You are on page 1of 17

EFFLUENT TREATMENT PLANT Document No.

TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011


Rev. No.0
Page 1 of 17

1.0 PIPING REQUIREMENTS

0 27.09.05 ISSUED FOR BIDS PIPLANI B. Halder N. Kaul


Rev. Date Purpose Prepared Checked Approved
No by by by
EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved
EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 2 of 17

1.1 Detailed Scope of Work

1.1.1 The Contractor’s scope of work shall include complete design, detail
engineering, checking of all specifications, preparation of drawings and
documents, obtaining approvals from Statutory authorities, supply &
procurement of all materials and consumables, flexibility analysis, dynamic
analysis, supporting, fabrication, laying, erection, chemical cleaning, testing,
flushing and pre-commissioning, including steam flushing, if required, complete
in all respects, of all pipelines in accordance with the final Process Package
and required for successful erection, commissioning, operation and
maintenance of the plant. In addition to the total aboveground piping scope, as
above, the Contractor’s scope shall also include painting and insulation of
piping as per the P&IDs, line schedule and specifications.

1.1.2 Following minimum drawings and documents shall be prepared by the


Contractor and submitted to EIL/OWNER for approval/review/information for
execution of piping works:

(i) Final Equipment Layout in plans, elevations, and sections, with all
Vendor data incorporated for. Approaches and roads around the
Unit, drop out areas, and maintenance areas to be clearly marked.

(ii) Key Plan and Area Division for unit and offsite area. Area division
for underground piping and above ground piping shall be same
however the underground and aboveground piping shall be made in
separate drawings.

(iii) Piping General Arrangement Drawings.

(iv) Nozzle Orientation for all vessels showing all nozzles, as


applicable.

(v) Piping Isometrics for all lines with support marking and Bill of
Material.

(vi) Trim Drawing for all Equipment Mountings.

(vii) Flexibility Analysis reports.

(viii) Support drawings and pipe supports cleats on Equipment. Pipe


support standards/drawings to cover entire piping.

(ix) Updated Piping Material Specifications (PMS) and Valve Material


Specifications (VMS).

(x) IBR package as per the requirements of IBR authorities. (wherever


applicable)

(xi) Quality plan for piping activities.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 3 of 17

(xii) Specifications for Procurement taking into account the


requirements of General Notes in Piping Material Specification 6-
44-05.

(xiii) “AS BUILT” GADs, Isometrics, Nozzle Orientation, Equipment


Layout etc.

(xiv) Updated Welding Specification (6-77-0005) & NDT Specification


Charts (6-44-16) for all piping classes if required.

1.1.3 Battery Limit Condition


Scope drawing for ETP Package
Drawing No: 6557-90-16-47-3-010

1.1.4 Scope of Supply

1.1.5 Owner’s Scope of Supply


Nil

1.1.6 Contractor’s Scope of Supply


a) Supply, Procurement & Storage of all piping materials including springs and
bellows for the total work along with all material test certificates.

(i) Prepare Bill of Materials including material summary on the basis of


P&IDs, GADs, Isometrics including fabrication allowance pre-
commissioning and commissioning spares.
(ii) Prepare Material Requisitions, Material Status Reports etc.

(iii) Place purchase orders for all piping items on vendors approved by
EIL/OWNER. Furnish Final vendor drawings for piping items e.g.
Valves, Bellows, Steam Traps, Strainers and Springs etc.

(iv) Arrange EIL/3rd party inspection of materials by approved


inspecting agencies as per requirements, transport and receive
materials at site and store with proper identification tags.

b) Execute piping fabrication, laying and erection including prefabrication,


preheating, welding, NDT including radiography, site fabrication, Post-weld
heat treatment, erection, supporting, water/steam flushing, air drying, nitrogen
purging, testing, cleaning, painting, insulation, electrical tracing etc. as per
specifications attached with the bid package.

c) Perform, Flexibility analysis, Dynamic analysis, Digital/analog study of piping


as required, support selection, support schedule and it’s marking in drawings
and prepare engineering data for springs etc.

d) Procure, supply insulation materials with all accessories and execute all
insulation jobs as per specifications.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 4 of 17

e) Pipe rack, technological structures, crossover etc. as per specifications.

f) Supply of all support Procure, supply paint and execute painting of all equipment,
piping, structural like platform materials and fabrication and installation of
supports.

g) Execute all mechanical jobs identified during OWNER/EIL check list, Technical
audits, pre-commissioning and commissioning, including additional supports
required to restrain pipe movement avoiding interference with nearby
structural/piping.

h) Set up Field Engineering Cell and execute field engineering, which becomes
necessary to resolve problems during prefabrication, shop fabrication, field
fabrication or erection at site. Necessary field design change drawings shall be
submitted for approval and shall be reflected in the “as built” drawings /
documents.
i) Obtain clearances and approval from all applicable statutory/Government
agencies e.g. IBR, PCB, OISD, CCE, TAC etc.

j) All piping materials required for testing and pre-commissioning e.g. piping spools,
bolting and gaskets, flanges, blinds or any other piping materials for carrying out
this activity is included in Contractor’s scope of supply.

K) LSTK Contractor shall fully familiarize himself with the site conditions, approach
roads, location of fabrication yards, and transportation from the fabrication yard
to the unit and offsite areas.

The above list of activities is not exhaustive and therefore not limited to the
above. The scope includes all such activities as required, supply of all materials
and components as required, for successful commissioning of the plant as per
the requirements of the P&IDs, line lists, Piping Design Basis and Engineering
specifications etc. enclosed in the bid document so as to result in a total
operable and maintainable plant

1.2 Design Basis

1.2.1 CODES AND STANDARDS

All piping shall be designed as per ASME B31.3, except for steam and
condensate, which shall meet the requirements of Indian Boiler Regulation also.
Bidder’s work, supplies and construction shall comply with all codes and
standards referred to in the piping design basis. In addition, OISD norms for
equipment layout as per “OISD-118" shall also be followed. In case of any
discrepancies between the documents, matter should be referred to EIL/OWNER
for approval.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 5 of 17

1.2.2 BASIS OF WORK

The following documents enclosed in the bid document form the basis of work for
the bidder.

(i) Process Package including P&ID's, line lists, Data Sheets, Standards /
Specifications.

(ii) Piping and Valve Material Specification attached with the bid package
(duly updated after EIL approval for additional requirements, if any) and
other specifications attached in the bid package.

(iii) EIL specifications and engineering standards, which should be considered


as a minimum requirement and can be improved upon on mutual
agreement. Deviations, if any, shall be applicable only after written
approval from EIL/OWNER.

1.2.3 EQUIPMENT/PIPING LAYOUT CRITERIA

Piping Design basis shall be followed and read in conjunction with the points
written below.

(i) In general foundation height of pumps and equipment shall be minimum


300mm above HPP (Highest Point of Paving).

(ii) Avoid Piping Trenching in the Unit unless approved by EIL/OWNER.

(iii) Sleeper spacing shall not exceed 6.0M.

LSTK Contractor shall develop and finalize a detailed Equipment layout showing
elevations and distance of all equipment and structures which shall conform to
the requirements of OISD 118-1995, battery limit, platforms, all anchor bays, all
access and maintenance corridors, tube removal areas, drop out areas,
staircases, ladders, Electrical/Instrument cable trenches/ducts/trays, cross
sections of pipe racks, Monorails with capacity, E.O.T. with capacity, Fixed /
sliding supports, location with number of hose stations, eye wash and safety
shower (required as per P&ID’s ) etc. shall be submitted for EIL/OWNER
approval.

1.2.4 PIPE RACK

A minimum of 20% space of the total width of the pipe rack for all tiers combined
together shall be earmarked for future expansion on the pipe rack. Width of the
pipe rack and number of tiers shall be finalized by the LSTK Contractor to meet
the present requirements +20% extra space for future expansion, with not less
than 1000mm on each tier. The extra space on each tier shall be all through the
pipe rack and shall not be staggered. Contractor shall submit the loading on the
pipe rack due to sustained, friction, wind, thermal, seismic loads on the pipe rack

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 6 of 17

for review by EIL. These loads shall also take into account the loads due to
space reserved for future.

1.2.5 PIPE SPACING

Minimum Pipe spacing shall be based on Piping Design Basis using insulation
thickness as given in line list/insulation charts. Even if a flange may not be
appearing in the line the spacing shall be as per the EIL guidelines. Actual line
spacing shall take care of thermal expansion of adjoining lines during operation
as well as pre-commissioning/start up conditions. The spacing of pipelines in
the transverse direction across the pipe rack should take into consideration the
longitudinal expansion of the pipe along the pipe rack. Contractor to prepare
detailed pipe spacing chart for both horizontal runs as well as for 45 deg.
crossings for all applicable ratings and submit it for EIL review.

1.2.6 UTILITY HOSE STATION

Utility hose stations shall be provided for Service Water and Plant Air as per
EIL standard 7-44-0401 and as indicated in the P&IDs. Adequate number of
hose stations shall be provided so that every area at Grade, in structure,
buildings, tower etc. can be reached from at least one hose station. Each hose
station shall be furnished with 1" dia., 15-meter long hose. All utility
connections at the hose stations shall be quick coupling for Water. Hose
Stations for Nitrogen and any other service shall be provided as per the
requirements of P&IDs. Hose stations with numbers are to be marked on the
Equipment Layout.

1.2.7 STRESS ANALYSIS

Piping arrangement shall provide for flexibility of lines to take care of the
thermal expansion, contraction and equipment settlement. Large reactions or
moments at equipment connections shall be avoided, refer 5.4 for nozzle
loads. Expansion computation shall be made on the basis of a base
temperature of 21.1 deg. C (70 deg. F) and shall cover (+ve or -ve) design
temperature(s) as shown in line schedule as well as start-up and shutdown
conditions.

(a) Flexibility analysis shall meet the requirements of Code ASME B-31.3 (latest
edition). Analysis shall consider stress intensification factors as per ASME B-
31.3.

(b) The following factors shall be considered in the stress analysis:

- Friction for lines >= 8"NB; @ steel to steel=0.3: @ STEEL to PTFE=


0.1

- Corrosion Allowance

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 7 of 17

- Initial displacement of nozzles at design temperature(s).

- Transverse deflections = 25mm (maximum)

- Longitudinal expansion/contraction = 200mm (maximum)


Special care to be taken to check for expansion loops and shoe
support
Lengths shall be finalized accordingly

The following shall always be analyzed using comprehensive computer


analysis:

(i) All lines 8" and above and Design Temp. > 150 deg. C

(ii) All lines 16" and above and Design Temp. > 80 deg. C

(iii) All lines 6" and above and Design Temp. > 65 deg. C, that are
connected to Rotating Equipment, Air Coolers or any other
sensitive equipment.

(iv) Any other system/line that stress engineer feels necessary for
stress check.

For computer analysis packages like ‘CAESER-II’, ‘CAEPIPE’ shall be


used. Bidder shall specify the package to be used in the offer.
Flexibility Analysis reports shall be submitted for EIL/Owner’s review.

1.2.8 PIPING SUPPORTS

All piping shall be adequately supported, guided or anchored so as to prevent


undue vibration, deflection/expansion or loads on connected equipment and
piping and leakage at joints. Piping at valves and equipment such as heat
exchangers and pumps, requiring periodic maintenance shall be supported in
such a way so that the valves and Equipment can be removed with a minimum
necessity of installing temporary pipe supports. The first solid support for
pump suction and discharge lines shall be adjustable type to facilitate
pump alignment. Pedestal for pipe supports for outdoor installation shall be
150mm above HPP.

Pipe support pedestal drawing shall be submitted for approval and the type of
pedestal including load capacity shall be marked on Isometrics. Piping support
standard, with load bearing capacity, shall be submitted for EIL review prior to
submitting the Isometrics. Special pipe supports not covered in the pipe
support standard are to be submitted for EIL review along with the respective
isometrics.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 8 of 17

Spring supports shall have Teflon pad on top slide plate of spring for
temperatures up to 200°C and graphite pad or roller bearing for higher
temperatures.
HDPE pipes shall be continuously supported.

1.2.9 DRAWING AND PROCEDURES

All piping drawings shall be prepared on EIL/OWNER approved formats and


shall be complete showing sufficient details to clearly indicate pipe routing,
clearances, loops, equipment foundations, pipe rack columns, beams,
technological structures, underground piping, manholes/catch basins, anchors,
sections, guides, supports, connections to equipment, orientation, coordinates
etc. Blow up details wherever required for clarity shall be made. All dimensions
shall be in millimeters whereas all levels and coordinates shall be in meters. Vital
installations and battery limits shall be marked with coordinates. GADs shall be
prepared in 1:33 1/3 scale for Unit piping and in 1:100 scale for Offsite piping. All
Elevations shall be given with respect to EL 100.000, which corresponds to
relevant HPP.

All future lines shall be routed and shown as chain dotted on GADs with full
details indicating dimensions line number etc. Nozzle schedule giving nozzle
number, size, rating, facing, projection, elevation and orientation shall be
inserted in the GAD’s.

1.2.10 PIPING MATERIAL SPECIFICATION

LSTK Contractor shall update the Piping Material Specification 6-44-05 enclosed
with the bid package, generate for any additional requirement and submit it for
review by EIL. The Piping Material Specification updated by the LSTK Contractor
shall give all the details as required in the EIL standard format for Piping Material
Specifications.

All calculations for pipe thickness, reinforcement pads etc. are to be submitted
along with the updated Piping Material Specification for all sizes covered in the
Process Package. For sizes not covered in the detailed specification sheets,
LSTK Contractor to do the pipe thickness calculations. Pipe thickness,
reinforcement calculations shall be as per ASME B31.3. However, for
underground lines Contractor to ensure that the pipe thickness meets the soil
cushion pressure as per API 1104. Thickness specified in PMS is the minimum
requirement, in case of increase of thickness based on calculations, same shall
be provided without any cost / time implication. Thickness and reinforcement
calculations for lines under IBR shall meet IBR requirements in addition to ASME
B31.3. All additions in the PMS shall be consistent with the given parameters and
specifications and in no case inferior to the items already covered therein.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 9 of 17

1.2.11 VALVE MATERIAL SPECIFICATION

Valve Material Specification 6-44-06 shall be followed for this Project, which is
based on the Piping Material Specification. LSTK Contractor shall generate the
valve material specifications for all types/sizes of valves not covered in 6-44-06
based on Piping material specification. The valve material specification shall be
developed on the EIL standard formats for each type of valve and shall be
submitted for review by EIL.
Only those valves that are mentioned in the piping material specification
shall be used.
Any change to Contractors proposal for additions during EIL review shall not
entitle Contractor to charge extra cost to OWNER.

1.2.12 FABRICATION, ERECTION, TESTING, FLUSHING & CHEMICAL


CLEANING

Following EIL specifications shall be followed as a minimum:

6-44-0012 for Fabrication and Erection of Piping

6-44-0013 for Inspection, Flushing and Testing of Piping Systems.


Erected piping systems shall be hydro tested & hydro test
pressure shall be calculated by the Contractor based on
ASME B31.3, however for lines coming under IBR the hydro
test pressure shall be calculated based on requirements of
IBR.

6-44-14 Pre commissioning Chemical Cleaning etc.

In addition following shall be followed:

(i) Fabrication of all stub-in branch connections shall meet the requirement of
the relevant codes. Reinforcement pad to be provided only after carrying
out visual and additional checks specified for the branch weld.

1.2.13 WELDING AND NDT

Welding, pre- and post-weld heat treatment shall be carried out as per EIL
welding specification 6-77-0001. and welding specification charts covered in 6-
77-0005. However, welding procedure / welder qualification shall be approved by
EIL. Non-destructive testing of welds shall be as per 6-44-16. Welding and NDT
charts 6-77-0005 and 6-44-16 respectively shall be updated by the LSTK
Contractor for modifications made in the Piping Material Specifications and also
for classes not covered in the charts as per the EIL standard format and
submitted for EIL review.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 10 of 17

1.2.14 PAINTING

EIL Standard specification 6-44-0004 shall be followed completely. All


equipment, machinery, vessels, Exchangers etc. and others not insulated but
painted shall have a color coding and other requirements of markings
regarding hazard marking, camouflaging etc. shall be taken care as per the
specification. Surface cleaning shall be performed by blast cleaning to ensure
cleanliness exactly in line with the specification.

1.2.15 DRAWING SCHEDULE

Index of all the drawings for the Project to be prepared by LSTK Contractor.
The LSTK Contractor shall furnish schedule for submission for all
drawings/documents during the kick-off meeting. Any change in submission
dates may lead to delay in EIL review. Contractor shall not be entitled to any
schedule extension due to this delay neither any extra claim shall be raised
by the Contractor due to the delay in review for documents not furnished as
per schedule.

Contractor shall also prepare a Schedule of Inputs required from


EIL/OWNER, for detail engineering of the project and submit it during the
kick-off meeting for review by EIL/OWNER. Any delay of these inputs shall
not entitle the Contractor any extension in time schedule automatically unless
OWNER/EIL is convinced based on the reasons to be spelt out by the
Contractor before occurrence of such delays. No such request for schedule
extension shall be raised after exchange of data takes place.

1.2.16 PUMP PIPING

Operation and maintenance access to be clearly marked around the pumps.


All auxiliary piping to be routed in such a way so as to ensure that there is no
hindrance in the access areas. Cone type temporary strainers shall not be
used to avoid dismantling & realignment of pump suction piping. Y-Type, T-
Type or basket type strainers are only to be used.

1.2.17 TECHNICAL AUDIT

EIL shall carry out Technical Audit for the above project at site during the
construction stage of the project in order to confirm compliance to the
comments given on engineering drawings/ documents during the detail
engineering phase.

Contractor shall intimate in advance the readiness of various sections of the


Unit and shall furnish all relevant drawings/documents needed at site for
completing the Technical audit and/or as deemed necessary by the Engineer-
in-Charge of Technical Audit.

Any reworking arising at site due to the recommendations of technical audit


due to non compliance to Design basis, Process Package,
EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved
EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 11 of 17

Standards/Specifications attached with the bid package, comments on


reviewed documents shall be done by LSTK Contractor. All the costs for
above reworking shall be borne by the Contractor and no extra claims shall
be made. Contractor shall also not ask for any extension of time schedule for
project completion due to the extra work arising therein.

1.2.18 DEVIATION

LSTK Contractor shall ensure compliance to all technical specifications,


standard, Piping design basis, design guides, Licensors specifications,
Process package and any other Standard/Specification, which is part of this
bid package. However, in certain cases wherein LSTK Contractor deems
necessary to take any deviations to the above specifications, it shall be taken
only on the standard deviation formats enclosed in the bid package. LSTK
Contractor to note that until the deviation requested by him is approved by
EIL/OWNER he shall not proceed further with
Engineering/Construction/Procurement. Any delay arising due to the
deviations sought by the Contractor shall be the sole responsibility of the
Contractor and the Contractor sighting the above delays shall seek no
schedule extensions.

Contractor to also note that any financial implications arising due to dilution
of acceptable deviations shall be chargeable to the Contractor based on
assessments made by EIL/OWNER in this regard, however no extra claims
shall be admissible in case of up gradation of specifications

1.3 Spares

Mandatory Spares

In addition to commissioning/pre-commissioning spares, Mandatory Spare


Parts to be made available at the time of handing over of Plant to OWNER
shall be as follows:

QUANTITY REMARKS
S.NO. PART DESCRIPTION SIZE (INCH)
REQUIRED % OF
AS BUILT*
1 PIPES AND FITTINGS ½ TO 1½ 10
2 TO 8 5

10 TO 36 3
ABOVE 36 2
2 VALVES AND FLANGES ½ TO 1½ 8
2 TO 4 4
2
6 TO 8

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 12 of 17

QUANTITY REMARKS
S.NO. PART DESCRIPTION SIZE (INCH)
REQUIRED % OF
AS BUILT*
10 AND NIL
ABOVE
3 BOLTS, NUT AND ALL SIZES 10
GASKETS
4 TRAPS ALL SIZES 8
5 EXPANSION BELLOWS ALL SIZES 100
BOLT TORQUE ---
6
WRENCHES
BOLT TENSIONING ---
7
EQUIPMENT
POSITIVE MATERIAL ---
8
IDENTIFICATION (PMI)
EQUIPMENT

NOTE-1: % of quantity required to be left as mandatory spares is for each and


every item consumed in as built. No substitution is allowed.
NOTE-2: As a minimum one piece (one pipe length) per item spare shall be
supplied. No substitution in size and material allowed.

1.4 Vendors Drawing / Documents Required

Vendor drawing shall be submitted for review of Owner/EIL.

1.4.1 Drawings / Documents Required with Bid

Plant/Equipment Layout

1.4.2 Drawings / Documents Required after Award of contract

The following table gives the requirements of documentation for


review/information/record of the OWNER/EIL. These shall be strictly
submitted in the sequence shown. No bunching of documents shall take
place. The prerequisite documents must have a review code 1 or review code
2 before submitting the downstream documents otherwise the document shall
not be reviewed and shall be sent back in review code-3. The requirements
of preceding/prerequisite documents have been highlighted in the remarks
column. The schedule of submission of deliverables by the LSTK Contractor

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 13 of 17

during the kick-off meeting shall be based on the sequence and deliverables
prerequisites mentioned herein.

It shall be the Contractor’s responsibility to ensure compliance with the


contract documents and relevant codes. The review/approval by EIL/OWNER
does not relieve the Contractor of his responsibility under this contract and
any omission/commission noticed at any stage shall be made good by the
Contractor within the quoted rates. No extra claims and extension of
schedule whatsoever shall be entertained on this account.

All documents/drawings submitted for EIL/OWNER’S review shall comply


with the contract documents viz. Design Basis, relevant
Standards/Specifications, P&IDs, Licensor’s requirements mentioned in the
bid package etc. If any document/drawing is returned with code-3 due to
noncompliance of the above, the efforts needed for review of the same by
EIL/OWNER shall be back charged to LSTK contactor. Contractor shall be
fully responsible for more time taken during review by EIL because of poor
quality of engineering performed.

EIL/OWNER reserve the right to change the category of documents from


review to records and vice versa.

1.5 LIST OF DELIVERABLES - PIPING

S.NO. Description Approval Review Records Remarks/prerequisite

1a. Activity wise quality plan U


List of all drawings/ Review at first
1b.
Documents with schedule of submission. Schedule
submission and schedule of U to be issued on monthly
inputs required from basis for information.
EIL/OWNER.
Updated piping material Based on EIL material
2a
specification along with all specification,
calculations for thickness, modifications ,
U
reinforcement calculations approved utility P&IDs
(list of changes and and line list.
additional specifications)
2b Completed PMS U
Updated Valve Material Approved ’2a’
3a
Specification (list of (NOTE -2) Piping
U
changes and additional Material Specifications.
specifications)
3b Completed VMS U

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 14 of 17

S.NO. Description Approval Review Records Remarks/prerequisite

Based on tentative
4a U equip. layouts attached
Equipment Layout
with bid document
4b Key Plan And Area Division Prerequisite: approved
Dwgs. U (note-2) equipment
layout
5 Piping spacing charts
U

6 Cross-sectional views of Prerequisite:


pipe rack for justifying pipe Reviewed (note-2)
U
rack width as per Bid utility P&IDs, line list.
document
7a Material summary (Unit
U Only in electronic form
wise U/G & A/G separately)
7b MR schedule U
Based on requirements
8 Technical specification for
of general notes for
procurement for piping
piping item as per
items U
Piping Material
Specification attached
in bid package
9 Flexibility analysis report
with stress isometrics U
marked with computer nodal
points and support location
Piping GADs Prerequisites: approved
10
equipment layout and
area division drawing.
U
Reviewed flexibility
reports as per
deliverable at item 11a
Piping supports standard Pedestal drawings
11
and pipe support pedestal U reviewed by Structure.
drawings
12 Special pipe supports i.e.
Not covered in standard
supports U

13 Vendor drawings for


bellows, ball valves, plug
valves, butterfly valves and U
special tagged items

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 15 of 17

S.NO. Description Approval Review Records Remarks/prerequisite

14 Vendor drawings for


strainers, steam traps, U
spring supports

15 As Built Drawings (GAD and


isometrics) U

S.NO. MARKED * * IS NOT APPLICABLE FOR THIS JOB

NOTES:
1. CONTRACTOR shall proceed for further detail Engineering after incorporation of
OWNER/EIL’s comments.

2. Reviewed prerequisite document may be in Code-1 or Code-2.

3. The documents shall be submitted in the sequence shown above.

4. The prerequisite documents must have a review code1 or review code2 before
submitting the downstream documents, otherwise the document shall not be
reviewed and shall be sent back in review code-3.

5. The requirements of preceding/prerequisite have been highlighted in the remarks


column.

All documents/drawings submitted for OWNER/EIL’s review shall comply with the
contract documents viz. Design Basis, Job Specifications, relevant
Standards/Specifications, P&IDs, Licensor’s requirements mentioned in the bid package
etc.

OWNER/EIL reserve the right to change the category of documents from review to
records and vice versa.

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 16 of 17

List of Enclosures

1.6 Data Sheets

S. No. Data Sheet No. Rev. Description


1 6557-6-44-0005 4 Piping Material
Specifications- A3A, A1N,
A1K, FS
2 6557-6-44-0006 5 Valve Material Specification
Nos. 51001, 51045, 51066,
51321, 51345, 51366, 52001,
52045, 52066, 52321, 52345,
52366, 53001, 53045, 53066,
53321, 53345, 53366

1.6.1 Drawings

S. No. Drawing No. Rev. Description


1 Not Applicable

1.6.2 Standard Specifications

S. No. Specification No. Rev. Description


1 0287-PT-0642-J-04 0 Job Standard specification
for Shop & Field Painting
2 6-44-0012 2 Std. Spec. for Fabrication &
Erection of Piping
3 6-44-0013 2 Std. Spec. for Flushing &
Testing of Piping System
4 6-44-0016 4 Std. Spec. for Non
Destructive Examination
Requirement of Piping
5 6-44-0017 1 Std. Spec. for Pressure
Testing of Erected Piping
Systems
6 6-44-51 3 Technical Notes for Pipes
7 6-44-52 4 Technical Notes for Valves
8 6-44-53 3 Technical Notes for flanges,
spectacle blind & drip ring
9 6-44-54 3 Technical Notes for Butt
Welded, Socket Welded &
Screwed Fitting
10 6-44-0056 2 Technical Notes for Gasket
11 6-44-0057 2 Technical Notes for Bolts &
Nuts

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved


EFFLUENT TREATMENT PLANT Document No.
TECHNICAL SPECIFICATIONS 6557-90-16-47-SP011
Rev. No.0
Page 17 of 17

1.6.3 Standards

S. No. Standard No. Rev. Description


1 7-44-0032 2 Stub-in Standard
2 7-44-0033 2 Details of Mitre Elbow
3 7-44-0350 2 Vents & Drains (On Lines
1.5” & Below)
4 7-44-0351 2 Vents & Drains (On Lines 2”
and Above)
5 7-44-0352 2 Orientation of Orifice Taps
6 7-44-0353 2 Well Installation
1.5” dia. Taps
7 7-44-0354 2 Pressure Tappings
(PA, PG, PC, PT, PIC ETC)
8 7-44-0302 2 T-Strainer Type-3
9 7-44-0303 2 T-Strainer Type-1, 2”-4”
10 7-44-0304 3 T-Strainer Type-1, 6”-24”
11 7-44-0305 2 T-Strainer Type-2, 2”-24”

1.7 Addendum to Standards / Specifications


Nil

EIL-1647-1883.8 Rev. 1 Copyrights EIL – All rights reserved

You might also like