1
VOLUME 2 PAGE 1 OF 189
REV. 2
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
SECTION 3.1
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
CONTENTS
PAGE
1. SCOPE OF WORKS 4
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
1. SCOPE OF WORKS
1.1 DESCRIPTION OF WORKS
The works of the Phase 10 Project are spread all over the State of Qatar including both newly
and already developed areas. The details as available at the time of preparation of this Tender
Documents are shown on the Location maps enclosed. The exact coordinates and ground
elevation shall be coordinated with the concerned Authorities during the project execution stage.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
66/11kV Doha Land-2 (Previously called Heart of Doha - 2): New Underground
Transmission Substation to be incorporated within the building constructed by
Developer and including 66kV GIS, 11kV metal enclosed switchgear (AIS/GIS),
66/11kV power transformers, 11/0.415kV station transformers and associated
equipment as required and as indicated elsewhere in the Tender document.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Hamur Super (AHS) from Package S-5. Telecommunication system for other
substations from Phase 10, shall be provided by Others. under the Phase 9, Contract
GTC/240C/2008.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Remote end modifications: The Scope of Works identifies remote end substations and type of
circuit, e.g. OHL/ cable, involved as connecting link between the two substations. In some cases
remote end substations are also part of the Phase 10 project. However there are cases where
remote ends are existing (or under construction as part of the previous Phases) substations /
generating (power) stations. In such cases, the scope of substation Contractor includes all
modifications in Protection, Station Control System, etc, related to the Contractor’s main Scope
of Works, pre-commissioning checks, end to end tests and all commissioning activities as
appropriate at the far end stations as well.
EHV and HV Cables: It is general approach that all EHV and HV cables for connections within
substations and between SWG and OHL terminal gantry / cable compound are in the substation
Contractor Scope of Works. The scope of substation Contractor also includes required co-
ordination with the Contractor(s) of far end substation(s), underground power cable Contractors
and OHL Contractors, for pre - commissioning checks, end to end tests and all commissioning
activities as appropriate. Each Contractor shall be responsible for the works (including his share
of interface points) as per the Scope of the Works. In the case of dispute, if any, KAHRAMAA ’s
decision in this regard shall be final and binding to all concerned parties.
The following is under the Scope of work for substation Contractor when is required to dismantle
oil filled cable to install new XLPE cable:
• Excavation and related civil work
• Removing oil tank
• Disconnect Gauge/manometer panels and control/alarm cables
• Cut and cap existing oil filled cables
• Remove the existing terminations
• Delivery of dismantled material to KAHRAMAA store
Dismantling works: Where substation Contractor Scope of the Works includes replacement of
existing substation, dismantling works of the existing facilities, generally, are not included in the
Scope of substation Contractor. However, site clearance of the area dedicated / required for the
substation Contractor Scope, including existing structures, if any, is obligation of substation
Contractor.
Future development: In the detailed scope of works below, planned future development for
each substation is clearly specified. Bidder should note all requirements for spare bays, space
for future bays, future transformers, capacitor banks, etc. Those should be considered during the
tendering and later in design stage in order to allocate sufficient space, to properly plan and size
cable corridors / ducts, common services such as uninterrupted power supply, HVAC and other
related facilities.
Pricing for civil works: Volume 7 of this Tender document includes site plot layout drawings
and general arrangement drawings for Control / Protection buildings. Commercial offer shall be
based on the subject drawings, considering specified minimum clearances and operation
distance requirements specified in Section 6.3 of this document and related specification,
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
considering actual Scope of Works and offered equipment. Bidder is obliged to ensure that
buildings are properly sized and to provide relevant layout drawings within the Technical offer.
Accordingly, no price variations will be allowed for change of the building size in the later stage
of Contract. Part of civil works such as perimeter fence, access road and filling works will be
measured and paid as “per actual” quantities.
Remote end modifications: Phase 10 specifications shall be apprlicable for all modification
works at remote end substations constructed under Phase 5 or earlier projects and which will be
connected to Phase 10 substations. Therefore protection relays need to be changed. Also
replacement of CTs is anticipated, and for this work separate unit price shall be provided.
It shall be noted that number of substations considered as “Remote End SS” is currently under
construction (Phase VIII, GTC 144 and Phase-IX, GTC 240A/2008, SIEMENS Consortium) and
all the equipment/systems will be under warranty for a period of 2 years from its date of Taking
Over. Hence, in case the equipment/system is still under warranty during modification under the
scope of this project, the Contractor shall execute the works in such a way as not to dilute or
nullify existing warranties in any way, whatsoever. All details of work such as, method
statements, interface requirements, intended subcontractors, etc shall be discussed and agreed
with Kahramaa well in advance of the scheduled commencement date of such works and full
clarity shall be established. The same is applicable for modification on the cable lines which are
part of this Contract.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the switchgear
¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:
11kV Switchgear A:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks
11kV Switchgear B:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks
¾ Three (3) Nos. Power Transformers 132/66kV, 96/120/160 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer
¾ Two (2) Nos. 132kV, 30MVAr Shunt Rectors provided with terminal CTs,
neutral CTs etc.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ All civil works related to new 132/11kV substation including building services
and works related to the diversion of 132kV and 66KV cables as per Appendix
F – Drawings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
Gharafa S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within S/S,
laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.
- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) cable links between 11kV switchgear and 11/0.415, 1000 kVA
Station transformers. Approx. route length: 30 m.
¾ Cable Diversions:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Existing 66kV cable circuits to Qatar University and Feriq Bin Omran shall not be
diverted to new Gharafa SS. They will be dismantled as described under introductory
note of this Section.
The diversion work of remaining cable circuits from existing Gharafa to Gharafa (New)
substation shall be done by the substation Contractor as specified below. The
substation Contractor should make all necessary arrangements to connect cable
termination with new 132kV/66kV GIS. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion. The following existing cable
circuits connected to the existing Gharafa substation shall be diverted to new Gharafa
S/S:
- Gharafa to Duhail: 132kV, 1x800 mm2, XLPE, 160 MVA double circuits
shall be diverted with associated fiber optic cable (24 Fibers) and DTS cable to
132kV GIS at Gharafa New S/S. This line is with cross bonding arrangement.
Approx. route length: 200m. Laying of DTS cable of approximately 2 x 200m
from diversion point to DTS termination box, including splicing with existing
DTS Cable and re-commissioning of DTS Unit in Duhail is included in the
Scope. The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.
- Gharafa to GGM: 132kV, 1x2000 mm2, XLPE, 260 MVA double circuits
shall be diverted with associated fiber optic cable (24 Fibers) to 132 GIS at
Gharafa New S/S, special bonded cable links. Approx. route length: 200m. The
Contractor shall include for all necessary modification works in the earthing
arrangement (cross bonding, single point bonding, mixed bonding) in order to
ensure that required current rating of diverted circuit is maintained. At the
moment this line is connected to Gharafa South West substation however
under the current contract (M/s ABB) it shall be diverted to 132/11kV GGM
substation.
- Gharafa to DNS: 132kV, 1x2000 mm2, XLPE, 225 MVA triple circuits shall
be diverted with associated fiber optic cable (24 Fibers) and DTS cable to 132
GIS at Gharafa New S/S, special bonded cable links. Approx. route length:
200m. Laying of DTS cable of approximately 1 x 200m from diversion point to
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
DTS termination box, including splicing with existing DTS Cable and re-
commissioning of DTS Unit in DNS is included in the Scope. The Contractor
shall include for all necessary modification works in the earthing arrangement
(cross bonding, single point bonding, mixed bonding) in order to ensure that
required current rating of diverted circuit is maintained.
- Gharafa to Gharafa South S/S: 66kV, 1x500 mm2, XLPE, 40 MVA double
circuits shall be diverted with associated fiber optic cable (24 Fibers) to 66kV
GIS at Gharafa New S/S, special bonded cable links. Approx. route length:
200m. The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.
- Gharafa to KTS (Khalifa Town South): 66kV, 3 x 150 mm2, Oil filled Cable,
Cu, 26 MVA double circuits shall be diverted to 66kV GIS at Gharafa New
S/S via 66kV, 1 x 300 mm2, Cu, XLPE Cable and Transition Joints,
including dismantling the terminations at Gharafa S/S and suction the oil from
existing cables*. Approx. route length: 500m. Necessary oil feeding
modification (oil tank, alarm panel, oil pressure gauge manometer, oil pipe
feeding, all test required for oil filled cables and concrete manhole for oil tank
and transition joint) for the existing cables shall be done according to the oil
profile details for existing cables ( design and arrangement shall be submitted
for approval). The exact location of cutting cables or diversion points and detail
design shall be responsibility of Contractor and to be covered by the contract
price. All required works for re-routing (laying) of Pilot Cu Cables shall be
included as well. Contractor shall include for all necessary modification works
in the earthing arrangement (cross bonding, single point bonding, mixed
bonding) in order to ensure that required current rating of diverted circuit is
maintained.
* - The remaining portion of diverted oil filled 66kV Cables will be abandoned along
the route and sealing the ends of oil filled cables left in ground without any
contamination or hazard to the surrounding environment (appropriate method
statement to be submitted for approval prior commencement of works).
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The scope of work shall include but not limited to the following:
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
Duhail Substation:
132/66/11kV Duhail substation is existing transformer feeder substation with GIS built
under Phase 5, Contract GTC/13/2003
GGM Substation:
132/11kV GGM substation is under the construction as part of the separate Contract
(developer M/s Ezdan) and shall be connected to KAHRAMAA network on 132kV
level via LILO of existing 132kV cable line between substations Gharafa South West
(Contract GTC 1, Marubeni) and existing Gharafa (outdoor type substation built
before Phase 4).
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
DNS Substation:
220/132/66/11kV Doha North Super (DNS) is existing substation with GIS built under
Phase 4 project
- Existing BCUs in 3x132kV bays utilized for connection towards Gharafa S/S
shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility
Al Sowaidi Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Duhail Substation:
- All modification, Testing and commissioning, end to end test to make it fully
operational is in present Scope of works.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. If required, additional CT core
or changing of the CTs shall be the responsibility of the Contractor. Optional
price for the (132kV side, 160 MVA Transformer bushing) CT replacement and
all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement.
GGM Substation:
Modifications of the remote substations Gharafa South West and Gharafa shall be
carried out by separate Contract recently awarded to M/s ABB (developer M/s.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Ezdan) and new protection shall be provided for GGM - Gharafa 132kV circuits
accordingly.
- All modification, Testing and commissioning, end to end test to make it fully
operational is under the present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement
DNS Substation:
- All modification, Testing and commissioning, end to end test to make it fully are
included in the present Scope
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. If required, additional CT core
or changing of the CTs shall be the responsibility of the Contractor. Optional
price for the (GIS) CT replacement and all associated works shall be provided
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement
Al Sowaidi Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning, end to end test to make it fully
operational are included in the present Scope
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement
Gharafa South:
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. The new CTs required parameters are given in
Protection standard Specification and standard CT ratio. Contractor has to
perform proper CT sizing calculation for KM review. If required, additional CT
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
core or changing of the CTs shall be the responsibility of the Contractor. CTs
are anticipated to be changed for which separate unit price shall be provided.
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
QP-Halul S/S shall be fed from Ras Girtas Power Station via double circuit 132kV,
250MVA, XLPE cables, which is part of Phase 10 Cable Contract (GTC 372/10). QP-
Halul S/S shall feed power demand on Halul Island via 132kV double circuit, sub
marine cables, approx. length 104km, both submarine cable and substation at Halul
Island shall be constructed by others (QP).
In order to compensate reactive power generated by the submarine cables, four shunt
reactors 132kV, shall be installed by QP: 2 of them at QP Halul S/S at Ras Laffan and
2 at QP Halul Island S/S at the island. Shunt reactors shall be connected to the
132kV Halul feeder bays through separate breakers for shunt reactors, as presented
on the relevant Single Line Diagram (SLD). Cable connection between shunt reactors
and 132kV GIS is within QP SOW. The Contract shall plan and provide sufficient
space for the subject reactors and their connections.
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Two (2) Nos. Outgoing cable / shunt reactor feeder bays (to Halul Island)
- Space for six future bays, three on each side of the switchgear
¾ Establish 33kV, 2500A at 40˚C, 31.5kA / 3 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the switchgear
¾ 2 Nos. 33kV Metallic Neutral Earthing Resistors 25.40 ohm at 50˚C rated for
750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/33kV 100MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with protection at Ras Girtas side shall be installed at QP Halul substation for
all feeders.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Standard specification for the bulk consumers shall apply. Guidelines for
Protection Energy Meter and System Control Requirements for Power Supply
to Bulk Consumers are included in the technical specification as appendices
(ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with SCS using
communication protocol.
¾ Air-conditioning system to cover the GIS buildings, control & relay building and
all other buildings
¾ Fire protection system for power transformers and Tie-in point for shunt
reactors
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ All QP requirements shall be considered while determining the capacity for fire
pumps & fire water tank, fire detection alarm system (Interfacing with QP fire
station), HSSD System inside the cable basements and other areas inside
substation, fire hydrant system including Ring Mains and if any other specific
QP requirements as per QP standards & specifications.
¾ Power cables
- 132kV, 1x630 mm2, XLPE, 100MVA, double circuit, special bonded at QP-
Halul S/S cable links, single point earthed with earth continuity conductor, the
links between new 132/33kV transformers and new 132kV GIS switchgear laid
in unfilled concrete troughs with all accessories. Approx. route length: 100m.
- 132kV, 1x500 mm2, XLPE, 100MVA, double circuits, special bonded at QP-
Halul S/S cable links, single point earthed with earth continuity conductor (four
(4) cables per phase), the links between new 132/33kV transformers and new
33kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m
- 33kV, 1x500 mm2, XLPE, double circuits, cable links between 33kV NER
and 132/33kV, 100 MVA Power Transformers. Approx. route length: 20 m.
- 33kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 33kV switchgear and 33/0.415, 1000 kVA
Station transformers. Approx. route length: 30 m.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Installation for 33kV outgoing cable feeders between 33kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
Spare bays at of 132kV GIS at Ras Girtas Power station shall be used for connection
of new 2x132 kV cables towards QP-Halul substation. All modifications required in the
existing 132kV GIS bays at Ras Girtas Power station shall be carried out under the
present scope of work. The scope of work shall include but not be limited to the
following:
- Re-testing and re-commissioning of the existing GIS bays along with Local
Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Ras Girtas 132kV (Spare) equipped bays, Main-1 ABB make RED670 and
Main-2 Siemens make 7SD522 relays is provided for 132kV line protection.
The new relays/equipment shall be installed at QP Halul substation to match
the protection provided at 132kV Ras Girtas substation end. All modification,
Testing and commissioning, end to end test to make it fully operational shall be
Contractor's responsibility.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾
3.1.3 132/11KV UNIVERSITY SOUTH SUBSTATION
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3s, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:
11kV Switchgear A:
- Space for six future bays, three on each side of the 11kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.
11kV Switchgear B:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the 11kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.
¾ 4Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C rated for
750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with North Road side shall be installed at University South substation for the
respective feeders.
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power Cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, Quadruple circuits, single point earthed
with earth continuity conductor underground cable links at University South
S/S cable links (four (4) cables per phase) between 132/11kV power
transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 60m
- 11kV, 1x630 mm2, XLPE, Quadruple circuit cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
All required modifications in North Road substation shall be carried out under this
project. The scope of work shall include but not limited to the following:
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
- In North Road S/S, 132kV (Spare) equipped bays, Main-1 Siemens make
7SD522 and Main-2 ABB make RED670 is to be provided for 132kV line
protection. The new relays/equipment shall be installed at University South
substation to match the protection provided at 132kV North Road substation
end. All modification, Testing and commissioning, end to end test to make it
fully operational shall be Contractor's responsibility.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Proposed location for DIS substation is within existing Tarig Bin Ziyad Military Camp
for Armed Forces.
¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 3150A at 40oC, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks
¾ One (1) Nos. Power Transformer 132/66kV, 96/120/160 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc The
transformer shall be identical to existing 2 numbers of 132/66kV 160MVA
Trasnformers which are in service at Saliyah substation.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. Shunt Reactors, 132kV, 30MVAr provided with terminal CTs,
neutral CTs etc.
¾ Three (3) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with Saliyah Super side shall be installed at DIS substation for all the feeders
to match the protection at Remote end
¾ Demolition of all existing buildings & fence that are currently located within the
substation plot, removal and disposal of waste materials to Government
approved location.
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings.
¾ Passive fire protection system for all cables in the basement of all buildings.
¾ Power cables:
- 220kV, 1x1600 mm2, XLPE, 315MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 220/132kV power transformers and new 220kV GIS switchgear laid in
unfilled concrete troughs with all accessories. Approx. route length: 150m
- 132kV, 1x2000 mm2, XLPE, 315MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- 132kV, 1x800 mm2, XLPE, 160MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 132/66kV transformers and new 132kV GIS switchgear laid in unfilled
concrete troughs with all accessories. Approx. route length: 100m. Two
160MVA transformers which shall be shifted from Saliyah S/S have air
bushings on 132kV side. The Contractor shall provide all materials and civil
works for connection of outdoor cable sealing ends with transformer.
- 132kV, 1x500 mm2, XLPE, 30MVA, double circuits, solid bonded at DIS
S/S cable links between new 132kV shunt reactors and new 132kV GIS
switchgear laid in unfilled concrete troughs with all accessories Approx. route
length: 100m.
- 66kV, 1x2000 mm2, XLPE, 160MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 132/66kV transformers and new 66kV GIS switchgear laid in unfilled
concrete troughs with all accessories. Approx. route length: 100m. Two
160MVA transformers which shall be shifted from Saliyah S/S have air
bushings on 132kV side. The Contractor shall provide all materials and civil
works for connection of outdoor cable sealing ends with transformer.
- 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at DIS S/S
cable links between 66/11kV transformers and new 66kV GIS switchgear laid
in unfilled concrete troughs with all accessories. Approx. route length: 50m
- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed with
earth continuity conductor underground cable links at DIS S/S cable links (four
(4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, triple circuit cable links between 11kV NER and
66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30m.
¾ Cable Diversions:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The diversion work of cable / OHL circuits and pertaining communication cables (FO
and Cu cables) from existing Saliyah to DIS substation (with exception of the 132kV
cables towards Al Wajbah Super SS, which will be done by Cable Contractor) will
be done by the substation Contractor as specified below. The substation Contractor
should make all necessary arrangements to connect OHL / cable termination with
132kV / 66kV GIS.
Following Existing cable circuits of Saliyah substation shall be diverted to DIS S/S:
- Salyiah South to Salyiah: 132kV, 1x1200 mm2, XLPE, 160 MVA, double
circuits shall be diverted to New Salyiah S/S, special bonded at DIS S/S cable
links, single point earthed with earth continuity conductor, with its own fiber
optic cable (24 Fibers), route length: 250 m. The Contractor shall include for
all necessary modification works in the earthing arrangement (cross bonding,
single point bonding, mixed bonding) in order to ensure that required current
rating of diverted circuit is maintained.
- GT to Salyiah 132kV: 1x500 mm2, XLPE, 75MVA, double circuits with its
own fiber optic cable (24 Fibers) to replace existing oil filled cables, directly
earthed at both ends. Route length: 300 m. Existing oil filled cable shall be
drained up, capped, protected and left in ground.
- 132kV OHL connection between Saliyah and Al Wajbah Super S/S will be
partially replaced by double circuit underground cable line between DIS and
cable compound. Though subject works are in the SOW of cable / OHL Phase
9 Contractors, it is responsibility of S/S Contractor to coordinate related works
with them and make all modifications required at the remote end due to those
changes.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- 66kV double circuit underground cable line between Doha Industrial F and DIS
will be established by Phase X Cable Contractor. However, coordination during
cable testing and connection into the GIS is obligation of Substation Contractor
according to Matrix of interface which is part of this document.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
The scope of work shall include but not be limited to the following:
- Re-testing and re-commissioning of the existing GIS bays in service along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
Saliyah GT Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
DSS Substation:
Doha South Super (DSS) is existing 220/132/11kV substation with 132kV level under
refurbishing as part of Phase 9, Stage 1 Contract GTC/240A/2008 with M/s Siemens.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
the NCC/ENCC including S/S work necessary for NCC/ENCC end to end
testing.
Two 220kV Bays to be connected to new DIS substation will be equipped with
Protection relays under Phase 8 (GTC 144A – Areva).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be provided under this
Contract. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, End to End test, Testing and commissioning and putting into
service of these two circuits is part of this Contract.
- Existing relays are ABB make. REL561 is used for Line Differential and
RET521 is used for Transformer Differential protection. Contractor shall
replace existing relays to match the protection at DIS end. Any additional relay
required to make a complete functional protection system shall be provided by
the Contractor.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.
Saliyah GT Substation:
- New CTs shall be installed to match with new protection and metering
requirements
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility
DSS Substation:
For 2 x 132kV OHL bays which will be connected to DIS substation, complete
functional protection system as per Standard specification shall be provided under
this Contract.
- In DSS S/S, 132kV equipped bays, Main-1 Siemens make 7SD522 and Main-2
ABB make RED670 is proposed to be provided for 132kV line protection under
Phase 9 Contract. The new relays/equipment shall be installed DIS substation
to match the protection provided at 132kV DSS end.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility
Al Wajbah Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
For 2 x 66kV Cable Transformer feeders connected to DIS, existing relays are Alstom
make, MICOM P543 and P631 used as Current Differential and Transformer
Differential respectively.
- Existing CTs in 11kV Incomer A18/A28 feeder shall be replaced (or additional
core provided) to suit F87C+T (Overall differential protection) which shall be
decided during detail engineering The new CTs required parameters are given
in Protection standard Specification and standard CT ratio. Contractor shall
perform proper CT sizing calculation and submit for KM review. If required,
additional CT core or changing of the CTs shall be the responsibility of the
Contractor
- All modification, Testing and commissioning, end to end test to make it fully
operational is under the present Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Two (2) Nos. 132/11 kV, 40MVA Outgoing Transformer bays. For the purposes
of tariff metering VT should be incorporated.
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11kV switchgear
- Space vacuum contactor panel, equipped with protection and the power-factor
controlled switching for the future capacitor banks
¾ Two (2) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for all feeders.
¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.
¾ All civil works related to new 132/11kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power Cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuit, single point earthed with
earth continuity conductor underground cable links (four (4) cables per
phase) between 132/11kV power transformers and 11kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m
- 11kV, 1x630 mm2, XLPE, double circuit, cable links between 11kV NER and
132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m
- Diversion works, Loop in / Loop out (LILO) of the existing 132kV, 1x1000mm2,
XLPE, 160MVA underground cable circuits with fiber optic cable (24 Fibers)
between Abu Nakhla Super and Doha Industrial E to new 132kV GIS are in
the SOW of S/S Contractor. Cable route is already diverted into substation plot
and cable joints are installed with sufficient sneaking provided. The Contractor
shall make all necessary arrangements to disconnect cables at joint bay, divert
them, connect into 132kV GIS and commission the same.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
ANS Substation:
DIE substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
ANS Substation:
- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at Logistic Village substation to match the
protection provided at 132kV ANS substation end.
- All modification, Testing and commissioning; end to end test are included in the
present Scope
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
DIE substation:
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Eight (8) Nos. Outgoing Overhead line feeder bays, two of them with GI bus –
duct for OHL direct connection
- Space for six future bays, three on each side of the switchgear.
¾ Establish 11kV, 2500A at 40˚C , 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for vacuum contactor panel equipped with protection and power-factor
controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) sets of 132kV outdoor lightning arresters for the incoming / outgoing
overhead lines.
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Al Kara’ana S/S cable
links (four (4) cables per phase) between 11kV switchgear and 132/11kV
power transformers within S/S, laid in unfilled concrete troughs with all
accessories. Approx. route length: 30m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 60 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the OHL Contractor for the termination of the
conductors at both ends
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Proposed location for Madinat Al Kebaan substation is located approximately half way
between Ras Girtas Power Plant and Al Sulaimi S/S. It shall be connected into
KAHRAMAA system through 132kV OHL to be constructed under the Phase 10 OHL
Contract (GTC 373/2010) as follows:
- 132kV, 250MVA connection towards Ras Girtas will include double circuit OHL
starting from Madinat Al Kabaan, until cable compound towards Ras Girtas.
This part of the line shall be constructed under the Contract GTC 373/2010 –
OHL. 132kV cable from the cable compound up to the 132kV GIS in Ras Girtas
Power Station shall be constructed under the Contract GTC 372/2010 -
Cables.
- Another double circuit 132kV OHL shall be connected from Madinat Al Kebaan
towards the T-off tower of 132 OHL Line Al Sulaimi – Al Jiffara presently under
construction by NCC as part of Scope for Phase 9 Stage 1 Project. Eventually
there will be two 132kV circuits formed by this line (also refer to Volume 7,
Single Line Diagram for more details):
Landing gantries for the above OHL connections at Madinat Al Kabaan S/S are under
the scope of Phase 10 OHL Contractor. Substation Contractor will provide GI bus-
ducts for direct connection of 132kV GIS to the OHL.
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Six (6) Nos. Outgoing Overhead line feeder bays, four of them with GI bus –
duct for OHL direct connection
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Four (4) sets of 132kV outdoor lightning arresters for the incoming / outgoing
overhead lines.
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Madinat Al Kabaan S/S
cable links (four (4) cables per phase) between 11kV switchgear and 132/11kV
power transformers within S/S, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Al Sulaimi is an existing 132/66/11kV substation with 132kV GIS. It was built by ABB
under contract GTC/033/2004.
132kV GIS at Ras Girtas Power Plant is recently completed by M/s HYUNDAI and is
ABB made.
All modifications required to the existing spare 132kV GIS bays at remote ends due to
described connections of Madinat Al Kabaan substation shall be carried out under the
present scope of work. The scope of work shall include but not limited to the following:
- Re-testing and re-commissioning of the existing GIS bays along with Local
Control
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the OHL Contractor for the termination of the
conductors at both ends.
Al Sulaimi Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Al Jiffara Substation:
Al Sulaimi Substation:
For 132kV OHL feeder which shall be connected to Al Jiffara, and later to Madinat Al
Kabaan substation, complete functional protection system as per Standard
specification shall be provided.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Al Jiffara Substation:
For 132 kV OHL feeder which shall be connected to Madinat Al Kabaan substation,
complete functional protection system as per Standard specification shall be
provided. In Al Jiffara S/S, 132kV equipped bays, Main-1 ABB make RED670 and
Main-2 Siemens make 7SD522 is provided for 132kV line protection.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility is included in the present Scope
For 2 x 132kV OHL feeders connected to Madinat Al Kabaan substation, Main-1 ABB
make RED670 and Main-2 Siemens make 7SD522 relays are provided for 132kV line
protection.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
132kV connection towards Al Jiffara will be OHL with cable compound at Al Jiffara
side. Both OHL and cable compound are under the scope of Phase 10, OHL
Contractor (GTC 373/2010). 132kV cable connection from cable compound (near Al
Jiffara SS) to 132kV GIS in Al Jiffara shall be constructed under this Contract.
Substation Contractor shall provide GI bus-ducts for direct connection of 132kV GIS
to the OHL.
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Six (6) Nos. Outgoing overhead line feeder bays, two of them with GI bus –
duct for OHL direct connection
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the
following:
- Space six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panel, equipped with protection and the power-
factor switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV, 40MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. The new relays/equipment shall be
installed at Al Ruwais substation to match the protection provided at 132kV
RGPC end.
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Two (2) sets of 132kV outdoor lightning arresters for the incoming / outgoing
OHL
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Al Ruwais S/S (four (4)
cables per phase) between 11kV switchgear and 132/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
All modifications required at Al Jiffara due to new OHL towards Al Ruwais are within
the present Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility is included in the present Scope
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Six (6) outgoing OHL feeder bays, two of them with GI bus – duct for OHL
direct connection
- Two (2) Incoming transformer bays for the future 400/132kV transformers.
- Space for ten future bays, five on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the switchgear
- Space for the vacuum contactor panel, equipped with protection and the
power-controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with Al Jiffara side shall be installed at Al Zubarah substation.
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Two sets of outdoor surge arresters including steel supports and foundations
¾ Power Cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at Al
Zubarah S/S cable links with earth continuity conductor, (four (4) cables per
phase) between 132/11kV power transformers and 11kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
All modifications required due to new OHL towards Al Zubarah are within the present
Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
- All modification, Testing and commissioning end to end test to make it fully
operational shall be Contractor's responsibility is included in the present
Scope
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3s, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:
11kV Switchgear A:
- Space for six future bays, three on each side of the 11kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.
11kV Switchgear B:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the 11kV switchgear
- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.
¾ Four (4) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
¾ Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.
¾ LV Service Equipment
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power Cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, quadralupe circuits, single point earthed
at Barzan Camp 1 S/S cable links with earth continuity conductor, (four (4)
cables per phase) between 132/11kV power transformers and 11kV
switchgear, layed in unfilled concrete troughs with all accessories. Approx.
route length: 50m.
- 11kV, 1x630 mm2, XLPE, quadralupe circuits, cable links between 11kV
NER and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Bani Hajer Super is substation, constructed by M/s HYUNDAI under Phase 8 Project.
All modifications required due to new cable connections towards Barzan Camp 1
substation are within the present Scope.
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
For 2 x 132kV cable feeders connected to Bani Hajer Super substation, complete
functional protection system as per Standard specification shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning end to end test to make it fully
operational shall be Contractor's responsibility is included in the present
Scope
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the
following:
- Space six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panel, equipped with protection and the power-
factor switching for the future capacitor banks
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV, 40MVA Power transformer.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. The new relays/equipment shall be
installed at BC 2 substation to match the protection provided at 132kV BC 1
end.
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Barzan
Camp 2 S/S cable links between new 132/11kV transformers and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories Approx.
route length: 50m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Barzan Camp 2 S/S
(four (4) cables per phase) between 11kV switchgear and 132/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits solid bonded (one cable
per phase), between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
There is sufficient space in the N-E side of the plot to accommodate all facilities under
the Scope of works. 66kV incomers are entering substation through this area.
Alternativelly, S-E area foreseen for the future 66kV SWG may be utilized considering
that existing facilities will be demolished upon completion of the works. Dismantlig of
outdoor substation equipment and demolishing of existing structures are included in
the Scope of this Contract. The Contractor shall make a comprehensive site survey
and submit method statement outlining detailed proposal for the execution of works,
including protection of existing facilities, which shall be subject to KAHRAMAA
approval prior to start of any site works. Contractor shall bear all the costs of repair in
case that any of the services are damaged / disturbed. Work shall be done in a way to
avoid any interruption of supply from the existing substation during execution of the
project.
The principal elements of 66/11kV primary GIS substation at Gharafa North shall be
as follows:
¾ Establish 11kV, 2500A at 40oC, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ LV Service Equipment.
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.
¾ Air-conditioning and ventilation systems to cover the control & relay building
and all other buildings.
¾ Fire protection system for the 11kV SWG room, control & relay building and all
other buildings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- Existing 2 x 66kV Underground cable circuits with associated fiber optic cable
(24 Fibers), coming from Doha North Super substation are connected to
66/11kV 25MVA transformers which are presently in service at Gharafa North
substation. Diversion and re-connection of those cables to new 40MVA
transformers are also included in the Scope of Works of substation Contractor.
Approx. route length: 100m
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor cable links, (four (4) cables per phase), between
66/11kV power transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m
- 11kV, 1x500mm2, XLPE, 500kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 500kVA station
transformers. Approx. route length: 30m
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
220/132/66/11kV Doha North Super is the existing substation with GIS built under
Phase 4 Project. All modifications required due to refurbishment works in Ghafara
North substation shall be carried out under the scope of this project. The scope of
work shall include but not be limited to the following:
¾ Re-testing and re-commissioning of the 66kV GIS bays along with Local
Control Panels, inscription of additional alarm facia, modification of indicating
meters, wiring, replacing of GIS name plates and any required works
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. Contractor shall perform proper CT sizing calculation
and submit for KM review. The new CTs’ construction and other dimensions
shall be identical to the existing CTs so that it can be mounted in the limited
space available in the indoor switchgear bay. The Contractor shall be fully
responsible for all associated works and required interfaces.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope
- Existing BCUs in 2 x 66kV bays utilized for connection towards Gharafa North
S/S shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Diversion works, Loop in / Loop out (LILO) of two 66kV, 1x2000sqmm, XLPE,
120MVA, underground cable circuits with fiber optic cable (24 Fibers) between
Doha Super S/S and Mergab Mall S/S to the new 66kV GIS in Bin Mahmood S/S.
Approx. route length: 300m. All equipment and works necessary for earthing system
arrangement, in order to maintain specified current rating, shall be provided.
Necessary details, schematic drawings etc., with accurate lengths shall be submitted
for approval during detailed engineering stage. The terminations are GIS at Bin
Mahmood S/S and joints at the diversion point near Bin Mahmood S/S. Refer to
attached drawing no. EHV-72-2010.
The substation Contractor should include in his scope of work co-ordination with the
cable Contractor to connect cable with the GIS, pre commissioning checks, end to
end tests and commissioning of the respective circuits.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of 11kV switchgear
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the future capacitor banks
¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ LV Service Equipment.
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Since Bin Mahmud S/S will be fed
from new 220/66/11kV Doha Super substation, constructed by Areva under
Phase 8, it is required that compatible relays and equipment shall be installed
at Bin Mahmood substation for all the feeders.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Bin
Mahmood S/S underground cable links between new 66/11kV transformers
and new 66kV GIS switchgear laid in unfilled concrete troughs with all
accessories. Approx. route length: 30m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
Bin Mahmood S/S underground cable links with earth continuity conductor,
(four (4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 60m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
220/66/11kV Doha Super is a new substation with Gas insulated switchgears being
constructed under Phase 8. The 66kV GIS spare bays at Doha Super Substation
shall be used for establishing the above underground cable connections between the
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
two substations. All modifications required due to LILO of the existing 66 kV cable line
Doha Super – AMM into Bin Mahmood S/S shall be carried out under subject SOW
All modifications required at Doha Super substation due to new cable connection
towards substation shall be carried out under the present scope of work.
Al Mergab Mall 66/11 kV substation was originally part of the Phase 10 Project
However, due to the needs for fast completion, it is excluded from Phase 10 and
awarded Phase 9 Project. All modifications required due to LILO of the existing 66 kV
cable line Doha Super – AMM into Bin Mahmood S/S shall be carried out under
subject SOW
The scope of work shall include but not limited to the following:
- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Bin Mahmood
substation. If necessary, existing termination female parts shall be replaced by
suitable one, including all necessary material and works required for such
modification.
- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- In Doha Super Substation, 66kV (Spare) equipped bays, Main-1 AREVA make
P545 and Main-2 Siemens make 7SD532 is provided for 66kV line protection.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and Adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The substation Contractor should include in his scope of work co-ordination with the
cable Contractor to connect cable with the GIS, pre commissioning checks, end to
end tests and commissioning of the respective circuits.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ LV Service Equipment.
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at Al
Mergab Mall S/S underground cable links with earth continuity conductor, (four
(4) cables per phase), between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The substation Contractor should include in his scope co-ordination with the cable
Contractor to connect cable with the GIS, pre commissioning checks, end to end tests
and commissioning of the respective circuits.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the switchgear
- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ LV Service Equipment.
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at MOI S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories Approx. route length:
100m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
MOI S/S underground cable links with earth continuity conductors, (four (4)
cables per phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
¾ Diversion works, Loop in / Loop out (LILO) of two 66kV, 1x2000sqmm, XLPE,
120MVA, underground cable circuits with fiber optic cable (24 Fibers)
between Doha Central S/S and Feriq Bin Omran S/S, to the new 66kV GIS in
MOI S/S. Approx. route length: 100m. All equipment and works necessary for
earthing system arrangement, in order to maintain specified current rating,
shall be provided. Necessary details, schematic drawings etc., with accurate
lengths shall be submitted for approval during detailed engineering stage. The
terminations are GIS at MOI S/S.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
66kV GIS spare bays at Doha Central Substation shall be used for establishing the
underground cable connections between the two substations. All the required
modifications to the spare 66kV GIS bays at Doha Central substation shall be carried
out under the present scope of work. The scope of work shall include but not limited
to the following:
- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from MOI substation.
If necessary, existing termination female parts shall be replaced by suitable
one, including all necessary material and works required for such modification
- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
¾ SCS and Power Control System Scope for remote end modification:
- Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect
new signals as per latest specification requirements. Hence Contractor shall
install additional BCU or other suitable device to transfer all the required
signals to SCC/NCC as per specification, including additional spre BI/BO.
- VTs are not available in 66kV GIS Spare bays. New GIS 66kV VT shall be
provided at Doha Central. The Contractor shall be fully responsible for all
associated works, interlocks and required interfaces
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
¾ Optional:
Feriq Bin Omran is existing 66/11kV transformer feeder station with 2x40MVA power
transformers, upgraded under KAHRAMAA Phase 6 Project (Contract GTC/116/2006
with ABB). It is presently fed from Gharafa substation. It is foreseen, Under Scope of
Phase 10, to install new 66kV double circuit underground cable line between MOI and
Feriq Bin Omran substations and cancel connection towards Gharafa. Subject works
will be in the SOW of Phase 10 Cable Contractor.
All modifications required at Feriq Bin Omran substation due to changed power
connections shall be carried out under the present scope of work. The scope of work
shall include but not be limited to the following:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
¾ SCS and Power Control System Scope for remote end modification:
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Optional:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
DIF S/S will be connected into KAHRAMAA network on 66kV level to New Doha
Industrial Super S/S (under Scope of Phase X, see Section 3.1.4 above) via double
circuit underground cable line which is under the Scope of Phase 10 Cable
Contractor.
The substation Contractor should include in his scope co-ordination with the cable
Contractor to connect cable with the GIS, pre commissioning checks, end to end tests
and commissioning of the respective circuits.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the switchgear
- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ One (1) Nos. 11kV metal enclosed switchgear, the same as described above
excluding bays for 11/0.415kV station transformers, will be installed in the
future development of substation. The Contractor shall consider this in the
design and sizing of the relevant systems.
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with associated neutral
earthing resistors, cable connections and other related equipment will be
installed in the future development of substation
¾ LV Service Equipment.
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Protection for incoming feeders
(from new Saliyah) shall be provided to match with the protection at new Doha
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at DIF S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories Approx. route length:
100m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
DIF S/S underground cable links with earth continuity conductors, (four (4)
cables per phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The Doha Land Development is located in the centre of Doha, with boundaries
defined by Al Rayan Rd, Al Diwan St, Musherib St and Jassim Bin Mohammed St. It
will be a mixed use development including residential, commercial, retail and leisure.
To meet the electrical power demand of the development, KAHRAMAA has identified
requirement for two one primary substations within the development area: Doha Land
1 (DL1) and Doha Land 2 (DL2) included in the Scope of Phase 9 10 Project.
Substations will be connected into KAHRAMAA network on 66kV level with the
following underground cable lines all of which are in the Scope of Phase 10, Cable
Contractor:
- Double circuits line SED – DL2
- Double circuits line DL2 – DL1
- Double circuit line DL1 – Grand Hamad Avenue
The lowest level, B4 will be cable basement. Above it will be level B3 foreseen for
transformer cells, service yard for transformers, fire suppression plant room, 66kV
SWG room, 11kV room, battery room, access and escape routes. Level B2 is
foreseen for control and relay room, telecommunication room, LV power supply
system, HVAC plant room. Additionally, DL1 will include staff facilities on the level B2.
Level B1 is spared for other services. On the ground level above DL1 the EID prayer
ground will be located; above DL2 will be new road.
Civil works associated with the substation buildings will be undertaken by developer,
Doha Land, as follows:
- Water retaining ground slab and retaining walls to form basement “box”
- Building frame with cast in-situ reinforced concrete columns and beams
- Floor slabs with cast in-situ reinforced concrete
- Earth electrode and mesh cast within piles and slabs as necessary and to
substation Contractor’s Design requirements described elsewhere on this
report. Substation Contractor will also be responsible for site test
- Ground level ventilation apertures and associated louvers for general
ventilation and transformer cell ventilation
- External wall – cast in-situ reinforced concrete with adequate water sealing
- Internal walls – non-load bearing block work
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Wall finishes – painted plaster to all internal wall surfaces. In the battery room,
Acid alkaline resistant painted wall
- Ceiling finish – Fair-faced concrete with a paint finish
- Floor finishes – Cable Basement, 66kV GIS and 11kV AIS: non slip 5mm thick
heavy duty epoxy paint finish; Battery room: chemical resistant 5mm thick
epoxy Acid and alkaline resistant paint finish; Control/Relay room,
LVAC/LVDC, and communication room: 700mm raised false floor. Raised floor
panels will be steel encapsulated mineral type, Toilet, Pantry, locker and mess:
non slip ceramic floor tiles
- Access doors and their frames – Steel framed self closing doors. All internal
doors are fire rated with the exception of toilets, mess pantry, and locker room
which will be timber doors and frames completed with required ironmongeries.
- Windows and their frames - Aluminium with powder coated finish completed
with security grills complete with required ironmongeries
- Ironmongeries - Master key for the main access door. Panic bars will be
provided to all external doors.
- Steel framed louvers to transformer cell fronts
- Electrically and manually operated steel roller shutters to GIS room access and
associated with required controls
- Fire shutters to transformer loading area (to be controlled by the substation
Contractors Fire detection System as well as tunnel fire detection system)
- Internal hand rails to all staircases
- Builders work holes and penetrations as specified by the substation Contractor
based upon their design
- Transformer cells subject as per substation Contractor requirements
- Rails to the transformer cells to put them in place and pulling anchors as per
substation Contractors design details
- Linear slots cast into the floor to mount GIS and other equipment as per
substation Contractors design details
- Potable water connection up to tie-in point for substation area
- Capped water connection for fire suppression system in the plant room
- Transformer oil and water catch pit and any additional drainage connection
point in the substation
- Drainage requirement as per substation Contractors design details
- Fire walls and fire compartments
- Permanent access roads to the substation via underground services tunnels
- Cable routes within the development area and entrances into the substation
building
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Furniture will not be provided as part of the base built substation. It will be
responsibility of KM appointed EPC Contractor to provide furniture as required
for substation operation
- KM appointed EPC Contractor’s Scope includes all substation equipment
according to KAHRAMAA specifications
- All required building service within the substation building, are within KM
appointed EPC Contractor’s Scope, including, but not limited to: small power,
lighting and emergency lighting, fire detection and alarm system, GIS cranes,
HVAC, air-conditioning and ventilation system within the substation building,
fire protection system, telecommunication
Detailed civil and structural design of the public facilities in which substations are
incorporated is completed. Interface between KM appointed EPC Contractor and civil
design team will be required in the early stage of the project, to ensure that any
specific builders’ work requirements are defined and integrated in construction works
in due time. High level of coordination between developer and substation Contractor
will be required during the complete construction period as specified in Annexure 1 –
Scope of Work for Doha Land Substation.
The substation Contractor should include in his scope of work co-ordination with the
Phase 10 Cable Contractor to connect cable with the GIS, pre commissioning checks,
end to end tests and commissioning of the respective circuits. Also coordination with
Substation Contractor Phase 10, Package 5 (Grand Hamad Avenue SS) is required.
The principal elements of 66/11kV Doha Land 1 (DL1) substation shall be as follows:
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Six bays, three on each side of the switchgear, are planned for future
development
¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
- Space for six future bays, three on each side of the 11kV switchgear
11kV Switchgear B:
- Space for six future bays, three on each side of the 11kV switchgear
¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Building services and civil works according to limit of works as specified in Item
3.4 above
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, quadruple circuits, solid bonded at DL1
S/S cable links between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx. route
length: 30m.
- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
DL1 S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within S/S,
laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.
- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
In the case that Grand Hamad Avenue substation, planned for Phase 10,Package 5 is
delayed, DL 1 substation will be connected directly to Ras Abu Aboud Super (RAA)
substation via 66kV double circuit underground cable line. Third circuit from RAA will
be installed by cable Contractor for future connection in Grand Hamad Avenue. In
that case, all works as specified in Item 3.5.1.1 below (Modifications at RAA Super
substation as remote end for Grand Hamad Avenue substation) shall be in the scope
for DL 1, considering connection DL 1 – RAA Super.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The substation Contractor should include in his scope of work co-ordination with the
Phase 10 Cable Contractor to connect cable with the GIS, pre commissioning checks,
end to end tests and commissioning of the respective circuits. Also coordination with
Substation Contractor Phase 10, Package 5 (Grand Hamad Avenue SS) is required.
The principal elements of 66/11kV Doha Land 2 (DL 2) substation shall be as follows:
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Six bays, three on each side of the switchgear, are planned for future
development
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11kV switchgear
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at DL2 S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories. Approx. route length:
30m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
DL2 S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The existing 66kV bays of Eid Mosque substation at SED shall be used for
establishing cable connection between SED and DL 2 substation. All modifications
required to the existing 66kV switchgear at SED substation due to connection towards
DL 2 shall be carried out under the present scope of work. These works are to be
carried out in phase manner after the commissioning of Doha Land 1 substation by
66kV supply from Grand Hamad Avenue New / Ras Abu Aboud substation. The
scope of work shall include but not limited to the following:
- Re-testing and re-commissioning of the existing 66kV spare bays along with
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of name plates and any required
works including, wiring, testing & complete re-commissioning of the above 66kV
bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
power cables rated 66kV and above at both ends.
¾ SCS and Power Control System Scope for remote end modification:
- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. Contractor shall perform proper CT sizing calculation
and submit for KM review. Additional CT core or changing of the CTs shall be
the responsibility of the Contractor. The existing CTs are of make Moser
Glaser of type ATE 72.5. The new CTs’ construction and other dimensions
shall be identical to the existing CTs so that it can be mounted in the limited
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
space available in the indoor switchgear bay. The Contractor shall be fully
responsible for all associated works and required interfaces.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
Doha Land 1 substation was originally part of the Phase 10 Project. However, due to
the needs for fast completion, it is excluded from Phase 10 and awarded to M/s ABB
under the Project GTC 318.
In the case that completion of DL2 S/S is delayed, a (ll modifications required at DL1
substation due to 66kV cable connection DL1 – DL2 shall be carried out under
subject SOW.
The scope of work shall include but not limited to the following:
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- In DL1, 66kV equipped bays shall be provided under the Project GTC 318 by
M/s. ABB. The new relays / equipment shall be installed at DL2 substation to
match the protection provided at DL1 substation end. All modification, testing
and comissioning, end to end test to make it fully operational shall be
Contractor’s responsibilty.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
66/11kV Sheraton Park is new substation, which will be integrated in the Sheraton
Park Project, hereby referred to as SPP. SPP is planned to be public landscaped park
with high aesthetics, quality and safety standards. Site is located in the West Bay, Al
Dafna area of Doha, adjacent to and towards the north west of the Sheraton Hotel.
Area is currently designated as a car park for the Sheraton Hotel and covers
approximately 76,926 square meters and faces the Cornice Road.
Sheraton Park substation will be connected into the KAHRAMAA network on 66kV
level via double circuit underground cable line to West Bay Super 1 substation, build
by M/s Siemens undr GTC 53 Project. It will feed Sheraton Park Project: Maintenance
and Storage Facility Area (MSF) and the Automatic People Mover system for the
West Bay Area, Doha Convention Center & Tower (DCC&T) and other consumers in
the West Bay Area.
Detailed civil and structural design of the public facilities in which substations are
incorporated is under progress. Interface between KM appointed EPC Contractor and
civil design team will be required in the early stage of the project, to ensure that any
specific builders’ work requirements are defined and integrated in construction works
in due time. High level of coordination between developer and substation Contractor
will be required during the complete construction period as specified in Annexure 2 –
Scope of Works for 66/11 kV Sheraton Park Substation.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Six bays, three on each side of the switchgear, are planned for future
development
¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks
¾ Three (3) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Passive fire protection system for all cables in the basement of all buildings
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS,
pre commissioning checks, end to end tests and commissioning of the
respective circuits
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at Sheraton
Park S/S cable links between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.
- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
Sheraton Park S/S cable links with earth continuity conductor underground,
(four (4) cables per phase), between 11kV switchgear and 66/11kV power
transformers, laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.
- 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER and
66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
Two 66kV GIS spare bays at West Bay Super-1 Substation shall be utilized for cable
connection towards Sheraton Park substation. All modifications required at West Bay
Super 1 substation due to subject connection, shall be carried out under the present
scope of work. The scope of work shall include but not limited to the following:
- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Sheraton Park
substation. If necessary, existing termination female parts shall be replaced by
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
suitable one, including all necessary material and works required for such
modification
- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- 66kV spare bay in WBS-1 substation shall be utilized to connect new Sheraton
Park substation. The new relays/equipment shall be installed at WBS-1
substation to match the protection provided at new 66kV Sheraton Park
substation end.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Substation will be located within the development boundary in the vicinity of parking
building in the southeast corner of the plot, at the intersection of Doha al-Jadeeda
Road and Salah Eddine Street.
The following building works associated with the Substation for the BARAYA
development will be undertaken by Developer:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Interface between KM appointed EPC Contractor and civil design team will be
required in the early stage of the project, to ensure that any specific builders’ work
requirements are defined and integrated in construction works in due time and
targeted completion dates are met from both parties. High level of coordination
between developer and substation Contractor will be required during the complete
construction period as specified in Annexure 3 – Scope of Works for 66/11 kV Barwa
Al Doha Substation.
Barwa Al Doha substation shall be connected into KAHRAMAA network on 66kV level
to Airport Super substation. Cable connection will be installed by Phase 10 Cable
Contractor. It is within substation scope of works to coordinate with the Cable
Contractor to connect cable with the GIS, complete pre commissioning checks, end to
end tests and commissioning of the respective circuits.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Six bays, three on each side of the switchgear, are planned for future
development
¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
11kV Switchgear A:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks
11kV Switchgear B:
- Space for six future bays, three on each side of the 11kV switchgear
- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks
¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
Barwa Al Doha S/S cable links with earth continuity conductor, (four (4) cables
per phase) between 11kV switchgear and 66/11kV power transformers within
S/S, laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.
- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
¾ 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
The existing 66kV GIS bays of Asmakh feeder shall be used for establishing the
above underground cable connections between the two substations. All modifications
required to the existing 66kV GIS at Airport Super substation due to change in power
connection shall be carried out under the present scope of work. The scope of work
shall include but not limited to the following:
- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- Existing BCUs in 2 x 66kV bays utilized for connection towards Barwa Al Doha
S/S shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility
- Minor modifications for existing ABB SCS system supplied under Phase 4
project.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Existing CTs shall be replaced with new CTs to match with new protection and
metering requirements. Contractor has to do the proper CT sizing calculation for KM
review. Additional CT core or changing of the CTs shall be the responsibility of the
Contractor. The Contractor shall be fully responsible for all associated works and
required interfaces.
Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Grand Hamad Avenue substation will be incorporated within multi storey parking
building for which plot of 65x40m is dedicated in area of Grand Hamad Avenue as
indicated on the site layout plan. Scope of works for KM nominated EPC includes all
substation works as detailed below but also complete design, approval of the design
and Building Permit procedure and all civil and construction works and building
services as per Appendix F – drawings which are related to the parking building.
¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Six bays, three on each side of the switchgear, are planned for future
development
¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the switchgear
- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ One (1) Nos. 11kV metal enclosed switchgear, the same as described above
excluding bays for 11/0.415kV station transformers, will be installed in the
future development of substation.
¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.
¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with associated neutral
earthing resistors, cable connections and other related equipment will be
installed in the future development of substation
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits
¾ Power cables:
- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Grand
Hamad Avenue S/S cable links between new 66/11kV transformers and new
66kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length: 100m.
- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
Grand Hamad Avenue 2 S/S cable links with earth continuity conductor, (four
(4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.
- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
¾ DL1 substation shall be connected directly to RAA substation with 66kV double
circuit underground cable line which is within the scope of Project GTC 318.
Third cable circuit, for the connection between Grand Hamad Avenue and RAA,
shall be installed by Phase 10 Cable Contractor. Once, when Grand Hamad
Avenue substation is completed, following works are required at Grand Hamad
Avenue substation and are in the Scope of S/S contractor:
Grand Hamad Avenue will be connected into KAHRAMAA network on 66kV level to
the existing RAA Super substation via triple circuit underground cable and to DL 1
substation (under the separate Contract GTC 318 between KAHRAMAA and M/s
ABB) via double circuit underground cable.
220/66/11kV Ras Abu Aboud substation is existing substation with GIS built under
Phase 6, Project GTC/05/2004. All modifications required to the existing 66kV
switchgear at RAA substation due to this connection shall be carried out under the
scope of this Contract. The scope of work shall include but not limited to the following:
- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Grand Hamad
Avenue substation. If necessary, existing termination female parts shall be
replaced by suitable one, including all necessary material and works required
for such modification
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Re-testing and re-commissioning of the existing 66kV spare bays along with
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of name plates and any required
works including, wiring, testing & complete re-commissioning of the above 66kV
bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
¾ SCS and Power Control System Scope for remote end modification:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- In Ras Abu Aboud substation 66kV equipped bays, Main-1 Siemens make
7SD532 and Main-2 ABB make REL561 relays are provided for 66kV line
protection.
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- Testing and commissioning, end to end test to make it fully operational shall be
Contractor's responsibility.
For 2x66 kV Cable feeders connected to Grand Hamad Avenue substation, complete
functional protection system as per Standard specification shall be provided.
- In DL1, 66kV equipped bays shall be provided under the Project GTC 318 by
M/s. ABB. The new relays / equipment shall be installed at Grand Hamad
Avenue substation to match the protection provided at DL1 substation end. All
modification, testing and commissioning, end to end test to make it fully
operational shall be Contractor’s responsibility.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The principal elements of new 220/66/11kV New Doha-B Super substation shall be
as follows:
¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Two (2) Nos. 220/66 kV, 120/150/200 MVA Outgoing transformer bays
- Space for six future bays, three on each side of the switchgear
¾ Establish 66kV, 3150A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgears with vacuum circuit breakers, consisting of the following:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the capacitor banks
¾ Two (2) Nos. Power Transformers 220/66kV, 120/150/200 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
¾ Three (3) Nos. Power Transformers 66/11kV, 32/40 MVA, with ONAN/ONAF
cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc
¾ Three (3) Nos. 11 kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer
¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000 kVA, with ONAN
cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc
¾ 66 kV, 200 MVA bus duct between 220/66 kV power transformers & 66 kV
GIS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
- 220 kV, 1x1200 mm2, XLPE, 200 MVA, duble circuits, special bonded
at NDBS S/S cable links, single point earthed with earth continuity
conductor, the links between 220/66 kV power transformers and new 220
kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approximate route length: 150 m
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
NDBS S/S cable links with earth continuity conductor, four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.
- 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.
- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) cable links between 11kV switchgear and 11/0.415,
1000 kVA Station transformers. Approx. route length: 30 m.
Diversion works, Loop in / Loop out (LILO) of the existing 220 kV, 1x1600mm2,
XLPE, 315 MVA underground cable Feeders 1 & 2 with fiber optic cable (24 Fibers)
between Doha North Super and New Doha – J (NDJ) to the new 220kV GIS in
NDBS Substation are in the present SOW of S/S Contractor. Approximate routhe
length: 600m. Cable route shall be diverted into substation plot with sufficient snaking
provided. The Contractor shall make all necessary arrangements to connect cables
at joint bay, divert them, connect into 220kV GIS and commission the same. All
equipment and works necessary for earthing system arrangement, in order to
maintain specified current rating, shall be provided. Necessary details, schematic
drawings etc., with accurate lengths shall be submitted for approval during detailed
engineering stage. The terminations will be in 220kV GIS in New Doha B Super S/S
and cable joints at diversion point.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
3.5.2.2 MODIFICATIONS AT NEW DOHA J (NDJ), NEW DOHA C AND DOHA NORTH
SUPER (DNS) SUBSTATIONS
220/132/66/11kV Doha North Super (DNS) is existing substation with Gas Insulated
switchgear, built under Phase 4 project. All modifications required due to LILO of the
existing 220 kV cable line NDJ – DNS into New Doha-B S/S shall be carried out
under subject SOW.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
NDJ Substation:
DNS substation:
- Existing BCUs in 2x220kV bays utilized for connection towards New Doha B
Super S/S shall be replaced with new BCUs. New BCUs shall be integrated
with the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
New Doha C:
NDJ Substation:
For 2 x 220 kV Cable feeders connected to New Doha-B Super substation, complete
functional protection system as per Standard specification shall be provided. In NDJ
substation, 220 kV equipped bays, Main-1 Siemens make 7SD532 and Main-2 ABB
make RED670 relays are provided for 220 kV line protection.
- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at NDBS substation to match the protection
provided at 220 kV NDJ substation end.
- All modification, Testing and commissioning, end to end test are included in the
present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
DNS Substation:
For 2 x 220 kV Cable feeders connected to New Doha-B Super substation, complete
functional protection system as per Standard specification shall be provided. In NDJ
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
substation, 220 kV equipped bays, Main-1 Siemens make 7SD532 and Main-2 ABB
make RED670 relays are provided for 220 kV line protection.
- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at NDBS substation to match the protection
provided at 220 kV DNS substation end.
- All modification, Testing and commissioning, end to end test are included in the
present Scope
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The principal elements of new 220/66/11kV Abu Hamour Super substation shall be
as follows:
¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Three (3) Nos. 220/66 kV, 120/150/200 MVA Outgoing transformer bays
- Space for six future bays, three on each side of the switchgear
¾ Establish 66kV, 3150A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Space for six future bays, three on each side of the switchgear
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgears with vacuum circuit breakers, consisting of the following:
- Space for six future bays, three on each side of the 11 kV switchgear
- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the capacitor banks
¾ Two (2) Nos. Power Transformers 220/66kV, 120/150/200 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
¾ Three (3) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer
¾ 66 kV, 200 MVA bus duct between 220/66 kV power transformers & 66 kV
GIS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules
¾ All civil works related to new 220/11kV substation including building services
and works related to the diversion of 220 kV and 66 kV cables as per Appendix
F – Drawings. Plinth and fire wall for the third 220/66kV power transformer,
foreseen for the future, is included in the present Scope of works.
¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.
¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power cables:
1. 220 kV, 1x1200 mm2, XLPE, 200 MVA, duble circuits, special bonded
at AHS S/S cable links, single point earthed with earth continuity
conductor, the links between 220/66 kV power transformers and new 220
kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approximate route length: 150 m
2. 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at AHS
S/S cable links, between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
3. 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
AHS S/S cable links with earth continuity conductor, four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within
S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.
4. 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.
5. 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) cable links between 11kV switchgear and 11/0.415,
1000 kVA Station transformers. Approx. route length: 30 m.
¾ Diversion works, Loop in / Loop out (LILO) of the existing 220 kV,
1x2500mm2, XLPE, 515 MVA underground cable circuits with fiber optic (24
Fibers) and DTS cable between Abu Hamour North and DSS to the new
220kV GIS in Abu Hamour Super Substation, are in the SOW of S/S
Contractor. Approximate routhe length: 500m. Cable route shall be diverted
into substation plot and cable joints to be installed with sufficient sneaking
provided. The Contractor shall make all necessary arrangements to connect
cables at joint bay, divert them, connect into 220kV GIS and commission the
same. All equipment and works necessary for earthing system arrangement, in
order to maintain specified current rating, shall be provided. Necessary details,
schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage. The terminations will be in 220kV GIS in
Abu Hamour Super S/S and cable joints at diversion point.
¾ Cable Diversions:
Existing OHL/ cable circuits, listed below, shall be diverted from Abu Hamour to AHS
substation under the present Scope of substation Contractor:
The substation Contractor should make all necessary arrangements to connect cable
termination with new 66kV GIS. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Abu Hamour to Abu Hamour East: 66 kV, 1x500 mm2, XLPE, 40 MVA
double circuits shall be diverted with associated multimode fiber optic cable
and telephone cables to 66 kV GIS at new Abu Hamour Super S/S.
Approximate routhe length: 500 m. Also new single mode fiber optic cables
(24 Fibers) shall be provided from Abu Hamour East to Abu Hamour Super.
The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.
Necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage. The terminations will
be in 66kV GIS in Abu Hamour Super S/S and cable joints at diversion point.
¾ Abu Hamour to Abu Hamour Super: New single mode fiber optic cables (24
Fibers) shall be provided from from Abu Hamour to Abu Hamour Super.
Approximate routhe length: 500 m.
¾ Abu Hamour to KSS: 66 kV, 1x500 mm2, XLPE, 40 MVA double circuits
shall be diverted with associated copper pilot cable to 66 kV GIS at new Abu
Hamour Super S/S. Approximate routhe length: 500m. The Contractor shall
include all necessary modification works in the earthing arrangement (cross
bonding, single point bonding, mixed bonding) in order to ensure that required
current rating of diverted circuit is maintained. Necessary details, schematic
drawings etc., with accurate lengths shall be submitted for approval during
detailed engineering stage. The terminations will be in 66kV GIS in Abu
Hamour Super S/S.
¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
220/66/11kV Abu Hamour North (AHN) substation is an existing substation built under
phase 5 project. All modifications required due to LILO of the existing 220 kV cable
line AHN – DSS into Abu Hamour Super S/S shall be carried out under subject SOW.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
the existing 220 kV cable line AHN – DSS into Abu Hamour Super S/S shall be
carried out under subject SOW.
66/11IV Khalifa Sport Stadium South (KSSS) substation is an existing substation built
under earlier KM project. All modifications required due to diversion of the existing
2x66 kV cables for KSSS substation to 66 kV GIS at new AHS shall be carried out
under subject SOW.
Abu Hamour East (AHE) substation is an existing substation built under earlier KM
project GTC/21. All modifications required due to diversion of the existing 2x66 kV
cables for Abu Hamour East substation to 66 kV GIS at new AHS shall be carried out
under subject SOW.
Abu Hamour 132/66/11 kV is an existing substation built under earlier KM project but
upgraded with 66kV GIS under phase 7 project by M/s Siemens. All modifications
required due to diversion of the existing 2x66 kV cables for Abu Hamour East
substation and the existing 2x66 kV cables for KSSS substation to 66 kV GIS at new
AHS shall be carried out under subject SOW.
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement.
- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.
All modification, Testing and commissioning; end to end test are included in the
present Scope
AHN Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
DSS substation:
Doha South Super (DSS) is existing substation with GIS built under Phase 4 project
- Existing BCUs in 2x220kV bays utilized for connection towards Abu Hamur
Super S/S shall be replaced with new BCUs. New BCUs shall be integrated
with the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
AHN Substation:
For 2 x 220 kV Cable feeders connected to Abu Hamour Super substation, complete
functional protection system as per Standard specification shall be provided. The new
relays/equipment shall be installed at Abu Hamour North substation to match the
(new) protection at Abu Hamour Super substation end.
- All modification, Testing and commissioning; end to end test are included in the
present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
DSS Substation:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
For 2 x 220 kV Cable feeders connected to new Abu Hamour Super substation,
complete functional protection system as per Standard specification shall be
provided. The new relays/equipment shall be installed at Doha South Super
substation to match the (new) protection at Abu Hamour Super substation end.
- All modification, Testing and commissioning; end to end test are included in the
present Scope.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
- Existing protection panels may not have adequate space to install new relays
and hence, new protection panels shall be provided for B11 and B21 bays.
Transformer differential relay (7UT61), REF relay (F87NH) and Over current
relay (F511) are located presently in 132/66/11 kV Abu Hamour Substation (in
the same compound) and all these relays are required to be installed in the
new panel in Abu Hamour East substation. Otherwise Contractor shall replace
existing relays to provide the complete new protection for 40MVA transformer
at Abu Hamour East substation. Any additional relay required to make a
complete functional protection system shall be provided by the Contractor.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Existing CTs in 11kV Incomer A18/A28 feeder shall be replaced (or additional
core provided) to suit F87C+T (Overall differential protection). The new CTs
required parameters are given in Protection standard Specification and
standard CT ratio. If required, according to the CT sizing calculation,
installation of additional CT core or changing of the CTs shall be the
responsibility of the Contractor
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
Substation Contractor shall provide the following for each pilot copper cable
diversion of existing double circuit Abu Hamur – Khalifa Sport Stadium South
(KSSS) cable lines to be Abu Hamour Super–KSSS cable lines.
• Pilot Copper Cable Terminal Box with all accessories required for
connection of protection equipment. Works for dismantling of existing
Pilot Copper Cable Terminal Box at Abu Hamur S/S. Alternatively,
existing Pilot Copper Cable Terminal Box at Abu Hamur S/S can be
utilized for installing the same in Abu Hamour Super substation.
For 2x66 kV Cable transformer feeders connected to Abu Hamour Super substation,
complete functional protection system as per Standard specification shall be
provided. The new relays/equipment shall be installed at KSSS substation to match
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
the (new) protection at Abu Hamour Super substation end. The protection relays shall
be compatible to work satisfactorily over Pilot Cable.
- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
132/22kV Qatar Aerospace City 1 (ASCQ1) substation is a new substation which will
be constructed on the plot 75x75m located in south of Al-Khore area. It will be fed
from existing 132kV Khore South Substation (under construction, Phase 9, GTC
240A), constructing LILO (Loop In Loop Out) on the existing 132kV, 250MVA
underground cable line Khore South – Semaisma (currently under installation under
Phase 9, GTC 241A/2008 Siemens Consortium).
The principal elements of new 132/22kV Qatar Aerospace City 1 substation shall be
as follows:
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Two (2) Nos. 132/22kV, 60/75/100MVA Transformer bays for 132/22kV TXs.
For the purposes of tariff metering VT should be incorporated.
- Space for six future bays, three on each side of the switchgear
¾ Establish 22kV, 3150A at 40˚C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear (GIS) with vacuum circuit breakers, consisting of the
following:
- Two (2) Nos. Incomers each rated 3150A for 132/22kV 60/75/100MVA TXs
- Space for six future bays, three on each side of the 22kV switchgear
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. of 22kV Metallic Neutral Earthing Resistors 17 ohm at 50˚C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/22kV 60/75/100MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for feeders connected to Khore South SS.
¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.
¾ All civil works related to new 132/22kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings
¾ Air-conditioning and ventilation systems to cover the GIS and Control & Relay
building and all other buildings.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Power Cables:
- 22kV, 1x800 mm2, XLPE, 100MVA, double circuit, single point earthed
with earth continuity conductor underground cable links (four (4) cables per
phase) between 132/22kV power transformers and 22kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.
- 22kV, 1x800 mm2, XLPE, double circuit cable links between 22kV NER and
132/22kV, 60/75/100MVA Power Transformers. Approx. route length: 20 m
- 22kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 22kV switchgear and 22/0.415, 1000kVA station
transformers. Approx. route length: 30 m
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Installation for 22kV outgoing cable feeders between 22kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning; end to end test are included in the
present Scope
- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
132/22kV Qatar Aerospace City 2 (ASCQ2) substation is a new substation which will
be constructed on the plot 75x75m located in south of Al-Khore area. It will be fed
from new 132kV Qatar Aerospace City 1 Substation, constructing LILO (Loop In Loop
Out) on existing 132kV, 250MVA underground cable line Khore South – Semaisma,
currently under installation under the Phase 9 project (GTC 241A/2008 Siemens
Consortium).
The principal elements of new 132/22kV Qatar Aerospace City 2 substation shall be
as follows:
¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:
- Two (2) Nos. 132/22kV, 60/75/100MVA Transformer bays for 132/22kV TXs.
For the purposes of tariff metering VT should be incorporated.
- Space for six future bays, three on each side of the switchgear
¾ Establish 22kV, 3150A at 40˚C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear (GIS) with vacuum circuit breakers, consisting of the
following:
- Two (2) Nos. Incomers each rated 3150A for 132/22kV 60/75/100MVA TXs
- Space for six future bays, three on each side of the 22kV switchgear
¾ Two (2) Nos. Power Transformers 132/22kV, 60/75/100 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Two (2) Nos. of 22kV Metallic Neutral Earthing Resistors 17 ohm at 50˚C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/22kV 60/75/100MVA Power transformer.
¾ LV Service Equipment
¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for feeders connected to Semaisma SS.
¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.
¾ All civil works related to new 132/22kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings
¾ Air-conditioning and ventilation systems to cover the GIS and Control & Relay
building and all other buildings.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Fire protection system for the GIS building, control & relay building and all
other buildings
¾ Passive fire protection system for all cables in the basement of all buildings
¾ Civil work, erection, laying and installation for 22kV outgoing cable feeders
(between 22kV GIS at S/S to substation boundary wall) included but not limited
to cable support, cable cleat, heat shrinkable cap and commissioning test shall
be part of scope of work, and shall include in contract prices. Contractor shall
coordinate with concerning KAHRAMAA department.
¾ Power Cables:
- 22kV, 1x800 mm2, XLPE, 100MVA, double circuit, single point earthed
with earth continuity conductor underground cable links (four (4) cables per
phase) between 132/22kV power transformers and 22kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.
- 22kV, 1x800 mm2, XLPE, double circuit cable links between 22kV NER and
132/22kV, 60/75/100MVA Power Transformers. Approx. route length: 20 m
- 22kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 22kV switchgear and 22/0.415, 1000kVA station
transformers. Approx. route length: 30 m
- Diversion works, Loop in / Loop out (LILO) of the existing 132kV, 1x2000mm2,
XLPE, 250MVA underground cable circuits with fiber optic cable (24 Fibers)
between Khore South and Semaisma to the new 132kV GIS in Aero Space
City 2 Substation, is in the scope of this Contract. Approx. route length: 500m.
All equipment and works necessary for earthing system arrangement, in order
to maintain specified current rating, shall be provided. Necessary details,
schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage. The terminations are GIS at Aero Space
City 2 S/S.
¾ Installation for 22kV outgoing cable feeders between 22kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.
- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.
- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All modification, Testing and commissioning; end to end test are included in the
present Scope
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
3.7.1 INTRODUCTION
The works under the Phase 10 project includes substation works for establishment of
new transmission substations as well as refurbishment/ modification/ upgrade/
replacement of existing transmission substations, overhead lines works and
underground power cables works.
The substation works under the Phase 10, are grouped into Packages S-1, S-2, S-3,
S-4, S-5 and S-6.
The works and services to be performed by the Contractor shall comprise the design,
manufacture, shop testing, packing, transport, insurance, unloading, storage at site,
construction works, erection, corrosion protection, site testing, submission of
documentation, commissioning, training of the Employer’s personnel and warranty of
works.
The obligation of the Contractor is to fully inform himself about the existing
telecommunication system and to provide all necessary new equipments, upgrade of
existing equipments, network modification and/or reconfiguration for connection of the
new and refurbished substations as per Drawings reference TED-PH10-TEL-001 –
Rev. 10 Telecommunication Links Diagram.
The Contractor shall make the best design based on Power Transmission Network
and Fiber Optic availability.
The proposed design shall be based on the Power Transmission Network and shall
therefore consider necessary sizing of the Substations in terms of Optical
Termination, Optical Transmission System and cross connection facilities for potential
future expansion of the network.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The Contractor shall meet Phase 10 S/S commissioning dates and therefore shall
establish telecom link to NCC/DCC as required in order to allow energization of S/S.
In case that approved design cannot be applied at S/S commissioning date because
of Fiber optic unavailability or any other reason, then the Contractor shall provide all
necessary temporary set up in order to establish the link on KM request.
The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:
The new fiber cables under this project shall be provided by the Phase 10: Substation
Contractor(s) GTC/371/2010, Cable Contractor(s) (GTC/372/2010) and OHLs
Contractor (GTC/373/2010) as follows:
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Recovery of all services affected by the insertion of a new S/S in the network.
- Recovery of telecom services (in Areva and ABB Telecom networks) due to cable
diversions and S/Ss dismantling.
- Updating of all Existing Drawings and update general documents such like
routing tables, overall network, IP addresses list, etc.
The detailed technical requirement for telecommunication system is given under the
General Technical Requirements and Technical Specifications in Volume 2 and
Volume 3, Section 3.3.11 of GTC/371/2010, Phase 10 Tender Documents.
- Works for Underground fiber optic approach cable between the Optical
Termination equipment (FOPP/OTP/OTB) in the substation telecommunication
room and the OPGW joint box closure (HOC - Hood Closure) located outside at
the overhead line gantry for all OHL links entering substations in addition to
FOPP/OTP works for the same.
- Works for fiber optic indoor cables to connect optical transmission equipment
(Protection, TSTU, SDH or PDH equipment) to optical termination equipment
(FOPP/OTP/OTB) at all stations.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Fiber Optic Patch Panels (FOPP) and Optical Termination Panel Cubicle (OTP)
instead of wall mounted Optical Terminal Box (OTB).
- FO Termination and end to end Test shall be responsibility of the cable supplier as
follows:
Telecom Contractor shall provide the following for each pilot copper cable diversion of
existing double circuit Abu Hamur – Khalifa Sport Stadium South (KSSS) cable lines to
be Abu Hamur Super (AHS) –KSSS cable lines and for each pilot copper cable diversion
of existing double circuit Asmakh – Airport Super cable lines to be Barwa Al Doha –
Airport Super cable lines:
- Terminal Box for installation of above barrier transformers and copper cable for
connection of Barrier Transformers Terminal Box and Pilot Copper Cable Terminal
Box.
- Screened twisted pairs copper cable for connection of barrier transformers and
telecom cabinet (HDSL equipment).
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Works for dismantling of existing Barrier Transformers, Terminal Boxes and 2MHz
Barrier Transformers at Abu Hamur S/S, Asmakh S/S, NEW DOHA B, NEW
DOHA C and delivering to KAHRAMAA stores packed and labeled as per KM
regulations.
The works required shall include all necessary works to include the new and
refurbished/replaced/upgraded substations into the existing telecommunication network
as per drawing ref. “TED-PH10-TEL-001 – Rev.10 Telecommunication Links Diagram”,
Technical Specification section 3.3.11, and Appendix B – Price Schedule.
All S/Ss with fiber optic cable terminated shall have multiplexer equipment with optical
interface.
• Two PAX extensions one for NCC PAX and one for DCC PAX with
respectively 3 and 2 telephones connected in parallel at the substation (total 5
telephone sets and outdoor bell at each substation).
• Two IEC-104 64 kbps TCP/IP connections from SCS gateways to NCC and
switching to ENCC (SCADA).
• One Ethernet connection (2Mb/s minimum) to NCC for TMS / RMS Monitoring
System.
• One Ethernet connection (2Mb/s minimum) to NCC for remote access to SCS
LAN at substation (For Fault recorder, Parameter settings …).
• One Ethernet connection connected to PMR file server at NCC and ENCC.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Exact channel requirements depend on the Substation and SCS design. Contractor shall
closely coordinate with Substation Contractor and SCS supplier to meet any of his
requirements with respect to communication channel to NCC, DCC and ENCC.
- Any equipment not running any services to be dismantled and delivered to KM.
- Recovery services and network re-configuration for all the S/S connected above a
modified S/S in all affected KM network.
- All necessary works for migration of existing communication links and services to
the new location at all refurbished/replaced substations.
- One unit 240 V AC outdoor bell for each new and refurbished/replaced substation
and all necessary related works.
- Work for PAX configuration (Alcatel and Sopho) to fully interconnect the network.
- Maintain 20% spares or existing % of spares in case that less than 20% spares
are available in the KM Telphone System at NCC/DCC (Alcatel and Sopho).
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- All communication system shall be compatible with the existing NMS systems.
- Works shall include the Software and Hardware Modifications of one or more
existing TMS System to connect the new Substations.
- The NMS license should be upgraded for the required additional nodes keeping
20% spare.
- All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new equipment or modifications/upgrading of existing
equipment including, survey, calculations, connecting, documentation and DC
distribution extensions etc.
- All works for 240VAC UPS and 110VDC Batteries at relative existing substations
to accept new telecommunication equipment or modifications/upgrading of
existing equipment including, survey, calculations, connecting, documentation and
AC distribution extensions etc.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- 240 VAC / 48 VDC converter shall be sized with enough spare power capacity for
a fully equipped cabinet.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the KM Telecommunication Network.
Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall
inform himself of Fiber Optic utilization and telecom network and to plan links
accordingly. This includes patching, network reconfiguration or any other action.
NAME OF
PACKAGE SCOPE OF WORK
SUBSTATION
1. Works for disconnection of telecom link
between Khalifat South Sport Stadium
- KSSS (223) and Abu Hamur and re-
Phase 9, Khalifat South Sport connection of KSSS to network via new
GTC/240A/2008 Stadium - 223 copper pilot cable KSSS - Abu Hamur
North, including all necessary works at
Abu Hamur North.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
NAME OF
PACKAGE SCOPE OF WORK
SUBSTATION
1. Works for disconnection of telecom link
between Abu Hamur and Abu Hamur
Abu Hamur
East and network re-connection.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
4. NOTES TO BIDDERS
Technical Requirement: The design, cable sizing etc., provided in the Tender
documents are only guiding principles. These shall be verified and it is the
responsibility of the prospective Contractor to ensure that the specified MVA rating
for each cable circuit is achieved by adopting appropriate method and/ or adequate
cable sizing, considering thermally independent cable circuits.
Technical parameters for all the equipment/ accessories required and offered shall
be filled in by Bidder even if certain specific formats are not provided in the Tender.
The total no of cable spans: The indicated cable spans are for pricing purposes.
However, necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage.
Power cables for all voltage levels connecting different equipment within
substation shall be supplied and installed by the Substation Contractor which will
present nominated subcontractor for the Cable Contractor.
HV cables between the transformers and switchgears and between cable gantry
located within substation boundary to transformer / switchgear shall be laid in the
unfilled concrete cable trough which will be constructed by the substation civil works
subcontractor.
HV Connections between outdoor sealing end and SF6 wall bushing: The
Necessary Jumper for connection between outdoor termination and SF6 wall bushing
shall be part of scope of supply of substation Contractor.
Civil works: In addition to all related civil works along the cable route, construction of
all cable troughs/ concrete trenches, steel support, foundations, structures etc., for
cable sealing ends/ connections inside the substations for the cable feeder lines
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
(except foundations/ structures for equipments inside cable compound and OHL
gantry and cable ducts to buildings, Road Crossing ducts etc., inside substations) as
well as necessary coordination with the respective cable/ OHL Contractor(s) to
ensure technical and programme compatibility and compliance, shall be part of the
substation Contractor’s scope and responsibility.
Outdoor Cable Sealing End: Substation Contractor responsible for cable line
connection with outdoor type termination shall include following in their bid price for
outdoor sealing end connection at cable compound/gantry:
- respective foundation, steel structure and all necessary material and accessories,
surge arresters including their foundation and steel structure, all material required for
earthing of equipment and structure – connection to the earth grid, terminals for
connection to OHL down leads, removing of existing cables and sealing end, if any,
and all related civil works. In case that existing foundation is suitable to be used,
Contractor may propose such solution and appropriate structural calculation shall be
provided for KAHRAMAA approval. KAHRAMAA decision will be followed in this
regard.
Substation Contractor shall supply, install, erect and commission cable links within
substation as per execution plan of substation without any delay; all required
interface arrangement shall be cable Contractor responsibility.
Testing and Equipment: In addition to all related equipment required for cable
installation and commissioning test for cable feeders connected to GIS switchgear
and cable feeders to transformers as well as necessary coordination with substation
manufacturer/Contractor, the test bushing and degassing, and gassing and oil
filling/derange shall be part of the substation Contractor’s scope and responsibility.
Specifications, technical schedules and drawings: New route and relevant new
drawings are provided where necessary. For referring to the main contract
information, please note that Single line diagrams are in Appendix – F – Drawings,
Technical Specifications are in Sections 3.2 & 3.3 and Technical Schedules in
Section 3.4 of this Appendix.
Route Length: The quantities given for cable length in TED are approximated for
Tendering purposes and shall be adjusted according to actual results of survey.
Empty Cable Drums: KM is considering possibility that empty Cable Drums shall
remain property of Contractor. Accordingly, Contractor shall fill the cost deduction in
appropriate item in Price Schedules.
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 173 OF 189
REV. 2
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
Fiber optic cable: A budget calculation note and cut over plan for divert the FO
cables shall be provided for KM approval.
Pilot cable: Installation of gland for termination of pilot cable at relay panel of 11kV
SWG is included in the Scope of substation Contractor.
Dismantling of Oil Filled Cable to install new XLPE cable: the following shall be
under scope of work for substation Contractor:-
Warranty: In the event that a new cable requiring connection to an existing cable
which is under warranty by the original contractor, the new cable Contractor will make
arrangements with the original contractor of the existing cable to carry out the
connection and to follow prudent procedures in order to avoid the cancellation of the
remaining warranty period on the existing cable. The original contractor of the
existing cable is expected to be cooperative and Kahramaa will view any reluctance
from the original contractor as unacceptable behavior which will have impact on
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
future approval of bids by such contractor. The new cable Contractor guarantees that
their work will be conducted as per normal procedures and will be responsible for the
repair of any damage they may cause to the existing circuit.
Third Party Damage During Warranty Period: No reduction to the Warranty Period
"as specified in Article 9.51 of the GCC" for the Works or any part of the Works, shall
take place for whatsoever reason during the Warranty Period. The Contractor is
responsible to make good all defects that may arise, in accordance with Article 9.53
of the GCC. If third party damage to the Works or any part of the Works occurs;
KAHRAMAA and the third party shall be responsible for the repair of the damaged
works in accordance with KAHRAMAA standard regulations and the specification of
the Contract.
KAHRAMAA may instruct the original Contractor to perform the repair of any third
party damage to the Works or any part of the Works, if the Contractor accepts
KAHRAMAA instruction to perform the repair or remedy of any third party damage.
The cost of such repair shall be paid by KAHRAMAA to the Contractor and shall be
calculated based on the unit rates of the Contract or within a reasonable range of.
If KAHRAMAA performs the repair works through any of its reputable Contractors,
the repair work shall be performed under the supervision of the original Contractor if
available at seven (7) days notice. Costs of supervisor shall be based on unit rates
of the original Contract or reasonable range of. If the original Contractor does not
make available to KAHRAMAA the required resources for the repair work or the
supervisor within above notice period, KAHRAMAA may conduct the repairs without
further notice to the original Contractor or the presence of their supervisor or
representative but always in accordance with procedures agreed by KAHRAMAA and
the original Contractor and clearly specified in the original contract document, in
absence of which KAHRAMAA will operate within its standard practices.
The above repair works shall in no way be used by the Contractor as an excuse to
limit or terminate the Warranty of the Works or the repaired parts.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ ET-P26-G2 Guidelines for System Control Requirements for Power Supply to Bulk
Customers
The Contractor shall plan his works to minimize Power supply interruption. The
dismantling and reconstruction shall be done in phased manner which has been
described in detail elsewhere. Where the shifting of respective 400kV, 220kV, 132kV
and 66kV OHL / Oil filled and /or XLPE cables work is allocated to another Contractor
under separate contract(s), all required co-ordination for work schedule, material
management etc shall be done with the other Contractor to complete the works in full
respect. The Contractor shall consider all such requirements and shall take all
necessary measures required for these works.
It may be noted that the diversion/ shifting of 11kV OHL / cable circuits, wherever
applicable, to the new substation is not within the scope of this contract unless
specified otherwise in detailed scope of works.
Wherever specified the Contractor shall supply set(s) of main protection relay e.g.
cable differential protection relay for each of the feeder for remote end stations.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
survey may be carried out by substation Contractor to study detailed scope of work
to be undertaken at remote substations presently connected to the substation. In
case of underground cable feeders care shall be taken to choose proper protection(s)
to connect with existing oil filled cable / XLPE power cable and pilot cable /fiber optic
cable. Remote end substation(s) where panels are equipped with protections, the
required modification to make it functional and compatible with the new substation is
under the Contractor’s scope as described under protection scope of works.
The project shall be executed as substation Contract. The works and services to be
performed by the substation Contractor shall comprise the design, manufacture, shop
tests, packing, transport, insurance, and charges incurred up to delivery to the port of
entry in Qatar, landing charges, customs, transport to Site, insurance, site clearing
and leveling, excavation, building road crossing ducts as required after detailed route
survey, cable laying and jointing, terminating, etc., in-fill, boundary wall, access
roads, drainage, sewage, construction works, erection of equipment, site testing,
submission of documentation, commissioning, training of KAHRAMAA ’s staff,
delivery of spare parts and tools, temporary site buildings and accommodation,
warranty and everything necessary to leave the plant complete and in full working
order at the expiration of the warranty period in accordance with the provisions of the
substation Contract.
The substation Contractor is bound to provide for all parts of the work to be
completed in every respect for commercial operation and to KAHRA-MAA’s
requirements notwithstanding that any details, accessories, etc. required for the
complete installation and satisfactory operation of the plant are not specifically
mentioned in the Specification. These are to be considered as included in the Scope
of Works and Contract Price.
The quantities indicated in the Schedule of Prices (Appendix B refers) and Drawings
(Appendix F refers) both attached to the Specification are provided for information
only. The substation Contractor is responsible to establish the exact details,
quantities of the equipment and accessories required to complete the whole of the
works as described throughout the Tender Documents, after the necessary
approvals.
General Technical Requirements are given in Section 3.2 of Appendix A, while the
specific requirements for the various equipment and works are set forth in Section
3.3 – Technical Specification and Section 3.4 – Technical Schedules of Appendix ‘A’.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
The Scope of Services shall include but be not limited to the following:
¾ Preparation of the detailed specification for each piece of the equipment up to the
satisfaction of KAHRA-MAA before commencement of manufacturing;
¾ Establishment of the project administration and all site and installation procedures
as detailed in the Specification;
¾ Project site organization, at Doha and site offices, stores, local transport etc;
¾ Detailed soil investigation report and excavation of trial pits and testing of the
original soil properties, including thermal properties;
¾ Detailed site survey at the approved locations, detailed route survey (for
underground cables), preparation of appropriate topographical drawings and
establishment of the project set-up;
¾ Circulate the location map and civil/architectural design drawing and approval
requests to all concerned government authorities. Follow up and obtain such
approvals. Regular renewal of the approvals and work permits as necessary;
¾ Establish the subcontract agreement with the approved local civil Contractor.
Follow up and supervise the civil works and ensure timely and quality execution of
the works;
¾ Site survey, soils investigation work and testing of soils, water and materials used;
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Site surfacing;
¾ Switchgear, control / relay buildings including all building services, compound wall,
gates, structure and plant foundations, cable ways, troughing and ducts;
¾ Temporary and permanent access roads to substation from public road and road
works within substation;
¾ Site lighting system, including security lighting, small power and lighting
installations. Fire detection & alarm system, FM200 system, passive fire protection
(fire sealant works & cable coating (for HV/ML/LV cables) inside the buildings and
fire protection system & transformer explosion prevention system for the
transformers & reactors shall be in accordance with KM HSE requirements
¾ Guard Rooms.
¾ Clearance of site;
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 179 OF 189
REV. 2
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
¾ Defects Clearance;
¾ Warranty Period Services. The period of Warranty for all the works executed under
this shall be 2 years from the date of Taking Over.
The Warranty obligation and the warranty period shall NOT be changed or reduced
by any third party damages to the Works or any part of the Works, in case the
Contractor perform the repair of that damage or the damage has been repaired under
the supervision of the Contractor.
The Warranty obligation and the warranty period shall NOT be changed or reduced
by any third party damages to the Works or any part of the Works, in case the
Contractor perform the repair of that damage or the damage has been repaired under
the supervision of the Contractor.
It should be noted that clearances in the GIS room and its final dimensions have to
be specified and confirmed by GIS manufacturer, considering GIS arrangement,
type, required space for testing, replacement of main components (such as circuit
breakers) if necessary, dimensions of specific GIS bays / components, arrangement
of pressure relief openings, etc. Drawings which clearly represent access to the
inspection points, testing arrangements, maintenance and replacement of main
components will be provided by Contractor as the base for building architectural
design.
Minimum clearance in the GIS / Control room as specified herein below are based
mainly on the regular maintenance and inspection requirements, conformity of
working space and safety requirement for minimum gangway distances.
- All round clearance around the GIS: This space should ensure sufficient space for
the free moving of gas cart and mobile platforms. It should be min. 1.5m.
- At the entrance to GIS room, on the side of offloading area of equipment,
additional space has to be provided to enable transport of equipment inside the
GIS and handling by the crane. It should be min. 2.5m after the space for the last
future bay.
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
- Space around LCC: LCCs without requirement for the rear access are preferable,
since they require less space. In this case they can be aligned to the wall with
minimum clearance for the easier cooling (i.e. 5cm). Minimum distance between
GIS and LCC should be 2m.
- Depth of working space in the front of panels (control, protection, etc.): Min. 1.2m.
- If the panels are accessible from the rear side, minimum clearance to the wall
shall be 1m. In this case it is required that rear doors (if any) are all closing on the
same side and in direction of emergency exit which will enable fast evacuation of
persons from this area.
- If panels are arranged in two or more lines, with doors opening to the same aisle,
minimum distance between panels is 2m.
- Minimum free height of working space is 2m.
In addition to above, working space around GIS shall ensure the following for repair /
replacement:
- Sufficient horizontal free space shall be provided to facilitate removal of
components that are deemed to be withdrawn horizontally
- Similarly, sufficient vertical free space shall be provided to facilitate removal of
components deemed to be withdrawn vertically.
For 33kV and 11kV metal enclosed SWG with withdrawable components: From the
component in draw-out position minimum clear space shall be 1.5m.
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
24 Phase Identification x
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Identification of bays / (circuits and power x
26
transformer) numbers and Kahramaa
x
29 Specify cable HV test requirements
x x
8 HV Test bushing
For new SS For existing SS
9 Testing leads x
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
All installation material up to and including
10 x
OTB / OTP
GENERAL AND HV CABLES - WORKS
A.3 (Including all tools and materials required
for completion)
Construction of cable trenches / ducts inside
1 SS from the perimeter fence to the GIS x
basement / transformer
Construction of cable ducts for roads and
2 x
fence crossing
Provision of free access for cable installation
3 and related civil works, preparation of cable x
terminations, electrical and HV AC testing
5 Cables installation x
6 Sealing of sleeves x
Supervise
9 Cable termination to GIS / Transformer x
For new SS
12 Seal x
17 Cable gland x
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
19 Insulating fluid x
20 Seal x
23 HV Test performance x
B FO CABLES
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Splicing of all GTC/371/2010 Telecom FO
13 x
cables at OTP / OTB including E-E test
Milestones for FO laying, termination & end-to-
14 x
end testing
DTS SYSTEM – Not Applicable for New
C
Lines
x x
7 DTS unit connection to TCP/IP Router
For new SS For existing SS
Provision of power cables for DTS Equipment
8 x
supply
D TELECOM EQUIPMENT
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Provision of data cables between gateways of
5 SCS to connectors at interface cards on x
telecom equipment
Provision of TCP/IP connections for OMS
6 x
remote access and non-SCADA applications
Provision of telecom alarm connection cables
7 between SCS common bay controller and x
terminals block at telecom cabinet.
Provision of earthing system inside telecom
8 x
room as part of common earthing system
Provision of 240V, AC power supply cables
9 from station services supply up to telecom x
cabinets for aux. services
Provision of cable installation for non-critical
10 services such as PMR, CCTV, etc. for future x
connection to telecom equipment
Provision of 240V, AC UPS and MCB for
11 x
Telecom equipment supply
Provision of power cables from MCBs to
12 x
Telecom equipment
Provision of data cables between alarm
13 terminal blocks at UPS and alarm terminals x
blocks at Telecom equipment
Modification in 48V DC power supply for
14 x
telecom equipment in existing SS
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Connection and Termination from Telecom
8 Equipment to Pilot Copper Cable Terminal x
Box (including Telecom Barrier Transformer)
Termination of all GTC/371/2010 SS copper
cables at Pilot Copper Cable Terminal Box
including E-E test (Copper cable E2E test shall
9 x
include at least the following tests: Continuity
test, Isolation test, Attenuation test, Near End
Crosstalk, Far End Crosstalk)
Termination of all GTC/372/2010 copper
cables at Pilot Copper Cable Terminal Box
including E-E test (Copper cable E2E test shall
10 x
include at least the following tests: Continuity
test, Isolation test, Attenuation test, Near End
Crosstalk, Far End Crosstalk)
Milestones for Copper Cable laying,
11 x
termination & end-to-end testing
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Steel supports for surge arresters, CSE and
4 x
link boxes
Outline and dimension drawings for CSE, SA
5 and LB (equipment with support and x
foundation)
Cable compound detailed layout drawing and
6 x
cross-sections
Foundations for steel supports and surge
7 x
arresters
14 Phase Identification x
x
15 Matching of phases on line terminal ends x
x
16 Identification of bays / circuits numbers
and Kahramaa
GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS
TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
B FO CONNECTIONS