Setting out” is the process of locating points for columns, site boundary level, pile position and other
necessary structural parts according to the construction drawing. Errors should be avoided because the
whole structure will be build based on the respective setting out. A setting out should be made to full fill
the requirements such as length, angle and level.
A temporary bench mark or level should be obtained to start the setting out for the whole building.
A specific height from a near land or from the road level can be obtained as the reference level point for
a setting out. This level point will conduct all over the building boundary area or 1m away from the
building boundary level.
Reason – The excavation work should be done as shown in the engineering drawing.
Mistake that can be achieved if a benchmark level shouldn’t be done on a building setting out is clearly
shown in the following picture.
1|Page
Buidling without Bench mark level – Buidling with Bench mark level
Pole
(Represent the column center)
Specific distance from
boundary
setting out
for column
From this point, can continue the setting out related to the given drawing.
2|Page
Take angular setting out – Right angles setting out to mark the next columns on a straight line. (Use the
Pythagoras theorem)
Finally, after the completion of setting out for the whole building, use a twine to connect the centre
lines of all columns. (Use the bench mark reference height to connect all of them).
3|Page
Setting
out for building, Surveying