You are on page 1of 1

IS 1343:2007

0.088 for R.C bridges & 0.154 for steel bridges. The impact stages, re-stressing for adjustment of force or
% for highway bridges can also be directly obtained from for monitoring of force, if required, etc.
the curves of IRC code. b) Calculated amount of tensile force and
IRC Class AA or 70R loadings. Less than 9m span- for corresponding expected elongation of each tendon
tracked vehicle 25% for span up 5m linearly reduced to 10% when methods described in (a) are followed.
for span of 9m. c) Minimum requirements of strength of concrete at
For span 9m & more, tracked vehicle- for RC bridges, 10% transfer (see also 16.2), stressing sequence with
up to a span of 40m & in accordance with spans exceeding respect to age of concrete or stage of construction,
40m. for steel bridges,25% for span up to 23m & as per span requirements with respect to grouting operations of
exceeding 23m. neighbouring tendons.
13.1.3 Detailed note on Beam and slab Deck bridges. d) Method(s) of measuring force and elongation. e)
Beam bridge: Is consist of a horizontal beam supported at Tolerances/limits of variation from design
each end by piers.(a)when the load pushes down on the requirements stated in (a) and (b) beyond which
beam the top edge is push together or compressed ,while the reference should be made to the designer (In the
bottom of the beam is stretched or is under tension.(b)The absence of any specified provision provided by the
beam must be strong enough so that it doesn't bend under its designer, method described in 13.2.1.3 may be
own weight and the added weight. adopted for acceptance).
13.1.4 Slab deck bridge: A bridge deck is the roadway or f) Assumptions made in calculation of
the pedestrian walkway, surface of bridge and is one forceelongation relationship should be given. These
structural element of the superstructure of the bridge. The include effective ‘E’ value of tendon, crosssectional
Deck may be constructed of concrete, steel, open granting or area of tendon, co-efficient of friction and wobble
wood. Sometimes the Deck is covered with the Asphalt factor between tendon and duct, assumed slip in
concrete or other pavement. When bridge Deck is installed anchoring devices, if any, efficiency of prestressing
in through Truss, it is sometimes called as Floor system. jacks where force is measured indirectly by
Some bridges such as Tide Arch or a Cable stayed, the deck pressure gauges on jacks, corrections to elongation
is primary structural element, carrying tension or due to changes in gripping length beyond
compression to support span. anchorages during stressing and any other relevant
13.1.4.3 The anchorage shall transfer effectively and information.
distribute, as evenly as possible, the entire force from the 13.2.1.2 Any slack in the prestressing tendon shall
prestressing tendon to the concrete without inducing first be taken up by applying a small initial tension.
undesirable secondary or local stresses. The initial tension required to remove slackness
13.1.4.4 The anchorage shall be safe and secure against both shall be taken as the starting point for measuring
dynamic and static loads as well as against impact (see elongation.
Annex C). Further increase of tension shall be carried out in
13.1.4.5 The anchorage shall have provision for the suitable steps and corresponding elongations noted.
introduction of a suitable protective medium, such as cement The ‘force-elongation’ relationship shall be
grout, for the protection of the prestressing steel unless recorded in tabular and/or graphical form. The
alternative arrangements are made. magnitude of initiatial effective elongation
13.2 Procedure for Tensioning and Transfer corresponding to initial tension applied to remove
13.2.1 Stressing slackness shall be obtained from the recorded and
13.2.1.1 The tensioning of prestressing tendons shall be linearized portion of measured tensione longation
carried out in a manner that will induce a smooth and even relationship and added to the measured elongation
rate of increase of stress in the tendons. The prestressing to give the total elongation. Alternatively, the same
shall be controlled by measuring both the force applied to correction can be carried out graphically as shown
the tendon and the elongation of the tendon. Stressing in Fig. 1.
schedule shall be incorporated in the design, which may 13.2.1.3 In practice, the force and elongation of
include the following: tendon may not exactly match with the expected
a) Details of equipment and procedure for applying values given in stressing schedule. In such cases
prestress, specification of one end or simultaneous either the force (or the elongation) will be achieved
stressing from both ends of tendons, stressing in first and the other value lag behind. In such cases
single stage or multiple the force (or elongation) shall be further increased,
but not exceeding 5 percent of the design value till
the elongation (or force), which

16

You might also like