reduce the amount of conflict. When managed properly, differences of opinion can lead to increased creativity and better
decision making.

Reference: PMBOK® Guide - Fifth Edition, pages 282 and 283


Question No : 159

Your company is a pioneer in the construction industry. The government recently floated a tender for setting up a new
airport. Since you do not have all the requisite skills within the company, you enter into a joint venture with a leading airport
construction company to bid jointly for the government contract. This is an example of:

Choice 1 Risk exploitation

Choice 2 Risk sharing

Choice 3 Risk enhancing

Choice 4 Risk mitigating

Correct Choice : 2

Justification :
Strategies for positive risks or opportunities (share): Sharing a positive risk involves allocating some or all of the ownership
of the opportunity to a third party who is best able to capture the opportunity for the benefit of the project. Examples of
sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint ventures, which can
be established with the express purpose of taking advantage of the opportunity so that all parties gain from their actions.

Reference: PMBOK® Guide - Fifth Edition, page 346


Question No : 160

As a project manager, you have created a document that describes the procurement item in sufficient detail to provide a
basis for the sellers to determine if they can provide the item. This document is referred to as:

Choice 1 Statement of work

Choice 2 Contract

Choice 3 Procurement document

Choice 4 Procurement statement of work

Correct Choice : 4

Justification :
Procurement Statements of Work: The statement of work (SOW) for each procurement is developed from the project scope
baseline and defines only that portion of the project scope that is to be included within the related contract. The
procurement SOW describes the procurement item in sufficient detail to allow prospective sellers to determine if they are
capable of providing the products, services, or results.

Option 1: Statement of work is a narrative description of products and services to be delivered by the project. Statement of
work is provided by the sponsor in case of internal projects, but for external projects, it is provided by the customer.

Option 2: Contract is a mutually binding agreement that obligates the seller to provide the specified product or service or
result and obligates the buyer to pay for it.

Option 3: Procurement document is a document utilized in bid and proposal activities, which includes the buyer’s invitation
for bid, invitation for negotiations, request for information, request for quotation, request for proposal and seller’s
responses.

Reference: PMBOK® Guide - Fifth Edition, pages 367 and 368


Question No : 161

You are a member of the committee which is appointed to oversee the awarding of an important contract in your company.
In this context, which of the following cannot be treated as conflict of interest situations?

Choice 1 Your friend bids for the contract and you inform the committee and the project sponsor about it.

Choice 2 Your relative bids for the contract and you do not inform the project sponsor about it.

Choice 3 Your close friend bids for the contract and you refrain from participating in the contract awarding decision process
without informing your sponsor.

Choice 4 Your friend bids for the contract and you make sure that the contract is awarded to him.

Correct Choice : 1

Justification :
Conflict of interest arises when personal interests out-weigh professional considerations. A person`s associations and
affiliations with others can also lead to conflict of interest.

Please note that if there is a conflict of interest situation, inform the appropriate stakeholders and distance yourself from the
conflict situation, if possible.

Reference: PMstudy.com comments


Question No : 162

Earlier you were working at the helpdesk of ABC company managing a team. Your job primarily involved handling customer
queries, analyzing customer feedback, and supervising your team. You have recently been re-assigned to a new project
involving integration of the helpdesk activities with an ERP (Enterprise Resource Planning) package. This project will
improve efficiency in the company and help in integrating all inter-related activities. In this context, which of the following is
not a difference between project work and work at helpdesk?

Choice 1 The objective of the project is to meet strategic objectives of the company. The objective of the helpdesk was to
sustain the business.

Choice 2 A project has to be planned, executed, and controlled, and it is not so in the case of helpdesk.

Choice 3 As part of the project, you are creating a new information system, but nothing unique was being created as part of
the helpdesk activities.

Choice 4 Unlike a project, helpdesk was an ongoing operational activity.

Correct Choice : 2

Justification :
Helpdesk work is an operational activity.

Organizations perform work to achieve a set of objectives. In many organizations, the work performed can be categorized as
either project or operations work. These two types of work share a number of characteristics as follows:
a. Performed by individuals
b. Limited by constraints including resource constraints
c. Planned, executed, monitored and controlled

Both projects and operations need to be planned, executed, and controlled. However, projects and operations differ
primarily in that operations are ongoing and produce repetitive products, services, or results. Projects are temporary, and
end.
Question No : 163

Project Integration Management includes the processes and activities needed to identify, define, combine, unify and
coordinate the various processes and project management activities within the Project Management Process Groups.
When a project is initiated, one of the processes taken up early on in the project initiation stage is:

Choice 1 Identify Stakeholders

Choice 2 Define Scope

Choice 3 Plan Human Resource Management

Choice 4 Develop Project Management Plan

Correct Choice : 1

Justification :
Identify Stakeholders is the process of identifying the people, groups, or organizations that could impact or be impacted by
a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their
interests, involvement, interdependencies, influence, and potential impact on project success... It is critical for project
success to identify the stakeholders early in the project or phase and to analyze their levels of interest, their individual
expectations, as well as their importance and influence.

Reference: PMBOK® Guide - Fifth Edition, pages 393 and 394

PMstudy.com comments: Identify Stakeholders is done as part of Initiating Process Group.


Question No : 164

Inspection includes activities such as measuring, examining, and testing undertaken to determine whether results conform
to requirements. Which of the following terms does not refer to Inspection?

Choice 1 Product review

Choice 2 Audit

Choice 3 Walkthrough

Choice 4 Stage-gate

Correct Choice : 4

Justification :
Inspections are sometimes called reviews, product reviews, audits, and walkthroughs.

Reference: PMBOK® Guide - Fifth Edition, page 135

PMstudy.com comments: Stage gates are also referred to as phase-end reviews or kill points. They are different from
Inspection.
Question No : 165

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes
to the schedule baseline. During this process, you undertake various activities that allow you to identify any changes, or
potential changes to the project schedule. In this context, which of the following is NOT true about the Control Schedule
process?

Choice 1 Project manager determines the current status of the project schedule

Choice 2 Project manager influences the factors that create schedule changes

Choice 3 Project manager takes the anticipated changes through the change control process.

Choice 4 Project manager manages the actual schedule changes as they occur

Correct Choice : 3

Justification :
The Control Schedule process is concerned with determining the current status of the project schedule, influencing the
factors that create schedule changes, determining if the project schedule has changed, and managing the actual changes
as they occur.

Reference: PMBOK® Guide - Fifth Edition, page 186

PMstudy.com comments: The Project Manager will take actual (not anticipated) identified changes through the change
control process. The Project Manager cannot approve all changes to the schedule. They must be approved by the
appropriate stakeholders, as designated in the change control procedures.
Question No : 166

Project A has an initial investment of $3 million, out of which $1.5 million has been spent. Project B, which meets the same
objectives as project A, requires only $1.6 million for completion. Which project should you select?

Choice 1 Project A

Choice 2 Project B

Choice 3 Neither project A nor project B

Choice 4 Both project A and project B

Correct Choice : 1

Justification :
Project A has already spent $1.5 million, the sunk cost, which need not be considered as it has already been incurred and
cannot be avoided. So $1.5 million is required to complete project A. However, $1.6 million is required to complete project
B, so it is better to select project A.

Reference: PMstudy.com comments


Question No : 167

Your company has implemented ISO standards for quality. In this context, which of the following statements regarding
quality is accurate?

A. The objective of a quality audit is to compare project deliverables against the product requirements as defined in the
WBS.
B. Process analysis identifies the needed improvements from an organizational and technical standpoint.
C. Control Quality is the process of monitoring and recording results of executing the quality activities to assess
performance and recommend necessary changes.
D. The Quality management plan describes how the project management team will implement the performing
organization`s quality policy.

Choice 1 B, C and D

Choice 2 C and D

Choice 3 B and D

Choice 4 A, B and C

Correct Choice : 1

Justification :
A quality audit is a structured, independent process to determine if project activities comply with organizational and project
policies, processes, and procedures.

Reference: PMBOK® Guide - Fifth Edition, page 247


Question No : 168

You are the manager of a project, which aims to start 15 more schools in your state. You have to deal with several non-
government organizations, state agencies, sponsors, and other stakeholders. There are conflicts between stakeholders. In
this context, you should know that maximum intensity of conflicts happens due to:

Choice 1 Personality conflict, cost, and administration

Choice 2 Risk management, status meetings, and Define Scope

Choice 3 Schedules, priorities, and manpower

Choice 4 Administration, technical issues, and procedures

Correct Choice : 3

Justification :

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, pages 302
Question No : 169

Probability distributions are popular tools of the Perform Quantitative Risk Analysis process. In this context, which of the
following statements on probability distributions is not accurate?

Choice 1 Beta Distribution is a continuous distribution.

Choice 2 Triangular distribution is a discrete distribution.

Choice 3 Discrete distributions can be used to represent uncertain events such as a possible scenario in a decision tree.

Choice 4 Uniform distributions can be used only if there is no obvious value that is more likely than any other between
specified high and low bounds.

Correct Choice : 2

Justification :
Beta distribution and Triangular distribution are two examples of widely used continuous distributions.

Reference: PMBOK® Guide - Fifth Edition, page 337, figure 11-14


Question No : 170

As a project manager, you would like to develop a procurement statement of work. This would require (select the best
answer):

Choice 1 Scope statement and WBS

Choice 2 WBS only

Choice 3 Contract

Choice 4 Scope baseline

Correct Choice : 4

Justification :
This is the correct answer. Scope baseline describes the need, justification, requirements, and current boundaries for the
project. Procurement statement of work for each of the procurements is developed from the project scope baseline.

Options 1 and 2: Scope statement describes the project deliverables and the work required to create those deliverables.
Work breakdown structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the
project team to accomplish the project objectives and create the required deliverables. The creation of procurement
statement of work does not directly require the scope statement and WBS or the latter alone.
Option 3: Contract is a mutually binding agreement that obligates the seller to provide the specified product or service or
result and obligates the buyer to pay for it. Creation of procurement statement of work does not directly rely on contract.

Reference: PMBOK® Guide - Fifth Edition, page 366 and 367


Question No : 171

Your company has been awarded an engineering, procurement and construction (EPC) contract to build a combined-cycle
gas turbine (CCGT) plant. You have been assigned to manage this project, but your expertise as a project manager is in
the field of information technology. In this context, what should you do?

Choice 1 Explain to your senior management about your knowledge and experience.

Choice 2 Ask for adequate training in your new area of operation.

Choice 3 Accept the responsibility and put in your best efforts.

Choice 4 Reject the assignment stating that it is beyond your capabilities and experience.

Correct Choice : 3

Justification :
A project manager must always be truthful while reporting about her qualification, experience, background, and past
performances to one`s prospective employers, customers, etc.

PMI believes that a project manager need not be a subject matter expert, and similar project management skills can be
used across different industries.

Reference: PMstudy.com comments


Question No : 172

You are working as the project manager simultaneously on four (4) projects in your organization, which vary in complexity.
In this context, which of the following does not contribute to the success of the projects?

Choice 1 Project Manager must comply with the requirements to meet stakeholders` needs and aspirations

Choice 2 Applying knowledge, skills, and processes uniformly across various projects in your portfolio

Choice 3 Balancing competing needs of time, cost, and quality

Choice 4 Using a defined approach to adapt the product specifications and plans to meet project and product requirements

Correct Choice : 2

Justification :
For any given project, the project manager, in collaboration with the project team, is always responsible for determining
which processes are appropriate, and the appropriate degree of rigor for each process.

Reference: PMBOK® Guide Fifth Edition, page 48

PMstudy.com comments: Knowledge, skills, and processes will not always be applied uniformly on all projects. Since the
projects are of varying complexity levels, the same processes may not be valid for all the four (4) projects. Please note that
options 1, 3, and 4 are requirements for a project to be successful.
Question No : 173

You are creating a project charter to formally authorize the project. A project statement of work will be helpful in creation of
the charter. In this context, which of the following is NOT a part of project statement of work?

Choice 1 Product scope description

Choice 2 Business need

Choice 3 Strategic plan

Choice 4 Project manager name

Correct Choice : 4

Justification :
The project statement of work references product scope description, business need, and strategic plan.

Reference: PMBOK® Guide - Fifth Edition, page 68

PMstudy.com comments: Although the project manager should be identified as soon as possible (preferably during
Initiating process), this is not mandatory. Also, this information would not be included in the statement of work.
Question No : 174

Project scope management includes the processes required to ensure that the project includes all the work required and
only the work required to complete the project successfully. In this context, the project charter plays a very important role
because it:

Choice 1 Provides a list of project deliverables

Choice 2 Provides high-level project description and product characteristics

Choice 3 Provides deliverable oriented grouping of work components

Choice 4 Describes the project plan parameters, i.e., quantifiable criteria that must be met for the project to be considered
successful

Correct Choice : 2

Justification :
The project charter provides the high-level project description and product characteristics.

Reference: PMBOK® Guide - Fifth Edition, page 121

PMstudy.com comments: Option 1 refers to benefits of scope statement. Option 3 refers to benefits of work breakdown
structure. Option 4 refers to project plan parameters, which is not defined in the PMBOK® Guide - Fifth Edition.
Question No : 175

In your project, you need to determine how each task is related to other tasks. This will ultimately help you develop the
schedule for the project. In which process will you determine these relationships?

Choice 1 Define Activities

Choice 2 Estimate Activity Durations

Choice 3 Sequence Activities

Choice 4 Develop Schedule

Correct Choice : 3

Justification :
Sequence Activities is the process of identifying and documenting relationships among the project activities.

Reference: PMBOK® Guide - Fifth Edition, page 153


Question No : 176

Please refer to the following diagram:

What is the Earned Value (EV)?

Choice 1 $5,000

Choice 2 $10,000

Choice 3 $11,000

Choice 4 $12,500

Correct Choice : 4
Justification :

Earned Value (EV)


= The sum of the approved cost estimates for activities completed during a given period
= Estimated cost of work that is completed after day 11
= $5,000 + $5,000 + $5,000 x 0.50 = $12,500 (because Tasks A and B are completed and Task C is 50% complete)

Acronym Term Description Formula


Planned Value
PV Physical work to be scheduled,
including the estimated value of the
(Budgeted Costs for
(BCWS) work
Work Scheduled)
Earned Value
EV
Physical work actually accomplished,
(Budgeted Costs for including estimated value of this work
(BCWP)
Work Performed)
AC Actual Cost Actual cost of the work completed
Negative SV: Behind Schedule
SV Schedule Variance EV – PV
Positive SV: Ahead of Schedule
Negative CV: Over Budget
CV Cost Variance EV – AC
Positive CV: Under Budget
Cost Performance
CPI Value got for $1 of Actual Cost EV/AC = BAC/EAC
Index
Schedule
SPI Progress as a % of Planned Progress EV/PV
Performance Index

Reference: PMstudy.com comments


Question No : 177

You are working on a construction project. You gather data regularly on the productivity of several employees and tasks
(e.g., concrete poured per hour, length of electrical wiring done by a person per day, etc.). You compare this with that of
similar projects embodied in your organizational process assets. This is a real life example of:

Choice 1 Force field analysis

Choice 2 Cost of quality

Choice 3 Benchmarking

Choice 4 Design of experiments

Correct Choice : 3

Justification :
Benchmarking involves comparing actual or planned project practices to those of comparable projects to identify best
practices, generate ideas for improvement, and provide a basis for measuring performance.

Reference: PMBOK® Guide - Fifth Edition, page 239


Question No : 178

In the executing phase of your project, you lose some key resources. Some new people have joined, and you (the project
manager) set up a meeting to get the team together. What should be the most important agenda item for this meeting?

Choice 1 Discussing team building activities

Choice 2 Inviting the team members to share their past project experiences

Choice 3 Reviewing WBS and responsibilities of all team members

Choice 4 Planning risk responses for existing risks

Correct Choice : 3

Justification :
The most important agenda item for the meeting should be reviewing of WBS to ensure that responsibilities are assigned.
Reviewing WBS and responsibilities of all team members helps in establishing clear expectations on acceptable behavior
and roles of all team members.

Early commitment to clear guidelines decreases misunderstandings and increases productivity.

Reference: PMstudy.com comments


Question No : 179

In your project, you have completed the Identify Risks process to determine which risks may affect the project, and a risk
register has been prepared. What should you do NEXT?

Choice 1 Risk probability and impact assessment

Choice 2 Avoid, transfer or mitigate negative risks

Choice 3 Exploit, share or enhance opportunities

Choice 4 Risk audits

Correct Choice : 1

Justification :
After the Identify Risks process, the next step is the Perform Qualitative Risk Analysis process. Risk probability and impact
assessment is one of the tools and techniques for the Perform Qualitative Risk Analysis process.

Reference: PMBOK® Guide - Fifth Edition, page 312 (figure 11-1)

PMstudy.com comments:

Option 2 (Avoiding, transferring or mitigating negative risks) is done during the Plan Risk Responses process, which
happens after the Perform Qualitative Risk Analysis and the Perform Quantitative Risk Analysis processes.

Option 3 (Exploiting, sharing or enhancing opportunities) is done during the Plan Risk Responses process, which happens
after the Perform Qualitative Risk Analysis and the Perform Quantitative Risk Analysis processes.

Option 4 (Risk audits) is a tool for the Control Risks process, which happens after the Perform Qualitative Risk Analysis,
the Perform Quantitative Risk Analysis and the Plan Risk Responses processes.
Question No : 180

The buyer wants to provide a single source contract, but your sponsor tells you that sole source contract would be better
for the company. In this context, how do sole source contracts differ from single source contracts?

Choice 1 Single source contracts are forms of non-competitive procurements, whereas sole source contracts are forms of
competitive procurements.

Choice 2 Single source contracts are forms of competitive procurements, whereas sole source contracts are forms of non-
competitive procurements

Choice 3 In single source contracts, you (buyer) contract a seller because he is your preferred seller, whereas in sole
source contracts, you (buyer) contract a seller because there are no other sellers for your required procurement
item.

Choice 4 Unlike sole source contracts, single source contracts help an organization to save time because they do not
involve procurement process before bids or proposals are received.

Correct Choice : 3

Justification :
Options 1 and 2: Both types are forms of non-competitive procurements.

Option 3: This is the correct answer. The major difference between single source contracts and sole source contracts—
though both are non-competitive forms of procurements— is that in single source contracts, the contract is awarded to a
seller because he is the organization’s preferred seller, whereas in sole source contracts, the contract is awarded to a
seller because there are no other sellers for the organization’s required procurement item.

Option 4: Sole source contracts also help organizations save time.

Reference: PMstudy.com study notes


Question No : 181

You and your sponsor are discussing the financial benefits of selecting between two similar projects - project A and project
B. When evaluating the projects, you realize that project A will cause some amount of short-term environmental damage
but minimal long-term environmental problems. In this context, what will be the best course of action?

Choice 1 Explain to your senior management about the potential environmental damage caused by project A and persuade
them to discard the project.

Choice 2 Select the project A as there is only low probability of causing long-term environmental damage.

Choice 3 Try to find solutions to the environmental damage that may occur in the future because of project A.

Choice 4 Undertake the project A but try to minimize the environmental damage, if any.

Correct Choice : 1

Justification :
Project managers, while making decisions regarding a project, should preferably select a project with no(or minimal)
negative impact on the environment, community and society.

Reference: PMstudy.com comments


Question No : 182

Which of the following statements relating to product-oriented processes and project management processes is accurate?

Choice 1 Product-oriented processes are defined in the project management life cycle

Choice 2 Product-oriented processes help in creating the project`s product

Choice 3 Project management processes rarely interact with product-oriented processes

Choice 4 Project management processes apply globally but to certain industry groups

Correct Choice : 2

Justification :
Product-oriented processes specify and create the project`s product.

Reference: PMBOK® Guide Fifth Edition, page 47

PMstudy.com comments:

Please note:
a. Option 1: Product-oriented processes are typically defined by the project life cycle (PMBOK® Guide Fifth Edition, page
47).
b. Option 3: Project management processes and product-oriented processes overlap and interact throughout the life of a
project (PMBOK® Guide Fifth Edition, page 48).
c. Option 4: Project management processes apply globally and across industry groups (PMBOK® Guide Fifth Edition, page
48).
Question No : 183

A new project manager has been appointed to manage a project which was terminated six months earlier because of
funding related issues. The project manager wants to find out the exact reasons for the termination of the project. He also
wants to know which deliverables were produced from the terminated project. Which of the following document(s) should
the project manager refer to?

Choice 1 Final product, service, or result transition

Choice 2 Project files

Choice 3 Historical information

Choice 4 Project closure documents

Correct Choice : 4

Justification :
If the project was terminated prior to completion, the formal documentation indicates why the project was terminated and
formalizes the procedures for the transfer of the finished and unfinished deliverables of the cancelled project to others.

Reference: PMBOK® Guide - Fifth Edition, page 104


Question No : 184

In your project, you are working with your customer to formalize acceptance of the completed project deliverables. This is
done as part of:

Choice 1 Planning

Choice 2 Executing

Choice 3 Monitoring and Controlling

Choice 4 Initiating

Correct Choice : 3

Justification :
Validate Scope is the process of formalizing acceptance of the completed project deliverables. This process belongs to the
Monitoring and Controlling Process Group.

Reference: PMBOK® Guide - Fifth Edition, page 133 and page 61 (table 3-1)
Question No : 185

You are the project manager on a research project. You have received the news that your shipment of supplies will be
delayed by two weeks due to bad weather. What will be your FIRST step?

Choice 1 Fast track the project to ensure that the project schedule is not delayed.

Choice 2 Determine how much float is available in that task.

Choice 3 Try to get additional supplies from an alternate location as soon as possible.

Choice 4 Take corrective action to minimize the impact of delay.

Correct Choice : 2

Justification :
Before you take corrective measures, determine the impact of the delay in shipment. For example, if the task has 3 weeks
float, you need not resort to options 1, 3, or 4.

Reference: PMstudy.com comments


Question No : 186

Please refer to the following diagram:

What is the status of the project?

Choice 1 Behind schedule, Under budget

Choice 2 Ahead of schedule, Under budget

Choice 3 Ahead of schedule, Over budget

Choice 4 Behind schedule, Over budget

Correct Choice : 3

Justification :
Earned value (EV)
= The sum of the approved cost estimates for activities completed during a given period
= Estimated cost of work that is completed after day 11
= $5,000 + $5,000 + $5,000 x 0.50 = $12,500 (because Task A, Task B are complete, Task C is 50% complete)

Planned value(PV)
= Planned work to be completed after day 11
= $5,000 + $5,000 + $5,000 x (1/5) (because at end of day 11, according to our plan, Task A, Task B should be complete;
Task C only one day out of 5 days should be complete, i.e., 20% complete ($1,000 of work should be done))
= $11,000

Actual cost (AC)


= Actual Cost of work completed
= $13,000

Schedule variance (SV)


= EV - PV = $12,500 - $11,000 = $1,500
Since SV is positive, we are ahead of schedule.

Cost variance (CV)


= EV - AC = $12,500 - $13,000 = - $500
Since CV is negative, we are over budget.

Acronym Term Description Formula


Planned Value
PV Physical work to be scheduled,
including the estimated value of the
(Budgeted Costs for
(BCWS) work
Work Scheduled)
Earned Value
EV
Physical work actually accomplished,
(Budgeted Costs for including estimated value of this work
(BCWP)
Work Performed)
AC Actual Cost Actual cost of the work completed
Negative SV: Behind Schedule
SV Schedule Variance EV – PV
Positive SV: Ahead of Schedule
Negative CV: Over Budget
CV Cost Variance EV – AC
Positive CV: Under Budget
Cost Performance
CPI Value got for $1 of Actual Cost EV/AC = BAC/EAC
Index
Schedule
SPI Progress as a % of Planned Progress EV/PV
Performance Index

Reference: PMstudy.com comments

Question No : 196

Please refer to the following diagram:

You know that current variances are atypical, i.e., similar variances will not occur in the future. What is the Estimate at
Completion (EAC)?

Choice 1 $15,000

Choice 2 $20,000
Choice 3 $20,500

Choice 4 $22,000

Correct Choice : 3

Justification :

Earned Value (EV)


= The sum of the approved cost estimates for activities completed during a given period
= Estimated cost of work that is completed after day 11
= $5,000 + $5,000 + $5,000 x 0.50 = $12,500 (because Tasks A and B are complete, Task C is 50% complete)

Actual Cost (AC)


= Actual Cost of work completed
= $13,000

Budget at Completion (BAC)


= Budget for the full project
= $5,000(Task A) + $5,000(Task B) + $5,000(Task C) + $5,000(Task D)
= $20,000

Estimate at completion (EAC) assuming that current variances are atypical


= AC + (BAC - EV)
= $13,000 + ($20,000 - $12,500)
= $13,000 + $7,500
= $20,500

Acronym Term Description Formula


Planned Value
PV Physical work to be scheduled,
including the estimated value of the
(Budgeted Costs for
(BCWS) work
Work Scheduled)
Earned Value
EV
Physical work actually accomplished,
(Budgeted Costs for including estimated value of this work
(BCWP)
Work Performed)
AC Actual Cost Actual cost of the work completed
Negative SV: Behind Schedule
SV Schedule Variance EV – PV
Positive SV: Ahead of Schedule
Negative CV: Over Budget
CV Cost Variance EV – AC
Positive CV: Under Budget
Cost Performance
CPI Value got for $1 of Actual Cost EV/AC = BAC/EAC
Index
Schedule
SPI Progress as a % of Planned Progress EV/PV
Performance Index

Reference: PMstudy.com comments


Question No : 187

You are the project manager of a car manufacturing company. You understand that there are costs associated with
improvement in quality parameters. To justify costs required to improve quality, you find out the incremental increase in
benefits for an incremental improvement in quality. This is an example of :

Choice 1 Parkinson`s law

Choice 2 Learning Curve theory

Choice 3 Marginal analysis

Choice 4 Maslow`s hierarchy of needs

Correct Choice : 3

Justification :
Marginal analysis balances the additional benefits from an action against the additional cost. It is an acknowledgement that
decisions should be made based on the incremental gains and losses that result from a decision.

Reference: PMstudy.com comments


Question No : 188

While working on the project, you set realistic (and challenging) targets. This is because you know that if extra time is
provided, "Work expands so as to fill the time available for its completion." This is also referred to as:

Choice 1 Herzberg`s Motivation Theory

Choice 2 Learning Curve Theory

Choice 3 Theory Y

Choice 4 Parkinson`s law

Correct Choice : 4

Justification :
Parkinson`s law states that work expands so as to fill the time available for its completion or in brief, "work expands to fill
the time available."

Reference: PMstudy.com comments


Question No : 189

In your project, you identified disaster situations (e.g. floods, earthquakes, etc.) as potential risks. The project sponsor
suggested that, at the project level, no steps could be taken to deal with such risks and recommended creation of a
contingency reserve (with 5% of the project budget) which could be used in case of disaster situations. This is an example
of:

Choice 1 Risk mitigation

Choice 2 Risk acceptance

Choice 3 Risk avoidance

Choice 4 Bad policy decision

Correct Choice : 2

Justification :
Accept: Risk acceptance is a risk response strategy whereby the project team decides to acknowledge the risk and not
take any action unless the risk occurs. This strategy is adopted where it is not possible or cost-effective to address a
specific risk in any other way. This strategy indicates that the project team has decided not to change the project
management plan to deal with a risk, or is unable to identify any other suitable response strategy... The most common
active acceptance strategy is to establish a contingency reserve, including amounts of time, money, or resources to handle
the risks.

Reference: PMBOK® Guide - Fifth Edition, page 345


Question No : 190

In your company, you have a practice of preparing your own estimates of the items to be procured or services to be
availed. This helps you conduct procurements to select seller. This can also be referred to as:

Choice 1 Preferred price

Choice 2 Independent Estimate.

Choice 3 Fixed price contract

Choice 4 Careful cost budgeting

Correct Choice : 2

Justification :
Option 2: For many procurement items, the procuring organization may elect to either prepare its own independent
estimate, or have an estimate of costs prepared by an outside professional estimator, to serve as a benchmark on
proposed responses. Significant differences in cost estimates can be an indication that the procurement statement of work
was deficient, ambiguous, and/ or that the prospective sellers either misunderstood or failed to respond fully to the
procurement statement of work.
Options 1 and 4: The answers provided in these options do not refer to the practice of preparing independent estimates of
the items to be procured or services to be availed.
Option 3: Fixed-price contracts involve setting a fixed price for defined product or service to be provided.

Reference: PMBOK® Guide - Fifth Edition, page 376


Question No : 191

Your company asks you to manage a project of its subsidiary unit in another country. You quickly realize that workers in
the subsidiary unit have poor work ethics as compared with that of your parent company. In this context, which of the
following will be the most appropriate course of action?

Choice 1 Ask your new team to emulate the work ethics of the teams of your parent company.

Choice 2 Take steps to change the work culture of your new team.

Choice 3 Regard your new team as lazy and impose sanctions.

Choice 4 Treat it as cultural differences, and try to determine ways to improve productivity.

Correct Choice : 4

Justification :
The PMI Code of Ethics and Professional Conduct requires a project manager to address things with an open mind and
accept the cultural and ethical diversity that exists between different countries. So, it is not the responsibility of the project
manager to enforce the work-ethics of one`s own country on the people of another country.

Reference: PMstudy.com comments


Question No : 192

Your construction company recently secured a project to build a new overpass on Interstate 10. You have been appointed
as project manager for the assignment. Your company has successfully executed similar projects in the past, and you
would like to refer to the past project documents. At what stage of the project should this be done FIRST?

Choice 1 Executing

Choice 2 Initiating

Choice 3 Planning

Choice 4 Monitoring and Controlling

Correct Choice : 2

Justification :
Organizational Process Assets is an input to Develop Project Charter (which is in the Initiating Process Group).

Reference: PMBOK® Guide Fifth Edition, page 66

PMstudy.com comments: Documentation about previous projects is included in the organizational process assets. In the
Initiating Process Group, documents about similar past projects would help the project team in getting a better
understanding of the project.
Question No : 193

Your project involves creating a launch vehicle for NASA satellites. For successful project implementation, it is important to
coordinate activities with other NASA operational groups and also divide your project into several phases to provide better
management control. To facilitate this, you should (select the BEST answer):

Choice 1 Break the project into several sub-projects.

Choice 2 Use life cycle approach to manage the project.

Choice 3 Develop specific deliverables, which are approved by the sponsor.

Choice 4 Create a very comprehensive project charter.

Correct Choice : 2

Justification :
A project life cycle is the series of phases that a project passes through from its initiation to its closure.

Reference: PMBOK® Guide - Fifth Edition, page 38

PMstudy.com comments:

Option 1: There is nothing in the question that suggests that breaking the project into several sub-projects will be required.
Instead, it mentions clearly that the project should be broken into several phases, which can be done by using a life cycle
approach.
Option 3 and Option 4: These are required for any project, but they do not address the specific requirements of the
question (e.g. coordinating different operational activities and dividing the project into several phases).
Question No : 194

You are the project manager of a software company involved in creating an anti-virus software product. You are in the
execution phase of the project when you realize that a requirement was not included in the product. This is due to an
omission in defining the scope baseline of the project. What should you do?

Choice 1 Issue a change request

Choice 2 Take corrective action

Choice 3 Add the requirements to your product and continue with execution

Choice 4 Take defect repair action

Correct Choice : 1

Justification :
Analysis of scope performance can result in a change request to the scope baseline or other components of the project
management plan.

Reference: PMBOK® Guide - Fifth Edition, page 140

PMstudy.com comments: Since the scope baseline is not fully defined, the requirement has been omitted. To incorporate
the missing requirement, a change request has to be issued.
Question No : 195

A project manager intends to identify and document interactivity dependencies. Which of the following inputs can the
project manager use for this purpose?

A. Project scope statement


B. Activity list
C. Project schedule
D. Activity attributes

Choice 1 B, C and D

Choice 2 A, C and D

Choice 3 A, B and D

Choice 4 A, B and C

Correct Choice : 3

Justification :
Activity list, activity attributes, milestone list, project scope statement are some of the inputs for the Sequence Activities
process.

Reference: PMBOK® Guide - Fifth Edition, page 153 (figure 6-7)

PMstudy.com comments: Project schedule is an output of the Develop Schedule process.


Question No : 196

Please refer to the following diagram:

You know that current variances are atypical, i.e., similar variances will not occur in the future. What is the Estimate at
Completion (EAC)?

Choice 1 $15,000

Choice 2 $20,000

Choice 3 $20,500

Choice 4 $22,000

Correct Choice : 3
Justification :

Earned Value (EV)


= The sum of the approved cost estimates for activities completed during a given period
= Estimated cost of work that is completed after day 11
= $5,000 + $5,000 + $5,000 x 0.50 = $12,500 (because Tasks A and B are complete, Task C is 50% complete)

Actual Cost (AC)


= Actual Cost of work completed
= $13,000

Budget at Completion (BAC)


= Budget for the full project
= $5,000(Task A) + $5,000(Task B) + $5,000(Task C) + $5,000(Task D)
= $20,000

Estimate at completion (EAC) assuming that current variances are atypical


= AC + (BAC - EV)
= $13,000 + ($20,000 - $12,500)
= $13,000 + $7,500
= $20,500

Acronym Term Description Formula


Planned Value
PV Physical work to be scheduled,
including the estimated value of the
(Budgeted Costs for
(BCWS) work
Work Scheduled)
Earned Value
EV
Physical work actually accomplished,
(Budgeted Costs for including estimated value of this work
(BCWP)
Work Performed)
AC Actual Cost Actual cost of the work completed
Negative SV: Behind Schedule
SV Schedule Variance EV – PV
Positive SV: Ahead of Schedule
Negative CV: Over Budget
CV Cost Variance EV – AC
Positive CV: Under Budget
Cost Performance
CPI Value got for $1 of Actual Cost EV/AC = BAC/EAC
Index
Schedule
SPI Progress as a % of Planned Progress EV/PV
Performance Index

Reference: PMstudy.com comments


Question No : 197

In your pharmaceutical company, quality is an important criterion to determine project success. Which of the following is
not an example of cost of nonconformance?

Choice 1 Training

Choice 2 Rework

Choice 3 Loss of reputation

Choice 4 Warranty

Correct Choice : 1

Justification :
Cost of quality: A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of
conformance) include costs for quality planning, quality control (QC), and quality assurance to ensure compliance to
requirements (i.e., training, QC systems, etc.). Failure costs (cost of nonconformance) include costs to rework products,
components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.

Reference: PMBOK® Guide - Fifth Edition, pages 235 and 535


Question No : 198

You are promoted to a new role in your company to replace someone who recently retired. To be an effective leader, which
of the following should you do FIRST?

Choice 1 Enroll in appropriate training programs

Choice 2 Understand all the leadership theories

Choice 3 Find out your strong and weak areas

Choice 4 Take advice from the person who retired from the company

Correct Choice : 3

Justification :
(Option 3) Finding out your strong and weak areas helps determine how you can do the job better and become an effective
leader. This may also result in identifying the needed training programs. Therefore, option 1(enroll in appropriate training
programs) and option 2 (learning all leadership theories) are not recommended. Option 4 (Taking advice from the person
who retired from the company) is recommended, but this can be done after determining your strong and weak areas.

Reference: PMstudy.com comments


Question No : 199

While doing a cost-benefit analysis, you determine that a new project has 60% probability of earning a profit of $1,000,000
or 30% probability of incurring a loss of $500,000. What is the expected monetary value of the decision?

Choice 1 $400,000

Choice 2 $600,000

Choice 3 $450,000

Choice 4 $200,000

Correct Choice : 3

Justification :
Expected monetary value (EMV) analysis is a statistical concept that calculates the average outcome when the future
includes scenarios that may or may not happen (i.e. analysis under uncertainty). The EMV of opportunities are generally
expressed as positive values, while those of threats are expressed as negative values... EMV for a project is calculated by
multiplying the value of each possible outcome by its probability of occurrence and adding the products together.

Reference: PMBOK® Guide - Fifth Edition, page 339

PMstudy.com notes:
Expected Monetary Value (EMV)
= Sum of (Probability x Impact) of individual decisions
= 0.60 x $1,000,000 – 0.30 x $500,000
= $600,000 - $150,000
= $450,000.
Question No : 200

The buyer has clearly specified that only companies that have revenues greater than $300 million and profitability of more
than $30 million over the past 3 years can bid for the contract. This can also be referred to as:

Choice 1 Procurement negotiation

Choice 2 Source selection criteria

Choice 3 Independent estimate

Choice 4 Make or buy analysis

Correct Choice : 2

Justification :
Source Selection Criteria: Selection criteria are often included as a part of the procurement documents. Such criteria are
developed and used to rate or score seller proposals, and can be objective or subjective.

Reference: PMBOK® Guide - Fifth Edition, page 368