ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL

D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD


DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

SOMMAIRE

1. INTRODUCTION .................................................................................................................................................... 1
1.1 CONTEXTE DE L’ETUDE ......................................................................................................................................... 1
1.2 OBJECTIFS DU PROJET ............................................................................................................................................ 2
1.3 PRESENTATION DE LA ZONE D’ETUDE .................................................................................................................... 3
2. PRESENTATION GENERALE ET DONNEES PHYSIQUES ........................................................................... 4
2.1 SITUATION GEOGRAPHIQUE ADMINISTRATIVE ET LOCALISATION DU SITE ............................................................. 4
2.2 DONNES SOCIO-ECONOMIQUES DE LA REGION....................................................................................................... 4
Démographie ................................................................................................................................................. 4
Education....................................................................................................................................................... 6
Santé et Nutrition ........................................................................................................................................... 6
Eau potable et Assainissement ...................................................................................................................... 7
Pêche et Aquaculture ..................................................................................................................................... 7
Commerce ...................................................................................................................................................... 8
Tourisme ........................................................................................................................................................ 8
2.3 CARACTERISTIQUES CLIMATIQUES ........................................................................................................................ 8
Les vents ........................................................................................................................................................ 8
Pluviométrie .................................................................................................................................................. 9
Température ................................................................................................................................................ 10
L’humidité relative ...................................................................................................................................... 10
L’insolation ................................................................................................................................................. 10
2.4 EFFETS DES CHANGEMENTS CLIMATIQUES........................................................................................................... 11
2.5 RESSOURCES EN EAUX ......................................................................................................................................... 11
Eaux de surface ........................................................................................................................................... 11
2.5.1.1 Le Gorom amont ..................................................................................................................................................... 12
2.5.1.2 Le Gorom aval ........................................................................................................................................................ 13
2.5.1.3 Le Lampsar ............................................................................................................................................................. 13
2.5.1.4 Le Kassack .............................................................................................................................................................. 14
2.5.1.5 Le Diovol (Diawel) ................................................................................................................................................. 15
2.5.1.6 Le Djeuss ................................................................................................................................................................ 15
2.5.1.7 Le Ngalam............................................................................................................................................................... 15
2.5.1.8 Les trois marigots :.................................................................................................................................................. 15
Eaux souterraines ........................................................................................................................................ 16
2.5.2.1 La nappe du Maastrichtien ...................................................................................................................................... 16
2.5.2.2 La nappe de l'Eocène .............................................................................................................................................. 16
2.5.2.3 La nappe du Continental Terminal .......................................................................................................................... 17
2.5.2.4 La nappe alluviale superficielle............................................................................................................................... 17
2.6 RESSOURCES EN SOLS .......................................................................................................................................... 18
2.7 RAPPEL DES RESULTATS DE L’ETUDE ENVIRONNEMENTALE ................................................................................ 21
3. DIAGNOSTIC DE MISE EN VALEUR .............................................................................................................. 23
3.1 METHODOLOGIE DE DIAGNOSTIC ......................................................................................................................... 23
3.2 NIVEAU DE MISE EN VALEUR AGRICOLE .............................................................................................................. 24
Superficie exploitée ..................................................................................................................................... 24
Systèmes de culture et occupation des sols .................................................................................................. 24
Modèle de culture ........................................................................................................................................ 25
3.2.3.1 Variétés de Riz ........................................................................................................................................................ 25
3.2.3.2 Le cycle cultural ...................................................................................................................................................... 25
Techniques culturales .................................................................................................................................. 26
3.2.4.1 Préparation du sol ................................................................................................................................................... 26
3.2.4.2 Les opérations de semis .......................................................................................................................................... 27
3.2.4.3 Les opérations d'entretien et de couverture ............................................................................................................. 27
3.2.4.4 Les opérations de récolte......................................................................................................................................... 27
3.2.4.5 Itinéraires techniques .............................................................................................................................................. 27
3.2.4.6 Rendements des cultures ......................................................................................................................................... 28
3.2.4.7 Intrants Agricoles .................................................................................................................................................... 29

Groupement MCG / SAFI i


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

3.3 BESOINS ACTUELS EN EAU ................................................................................................................................... 31


Coefficient cultural Kc................................................................................................................................. 31
L’efficience des réseaux............................................................................................................................... 32
Tour d’eau actuel ........................................................................................................................................ 32
Main d’eau et durée d’irrigation ................................................................................................................. 32
Récapitulatif des besoins actuels en eau ..................................................................................................... 33
Main d’œuvre Agricole ................................................................................................................................ 35
Bétail ........................................................................................................................................................... 35
Machines Agricoles et Utilisation ............................................................................................................... 35
3.4 L’ELEVAGE .......................................................................................................................................................... 36
Contribution de l’élevage dans la vie socioéconomique ............................................................................. 37
Mode de conduite ........................................................................................................................................ 37
3.5 ORIENTATIONS FUTURES DU PROJET .................................................................................................................... 38
4. DIAGNOSTIC DES INFRASTRUCTURES ....................................................................................................... 39
4.1 HISTORIQUE DE L’AMENAGEMENT ...................................................................................................................... 39
4.2 METHODOLOGIE DE DIAGNOSTIC ......................................................................................................................... 41
4.2.1.1 Les moyens humains du diagnostic ......................................................................................................................... 41
4.2.1.2 Les moyens matériels .............................................................................................................................................. 42
4.2.1.3 Déroulement du diagnostic ..................................................................................................................................... 42
4.3 DIAGNOSTIC DE LA STATION DE POMPAGE ........................................................................................................... 44
Présentation de la station de pompage de Grand Digue-Tellel................................................................... 45
Résume du programme de réhabilitation des équipements ......................................................................... 47
4.4 DIAGNOSTIC DU RESEAU D’IRRIGATION ............................................................................................................... 50
4.5 OUVRAGES SUR RESEAU D’IRRIGATION ............................................................................................................... 72
4.6 RESEAU DE DRAINAGE ......................................................................................................................................... 76
4.7 RESEAU DE PISTE ................................................................................................................................................. 77
4.8 RESULTATS ET ORIENTATION DU PROJET DE REHABILITATION ............................................................................. 79
5. PROJET DE REHABILITATION ....................................................................................................................... 81
5.1 DESCRIPTION DES TRAVAUX DE REHABILITATION ............................................................................................... 82
5.2 TRAVAUX TOPOGRAPHIQUES .................................................................................................................... 83
Méthodologie ............................................................................................................................................... 83
5.2.1.1 Implantation et levé des bornes d’appui .................................................................................................................. 83
5.2.1.2 Précision des levés .................................................................................................................................................. 85
5.2.1.3 Levé des canaux ...................................................................................................................................................... 85
5.2.1.4 Levé des pistes ........................................................................................................................................................ 85
5.2.1.5 Levé du terrain naturel ............................................................................................................................................ 85
5.2.1.6 Difficultés rencontrées lors des levés : .................................................................................................................... 86
5.2.1.7 Traitement et compte rendu .................................................................................................................................... 86
Les moyens utilisées .................................................................................................................................... 86
Conclusion ................................................................................................................................................... 86
6. SCHEMA D’AMENAGEMENT HYDRAULIQUE ........................................................................................... 87
6.1 ORIENTATION CULTURALE ET BESOINS EN EAUX ................................................................................................. 87
Découpage du périmètre ............................................................................................................................. 87
Mise en valeur ............................................................................................................................................. 87
Occupation future du sol et assolement ....................................................................................................... 87
Superficie future du périmètre ..................................................................................................................... 87
Système de desserte ..................................................................................................................................... 88
Le cycle cultural .......................................................................................................................................... 90
Besoins futur en eau .................................................................................................................................... 91
6.1.3.1 Débit effectif ........................................................................................................................................................... 91
6.1.3.2 Découpage des quartiers ......................................................................................................................................... 91
6.1.3.3 Main d’eau .............................................................................................................................................................. 91
6.1.3.4 Dose d’irrigation ..................................................................................................................................................... 91
6.1.3.5 Durée d’irrigation et tour d’eau ............................................................................................................................... 92
6.1.3.6 Débit d’équipement ................................................................................................................................................. 93
6.2 ALIMENTATION PARTIELLE DU PERIMETRE GRAVITAIREMENT A PARTIR DU LAMPSAR ........................................ 93
Description .................................................................................................................................................. 93

Groupement MCG / SAFI ii


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Objectif ........................................................................................................................................................ 93
Evaluation du niveau d’eau dans le fleuve .................................................................................................. 94
Evaluation du niveau d’eau dans la station................................................................................................. 95
6.3 REHABILITATION DU RESEAU D’IRRIGATION ....................................................................................................... 97
Actions de réhabilitation retenues ............................................................................................................... 97
Superficie du projet ..................................................................................................................................... 97
Superficie à irriguer par canal .................................................................................................................... 97
6.3.3.1 Canaux d’ordre primaire ......................................................................................................................................... 97
6.3.3.2 Canaux d’ordre secondaire (canaux secondaire, tertiaires, quaternaires et quinquénaires) ..................................... 98
Débit du projet........................................................................................................................................... 110
Calage du réseau d’irrigation ................................................................................................................... 110
6.3.2.1 Pente de calage ...................................................................................................................................................... 110
6.3.2.2 Perte de charge .................................................................................................................................................... 110
6.3.2.3 Calage de plan d’eau ........................................................................................................................................... 112
6.3.2.4 Profil en long ........................................................................................................................................................ 112
Dimensionnement du réseau d’irrigation .................................................................................................. 134
Revanche ................................................................................................................................................... 135
6.4 OUVRAGE SUR CANAUX D’IRRIGATION .............................................................................................................. 169
Actions de réhabilitation retenues ............................................................................................................. 169
Ouvrage sur canaux principaux ................................................................................................................ 169
6.4.2.1 Ouvrage Partiteur .................................................................................................................................................. 169
6.4.2.2 Ouvrage partiteur modulé ..................................................................................................................................... 172
6.4.2.3 Ouvrage de transition ............................................................................................................................................ 177
6.4.2.4 Ouvrage de franchissement ................................................................................................................................... 177
6.4.2.5 Vanne de contrôle ................................................................................................................................................. 179
6.4.2.6 Ouvrages de traversée ........................................................................................................................................... 179
Ouvrage sur canaux d’ordre secondaire ................................................................................................... 182
6.5 REHABILITATION DU RESEAU DE DRAINAGE ...................................................................................................... 191
Actions de réhabilitation retenues ............................................................................................................. 191
Drains principaux et superficie drainée .................................................................................................... 191
Débit du projet........................................................................................................................................... 191
Profil en long des drains ........................................................................................................................... 192
Dimensionnement du réseau de drainage .................................................................................................. 204
Revanche ................................................................................................................................................... 204
6.6 OUVRAGES SUR RESEAU DRAINAGE ................................................................................................................... 215
Actions de réhabilitation retenues ............................................................................................................. 215
6.6.1.1 Dimensionnement des ouvrages de traversées ...................................................................................................... 215
6.7 REHABILITATION DU RESEAU DE PISTES ............................................................................................................ 220
Actions de réhabilitation retenues ............................................................................................................. 220
Dimensionnement de la structure des pistes : ........................................................................................... 220
6.7.2.1 Hypothèses de dimensionnement .......................................................................................................................... 220
6.7.2.2 Modélisation de la structure avec le logiciel ALIZE ............................................................................................. 220
6.7.2.3 Sol support ............................................................................................................................................................ 221
Conception géométrique des pistes ........................................................................................................... 221
6.7.3.1 Vue en plan ........................................................................................................................................................... 221
6.7.3.2 Profil en long ........................................................................................................................................................ 221
6.8 NIVELLEMENT DES PARCELLES .......................................................................................................................... 222
7. AVANT-METRES ET DEVIS QUANTITATIF DES TRAVAUX .................................................................. 224
8. MESURES D’ACCOMPAGNEMENT .............................................................................................................. 233
8.1 AMELIORATION DES CONDITIONS DE VIE DES FEMMES ...................................................................................... 233
8.2 FORMATION ET RENFORCEMENT DES CAPACITES ............................................................................................... 233
Organisation des exploitants ..................................................................................................................... 234
Amélioration des conditions d’accès aux crédits ...................................................................................... 234
Formation des exploitants et des organisations paysannes ....................................................................... 234
8.2.3.1 Dirigeants des organisations paysannes : .............................................................................................................. 234
8.2.3.2 Exploitants : .......................................................................................................................................................... 235
Renforcement de la recherche-développement .......................................................................................... 236
8.3 EQUIPEMENTS D’APPUI ...................................................................................................................................... 237
Maison Communautaire (Maison du Village) ........................................................................................... 237

Groupement MCG / SAFI iii


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Magasin ..................................................................................................................................................... 237


Magasin pour Machines Agricoles ............................................................................................................ 237
Rizerie ........................................................................................................................................................ 237
Département PR ........................................................................................................................................ 237
Chambre du Concierge.............................................................................................................................. 237
9. SPECIFICATIONS TECHNIQUES DU PROJET DE REHABILITATION ................................................ 239
9.1 EQUIPEMENTS HYDROMECANIQUES ET PIECES SPECIALES ................................................................................. 239
Remise en état des pièces à conserver ....................................................................................................... 239
Remplacement des pièces défectueuses ..................................................................................................... 239
9.2 RESEAU D’IRRIGATION ...................................................................................................................................... 239
Canaux bétonnés ....................................................................................................................................... 239
9.2.1.1 Déblai.................................................................................................................................................................... 239
9.2.1.2 Remblai ................................................................................................................................................................. 240
9.2.1.3 Construction des canaux ....................................................................................................................................... 240
Canaux en terre ......................................................................................................................................... 240
9.2.2.1 Canaux à renouveler ............................................................................................................................................. 240
9.2.2.2 Canaux à réhabiliter .............................................................................................................................................. 241
9.2.2.3 Caractéristiques des canaux .................................................................................................................................. 241
9.3 DRAINS .............................................................................................................................................................. 241
Travaux prévus .......................................................................................................................................... 241
Drain à renouveler .................................................................................................................................... 242
9.4 PISTES ............................................................................................................................................................... 242
9.5 OUVRAGES COURANTS ...................................................................................................................................... 243
10. RECOMMANDATIONS COMMUNES POUR LA GESTION DU PERIMETRE .................................... 244
10.1 CONTROLE DES NIVEAUX D’EAU ...................................................................................................................... 244
10.2 CONTROLE DES DEBITS .................................................................................................................................... 244
10.3 GESTION HYDRAULIQUE DE LA STATION DE POMPAGE ..................................................................................... 244
10.4 ENTRETIEN ...................................................................................................................................................... 245
Entretien des canaux et collecteur de drainage ....................................................................................... 245
Entretien des ouvrages ............................................................................................................................ 245
11. CONDITIONS DE REALISATION DES TRAVAUX ................................................................................... 247
11.1 REPARTITION EN LOTS ..................................................................................................................................... 247
11.2 PROGRAMMATION DES TRAVAUX .................................................................................................................... 247

Groupement MCG / SAFI iv


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

LISTE DES TABLEAUX

TABLEAU N° 1 : POPULATION ESTIMEE EN 2017 DANS LA ZONE DU PROJET ..................................................................... 4


TABLEAU N° 2 : MOTIFS DE CONSULTATION ET MORBIDITE............................................................................................. 6
TABLEAU N° 3 : CAUSES DE CONSULTATIONS.................................................................................................................. 6
TABLEAU N° 4 : PRODUCTIONS ENTRE 2014 ET 2015....................................................................................................... 8
TABLEAU N° 5 : DIRECTION DES VENTS DOMINANTS A SAINT-LOUIS (15 ANS) ................................................................ 9
TABLEAU N° 6 : PLUVIOMETRIE A SAINT-LOUIS (15 ANS) ............................................................................................... 9
TABLEAU N° 7 : TEMPERATURE A LA STATION DE SAINT-LOUIS (15 ANS) ..................................................................... 10
TABLEAU N° 8 : HUMIDITE RELATIVE A LA STATION DE SAINT-LOUIS (15 ANS) ............................................................ 10
TABLEAU N° 9 : FONCTION DES AXES HYDRAULIQUES DE LA ZONE DU PROJET.............................................................. 15
TABLEAU N° 10 : POTENTIALITE DES SOLS .................................................................................................................... 20
TABLEAU N° 11 : SUPERFICIE DU PERIMETRE GDT ....................................................................................................... 24
TABLEAU N° 12 : CYCLE CULTURAL ACTUEL ................................................................................................................ 25
TABLEAU N° 13 : FICHE TECHNIQUE DU RIZ .................................................................................................................. 27
TABLEAU N° 14 : PRODUCTION AGRICOLE DANS LE PERIMETRE GDT........................................................................... 29
TABLEAU N° 15 : PRODUITS CONTRE LES RAVAGEURS DES PARCELLES RIZICOLES : ...................................................... 29
TABLEAU N° 16 : PRINCIPAUX RAVAGEURS ET MALADIES DES CULTURES MARAICHERES ............................................. 31
TABLEAU N° 18 : RECAPITULATIF DES BESOINS EN EAU ACTUELS ................................................................................. 34
TABLEAU N° 19 : MAIN D’ŒUVRE AGRICOLE ............................................................................................................... 35
TABLEAU N° 20 : MACHINE AGRICOLES, OUTILS , ET EQUIPEMENTS POUR LE TRAITEMENT DES PRODUITS
AGRICOLES ........................................................................................................................................................... 36
TABLEAU N° 21 : ESTIMATION CHEPTEL (2017) ............................................................................................................ 36
TABLEAU N° 22 : LINEAIRES DES CANAUX ET SUPERFICIE IRRIGUEE ............................................................................. 50
TABLEAU N° 23 : DIAGNOSTIC DU CANAL PRINCIPAL C-1 ............................................................................................. 51
TABLEAU N° 24 : DIAGNOSTIC DE CANAL PRINCIPAL C-2 .............................................................................................. 51
TABLEAU N° 25 : DIAGNOSTIC DE CANAL PRINCIPAL C-3 .............................................................................................. 52
TABLEAU N° 26 : DIAGNOSTIC DE CANAL PRINCIPAL C-4 .............................................................................................. 53
TABLEAU N° 27 : DIAGNOSTIC DES CANAUX SECONDAIRES (C-1) ................................................................................. 54
TABLEAU N° 28 : DIAGNOSTIC DES CANAUX TERTIAIRES (C-1) ..................................................................................... 54
TABLEAU N° 29 : DIAGNOSTIC DES CANAUX QUATERNAIRES (C-1) ............................................................................... 56
TABLEAU N° 30 : DIAGNOSTIC DES CANAUX QUINQUENAIRES(C-1) .............................................................................. 58
TABLEAU N° 31 : DIAGNOSTIC DES CANAUX SECONDAIRES (C-3) ................................................................................. 59
TABLEAU N° 32 : DIAGNOSTIC DES CANAUX TERTIAIRES (C-3) ..................................................................................... 60
TABLEAU N° 33 : DIAGNOSTIC DES CANAUX QUATERNAIRE (C-3) ................................................................................ 61
TABLEAU N° 34 : DIAGNOSTIC DES CANAUX QUINQUENAIRES (C-3) ............................................................................. 62
TABLEAU N° 35 : DIAGNOSTIC DES CANAUX SECONDAIRES (C-2) ................................................................................. 62
TABLEAU N° 36 : DIAGNOSTIC DES CANAUX TERTIAIRES(C-2) ...................................................................................... 63
TABLEAU N° 37 : DIAGNOSTIC DES CANAUX QUATERNAIRES (C-2) ............................................................................... 64
TABLEAU N° 38 : DIAGNOSTIC DES CANAUX QUINQUENAIRES (C-2) ............................................................................. 66
TABLEAU N° 39 : DIAGNOSTIC DES CANAUX QUINQUENAIRES (C-2) ............................................................................. 66
TABLEAU N° 40 : DIAGNOSTIC DES CANAUX SECONDAIRES (C-4) ................................................................................. 67
TABLEAU N° 41 : DIAGNOSTIC DES CANAUX TERTIAIRES (C-4) ..................................................................................... 67
TABLEAU N° 42 : DIAGNOSTIC DES CANAUX QUATERNAIRES (C-4) ............................................................................... 69
TABLEAU N° 43 : DIAGNOSTIC DES CANAUX QUINQUENAIRES (C-4) ............................................................................. 70
TABLEAU N° 44 : DIAGNOSTIC DES OUVRAGES SUR C-1 ................................................................................................ 73
TABLEAU N° 45 : DIAGNOSTIC DES OUVRAGES SUR C-2 ................................................................................................ 73
TABLEAU N° 46 : DIAGNOSTIC DES OUVRAGES SUR C-3 ................................................................................................ 74
TABLEAU N° 47 : DIAGNOSTIC DES OUVRAGES SUR C-4 ................................................................................................ 74
TABLEAU N° 48 : LISTING DES BORNES ......................................................................................................................... 83
TABLEAU N° 49 : BORNES DE RATTACHEMENT.............................................................................................................. 84
TABLEAU N° 50 : SUPERFICIE DU PERIMETRE GDT ....................................................................................................... 87
TABLEAU N° 51 : CYCLE CULTURAL .............................................................................................................................. 90
TABLEAU N° 52 : SUPERFICIE DU PROJET....................................................................................................................... 97
TABLEAU N° 53 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL PRINCIPAL ................................................................. 97
TABLEAU N° 54 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL SECONDAIRE (C-1) .................................................... 98
TABLEAU N° 55 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL TERTIAIRES (C-1) ...................................................... 98

Groupement MCG / SAFI v


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

TABLEAU N° 56 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUATERNAIRE (C-1) ................................................. 99


TABLEAU N° 57 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUINQUENAIRES (C-1) ............................................ 100
TABLEAU N° 58 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL SECONDAIRE (C-3) .................................................. 101
TABLEAU N° 59 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL TERTIAIRE (C-3)...................................................... 101
TABLEAU N° 60 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUATERNAIRE (C-3) ............................................... 102
TABLEAU N° 61 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUINQUENAIRE (C-3) .............................................. 102
TABLEAU N° 62 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL SECONDAIRE (C-2) .................................................. 103
TABLEAU N° 63 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL TERTIAIRE (C-2)...................................................... 103
TABLEAU N° 64 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUATERNAIRE (C-2) ............................................... 104
TABLEAU N° 65 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUINQUENAIRE (C-2) .............................................. 105
TABLEAU N° 66 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL SECONDAIRE (C-4) .................................................. 105
TABLEAU N° 67 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL TERTIAIRE (C-4)...................................................... 105
TABLEAU N° 68 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUATERNAIRE (C-4) ............................................... 106
TABLEAU N° 69 : SUPERFICIE A IRRIGUER POUR CHAQUE CANAL QUINQUENAIRE (C-4) .............................................. 107
TABLEAU N° 70 : PENTES LONGITUDINALES DES CANAUX ........................................................................................... 110
TABLEAU N° 71 : PERTE DE CHARGE DANS LES OUVRAGES ......................................................................................... 111
TABLEAU N° 72 : CALAGE DU CANAL PRINCIPAL C-1 .................................................................................................. 113
TABLEAU N° 73 : CALAGE DU CANAL PRINCIPAL C-2 .................................................................................................. 120
TABLEAU N° 74 : CALAGE DU CANAL PRINCIPAL C-3 .................................................................................................. 124
TABLEAU N° 75 : CALAGE DU CANAL PRINCIPAL C-4 .................................................................................................. 129
TABLEAU N° 76 : RECAPITULATIF DE DIMENSIONNEMENT DU CANAL PRINCIPAL C -1 ............................................. 136
TABLEAU N° 77 : RECAPITULATIF DE DIMENSIONNEMENT DU CANAL PRINCIPAL C -2 ............................................. 141
TABLEAU N° 78 : RECAPITULATIF DE DIMENSIONNEMENT DU CANAL PRINCIPAL C -3 ............................................. 145
TABLEAU N° 79 : RECAPITULATIF DE DIMENSIONNEMENT DU CANAL PRINCIPAL C -4 ............................................. 148
TABLEAU N° 80 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX SECONDAIRES (C-1) ..................................... 151
TABLEAU N° 81 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX TERTIAIRES (C-1) ......................................... 152
TABLEAU N° 82 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUATERNAIRES (C-1) ................................... 154
TABLEAU N° 83 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUINQUENAIRES (C-1) ................................. 156
TABLEAU N° 84 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX SECONDAIRE (C-3) ....................................... 157
TABLEAU N° 85 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX TERTIAIRES (C-3) ......................................... 157
TABLEAU N° 86 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUATERNAIRES (C-3) ................................... 159
TABLEAU N° 87 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUINQUENAIRES (C-3) ................................. 159
TABLEAU N° 88 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX SECONDAIRES (C-2) ..................................... 160
TABLEAU N° 89 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX TERTIAIRES (C-2) ......................................... 160
TABLEAU N° 90 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUATERNAIRES (C-2) ................................... 162
TABLEAU N° 91 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUINQUENAIRES (C-2) ................................. 163
TABLEAU N° 92 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX SECONDAIRES (C-4) ..................................... 164
TABLEAU N° 93 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX TERTIAIRES (C-2) ......................................... 164
TABLEAU N° 94 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUATERNAIRES (C-4) ................................... 166
TABLEAU N° 95 : RECAPITULATIF DE DIMENSIONNEMENT DES CANAUX QUINQUENAIRE(C-4) .................................... 167
TABLEAU N° 96 : COORDONNEES DES OUVRAGES PARTITEURS ................................................................................... 169
TABLEAU N° 97 : DIMENSION DES PARTITEURS PRINCIPAUX ....................................................................................... 169
TABLEAU N° 98 : OUVRAGES MODULES SUR CANAL C-1 ............................................................................................. 172
TABLEAU N° 99 : OUVRAGES MODULES SUR CANAL C-2 ............................................................................................. 172
TABLEAU N° 100 : OUVRAGES MODULES SUR CANAL C-3 ........................................................................................... 172
TABLEAU N° 101 : OUVRAGES MODULES SUR CANAL C-4 ........................................................................................... 173
TABLEAU N° 102 : DIMENSIONNEMENT DES OUVRAGE MODULE SUR C-1.................................................................... 173
TABLEAU N° 103 : DIMENSIONNEMENT DES OUVRAGE MODULE SUR C-2.................................................................... 174
TABLEAU N° 104 : DIMENSIONNEMENT DES OUVRAGE MODULE SUR C-3.................................................................... 175
TABLEAU N° 105 : DIMENSIONNEMENT DES OUVRAGE MODULE SUR C-4.................................................................... 176
TABLEAU N° 106 : COORDONNEES D’OUVRAGE DE TRANSITION ................................................................................. 177
TABLEAU N° 107 : COORDONNEES DES OUVRAGES DE FRANCHISSEMENT ................................................................... 177
TABLEAU N° 108 : DIMENSION OUVRAGE DE FRANCHISSEMENT ................................................................................. 177
TABLEAU N° 109 : COORDONNEES DES VANNES DE CONTROLE ................................................................................... 179
TABLEAU N° 110 : DIMENSIONS DES VANNES DE CONTROLE ....................................................................................... 179
TABLEAU N° 111 : COORDONNEES DES OUVRAGE DE TRAVERSEES ............................................................................. 179
TABLEAU N° 112 : COORDONNEES DES OUVRAGES PROJETES SUR CANAUX D’ORDRE SECONDAIRES (SECTEUR GRANDE
DIGUE) ................................................................................................................................................................ 182

Groupement MCG / SAFI vi


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

TABLEAU N° 113 : COORDONNEES DES OUVRAGES PROJETES SUR CANAUX D’ORDRE SECONDAIRES (SECTEUR TELLEL)
............................................................................................................................................................................ 183
TABLEAU N° 114 : DIMENSIONNEMENT DES OUVRAGE MODULE (C-1) ........................................................................ 184
TABLEAU N° 115 : DIMENSIONNEMENT DES OUVRAGE MODULE (C-2) ........................................................................ 186
TABLEAU N° 116 : DIMENSIONNEMENT DES OUVRAGE MODULE (C-3) ........................................................................ 187
TABLEAU N° 117 : DIMENSIONNEMENT DES OUVRAGE MODULE (C-4) ........................................................................ 188
TABLEAU N° 118 : DRAIN ET SUPERFICIE DRAINEE ...................................................................................................... 191
TABLEAU N° 119 : PENTE LONGITUDINALE DES CANAUX ............................................................................................ 192
TABLEAU N° 120 : CALAGE DE DRAIN PRINCIPAL D-1 ................................................................................................. 194
TABLEAU N° 121 : CALAGE DE DRAIN PRINCIPAL D-2 ................................................................................................. 195
TABLEAU N° 122 : CALAGE DE DRAIN PRINCIPAL D-3 ................................................................................................. 196
TABLEAU N° 123 : CALAGE DE DRAIN PRINCIPAL D1-1 ............................................................................................... 198
TABLEAU N° 124 : CALAGE DE DRAIN PRINCIPAL D1-2 ............................................................................................... 199
TABLEAU N° 125 : CALAGE DE DRAIN PRINCIPAL D2-1 ............................................................................................... 200
TABLEAU N° 126 : CALAGE DE DRAIN PRINCIPAL D2-2 ............................................................................................... 201
TABLEAU N° 127 : CALAGE DE DRAIN PRINCIPAL D2-3 ............................................................................................... 201
TABLEAU N° 128 : CALAGE DE DRAIN PRINCIPAL D2-4 ............................................................................................... 202
TABLEAU N° 129 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN PRINCIPAL D-1 ................................................ 205
TABLEAU N° 130 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN PRINCIPAL D-2 ................................................ 206
TABLEAU N° 131 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN PRINCIPAL D-3 ................................................ 207
TABLEAU N° 132 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D1-1 .......................................... 209
TABLEAU N° 133 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D1-2 .......................................... 210
TABLEAU N° 134 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D2-1 .......................................... 211
TABLEAU N° 135 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D2-2 .......................................... 211
TABLEAU N° 136 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D2-3 .......................................... 212
TABLEAU N° 137 : RECAPITULATIF DE DIMENSIONNEMENT DU DRAIN SECONDAIRE D2-4 .......................................... 213
TABLEAU N° 138 : COORDONNEES DES OUVRAGES DE TRAVERSEES ........................................................................... 215
TABLEAU N° 139 : COORDONNEES DES OUVRAGES DE REJET ...................................................................................... 216
TABLEAU N° 140 : DIMENSIONNEMENT DES OUVRAGES DE TRAVERSES ...................................................................... 217
TABLEAU N° 141 : AVANT METRES ET DEVIS QUANTITATIF DU PERIMETRE TELLEL .................................................... 224
TABLEAU N° 142 : AVANT METRES ET DEVIS QUANTITATIF DU PERIMETRE GRANDE DIGUE ....................................... 229
TABLEAU N° 143 : LE COUT DE CETTE INTERVENTION EST VENTILE COMME SUIT : ..................................................... 235
TABLEAU N° 144 : COUTS DE LA COMPOSANTE RECHERCHE DEVELOPPEMENT........................................................... 236
TABLEAU N° 145 : EQUIPEMENTS D’APPUI AUX AGRICULTEURS.................................................................................. 238
TABLEAU N° 146 : CARACTERISTIQUES DES CANAUX D’ORDRE PRIMAIRE ET SECONDAIRE ......................................... 241
TABLEAU N° 147 : CARACTERISTIQUES DES COLLECTEURS DE DRAINAGE .................................................................. 242
TABLEAU N° 148 : FREQUENCES STANDARDS DES TRAVAUX D’ENTRETIEN PERIODIQUE ............................................. 245
TABLEAU N° 149 : OPERATIONS DE MAINTENANCE DES OUVRAGES CIVILS ET DES STRUCTURES METALLIQUES.......... 245

LISTE DES FIGURES


FIGURE 1. SCHEMA HYDRAULIQUE DU DELTA ET DISPONIBILITE DES RESSOURCES EN EAU .............................. 12
FIGURE 2. AXES HYDRAULIQUES DE LA ZONE DU PROJET....................................................................................... 16
FIGURE 3. STATION DE POMPAGE PERIMETRE GDT................................................................................................ 46
FIGURE 4. CANAL PRINCIPAL D’IRRIGATION .......................................................................................................... 50
FIGURE 5. OUVRAGE DE MODULE SUR CANAUX SECONDAIRES .............................................................................. 72
FIGURE 6. OUVRAGE DE MODULE SUR CANAL TERTIAIRE (A GAUCHE) ET QUATERNAIRE (A DROITE) ..................... 72
FIGURE 7. COLLECTEUR PRINCIPAL DE DRAINAGE ................................................................................................. 76
FIGURE 8. PISTES DEGRADEE DANS LE PERIMETRE GDT ........................................................................................ 78
FIGURE 9. BORNE LM1 ET RRS2 068 .................................................................................................................... 84
FIGURE 10. NIVEAU D'EAU: DIAMA .......................................................................................................................... 94
FIGURE 11. NIVEAU D'EAU: ROSSO .......................................................................................................................... 95
FIGURE 12. NIVEAU D'EAU AU LAMPSAR ................................................................................................................. 95
FIGURE 13. COUPE TYPE DU CANAL PRINCIPAL ...................................................................................................... 134
FIGURE 14. COUPE TYPE DU CANAL D’ORDRE SECONDAIRE ................................................................................... 134
FIGURE 15. COUPE TYPE D’UNE SECTION TRANSVERSALE DE DRAIN ...................................................................... 204
FIGURE 16. PROFIL EN TRAVERS TYPE.................................................................................................................... 222

Groupement MCG / SAFI vii


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

ACRONYMES

AEP : Alimentation en eau potable


AGR : Activités Génératrices de revenues
ANAMS : Agence nationale de la Météorologie du Sénégal
APS : Avant-Projet-Sommaire
ARD : Agence Régionale de Développement
BM : Banque Mondiale
CADL : Centre d’Appui au Développement Local
CC : Changement climatique
CFAHS : Coopération fédérative des Acteurs de l’horticulture du Sénégal
CLC : Comité Local de Concertation
CRSE : Comité Régional de Suivi Environnemental
DPN : Direction des Parcs Nationaux
DPV : Direction de la Protection des Végétaux
DEFCCS : Direction des Eaux et Forêts Chasse et Conservation des Sols
DEEC : Direction de l’Environnement et des Établissements Classés
DGPRE : Direction de la Gestion et de la Planification des Ressources en Eau
DNH : Direction Nationale de l’Hygiène
DRDR : Directions Régionales du Développement Rural
EDS : Enquête Démographie et Santé
EES : Expert Environnement et Social
GDT : Grande Digue Tellel
GES : Gaz à effet de serre
GIE : Groupement d’Intérêt Économique
GIRE : Gestion Intégrée des ressources en eau
GPF : Groupement de Promotion Féminine
ISRA : Institut Sénégalais de Recherche Agricole
IREF : Inspection Régionale des Eaux et Forêt
MAER : Ministère de l’Agriculture et de l’Équipement rural
MHA : Ministère de l’Hydraulique et de l’Assainissement
MTN : Maladies tropicales négligées
MSAS : Ministère de la Santé et de l’Action Sociale
OLAC : Office des Lac et Cours d’eau
OMS : Organisation Mondiale de la Santé
OMVS : Organisation pour la Mise en Valeur du Fleuve Sénégal
ONG : Organisation Non Gouvernementale
OP/GDT : Organisation des producteurs de la grande digue Tellel
PGIRE : Projet de gestion intégrée des ressources en eau et de développement
des usages multiples du bassin du fleuve Sénégal (PGIRE2)
PGES : Plan de Gestion Environnementale et Sociale
PDIDAS : Projet de Développement Inclusif et Durable de l’Agrobusiness au Sénégal
PDMAS : Programme de Développement des Marchés Agricoles au Sénégal
PME : Petites et moyennes entreprises
SAED : Société d’Aménagement et d’Exploitation des terres du Delta du fleuve
Sénégal et des Vallées du fleuve Sénégal et de la Falémé
SENELEC : Société Nationale d’Exploitation de l’Électricité
SDDR : Services départementaux Développement Rural
SDE : Société Des Eaux du Sénégal

Groupement MCG / SAFI viii


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

1-Présentation du projet (A4)

Groupement MCG / SAFI ix


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

1. INTRODUCTION

1.1 CONTEXTE DE L’ETUDE


Depuis plusieurs années le Sénégal déploie beaucoup d’efforts en vue de diversifier les secteurs
sur lesquels son économie doit se reposer. Ainsi, plusieurs actions ont été entreprises par la
Société Nationale d’Aménagement et d’Exploitation des Terres du Delta du Fleuve Sénégal et des
Vallées du Fleuve Sénégal et de la Falémé (SAED) pour promouvoir l’agriculture dans la vallée.

Eu égard à cette situation, l’agriculture continue à occuper une place privilégiée dans la stratégie
nationale de développement économique et sociale, comme l’illustrent les efforts importants qui
lui sont consacrés pour promouvoir son développement et assurer l’autosuffisance alimentaire du
pays.

Pour renverser ces tendances et créer les meilleures conditions de promotion d’un développement
durable, le Sénégal a continué d’entreprendre des actions permettant d’assurer une répartition
spatiale des ressources en eau de surface, compatible avec une valorisation de toutes les
potentialités du pays.

Le périmètre objet de la présente étude « Grande Digue-Tellel » est situé dans le Delta du fleuve
Sénégal, à une cinquantaine de kilomètres de la ville de Saint Louis. Ce périmètre, aménagé en
1976 par le financement de la Caisse Centrale de Coopération Economique (CCCE), devenue
Agence Française de Développement (AFD), était un projet d’irrigation fournissant de l’eau
d’irrigation à 2500 ha avec installation des stations de pompage, des canaux d’irrigation, des
canaux de drainage, des ouvrages de régulation et de contrôle…

La productivité dudit périmètre, 40 ans après sa construction, a baissé et ce suite au déclinement


de l’efficience de l’irrigation liée à la détérioration des équipements d’irrigation.

Un ordre de service a été notifié par la Société Nationale d’Aménagement et d’Exploitation des
Terres du Delta du Fleuve Sénégal et des Vallées du Fleuve Sénégal et de la Falémé (SAED) au
Groupement MCG-SAFI ; cet ordre de service prescrit au Consultant de commencer les
prestations objet dudit contrat.

Les Etudes d’Avant-Projet Détaillé (APD) pour la réhabilitation et l’extension du périmètre de


Grande Digue Tellel pour 3 600 ha et de Dossier d’Appel d’Offres (DAO) pour la réhabilitation
de la station de pompage de Grande Digue Tellel ainsi que celles du périmètre de
Tellel comportent les parties suivantes :

 Partie 1 : Etudes d’Avant-Projet Détaillé (APD) pour la réhabilitation (3000) et


l’extension (600) du périmètre de Grande Digue Tellel et de Dossier d’Appel d’Offres
(DAO) pour la réhabilitation de la station de pompage de Grande Digue Tellel.

Groupement MCG / SAFI 1


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 Partie 2 : Contrôle des travaux pour la réhabilitation (3000) et l’extension (600) du


périmètre de Grande Digue Tellel et de Dossier d’Appel d’Offres (DAO) pour la
réhabilitation de la station de pompage de Grande Digue Tellel.

Le présent rapport accompagné de ses annexes constitue le rapport APD du périmètre Grande
Digue-Tellel, il décrit les différentes actions réalisées dans le cadre de la réhabilitation du
périmètre objet de cette étude et comprend les chapitres Suivants :

 PRESENTATION GENERALE ET DONNEES PHYSIQUES


 DIAGNOSTIC DE MISE EN VALEUR
 DIAGNOSTIC DES INFRASTRUCTURES
 PROJET DE REHABILITATION
 SCHEMA D’AMENAGEMENT HYDRAULIQUE
 AVANT-METRES ET DEVIS QUANTITATIF DES TRAVAUX
 MESURES D’ACCOMPAGNEMENT
 SPECIFICATIONS TECHNIQUES DU PROJET DE REHABILITATION
 RECOMMANDATIONS COMMUNES POUR LA GESTION DU PERIMETRE
 CONDITIONS DE REALISATION DES TRAVAUX
 PROGRAMMATION DES TRAVAUX

1.2 OBJECTIFS DU PROJET


Ce projet contribuera à :

 La réalisation de l’objectif sénégalais d’autosuffisance alimentaire grâce à


l’accroissement de la production de riz et d’autres produits agricoles,

 Réduction de la pauvreté chez les paysans de la zone du projet,

 Amélioration des conditions de vie des paysans de la zone du projet,

 Amélioration des conditions environnementales grâce à l’arrêt de la désertification due


à l’expansion des surfaces couvertes par le paddy etc.

Les zones aménagées non exploitées augmentent en surface à cause d’une maintenance
insuffisante. Ce projet devrait être un bon exemple d’aménagement où la double culture est
pratiquée au lieu de l’actuelle campagne unique en saison sèche alors que la double culture est
normalement possible.

Quand ce projet sera terminé, 15.000 résidents de la Commune de Ross Bethio en tireront profit
immédiatement, il y aura des effets induits dans les domaines agricoles et industriels, tout en
contribuant simultanément à la réalisation de l’objectif final du projet : le développement rural et
l’éradication de la pauvreté ainsi que l’autosuffisance alimentaire des résidents.

Groupement MCG / SAFI 2


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

1.3 PRESENTATION DE LA ZONE D’ETUDE


La zone du projet, périmètre Grande Digue-Tellel, est située dans le delta du Fleuve Sénégal avec
des frontières administratives dans la Communauté Rurale de Ross-Béthio, Département de
Dagana, Région de Saint Louis. Au Nord, la limite est le marigot Kassack, à l'Est et au Sud la
zone est limitée par la route vers Saint-Louis et Ross-Béthio et à l'Ouest par le marigot Lampsar.

Le projet, réalisé en 1977 avec l'appui du Gouvernement Français, était un projet d'irrigation
fournissant de l'eau d'irrigation à 2,500 ha avec l’installation de station de pompage, des canaux
d'irrigation, des canaux de drainage et des ouvrages de distribution et de contrôle.

Mais dans la condition actuelle du périmètre irrigué, 40 ans après sa réalisation, la productivité a
sérieusement baissé à cause de la baisse de l'efficience de l'irrigation liée à la détérioration des
équipements d'irrigation. Depuis quelques années, la SAED a commencé la réhabilitation des
équipements d'irrigation mais sans remise à neuf parce que les installations sont trop vieilles et la
surface est trop grande.

Groupement MCG / SAFI 3


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

2. PRESENTATION GENERALE ET DONNEES PHYSIQUES

2.1 SITUATION GEOGRAPHIQUE ADMINISTRATIVE ET LOCALISATION DU SITE


Le périmètre irrigué de Grande Digue Tellel se situe dans le Delta du fleuve Sénégal, à une
cinquantaine de kilomètres de la ville de Saint-Louis. Le projet d’aménagement de la Grande
Digue Tellel est situé entre les communes de Diama et de Ross Béthio, situé dans
l’arrondissement de Ndiaye et dans le département de Dagana.

L’aménagement est constitué de deux parties. (i) La première appelée Tellel qui est la partie aval
de Lampsar à partir de la station de pompage. (ii) La deuxième appelée Grande digue est
subdivisée en plusieurs mailles hydrauliques et irriguée à partir de deux canaux principaux.

L’aménagement hydro-agricole est mis en valeur essentiellement par les populations des
communes de Ross Béthio et de Diama. Les exploitants privés proviennent de diverses zones.

La carte de localisation du périmètre Grande Digue Tellel est donnée ci-après

2.2 DONNES SOCIO-ECONOMIQUES DE LA REGION

Démographie

La population du département de Dagana est estimée à 268 346 habitants en 2017 contre 261 396
en 2016 selon les projections de l’ANSD. Les femmes représentent 48% de la population pour
52% d’hommes. Le département compte près de 27% de la population régionale pour une densité
moyenne de 48 habitants au km 2.

Tableau n° 1 : Population estimée en 2017 dans la zone du projet


2016 2017
Nom de localité
Homme Femme total Homme Femme total
Département
134 941 126 455 261 396 138 529 139 817 268 346
Dagana
Ross Béthio 6 637 5 895 12 533 6 814 6 052 12 866
Diama 18 882 18 786 37 667 19 384 19 285 38 668
Source : ANSD, Rapport projection de la population du Sénégal 2013-2063

Groupement MCG / SAFI 4


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

2-Plan de situation du périmètre GDT (A4)

Groupement MCG / SAFI 5


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Education

Dans le domaine de la DIPE, le TBPS est de 8,15% au niveau du département de Dagana (9,31%
pour les filles et 7,06% pour les garçons). Pour l’élémentaire, le TBS est de 79,35% (83,50% pour
les filles et 83,50% % pour les garçons). Pour l’enseignement moyen, le TBS est de 55,16%
(52,25% pour les filles et 51,37% pour les garçons). Au plan de l’enseignement secondaire, le
taux d’accès est de 27,04%, soit 25,63% pour les filles et 28,34% pour les garçons. Le taux
d’alphabétisation dans le département de Dagana est de l’ordre de 36%.

Santé et Nutrition

La carte sanitaire du département de Dagana est bâtie autour de 2 districts sanitaires (Dagana et
Richard-Toll) avec 01 centre hospitalier, 02 centres de santé, 32 postes de santé, 38 cases de santé
et 04 cabinets médicaux privés. Au plan de la morbidité globale, les premières causes de
consultation concernes principalement les affections suivantes : les maladies diarrhéiques (18%),
les IRA (15%), les Bilharzioses (5%), l’HTA (4%), les dermatoses (03%) et les IST (03%). Pour
les enfants de moins de 5 ans, les principales causes de morbidité sont : les maladies diarrhéiques
(30%), les IRA (26%) et la mal nutrition (5%). Les principales contraintes du secteur sont : déficit
d’infrastructures, déficit en personnel qualifié, etc. (source : District sanitaire de Dagana / Bilan
des activités du deuxième trimestre 2013).

Tableau n° 2 : Motifs de consultation et morbidité


Premier Deuxième Troisième Quatrième Cinquième
Commune de Nbre de cas Nbre de cas Nbre de cas Nbre de cas Nbre de cas
Diama Grippe Epigastralgie Hta Helminthiase Dermatose
712 703 601 377 306
Premier Deuxième Troisième Quatrième Cinquième
Commune Nbre de cas Nbre de cas Nbre de cas Nbre de cas Nbre de cas
Ross Bethio Helminthiase Rhumatisme Epigastralgie Carie dentaire Grippe
212 153 126 124 121
(Source : District sanitaire de Richard-Toll /Bilan des activités de l’année 2015)
Au niveau des communes du projet, pour l’année 2016, pour l’ensemble des postes de santé de la
commune de Diama (Mboundou, Niasséne, Diama, Savoigne et Débi), les premières causes de
consultations concernent les affections suivantes :

Tableau n° 3 : Causes de consultations


PS PS PS PS PS Débi Total
Affections Mboundoum Niassene Diama Savoigne Tiguette Commune Pourcentage
Diarrhées 630 399 385 569 229 2212 10,43
IRA basses 399 343 145 864 366 2117 9,98
Toux/Rhume 587 91 434 224 183 1519 7,16
Dermatoses 351 248 35 302 103 1039 4,90
Helminthiases 79 321 317 59 80 856 4,04

Groupement MCG / SAFI 6


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

PS PS PS PS PS Débi Total
Affections Mboundoum Niassene Diama Savoigne Tiguette Commune Pourcentage
HTA 199 214 209 76 22 720 3,4
(Source: District sanitaire de Richard-Toll / Bilan des activités de l’année 2016).
Concernant la commune de Ross-Béthio, pour la morbidité globale pour l’année 2016, les
premières causes de consultations au niveau du poste de santé de Ross-Béthio concernent
principalement les affections suivantes : les maladies diarrhéiques (5.90%), la dysenterie (4.61%),
les Toux/Rhume (8.94), l’HTA (2.67%), les dermatoses (6.50%) et les IST (1.36%). (Source :
District sanitaire de Richard-Toll / Bilan des activités de l’année 2016).

Pour les enfants de moins de 5 ans (0-59 mois), les principales causes de morbidité sont : les
maladies diarrhéiques, les IRA et la mal nutrition. Ainsi, la commune de Ross-Béthio a enregistré
pour l’année 2016, 155 cas de diarrhée, pour les Infections Respiratoires nous avons noté 1 cas de
pneumonie, 349 cas de toux/rhume, 15 cas de bronchiolite/asthme et 20 cas de toux de plus de 15
jours, et en fin 94 cas de malnutrition (contre 529 cas d’enfant en bon état nutritionnel). Pour la
commune de Diama, les données nutrition santé de l’enfant en 2016 ont permis de noter 1936 cas
de diarrhée, pour les IRA, il a été enregistré 1451 cas de pneumonie, 866 cas de toux/rhume, 77
cas de bronchiolite/asthme et 1 cas de toux de plus de 15 jours. Et la surveillance nutritionnelle en
2016 a permis de noter 168 cas de surpoids, 1490 cas de malnutrition (contre 9090 cas d’enfants
en bon état nutritionnel).

Eau potable et Assainissement

Au plan de l’accès à l’eau potable, 28% des localités du département de Dagana raccordées sont
alimentées par la SDE et 72% par les forages et stations de traitement. Le taux moyen de
couverture de la population à l’échelle départementale est de 88%, contre 87% pour la commune
de Ross-Béthio et 84% pour celle de Diama. Au plan de l’assainissement, seules les communes
de Richard-Toll et de Dagana sont dotées de réseau d’évacuation d’eaux pluviales. Le secteur est
confronté à plusieurs contraintes dont la croissance démographique très rapide en zone urbaine,
l’habitat non contrôlé dans certains quartiers, la faible étanchéité des fosses (risque de pollution
de la nappe phréatique), la vétusté des réseaux primaires de distribution d’eau potable,
l’insuffisance des branchements sociaux et individuels, la faiblesse des investissements surtout
dans le sous-secteur de l’assainissement, etc.

Pêche et Aquaculture

Dans le département, la pêche continentale est pratiquée dans la zone éco-géographique du Waalo
et la sous zone du Lac de Guiers, au niveau du fleuve Sénégal et de ses défluents qui, avec des
ressources humaines expérimentées, en constituent les atouts et potentialités. Entre 2014 et 2015,

Groupement MCG / SAFI 7


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

le volume de la pêche artisanale a baissé de 3 075,14 tonnes alors que la production aquacole a
augmenté de 175 702 tonnes.

Tableau n° 4 : Productions entre 2014 et 2015


Production 2014 2015 Écarts
Production de la pêche artisanale (tonnes) 4 361.2 1 286.06 -3 075,14
Production aquacole (en tonnes) 278 206 453 908 175 702
Nombre de plans d’aménagement des pêcheries mises 123 204 81
en œuvre
Source : Rapport départemental pour la revue 2016 / SD Pêche Dagana et ANA

Commerce

Le département de Dagana dispose de 741 unités commerciales, 8 marchés permanents et 6


marchés hebdomadaires. Le secteur du commerce connaît un certain nombre de contraintes parmi
lesquelles l’insuffisance et la vétusté des infrastructures marchandes et commerciales, la difficulté
de conservation et de stockage des productions agricoles, maraichères en particulier,
l’insuffisance de dispositifs (fonds, comptoirs commerciaux, etc.) d’appui à la commercialisation
des produits.

Tourisme

Le département de Dagana ne dispose pas d’établissements touristiques homologués ni classés


malgré que les réceptifs recensés sont, pour la plupart, agréés par le Ministère du Tourisme. On
dénombre en 2015, 12 réceptifs au total dans le Département dont 2 hôtels, 5 campements
touristiques et 5 auberges. Cependant, beaucoup de facteurs entravent la bonne marche du secteur
dans le département notamment le vieillissement des circuits touristiques, la faiblesse de la
qualité de service, la faible conservation/valorisation du patrimoine culturel et touristique.

2.3 CARACTERISTIQUES CLIMATIQUES


La zone du projet jouit d’un climat sahélien qui est marqué par l'alternance de deux saisons
annuelles : la saison des pluies ou hivernage et la saison sèche. Mais l'irrégularité et la faiblesse
des pluies jouent un rôle important aussi bien au niveau de l’hydrologie et du couvert végétal
qu’au niveau de la morphogenèse. D'autres éléments du climat notamment : les vents, les
températures élevées, l’humidité relative et l'évaporation caractérisent ce type de climat. Les
informations climatiques ci-après présentées sont issues des relevés de la station météorologique
de Dagana, Saint-Louis, Podor comme référence.

Les vents

Dans la zone du projet, les vents sont très forts surtout pendant la saison sèche. Leur action est
déterminante pour la morphogénèse car quand ils soufflent dans les zones salées à structure

Groupement MCG / SAFI 8


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

poudreuse, la déflation crée des microreliefs typiques. Pendant la saison sèche et surtout à partir
du mois de février, les alizés et le harmattan prédominent. Les alizés continentaux de direction
NE sont dominants dans la basse vallée du Sénégal, chauds et secs, ils sont souvent forts
(environ 40% d'entre eux ont une vitesse comprise entre 7 et 14 m/s). Par contre, les alizés
maritimes de direction NNW ont une vitesse moyenne de 7m/s. Ils soufflent généralement vers
Saint-Louis mais leur action se senti aussi dans la zone du projet. Le harmattan ou le vent d'Est
qui souffle pendant toute la saison sèche, constitue un danger permanent pour les cultures de
contre-saison vu son pouvoir desséchant. A partir du mois d’Aout, la mousson couvre tout le
pays. Ce sont les vents d'Ouest ou du Sud-Ouest qui soufflent avec une vitesse généralement
faible. Dans l'ensemble, ces vents réguliers ont une vitesse moyenne de plus de 3 m/s et
s'opposent à des vents locaux dont les plus connus dans la zone du périmètre de la Grande Digue
Tellel sont les tourbillons et les vents de sable.

Tableau n° 5 : Direction des vents dominants à Saint-Louis (15 ans)


Mois Janv Fev Mars Avril Mai Juin Juil Août Sept Oct Nov Dec
Direction NE NE N N NNW E NW W NW NNW ENE ENE
Vitesse 3,4 3,9 3,6 4,3 3,8 3,5 3,4 2,8 2,5 2,9 2,7 2,5
(Source ANACIM, )

Pluviométrie

Le climat de la zone est de type sahélien marqué par une pluviométrie peu abondante avec de
fortes variations annuelles et la distinction de deux saisons climatiques : la saison des pluies de
juillet à octobre avec les maxima de pluviométrie localisés aux mois d’août et de septembre d’une
part ; la saison sèche (de novembre à juin) d’autre part.

Tableau n° 6 : Pluviométrie à Saint-Louis (15 ans)


Mois Jan Fév Mar Avr Mai Jui Jui Aoû Sep Oct Nov Déc
Pluviométrie (mm) 1.68 2.16 0.24 0 0.24 8.16 45.24 95.88 94.32 26.76 0.48 0.84
Pluviométrie moyenne mensuelle à la station de Saint-Louis (Source ANACIM)
La répartition inter-mensuelle de la pluviométrie à la station de Saint Louis permet de constater
ce qui suit :

 Un début timide des précipitations dès le mois de juin,

 Un maximum de précipitation atteint au mois d’août avec en général plus de 95.9 mm


de pluie,

 L’achèvement de la pluviométrie au mois d’octobre.

Groupement MCG / SAFI 9


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Température

Les températures sont élevées durant toute l’année. Cependant, les températures moyennes
maximales (entre 31.1°C et 41.2°C) connaissent une évolution bimodale avec un maximum
principal en Mai et un minimum principal en Janvier. Le maximum secondaire est au mois de
Juin et le minimum secondaire en Février. Les maxima de température sont influencés par les flux
d’Est qui sont dominants au mois de Mai et Juin.

Les températures moyennes mensuelles sont situées entre 23.3°C et 32.5°C. Sous l’influence des
alizés, les températures sont relativement basses entre Décembre et Mai. Les minima peuvent
descendre jusqu’à 15.5°C en Janvier.

Tableau n° 7 : Température à la station de Saint-Louis (15 ans)


Mois Janv Fev Mars Avril Mai Juin Juillet Août Sept Oct Nov Dec
Max 31,8 32,0 31,9 30,8 30,3 30,0 31,2 31,9 32,8 34,3 33,5 31,8
Min 15,8 16,1 17,75 18,25 20,00 22,87 24,82 25,15 25,40 15,50 20,25 16,75
Moy 23,8 24,0 24,8 24,5 25,2 26,4 28,0 28,5 29,1 24,9 26,9 24,3
(Source ANACIM)

L’humidité relative

Dans la zone du projet, l'évolution de l'humidité atmosphérique est liée au régime des vents et à la
pluviosité. L’hygrométrie augmente au fur et à mesure que le FIT remonte, elle culmine au mois
d’août avec l'arrivée des pluies. Elle régresse avec l'arrêt des précipitations et baisse brutalement
avec l'apparition de l'alizé continental. Si l'on tient compte du régime des vents, on voit que la
zone bénéficie de la fraicheur apportée par l’alizé maritime très chargé en vapeur d’eau (entre 6 et
11 grammes de vapeur d’eau par m 3 d’air). Quant à la mousson, elle alimente les précipitations et
élève l’hygrométrie de l'air. Elle contient environ 15 à 20 grammes de vapeur d'eau par m 3 d'air.

Le harmattan, qui ne contient que 2 à 4 grammes de vapeur d'eau par m 3 d'air, réduit l'humidité
relative et accélère les phénomènes d’évapotranspiration.

Tableau n° 8 : Humidité relative à la station de Saint-Louis (15 ans)


Mois Janv Fev Mars Avril Mai Juin Juillet Août Sept Oct Nov Dec
Max 80 81 88,5 91,5 93,75 94,25 92,25 94,5 95,75 95,75 91,75 77
Min 30,5 26 40,25 46,25 55,5 64,75 66,75 69,5 66,75 54,5 39,25 29,25
Moy 55,25 53,5 64,375 68,875 74,625 79,5 79,5 82 81,25 75,125 65,5 53,125
(Source ANACIM)

L’insolation

Les valeurs inter-mensuelles de l’insolation de la station de Saint-Louis restent élevées toute


l’année. Les plus fortes valeurs sont enregistrées pendant la période qui s’étend de Mars (278,3h)

Groupement MCG / SAFI 10


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

à Mai (267,3h), durant laquelle on enregistre le maximum au mois d’Avril. Le minimum


intervient au mois de Décembre. La durée de l’insolation atteint la valeur de 2948 heures par an.

2.4 EFFETS DES CHANGEMENTS CLIMATIQUES


Le Sénégal subit les conséquences des changements climatiques. Les secteurs les plus touchés
sont ceux des ressources en eau, de l’agriculture et des zones côtières. Cette vulnérabilité se
manifeste, entre autres, par des pertes de l’espace agricole dues à la désertification (estimées à 5
pour cent du potentiel agricole).

La variabilité des précipitations durant la saison des pluies est actuellement à la hausse, en
particulier dans le nord du Sénégal, zone très susceptible à la désertification. Parmi les projections
futures figurent l’érosion, les inondations et la salinisation des sources d’eau douce, qui seront
causées et aggravées par la montée du niveau de la mer.

De façon globale, l’impact des changements climatiques, déjà perceptible sur les ouvrages et leur
fonctionnement, résultera de la hausse des niveaux de risque de non satisfaction de la demande en
eau. En effet, la réduction des précipitations et la hausse des températures pourraient affecter les
volumes d’eau à mobiliser pour les différents services dans le bassin. Une première conséquence
est la réduction de la vitesse d’écoulement dans les chenaux d’irrigation. Cette situation offre
également les conditions idéales pour la multiplication des vecteurs des maladies hydriques. De
même que les équilibres de l’écosystème seront affectés par la baisse des précipitations et de
débits au niveau des ouvrages qui pourraient se traduire par une réduction significative des zones
humides naturelles, de la biodiversité et des aires de conservation. La sécheresse chronique qui
résulte des changements climatiques est un facteur de désertification avec comme conséquence la
dégradation du couvert végétal et du sol (ruissellement ; érosion).

2.5 RESSOURCES EN EAUX

Eaux de surface

Le réseau hydrographique du delta est relativement dense et constitue la principale ressource en


eau potable des villes de Saint Louis par la réserve de Bango, et de Dakar par le lac de Guiers
alimenté par le canal de la Taouey de Richard Toll. Ce réseau est concentré dans le bas Delta qui
englobe la zone du projet.

La carte suivante présente le réseau hydrographique de la zone de la basse vallée du fleuve


Sénégal:

Groupement MCG / SAFI 11


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Figure 1. Schéma hydraulique du delta et disponibilité des ressources en eau

Ce réseau constitue un système complexe dont le fonctionnement est ci-dessous décrit avec l’état
actuel des différents cours d’eau.

2.5.1.1 Le Gorom amont

Long de 25 km entre Ronq et Boundoum Barrage, il assure l’irrigation de près de 5000 ha et


l’alimentation du Kassack et du Lampsar qui se poursuit jusqu’à la réserve en eau potable de
Saint-Louis (Réserve Bango).

Il est alimenté à partir du fleuve Sénégal par la prise de Ronq comprenant une station de pompage
et un ouvrage gravitaire. La station de pompage est équipée de 4 pompes et débite environ 8 m 3/s.
Elle fonctionne quand le niveau amont est inférieur ou égal à 1,80 m IGN.

L’ouvrage gravitaire est calé à la cote -1,12 m IGN. Il comprend 8 ouvertures dont quatre sont
obturées et quatre autres vannées (2,50 m de large et 3,60 m de haut) permettant de transiter un
débit maximum de 20m 3/s. Cet ouvrage a pour d’assurer de satisfaire un débit minimum de

Groupement MCG / SAFI 12


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

14m3/s préconisé par le schéma hydraulique sous l’hypothèse d’une gestion de Diama à la cote
2 ,50 m IGN.

Il présente un état très sinueux et de faible gabarit. Il a été curé en partie dans le cadre du
programme d’entretien de la Délégation de Dagana sur 5 km environ à partir de Ronq pour les
deux rives et sur 10 km pour la rive gauche. Le reste du cours d’eau est encore enherbé et
l’écoulement est alors perturbé.

Sur le Gorom aval a été construite la station de drainage de Gaéla qui assure l’exhaure des eaux
de drainage de la cuvette de Boundoum (plus de 3300 ha aménagés pour la riziculture de
submersion) et le rejet de ces eaux vers la dépression de Krankaye via la Branche B de
l’émissaire du delta.

2.5.1.2 Le Gorom aval

Compte tenu de ses deux fonctions de drainage et d’irrigation, le Gorom aval a été isolé du
Gorom amont par le barrage de Boundoum pour servi de collecteur des eaux de drainage du
périmètre de Boundoum. Deux stations d’exhaure assurent l’évacuation de ces eaux dans le
marigot. Quelques hectares irrigués villageois sont installés le long du Gorom aval qui s’étend sur
30 km jusqu’à l’ouvrage gravitaire G qui la relie au fleuve sénégal.

Sa capacité est estimée à 40 m 3/s. Selon l’étude du PDRG (Plan Directeur Rive Gauche du
Fleuve Sénégal, 1989) qui devrait être intégré dans le système des adducteurs du delta pour
sauvegarder l’environnement du parc national de Djoudj.

En conséquence, l’ouvrage G a été réhabilité par l’OMVS pour transiter un débit minimum de 36
mètres cube par seconde et est calé à la cote -0,632 m IGN. Son fonctionnement actuel
correspond à celui du Gorom aval qui peut couler dans les deux sens selon les niveaux amont et
aval de l’ouvrage. Il comprend quatre ouvertures dont trois sont obturées.

2.5.1.3 Le Lampsar

Il est alimenté par le Gorom amont avec lequel il forme ce qu’on appelle l’axe Gorom-Lampsar
qui constitue la principale voie d’eau du delta. L’axe s’étend sur une longueur de 95 km jusqu’à
Dakar Bango. Il est composé de trois biefs séparés par les ouvrages de Ross-Béthio et de Ndiol.
Le Lampsar a un tracé sinueux entre le barrage de Boundoum et le pont Demba. Il alimente le
Kassack aval et constitue à sa partie aval, avec le Djeuss et le Ngalam la réserve de Saint-Louis.
Environ une dizaine de milliers d’hectares sont aménagés le long du Lampsar.

Il présente une géométrie assez variable d’amont en aval : un très faible gabarit en amont et une
largeur importante vers l’aval avec souvent des profondeurs assez faibles et très enherbées.

Groupement MCG / SAFI 13


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Le marigot connait d’énormes difficultés pour satisfaire les besoins en eaux, surtout dans le bief
médian. Ceci amène souvent les responsables de la gestion à l’alimenter à partir de l’aval par
l’intermédiaire de l’ouvrage et ce depuis plus d’une vingtaine d’années.

Le Lampsar comprend plusieurs ouvrages d’amont à l’aval :

 Pont de Boundoum situé sur la piste du village de Boundoum : cet ouvrage a été
réhabilité en 2000 ;

 Pont de Ross-Béthio : il délimite le bief amont et sert de régulateur de niveau d’eau et


de passage sur piste. Il est constitué de quatre passes vannées de 2, 3 m x 2,1 m. Les
vannes ne sont plus fonctionnelles. L’ouvrage doit être ensablé faute de chasse
d’entretien ;

 Pont de Ndiol-Savoigne. Il délimite le bief médian et joue le même rôle que l’ouvrage
de Ross-Béthio. Il comprend trois passes de 2.5x2.5 m et est initialement calé à -1.45
m. Les vannes sont difficilement manœuvrables ;

 Pont de Mboubène sur la route de Diama. Il est en très bon état. L’écoulement se fait
en surface libre ;

 Pont de Ndiawdoun : désaxé il se trouve sur la route nationale. Il isole le Ngalam


pendant la saison sèche. Sa position actuelle est différente (construction d’un nouveau
pont). Il est constitué de sept (07) de passes de 1.5 m de large chacune. Lorsqu’il est
complètement ouvert son seuil d’écoulement se situe à la cote IGN de 0,16 m ;

 Le Barrage de Bango. C’est le dernier ouvrage en aval. Il isole la réserve d’eau de


Saint-Louis des eaux saumâtres du fleuve. C’est un ouvrage de vidange de la réserve
comprenant trois passes vannées de 2.15x1.20 m.

Principale source d’eau d’irrigation et d’alimentation de la réserve de Saint-Louis, l’hydraulicité


de Lampsar à l’instar du Gorom, doit être constamment améliorée pour contribuer à la
satisfaction des besoins en eau totaux de la zone du bas delta.

2.5.1.4 Le Kassack

Il prend source sur le Gorom amont qui l’alimente par l’ouvrage Djambar. Il est relié à l’aval au
Lampsar par l’ouvrage Demba. Le Kassack comprend deux biefs amont et aval reliés par un
ouvrage siphon sous la piste de Kassack nord. Il est donc alimenté dans les deux sens à l’amont
par le Gorom amont et à l’aval par le Lampsar. Le Kassack est quasiment enherbé sur toute sa
longueur et il faut régulièrement passer au faucardage, ce qui éviterait d’affaiblir sa débitance
néanmoins il alimente une bonne superficie de périmètre irrigué dont les casiers de Kassack sud
et Kassack nord.

Groupement MCG / SAFI 14


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Le Kassack présente deux ouvrages vannés aux deux confluents avec le Gorom amont et avec le
Lampsar ; Et un siphon sur la piste de Kassack nord. L’ouvrage Djambar permet d’isoler le
Kassack du Gorom ou de l’alimenter à partir de ce dernier. L’ouvrage Demba en aval joue le
même rôle. Le Kassack amont permet aussi d’alimenter le Diovol.

2.5.1.5 Le Diovol (Diawel)

Le Diovol était utilisé comme collecteur des eaux de drainage. Il était isolé du système des
adducteurs du delta jusqu’en 1989, date à laquelle il fut relié au Kassack amont par un ouvrage
busé. Il permet d’irriguer plus de 2000 ha de périmètre villageois ou privé c’est un axe
hydraulique qui doit être constamment entretenu pour éviter l’enherbement qui pourrait faire
diminuer sa capacité.

2.5.1.6 Le Djeuss

Le Djeuss jadis utilisé comme adducteur mais également comme drain. Avec les travaux du
MCA, le djeuss naturel a été transformé en drain et constitue le prolongement de l’émissaire delta
branche B jusqu’à la station d’exhaure de Mboubéne.

2.5.1.7 Le Ngalam

Le Ngalam constitue un point d’eau incontournable dans la zone puisqu’il alimente les trois
marigots et le canal de Gandiolais. Il se présente comme un déversoir des eaux de la réserve
douce de saint louis par l’intermédiaire de l’ouvrage de Ndiawdoume. Il est connecté aux trois
marigots qui constituent son prolongement vers la dépression de Ndiael.

2.5.1.8 Les trois marigots :

Ils sont formés de trois dépressions inter-dunaires : khant, nguine et le ndiasséou. Ils sont situés
dans une zone au relief un peu accentué et se présentent sous forme de trois mares allongées dans
une cuvette. Les trois marigots sont sensiblement parallèles et séparés par un système dunaire et
jouent une fonction écologique par le remplissage de la réserve du Ndiael pendant la période
d’hivernage.

Tableau n° 9 : Fonction des axes hydrauliques de la zone du projet


Axes Hydrauliques Fonction
Gorom Amont Irrigation-AEP
Gorom Aval Irrigation-AEP
Lampsar Irrigation-AEP
Kassack Irrigation
Djeuss Irrigation
Diovol (Diawel) Irrigation
Ngalam Irrigation
Trois marigots Écologique

Groupement MCG / SAFI 15


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Figure 2. Axes hydrauliques de la zone du projet

Eaux souterraines

Dans le bassin du fleuve Sénégal l'hydrogéologie est caractérisée par l'existence de plusieurs
nappes souterraines bien connues et qui correspondent à des formations géologiques différentes
qui se sont respectivement mises en place au primaire, à la fin du Secondaire, du Tertiaire et au
Quaternaire. Ci-dessous sont présentées les caractéristiques principales à travers en particulier
leur liaison avec le fleuve.

2.5.2.1 La nappe du Maastrichtien

On la trouve dans tout le bassin sénégalo-mauritanien. Sur la rive gauche, elle constitue, selon
certains auteurs, une zone d'alimentation de la nappe à partir du Fleuve.

2.5.2.2 La nappe de l'Eocène

La nappe de l’Éocène est présenté sur tout le bassin sédimentaire, excepté la zone d'affleurement
ou de sub-affleurement du Maastrichtien où elle a été érodée.

L'alimentation de cette nappe est tributaire des eaux de pluie, des eaux du fleuve (infiltration suite
aux crues) ou des eaux de la nappe maastrichtienne par drainage verticale.

Groupement MCG / SAFI 16


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

2.5.2.3 La nappe du Continental Terminal

La nappe du continental terminal est aussi appelée « nappe du Trarza » elle constitue la nappe la
plus importante et la plus régulière de tout le bassin sédimentaire côtier en Mauritanie.

Du coté Sénégal, elle est située dans le ferlo hors de la vallée proprement dite. L’alimentation de
cette nappe semble se faire uniquement sur ses bordures par les crues du fleuve. Un apport direct
des eaux de pluie par la surface n’est guère possible, à cause de la grande profondeur de la nappe
et des conditions climatiques très souvent défavorables.

2.5.2.4 La nappe alluviale superficielle

Les formations du quaternaire sont constituées d’une part d'argiles et de sables fins qui
correspondent aux dépôts Post Nouakchottien et d'autre part d'alluvions grossiers ou graveleux,
de sables argileux correspondant aux formations de la période de l'ogolien et du Quaternaire
ancien et moyen.

La nappe alluviale est présente dans toute la zone du projet (comme sur tout le lit majeur du
fleuve dans le Delta). Son aquifère principal est formé par des sables nouakchottiens situés sous
les alluvions elles-mêmes et sa profondeur piézométrique est inférieure à 2 mètres, pour une
épaisseur moyenne estimée à 25 mètres. En raison de l’hétérogénéité des alluvions et de leur
stratification lenticulaire plusieurs nappes plus ou moins interdépendantes existent.

Cette nappe est à proximité immédiate du lit mineur, sous la dépendance du niveau du fleuve,
mais celle-ci paraît limitée à quelques dizaines de mètres du lit mineur, probablement en raison
des discontinuités texturales des matériaux alluviaux (présence de deltas de ruptures en
particulier). Actuellement l’alimentation verticale de cette nappe par les eaux de pluie ou de
débordement est réduite dans la zone du projet et dans la basse vallée en général par la présence
des endiguements et la diminution du débit lié à la sécheresse, ce qui n’est pas sans effet sur le
peuplement naturel arboré (Acacia nilotica) ; par contre elle subit d’importantes fluctuations
piézométriques saisonnières sous l’influence de la riziculture submergée dont les apports sont
souvent compris entre 12000 et 15000m3/ha en une campagne, pendant une centaine de jours. En
dehors de cette période, elle est soumise à l’évaporation par remontées capillaires et le fait
qu’elle soit très chargée en sels solubles n’est pas sans influence sur la qualité des sols et le
rendement des cultures.

En plus, des études piézométriques ont montré que les nappes alluviales sont alternativement
alimentées et drainées par le fleuve.

Groupement MCG / SAFI 17


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

2.6 RESSOURCES EN SOLS


L’étude pédologique, pour l’aménagement hydro-agricole du périmètre irrigué Grand Digue de
Tellel, vise à évaluer les potentialités de mise en valeurs sous irrigation des sols, particulièrement
pour la riziculture (la vocation actuelle dominante dans le périmètre) et les polycultures
annuelles. L’ensemble de la zone prospectée couvrent une superficie brute totale de 4218 ha,
définie comme l’ancien périmètre irrigué avec quelques extensions programmées, dans le
département de Degana de la région de Saint-Louis au Nord-Ouest du Sénégal. L’étude
pédologique a les objectifs suivants :

 Caractérisation morpho-pédologique détaillé des différentes unités rencontrées,

 Evaluation des potentialités de mise en valeur des terres sous irrigation pour la
riziculture et les cultures annuelles,

 Elaboration des cartes des ressources en sols et d’aptitude culturales sous irrigation
pour chaque marais objets de l’étude.

La prospection pédologique est réalisée au cours des mois de Mai 2017, et elle s’est basée
principalement sur les observations du terrain et les analyses physico-chimique des sols. On a
effectué les observations pédologiques avec une densité d’un profil pédologique tous les 100 ha,
complété par des trous de tarières. Pour couvrir l’ensemble de la zone d’étude, on a creusé 37
profils complétés par 40 trous de tarière.

Les investigations de terrain complétés par les résultats d’analyses ont montrés que la couverture
pédologique des périmètres étudiés est dominée par des sols d’origine alluviales, vue leur position
géomorphologiques dans un domaine de cuvettes de décantation formés dans des levées
deltaïques caractéristiques du delta du fleuve Sénégal. Tout au long du quaternaire, Ce domaine
est fortement influencé par deux phénomènes contradictoire ; un phénomènes d’inondations et
d’alluvionnement pendant les saisons de crues et un phénomène d’engorgement par les eaux
salées causé par l’intrusion marine, ce qui a formé une nappe perchée très salée et peu profonde.
La couverture pédologique et étroitement liée aux différents phénomènes géomorphologiques
cités, on a donc identifié les différents phénomènes pédogénétiques qui ont

 Alluvionnement,

 Hydmorphie,

 Salinisation secondaire,

 Ensablement.

Groupement MCG / SAFI 18


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

On n’a pas constatés des indices d’évolution prononcés dans la grande partie des profils, ils sont
classés dans la grande classe des sols peu évolués non climatiques d’apport alluvial. Quelques
caractères secondaires peuvent faire la différence entre les unités pédologiques

 Epaisseur des couches alluviales,

 Nature des alluvions déposés,

 Hydromorphie de profondeur,

 Salinité de profondeur.

Sur la base des fiches descriptives des profils pédologiques, des résultats d’analyses et traitement
de l’ensemble des données cartographiques disponible, et en utilisant les caractères de
différentiation déjà mentionnés on a défini cinq types de sols dans le domaine d’étude :

 Sol Peu évolué d’apport Alluvial profond à texture équilibrés, ils sont dominant
dans le périmètre et ils sont caractérisé par une texture équilibré à grossière sur
l’ensemble du profil, ils sont parfois salé en profondeur.

 Sol Peu évolué d’apport Alluvial profond à texture argileuse, à caractère


hydromorphe, ils sont rencontrés dans les petites cuvettes de décantation. Ils sont
marqués par leur texture argileuse sur les premiers 80 cm, qui se reposent sur des
formations sableuse plus anciennes. Ils sont généralement affectés par une importante
salinisation secondaire principalement en profondeur.

 Sol Peu évolué d’apport Alluvial peu profond à texture argileuse, à caractère
hydromorphe, ils sont rencontrés en bordure des petites cuvettes de décantation, où
l’épaisseur des couches argileuses devient plus réduite <80 cm. Ils sont marqués par
leur texture argileuse des horizons de surface, qui se reposent sur des matériaux
limoneux des levés deltaïques ou directement sur les formations sableuse plus
anciennes. Ils sont généralement affectés par une importante salinisation secondaire
principalement en profondeur.

 Sol Peu évolué d’apport Alluvial profond à texture sableuse, ils sont rencontré dans
la partie Sud du périmètre, en proximité des cordons dunaires ou sur les terrasses
marines sableuses. ils sont caractérisés par une texture grossière sur l’ensemble du
profil, ils sont parfois salés en profondeur.

Compte tenus de l’objectif de la présente étude pour création d’un périmètre irrigué pour la
production du riz et des polycultures annuelles, on a classé les différentes unités pédologiques en
fonction des critères d’évaluation en classe d’aptitude culturales pour la rizicultures (R1 pour les
sols qui plaide pour la riziculture, R2 pour les sols convenant moyennement pour la riziculture er

Groupement MCG / SAFI 19


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

R3 pour les sols médiocres pour la riziculture) et pour les polycultures annuelles (Pc1, Pc2 et
Pc3).

Le tableau suivant présente la potentialité des sols pour la mise en valeurs résultant de la
prospection pédologique effectuée

Tableau n° 10 : Potentialité des sols


Zone Classe
Type de sol Caractéristiques
D’étude d’aptitude
- Profond

sols peu évolués profonds à - Bonne épaisseur de la couche argileuse


R1 Pc2 texture argileuse, à caractère
hydromorphe - Texture argileuse
- Faible perméabilité

- Profond
- Bonne épaisseur de la couche argileuse
sols peu évolués profonds à
R2 Pc3 texture argileuse, à caractère - Texture argileuse
hydromorphe, salé en profondeur
- Faible perméabilité
- Salé en profondeur

Grand - Peu Profond


Digue de
Tellel sols peu évolués peu profonds à - faible épaisseur de la couche argileuse
R2 Pc2
texture argileuse, à caractère
hydromorphe - Texture argileuse en surface
- Faible perméabilité

- Absence de la couche argileuse de surface


Sols peu évolués peu profonds à - Texture équilibrée en surface
Pc1 R2
texture équilibrée
- Perméabilité modéré

- Absence de la couche argileuse de surface

Sols peu évolués peu profonds à - Texture équilibrée en surface


Pc2 R3 texture équilibrée, salé en
profondeur - Perméabilité modéré
- Salé en profondeur

- Absence de la couche argileuse de surface


Sols peu évolués peu profonds à - Texture sableuse
Pc3 R3
texture grossière
- Forte perméabilité

Groupement MCG / SAFI 20


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Zone Classe
Type de sol Caractéristiques
D’étude d’aptitude
- Parfois Salé en profondeur

2.7 RAPPEL DES RESULTATS DE L’ETUDE ENVIRONNEMENTALE


Conformément à la nature des travaux et à la problématique environnementale et sociale dans le
Delta du fleuve du Sénégal le projet de réhabilitation et d’extension de périmètre irriguée de
GDT, présente des impacts spécifiques particulièrement au cours des travaux. En phase
d’exploitation, les impacts sont identiques et se cumulent à ceux observés dans l’ensemble de la
zone. Au détail, le projet de réhabilitation et d’extension est une initiative louable car en dehors
de l’objectif principal, qui est la mise en place d’un projet qui contribue à l’augmentation de la
production et à l’amélioration de la sécurité alimentaire, il permet par son volet d’assurer
l’approvisionnement en intrants et la commercialisation des productions et par conséquent de
lutter contre la pauvreté.

Le rapport, a décrit l’état initial de l’environnement sur les plans biophysique et humain et ce
après avoir passé en revue le cadre légal, réglementaire et institutionnel du Sénégal et de la zone
du projet en particulier et de la Banque Mondiale relatif au projet

On note qu’en phase de construction, plusieurs impacts négatifs majeurs sur le milieu
biophysique sont pressentis. Il y a d’abord la perte de la végétation et d’habitats pour la faune.
Les travaux de réhabilitation des réseaux d’irrigation, de drainage et des pistes surtout pendant la
phase de construction auront des impacts sociaux négatifs sur la santé des usagers et des riverains,
notamment les risques de contamination par les IST et le VIH/SIDA. Les pollutions
atmosphérique et sonore seront les principales causes des maladies respiratoires et des nuisances.
Les problèmes liés à la sécurité proviendront du transport des matériaux, de la circulation des
machineries pendant les travaux et des risques d’incendie. Pendant la phase d’exploitation. Mais
le projet en lui-même a un caractère économique et social qu’il importe d’encourager. L’impact
sur les emplois, l’économie locale des agglomérations riveraines et la coopération multilatérale
est majeure. Cependant, il est recommandé de prendre des mesures d’atténuation et de
compensation des impacts identifiés dans le rapport d’EIES. Dans ce registre, il faut noter que
plusieurs mesures d’amélioration du milieu humain (santé, sécurité routière, renforcement de
capacités… etc.) ont été proposées. Certaines mesures sont du ressort des entreprises qui seront
astreintes au respect du cahier des prescriptions environnementales. D’autres par contre seront
prises en charge par le projet. En tout état de cause, l’approche participative a été la clé de voûte
du processus d’EIES. Elle doit être privilégiée pendant la mise en œuvre du PGES. Pour atténuer
l’impact de la perte de végétation dans les emprises, il est suggéré d’effectuer la récupération
intégrale de la matière ligneuse qui sera abattue aux fins d’usage énergétique, de mettre en place

Groupement MCG / SAFI 21


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

des bosquets, des plantations pour lutter contre l’érosion des berges au droit des GMP et des
plantations de brise-vent. Certains impacts peuvent difficilement être atténués.

En tout état de cause, de nombreux impacts positifs d’importance majeure ont été identifiés dans
le rapport dont les propositions de bonification viendront renforcer les nombreux avantages
découlant de la réalisation du projet.

En définitif, les impacts négatifs qui pour la plupart, peuvent être atténués, n’engendrent pas de
risques majeurs en mesure de compromettre la réalisation du projet. Quant aux impacts positifs,
ils sont nombreux et présentent beaucoup d’opportunités de bonification. L’atténuation et la
bonification de l’ensemble de ces impacts contribueront à atteindre les objectifs du projet dans les
délais requis. Les mesures d’atténuation, de bonification, de compensation, de suivi et de
surveillance environnementale font l’objet du présent Plan de Gestion Environnementale et
Sociale (PGES).

Le PGES s’est intéressé enfin, aux actions complémentaires et à leur mise en œuvre, au prjet de
surveillance et de suivi environnemental, aux aspects de responsabilités et des dispositions
institutionnelles, à l’échéancier de mise en œuvre et de production de rapports.

Pendant la phase terrain, l’approche adoptée par le consultant, comme il a été sus-indiquée est
l’approche participative. En effet, les populations à travers les consultations publiques ont donné
leurs points de vue et suggestions sur le projet. Lors de la mise en œuvre, cette option doit être
privilégiée.

La mise en œuvre des mesures environnementales et sociales du PGES coûtera Cent Quatre Vingt
Dix Millions (190 000 000) francs CFA.

Pour plus de détails voir le rapport environnemental

Groupement MCG / SAFI 22


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

3. DIAGNOSTIC DE MISE EN VALEUR

3.1 METHODOLOGIE DE DIAGNOSTIC


La méthodologique adoptée a été conçue conformément aux termes de référence, elle se traduit
par une démarche participative comprenant les étapes suivantes :

 Prise de contact avec les différents acteurs,

 Compréhension commune des exigences des termes de référence,

 Elaboration d’outils et guides d’entretien, check listes,

 Réalisation d’un diagnostic participatif avec les usagers (certains agriculteurs, les
membres du comité de gestion, le comptable, les magasiniers, les pompistes, les
aiguadiers) qui ont listé et hiérarchisé les difficultés au cours des réunions,

 Visites de terrain en compagnie des membres de quelques usagers pour visualiser,


photographier les différents types de dégâts et défaillances et inventorier les
dysfonctionnements,

 Analyse des données issues des rencontres, réunions et visites de terrain,

 Détermination des travaux complémentaires à réaliser,

 Analyse de la documentation disponible en rapport avec le projet.

Le diagnostic de la mise en valeur agricole a été réalisé en collaboration avec les principaux
acteurs à savoir : les responsables de comité de gestion, les directions régionales techniques
(Agriculture, élevage, environnement…)

Le diagnostic s’est apporté sur :

 Le calendrier cultural,

 L’occupation du sol,

 La préparation des semences,

 Les opérations culturales et leurs modes d’exécution,

 L’emploi des intrants et leurs modes d’approvisionnement,

 Les rendements,

 Les possibilités d’améliorations,

 Les possibilités de l’activité d’élevage.

Groupement MCG / SAFI 23


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

3.2 NIVEAU DE MISE EN VALEUR AGRICOLE

Superficie exploitée

Le site du projet couvre une superficie totale de 4218 ha, dont 2783 ha, soit près de 65%, sont
actuellement irrigués par la station de pompage. Il est constitué des zones de Grande Digue (1262
ha) et de Tellel (1521 ha), et des extensions (781ha) composées des zones non aménagées situées
à la périphérie du périmètre et qui n’utilisent pas l’eau du canal pour l’irrigation, mais
s’alimentent à partir du Lampsar à l’aide de motopompes privées. La culture du riz constitue la
principale spéculation avec plus de 95% des superficies emblavées. Le maraichage, pratiqué à
faible échelle, concerne le gombo, les aubergines, la tomate, etc., essentiellement destiné à
l’autoconsommation.

Tableau n° 11 : Superficie du périmètre GDT


Grande digue
Superficie Tellel (ha) Total (ha)
(ha)
Superficie de la zone 1806 2412 4218
Superficie infrastructure 40 45 84
Superficie de terrain inculte 135 283 418
Superficie de dépression 38 114 152
Superficie actuellement irriguée 1262 1521 2783
Superficie d'extension 331 450 781
Superficie projet 1593 1971 3564

Systèmes de culture et occupation des sols

Les études récentes, menées par la SAED dans le Delta Central, montrent que l’agriculture demeure la
principale activité des exploitations agricoles privées du Delta (97%) à côté de l’élevage et du
commerce. A l’intérieur du périmètre de la GDT, la riziculture est la principale activité agricole, au
niveau de la périphérie on observe quelques parcelles maraichères. En fonction de la disponibilité de
l’eau ou de la topographie certaines parcelles sont abandonnées au risque de supporter des couts
d’exploitations assez élevés.

Le riz est la culture principale dans la zone d’étude, mais, à cause du stade de dégradation avancée
du réseau hydraulique et à cause des problèmes de drainage, les chiffres pour le rendement à l'hectare
sont clairement en dessous de la moyenne pour la Délégation de Dagana

Les surfaces irrigables existantes sont de 2783 ha dans le Périmètre GDT, et 781 ha dans les zones
alentours qui sont irriguées par les paysans eux-mêmes en utilisant des pompes privées et les terres
plus basses peuvent être irrigués gravitairement.

Groupement MCG / SAFI 24


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

En plus, l'arachide et la patate douce sont cultivées sur 50 ha; et le gombo, l’aubergine, et le
diakhatou sont cultivés sur 10 ha en saison sèche chaude, le gombo et 1'aubergine sont cultivés sur 1.5
ha en saison sèche froide

Modèle de culture

3.2.3.1 Variétés de Riz

La variété de riz la plus populaire est le Sahel 108 dans la Région du Fleuve Sénégal. Le Sahel
108 est également cultivé dans la majeure partie de la zone du projet. Le cycle en saison des
pluies est de 105 jours et en saison sèche ce cycle est de 120 jours. Le Sahel 201 est la deuxième
variété dans la zone du projet, parce que le cycle de cette variété est de 127 à 142 jours en saison
des pluies et en saison sèche chaude; les surfaces cultivées ne sont pas très importantes.

3.2.3.2 Le cycle cultural

La mise en valeur agricole du delta du fleuve Sénégal est confrontée dès le début par la salinité
importante des sols. La teneur en sels des sols du delta est naturelle en raison de la genèse du
delta qui est une suite de transgression et de régression de l’océan Atlantique.

A cause de cette salinité importante du sol et de la dégradation avancée du système de drainage et


les gens ne font qu’une seule compagne en saison sèche.

Tableau n° 12 : Cycle cultural actuel


Mois Janv Fev Mars Avril Mai Juin Juillet Août Sept Oct Nov Dec
Riz saison sèche
chaude
Préparation de la
terre
Semis
Maintenance
Fertilisation
Conduite
Récolte
Polyculture
Les principales dates relatives aux différentes étapes des cycles culturaux sont comme suit (+/-
indicatif) :

 Culture de riz

- Préparation des terres : 15-25 Fév,

- Semis : 25-30 Fév,

- Fertilisation : 20-30 Mars,

- Conduite culturale des parcelles de riz : 1 Avr-15 Juin,

Groupement MCG / SAFI 25


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

- Récolte : 15 juin - 5 juil.

 Cultures maraîchères et polyculture

Le cycle de ces cultures, pratiquées en dehors d’une prévision planifiée, suit le cycle de la
principale culture conduite durant cette période à savoir le riz et ce en raison de la disponibilité
des eaux d'irrigation soit :

- Saison sèche : début Jan - fin Mars, soit 3 mois,

- Saison des pluies : Début aout – fin Nouv soit 4 mois.

Techniques culturales

L'itinéraire technique suivi pour la conduite culturale des différentes cultures est variable selon
plusieurs facteurs :

 Importance de la culture pour le revenu et le système vivrier de l'exploitant,

 La disponibilité des intrants et des moyens de travail notamment la main d'œuvre et la


mécanisation,

 Les conditions climatiques particulièrement la précocité et l'importance des pluies.

3.2.4.1 Préparation du sol

Elle comprend l'ensemble des opérations culturales de préparation du lit de semence : les labours
et les ''recroisements'' (labour et pseudo-labours croisés), l'ameublissement par des façons
aratoires et de brise mottes, le nivelage des parcelles pour l'irrigation par submersion du riz,
l'épandage des fumures de fonds y compris la fertilisation organique, le billonnage pour le
repiquage des plants ou de tubercules de pomme de terre ou de plants/ bulbes d'oignon.

En somme ces opérations sont généralement exécutées manuellement ou par la traction animale
(attelage de bœufs ou d'asins). Les outils utilisés pour les labours et les façons aratoires
d'ameublissement ou de nivelage sont des charrues araires attelées ou des houes manuelles. La
profondeur des labours ne dépasse pas 20-25 cm, les façons aratoires sont de l'ordre de 10 cm; ces
profondeurs peuvent être considérées moyennement suffisantes mais elles méritent d'être plus
supérieures afin de briser la semelle de labour et faciliter l'infiltration et le ''stockage'' des eaux de
pluies et des crues précoces.

L'opération de planage et de nivelage des parcelles rizicoles demeure délicate notamment si les
labours n'ont pas été bien exécutés étant donné la compacité du sol et l'absence de pré irrigation
d'humectation.

Groupement MCG / SAFI 26


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

L'application des fumures de fonds qu’elles soient minérales ou organiques demeure manuelle.
Les doses appliquées sont plus ou moins conformes aux orientations de la vulgarisation.
Cependant, pour la riziculture les doses de fertilisation de fonds sont appliquées après le
repiquage de crainte de percolation en profondeur ; cette approche réduit l'efficacité des engrais
potassiques et phosphatés qui nécessitent une durée de 3 à 4 semaines pour devenir assimilables.

3.2.4.2 Les opérations de semis

Quelles soient pour le riz ou pour les cultures en extensif, ces opérations sont effectuées
manuellement. La main d'œuvre employée est satisfaisante mais mérite un perfectionnement pour
le respect de l'alignement et la bonne conduite de l’opération de semis

3.2.4.3 Les opérations d'entretien et de couverture

Ces opérations comprennent les désherbages, les démariages, les binages, l'épandage des engrais
de couverture et la réfection des diguettes inter parcellaires de séparation. Ces opérations sont
faites exclusivement manuellement ou moyennant un équipement rudimentaire : pulvérisateur à
dos, binette- sarcleuse, araire attelé pour les façons aratoires d'interlignes

3.2.4.4 Les opérations de récolte

Ces opérations comprennent : la moisson (fauche et gerbage), le séchage, le battage, le vannage,


le ramassage de paille et la mise en sac du paddy ;

Ces opérations sont réalisées manuellement où en faisant recours à la traction animale pour le
battage ou le transport.

3.2.4.5 Itinéraires techniques

Les cultures intensives : la riziculture

Les principaux itinéraires techniques de cette culture sont récapitulés dans le tableau suivant :

Tableau n° 13 : Fiche technique du riz


Operations techniques Description

Préparation de terre  Séparation (division) de la surface en parcelles.


 Labour de la surface sur une profondeur de 12-
15 cm.
 Planage des parcelles, 7 jours avant le semis.
Semis  Semis dans l'eau à la volée les grains pré germés
(Semis direct sur lit humide).
 Densité du semis 100-120 kg/ha .
 Lame d'eau dans la parcelle au moment du semis
en pré germé: 5-10 cm .
 Densité spécifiée assure à rune distribution

Groupement MCG / SAFI 27


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Operations techniques Description

régulière de semences.
 Grains pré germés semés à la volée en deux
applications: la première 60 pour cent, la
seconde 40 pour cent.
 Irrigation: Lame d'eau 5-10 cm.

Sarclage/  Désherbage manuel en fonction de l’état


désherbage d’enherbement de la parcelle ou en une
application de l’herbicide.
 2j/ha
Fertilisation  fumure de fonds : non appliquée au moment de
la préparation du sol, mais effectuée 3 à 4
semaines après repiquage 400 à 500 kg/ ha de
NPK (15-15-15)
 fertilisation de couverture : au 2eme mois 200
Entretien kg d'urée
 1,25 h / ha et par passage soit près 0,5j /ha pour
les 2 applications (Ep+ transport)
Protection  Herbicidage pour préparation du sol ou pour
phytosanitaire désherbage en entretien : très limité (lomdax,
dadiax et gossis) :
 2 hj/ha
Irrigation  Entretien 5j/ha
 Irrigation : 40 à 60j/ha / campagne

Récolte  Réalisée manuellement par coupe des pailles à


quelques cm du sol à l’aide de faucilles ou de
couteaux d’une part ou par prélèvement des
panicules d’autre part. Rendement moyen actuel
de 4.5 t/ha 'SH) à 6-7 t/ha (SS) dans la zone.
 Main d’œuvre : moisson 8,5j, + attachage 5, +
assemblage 10j, battage 10, vannage et
séparation 5, + ensachage 1.5j == soit 40 HJ/ha.

3.2.4.6 Rendements des cultures

Le riz est la principale spéculation cultivée dans le périmètre GDT. On remarque un inversement
des campagnes principales dans les cinq dernière années (2012-2017), la saison chèche devient la
compagne principale.

Les rendements et productions ont beaucoup évolué dans la zone. Pour l’hivernage, la moyenne
se trouve autour de 5 Tonnes à l’hectare. Tandis que pour la campagne de saison sèche chaude la
moyenne est autour de 7 tonnes pendant ces 5 dernières années.

Groupement MCG / SAFI 28


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Tableau n° 14 : Production Agricole dans le périmètre GDT


Saison humide Saison sèche chaude Total Annuel
Campagne
Sup Rdt Production Sup Rdt Production Sup Production
1996/97 924 3,82 3 530 924 3 530
1997/98 647 4,83 3 125 647 3 125
1998/99 558 4,8 2 678 558 2 678
1999/00 4,8 - 0 -
2001/02 1 542 5,66 8 728 1542 8 728
2002/03 741 5,76 4 268 741 4 268
2003/04 1 515 5,92 8 969 1515 8 969
2004/05 1 701 5,71 9 713 1701 9 713
2005/06 1 419 5,38 7 634 1419 7 634
2006/07 1 585 4,93 7 814 1585 7 814
2007/08 1 772 5,5 9 746 1772 9 746
2008/09 1 973 5,85 11 542 1973 11 542
2009/10 2 017 4,62 9 319 2017 9 319
2010/11 1 746 5,04 8 800 1746 8 800
2011/12 1 328 5,04 6 693 1 481 6,83 10 115 2809 16 808
2012/13 341 5,04 1 719 1 704 6,79 11 570 2045 13 289
2013/14 - 1 645 7,1 11 680 1645 11 680
2014/15 41 - 2 159 7,13 15 394 2200 15 394
2015/16 - 2 090 6,93 14 484 2090 14 484
Source : SAED_UPGDT
3.2.4.7 Intrants Agricoles

Les paysans de la zone du Projet préfèrent utiliser des semences certifiées HYV. Mais, leur
utilisation par l'agriculteur ordinaire est difficile du fait que le prix des semences certifiées est le
double de celui des semences localement produites.

Les paysans ont bien reconnu les avantages de l'utilisation des engrais, qui augmentent la
production. Le Gouvernement Sénégalais a subventionné 50 pour cent du prix de l'urée et des
herbicides depuis 2008 l'application des engrais et herbicides a augmenté ce qui a contribué à une
augmentation de la production d'environ 20 pour cent.

La plupart des agriculteurs de la zone du Projet ont acheté les intrants agricoles à Ross-Béthio et à
Saint Louis.

Le tableau suivant présente les principaux produits utilisés contre les ravageurs des parcelles
rizicoles :

Tableau n° 15 : Produits contre les ravageurs des parcelles rizicoles :


Classe Famille Nom Matière Dose à l’ha Toxicité Homologatio
commerciale active n
Fongicides Carbamates Furadan Carbofuran 10 kg / ha Aigue Usage retiré
Insecticides
Amines Propanil Propanil 6L Aigue Homologué
Herbicides Aryloxyacides Weedone 2-4-D 2L Pas très Homologué
toxique

Groupement MCG / SAFI 29


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Classe Famille Nom Matière Dose à l’ha Toxicité Homologatio


commerciale active n
Aminés Round up Glyphosate 1 L / ha Chronique Homologué
Sulfonylurées Londax Bensulfuron 80 g /ha Chronique Homologué
méthyl
Pyréthrinoïdes Karaté Lamdacyhalot 0,15 L ha Aigue Homologué
hrine
Insecticides
Organophospho Dursban Chlorpiryphos 0,5 L /ha Aigue Homologué
rés ethyl
Avicides Organophospho Quélétox Fenthion 3 L / ha Aigue Homologué
rés
Indadione Chlorophacino Bromodiolone 0,002 L / kg Chronique Homologué
ne / 10 m
Coumarines Racumen Coumatetralyl 100-200 g / Aigue Homologué
10 m
Raticides
Coumarines Coumafène Warfarine 100-200 g / Chronique Homologué
10m
Non classé Phosphure de Phosphure de 0,75 % Aigue Homologué
zinc zinc

(a) Fertilisants utilisés dans la zone


Deux types d'engrais sont utilisés (urée, DAP) :

 L'urée avec une teneur de 45 à 46 % d'azote

L’azote est l’élément fertilisant le plus important en riziculture. Il est absorbé en grande quantité
par la plante. Il agit sur la croissance, le développement, le rendement et la qualité du grain.

 Le phosphate diammoniacal (DAP) ou 18-46-0

Il est le plus utilisé dans la vallée et donne le phosphore. Il stimule l'enracinement, équilibre le
tallage, stimule la fécondation et raccourcit la maturation. Il stimule la reprise après un stress. Sa
carence peut limiter les rendements.

 Le Potassium

Il joue un rôle important dans la synthèse, la transformation et le transport des assimilas vers les
grains. Il est souvent présent dans les sols de la vallée. Son apport est négligé. La fertilisation se
fait par épandage manuel.

(b) Principaux ravageurs et maladies des cultures


maraichères
Les principales spéculations maraîchères cultivées dans la zone sont : l’oignon, la tomate, le
gombo, l’aubergine et le piment.

Elles permettent aux populations de diversifier et d’améliorer leur régime alimentaire grâce à
l’apport en vitamines et en sels minéraux mais aussi d’assurer une augmentation du revenu
monétaire des producteurs.

Groupement MCG / SAFI 30


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Tableau n° 16 : Principaux ravageurs et maladies des cultures maraichères


Spéculations Ravageurs Produits
Thrips tabaci Acephate (Orthène 50),
Diazinon (Basudine)
Diméthoate
L’oignon variétés résistantes
Heliothis armigera, Orthène 50
Spodoptera exigua Biobit
Spdoptera littoralis décis
Heliothis armigera Fenvalérate (Sumicidine),
Acéphate (Orthène)
Cyperméthrine (Cymbus)
La tomate Décis
Aculops lycopersici diméothoate
Alternaria solani Captafol (difolatan)
Manébe (manate 80)
Chenilles cyperméthrine deltaméthrine
Le gombo Les jassides diméthoate
Le Blanc le soufre ou les variétés tolérantes.
Cryptophlebia leucotreta des pyrethrinoïdes
Le piment
Spodoptera exigua diméthoate
Chenilles Diméthoate
L’aubergine
Cécidomie Détruire les fruits attaqués

3.3 BESOINS ACTUELS EN EAU


Le calcul des besoins en eau d'irrigation a été fait en suivant la démarche FAO adaptée aux
conditions climatiques et d'efficience des réseaux propres au périmètre GDT.

Le besoin en eau d’irrigation a été établi sur la base des données et hypothèses suivantes :

 Données climatiques (évapotranspiration et précipitations) ;

 Pluie efficace : La quantité d’eau pluviale retenue dans la zone racinaire est nommée
pluie efficace et doit être déduite des besoins totaux en eau d’irrigation. Dans le cas
présent, la valeur de la pluie efficace est fixée à 80 % des précipitations ;

 Infiltration : base 3 mm par 1jour (résultat réel dans la zone du projet) ;

 profondeur submersion : 50 mm (Résultat de terrain) ;

 Saturation du sol : 100 mm (Résultat de terrain).

Coefficient cultural Kc

Le coefficient cultural Kc pour la riziculture est présenté dans le tableau suivant :

Groupement MCG / SAFI 31


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Tableau n° 17 : Coefficient cultural pour le riz


Phase Phase de Phase mi- Phase arrière-
Spéculation
initiale Développement saison saison
Riz 0.6 0.9 1.1 0.7
Source : Document d’irrigation, FAO

L’efficience des réseaux

Du fait du mauvais état physique des réseaux et des déficiences dans l’entretien, les sections de
passage des canaux ne sont plus aux normes : ils ne sont plus capables de faire transiter les débits
prévus.

Selon nos constatations les pertes en eau ont lieu à tous les niveaux du réseau :

 Au niveau des canaux (nombreuses fuites, ruptures de cavaliers,...) ;

 Au niveau des arroseurs ;

 Au niveau des ouvrages de contrôle et distribution.

En conséquence, pour apporter la quantité d’eau requise, les pompes doivent fonctionner plus
longtemps, ce qui engendre des coûts supplémentaires (Energie plus élevées, entretien et
réparations plus important) d’une part et augmente la fréquence des pannes des pompes d’autre
part,

En conclusion, l’efficience de l’irrigation du périmètre est en général faible. Selon nos


observations l’efficience devrait se situer à un niveau de 60%.

Tour d’eau actuel

La viabilité d’un périmètre repose essentiellement sur la disponibilité en eau et sa distribution


règlementaire. Un tour d’eau existe au niveau du périmètre qui est de 7 à 15 jours. La distribution
de l’eau est essentiellement assurée par la station de pompage. A cette situation s’ajoutent les
coupures récurrentes du courant électrique qui fragilisent la distribution régulière de l’eau

Au niveau de périmètre GDT des délégués sont chargés d’assurer la distribution de l’eau mais
l’ensablement des canaux, le manque d’entretien permanent et l’absence des ouvrages de
distribution et de contrôle ne permettent pas une bonne irrigation et par conséquent une
distribution irrégulière de l’eau.

Main d’eau et durée d’irrigation

Dans un système de distribution au tour d'eau, le périmètre est loti en une succession d'ilots
appelés «quartiers hydrauliques» dont les parcelles partagent à tour de rôle une « main d'eau ».

Groupement MCG / SAFI 32


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

La main d'eau se définit comme le débit, maîtrisable par l'exploitant, que l'on alloue à l'îlot et qui
est destiné à « changer de main».

La main d'eau varie de 15 à 40 litres par seconde, ce débit n’est pas généralement contrôlé suite à
la disparition des ouvrages de distribution.

Le débit d'équipement actuel du périmètre GDT étant de 2.3 litres par seconde par hectare, la
superficie irrigable avec une main d'eau donnée est égale au rapport de cette main d'eau au débit
d’équipement. Ainsi, la main d'eau de 15 litres par seconde permet l'irrigation d'environ 6.5
hectares de même une main d'eau de 40 lires par seconde autorise l'irrigation de 17 hectares. Par
conséquent, la durée d’irrigation d’une parcelle de 0.5ha est égale à 1,5 heures. Toutefois cette
durée est plus moins non respectée étant donné les subdivisions subies par la parcelle.

Récapitulatif des besoins actuels en eau

Le tableau ci-après récapitule les résultats de ces calculs

Groupement MCG / SAFI 33


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES (DAO) POUR LES TRAVAUX DE
REHABILITATION ET L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE Rapport APD
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 18 : Récapitulatif des besoins en eau actuels

No Description (suivant standardisation FAO) Formule Unité Janv. Fév. Mars Avr. Mai. Jui Jui
(1)=Projet (Station
1 Evapotranspiration de Référence (ET0) mm 38.0 40.0 47.3 46.0 49.0 42.0 56.0 59.3 68.0 64.3 66.5 70.8 76.5 81.3 86.3 75.1 72.0 66.8 61.6
S.LOUIS)
2 (2)=Superficie périmètre ha
3 Pourc. de la superficie totale sous irrigation (3)=Projet % 100 100 100 100 100 100 100 100 100 100 100 100 - -
4 Coefficient cultural (Kc) (4)=Projet, Pub. FAO 29 - - - - - - 0.8 0.8 0.9 0.9 1.1 1.1 1.1 1.1 1.1 0.9 0.9 0.8 - -
5 Besoin en Eau (ETcult. = Kc x ET0) (5)=(1)x(4) mm - - - - - 34 45 53 61 71 73 78 84 89 78 68 58 - -
6 Pré-irrigation (S) et mise en boue (6)=Projet mm - - - - - 30 30 30 0 0 0 0 0 0 0 0 0 - -
7 Infiltration (In) (7)=Projet mm - - - - - 20 20 20 20 20 20 20 20 20 20 20 20 - -
8 Besoin en Eau total (ETcult.+ S + In) (8)=(5)+(6)+(7) mm - - - - - 84 95 103 81 91 93 98 104 109 98 88 78 - -
(9)=Projet (Station
9 Pluie décadaire moyenne (P) mm - - - - - 0.6 0.24 0 0 0 0 0 0 0 0.24 0.96 1.32 - -
S.LOUIS)
10 Coefficient d'efficience de pluie (er) (10)=Projet, Pub. FAO 29 - - - - - - 0.8 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 - -
11 Pluie efficace (Pe=P x er) (11)=(9)x(10) mm - - - - - 0.5 0 0 0 0 0 0 0 0 0 1 1 - -
Besoin Net en Eau d'Irrigation (Inet=ETcult.+ S + In -
12 (12)=(8)-(11) mm - - - - - 83.1 95 103 81 91 93 98 104 109 97 87 77 - -
Pe )
13 Efficience du Système d'Irrigation (ep) (13)=Projet, ILRI Pub. 19 - - - - - - 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 - -
14 Besoin Brut en Eau d'Irrigation (Ibrut = Inet / ep) (14)=(12)/(13) mm - - - - - 138 158 172 135 151 155 163 174 182 162 145 128 - -
Besoin Brut en Eau d'Irrigation en mm/jour (Ibrut /
15 (15)=(14)/30 mm/j - - - - - 13.9 15.8 17.2 13.5 15.1 15.5 16.3 17.4 18.2 16.2 14.5 12.8 - -
10)
16 Débit spécifique continu pour 24h/24h (16)=(15)/8,64 l/s/ha - - - - - 1.6 1.8 2.0 1.6 1.7 1.8 1.9 2.0 2.1 1.9 1.7 1.5 - -
17 Durée de fonctionnement de la station (1 7) (h) - - 16.0 18.0 20.0 16.0 18.0 18.0 19.0 20.0 21.0 19.0 17.0 15.0
18 Débit spécifique (18)=(16/17) l/s/ha - - 2.4 2.4 2.4 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 - -

L’observation du tableau précédent fait ressortir que :

 La durée journalière de pompage varie au cours du cycle cultural selon le besoin en eau (de 16 à 20 heures),

 Le besoin spécifique actuel est de l’ordre de 2.3 l/s/ha (avec une efficience du réseau de 60 ℅).

Groupement MCG / SAFI 34


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Main d’œuvre Agricole

Il y a 5,048 travailleurs agricoles, 4,022 personnes sont à temps plein, et 1,026 sont à temps
partiel dans 7 villages. Le ratio de femmes travailleuses est plus faible 33.5 pour cent, et elles
font des travaux simples, tels que la récolte. La main d’œuvre moyenne par famille est de 2.17
personnes. (Se référer au Tableau 2.27).

Tableau n° 19 : Main d’œuvre Agricole


Village Total Temps Plein Occasionnellement
Total Mâle Femelle Total Mâle Femelle Total Mâle Femelle
Zone du Projet 5,048 3,355 1,693 4,022 2,863 1,159 1,026 492 534
Ross Béthio 2,757 1,914 843 2,418 1,787 631 339 127 212
Ndiomo 1'171 880 291 880 731 149 291 149 142
Soulou! 164 59 105 156 52 104 8 7 1
Ouroulbé begaye 102 63 39 58 47 11 44 16 28
Fondé boki 191 80 111 152 62 90 39 18 21
Raynabé 1 & 2 538 289 249 293 134 159 245 !55 90
Wouro Séna 125 70 55 65 50 15 60 20 40

Bétail

La principale activité économique dans la zone est l'élevage; Le bétail consiste en des vaches, des
moutons, et des chèvres dans la brousse. D'autres groupes ethniques également élèvent des moutons
et des chèvres. Les chevaux et les ânes sont d'importants moyens de transport dans la zone du
Projet.

Il y a 41,196 têtes de vaches, de moutons, de chèvres, et d’ânes dans la zone du Projet. Les prix de
vente à la ferme pour: les vaches varient de FCFA 160,000 à 228,000; les moutons varient de FCFA
40,000 à 70,000; les chèvres varient de FCFA 17,500 à 42,500; les ânes varient de FCFA 31,000 à
60,000; et le poulet, varient de FCFA 1,000 à 2,500.

Etant donné que la paille de riz et le chaume sont utilisés pour nourrir le bétail, tel que les vaches,
les moutons et les chèvres, le nombre de cheptel augmente en fonction de l’augmentation des
surfaces rizicoles.

Machines Agricoles et Utilisation

Il y a 11 tracteurs dans les villages en relation avec le projet. Les zones autour du village de Ross
Béthio sont une sorte de centre agricole dans la Commune et il y a des unités de décorticage du riz
et des entreprises de location de machines agricoles et des propriétaires privés dans la zone autour

Groupement MCG / SAFI 35


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

du village de Ross Béthio. Ces entreprises/propriétaires privés et propriétaires de machines de


décorticage faisaient des affaires non seulement pour la zone du Projet Grande Digue-Tellel, mais
aussi pour les zones des alentours.

L'épandage des pesticides est fait avec des pulvérisateurs manuels sur le dos et d’autres travaux
agricoles sont faits avec des houses, des pelles, des faucilles et d'autres petits outils de travail
agricole.

Il n'y avait pas d’usines de décorticage fonctionnant sous l'autorité des Organisations Paysannes. Il
y a 38 batteuses et 403 pulvérisateurs sur le dos dans les villages en relation avec le projet.

Tableau n° 20 : Machine Agricoles, Outils, et Equipements pour le Traitement des Produits


Agricoles
Equipements pour
Machines Agricoles Outils Agricoles
Traitement Prod.
Village Agricole
Tracteur Batteuse Pulvé .sur Houe Pelle Sarcloir Faucille Usine de Décorti-
Dos Décorti gueuse
Zone du Projet 11 38 403 234 1,041 1,141 2,133 - 7
Ross Béthio 4 31 232 76 510 816 826 - 5
Nd iomo 7 7 127 118 246 110 477 - 1
Soulou! 0 0 11 0 46 2 165 - 1
Ourou1bé 0 0 8 3 16 6 4 - 0
begaye
Fondé boki 0 0 1 0 6 6 15 - 0
Raynabé 1 & 2 0 0 21 32 209 191 606 - 0
Wouro Séna 0 0 3 5 8 10 40 - 0

3.4 L’ELEVAGE
D’après le dernier recensement de 2013, le cheptel du département est estimé à 529 445 têtes dans le
département de Dagana. Il est composé de bovins, ovins, caprins, équins, asins, camelins et
volailles. La filière lait a connu une bonne performance avec une augmentation 1,203 millions de
litres en 2015. Cependant, la quantité de viande et d’abats a connu une baisse considérable de 233,9
tonnes. (Source : Rapport départemental pour la revue 2016 / SD Elevage Dagana).

Dans la zone d’influence élargie du projet, on dénombre en 2017, 12 420 bovins, 26 000 ovins-
caprins, 200 asins et 160 000 volailles. Au plan des infrastructures, on compte 04 parcs à
vaccination (03 à Diama et 01 à Ross Béthio), 01 magasin à bétail à Ross Béthio et 01 mini laiterie à
Ross Béthio, 03 tanneries à Diama.

Tableau n° 21 : Estimation cheptel (2017)


Localités Bovins Petits ruminants Équins Asins Volaille rurale
Diama 10 000 20 000 100 80 100 000
Groupement MCG / SAFI 36
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Localités Bovins Petits ruminants Équins Asins Volaille rurale


Ross Béthio 2 420 6 000 100 125 60 000
Total 12 420 26 000 200 205 160 000
Source : SD Élevage – Dagana
Les aléas climatiques, l’accès à l’eau douce pour le bétail et les maladies parasitaires dues
essentiellement à la prolifération des plantes aquatiques sont les principales contraintes qui freinent
le développement du secteur de l’élevage au niveau du département.

Contribution de l’élevage dans la vie socioéconomique

Au plan individuel, l’élevage joue un rôle extrêmement important. Ainsi pour l’éleveur voire même
l’agriculteur, l’animal est un placement qui sécurise l’argent et qui rapporte des plus-values
puisqu’il produit : viande et lait (bovins, ovins, caprins, camelins), travail (asins, équins, camelins,
bovins) fumier et progénitures (tous les animaux). L’élevage représente la principale source de
revenu des pasteurs. Il leur permet de payer les impôts, les habits, les aliments et de couvrir d’autres
dépenses telles que les mariages, le pèlerinage, etc.

En plus du rôle purement économique, l’élevage joue un important rôle socioculturel qui apparaît à
travers les multiples manifestations culturelles et les liens sociaux entre personnes : prestiges,
sacrifices lors des cérémonies religieuses (fête du mouton), courses hippiques, fantasias et autres
jeux de paris (pour ce qui concerne les chevaux et les dromadaires), les trocs, etc

Mode de conduite

Le mode de conduite dominant dans la zone des périmètres irrigués est du type extensif : les
animaux s'alimentent essentiellement à partir des pâturages qui couvrent près de 100% des besoins
alimentaires.

L'exploitation des parcours est assurée soit directement par le propriétaire ou par des bouviers ou
bergers engagés par la population et rémunérés en nature ou en espèce par saison.

Ce mode d'alimentation reste précaire et aléatoire dépendant de la végétation spontanée des parcours
dont l'intensité et la richesse est variable en fonction de la pluviométrie et l'état des sols.

La complémentation de la ration est de plus en plus adoptée par les paysans (éleveurs ou
agriculteurs) notamment pour le gros bétail et les bêtes de trait. Issue de foin ou de paille achetés,
elle pourrait comprendre des résidus de cultures ou des usines de riz ainsi que des pierres à lécher
pour les sels minéraux.

Groupement MCG / SAFI 37


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

3.5 ORIENTATIONS FUTURES DU PROJET


L'analyse de la situation de mise en valeur agricole actuelle a permis de dégager les insuffisances
suivantes pour lesquelles des corrections doivent être portées :

 Itinéraires techniques :

- La préparation du lit de semence demeure imparfaite étant donné la faiblesse relative de la


traction : labour à l'araire attelé (profondeur insuffisante du labour) et l'absence de fumure
organique et l’application de fumure de fond à temps ;

- Le choix de bonne semence demeure aléatoire en fonction de la disponibilité des semences


sélectionnées à temps et en quantité suffisantes

- la parcellisation et le morcellement de l’exploitation après le découpage des parcelles


initiales engendre des difficultés de bonne irrigation et de bon drainage ;

- L'introduction de la mécanisation est à notre sens incontournable pour mieux réussir les
cultures et obtenir de bons rendements ; une mécanisation appropriée serait un vecteur de
techniques nouvelles et d'amélioration de valorisation de ressources tout en respectant les
aspects environnementaux.

 Irrigation : des difficultés réelles persistent pour une distribution correcte des eaux
d’irrigation : respect du tour d'eau et des doses d'irrigation.

 Assolement : l'absence d’une rotation culturale adéquate et la succession indéfinie de riz


sur riz, ajoutées à une fertilisation loin d'être appropriée sont à l'origine d'un
appauvrissement du sol et la stagnation sinon la régression de la productivité ;

 Intégration de l’élevage : l'exclusion de cette activité de la forme de mise en valeur et son


non-intégration dans le système cultural pratiqué résultant d'une perception ancienne du
développement agricole, génère une distorsion de réflexion contradictoire chez le paysan
lui forçant de déclasser cette activité et de la considérer secondaire en dépit de sa grande
importance dans la résolution de ses problèmes financiers et familiaux.

 Renforcement de capacité : le niveau technique des exploitants dont la plupart sont de la


2éme génération (des héritiers) mérite une mise à niveau conséquente quant à l'application
des nouveautés techniques et l'implication des aspects économiques dans le mode de
gestion, il ne suffit plus de produire mais il faudrait produire et bien vendre avec une
durabilité rassurante.

Groupement MCG / SAFI 38


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

4. DIAGNOSTIC DES INFRASTRUCTURES

4.1 HISTORIQUE DE L’AMENAGEMENT


L’histoire de l’aménagement de la GDT se résume comme suit :

 En 1959, création d'une cuvette de 12 ha avec irrigation gravitaire par l’OAD, à l'époque
la mise en valeur est faite par la coopérative 1 de Ross-Béthio regroupant les villages de
Ross-Béthio, Ndiorno et Tellel,

 En 1960, création de la 2éme coopérative regroupant les sections actuelles de Ross-Béthio


3 et 4, et augmentation de la superficie qui passe à 700 ha,

 En 1965, avènement de la SAED et la surface est passée de 700 à 1000 ha avec


submersion contrôlée,

 En 1976, sous financement CCCE la superficie aménagée est portée à 1 501, 54 ha en


aménagement tertiaire de 2éme génération qui comprend essentiellement la partie Tellel.
575,52 ha d'extension ont été rattachés au réseau initial amenant la surface totale
aménagée à 2077,06 ha avec une seule station de pompage située sur l’ancien ouvrage
gravitaire de grande digue,

 Equipement de 4 pompes "GUINARD" avec un débit de 1400 litres par seconde pour
chacune d’elles,

 une vanne avio située en aval régule le niveau de l'eau dans les canaux primaires dont 2
desservent la partie grande digue et 2 la partie Tellel,

 En 1983, date de l'électrification, la station était équipée de 2 générateurs de 150 KVA


chacun,

 le drainage est jusqu'ici gravitaire avec une connexion des drains principaux sur la
dépression du Ndiaél (reprise 2009).

Groupement MCG / SAFI 39


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

3-Plan d’aménagement de périmètre GDT (A4)

Groupement MCG / SAFI 40


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

4.2 METHODOLOGIE DE DIAGNOSTIC


La méthodologie adoptée pour le diagnostic de l’état actuel des infrastructures consiste à examiner
et analyser l’état des stations de pompages, des réseaux et des ouvrages des systèmes d’irrigation, de
drainage et des pistes.

Le diagnostic du terrain a intéressé toutes les composantes de l’aménagement et l’examen de chaque


composante a intéressé son état physique ainsi que les paramètres et les conditions de son
exploitation et de son fonctionnement.

Le traitement des données collectées lors de la mission de diagnostic a permis de relever l’état des
infrastructures et d’en déduire les anomalies qui entravent leur bon fonctionnement.

Ce diagnostic a été réalisé sur le terrain et en concertation avec les exploitants (agriculteurs, comité
de gestion), il a permis d’identifier les problèmes particuliers et spécifiques de fonctionnement des
réseaux ainsi que les solutions attendues par les exploitants afin d’améliorer le système.

Il a été traité d’une manière participative et a intéressé toutes les infrastructures de l’amont vers
l’aval (de la station de pompage jusqu’à la distribution).

Cette démarche a permis de détailler les points suivants :

 Etat physique des différentes composantes,

 Modes de fonctionnement actuel des infrastructures,

 Historique et causes des problèmes de fonctionnement et des interventions engagées,

 Problèmes au niveau des réseaux et des différents ouvrages,

 Et les différents problèmes sociaux, de mise en valeur et de gestion.

Le diagnostic détaillé des infrastructures hydrauliques a permis d’évaluer l’état actuel des ouvrages
(état physique, fonctionnement, défaillances observées…).

4.2.1.1 Les moyens humains du diagnostic

L’équipe chargée du diagnostic est composée principalement de :

 1 ingénieur génie rural,

 1 ingénieur génie civil,

 1 ingénieur électromécanicien,

 4 techniciens génie civil,


Groupement MCG / SAFI 41
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 1 technicien secrétaire pour saisir les fiches.

 2 brigades topographiques.

4.2.1.2 Les moyens matériels

Le matériel utilisé pour faire le diagnostic est composé de :

 4 GPS,

 4 Mètres pliables,

 Fiches de diagnostic,

 Plans du périmètre,

 Matériels roulants (2 voitures,…)

4.2.1.3 Déroulement du diagnostic

Le diagnostic des différentes composantes a été effectué de la manière suivante :

(a) Station de pompage


L’expert électromécanicien a relevé les états des différentes composantes :

 Electrique ;

 Electromécanique ;

 Hydromécanique.

Il a analysé l’état actuel des différentes composantes et l’historique de fonctionnement. L’expert


génie civil a relevé les dimensions et l’état du génie civil des locaux des stations.

Des fiches de diagnostic ont été établies pour orienter le diagnostic des stations et dégager les
imperfections.

Il s'agit de diagnostiquer l’état du génie civil et des équipements hydromécaniques et


électromécaniques, de répertorier les défaillances, d’identifier les problèmes de fonctionnement et
de définir les améliorations nécessaires pour garantir le bon fonctionnement du système.

(b) Réseau d’irrigation


Le réseau d’irrigation est parcouru de l’amont vers l’aval tout en procédant à :

 Vérifier sur le terrain, le tracé, les caractéristiques dimensionnelles et l’état par bief,

Groupement MCG / SAFI 42


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 Vérifier l'état de génie civil des ouvrages (génie civil à réhabiliter, à refaire, buse à
déboucher ou à remplacer …),

 Vérifier l'état de terrassement (cavalier dégradé, remblais à dégager, canal ensablé …),

 Nettoyer et démolir (Arbre et arbuste, …),

 Vérifier l'état des équipements des ouvrages (Masque inexistant ou à réhabiliter ou à


remplacer, vannettes inexistantes ou à remplacer …),

 Examiner le mode de fonctionnement des réseaux et les problèmes enregistrés


(déroulement du tour d’eau, contrôle des débits et des niveaux d’eau,…).

 Les différents biefs ou ouvrages sont classés selon leurs nomenclatures et référenciés par
leurs coordonnées GPS, ce qui permet de les localiser et les implanter sur les plans.

(c) Réseau de drainage


De la même manière que le réseau d’irrigation, le réseau de drainage a été diagnostiqué de l’amont
vers l’aval tout en notant :

 Les dimensions des collecteurs ;

 L’envasement et les végétations ;

 Les débordements au niveau des ouvrages des traversées ;

 L’analyse des conditions de drainage : état de l'exutoire, zones de stagnation,

 Le diagnostic de l’état des ouvrages : débouchées, ouvrages de franchissement, passages,

 L’analyse des défaillances et des disfonctionnements du système et l’évaluation de leurs


impacts sur les autres composantes (pistes, parcelles, canaux).

 Le réseau de drainage est ainsi, classé selon sa nomenclature et référencié par ses
coordonnées GPS.

(d) Piste
Les pistes ont été parcourues par l’expert du groupement. Les objectifs du diagnostic sont :

 Les tracés (relevés par GPS) ;

 Les caractéristiques (nature, linéaire, largeur, hauteur, talus,…) ;

 L’état : dégradé, revêtement latéritique, végétation, bouché, ensablement…).

Groupement MCG / SAFI 43


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

(e) Analyse des données disponibles


Les données et les documents disponibles (études, plans d’exécution, plans de récolement,
documents de suivi et de gestion…) fournis par les différents intervenants ont été examinés et
valorisés pour les besoins du projet.

4.3 DIAGNOSTIC DE LA STATION DE POMPAGE


Le site de la station de pompage est situé à une dizaine de kilomètres de Ross-Béthio. Il est
accessible à partir de la route nationale N2, par la piste latéritique principale qui désenclave le Delta.
La station de pompage construite en rive gauche du Lampsar, est reliée à ce dernier par un chenal
d’alimentation.

La station de pompage fournit l'eau d'irrigation au périmètre Grande Digue-Tellel par des pompes à
axe vertical installées dans cette station et qui reçoivent l'eau arrivée du Marigot Lampsar via le
chenal d’amenée.

La station de pompage a été construite en 1977, la capacité des pompes est de 5.4 m3/s dont le type
de pompe est à axe vertical et leurs nombre est de quatre. Les équipements de pompage ont été
remplacés en 2009 à cause de l'usure.

La capacité des pompes remplacées en 2009, a augmentée et est portée à 6.0 m3/s, enregistrant une
amélioration de 0.6 [m3/sec] par rapport à la capacité précédente. Le type de pompe est le même
que le type précédent, Pompes à Axe Vertical, et il y a donc 4 pompes actuellement installées,
chacune d'elles débite l.5 m3/s avec un diamètre de 900 mm

Il y a une piste de 4.0 m de largeur entre la station de pompage et les ouvrages d'admission et l'eau
est délivrée à la station à travers ces ouvrages d'admission qui sont situés sous la piste.

La station de pompage est composée de :

 Un chenal d’amenée,

 Un bâtiment en béton armé,

 Des installations de pompage,

 Des installations électriques et hydromécaniques,

 Des ouvrages de maintenance,

 Des ouvrages de régulation.

Groupement MCG / SAFI 44


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

L'eau pompée est refoulée vers le bassin de dissipation de la station de pompage puis, elle est
envoyée vers les canaux d'irrigation pour la fourniture d'eau d'irrigation aux parcelles du projet. Il y
a 4 clapets anti retour installés face au basin de dissipation pour empêcher le retour de l'eau refoulée
par la station.

Il y a une vanne à niveau constant installée juste à l'aval du bassin de dissipation qui assurait un
contrôle automatique en fonction du niveau d’eau. Cette vanne radiale est installée pour empêcher
l'inondation du bassin de dissipation qui suit la station. Aussi, il y a un déversoir pour les cas
d'urgence et une vanne associés au bassin installés pour empêcher l'inondation du bassin quand les
pompes fonctionnent mal et que le niveau d'eau monte rapidement, en retournant les eaux
excédentaires au chenal d'amenée.

Présentation de la station de pompage de Grand Digue-Tellel

La station de pompage de Grand Digue Tellel est réalisée sur un chenal alimenté par le marigot
Lampsar, elle est mise en service en 1977 et a subi plusieurs réhabilitations (1984,2006) la dernière
en date a été exécutée en 2009, avec un remplacement des 04 électropompes, elle dispose d’une
capacité de refoulement de 6m3/s. La station se situe à environ 6 km de la localité de Rosso -
Béthio, l’accès à la station de pompage est relativement facile, car elle est reliée à ces localités par
une piste en latérite.

Elle assure actuellement le refoulement d’un débit global Q = 6000 l/s, et dispose de 04 groupes de
pompage de type axe vertical de débit unitaire de Q = 1500l/s – HMT = 2, 38Mce, de Marque
KIRLOSKAR .Ces électropompes ont été installées lors de la dernière réhabilitation réalisée en
2009, ces groupes de pompage sont actuellement en bon état de fonctionnement. La pompe P2 est
actuellement en arrêt car la roue est bloquée par un corps étranger.

La station de pompage de Grand Digue Tellel est alimentée par une bretelle du réseau MT de la
SENELEC de 6Km de long, raccordée à partir de Rosso Béthio à une dérivation du réseau MT de
l’axe Rosso – St - Louis.

Groupement MCG / SAFI 45


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Figure 3. Station de pompage périmètre GDT

Les équipements des stations fonctionnent en 380/400 V et sont initialement alimentés par
l’intermédiaire d’un transformateur de puissance égale à 400 KVA – 30KV /50 Hz – I = 400A, ce
transformateur est accolé aux cellules d’arrivée, de protection et de départ.

La disposition de la station de pompage comprendra de l’amont vers l’aval :

 Un chenal d’amenée des eaux du marigot au bout duquel sera aménagé une prise d’eau
constituée de 04 passes pour l’alimentation de la bâche de pompage et l’écoulement
gravitaire des eaux d’irrigation ;

 Les passes sont équipées de rainures de batardeaux et de 04 grilles inclinées par rapport à
l’horizontal (2,35 x 2,00), constituées de barreaux en fer plat et espacées de 50mm ;

 Une bâche partiellement cloisonnée et divisée en cellules ou logent les groupes de


pompage recevant ces cellules et abritent les 04 électropompes à axe vertical (Q= 1500l/s,
HMT= 2,38Mce) ;

 Le local abritant les armoires électriques, et les groupes de pompage ;

 Le bâtiment poste de transformation et ses différentes cellules (arrivée, protection et


comptage) avec l’arrivée de la ligne électrique 30 kV de la SENLEC ;

 La ligne MT (30kv) alimentant la station aboutie au poste de transformation via les


cellules d’arrivée et de protection ;

 Le chenal d’amenée et l’ouvrage de prise d’eau sur le Lampsar ainsi que son
raccordement à la station ;
Groupement MCG / SAFI 46
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 Le bassin de dissipation et le canal de restitution qui alimente les périmètres irrigués ;

 Les armoires électriques de commande et de contrôle des groupes de pompage ;

 Le dispositif de levage qui assure la manutention des équipements et groupes de


pompages (portique et palan mécanique de 5T), est vétuste et est amorti, la charpente
métallique présente beaucoup de corrosions et d’anomalies ;

 Le dispositif de levage portique monorail, installé au-dessus de la prise d’eau qui assure la
manutention des grilles et des batardeaux (portique et palan mécanique de 5T), est vétuste
et est amorti, la charpente métallique présente beaucoup de corrosions et d’anomalies ;

 Tous les éléments constituants les gardes corps et accessoires métalliques (échelles,
caillebotis en tôle striée, Batardeaux, etc.), sont dans un état de dégradation avancé ;

 La vanne type AVIO, destinée à la régulation des niveaux d’eau du canal principal
d’irrigation, est bloquée en position haute depuis plusieurs années ;

 La vanne murale de 1,00mx 1,00m, installée sur la passe gravitaire, est complètement
dégradée et est depuis longtemps hors service.

Résume du programme de réhabilitation des équipements

La station de pompage de Grand Digue-Tellel refoule actuellement un débit d’environ de 6m3/s,


elle sera l’objet d’une réhabilitation profonde et d’un redimensionnement de ses équipements en
fonction de leurs besoin des équipements en tenant compte de la totalité du débit à refouler du débit
(Q = 6m3/s),

Le nombre de groupes de pompage à installer sera donc de 04, mais les pompes en service doivent
être égales à Trois 04(3+1) pour la station. Notons cependant que 03 pompes doivent fonctionner
simultanément pour garantir le refoulement du débit global de 6000 l/s le choix des pompes en
marche peut être alterné et une pompe sera en permanence de réserve.

Les électropompes installées seront du type submersible au lieu du type axe vertical et de débit
unitaire de Q = 2000 l/s, HMT = 2,40mce

La réalisation des travaux de réhabilitation et le renforcement de la station nécessiteront un


remplacement de l’ensemble des équipements de pompage et accessoires, qui concernera
essentiellement les équipements électromécaniques, électriques et hydrauliques ci – après :

Groupement MCG / SAFI 47


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 Le remplacement du Transformateur 400KVA– 30KV /50Hz par un Transformateur de


puissance supérieure (Puissance à déterminer selon celle des pompes), avec les éléments
de protection du poste de transformation, la réalisation de l’ensemble du câblage entre le
poste de transformation MT/BT et le tableau de distribution de la basse tension TGBT, et
les différents départs vers les utilisations .de la station,

 Le remplacement de la cellule d’arrivée avec sectionneur d’isolement, de la cellule de


protection générale équipée d’un interrupteur sectionneur associé à des fusibles HPC et de
la cellule de comptage par des cellules compactes, de type préfabriqué de technologie
récente, et moins encombrantes,

 Le Remplacement du Tableau de distribution TGBT 380/400 V de distribution du


courant alternatif qui présente un parfait désordre, les câbles sont installés pèle -mêle, pas
de repères, pas de chemin de câbles ni de gaines de protection,

 Le renouvellement du câblage et le cheminement des câbles entre les armoires de


commande et les groupes électropompes, nécessiterait la mise en place de chemin de
câbles avec tous les éléments de protection,

 La remplacement des câbles des départs qui alimentent la station ,des disjoncteurs
généraux et des disjoncteurs de protection des moteurs qui sont vétustes et qui n’assurent
plus l’isolement des installations de la station et la protection des équipements et des
personnes,

 Le remplacement du câblage et appareillage des circuits des terres, des masses


métalliques des piquets de terre du poste de transformation et des équipements électriques
du local des pompes, Il sera aussi nécessaire de réaliser un circuit de terre avec liaisons
équipotentielles de toutes les parties métalliques susceptibles d’être portées à un potentiel
dangereux pour les personnes. La prise de terre de la station doit être installée
conformément à la norme,

 La mise en place des parafoudres en lieu et place des éclateurs qui semblent mal raccordés
et pas fonctionnels,

 L’installation de nouvelles armoires de commande, de protection et de contrôle


conformément à la norme en vigueur et tenant compte du fonctionnement automatique du
groupe électropompe (avec tous les accessoires de commande et de contrôle permettant
une permutation cyclique entre les groupes),
Groupement MCG / SAFI 48
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

 Le remplacement de tous les groupes de pompage de type axe vertical existants par
l’installation de 04 nouveaux groupes de pompage 04(3+1) de type submersible de
caractéristiques ci-dessous indiquées : Q = 2000l/s et HMT = 2,40mce, avec tube de
refoulement DN 1000mm, et tous les accessoires de raccordement électriques et
hydrauliques,

 Le réaménagement du génie civil par la réalisation des cloisonnements des cellules de


pompage et une réfection du local de la station et l’adaptation des fosses de pompage aux
nouvelles pompes submersibles de type Amacan P A4,

 Mise en place des 04 tubulures de refoulement des pompes DN 1000 mm,

 Le remplacement des 04 Grilles 3,60 x 4,40 m, installées sur les prises d’eau de la station
et le batardeau,

 Le remplacement du portique existant par la mise en place d’un Pont roulant électrique
équipé de palan électrique de 10 Tonnes, installé à l’intérieur de la station en lieu et place
de l’existant pour la manutention des groupes électropompes et équipements annexes,

 Mise en place d’un Portique monorail équipé de palan mécanique de 5T pour la


manutention des grilles et batardeaux installés au-dessus de la prise d’eau,

 Le remplacement de la vanne type AVIO, destinée à la régulation des niveaux d’eau et du


canal principal d’irrigation qui est bloqué en position haute depuis plusieurs années,

 Le remplacement de la vanne murale de 1,00mx 1,00m installée sur la passe gravitaire est
complètement dégradée et depuis longtemps hors service,

 Remplacement des gardes corps et des accessoires métalliques (échelles, caillebotis en


tôle striée, Batardeaux, etc.), qui sont dans un état de dégradation avancé

Pour plus de détails voir le rapport électromécanique.

Groupement MCG / SAFI 49


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

4.4 DIAGNOSTIC DU RESEAU D’IRRIGATION


La surface irriguée nette du périmètre de Grande Digue-Tellel est de 2783 ha avec une longueur
totale des canaux principaux de 28 km .Les tirants d'eau sont de 1.5 rn et la revanche est de 0.4 m.
Les talus des canaux sont 3/2.

Figure 4. Canal principal d’irrigation

Les canaux d’irrigation existants du projet sont en terre avec une section trapézoïdale et ses sections
ont été maintenues sans entretien approprié, ils sont déformés par la sédimentation sur le fond des
canaux, l’érosion des talus, la couverture de la section du canal par les herbes et spécialement la
détérioration des ouvrages sur réseau et ont besoin d’une réhabilitation ou d’une nouvelle
construction.

Tableau n° 22 : Linéaires des canaux et superficie irriguée


Canal principal Longueur (ml) Superficie (ha)
C-1 6475 971
C-2 8218 227
C-3 6812 272
C-4 6868 730
Les canaux d’irrigation ont été diagnostiqués de l’amont à l’aval tout en identifiant les états de
dégradation et les interventions nécessaires pour les remettre en état.

Groupement MCG / SAFI 50


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Tableau n° 23 : Diagnostic du canal principal C-1


Section actuelle Etat actuel
Largeur
Ouvrage Cote Largeur
L Profondeur en Talus Section
Modulé fond de base Calage
(m) (m) gueule (m/m) hydraulique
(m) b(m)
B(m)
D1/C1 140 1 2.5 14.8 3.8 2.2
D2/C2 240 0.6 2.2 15.5 5.38 2.3
D-1 540 0.6 2.2 15.5 6.26 2.1
D3/C3 30 0.3 2.5 14 4.5 1.9
M1/C1 100 0.3 2.2 13 4.2 2
M2/C1 230 0.3 2.2 10 0.76 2.1
M3/C1 355 0.7 1.7 10 3.2 2
M4/C1 725 0.7 1.8 10 3.52 1.8
M5/C1 60 0.6 2 10 2.4 1.9
M5
230 0.5 2 10 2 2
bis/C1
M6/C1 440 0.7 1.8 12 8.4 1 Suffisante
D-2 30 0.7 1.8 12 6.24 1.6
M7/C1 470 0.37 2.33 10 0.68 2
M8/C1 260 0.5 1.9 10.5 4.42 1.6
problème de calage
M9/C1 80 0.38 1.82 11.5 6.04 1.5
M10/C1 490 0.5 1.7 10.7 3.9 2
M11/C1 185 0.34 1.96 9.5 1.268 2.1
OF-1 210 0.34 1.96 9.5 1.66 2
M12/C1 510 0.38 2.02 10 3.536 1.6
M13/C1 75 0.35 1.85 10 2.97 1.9
M14/C1 75 0.36 1.84 10 3.376 1.8
M15/C1 290 0.3 1.8 9 1.8 2
M16/C1 160 0.3 1.9 8.5 0.9 2 Insuffisante
M17/C1 450 0.4 1.7 9 2.2 2
M18/C1 25 0.3 1.8 7.8 2.04 1.6
M19/C1 215 1.3 0.9 4.5 1.8 1.5
M20/C1 90 1.3 0.9 4.5 0.9 2
Suffisante
M21/C1 210 1.6 0.7 4 1.76 1.6
M22/C1 1725 0 2.3 9 0.72 1.8
M23/C1 1550 0.35 1.85 9 1.6 2

Tableau n° 24 : Diagnostic de canal principal C-2


Section actuelle Etat actuel
Largeur
Ouvrage Cote Largeur
L Profondeur en Talus Section
Modulé fond de base Calage
(m) (m) gueule (m/m) hydraulique
(m) b(m)
B(m)
M1/C2 121 0.83 1.27 8.1 3.02 2 Suffisante

Groupement MCG / SAFI 51


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Largeur
Ouvrage Cote Largeur
L Profondeur en Talus Section
Modulé fond de base Calage
(m) (m) gueule (m/m) hydraulique
(m) b(m)
B(m)
M2/C2 484 0.68 1.52 9.5 3.42 2
M3/C2 452 0.81 1.59 9 2.64 2
M4/C2 615 1.18 0.82 9.3 6.676 1.6
D-3 610 1.18 0.82 9.3 6.676 1.6
M5/C2 30 0.65 1.75 8.8 3.55 1.5 Suffisante
M6/C2 1312 0.57 1.83 8 0.68 2
M7/C2 270 0.35 1.95 10.3 2.11 2.1
M8/C2 230 0.86 1.54 9 2.84 2
M9/C2 245 0.93 1.57 10 4.348 1.8 problème de calage
M10/C2 20 0.82 1.58 12 5.996 1.9 Insuffisante
D-4 410 0.82 1.58 12 5.996 1.9
M11/C2 30 0.66 1.54 10 3.84 2
M12/C2 20 0.66 1.54 10 4.456 1.8
Suffisante
M13/C2 585 0.76 1.64 13 6.768 1.9
M14/C2 20 0.76 1.64 13 6.44 2
M15/C2 630 0.8 1.5 11.2 5.2 2
M16/C2 20 0.8 1.5 11.2 5.2 2 Insuffisante
M17/C2 770 0.74 1.56 8.7 2.46 2
M18/2 200 1.55 0.45 2.6 0.8 2
Suffisante
M19/2 1200 1.5 0.33 2.2 0.88 2

Tableau n° 25 : Diagnostic de canal principal C-3


Section actuelle Etat actuel
Ouvrage Cote Largeur Largeur
L Profondeur Talus Section
Modulé fond en gueule de base Calage
(m) (m) (m/m) hydraulique
(m) B(m) b(m)
M1/C3 90 0.5 2 9.5 3.5 1.5
M2/C3 680 1 1.4 11.4 5.8 2
M3/C3 160 0.8 1.7 8 0.86 2.1
M4/C3 415 0.7 1.8 10 4.24 1.6
M5/C3 220 0.8 1.7 10.4 5.3 1.5
Suffisante
M6/C3 485 0.7 1.8 11.5 4.3 2
M7/C3 525 0.8 1.5 7.4 1.1 2.1
D-5 300 0.8 1.5 7.4 1.4 2 problème de calage
M8/C3 25 0.7 1.8 10 2.44 2.1
M9/C3 495 0.8 1.4 9 4.52 1.6
M10/C3 300 0.5 1.7 9 3.9 1.5
M11/C3 570 0.5 1.7 11 5.56 1.6 Insuffisante
M12/C3 245 0.4 2 10 4 1.5
M13/C3 480 0.9 1.5 11 5 2
Suffisante
M14/C3 280 0.6 1.8 9 1.44 2.1
Groupement MCG / SAFI 52
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION Rapport APD
DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Ouvrage Cote Largeur Largeur
L Profondeur Talus Section
Modulé fond en gueule de base Calage
(m) (m) (m/m) hydraulique
(m) B(m) b(m)
M15/C3 200 0.6 1.6 9 2.6 2
M16/C3 610 0.7 1.6 9 3.24 1.8 Insuffisante
M17/C3 150 0.9 1.5 9 3.3 1.9
M18/C3 290 0.8 1.4 10 4.96 1.8
Suffisante
M19/C3 270 0.7 1.5 10 4 2

Tableau n° 26 : Diagnostic de canal principal C-4


Section actuelle Etat actuel
Largeur
Ouvrage Cote Largeur
L Profondeur en Talus Section
Modulé fond de base Calage
(m) (m) gueule (m/m) hydraulique
(m) b(m)
B(m)
M1/C4 47 0.43 2.17 10.5 1.82 2
M2/C4 1160 0.68 1.72 9.3 2.42 2
M3/C4 212 0.73 1.7 12.5 5.7 2
M4/C4 140 0.8 1.8 9.6 2.4 2
M5/C4 132 0.93 1.42 7.4 2.856 1.6
M6/C4 740 0.68 1.56 10.5 4.884 1.8
OF-2 310 0.68 1.56 10.5 4.572 1.9
M7/C4 255 0.65 1.65 10 4.06 1.8
Suffisante
M8/C4 466 0.76 1.54 8.7 3.156 1.8
M9/C4 420 0.73 1.57 10 4.348 1.8
problème de calage
M10/C4 60 0.99 1.11 8 3.8042 1.89
M11/C4 280 0.7 1.4 10 5.24 1.7
M12/C4 320 0.73 1.47 8.5 3.208 1.8
M13/C4 71 0.91 1.29 9.5 4.34 2
M14/C4 495 0.59 1.51 8.6 4.372 1.4
M15/C4 148 0.67 1.63 9.5 2.98 2
M16/C4 650 0.85 1.65 12 5.4 2
M17/C4 275 0.69 1.31 6.8 1.298 2.1 Insuffisante
M18/C4 280 0.42 1.78 8 0.88 2
M19/C4 405 0.64 1.46 10.5 4.368 2.1 Suffisante

Groupement MCG / SAFI 53


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Tableau n° 27 : Diagnostic des canaux secondaires (C-1)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.2 1660.00 16.12 1.70 0.60 3.30 1.50 1.90 problème de calage
Suffisante
C1.5 205.00 53.81 1.60 0.70 3.40 1.30 1.70 acceptable
C1.5 bis 225.00 20.20 1.60 0.70 3.80 1.70 2.00
C1.6 150.00 138.01 0.90 1.50 8.40 3.90 1.80 Insuffisante
C1.8 530.00 149.23 0.30 2.10 6.70 0.40 1.80
problème de calage
C1.9 515.00 19.23 1.60 0.30 4.00 3.10 1.80 Suffisante
C1.10 105.00 14.97 1.20 0.80 3.50 1.10 1.50
Insuffisante
C1.13 507.00 11.40 1.40 0.80 4.00 1.60 1.50
C1-14 695.00 37.83 1.70 0.50 3.50 2.00 1.90 Suffisante acceptable
C1.18 525.00 8.07 1.20 0.60 2.70 0.90 1.50
problème de calage
C1.19 940.00 13.84 1.20 0.80 4.30 1.90 1.90 Insuffisante
C1.20 850.00 11.39 1.30 0.80 5.00 2.60 1.50 problème de calage

Tableau n° 28 : Diagnostic des canaux tertiaires (C-1)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.1.1 375.00 10.99 1.50 0.50 2.00 0.50 1.50 Suffisante
C1.1.2 550.00 10.45 1.50 0.50 2.40 0.90 1.90
C1.3.1 275.00 11.58 1.60 0.60 3.60 1.80 1.80
C1.3.2 275.00 10.83 1.50 0.70 3.20 1.10 1.50
Insuffisante problème de calage
C1.4.1 390.00 11.05 1.40 0.60 2.50 0.70 1.80
C1.4.2 315.00 7.96 1.40 0.70 2.40 0.30 1.50
C1.4.3 470.00 7.73 1.60 0.50 4.00 2.50 1.50

Groupement MCG / SAFI 54


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.5.1 1200.00 10.20 1.80 0.60 3.00 1.20 1.80 Suffisante
C1.5.2 160.00 6.05 1.60 0.50 3.00 1.50 1.90
C1.5.3 140.00 6.42 1.60 0.40 2.40 1.20 1.50
Insuffisante
C1.5.4 250.00 31.14 1.60 0.70 3.00 0.90 1.80
C1.5 bis-1 875.00 8.36 1.50 0.60 3.30 1.50 1.90
C1.5 bis-2 1040.00 11.84 1.60 0.50 2.00 0.50 1.50
Suffisante
C1.6.2 178.00 67.36 1.50 0.20 3.00 2.40 1.50 acceptable
C1.6.1 540.00 70.64 0.70 1.50 8.00 3.50 1.80 Insuffisante
C1.7.2 700.00 10.59 1.60 0.40 2.50 1.30 1.50
Suffisante
C1.7.3 325.00 24.84 1.50 0.50 2.70 1.20 1.90 problème de calage
C1.7.4 900.00 9.94 1.40 0.60 2.60 0.80 1.80
C1.8.1 590.00 133.87 0.50 1.50 8.00 3.50 1.80
C1.8.2 320.00 7.70 1.40 0.90 3.40 0.70 1.50 acceptable
C1.8.4 400.00 7.67 1.20 0.50 3.00 1.50 1.50
C1.9.1 285.00 7.97 1.50 0.50 2.40 0.90 1.80
C1.9.2 890.00 11.26 1.50 0.50 2.20 0.70 1.80 Insuffisante
C1.10.1 290.00 8.42 1.50 0.50 2.00 0.50 1.50
C1.10.2 730.00 6.55 1.50 0.50 2.60 1.10 1.50
C1.11.1 480.00 7.83 1.50 0.70 4.00 1.90 1.90 problème de calage
C1.11.3 450.00 7.84 1.30 0.50 2.80 1.30 1.90
C1.12.2 660.00 40.98 1.30 0.80 3.80 1.40 1.80
C1.12.3 301.00 30.53 1.50 0.60 2.60 0.80 1.50 Suffisante
C1.14.1 180.00 13.23 1.20 0.30 2.50 1.60 1.50 Suffisante
C1.14.2 100.00 11.61 0.90 0.50 2.80 1.30 1.50
Insuffisante
C1.14.3 650.00 12.99 1.10 0.90 4.00 1.30 1.90 acceptable
C1.15.2 1380.00 90.42 1.20 0.60 2.40 0.60 1.80 Suffisante
problème de calage
C1.16.1 250.00 43.73 1.40 0.60 2.00 0.20 1.50 Insuffisante
Groupement MCG / SAFI 55
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.16.2 860.00 10.39 1.40 0.70 3.01 0.91 1.80
C1.17.1 375.00 10.28 1.40 0.60 2.80 1.00 1.50
C1.17.2 695.00 61.36 1.50 0.60 3.00 1.20 1.80
C1.21.3 530.00 36.55 1.70 0.70 3.20 1.10 1.90
C1.22.1 330.00 27.94 1.60 0.40 2.00 0.80 1.50 Suffisante
C1.22.2 830.00 86.12 0.00 2.00 10.00 4.00 1.50
C1.22.3 855.00 13.36 1.70 0.50 3.20 1.70 1.50 Insuffisante
C1.23.1 700.00 69.91 0.00 2.00 9.50 3.50 1.80
C1.23.2 715.00 16.49 1.50 0.50 2.20 0.70 1.80 Suffisante

Tableau n° 29 : Diagnostic des canaux quaternaires (C-1)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.5.4.1 220.00 24.38 1.60 0.60 2.70 0.90 1.50
C1.5.4.2 965.00 6.76 1.50 0.70 3.50 1.40 1.50
problème de calage
C1.6.2.1 265.00 13.84 1.40 0.80 3.40 1.00 1.90
C1.6.2.2 590.00 43.59 1.20 0.70 3.80 1.70 1.80
C1.6.2.3 300.00 9.93 1.40 0.60 3.60 1.80 1.50
acceptable
C1.6.1.1 260.00 4.13 1.40 0.30 2.00 1.10 1.80
Insuffisante
C1.6.1.2 280.00 25.67 1.00 0.70 4.60 2.50 1.50
C1.6.1.3 217.00 9.54 1.30 0.60 3.60 1.80 1.50
C1.6.1.4 425.00 31.31 1.30 1.00 5.00 2.00 1.80
problème de calage
C1.7.2.1 270.00 13.48 1.40 0.60 2.30 0.50 1.90
C1.7.2.2 575.00 11.36 1.50 0.50 3.20 1.70 1.50
C1.8.1.1 480.00 41.15 1.10 1.00 4.50 1.50 1.80

Groupement MCG / SAFI 56


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.8.1.2 453.00 13.82 1.30 0.70 4.00 1.90 1.90
C1.8.1.3 560.00 14.70 1.30 0.90 4.00 1.30 1.50
C1.8.1.4 450.00 12.45 1.30 0.90 4.00 1.30 1.50
acceptable
C1.8.1.5 830.00 51.74 1.30 0.70 3.20 1.10 1.80
C1.12.2.1 390.00 7.34 1.40 0.60 2.60 0.80 1.50
C1.12.2.2 515.00 10.28 1.60 0.60 3.40 1.60 1.90
C1.12.2.3 600.00 9.96 1.50 0.50 2.00 0.50 1.80
C1.12.2.4 755.00 13.40 1.50 0.50 2.50 1.00 1.80
C1.12.3.1 545.00 15.57 1.40 0.60 3.00 1.20 1.50
C1.12.3.2 960.00 14.96 1.50 0.80 3.50 1.10 1.50
C1.16.1.2 1070.00 13.71 1.40 0.60 2.50 0.70 1.80
problème de calage
C1.16.1.3 1160.00 18.31 1.50 0.60 3.10 1.30 1.80
C1.17.2.1 264.00 8.92 1.10 0.90 3.60 0.90 1.50
C1.17.2.2 490.00 12.59 1.10 0.80 2.50 0.10 1.50
C1.17.2.3 1010.00 11.63 0.50 0.50 2.80 1.30 1.90
C1.17.2.4 350.00 19.07 0.50 0.70 3.30 1.20 1.90
C1.21.2.1 505.00 14.10 1.30 0.60 2.00 0.20 1.80
C1.21.2.2 605.00 8.86 1.30 0.70 3.60 1.50 1.50
C1.21.3.1 480.00 10.28 1.80 0.60 3.60 1.80 1.50 acceptable
C1.21.3.3 430.00 8.38 1.70 0.50 2.40 0.90 1.50
C1.21.3.4 530.00 7.47 1.90 0.40 2.10 0.90 1.90
C1.22.1.1 405.00 15.41 1.10 0.90 3.30 0.60 1.80
C1.22.2.1 800.00 14.24 1.50 0.80 3.50 1.10 1.50
problème de calage
C1.22.2.2 770.00 9.78 1.30 0.70 2.20 0.10 1.80
C1.22.2.3 315.00 27.78 1.20 0.80 2.00 -0.40 1.50
C1.22.2.4 650.00 8.46 1.10 0.80 2.70 0.30 1.50
C1.22.2.5 620.00 7.88 1.10 0.80 3.20 0.80 1.50
Groupement MCG / SAFI 57
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.22.2.6 595.00 8.35 1.40 0.60 3.50 1.70 1.50
C1.22.2.8 750.00 9.63 1.30 0.70 3.30 1.20 1.50
C1.23.1.1 620.00 10.83 1.50 0.50 2.50 1.00 1.50
C1.23.1.2 720.00 17.80 1.60 0.40 2.70 1.50 1.50
C1.23.1.3 615.00 14.00 1.60 0.40 3.60 2.40 1.50 Insuffisante
C1.23.1.4 615.00 16.88 1.40 0.60 2.50 0.70 1.50
C1.23.1.6 850.00 10.39 1.50 0.60 3.30 1.50 1.50

Tableau n° 30 : Diagnostic des canaux quinquénaires(C-1)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quinquénaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.5.4.1.1 185.00 7.47 1.50 0.50 3.00 1.50 1.80
C1.5.4.1.2 250.00 10.28 1.50 0.50 3.00 1.50 1.90 problème de calage
C1.5.4.1.3 600.00 6.64 1.40 0.70 3.00 0.90 1.50
C1.6.2.2.1 302.00 13.45 1.50 0.50 2.20 0.70 1.50
acceptable
C1.6.2.2.2 730.00 9.69 1.40 0.60 2.80 1.00 1.80
C1.6.2.2.3 305.00 11.21 1.50 0.60 3.00 1.20 1.50
C1.6.2.2.4 115.00 9.24 1.40 0.60 2.40 0.60 1.90
Insuffisante
C1.6.1.2.1 460.00 12.99 0.80 0.60 3.10 1.30 1.80
C1.6.1.2.2 510.00 12.68 0.70 0.80 3.30 0.90 1.80
C1.6.1.4.1 460.00 15.32 1.10 0.80 3.50 1.10 1.50 problème de calage
C1.6.1.4.2 410.00 15.98 1.20 0.60 3.40 1.60 1.50
C1.8.1.1.1 575.00 7.99 1.10 0.90 3.50 0.80 1.80
C1.8.1.1.2 513.00 15.66 1.10 0.70 4.00 1.90 1.80
C1.8.1.1.5 425.00 10.08 1.10 0.80 3.30 0.90 1.50

Groupement MCG / SAFI 58


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quinquénaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C1.8.1.1.6 610.00 7.43 0.80 0.70 3.10 1.00 1.50
C1.8.1.3.1 250.00 6.06 1.00 0.90 3.60 0.90 1.90
C1.8.1.3.2 252.00 8.64 1.00 0.80 3.50 1.10 1.90
C.1.8.1.5.1 200.00 10.78 1.30 0.70 2.80 0.70 1.80
C.1.8.1.5.2 590.00 17.70 1.10 0.50 2.00 0.50 1.50
C.1.8.1.5.3 265.00 11.86 0.90 0.60 2.60 0.80 1.50
C.1.8.1.5.4 425.00 11.39 0.90 0.60 2.70 0.90 1.50
C1.17.2.4.1 330.00 7.31 0.50 1.00 3.70 0.70 1.90
C1.17.2.4.2 480.00 11.76 0.50 0.70 3.70 1.60 1.80
C1.22.2.3.1 430.00 9.16 1.40 0.60 3.10 1.30 1.50
C1.22.2.3.2 405.00 8.75 1.30 0.40 2.10 0.90 1.80
C1.22.2.3.3 650.00 9.87 1.30 0.70 2.10 0.00 1.50
C1.23.1.5.1 440.00 8.72 1.50 0.50 3.20 1.70 1.50
C1.23.1.5.2 450.00 8.69 1.30 0.50 2.50 1.00 1.50
C1.23.1.5.3 650.00 7.97 1.30 0.50 2.50 1.00 1.50

Tableau n° 31 : Diagnostic des canaux secondaires (C-3)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.1 380.00 13.61 1.80 0.58 1.80 0.06 1.50 acceptable
C3.5 510.00 6.28 1.46 0.79 3.00 0.63 1.50
C3.11 1100.00 15.95 1.22 0.60 2.60 0.80 1.50 Insuffisante problème de calage
C3.13 480.00 17.67 1.30 0.75 3.50 1.25 1.50
C3.15 310.00 9.67 1.28 0.53 2.20 0.61 1.50 acceptable
C3.17 460.00 18.88 1.34 1.21 4.80 1.17 1.50 problème de calage

Groupement MCG / SAFI 59


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.18 300.00 12.78 1.16 0.69 2.60 0.53 1.50

Tableau n° 32 : Diagnostic des canaux tertiaires (C-3)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.2.1 460.00 12.83 1.22 0.98 4.20 1.26 1.50
C3.2.2 640.00 11.27 1.17 0.89 3.30 0.63 1.50
problème de calage
C3.2.3 440.00 13.31 1.27 1.03 4.00 0.91 1.50
C3.3.1 660.00 12.64 1.50 0.64 3.20 1.28 1.80
C3.3.2 1050.00 15.82 1.57 0.53 2.60 1.01 1.50
C3.4.2 325.00 14.32 1.56 0.64 3.30 1.38 1.90
C3.6.1 345.00 11.10 1.60 0.40 1.80 0.60 1.80
C3.6.2 305.00 19.23 1.50 0.50 2.60 1.10 1.80 acceptable
C3.6.3 310.00 11.09 1.87 0.36 2.20 1.12 1.50
Insuffisante
C3.8.1 520.00 12.92 1.45 0.53 2.40 0.81 1.50
C3.8.2 490.00 12.42 1.54 0.44 2.30 0.98 1.80
C3.9.1 390.00 11.97 1.34 0.47 2.50 1.09 1.80
C3.9.2 380.00 11.56 1.41 0.62 2.70 0.84 1.50
C3.10.1 510.00 12.17 1.47 0.48 3.30 1.86 1.50
C3.10.2 1480.00 10.25 1.50 0.50 3.00 1.50 1.90 problème de calage
C3.10.3 550.00 10.32 1.54 0.43 2.80 1.51 1.90
C3.10.4 430.00 30.89 1.37 0.78 3.50 1.16 1.80
C3.10.5 360.00 40.63 1.40 0.55 3.00 1.35 1.50

Groupement MCG / SAFI 60


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.12.1 365.00 10.93 1.50 0.60 3.20 1.40 1.50
C3.12.2 365.00 8.95 1.18 0.82 3.40 0.94 1.50
C3.14.1 460.00 10.73 1.30 0.76 3.60 1.32 1.90
C3.14.2 485.00 43.51 1.39 0.51 2.80 1.27 1.80
C3.14.3 250.00 12.86 1.22 0.60 2.80 1.00 1.50
acceptable
C3.16.1 290.00 10.44 1.59 0.68 2.80 0.76 1.80
C3.16.2 115.00 5.63 1.71 0.69 3.80 1.73 1.50
C3.17.1 270.00 13.23 1.19 1.00 4.00 1.00 1.50
C3.17.2 180.00 5.65 1.24 0.78 3.00 0.66 1.50
C3.19.1 830.00 46.47 1.23 1.15 5.40 1.95 1.50 problème de calage
C3.19.2 120.00 58.46 1.39 0.60 2.70 0.90 1.50 Suffisante

Tableau n° 33 : Diagnostic des canaux quaternaire (C-3)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.6.2.1 325.00 9.86 1.00 0.67 2.60 0.59 1.80 problème de calage
C3.6.2.2 325.00 9.37 1.20 0.48 1.80 0.36 1.50 acceptable
C3.10.4.1 1640.00 15.17 1.56 0.64 3.40 1.48 1.80
problème de calage
C3.10.4.2 890.00 15.72 1.13 0.83 3.20 0.71 1.50
Insuffisante
C3.10.5.1 535.00 13.66 1.35 0.61 3.20 1.37 1.50
acceptable
C3.10.5.2 960.00 14.67 1.37 0.49 3.80 2.33 1.50
C3.10.5.3 850.00 12.30 1.26 0.40 2.50 1.30 1.80 problème de calage
C3.14.2.1 300.00 10.59 1.18 0.91 4.50 1.77 1.50

Groupement MCG / SAFI 61


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C3.14.2.2 305.00 10.79 1.25 0.52 2.50 0.94 1.80
C3.14.2.3 490.00 11.97 1.09 0.98 4.50 1.56 1.50
C3.14.2.4 405.00 10.16 1.10 0.60 2.40 0.60 1.50
acceptable
C3.19.1.1 330.00 12.23 1.45 0.89 4.40 1.73 1.50
C3.19.1.2 445.00 12.78 1.42 0.81 4.30 1.87 1.80
C3.19.1.3 680.00 15.14 1.06 0.89 4.70 2.03 1.50
C3.19.1.4 370.00 6.33 1.36 0.89 4.20 1.53 1.80 problème de calage
C3.19.2.1 375.00 14.09 1.35 0.57 2.10 0.39 1.50
C3.19.2.2 470.00 30.64 1.24 0.75 2.70 0.45 1.50
C3.19.2.3 295.00 13.72 1.36 0.54 2.20 0.58 1.50 Insuffisante problème de calage

Tableau n° 34 : Diagnostic des canaux quinquénaires (C-3)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de base Talus Section
quinquénaire (ml) (ha) Calage
(m) (m) gueule B(m) b(m) (m/m) hydraulique
C3.19.2.2.1 240.00 15.80 1.10 0.41 1.90 0.67 1.50
Insuffisante acceptable
C3.19.2.2.2 385.00 14.84 0.94 0.55 2.10 0.45 1.50

Tableau n° 35 : Diagnostic des canaux secondaires (C-2)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C2.1 119.57 21.42 1.30 0.50 3.20 1.70 1.50
Insuffisante acceptable
C2.6 171.75 51.19 1.40 0.60 3.00 1.20 1.50

Groupement MCG / SAFI 62


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

C2.8 268.69 8.92 1.20 0.40 2.40 1.20 1.50 Suffisante


problème de calage
C2.11 266.30 10.62 1.16 0.94 3.20 0.38 1.50
C2.13 231.45 151.89 1.55 0.65 3.40 1.45 1.50
Insuffisante acceptable
C2.15 628.04 87.61 1.37 0.60 2.50 0.70 1.50
C2.18 1073.09 12.36 1.50 0.50 3.00 1.50 1.50 problème de calage

Tableau n° 36 : Diagnostic des canaux tertiaires(C-2)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 2.1-1 401.66 9.74 1.85 0.60 3.20 1.40 1.80 Insuffisante
C 2.1-2 1060.65 11.68 2.06 0.17 2.30 1.79 1.50
Suffisante
C2.2.1 468.47 7.12 1.91 0.42 2.40 1.14 1.50 problème de calage
C2.2.2 313.84 4.34 1.51 0.75 4.20 1.95 1.50
C2.2.3 471.12 9.20 1.19 0.71 3.80 1.67 1.80
C 2.3.1 210.00 8.99 1.77 0.71 4.00 1.87 1.50 Insuffisante
C 2.3.2 296.37 15.58 1.68 0.62 2.70 0.84 1.80 acceptable
C 2.3.3 197.18 9.76 1.70 0.50 2.00 0.50 1.50
C 2.4.1 356.22 12.24 1.68 0.42 2.00 0.74 1.50 Suffisante
C 2.4.2 362.59 14.61 1.47 0.73 3.00 0.81 1.50 Insuffisante
C 2.4.3 445.47 27.40 1.49 0.61 2.30 0.47 1.50 Suffisante
C 2.5.1 250.83 10.41 1.41 0.69 3.50 1.43 1.80 problème de calage
C 2.5.2 662.32 10.17 1.39 0.71 3.70 1.57 1.50
Insuffisante
C 2.5.3 390.51 9.34 1.47 0.63 4.00 2.11 1.50
C2.6.2 369.39 5.80 1.54 0.46 2.70 1.32 1.50

Groupement MCG / SAFI 63


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C2.7.1 471.87 13.46 1.24 0.66 3.20 1.22 1.80
C2.7.2 240.70 4.61 1.43 0.77 2.80 0.49 1.50
C2.10.1 613.06 8.49 1.64 0.56 2.00 0.32 1.80
acceptable
C2.10.2 161.52 8.94 1.63 0.47 2.40 0.99 1.50
C 2.12.1 0.00 12.03 1.57 0.40 1.80 0.60 1.50 Suffisante
C 2.12.2 332.98 14.48 1.30 0.40 1.80 0.60 1.50 Suffisante
C 2.12.3 197.55 9.08 1.48 0.50 2.00 0.50 1.50
C 2.13.1 1915.56 87.99 1.49 0.51 2.90 1.37 1.80
C2.13.2 1176.42 63.90 1.35 0.75 2.60 0.35 1.50
C 2.14.1 203.11 8.82 1.56 0.74 3.00 0.78 1.50 problème de calage
C 2.14.2 276.15 17.83 1.37 0.63 2.80 0.91 1.50
Insuffisante
C 2.14.3 179.00 8.88 1.70 0.50 2.80 1.30 1.80
C 2.15.1 490.00 11.19 1.46 0.64 3.00 1.08 1.50
C 2.15.2 404.02 8.90 1.37 0.58 2.70 0.96 1.80
C 2.15.3 457.22 8.83 1.37 0.73 2.70 0.51 1.50
C 2.16.1 174.74 8.74 1.50 0.50 2.00 0.50 1.50 acceptable
C 2.16.2 269.87 18.00 1.50 0.45 2.60 1.25 1.50
C 2.16.3 174.42 8.76 1.60 0.40 2.00 0.80 1.50 Suffisante
C 2.17.1 568.07 56.02 1.22 0.78 3.00 0.66 1.50
problème de calage
C 2.17.2 622.29 67.93 0.96 1.04 4.00 0.88 1.50
C 2.19.1 902.14 73.63 1.20 0.60 3.50 1.70 1.50 Insuffisante
C 2.19.2 982.54 9.54 1.40 0.50 3.20 1.70 1.50

Tableau n° 37 : Diagnostic des canaux quaternaires (C-2)


Canal Linéaire Superficie Section actuelle Etat actuel

Groupement MCG / SAFI 64


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

quaternaire (ml) (ha) Cote fond Profondeur Largeur en Largeur de Talus Section
Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 2.3.2.1 191.70 7.29 1.09 0.61 2.50 0.67 1.50
C 2.3.2.2 203.62 8.29 1.05 0.55 2.50 0.85 1.50
C 2.4.3.1 343.52 14.02 1.27 0.53 2.70 1.11 1.80
C 2.6.1.1 132.59 5.93 1.37 0.56 2.70 1.02 1.50
C 2.6.1.2 519.75 6.55 1.54 0.66 3.70 1.72 1.50
C 2.6.1.4 448.37 7.46 1.68 0.52 2.50 0.94 1.50 Insuffisante problème de calage
C 2.6.1.5 454.94 6.93 1.60 0.35 2.00 0.95 1.80
C 2.6.1.6 410.37 6.31 1.68 0.42 2.50 1.24 1.50
C 2.6.1.7 511.60 4.97 1.80 0.40 2.70 1.50 1.80
C 2.12.2.1 186.04 7.34 1.00 0.60 2.00 0.20 1.50
C 2.12.2.2 181.76 7.14 1.00 0.56 2.20 0.52 1.50
C 2.13.1.1 499.56 10.39 1.50 0.40 1.70 0.50 1.50 Suffisante
problème de calage
C 2.13.1.2 350.91 10.45 1.46 0.38 2.00 0.86 1.50
C 2.13.1.3 383.70 10.04 1.49 0.60 3.00 1.20 1.50
C 2.13.1.4 194.75 6.56 1.65 0.39 2.40 1.23 1.50 acceptable
C 2.13.1.5 231.59 9.43 1.39 0.71 3.20 1.07 1.50
Insuffisante
C 2.13.1.6 159.59 8.40 1.56 0.54 2.50 0.88 1.50
C 2.13.1.7 963.75 7.61 1.62 0.76 3.50 1.22 1.80
C 2.13.1.8 80.56 6.20 1.85 0.35 2.50 1.45 1.50
C 2.13.1.9 263.69 10.11 1.78 0.54 3.70 2.08 1.50
C 2.13.1.10 566.50 8.80 2.06 0.30 1.90 1.00 1.50 problème de calage
Suffisante
C 2.13.2.1 275.47 26.06 1.74 0.25 1.60 0.85 1.80
C 2.13.2.2 94.51 15.19 1.50 0.70 3.00 0.90 1.50
C 2.14.2.1 179.19 8.77 1.00 0.80 3.00 0.60 1.80
C 2.14.2.2 179.59 9.06 1.05 0.85 3.30 0.75 1.50
Insuffisante
C 2.16.2.1 194.33 9.18 1.10 0.50 2.00 0.50 1.50
C 2.16.2.2 192.90 8.82 1.27 0.43 2.00 0.71 1.50
acceptable
C 2.17.1.1 275.20 11.17 1.34 0.46 2.00 0.62 1.50
Groupement MCG / SAFI 65
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
quaternaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 2.17.1.2 287.50 11.90 1.55 0.39 2.00 0.83 1.50
C 2.17.1.3 385.31 21.47 1.04 0.74 2.40 0.18 1.80
C 2.17.1.4 345.10 11.48 1.38 0.48 2.20 0.76 1.50
C 2.17.2.1 514.85 14.62 1.33 0.50 2.70 1.20 1.50
C 2.17.2.3 545.24 9.77 1.16 0.64 3.30 1.38 1.50
C 2.17.2.4 516.52 12.41 1.04 0.56 2.80 1.12 1.80
C 2.17.2.5 791.59 13.63 1.02 0.50 2.80 1.30 1.50
C 2.19.1.1 805.93 15.40 1.20 0.40 3.00 1.80 1.80 problème de calage
C 2.19.1.2 514.51 12.00 1.50 0.60 3.20 1.40 1.50
C 2.19.1.3 735.56 8.14 1.30 0.50 2.50 1.00 1.50
C 2.19.1.4 778.20 5.51 1.20 0.50 2.50 1.00 1.50
C 2.19.1.5 791.36 8.04 1.30 0.60 2.40 0.60 1.50
C 2.19.1.6 799.23 7.33 1.20 0.40 2.40 1.20 1.50
C 2.19.1.7 817.46 7.90 1.30 0.50 2.40 0.90 1.50
C 2.19.1.8 656.04 9.30 1.10 0.60 2.50 0.70 1.50

Tableau n° 38 : Diagnostic des canaux quinquénaires (C-2)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 2.13.2.2.1 393.65 6.99 1.60 0.50 3.00 1.50 1.50
C 2.13.2.2.2 687.47 8.20 1.40 0.70 3.00 0.90 1.50 problème de calage
Insuffisante
C 2.17.1.3.1 160.45 10.77 1.00 0.60 2.50 0.70 1.50
C 2.17.1.3.2 322.89 10.70 1.18 0.62 2.20 0.34 1.50 acceptable

Tableau n° 39 : Diagnostic des canaux quinquénaires (C-2)

Groupement MCG / SAFI 66


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quinquénaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 2.13.2.2.1 393.65 6.99 1.60 0.50 3.00 1.50 1.50
C 2.13.2.2.2 687.47 8.20 1.40 0.70 3.00 0.90 1.50 problème de calage
Insuffisante
C 2.17.1.3.1 160.45 10.77 1.00 0.60 2.50 0.70 1.50
C 2.17.1.3.2 322.89 10.70 1.18 0.62 2.20 0.34 1.50 acceptable

Tableau n° 40 : Diagnostic des canaux secondaires (C-4)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
secondaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C4.3 276.22 16.90 1.63 0.57 2.50 0.79 1.50 acceptable
C 4-8 724.76 41.75 1.00 0.76 2.80 0.52 1.50
C4-9 501.24 30.70 1.26 0.84 3.50 0.98 1.50
Insuffisante
C4-12 912.05 48.51 1.57 0.68 5.20 3.16 1.50
problème de calage
C4-14 341.90 22.77 1.13 1.02 4.70 1.64 1.50
C4-17 655.09 36.70 1.66 0.74 4.50 2.28 1.50
C4-18 946.93 50.24 1.70 0.46 2.70 1.32 1.50 Suffisante

Tableau n° 41 : Diagnostic des canaux tertiaires (C-4)


Section actuelle Etat actuel
Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 4-1-1 724.48 7.23 1.37 0.50 2.50 1.00 1.50 problème de calage
C 4-1-2 577.52 6.48 1.89 0.31 2.50 1.57 1.50
Insuffisante
C 4-2-1 312.48 6.09 1.41 0.56 3.50 1.82 1.50 acceptable
C 4-2-2 310.60 7.02 1.37 0.63 4.00 2.11 1.50

Groupement MCG / SAFI 67


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C4.3.1 404.73 9.02 1.44 0.36 1.90 0.82 1.80
C4.3.2 223.38 7.88 1.50 0.64 3.50 1.58 1.50
C4.4.1 361.49 20.97 1.40 0.75 3.20 0.95 1.50
C4.4.2 281.35 40.61 1.70 0.40 2.80 1.60 1.50 Suffisante problème de calage
C4.4.3 1122.49 20.11 1.65 0.64 2.65 0.73 1.80
C 4-5-1 289.80 6.67 1.33 0.57 3.00 1.29 1.50
C 4-5-2 330.17 7.69 1.34 0.41 2.40 1.17 1.80
C 4-6-1 444.58 6.04 1.67 0.52 2.90 1.34 1.50
C 4-6-2 434.96 8.43 1.67 0.63 4.00 2.11 1.50
C 4-6-3 189.76 7.96 1.65 0.55 2.40 0.75 1.50
acceptable
C 4-6-4 519.10 10.42 1.50 0.60 3.50 1.70 1.50
C 4-7-1 194.66 7.61 1.36 0.64 3.00 1.08 1.50
C 4-7-2 256.27 7.49 1.44 0.56 2.70 1.02 1.50
C 4-7-3 417.54 7.50 1.16 0.78 3.50 1.16 1.50
C4-8-2 791.25 8.71 1.20 0.70 3.00 0.90 1.80
C4-8-3 466.67 11.57 1.47 0.39 2.30 1.13 1.50 Insuffisante
C4-8-4 596.46 13.30 1.44 0.56 2.80 1.12 1.50
C4-9-1 504.83 11.65 1.09 0.77 3.30 0.99 1.50 problème de calage
C4-9-2 488.46 9.88 1.30 0.70 3.50 1.40 1.80
C4-9-3 635.72 9.17 1.34 0.66 2.80 0.82 1.50
C4-10-1 840.13 17.50 1.34 0.61 2.20 0.37 1.80
C4-10-2 440.60 37.17 1.41 0.69 2.80 0.73 1.50
C4-11-1 355.36 7.28 1.29 0.71 2.80 0.67 1.50
C4-11-2 359.41 7.32 1.38 0.52 2.80 1.24 1.50 acceptable
C 4-12-1 351.02 8.90 1.57 0.43 2.80 1.51 1.50
C 4-12-2 313.84 5.84 1.53 0.47 1.90 0.49 1.50
problème de calage
C 4-12-3 389.81 7.83 1.59 0.41 2.60 1.37 1.50
Groupement MCG / SAFI 68
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote fond Profondeur Largeur en Largeur de Talus Section
tertiaire (ml) (ha) Calage
(m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 4-12-5 398.75 7.84 1.65 0.35 1.60 0.55 1.50
C 4-12-6 564.97 10.22 1.66 0.30 1.80 0.90 1.50
C4-13-1 441.95 22.42 1.16 0.68 3.30 1.26 1.80
C4-13-3 417.84 13.93 1.50 0.40 1.80 0.60 1.50
acceptable
C4-13-4 452.59 20.38 1.30 0.60 2.40 0.60 1.50
C4-14-1 437.22 7.30 1.48 0.51 2.80 1.27 1.80
C4-14-2 585.72 9.57 1.60 0.50 2.70 1.20 1.50
C4-14-3 844.05 5.89 2.00 0.20 2.00 1.40 1.80
C4-16-1 189.50 9.14 1.24 0.46 2.50 1.12 1.50
C 4-17-1 212.96 4.36 1.10 0.70 3.00 0.90 1.50
C 4-17-2 134.35 7.18 1.10 0.70 3.00 0.90 1.50
C 4-17-3 300.08 7.02 1.23 0.61 2.60 0.77 1.50 problème de calage
C 4-17-4 500.84 9.13 1.47 0.53 2.80 1.21 1.50
C 4-17-5 750.32 9.01 1.73 0.37 3.00 1.89 1.50
C 4-18-1 179.12 6.85 1.60 0.40 2.20 1.00 1.50
C 4-18-2 284.39 9.81 1.28 0.44 2.50 1.18 1.50
C 4-18-3 374.90 7.71 1.60 0.40 2.00 0.80 1.50
C 4-18-4 261.30 6.20 1.65 0.35 2.50 1.45 1.50
C 4-18-5 370.69 9.40 1.80 0.30 2.00 1.10 1.50 acceptable
C 4-18-6 606.50 10.26 1.52 0.67 3.00 0.99 1.50
C 4.19-1 382.47 10.59 0.97 0.81 3.40 0.97 1.50
problème de calage
C 4.19-2 1061.93 80.69 1.16 0.76 3.50 1.22 1.50
C 4.19-3 748.56 54.58 1.40 0.40 3.00 1.80 1.50 Suffisante

Tableau n° 42 : Diagnostic des canaux quaternaires (C-4)


Canal Linéaire Superficie Section actuelle Etat actuel

Groupement MCG / SAFI 69


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

quaternaire (ml) (ha) Cote Profondeur Largeur en Largeur de Talus Section


Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 4-4-1-1 1126.05 8.94 1.34 0.75 4.00 1.75 1.50
C 4-4-1-2 1103.22 12.03 1.40 0.69 4.50 2.43 1.80
C 4-4-2-1 1131.11 6.64 1.16 0.84 4.30 1.78 1.50
C 4-4-2-2 1087.16 11.22 1.14 0.73 3.00 0.81 1.50
C 4-4-2-3 1152.38 11.90 1.25 0.64 3.00 1.08 1.50
problème de calage
C 4-4-2-4 1125.52 10.85 1.30 0.80 4.20 1.80 1.80
C4-10-2-2 865.40 7.56 1.39 0.58 2.50 0.76 1.80
C4-10-2-3 842.21 6.76 1.35 0.85 3.60 1.05 1.50
C4-10-2-4 625.52 6.90 1.39 0.71 3.00 0.87 1.50
C4-10-2-5 764.32 8.33 1.42 0.58 2.60 0.86 1.50
C 4-13-1-1 307.63 11.78 1.20 0.50 2.40 0.90 1.50
C 4-13-1-2 306.48 10.65 1.05 0.71 2.20 0.07 1.80
acceptable
C4-13-4-1 258.13 10.17 1.26 0.64 2.40 0.48 1.50
Insuffisante
C4-13-4-2 385.50 10.21 1.34 0.53 2.20 0.61 1.50
C 4.19-2-1 591.13 10.18 0.85 0.71 3.30 1.17 1.50
C 4.19-2-2 598.72 8.90 0.80 0.80 3.30 0.90 1.80
C 4.19-2-3 549.18 7.87 0.94 0.73 3.10 0.91 1.50
C 4.19-2-4 703.13 9.61 1.00 0.50 3.00 1.50 1.80
C 4.19-2-5 743.39 12.99 0.86 0.74 3.00 0.78 1.50
C 4.19-2-6 606.93 12.03 1.10 0.55 2.70 1.05 1.50
problème de calage
C 4.19-2-7 451.88 10.44 1.05 0.67 3.00 0.99 1.50
C 4.19-2-8 654.39 8.67 1.08 0.69 3.40 1.33 1.50
C 4.19-3-1 610.18 20.97 1.69 0.86 4.30 1.72 1.50
C 4.19-3-2 420.42 7.56 1.28 0.64 3.00 1.08 1.50
C 4.19-3-3 388.08 12.67 1.40 0.47 3.20 1.79 1.50
C 4.19-3-4 294.67 13.38 1.00 0.47 2.50 1.09 1.50

Tableau n° 43 : Diagnostic des canaux quinquénaires (C-4)


Groupement MCG / SAFI 70
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL D'OFFRES
(DAO) POUR LES TRAVAUX DE REHABILITATION ET L'EXTENSION DU Rapport APD
PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES TRAVAUX DE
REHABILITATION DE LA STATION DE POMPAGE DE GRANDE DIGUE-TELLEL
(3600 HA

Section actuelle Etat actuel


Canal Linéaire Superficie
Cote Profondeur Largeur en Largeur de Talus Section
quinquénaire (ml) (ha) Calage
fond (m) (m) gueule B(m) base b(m) (m/m) hydraulique
C 4.19-3-1-1 420.87 9.40 1.83 0.35 2.50 1.45 1.50
C 4.19-3-1-2 234.64 7.44 1.83 0.61 2.70 0.87 1.50 Insuffisante problème de calage
C 4.19-3-1-3 236.45 4.12 1.90 0.37 3.00 1.89 1.50

Groupement MCG / SAFI 71


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

4.5 OUVRAGES SUR RESEAU D’IRRIGATION


Les canaux d’irrigation sont équipés d’ouvrages de contrôle des débits (modules à masques, prises
modulées), de contrôle du plan d’eau (vanne de contrôle), des partiteurs, des franchissements et
d’autres infrastructures (ouvrage de traversée de pistes, passages inférieurs de colature).

Figure 5. Ouvrage de modulé sur canaux secondaires

Figure 6. Ouvrage de modulé sur canal tertiaire (à gauche) et quaternaire (à droite)

Les ouvrages sur les canaux d’irrigation ont été diagnostiqués de l’amont à l’aval tout en identifiant
les états de dégradation et les interventions nécessaires pour les remettre en état.

Groupement MCG / SAFI 72


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 44 : Diagnostic des ouvrages sur C-1


Etat génie civil Etat équipement
Ouvrage
Type GC à GC à Eq à Ep à
Modulé
réhabiliter refaire réhabiliter remplacer
D1/C1 Partiteur X X
D2/C2 Partiteur X X
D-1 Ouvrage de traversée X X
D3/C3 Partiteur X X
M1/C1 Ouvrage modulé X X
M2/C1 Ouvrage modulé X X
M3/C1 Ouvrage modulé X X
M4/C1 Ouvrage modulé X X
M5/C1 Ouvrage modulé X X
M5 bis/C1 Ouvrage modulé X X
M6/C1 Ouvrage modulé X X
D-2 Ouvrage de traversée X X
M7/C1 Ouvrage modulé X X
M8/C1 Ouvrage modulé X X
M9/C1 Ouvrage modulé X X
M10/C1 Ouvrage modulé X X
M11/C1 Ouvrage modulé X X
OF-1 Ouvrage de franchissement X X
M12/C1 Ouvrage modulé X X
M13/C1 Ouvrage modulé X X
M14/C1 Ouvrage modulé X X
M15/C1 Ouvrage modulé X X
M16/C1 Ouvrage modulé X X
M17/C1 Ouvrage modulé X X
M18/C1 Ouvrage modulé X X
M19/C1 Ouvrage modulé X X
M20/C1 Ouvrage modulé X X
M21/C1 Ouvrage modulé X X
M22/C1 Ouvrage modulé X X
M23/C1 Ouvrage modulé X X

Tableau n° 45 : Diagnostic des ouvrages sur C-2


Etat génie civil Etat équipement
Ouvrage
Type GC à Eq à Ep à
Modulé GC à refaire
réhabiliter réhabiliter remplacer
M1/C2 Ouvrage modulé X X
M2/C2 Ouvrage modulé X X
M3/C2 Ouvrage modulé X X
M4/C2 Ouvrage modulé X X
Ouvrage de
D-3 X X
traversée
M5/C2 Ouvrage modulé X X
M6/C2 Ouvrage modulé X X
M7/C2 Ouvrage modulé X X
M8/C2 Ouvrage modulé X X
M9/C2 Ouvrage modulé X X
M10/C2 Ouvrage modulé X X

Groupement MCG / SAFI 73


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Etat génie civil Etat équipement


Ouvrage
Type GC à Eq à Ep à
Modulé GC à refaire
réhabiliter réhabiliter remplacer
Ouvrage de
D-4 X X
traversée
M11/C2 Ouvrage modulé X X
M12/C2 Ouvrage modulé X X
M13/C2 Ouvrage modulé X X
M14/C2 Ouvrage modulé X X
M15/C2 Ouvrage modulé X X
M16/C2 Ouvrage modulé X X
M17/C2 Ouvrage modulé X X
M18/2 Ouvrage modulé X X
M19/2 Ouvrage modulé X X

Tableau n° 46 : Diagnostic des ouvrages sur C-3


Etat génie civil Etat équipement
Ouvrage
Type GC à GC à Eq à Ep à
Modulé
réhabiliter refaire réhabiliter remplacer
M1/C3 Ouvrage modulé X X
M2/C3 Ouvrage modulé X X
M3/C3 Ouvrage modulé X X
M4/C3 Ouvrage modulé X X
M5/C3 Ouvrage modulé X X
M6/C3 Ouvrage modulé X X
M7/C3 Ouvrage modulé X X
Ouvrage de
D-5 X X
traversée
M8/C3 Ouvrage modulé X X
M9/C3 Ouvrage modulé X X
M10/C3 Ouvrage modulé X X
M11/C3 Ouvrage modulé X X
M12/C3 Ouvrage modulé X X
M13/C3 Ouvrage modulé X X
M14/C3 Ouvrage modulé X X
M15/C3 Ouvrage modulé X X
M16/C3 Ouvrage modulé X X
M17/C3 Ouvrage modulé X X
M18/C3 Ouvrage modulé X X
M19/C3 Ouvrage modulé X X

Tableau n° 47 : Diagnostic des ouvrages sur C-4


Etat génie civil Etat équipement
Ouvrage
Type GC à GC à Eq à Ep à
Modulé
réhabiliter refaire réhabiliter remplacer
M1/C4 Ouvrage modulé X X
M2/C4 Ouvrage modulé X X
M3/C4 Ouvrage modulé X X
M4/C4 Ouvrage modulé X X

Groupement MCG / SAFI 74


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Etat génie civil Etat équipement


Ouvrage
Type GC à GC à Eq à Ep à
Modulé
réhabiliter refaire réhabiliter remplacer
M5/C4 Ouvrage modulé X X
M6/C4 Ouvrage modulé X X
OF-2 Ouvrage de franchissement X X
M7/C4 Ouvrage modulé X X
M8/C4 Ouvrage modulé X X
M9/C4 Ouvrage modulé X X
M10/C4 Ouvrage modulé X X
M11/C4 Ouvrage modulé X X
M12/C4 Ouvrage modulé X X
M13/C4 Ouvrage modulé X X
M14/C4 Ouvrage modulé X X
M15/C4 Ouvrage modulé X X
M16/C4 Ouvrage modulé X X
M17/C4 Ouvrage modulé X X
M18/C4 Ouvrage modulé X X
M19/C4 Ouvrage modulé X X

Groupement MCG / SAFI 75


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

4.6 RESEAU DE DRAINAGE


Le périmètre rizicole est associé à des réseaux de drainage hiérarchisés à ciel ouvert qui rejettent les
eaux de drainage soit dans les dépressions naturelles du delta soit dans les axes hydrauliques.

Pour drainer le périmètre de Grande Digue-Tellel plusieurs, canaux de drainage sont fournis : 3
drains principaux, 6 drains latéraux et 60 drains tertiaires sont décrits ci-dessous :

 Canal de drainage Kassack existant: passe par la partie Est de Grande Digue et de Tellel et
livre l'eau à la station d’exhaure. Tous les drains principaux du projet drainent vers le Drain
Kassack existant,

 Drain Principal D-1 : Drainage de la partie Grande Digue sur une longueur d'environ 5.2
km. délivre l'eau au Kassack de drainage,

 Drain Principal D-2: Drainage de la partie Est de Tellel sur une longueur d'environ 1.0 km
qui délivre l'eau au Kassack de drainage,

 Drain Principal D-3: Drainage de la partie Ouest de Tellel sur une longueur d'environ 5.7
km qui délivre l'eau au Kassack de drainage.

Figure 7. Collecteur principal de drainage

Le diagnostic du réseau de drainage montre plusieurs défaillances au niveau du système :

 Les drains principaux et secondaires sont dans un état médiocre. En effet, les sections de
ces drain sont envasées et occupées par la végétation dont la densité empêche l’écoulement
et crée des zones de stagnation d’eau qui débordent parfois sur les parcelles limitrophes et
sur les pistes et posent des problèmes de circulation,

Groupement MCG / SAFI 76


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Toutes les débouchées des colatures sont colmatées et couvertes par la végétation ce qui
pose des problèmes d’écoulement des eaux vers la station d’exhaure,

 Les passages busés et inférieurs sont tous obstrués et présentent des sections réduites et
défavorables aux écoulements.

4.7 RESEAU DE PISTE


Les pistes à l'intérieur du projet ne sont pas revêtues mais le réseau de ces pistes s’est bien organisé le
long des canaux principaux d'irrigation et de drainage.

Le périmètre irrigué GDT comprend 63 150 ml de pistes principales et secondaires. L’état des pistes
du périmètre se présente comme suit :

 Le revêtement latéritique de toutes les pistes est quasi-inexistant,

 Les pistes du périmètre sont le siège de dégradations résultant des fuites d’eau des canaux
et de la stagnation des eaux de colatures. Ceci a abouti à la création de zones impraticables
et de tronçons de pistes difficilement carrossables,

 Certaines pistes, surtout au niveau du secteur Tellel, sont ensablées et doivent être reprises.
Le linéaire total des pistes ensablées est à reprendre,

 Les pistes sont envahies par la végétation. Ceci pose des problèmes de circulation et se
traduit par des pistes qui sont transformées en simples sentiers,

 La quasi-totalité des fossés des pistes est dans un état médiocre. Cette situation a engendré
des problèmes d’évacuation des eaux (pluies, fuites, débordements) vers le système de
drainage et ces eaux sont souvent piégées sur les pistes contribuant à la dégradation de
leurs structures.

Groupement MCG / SAFI 77


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Figure 8. Pistes dégradée dans le périmètre GDT

Groupement MCG / SAFI 78


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

4.8 RESULTATS ET ORIENTATION DU PROJET DE REHABILITATION


L'analyse de la situation du périmètre GDT a permis de dégager les insuffisances suivantes pour
lesquelles des corrections doivent être portées :

 Station de pompage

Suite au diagnostic des différentes composantes de la station de pompage nous pouvons retenir que
celle-ci est très ancienne, cependant et a été plusieurs fois réhabilitée et que les équipements
électromécaniques et hydromécaniques sont âgés, amortis et en mauvais état.

Les groupes de pompage existant sont en parfaits état de fonctionnement mais, pour les besoins en
eau croissants correspondants à la demande des périmètres, les groupes de pompage seront
redimensionnés et remplacés par des électropompes plus adaptées à la nouvelle configuration des
périmètres.

Le renforcement et l’amélioration de la qualité de pompage passent donc obligatoirement par le


renouvellement des équipements électriques et hydromécaniques de la station.

 Réseau d’irrigation

Le projet de réhabilitation de l’aménagement hydro-agricole doit aboutir à une remise en état des
canaux d’irrigation par l’élimination des anomalies entravant leur bon fonctionnement. Il s’agit
principalement de préserver les infrastructures en bon état, de corriger les défaillances, de réparer les
dégradations et de renforcer les capacités de ces infrastructures en vue d'assurer correctement leurs
rôles.

Les principales actions de réhabilitation proposées pour remettre en état les canaux d’irrigation se
résument comme suit :

- L'établissement d'un système de régulation de fonctionnement du réseau d'irrigation

- Calage et reprofilage de tous les canaux d’irrigation

- Revêtement d’une partie du canal principal CP-1

- Renouvellement de tous les ouvrages de distribution et de contrôle

- Création de nouveaux ouvrages de traversées et de passage inférieur

 Réseau de drainage

Les actions prévues pour la réhabilitation du réseau de drainage sont les suivantes :

- Le calage et le reprofilage de tous les drains,

Groupement MCG / SAFI 79


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

- Le renouvellement de tous les passages busés et passages inférieurs pour améliorer les
conditions d’écoulement des eaux vers l’exutoire,

- Création de nouveaux ouvrages de rejet des eaux de drainage.

 Piste

Pour améliorer les conditions de desserte et de circulation à l’intérieur du périmètre irrigué, le réseau
de pistes doit être remis en état. Les actions prévues à cet effet sont les suivantes :

- La reprise des tronçons de pistes dégradés par des opérations de surfaçage et d’apport de
remblai ;

- Le nettoyage des pistes par l’abattage et l’élimination d’arbres et d’arbustes ;

- Le revêtement de toutes les pistes principales par une couche latéritique

 Nivellement et planage des parcelles mal irriguées

Groupement MCG / SAFI 80


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

5. PROJET DE REHABILITATION

De nombreux projets d'irrigation ont été réalisés et sont en service à travers le monde. Cependant,
après un certain temps et malgré un entretien convenable, les besoins à satisfaire changent, les
aménagements existants nécessitent des modifications structurelles ou encore la quantité et la qualité
de l'eau ne correspondent plus aux données d'origine du projet. L'un quelconque de ces facteurs et
bien d'autres sont susceptibles de faire de la réhabilitation et la modernisation d’un projet d'irrigation
une opération avantageuse et rentable.

Le processus de réhabilitation consiste en la rénovation ou la réparation des aménagements existants


en mauvais état et de ceux dont les performances ne répondent plus aux critères et besoins d'origine
du projet. Il inclut la modification des procédures opératoires, de la gestion et des aspects
institutionnels. L'objet de la réhabilitation est d'améliorer la situation économique et sociale des
usagers. Le processus inclut les modifications d'aménagements existants, de la gestion et des aspects
institutionnels. Les modifications sont conçues pour élever le niveau social et économique des
usagers et de la région.

Les principales conclusions du diagnostic réalisé sur le périmètre sont :

 La défaillance des infrastructures du périmètre : stations de pompages, canaux, drains et


pistes.

 La vétusté des aménagements,

 L’inondation saisonnière d’une partie du périmètre.

Les objectifs de réhabilitation doivent définir les dispositions techniques à apporter aux
infrastructures existantes d’une part et les actions à mettre en œuvre par le gestionnaire et l’exploitant
du périmètre pour une meilleure exploitation des infrastructures d’autre part.

La réhabilitation devra être suivie par un encadrement plus rapproché des irrigants et une bonne
intégration dans les cellules organisationnelles existantes.

Donc le projet de réhabilitation vise à rechercher des solutions techniquement fiables, durables et
adaptées aux conditions locales d’une part et économiquement acceptables en intégrant les coûts
d’entretien maîtrisables traduisant un coût du mètre cube d’eau à la portée des agriculteurs et assurant
une prise en charge de la gestion des infrastructures réhabilitées d’autre part.

Le projet de réhabilitation vise essentiellement :

 La remise en état de l’infrastructure hydraulique d’irrigation depuis la station de pompage


jusqu’aux parcelles ;

Groupement MCG / SAFI 81


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Le calage et reprofilage des canaux en terre ;

 La projection des nouveaux ouvrages de régulation de débit, des ouvrages de traversée et


des ponceaux sur le réseau d’irrigation ;

 La réhabilitation du système de drainage par le recalibrage des drains et l’installation des


ouvrages qui facilitent les écoulements des eaux vers la station d’exhaure ;

 L’amélioration du réseau de pistes ;

 Le nivellement et planage des parcelles hautes ;

 L’amélioration de la mise en valeur agricole ;

 Le renforcement des structures existantes de gestion et d’exploitation du périmètre.

5.1 DESCRIPTION DES TRAVAUX DE REHABILITATION


Les spécificités socio-économiques et techniques militent en faveur du choix des scénarios les plus
adaptés au contexte du périmètre et qui défavorisent toute solution hasardeuse pouvant induire des
effets négatifs.

Ainsi, la réhabilitation sera conçue en respectant :

 La vocation culturale du périmètre,

 Le mode d’irrigation,

 Le schéma hydraulique,

 Le type de réseau d’irrigation et de drainage,

 Le système de pompage.

 L’intégration des parcelles initialement hors aménagements (781 ha),

 Les aménagements connexes,

Le projet de réhabilitation vise à maîtriser les coûts d’investissement d’une part et de réduire les
pertes en eaux, sécuriser le système et améliorer le contrôle et l’exploitation du réseau d’autre part.

Ce projet consiste d’une part à introduire des actions de réhabilitation à un niveau de modernisation
qui peut être partielle ou totale et d’autre part à réaliser de nouveaux ouvrages de contrôle de la
distribution de l’eau pour améliorer la gestion et l’exploitation des réseaux. Cette amélioration
apporte une souplesse dans l’exploitation du réseau d’irrigation et l’organisation du tour d’eau.

Groupement MCG / SAFI 82


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

5.2 TRAVAUX TOPOGRAPHIQUES


Dans le cadre du projet du périmètre GDT, une étude topographique, suivant la méthodologie ci-
après a été menée pour la collecte des données nécessaires à l’aménagement attendu.

Méthodologie

5.2.1.1 Implantation et levé des bornes d’appui

 Les bornes implantées, servant d’ossature aux différents levés, sont de deux types :

- Les bornes principales d’appui (dénommées PP), de forme carrée et de dimensions


20x20x30cm,

- Les bornes secondaires d’appui (dénommées PS), de forme circulaire et de dimensions


20x20x30cm.

 Une tige de fer de diamètre 10 mm et de hauteur h=50cm, dépassant le niveau de la face


supérieure de chaque borne de 1 cm et qui occupe le milieu de celle-ci,

 Sur le béton de la face supérieure de chaque borne est gravé un numéro unique
d’identification.

Tableau n° 48 : Listing des bornes


Listing
X insertion Y insertion Z insertion Matricule X insertion Y insertion Z insertion
Matricule
B.1 384205.0 1802000.5 2.96 PS12 383499.6 1808284.3 2.67
B.2 384463.1 1802165.2 3.20 PS12R 383584.1 1807696.7 2.52
B.3 385130.2 1802664.5 1.12 PS13 383889.4 1807314.8 2.56
B.79 383595.8 1805378.5 1.57 PS14 384523.0 1807645.0 2.67
B14 382107.6 1804799.5 2.26 PS14R 384810.4 1807802.1 2.51
B78C 384286.2 1804810.6 4.84 PS15 385991.0 1808517.2 2.72
PP1 381214.5 1806341.7 2.59 PS16 383233.5 1806290.1 2.79
PP2 381305.4 1806214.5 2.72 PS17 384578.7 1806194.1 2.63
PP3 381993.1 1805811.4 2.67 PS18 385033.0 1806132.0 2.74
PS.1 385107.3 1802780.6 1.66 PS19 385550.3 1806696.9 2.64
PS.10 382121.1 1806809.7 2.77 PS20 386469.5 1807493.6 2.16
PS.11 382627.9 1807625.6 2.04 PS21 387253.0 1807678.9 2.15
PS.12 383499.6 1808284.3 2.67 PS22 383152.2 1805372.8 3.58
PS.13 383889.4 1807314.8 2.56 PS22R 383110.6 1804945.6 2.87
PS.14 384523.0 1807645.0 2.67 PS23 382917.2 1804539.2 2.82
PS.15 385991.0 1808517.2 2.72 PS24 383463.1 1804089.2 2.71
PS.16 383233.5 1806290.1 2.79 PS25 384322.4 1804051.1 2.61
PS.17 384578.7 1806194.1 2.63 PS26 385764.6 1804063.0 2.51
PS.18 385033.0 1806132.0 2.74 PS26R 385131.3 1804251.4 2.78
PS.19 385550.3 1806696.9 2.64 PS27 381393.7 1805900.9 2.75
PS.2 384506.5 1805262.5 2.74 PS27R 381233.5 1804957.9 2.52
PS.20 386469.5 1807493.6 2.16 PS28 380800.4 1804057.8 2.72
PS.21 387253.0 1807678.9 2.15 PS29 380653.7 1803225.0 2.37

Groupement MCG / SAFI 83


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Listing
X insertion Y insertion Z insertion Matricule X insertion Y insertion Z insertion
Matricule
PS.22 383152.2 1805372.8 3.58 PS30 380708.9 1802260.7 2.69
PS.23 382917.2 1804539.2 2.82 PS30R 380476.4 1802776.3 2.82
PS.24 383463.1 1804089.2 2.71 PS32 381920.4 1802266.4 2.49
PS.25 384322.4 1804051.1 2.61 PS32R 382105.8 1802134.0 2.47
PS.26 385764.6 1804063.0 2.51 PS33 382678.6 1801535.8 2.49
PS.27 381393.7 1805900.9 2.75 PS34 381585.3 1804193.2 1.82
PS.28 380800.4 1804057.8 2.72 PS36 382391.3 1806204.2 1.96
PS.29 380653.7 1803225.0 2.37 PS39 383169.7 1801588.7 2.32
PS.3 384172.2 1805363.1 1.99 PS4 387350.9 1806723.0 2.49
PS.30 380708.9 1802260.7 2.69 PS40 384388.3 1804419.4 3.33
PS.32 381920.4 1802266.4 2.49 PS41 385977.0 1805085.8 3.72
PS.33 382678.6 1801535.8 2.49 PS5 386920.7 1807936.2 2.28
PS.7 388019.0 1807337.1 3.04 PS6 384538.9 1806199.2 2.67
PS10 382121.1 1806809.7 2.77 PS8 381769.0 1804747.8 2.15
PS10R 382393.7 1807367.8 2.58 PS9 382898.2 1806578.9 1.91
PS11 382627.9 1807625.6 2.04
Les coordonnées des bornes de rattachements identifiés dans la zone du projet sont données par le
tableau suivant :

Tableau n° 49 : Bornes de rattachement


Borne X (m) Y(m) Z (m)
RRS2 068 378 672,489 18 010 259,99 2,128
LM1 377 175,506 1 800 271,591 2,116
SPNGE 372 936 1 800 504 1,355

Figure 9. Borne LM1 et RRS2 068

Groupement MCG / SAFI 84


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

L’implantation des bornes principales est effectuée le long du canal principal branché à la station de
pompage.

Les bornes secondaires sont, quant à elles, implantées le long des 4 canaux principaux et des drains
existants, en raison d’une borne par kilomètre.

La densité des bornes ainsi implantées est raisonnable pour les levés effectués au moyen des GPS
Différentiels et également pour d’autres opérations topographiques menées à l’aide d’une station
totale.

Les levés de toutes les bornes implantées sont effectués à l’aide d’un GPS différentiel, bi fréquence
Leica GS 10, de précision centimétrique, en mode de levé temps réel (RTK). Ces levés de bornes
sont rattachés, en coordonnées X, Y, et Z au repère RRS 065 du réseau géodésique du Sénégal, situé
à Ross Béthio.

5.2.1.2 Précision des levés

La précision absolue, obtenue pendant ces levés, est de 1.5 cm en planimétrie et 1cm en altimétrie.

5.2.1.3 Levé des canaux

Le réseau d’irrigation existant est composé de quatre canaux principaux C-1, C-2, C-3 et C-4
traversant tout le périmètre. Des canaux tertiaires aménagés et non aménagés, des drains principaux
et secondaires.

Les levés de ces éléments du réseau sont effectués en profil en long, en raison d’un profil en travers
tous les 50m, en tenant compte de la forme de chaque élément.

5.2.1.4 Levé des pistes

Le réseau de pistes est constitué des pistes principales et secondaires. Les pistes principales longeant
les canaux sont levés en même temps que ces derniers. Les pistes secondaires sont levées en profils
en travers en raison d’un profil tous les 50m.

5.2.1.5 Levé du terrain naturel

Les levés du relief du terrain naturel sont effectués à l’intérieur des parcelles, délimitées par les
divers éléments du réseau. Ces levés sont effectués dans les zones hors d’eau par quadrillage de
20x20m. Dans les zones couvertes par les eaux, les levés sont effectués par semis de points en
essayant d’avoir une densification suffisante de points permettant de mieux représenter le terrain. Ces
levés sont effectués à l’aide des GPS différentiels Leica GS10, avec une précision centimétrique en
mode temps réel et sont rattachés aux bornes d’appui secondaires.

Groupement MCG / SAFI 85


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

5.2.1.6 Difficultés rencontrées lors des levés :

Nous tenons à préciser que les levés ont été menés en période de campagne agricole. Le déplacement
des équipes topographiques dans les parcelles contenant les plans de riz repiqués était difficile en
évitant de les briser. Les zones basses, les canaux secondaires et le canal principal étaient totalement
inondés de sorte que les levés à ces niveaux étaient difficiles.

5.2.1.7 Traitement et compte rendu

Les résultats obtenus des levés sur le terrain ont permis d’établir un plan coté, où tous les réseaux et
pistes existants sont représentés. Des courbes de niveaux d’équidistance 0.25m sont filées sur
l’ensemble de la superficie relevée, donnant ainsi l’allure du relief du terrain naturel.

Les moyens utilisées

Les moyens déployés par le groupement sont composés de :

5.2.2.1.1 Moyens Humains


Un Ingénieur, Expert Géomètre, superviseur validant les résultats de terrain et la confection du plan
coté.

 Deux Techniciens topographes expérimentés en levés topographiques de grandes surfaces,

 Deux aides topographes.

5.2.2.1.2 Moyens Matériel


Le matériel utilisé pour venir à bout de cette prestation topographique est composé de :

 2 GPS différentiels Leica GS10, de précision centimétrique en mode RTK (mode temps
réel), et accessoires,

 Du petit matériel topographique nécessaire,

 2 véhicules tout terrain de liaison.

Conclusion

Tous les moyens déployés et le professionnalisme des équipes mises en place, ont permis d’exécuter
les travaux topographiques décrits ci-haut, dans les règles de l’art.

Groupement MCG / SAFI 86


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6. SCHEMA D’AMENAGEMENT HYDRAULIQUE

6.1 ORIENTATION CULTURALE ET BESOINS EN EAUX


L’orientation culturale retenue pour le périmètre GDT reste inchangée et correspond à l’orientation
initiale basée sur la riziculture.

Découpage du périmètre

Le découpage actuel du périmètre sera maintenu. Les différentes parcelles seront conservées. Ces
unités seront alimentées à partir de la station de pompage existante en tête du périmètre.

Mise en valeur

L'objectif principal du projet est d'exploiter d'une manière rationnelle toutes les ressources naturelles
et humaines de la zone et de valoriser en particulier les ressources en eau mobilisées.

La stratégie de développement agricole de périmètre doit tenir compte des considérations suivantes:

 La spécificité de la région,

 Les activités actuelles et l'assise technique développée dans la région,

 Les aptitudes culturales des sols,

 Les ressources en eaux mobilisables et les conditions climatiques.

Occupation future du sol et assolement

Conformément aux orientations de développement agricoles et aux résultats de l’étude pédologique


les spéculations retenues sont : le riz (Sahel 108) et quelques hectares de polyculture.

Superficie future du périmètre

La superficie future de la zone d’étude sera 3564 ha par l’extension du périmètre GDT (1783 ha)
d’une superficie de 781 ha

L’occupation future du périmètre est donnée dans le tableau suivant :

Tableau n° 50 : Superficie du périmètre GDT


Grande digue
Désignation Tellel (ha) Total (ha)
(ha)
Superficie de la zone 1806 2412 4218
Superficie de terrain inculte 135 283 418
Superficie actuellement irriguée 1262 1521 2783
Superficie d'extension 331 450 781
Superficie projet 1593 1971 3564

Groupement MCG / SAFI 87


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Système de desserte

Chaque quartier hydraulique sera alimenté par une main d’eau qui dessert les différentes parcelles.
Un tour d’eau sera pratiqué entre les différentes parcelles du même quartier hydraulique.

Groupement MCG / SAFI 88


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

4-Carte superficie actuelle et extension (A4)

Groupement MCG / SAFI 89


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Le cycle cultural

Le cycle cultural future de périmètre GDT sera de double compagne (saison sèche de Fév.- juin et autre humide de Aout- Nov.) avec un allongement de la
période de mise en boue afin de réduire le besoin de pointe.

Tableau n° 51 : Cycle cultural


Mois Janv. Fév. Mars Avril Mai Juin Juillet Août Sept Oct. Nov. Déc.
Riz saison sèche
chaude (1 ère
compagne)
Préparation de la
terre et mise en boue
Semis
Maintenance
Fertilisation
Conduite
Récolte
Riz saison des
pluies (2 éme
compagne)
Préparation de la
terre et mise en boue
Semis
Maintenance
Fertilisation
Conduite
Récolte
Polyculture

Groupement MCG / SAFI 90


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Besoins futur en eau

Le calcul des besoins en eau d'irrigation a été fait en suivant la démarche FAO adaptée aux
conditions climatiques et à l’efficience des réseaux après réhabilitations du périmètre GDT.

Les besoins en eau d’irrigation ont été établis sur la base des données et hypothèses suivantes :

 Données climatiques (évapotranspiration et précipitations) ;

 Pluie efficace : La quantité d’eau pluviale retenue dans la zone racinaire est nommée pluie
efficace et doit être déduite des besoins totaux en eau d’irrigation. Dans le cas présent, la
valeur de la pluie efficace est fixée à 80 % des précipitations ;

 Infiltration : base 3 mm par jour (résultat réel dans la zone du projet) ;

 Gestion de l'eau : 70 mm (profondeur de submersion) ;

 Saturation du sol : 120 mm (profondeur : 40 cm x porosités 30%) ;

 Efficience d’irrigation : sera à 70%.

6.1.3.1 Débit effectif

D’après le tableau de besoin futur en eau du périmètre à réhabiliter, il existe deux pointe de besoin en
eau

 2.8 l/s/h au mois de mars au cours de la mise en boue (débit projet pour le
dimensionnement des canaux et des ouvrages),

 2.1 l/s/ha au mois de mai au cours de la conduite culturale (débit projet pour le pompage).

6.1.3.2 Découpage des quartiers

Le découpage initial du périmètre GDT sera conservé avec des améliorations au niveau de certains
quartiers et surtout dans les zones d’extension.

6.1.3.3 Main d’eau

La main d’eau est le débit qui arrive à la tête de la parcelle et qui est maîtrisable par les irrigants de la
région. Les mains d’eau choisies sont proportionnelles à la superficie irriguée, elles varient entre 15
et 40 l/s

6.1.3.4 Dose d’irrigation

La dose théorique d’irrigation, valeur représentative de la réserve utile du sol, est déterminée en
fonction de la texture du sol et de la profondeur d’enracinement des cultures par la formule suivante :

Groupement MCG / SAFI 91


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Dose (m3 / ha)  2 ( H cc  H pfp ) . P . 103


3
Avec

 Hcc-Hpfp: le réserve utile (15%) ;

 P : la profondeur d’enracinement en (0.7 m);

La dose d'irrigation correspond à la quantité d'eau nécessaire à la satisfaction des besoins de culture
en eau. La dose d’irrigation a été estimée à 70 mm.

6.1.3.5 Durée d’irrigation et tour d’eau

(a) Durée d’irrigation


La détermination de la valeur de la dose d’irrigation pratiquée a permis de calculer les paramètres du
tour d’eau, la durée d’irrigation par hectare (DI) et la période de retour du tour d’eau (T):

Soit :

Dose
DI (h / ha ) 
M . 0,36
Avec

- DI : la durée d’irrigation en h/ha,

- D : la dose d’irrigation pratiquée en mm,

- M : la main d’eau en l/s,

(b) Tour D’eau d’irrigation


S . DI
T 
N
Avec

- T : période de retour en jours,

- S : superficie du quartier en ha,

- DI : durée d’irrigation en h/ha,

- N : Nombre d’heures d’irrigation par jour,

Les valeurs ainsi calculées seront retenues si la période est convenable pour les cultures et si la durée
d’irrigation au niveau des parcelles est suffisante pour une manipulation aisée de l’irrigation par les
agriculteurs.

En tenant compte des conditions climatiques de la région d’étude, les résultats de calcul pour les
différents paramètres d’irrigation sont donnés en annexe.

Groupement MCG / SAFI 92


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.1.3.6 Débit d’équipement

La superficie future du projet est 3564 ha, avec un débit spécifique de 2.1 l/s/ha, le débit nécessaire
en tête du réseau serait de 7500 l/s soit un débit supplémentaire nécessaire par rapport à celui fourni
actuellement par la station de pompage de 1500 l/s.

Le complément sera assuré :

- soit par la station de pompage réhabilitée

- soit par une alimentation gravitaire moyennant un chenal projeté.

6.2 ALIMENTATION PARTIELLE DU PERIMETRE GRAVITAIREMENT A PARTIR DU LAMPSAR

Description

Dans le but de favoriser le développement de la région et sous l'impulsion de l'OMVS, deux grands
barrages ont été réalisés : Manantali et Diama.

Le Lampsar est alimenté par le Gorom amont avec lequel il forme ce qu'on appelle l'axe Gorom -
Lampsar et qui constitue la principale voie d'eau du delta. L'axe s'étale sur une longueur de 95 km
jusqu'à Dakar Bango. Il est composé de trois biefs séparés par les ouvrages de Ross-Béthio et de
Ndiol. Le Lampsar a un tracé sinueux entre le barrage de Boundoum et le pont Demba. Il alimente le
Kassack aval et constitue à sa partie aval, avec le Djeuss et le Ngalam, la réserve de Saint-Louis.

Il présente une géométrie assez variable d'amont en aval : un très faible gabarit en amont (bief situé à
l’aval de Boundoum) et une largeur importante vers l'aval avec souvent des profondeurs assez faibles
et très enherbées.

Le Lampsar comprend plusieurs ouvrages d'amont à l'aval : Pont de Boundoum; Barrage de Ross-
Béthio; Barrage de Ndiol- Savoigne; Pont de Mboubène; Barrage de Bango.

Principale source d'eau d'irrigation et d'alimentation de la réserve de Saint-Louis, le Lampsar à


l'instar du Gorom doit voir sa capacité améliorée pour contribuer à terme à la satisfaction des besoins
totaux de la zone du bas-delta en eau

Le périmètre est alimenté par l’axe hydraulique de Lampsar situé dans le Delta du fleuve Sénégal.

Objectif

L’objectif essentiel est de fournir une partie des besoins du périmètre GDT en eau d’une façon
gravitaire pour minimiser le pompage et réduire les frais d’énergie.

Groupement MCG / SAFI 93


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Evaluation du niveau d’eau dans le fleuve

A partir de séries vérifiées tirées de la banque de données hydrométriques observées du fleuve


Sénégal, des séries de niveaux d’eau caractéristiques de crue sur presque 10 ans consécutifs (1997-
2009) sont établis pour les stations de Diama et Rosso.

L’analyse de la variation de niveau d’eau au niveau de fleuve entre les deux stations montre que le
niveau d’eau atteint 2.15 m pendant la saison d’hivernage et 1.93 m pendant la saison sèche.

3.50

3.00

2.50

2.00 Niveau moy


Niveau max
1.50
Niveau min
1.00

0.50

0.00

Figure 10. Niveau d'eau: Diama

Groupement MCG / SAFI 94


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

3.50

3.00

2.50

2.00 Niveau moy


Niveau max
1.50
Niveau min
1.00

0.50

0.00

Figure 11. Niveau d'eau: Rosso

Evaluation du niveau d’eau dans la station

Pour la détermination du niveau d’eau au point d’alimentation de la station ; bras de Lampsar ; une
interpolation linéaire a été faite en supposant que la pente est constante sur toute la longueur du bief
fleuve.

2.5
Lampsar
ST Diama ST Rosso
2
Niveau d'eau

H(m)
1.5
H max
1 Hmin

0.5

0
0 20 40 60 80 100 120
Distance (km)

Figure 12. Niveau d'eau au Lampsar

Groupement MCG / SAFI 95


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Le niveau d’eau moyen calculé au niveau de Lampsar est estimé à 2.16 m IGN.

Le niveau d’eau pendant la période sèche atteint 1.94 m IGN alors que pendant la période humide est
de 2.38 m IGN

D’après ces résultats nous pouvons conclure que le périmètre GDT peut être alimenté gravitairement
avec une lame d’eau variant de 0.93 à 1.15m au niveau de la station de pompage, ce niveau induit un
volume d’eau qui peut être exploité pour le remplissage des canaux principaux pendant la nuit et pour
diminuer les frais de pompage pendant les journées d’irrigation.

Le projet prévoit la création d’un dalot double de section 2(1.5x2m) et de longueur 45 m reliant relie
le chenal d’amené au canal principal permettant d’alimenter le périmètre gravitairement avec un débit
variant de 2000 à 3000 l/s

Groupement MCG / SAFI 96


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.3 REHABILITATION DU RESEAU D’IRRIGATION

Actions de réhabilitation retenues

Les actions prévues pour la réhabilitation du réseau d’irrigation sont les suivantes :

 Conservation du tracé des canaux d’ordre primaire et secondaires

 Calage des canaux d’irrigation en respectant les contraintes du projet : topographie, lame
d’eau, perte de charge régime d’écoulement, débit d’équipement et étude géotechnique,

 Création des nouveaux canaux d’ordre secondaire,

 Renouvellement de tous les ouvrages sur le réseau,

 Création des nouveaux ouvrages de régulation et de gestion du périmètre,

 L'établissement d'un système de régulation de fonctionnement du réseau d'irrigation,

 Revêtement d’une partie du canal principal C-1,

 Création de nouveaux ouvrages de traversées et de passage inférieur.

Superficie du projet

La surface irriguée envisagée passe des 2783 ha existants à 3564 ha avec l'addition de 781 ha. La
surface totale à aménager sera de 3648 ha, incluant la surface des infrastructures.

Tableau n° 52 : Superficie du projet


Désignation Grande Digue Tellel Totale -
Superficie actuellement irriguée 1262 1521 2783
Superficie d'extension 331 450 781
Superficie projet 1593 1971 3564

Superficie à irriguer par canal

6.3.3.1 Canaux d’ordre primaire

Le secteur Grande Digue est alimenté par les canaux principaux C-2 et C-4, alors que le secteur
Tellel est irrigué par les C-1 et C-3. Spécialement pour la zone d’extension, le canal principal C-1
existant sera prolongé de 3.6 km. La longueur totale des canaux principaux est de 32.07 rn. Le
tableau ci-après présente les superficies et les linéaires pour chaque canal.

Tableau n° 53 : Superficie à irriguer pour chaque canal principal


Canal Longueur (ml) Superficie (ha)
C-1 10172 1324
C-2 8218 860

Groupement MCG / SAFI 97


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Canal Longueur (ml) Superficie (ha)


C-3 6812 645
C-4 6868 735
6.3.3.2 Canaux d’ordre secondaire (canaux secondaire, tertiaires, quaternaires et
quinquénaires)

En général, le canal secondaire diverge du canal principal d’irrigation et le canal tertiaire fournit
l’eau directement aux champs de paddy. Cependant, il y a plusieurs canaux secondaires qui
fournissent l’eau directement aux parcelles, fonctionnant comme des canaux tertiaires. Aussi, des
canaux tertiaires fournissent l’eau à d'autres canaux tertiaires, fonctionnant comme des canaux
secondaires de même pour les canaux quaternaires. C'est pourquoi, il est difficile de faire la
différence entre eux, et donc cette notation sert uniquement à les distinguer.

Les tableaux ci-après présentent la superficie et le linéaire de chaque canal d’ordre secondaire ainsi
que l’ouvrage correspondant.

Tableau n° 54 : Superficie à irriguer pour chaque canal secondaire (C-1)


Ouvrage
Canal secondaire Linéaire (ml) Superficie (ha)
Modulé
M2/C1 C1.2 1660 16.12
M5/C1 C1.5 205 53.81
M5 bis/C1 C1.5 bis 225 20.20
M6/C1 C1.6 150 138.01
M8/C1 C1.8 530 178.76
M9/C1 C1.9 515 19.23
M10/C1 C1.10 105 14.97
M13/C1 C1.13 507 11.40
M14/C1 C1-14 695 37.83
M18/C1 C1.18 525 8.07
M19/C1 C1.19 940 13.84
M20/C1 C1.20 850 11.39

Tableau n° 55 : Superficie à irriguer pour chaque canal tertiaires (C-1)

Ouvrage modulé Canal tertiaire Linéaire (ml) Superficie (ha)


C1.1.1 375 10.99
M1
C1.1.2 550 10.45
C1.3.1 275 11.58
M3
C1.3.2 275 10.83
C1.4.1 390 11.05
M4 C1.4.2 315 7.96
C1.4.3 470 7.73
C1.5.1 1200 10.20
C1.5.2 160 6.05
T1
C1.5.3 140 6.42
C1.5.4 250 31.14
C1.5 bis-1 875 8.36
T4
C1.5 bis-2 1040 11.84
C1.6.2 178 67.36
T5
C1.6.1 540 70.64

Groupement MCG / SAFI 98


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage modulé Canal tertiaire Linéaire (ml) Superficie (ha)


C1.7.1 1550 17.33
C1.7.2 700 10.59
M7
C1.7.3 325 24.84
C1.7.4 900 9.94
T13 C1.8.1 590 154.92
C1.8.2 320 7.70
T12 C1.8.3 285 8.47
C1.8.4 400 7.67
C1.9.1 285 7.97
T22
C1.9.2 890 11.26
C1.10.1 290 8.42
T23
C1.10.2 730 6.55
C1.11.1 480 7.83
M11 C1.11.2 220 8.05
C1.11.3 450 7.84
C1.12.1 695 7.02
M12 C1.12.2 660 40.98
C1.12.3 301 30.53
T28 C1.14.1 180 13.23
C1.14.2 100 11.61
T29
C1.14.3 650 12.99
C1.15.1 220 7.63
M15 C1.15.2 1380 90.42
C1.15.3 520 13.12
C1.16.1 250 43.73
M16
C1.16.2 860 10.39
C1.17.1 375 10.28
M17
C1.17.2 695 61.36
C1.21.1 1100 10.92
C1.21.2 840 22.96
M21
C1.21.3 530 36.55
C1.21.4 595 10.29
C1.22.1 330 27.94
M22 C1.22.2 830 96.73
C1.22.3 855 13.36
C1.23.1 700 95.29
M23
C1.23.2 715 16.49

Tableau n° 56 : Superficie à irriguer pour chaque canal quaternaire (C-1)


Ouvrage Canal Linéaire Superficie
modulé quaternaire (ml) (ha)
C1.5.4.1 220 24.38
T2
C1.5.4.2 965 6.76
C1.6.2.1 265 13.84
T6 C1.6.2.2 590 43.59
C1.6.2.3 300 9.93
C1.6.1.1 260 4.13
C1.6.1.2 280 25.67
T8
C1.6.1.3 217 9.54
C1.6.1.4 425 31.31
C1.7.2.1 270 13.48
T11
C1.7.2.2 575 11.36
T14 C1.8.1.1 480 62.21
T18 C1.8.1.2 453 13.82

Groupement MCG / SAFI 99


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire Superficie


modulé quaternaire (ml) (ha)
C1.8.1.3 560 14.70
C1.8.1.4 450 12.45
C1.8.1.5 830 51.74
T24 C1.12.2.1 390 7.34
T25 C1.12.2.2 515 10.28
C1.12.2.3 600 9.96
T26
C1.12.2.4 755 13.40
C1.12.3.1 545 15.57
T27
C1.12.3.2 960 14.96
T30 C1.15.2.1 281 9.35
C1.15.2.2 385 12.95
T31
C1.15.2.3 330 9.65
C1.15.2.4 340 41.14
T32 C1.15.2.5 1410 11.44
C1.15.2.6 370 15.24
T35 C1.16.1.1 860 11.71
C1.16.1.2 1070 13.71
T36
C1.16.1.3 1160 18.31
T37 C1.17.2.1 264 8.92
T38 C1.17.2.2 490 12.59
C1.17.2.3 1010 11.63
T39 C1.17.2.4 350 19.07
C1.17.2.5 230 9.15
C1.21.2.1 505 14.10
T41
C1.21.2.2 605 8.86
T42 C1.21.3.1 480 10.28
T43 C1.21.3.2 440 10.41
C1.21.3.3 430 8.38
T44
C1.21.3.4 530 7.47
C1.22.1.1 405 15.41
T45
C1.22.1.2 405 12.54
T46 C1.22.2.1 800 14.24
T47 C1.22.2.2 770 9.78
T48 C1.22.2.3 315 27.78
C1.22.2.4 650 8.46
T49
C1.22.2.5 620 7.88
C1.22.2.6 595 8.35
T50 C1.22.2.7 490 10.61
C1.22.2.8 750 9.63
T53 C1.23.1.1 620 10.83
T54 C1.23.1.2 720 17.80
C1.23.1.3 615 14.00
C1.23.1.4 615 16.88
T55
C1.23.1.5 318 25.38
C1.23.1.6 850 10.39

Tableau n° 57 : Superficie à irriguer pour chaque canal quinquénaires (C-1)


Ouvrage Canal Linéaire Superficie
modulé quinquénaires (ml) (ha)
C1.5.4.1.1 185 7.47
T3 C1.5.4.1.2 250 10.28
C1.5.4.1.3 600. 6.64
C1.6.2.2.1 302 13.45
T7
C1.6.2.2.2 730 9.69

Groupement MCG / SAFI 100


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire Superficie


modulé quinquénaires (ml) (ha)
C1.6.2.2.3 305 11.21
C1.6.2.2.4 115 9.24
C1.6.1.2.1 460 12.99
T9
C1.6.1.2.2 510 12.68
C1.6.1.4.1 460 15.32
T10
C1.6.1.4.2 410 15.98
T15 C1.8.1.1.1 575 7.99
T16 C1.8.1.1.2 513 15.66
C1.8.1.1.3 440 10.16
C1.8.1.1.4 845 10.90
T17
C1.8.1.1.5 425 10.08
C1.8.1.1.6 610 7.43
C1.8.1.3.1 250 6.06
T21
C1.8.1.3.2 252 8.64
C.1.8.1.5.1 200 10.78
T19
C.1.8.1.5.2 590 17.70
C.1.8.1.5.3 265 11.86
T20
C.1.8.1.5.4 425 11.39
T33 C1.15.2.4.1 660 10.58
C1.15.2.4.2 600 16.18
T34
C1.15.2.4.3 800 14.38
C1.17.2.4.1 330 7.31
T40
C1.17.2.4.2 480 11.76
T51 C1.22.2.3.1 430 9.16
C1.22.2.3.2 405 8.75
T52
C1.22.2.3.3 650 9.87
T56 C1.23.1.5.1 440 8.72
C1.23.1.5.2 450 8.69
T57
C1.23.1.5.3 650 7.97

Tableau n° 58 : Superficie à irriguer pour chaque canal secondaire (C-3)


Ouvrage Canal Linéaire Superficie
Modulé secondaire (ml) (ha)
M1/C3 C3.1 380 13.61
M5/C3 C3.5 510 6.28
M10/C3 C3.10 700 120.23
M11/C3 C3.11 1100 15.95
M13/C3 C3.13 480 17.67
M15/C3 C3.15 310 9.67
M17/C3 C3.17 460 18.88
M18/C3 C3.18 300 12.78

Tableau n° 59 : Superficie à irriguer pour chaque canal tertiaire (C-3)


Ouvrage Canal Linéaire Superficie
Modulé tertiaire (ml) (ha)
C3.2.1 460 12.83
M2 C3.2.2 640 11.27
C3.2.3 440 13.31
C3.3.1 660 12.64
M3
C3.3.2 1050 15.82
C3.4.1 270 8.48
M4 C3.4.2 325 14.32
C3.4.3 250 8.56

Groupement MCG / SAFI 101


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire Superficie


Modulé tertiaire (ml) (ha)
C3.6.1 345 11.10
M6 C3.6.2 305 19.23
C3.6.3 310 11.09
C3.7.1 670 11.15
M7 C3.7.2 920 11.07
C3.7.3 600 11.77
C3.8.1 520 12.92
M8
C3.8.2 490 12.42
C3.9.1 390 11.97
M9
C3.9.2 380 11.56
T60 C3.10.1 510 12.17
T61 C3.10.2 1480 10.25
T62 C3.10.3 550 10.32
T63 C3.10.4 430 30.89
C3.10.5 360 40.63
T64
C3.10.6 1430 15.96
C3.12.1 365 10.93
M12
C3.12.2 365 8.95
C3.14.1 460 10.73
M14 C3.14.2 485 43.51
C3.14.3 250 12.86
C3.16.1 290 10.44
M16
C3.16.2 115 5.63
C3.17.1 270 13.23
T69
C3.17.2 180 5.65
C3.19.1 830 46.47
M19
C3.19.2 120 58.46

Tableau n° 60 : Superficie à irriguer pour chaque canal quaternaire (C-3)


Ouvrage Canal Linéaire Superficie
modulé quaternaire (ml) (ha)
C3.4.2.1 275 7.44
T58
C3.4.2.2 260 6.88
C3.6.2.1 325 9.86
T59
C3.6.2.2 325 9.37
C3.10.4.1 164 15.17
T65
C3.10.4.2 890 15.72
T66 C3.10.5.1 535 13.66
C3.10.5.2 960 14.67
T67
C3.10.5.3 850 12.30
C3.14.2.1 300 10.59
C3.14.2.2 305 10.79
T68
C3.14.2.3 490 11.97
C3.14.2.4 405 10.16
C3.19.1.1 330 12.23
C3.19.1.2 445 12.78
T70
C3.19.1.3 680 15.14
C3.19.1.4 370 6.33
C3.19.2.1 375 14.09
T71 C3.19.2.2 470 30.64
C3.19.2.3 295 13.72

Tableau n° 61 : Superficie à irriguer pour chaque canal quinquénaire (C-3)

Groupement MCG / SAFI 102


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire


Superficie (ha)
modulé quinquénaire (ml)
C3.19.2.2.1 240 15.80
T72
C3.19.2.2.2 385 14.84

Tableau n° 62 : Superficie à irriguer pour chaque canal secondaire (C-2)


Ouvrage Canal Linéaire
Superficie (ha)
Modulé secondaire (ml)
M1/C2 C2.1 120 21.42
M6/C2 C2.6 172 51.19
M8/C2 C2.8 269 8.92
M9/C2 C2.9 429 7.09
M11/C2 C2.11 266 10.62
M13/C2 C2.13 231 151.89
M15/C2 C2.15 628 87.61
M18/2 C2.18 1073 12.36

Tableau n° 63 : Superficie à irriguer pour chaque canal tertiaire (C-2)


Ouvrage Canal Linéaire
Superficie (ha)
modulé tertiaire (ml)
C 2.1-1 402 9.74
G1
C 2.1-2 1061 11.68
C2.2.1 468 7.12
M2 C2.2.2 314 4.34
C2.2.3 471 9.20
C 2.3.1 210 8.99
M3 C 2.3.2 296 15.58
C 2.3.3 197 9.76
C 2.4.1 356 12.24
M4 C 2.4.2 363 14.61
C 2.4.3 445 27.40
C 2.5.1 251 10.41
M5 C 2.5.2 662 10.17
C 2.5.3 391 9.34
C2.6.1 1558 45.39
G4
C2.6.2 369 5.80
C2.7.1 471 13.46
M7
C2.7.2 240 4.61
C2.10.1 613 8.49
M10
C2.10.2 161 8.94
C 2.12.1 125 12.03
M12 C 2.12.2 332 14.48
C 2.12.3 197 9.08
C 2.13.1 1916 87.99
G12
C2.13.2 1176 63.90
C 2.14.1 203 8.82
M17 C 2.14.2 276 17.83
C 2.14.3 179 8.88
G31 C 2.15.1 490 11.19
C 2.15.2 404 8.90
G32
C 2.15.3 457 8.83
G33 C 2.15.4 747 6.89
G34 C 2.15.5 736 7.18
G35 C 2.15.6 647 21.34
G38 C 2.15.7 643 11.76

Groupement MCG / SAFI 103


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire


Superficie (ha)
modulé tertiaire (ml)
C 2.15.8 894 11.52
C 2.16.1 174 8.74
M16 C 2.16.2 269 18.00
C 2.16.3 174 8.76
C 2.17.1 568 56.02
M17 C 2.17.2 622 67.93
C 2.17.3 407 12.40
C 2.19.1 902. 73.63
M19
C 2.19.2 982 9.54

Tableau n° 64 : Superficie à irriguer pour chaque canal quaternaire (C-2)


Ouvrage Canal Linéaire
Superficie (ha)
modulé quaternaire (ml)
C 2.3.2.1 192 7.29
G2
C 2.3.2.2 204 8.29
C 2.4.3.1 344 14.02
G3
C 2.4.3.2 344 13.38
G5 C 2.6.1.1 133 5.93
G6 C 2.6.1.2 520 6.55
G7 C 2.6.1.3 466 7.23
G8 C 2.6.1.4 448 7.46
G9 C 2.6.1.5 455 6.93
C 2.6.1.6 410 6.31
G10
C 2.6.1.7 512 4.97
C 2.12.2.1 186 7.34
G11
C 2.12.2.2 182 7.14
G13 C 2.13.1.1 499 10.39
G14 C 2.13.1.2 350 10.45
G15 C 2.13.1.3 383 10.04
G16 C 2.13.1.4 194 6.56
G17 C 2.13.1.5 231 9.43
G18 C 2.13.1.6 159 8.40
G19 C 2.13.1.7 963 7.61
G20 C 2.13.1.8 80 6.20
C 2.13.1.9 263 10.11
G21
C 2.13.1.10 566 8.80
G22 C 2.13.2.1 275 26.06
G26 C 2.13.2.2 94 15.19
G28 C 2.13.2.3 244 9.51
C 2.13.2.4 250 6.66
G29
C 2.13.2.5 480 6.48
C 2.14.2.1 179 8.77
G30
C 2.14.2.2 179 9.06
G36 C 2.15.6.1 276 6.64
C 2.15.6.2 311 7.69
G37
C 2.15.6.3 308. 7.01
C 2.16.2.1 194 9.18
G39
C 2.16.2.2 192 8.82
C 2.17.1.1 275 11.17
C 2.17.1.2 287 11.90
G41
C 2.17.1.3 385 21.47
C 2.17.1.4 345. 11.48
G42 C 2.17.2.1 514. 14.62
G43 C 2.17.2.2 1005 17.50

Groupement MCG / SAFI 104


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire


Superficie (ha)
modulé quaternaire (ml)
G44 C 2.17.2.3 545 9.77
C 2.17.2.4 516 12.41
G45
C 2.17.2.5 791 13.63
G46 C 2.19.1.1 805 15.40
G47 C 2.19.1.2 514 12.00
G48 C 2.19.1.3 735 8.14
G49 C 2.19.1.4 778 5.51
G50 C 2.19.1.5 791 8.04
G51 C 2.19.1.6 799 7.33
C 2.19.1.7 817 7.90
G52
C 2.19.1.8 656 9.30

Tableau n° 65 : Superficie à irriguer pour chaque canal quinquénaire (C-2)


Ouvrage Canal Linéaire
Superficie (ha)
modulé quinquénaire (ml)
G23 C 2.13.2.1.1 746 7.33
G24 C 2.13.2.1.2 746 6.08
C 2.13.2.1.3 724 6.05
G25
C 2.13.2.1.4 814 6.60
C 2.13.2.2.1 393 6.99
G27
C 2.13.2.2.2 687 8.20
C 2.17.1.3.1 160 10.77
G40
C 2.17.1.3.2 322 10.70

Tableau n° 66 : Superficie à irriguer pour chaque canal secondaire (C-4)


Ouvrage Canal Linéaire
Superficie (ha)
Modulé secondaire (ml)
M3/C4 C4.3 276 16.90
M8/C4 C 4-8 725 41.75
M9/C4 C4-9 501 30.70
M12/C4 C4-12 912 48.51
M14/C4 C4-14 342 22.77
M17/C4 C4-17 655 36.70
M18/C4 C4-18 947 50.24

Tableau n° 67 : Superficie à irriguer pour chaque canal tertiaire (C-4)


Ouvrage Linéaire
Canal tertiaire Superficie (ha)
Modulé (ml)
C 4-1-1 724 7.23
M1
C 4-1-2 577 6.48
C 4-2-1 312 6.09
M2
C 4-2-2 310 7.02
C4.3.1 404 9.02
G53
C4.3.2 223 7.88
C4.4.1 361 20.97
M4 C4.4.2 281 40.61
C4.4.3 1122 20.11
C 4-5-1 290 6.67
M5
C 4-5-2 330 7.69
C 4-6-1 445 6.04
C 4-6-2 435 8.43
M6
C 4-6-3 190 7.96
C 4-6-4 519 10.42

Groupement MCG / SAFI 105


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Linéaire
Canal tertiaire Superficie (ha)
Modulé (ml)
C 4-7-1 195 7.61
M7 C 4-7-2 256 7.49
C 4-7-3 418 7.50
G58 C4-8-1 470 8.17
G59 C4-8-2 791 8.71
C4-8-3 467 11.57
G60
C4-8-4 596 13.30
G61 C4-9-1 505 11.65
C4-9-2 488 9.88
G62
C4-9-3 636 9.17
C4-10-1 840 17.50
M10
C4-10-2 441 37.17
C4-11-1 355 7.28
M11
C4-11-2 359 7.32
G67 C 4-12-1 351 8.90
G68 C 4-12-2 314 5.84
G69 C 4-12-3 390 7.83
G70 C 4-12-4 394 7.88
C 4-12-5 399 7.84
G71
C 4-12-6 565 10.22
C4-13-1 442 22.42
C4-13-2 322 9.10
M13
C4-13-3 418 13.93
C4-13-4 453 20.38
G74 C4-14-1 437 7.30
C4-14-2 586 9.57
G75
C4-14-3 844 5.89
C4-15-1 217 7.96
M15
C4-15-2 342 7.99
C4-16-1 190 9.14
M16
C4-16-2 337 8.85
C 4-17-1 213 4.36
G76
C 4-17-2 134 7.18
G77 C 4-17-3 300 7.02
C 4-17-4 501 9.13
G78
C 4-17-5 750 9.01
C 4-18-1 179 6.85
G79
C 4-18-2 284 9.81
G80 C 4-18-3 375 7.71
G81 C 4-18-4 261 6.20
C 4-18-5 371 9.40
G82
C 4-18-6 607 10.26
C 4.19-1 382 10.59
M19 C 4.19-2 1062 80.69
C 4.19-3 748 54.58

Tableau n° 68 : Superficie à irriguer pour chaque canal quaternaire (C-4)


Ouvrage Canal Linéaire
Superficie (ha)
modulé quaternaire (ml)
C 4-4-1-1 1126 8.94
G54
C 4-4-1-2 1103 12.03
G55 C 4-4-2-1 1131 6.64
G56 C 4-4-2-2 1087 11.22
G57 C 4-4-2-3 1152 11.90

Groupement MCG / SAFI 106


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage Canal Linéaire


Superficie (ha)
modulé quaternaire (ml)
C 4-4-2-4 1125 10.85
G63 C4-10-2-1 848 7.61
G64 C4-10-2-2 865 7.56
G65 C4-10-2-3 842 6.76
C4-10-2-4 625 6.90
G66
C4-10-2-5 764 8.33
C 4-13-1-1 307 11.78
G72
C 4-13-1-2 306 10.65
C4-13-4-1 258 10.17
G73
C4-13-4-2 385 10.21
G83 C 4.19-2-1 591 10.18
G84 C 4.19-2-2 598 8.90
G85 C 4.19-2-3 549 7.87
G86 C 4.19-2-4 703 9.61
G87 C 4.19-2-5 743 12.99
G88 C 4.19-2-6 606 12.03
C 4.19-2-7 451 10.44
G89
C 4.19-2-8 654 8.67
G90 C 4.19-3-1 610 20.97
G94 C 4.19-3-2 420 7.56
C 4.19-3-3 388 12.67
G95
C 4.19-3-4 294 13.38

Tableau n° 69 : Superficie à irriguer pour chaque canal quinquénaire (C-4)


Ouvrage Canal Linéaire
Superficie (ha)
modulé quinquénaire (ml)
G91 C 4.19-3-1-1 420 9.40
G92 C 4.19-3-1-2 234 7.44
G93 C 4.19-3-1-3 236 4.12

Groupement MCG / SAFI 107


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

5-Schéma-irrigation-1 (A3)

Groupement MCG / SAFI 108


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6-Schéma-irrigation-1 (A3)

Groupement MCG / SAFI 109


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Débit du projet

Le débit unitaire du projet est de 2.8 l/s/ha, ce débit est utilisé pour dimensionner les canaux et les
ouvrages. Le débit à délivrer par chaque bief de canal est déterminé par la méthode de sommation des
débits de l’aval vers l’amont. Toutefois, les canaux ont été dimensionnés pour des débits supérieurs
afin de tenir compte du débit maximal délivré par la station de pompage.

Calage du réseau d’irrigation

6.3.2.1 Pente de calage

La pente longitudinale du canal est fixée en prenant en compte les critères d'étude de la SAED, et du
résultat de l’étude topographique effectuée dans le cadre de ce projet, le tableau ci-après présente les
pentes longitudinales utilisées pour le calage et le dimensionnement du réseau d’irrigation.

Tableau n° 70 : Pentes longitudinales des canaux


Canal Pente
Canaux principaux 0,01 ‰
Canaux secondaires, tertiaires, quaternaires et
1‰
quinquénaires
6.3.2.2 Perte de charge

Les pertes de charge dans les canaux doivent être prises en compte pour la conception de ces canaux

(a) Pertes de charge dans les canaux


Les pertes de charge des canaux ouverts tels que les canaux en terre et les principaux ouvrages de
franchissement en béton sont calculées par la formule suivante qui utilise la pente longitudinale du
canal.

∆𝐻 = 𝐿 × 𝑖

Avec

 ∆H : Perte de charge du canal (rn),

 L: Longueur du canal ouvert (rn),

 i: Pente longitudinal du canal (m/m).

Groupement MCG / SAFI 110


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

(b) Pertes de charge dans les ouvrages


Le tableau suivant présente les formules utilisées pour l’estimation de perte de charge dans les
ouvrages :

Tableau n° 71 : Perte de charge dans les ouvrages

Nom technique Schéma général de l’ouvrage Formule

Ouvrage de ∆𝐻 = 0.056 × (𝑉2 2 − 𝑉1 2 )


transition Avec
V1 et V2 : vitesse amont et aval

2 1−𝐾 2
∆𝐻 = 𝑉 ⁄2𝑔 ( )
𝐾
Ouvrage Avec
partiteur K : le rapport de la section
étranglée et la section mouillée
normal

Selon le type du module X ou


Ouvrage
XX la perte de charge est
modulé
variable de 6.5 à 11 cm

Groupement MCG / SAFI 111


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Nom technique Schéma général de l’ouvrage Formule

(𝑉2 2 − 𝑉1 2 )
∆𝐻 = 𝑓 × ⁄ + 𝑖𝐿
2𝑔
f: Coefficient de perte de
charge pour un rétrécissement
Ouvrage de V1 et V2 : vitesse amont et
traversée aval
i : Gradient hydraulique moyen
de la transition

2 1−𝐾 2
∆𝐻 = 𝑉 ⁄2𝑔 ( )
𝐾
Ouvrage de Avec
sectionnement K : le rapport de la section
étranglée et la section mouillée
normal

6.3.2.3 Calage de plan d’eau

Le niveau d'eau à la sortie de la station de pompage (Niveau d’eau calculé pour le point de départ du
canal principal C-1) est déterminé sur la base du niveau de la parcelle au point terminal, de la lame
d'eau et des pertes de charge :

 Elévation de la parcelle (plus haute),

 Lame d'eau minimale au niveau de parcelle,

 Perte de charge totale jusqu'au point terminal.

6.3.2.4 Profil en long

Les profils en long des canaux principaux d'irrigation sont illustrés dans l’annexe et le dossier plan.
Ils sont basés sur ce qui suit :

 Niveau d’eau (plan de charge) au point de départ : cote radier + lame d’eau,

 Cote de calage (du fond de canal),

 Pertes de charge linéaires= Longueur x Pente,

 Perte de charge au niveau des ouvrages.

Groupement MCG / SAFI 112


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 72 : Calage du canal principal C-1


Distance Section projetée Perte de charge
Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

1 P1 TR-1 0.0 0.0 Béton 0.001% 1.5 2.6 0.3 0.0 0.1 0.1 1.0 3.5 3.5
2 P2 21.4 21.4 Béton 0.001% 1.5 2.6 0.3 0.0 0.0 1.0 3.5 3.5
3 P3 66.7 88.1 Béton 0.001% 1.5 2.6 0.3 0.0 0.0 1.0 3.5 3.5
D1/C1+VC-
4 P4 52.9 141.0 Béton 0.001% 1.5 2.6 0.3 0.0 0.1 0.1 1.0 3.4 3.5
1
5 P5 17.9 158.8 Béton 0.001% 1.5 2.2 0.3 0.0 0.0 1.0 3.4 3.5
6 P6 17.6 176.4 Béton 0.001% 1.5 2.2 0.3 0.0 0.0 1.0 3.4 3.5
7 P7 97.0 273.4 Béton 0.001% 1.5 2.2 0.3 0.0 0.0 1.0 3.4 3.5
D2/C1+VC-
8 P8 97.8 371.1 Béton 0.001% 1.5 2.2 0.3 0.0 0.1 0.1 1.0 3.3 3.5
S1 2
9 P9 31.3 402.4 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
10 P10 98.6 501.0 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
11 P11 102.5 603.5 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
12 P12 99.7 703.2 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
13 P13 86.8 790.0 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
14 P14 86.4 876.4 Béton 0.001% 1.5 1.9 0.3 0.0 0.0 1.0 3.3 3.5
15 P15 D-1 51.7 928.1 Béton 0.001% 1.5 1.9 0.3 0.0 0.1 0.1 1.0 3.3 3.5
D3/C1+VC-
16 P16 17.0 945.1 en terre 0.001% 1.5 1.9 0.3 0.0 0.1 0.1 1.0 3.2 3.5
3
17 P17 24.2 969.3 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
18 P18 M1/C1 87.5 1056.7 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
19 S2 P19 104.2 1161.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
20 P20 98.7 1259.6 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
21 P21 M2/C1 34.3 1293.9 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5

Groupement MCG / SAFI 113


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

22 P22 36.3 1330.1 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
23 P23 95.9 1426.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
24 P24 99.4 1525.4 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.2 3.5
25 P25 M3/C1 94.9 1620.3 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
26 P26 93.1 1713.5 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
27 P27 99.1 1812.6 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
28 P28 93.4 1906.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
29 P29 49.1 1955.1 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
30 P30 109.3 2064.4 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
31 P31 96.5 2160.9 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
32 P32 93.7 2254.6 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
33 P33 15.2 2269.8 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
34 P34 16.4 2286.1 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
35 P35 M4/C1 61.7 2347.8 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
36 P36 33.0 2380.9 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
37 P37 M5/C1 40.2 2421.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 1.0 3.1 3.5
38 P38 59.9 2480.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
39 P39 96.2 2577.1 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
40 P40 M5 bis/C1 69.8 2646.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
41 P41 103.2 2750.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
42 P42 96.1 2846.1 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
43 P43 97.3 2943.4 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
44 P44 94.3 3037.7 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
45 P45 66.1 3103.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5

Groupement MCG / SAFI 114


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

46 P46 M6/C1 11.2 3115.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
47 P47 13.0 3128.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
48 P48 D-2 16.3 3144.3 en terre 0.001% 1.5 2.4 0.1 0.0 0.1 0.1 1.0 3.1 3.5
49 P49 97.5 3241.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
50 P50 89.4 3331.3 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
51 P51 91.5 3422.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
52 P52 99.0 3521.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
S3
53 P53 M7/C1 59.7 3581.6 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
54 P54 41.0 3622.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.1 3.5
55 P55 83.8 3706.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.1 3.5
56 P56 104.6 3811.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.1 3.5
57 P57 24.5 3835.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.1 3.5
58 P58 M8/C1 10.5 3846.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.1 3.5
59 P59 11.4 3857.4 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
60 P60 54.6 3912.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
61 P61 M9/C1 11.2 3923.2 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
62 P62 16.6 3939.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
63 P63 97.9 4037.7 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.1 3.5
64 S4 P64 97.1 4134.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.0 3.5
65 P65 94.0 4228.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.0 3.5
66 P66 99.4 4328.2 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.0 3.5
67 P67 49.9 4378.2 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.0 3.5
68 P68 M10/C1 19.4 4397.5 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 1.0 3.0 3.5
69 P69 47.3 4444.9 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5

Groupement MCG / SAFI 115


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

70 P70 48.7 4493.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5
71 P71 M11/C1 99.9 4593.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5
72 P72 90.2 4683.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5
73 P73 90.4 4774.1 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5
74 P74 19.8 4794.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 3.0 3.5
75 P75 OF-1 12.6 4806.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.1 0.1 1.0 2.9 3.5
76 P76 8.4 4815.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 2.9 3.5
77 P77 15.9 4830.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 2.9 3.5
78 P78 32.3 4863.1 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 2.9 3.5
79 P79 23.0 4886.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 2.9 3.5
80 P80 36.2 4922.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 1.0 2.9 3.5
81 P81 80.9 5003.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
82 P82 24.0 5027.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
83 P83 92.8 5120.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
84 P84 105.8 5225.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
85 P85 M12/C1 102.8 5328.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
86 P86 23.0 5351.6 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
87 P87 M13/C1 29.9 5381.5 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
88 P88 M14/C1 93.1 5474.5 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
89 P89 96.8 5571.3 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 2.9 3.4
90 P90 105.0 5676.4 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 2.9 3.4
91 P91 M15/C1 73.1 5749.5 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 2.9 3.4
92 P92 30.8 5780.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4
S5
93 P93 M16/C1 99.3 5879.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 2.9 3.4

Groupement MCG / SAFI 116


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

94 P94 106.7 5986.1 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
95 P95 92.7 6078.8 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
96 P96 101.6 6180.4 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
97 P97 99.3 6279.7 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
98 P98 M17/C1 76.5 6356.2 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 2.9 3.4
99 P99 M18/C1 22.7 6379.0 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
100 P100 29.9 6408.9 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
101 P101 69.0 6477.8 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
102 P102 58.3 6536.2 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
103 P103 35.4 6571.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
104 P104 7.0 6578.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
105 P105 8.7 6587.3 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
106 P106 M19/C1 17.6 6604.9 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
107 P107 62.7 6667.6 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
108 P108 M20/C1 23.0 6690.6 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 2.9 3.4
109 P109 23.0 6713.6 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 2.9 3.4
110 P110 57.7 6771.3 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 2.9 3.4
111 P111 23.2 6794.4 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 2.9 3.4
112 P112 M21/C1 106.7 6901.1 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 2.9 3.4
113 P113 25.5 6926.5 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
114 P114 49.5 6976.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
115 P115 51.3 7027.4 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
116 P116 56.8 7084.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
117 P117 53.2 7137.4 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4

Groupement MCG / SAFI 117


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

118 P118 58.6 7196.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
119 P119 69.0 7265.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
120 P120 58.0 7323.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
121 P121 61.2 7384.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
122 P122 57.9 7442.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
123 P123 59.1 7501.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
124 P124 55.4 7556.6 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
125 P125 39.7 7596.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
126 P126 52.7 7649.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
127 P127 12.1 7661.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
128 P128 53.3 7714.5 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
129 P129 29.4 7743.9 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
130 P130 29.2 7773.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
131 P131 29.7 7802.8 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
132 P132 41.5 7844.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
133 P133 40.6 7884.9 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
134 P134 44.4 7929.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
135 P135 52.3 7981.6 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
136 P136 52.5 8034.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
137 P137 38.4 8072.5 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
138 P138 57.9 8130.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
139 P139 46.8 8177.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
140 P140 53.5 8230.7 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
141 P141 49.2 8279.8 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4

Groupement MCG / SAFI 118


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) plafond (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

142 P142 53.2 8333.0 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
143 P143 48.6 8381.6 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
144 P144 54.4 8436.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
145 P145 47.1 8483.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
146 P146 52.9 8536.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
147 P147 44.2 8580.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
148 P148 19.0 8599.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
149 P149 2.8 8602.1 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
150 P150 3.3 8605.4 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
151 P151 M22/C1 16.8 8622.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 2.9 3.4
152 P152 12.6 8634.8 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.9 3.4
153 P153 132.5 8767.3 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.9 3.4
154 P154 137.1 8904.4 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.9 3.4
155 P155 248.4 9152.8 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
156 P156 149.7 9302.5 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
157 P157 112.9 9415.4 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
158 P158 141.2 9556.6 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
159 P159 131.8 9688.4 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
160 P160 144.0 9832.4 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
161 P161 110.3 9942.7 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
162 P162 157.1 10099.7 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
163 P163 63.3 10163.0 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4
164 P164 M23/C1 9.3 10172.3 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 2.8 3.4

Groupement MCG / SAFI 119


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 73 : Calage du canal principal C-2


Distance Section projetée Perte de charge
Cote fond Cote Yn Cote plafond
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)
1 P1 D1/C1 0.0 0.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.1 0.1 1.0 3.3 3.5
2 P2 113.7 113.7 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
3 P3 M1/C2 18.2 131.8 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
4 P4 79.1 211.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
5 P5 90.3 301.3 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
6 P6 95.1 396.4 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
7 P7 91.7 488.0 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
8 P8 95.8 583.8 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
9 P9 M2/C2 40.3 624.1 en terre 0.001% 1.5 2.5 0.1 0.0 0.0 0.9 3.3 3.4
10 P10 26.4 650.6 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
11 P11 95.2 745.8 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
12 S1 P12 97.8 843.6 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
13 P13 96.5 940.1 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
14 P14 92.3 1032.4 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
15 P15 M3/C2 42.6 1075.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
16 P16 65.1 1140.1 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
17 P17 100.9 1240.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
18 P18 98.0 1339.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
19 P19 96.5 1435.4 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
20 P20 99.6 1535.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
21 P21 106.9 1641.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
22 P22 M4/C2 49.2 1691.1 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.3 3.4
23 P23 114.1 1805.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4

Groupement MCG / SAFI 120


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)
24 P24 108.4 1913.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4
25 P25 95.3 2008.9 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4
26 P26 91.5 2100.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4
27 P27 99.0 2199.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4
28 P28 98.8 2298.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.3 3.4
29 P29 D-3 11.4 2309.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.1 0.1 0.9 3.2 3.4
30 P30 M5/C2 26.9 2336.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
31 P31 57.3 2393.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
32 P32 98.9 2492.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
33 P33 94.8 2587.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
34 P34 98.3 2685.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
35 P35 98.9 2784.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
36 P36 36.5 2821.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
37 P37 55.2 2876.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
38 P38 102.7 2979.0 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
39 P39 96.7 3075.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
40 P40 86.8 3162.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
41 P41 11.0 3173.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
42 P42 16.0 3189.6 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
43 P43 102.7 3292.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
44 P44 11.1 3303.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
45 P45 15.3 3318.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
46 P46 110.6 3429.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
47 P47 113.4 3542.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4

Groupement MCG / SAFI 121


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)
48 P48 M6/C2 103.0 3645.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
49 P49 103.3 3749.0 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.2 3.4
50 P50 96.9 3845.9 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.2 3.4
51 P51 M7/C2 69.4 3915.3 en terre 0.001% 1.5 2.4 0.1 0.0 0.0 0.9 3.2 3.4
52 P52 102.5 4017.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
53 P53 100.7 4118.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
54 P54 M8/C2 17.6 4136.1 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
55 P55 86.1 4222.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
56 P56 97.7 4319.9 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
57 P57 M9/C2 66.1 4385.9 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
58 P58 M10/C2 7.2 4393.2 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
59 P59 13.3 4406.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
60 S2 P60 97.0 4503.4 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
61 P61 98.4 4601.8 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
62 P62 101.9 4703.7 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.2 3.4
63 P63 D-4 88.8 4792.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.1 0.1 0.9 3.1 3.4
64 P64 14.8 4807.3 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.1 3.4
65 P65 M11/C2 15.2 4822.5 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.1 3.4
66 P66 M12/C2 9.5 4832.1 en terre 0.001% 1.5 2.3 0.1 0.0 0.0 0.9 3.1 3.4
67 P67 71.5 4903.5 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
68 P68 97.0 5000.5 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
69 P69 85.2 5085.7 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
70 P70 96.7 5182.4 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
71 P71 97.3 5279.7 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4

Groupement MCG / SAFI 122


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)
72 P72 103.9 5383.6 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
73 P73 M13/C2 27.2 5410.8 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.1 3.4
74 P74 M14/C2 10.0 5420.8 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
75 P75 73.8 5494.6 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
76 P76 103.9 5598.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
77 P77 99.7 5698.2 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
78 P78 56.5 5754.6 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
79 P79 102.8 5857.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
80 P80 99.3 5956.8 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
81 P81 M15/C2 85.2 6042.0 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
82 P82 M16/C2 17.4 6059.4 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
83 P83 99.5 6158.9 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
84 P84 99.2 6258.1 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
85 S3 P85 99.4 6357.5 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
86 P86 109.1 6466.6 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
87 P87 105.3 6571.9 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
88 P88 104.1 6676.0 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
89 P89 110.5 6786.6 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
90 P90 M17/C2 35.0 6821.6 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
91 P91 44.3 6865.9 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.1 3.4
92 P92 42.8 6908.7 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.1 3.4
93 P93 66.9 6975.6 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.1 3.4
94 P94 M18/C2 40.7 7016.2 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.1 3.4
95 P95 19.8 7036.1 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4

Groupement MCG / SAFI 123


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Section Tab. Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)
96 P96 68.2 7104.3 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
97 P97 77.5 7181.8 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
98 P98 80.9 7262.6 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
99 P99 74.3 7336.9 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
100 P100 68.8 7405.6 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
101 P101 78.3 7484.0 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
102 P102 42.9 7526.9 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
103 P103 48.9 7575.8 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
104 P104 79.3 7655.0 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
105 P105 73.9 7728.9 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
106 P106 82.1 7811.1 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
107 P107 71.5 7882.6 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
108 P108 72.2 7954.8 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
109 P109 66.8 8021.6 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
110 P110 23.0 8044.7 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
111 P111 148.7 8193.3 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4
112 P112 M19/C2 24.8 8218.1 en terre 0.001% 1.5 1.0 0.1 0.0 0.0 0.9 3.1 3.4

Tableau n° 74 : Calage du canal principal C-3


Distance Section projetée Perte de charge
Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

1 P1 S1 D2/C1 0.0 0.0 en terre 0.001% 1.5 2.2 0.1 0.0 0.1 0.1 1.0 3.2 3.5

Groupement MCG / SAFI 124


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

2 P2 M1/C3 112.9 112.9 en terre 0.001% 1.5 2.2 0.1 0.0 0.0 0.9 3.2 3.4
3 P3 21.8 134.7 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
4 P4 61.1 195.8 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
5 P5 89.3 285.1 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
6 P6 95.1 380.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
7 P7 92.8 473.0 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
8 P8 18.2 491.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
9 P9 94.0 585.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
10 P10 95.0 680.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
11 P11 M2/C3 97.0 777.3 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
12 P12 73.3 850.6 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
13 P13 M3/C3 89.8 940.4 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
14 P14 101.8 1042.2 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
15 P15 62.4 1104.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
16 P16 111.8 1216.3 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
17 P17 95.6 1311.9 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
18 P18 M4/C3 52.3 1364.2 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
19 P19 26.9 1391.1 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
20 P20 105.2 1496.3 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
21 P21 M5/C3 82.9 1579.2 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
22 P22 18.6 1597.8 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
23 P23 98.8 1696.6 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
S2
24 P24 93.6 1790.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
25 P25 90.1 1880.3 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4

Groupement MCG / SAFI 125


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

26 P26 83.1 1963.3 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
27 P27 M6/C3 105.6 2068.9 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
28 P28 93.3 2162.2 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
29 P29 98.3 2260.5 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
30 P30 109.9 2370.4 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
31 P31 91.2 2461.6 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
32 P32 97.5 2559.1 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
33 P33 M7/C3 31.6 2590.7 en terre 0.001% 1.5 2.1 0.1 0.0 0.0 0.9 3.2 3.4
34 P34 15.9 2606.6 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
35 P35 96.7 2703.4 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
36 P36 80.3 2783.7 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.2 3.4
37 P37 D-5 100.4 2884.0 en terre 0.001% 1.5 2.0 0.1 0.0 0.1 0.1 0.9 3.1 3.4
38 P38 M8/C3 36.5 2920.5 en terre 0.001% 1.5 2.0 0.1 0.0 0.0 0.9 3.1 3.4
39 P39 38.8 2959.4 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
40 P40 102.2 3061.5 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
41 P41 92.6 3154.1 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
42 P42 88.8 3242.9 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
43 P43 103.6 3346.5 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
44 P44 36.0 3382.4 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
45 P45 M9/C3 35.2 3417.6 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
46 P46 65.6 3483.2 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
47 P47 96.7 3579.9 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
48 P48 44.4 3624.3 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
49 P49 44.0 3668.2 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4

Groupement MCG / SAFI 126


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

50 P50 27.3 3695.5 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
51 P51 M10/C3 19.8 3715.3 en terre 0.001% 1.5 1.9 0.1 0.0 0.0 0.9 3.1 3.4
52 P52 21.2 3736.5 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
53 P53 46.6 3783.1 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
54 P54 95.3 3878.4 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
55 P55 104.7 3983.1 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
56 P56 104.0 4087.2 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
57 P57 91.5 4178.7 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
58 P58 88.0 4266.7 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
59 P59 M11/C3 20.8 4287.5 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
60 P60 14.4 4301.9 en terre 0.001% 1.5 1.5 0.1 0.0 0.0 0.9 3.1 3.4
61 P61 97.1 4399.0 en terre 0.001% 1.5 1.5 0.1 0.0 0.0 0.9 3.1 3.4
62 P62 99.6 4498.6 en terre 0.001% 1.5 1.5 0.1 0.0 0.0 0.9 3.1 3.4
63 P63 M12/C3 34.4 4533.0 en terre 0.001% 1.5 1.5 0.1 0.0 0.0 0.9 3.1 3.4
64 P64 67.6 4600.6 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
65 P65 93.7 4694.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
66 P66 100.2 4794.5 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
67 P67 99.8 4894.3 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
68 P68 M13/C3 101.9 4996.2 en terre 0.001% 1.5 1.7 0.1 0.0 0.0 0.9 3.1 3.4
S3
69 P69 40.7 5036.9 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
70 P70 20.0 5056.9 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
71 P71 102.4 5159.3 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
72 P72 94.7 5254.0 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4
73 P73 M14/C3 42.4 5296.4 en terre 0.001% 1.5 1.6 0.1 0.0 0.0 0.9 3.1 3.4

Groupement MCG / SAFI 127


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

74 P74 24.8 5321.2 en terre 0.001% 1.5 1.4 0.1 0.0 0.0 0.9 3.1 3.4
75 P75 61.1 5382.3 en terre 0.001% 1.5 1.4 0.1 0.0 0.0 0.9 3.1 3.4
76 P76 37.3 5419.6 en terre 0.001% 1.5 1.4 0.1 0.0 0.0 0.9 3.1 3.4
77 P77 50.1 5469.6 en terre 0.001% 1.5 1.4 0.1 0.0 0.0 0.9 3.1 3.4
78 P78 M15/C3 31.6 5501.2 en terre 0.001% 1.5 1.4 0.1 0.0 0.0 0.9 3.1 3.4
79 P79 98.1 5599.3 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
80 P80 52.5 5651.7 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
81 P81 63.9 5715.6 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
82 P82 49.5 5765.1 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
83 P83 29.0 5794.2 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
84 P84 99.7 5893.9 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
85 P85 98.0 5991.9 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
86 P86 58.3 6050.2 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
87 P87 M16/C3 57.1 6107.4 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
88 P88 42.9 6150.3 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
89 P89 56.4 6206.7 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
90 P90 24.0 6230.6 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.1 3.4
91 P91 M17/C3 37.3 6267.9 en terre 0.001% 1.5 1.3 0.1 0.0 0.0 0.9 3.0 3.4
92 P92 72.2 6340.1 en terre 0.001% 1.5 1.2 0.1 0.0 0.0 0.9 3.0 3.4
93 P93 21.9 6362.0 en terre 0.001% 1.5 1.2 0.1 0.0 0.0 0.9 3.0 3.4
94 P94 20.0 6382.0 en terre 0.001% 1.5 1.2 0.1 0.0 0.0 0.9 3.0 3.4
95 P95 93.9 6475.9 en terre 0.001% 1.5 1.2 0.1 0.0 0.0 0.9 3.0 3.4
96 P96 M18/C3 69.5 6545.4 en terre 0.001% 1.5 1.2 0.1 0.0 0.0 0.9 3.0 3.4
97 P97 33.1 6578.6 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.0 3.4

Groupement MCG / SAFI 128


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote fond Cote Yn Cote plafond
N° Tab. Section Ouvrage Pente m Yn V Canal Ouvrage Totale
Partielle Cumulée Nature canal (m) (m) (m)
(m/m) (m/m) (m) (m/s) (m) (m) (m)

98 P98 98.5 6677.1 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.0 3.4
99 P99 87.9 6765.0 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.0 3.4
100 P100 M19/C3 47.5 6812.5 en terre 0.001% 1.5 1.1 0.1 0.0 0.0 0.9 3.0 3.4

Tableau n° 75 : Calage du canal principal C-4

Distance Section projetée Perte de charge


Cote
Cote fond Cote
N° Section Tab. Ouvrage plafond
Pente m Yn Section V Canal Ouvrage Totale canal (m) Yn (m)
Partielle Cumulée Nature (m)
(m/m) (m/m) (m) (m²) (m/s) (m) (m) (m)
1 P1 D3/C1 0.0 0.0 en terre 0.001% 1.5 2.3 17.2 0.1 0.0 0.1 0.1 1.0 3.1 3.5
2 P2 M1/C4 46.2 46.2 en terre 0.001% 1.5 2.3 17.2 0.1 0.0 0.0 0.9 3.1 3.4
3 P3 82.9 129.2 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
4 P4 92.4 221.6 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
5 P5 102.7 324.3 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
6 P6 71.8 396.1 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
7 P7 97.1 493.2 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
8 S1 P8 95.6 588.8 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.1 3.4
9 P9 96.3 685.2 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
10 P10 97.7 782.9 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
11 P11 106.5 889.3 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
12 P12 26.8 916.2 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
13 P13 87.9 1004.1 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
14 P14 76.1 1080.2 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
15 P15 23.2 1103.4 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4

Groupement MCG / SAFI 129


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote
Cote fond Cote
N° Section Tab. Ouvrage plafond
Pente m Yn Section V Canal Ouvrage Totale canal (m) Yn (m)
Partielle Cumulée Nature (m)
(m/m) (m/m) (m) (m²) (m/s) (m) (m) (m)
16 P16 15.9 1119.3 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
17 P17 M2/C4 81.7 1201.0 en terre 0.001% 1.5 2.3 17.0 0.1 0.0 0.0 0.9 3.0 3.4
18 P18 25.5 1226.5 en terre 0.001% 1.5 2.3 16.8 0.1 0.0 0.0 0.9 3.0 3.4
19 P19 98.1 1324.6 en terre 0.001% 1.5 2.3 16.8 0.1 0.0 0.0 0.9 3.0 3.4
20 P20 M3/C4 90.3 1414.9 en terre 0.001% 1.5 2.3 16.8 0.1 0.0 0.0 0.9 3.0 3.4
21 P21 16.7 1431.5 en terre 0.001% 1.5 2.2 16.5 0.1 0.0 0.0 0.9 3.0 3.4
22 P22 12.9 1444.5 en terre 0.001% 1.5 2.2 16.5 0.1 0.0 0.0 0.9 3.0 3.4
23 P23 M4/C4 96.4 1540.9 en terre 0.001% 1.5 2.2 16.5 0.1 0.0 0.0 0.9 3.0 3.4
24 P24 102.0 1642.9 en terre 0.001% 1.5 2.1 15.0 0.1 0.0 0.0 0.9 3.0 3.4
25 P25 M5/C4 43.5 1686.4 en terre 0.001% 1.5 2.1 15.0 0.1 0.0 0.0 0.9 3.0 3.4
26 P26 61.3 1747.6 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
27 P27 96.8 1844.4 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
28 P28 93.2 1937.6 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
29 P29 96.7 2034.3 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
30 P30 91.8 2126.1 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
31 P31 97.0 2223.0 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
32 P32 98.0 2321.0 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
33 P33 M6/C4 98.6 2419.6 en terre 0.001% 1.5 2.1 14.8 0.1 0.0 0.0 0.9 3.0 3.4
34 P34 101.4 2521.1 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 3.0 3.4
35 P35 96.9 2618.0 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 3.0 3.4
36 P36 93.1 2711.2 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 3.0 3.4
S2
37 P37 OF-2 18.6 2729.8 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.1 0.1 0.9 2.9 3.4
38 P38 26.9 2756.7 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 2.9 3.4
39 P39 105.7 2862.4 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 2.9 3.4

Groupement MCG / SAFI 130


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote
Cote fond Cote
N° Section Tab. Ouvrage plafond
Pente m Yn Section V Canal Ouvrage Totale canal (m) Yn (m)
Partielle Cumulée Nature (m)
(m/m) (m/m) (m) (m²) (m/s) (m) (m) (m)
40 P40 90.7 2953.2 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 2.9 3.4
41 P41 M7/C4 39.1 2992.2 en terre 0.001% 1.5 2.2 14.0 0.1 0.0 0.0 0.9 2.9 3.4
42 P42 60.8 3053.0 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
43 P43 93.5 3146.5 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
44 P44 49.3 3195.8 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
45 P45 9.8 3205.7 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
46 P46 11.1 3216.7 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
47 P47 94.2 3310.9 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
48 P48 93.3 3404.2 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
49 P49 M8/C4 60.3 3464.5 en terre 0.001% 1.5 2.2 13.6 0.1 0.0 0.0 0.9 2.9 3.4
50 P50 17.0 3481.5 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
51 P51 11.1 3492.5 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
52 P52 105.3 3597.8 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
53 P53 87.9 3685.8 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
54 P54 98.8 3784.6 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
55 P55 45.7 3830.3 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
56 P56 28.0 3858.3 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
57 P57 M9/C4 34.8 3893.1 en terre 0.001% 1.5 2.1 12.8 0.1 0.0 0.0 0.9 2.9 3.4
58 P58 39.8 3932.9 en terre 0.001% 1.5 2.0 12.2 0.1 0.0 0.0 0.9 2.9 3.4
59 P59 M10/C4 9.5 3942.4 en terre 0.001% 1.5 2.0 12.2 0.1 0.0 0.0 0.9 2.9 3.4
60 P60 87.5 4029.9 en terre 0.001% 1.5 2.1 11.0 0.1 0.0 0.0 0.9 2.9 3.4
61 P61 108.6 4138.5 en terre 0.001% 1.5 2.1 11.0 0.1 0.0 0.0 0.9 2.9 3.4
S3
62 P62 M11/C4 80.4 4218.9 en terre 0.001% 1.5 2.1 11.0 0.1 0.0 0.0 0.9 2.9 3.4
63 P63 32.1 4250.9 en terre 0.001% 1.5 2.1 10.8 0.1 0.0 0.0 0.9 2.9 3.4

Groupement MCG / SAFI 131


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote
Cote fond Cote
N° Section Tab. Ouvrage plafond
Pente m Yn Section V Canal Ouvrage Totale canal (m) Yn (m)
Partielle Cumulée Nature (m)
(m/m) (m/m) (m) (m²) (m/s) (m) (m) (m)
64 P64 99.3 4350.2 en terre 0.001% 1.5 2.1 10.8 0.1 0.0 0.0 0.9 2.9 3.4
65 P65 104.0 4454.2 en terre 0.001% 1.5 2.1 10.8 0.1 0.0 0.0 0.9 2.9 3.4
66 P66 M12/C4 94.5 4548.7 en terre 0.001% 1.5 2.1 10.8 0.1 0.0 0.0 0.9 2.9 3.4
67 P67 52.9 4601.6 en terre 0.001% 1.5 2.0 9.8 0.1 0.0 0.0 0.9 2.9 3.4
68 P68 M13/C4 10.5 4612.1 en terre 0.001% 1.5 2.0 9.8 0.1 0.0 0.0 0.9 2.9 3.4
69 P69 13.9 4625.9 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
70 P70 96.5 4722.5 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
71 P71 94.5 4816.9 en terre 0.001% 1.5 1.8 8.3 0.0 0.0 0.9 2.9 3.4
72 P72 96.9 4913.9 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
73 P73 105.1 5019.0 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
74 P74 74.2 5093.2 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
75 P75 M14/C4 18.5 5111.8 en terre 0.001% 1.5 1.8 8.3 0.1 0.0 0.0 0.9 2.9 3.4
76 P76 80.3 5192.1 en terre 0.001% 1.5 1.7 7.9 0.1 0.0 0.0 0.9 2.9 3.4
77 P77 M15/C4 61.9 5254.0 en terre 0.001% 1.5 1.7 7.9 0.1 0.0 0.0 0.9 2.9 3.4
78 P78 23.9 5277.9 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.9 3.4
79 P79 10.8 5288.7 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.9 3.4
80 P80 98.9 5387.5 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.9 3.4
81 P81 93.5 5481.1 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.9 3.4
82 P82 94.1 5575.2 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.9 3.4
83 P83 102.4 5677.5 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.8 3.4
84 P84 100.5 5778.0 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.8 3.4
85 P85 111.9 5889.9 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.8 3.4
86 P86 M16/C4 16.8 5906.7 en terre 0.001% 1.5 1.7 7.5 0.1 0.0 0.0 0.9 2.8 3.4
87 P87 16.3 5923.1 en terre 0.001% 1.5 1.6 7.1 0.1 0.0 0.0 0.9 2.8 3.4

Groupement MCG / SAFI 132


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote
Cote fond Cote
N° Section Tab. Ouvrage plafond
Pente m Yn Section V Canal Ouvrage Totale canal (m) Yn (m)
Partielle Cumulée Nature (m)
(m/m) (m/m) (m) (m²) (m/s) (m) (m) (m)
88 P88 107.4 6030.4 en terre 0.001% 1.5 1.6 7.1 0.1 0.0 0.0 0.9 2.8 3.4
89 P89 31.2 6061.6 en terre 0.001% 1.5 1.6 7.1 0.1 0.0 0.0 0.9 2.8 3.4
90 P90 96.8 6158.5 en terre 0.001% 1.5 1.6 7.1 0.1 0.0 0.0 0.9 2.8 3.4
91 P91 M17/C4 29.6 6188.1 en terre 0.001% 1.5 1.6 7.1 0.1 0.0 0.0 0.9 2.8 3.4
92 P92 69.2 6257.3 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
93 P93 32.7 6290.0 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
94 P94 14.7 6304.7 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
95 P95 25.7 6330.4 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
96 P96 100.8 6431.2 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
97 P97 M18/C4 38.6 6469.7 en terre 0.001% 1.5 1.5 6.3 0.1 0.0 0.0 0.9 2.8 3.4
98 P98 49.4 6519.1 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4
99 P99 106.7 6625.8 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4
100 P100 30.0 6655.8 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4
101 P101 64.9 6720.7 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4
102 P102 89.7 6810.4 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4
103 P103 M19/C4 57.4 6867.8 en terre 0.001% 1.5 1.3 5.1 0.1 0.0 0.0 0.9 2.8 3.4

Groupement MCG / SAFI 133


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Dimensionnement du réseau d’irrigation

Les calculs hydrauliques de la section des canaux d’irrigation sont faits sur la base de la surface
irriguée et des normes pour la conception du système d’irrigation. La formule de Manning est utilisée
pour le dimensionnement des canaux.

Q  K S R 2/3
H i1/2
Avec :

 Q : débit en m3/s,
 K : coefficient de Manning-Strickler,
 S : la section mouillée,
 RH : rayon hydraulique,
 i : pente longitudinale en m/m.
Les détails du calcul et du dimensionnement des différents canaux d’irrigation sont présentés en
annexe.

Figure 13. Coupe type du canal principal

Figure 14. Coupe type du canal d’ordre secondaire

Groupement MCG / SAFI 134


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Revanche

La revanche dans un canal en terre dépend de la profondeur du canal et de la vitesse d’écoulement,


elles sont prises comme suit :

 Canaux principaux : 60 cm,

 Canaux d’ordre secondaire : 20 à 30 cm.

Groupement MCG / SAFI 135


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 76 : Récapitulatif de dimensionnement du canal principal C -1


Distance Section projetée
Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
1 P1 TR-1 0.0 0.0 9935.0 8.0 Béton 70.0 0.001% 1.5 2.6 0.6 30.7 0.3 8.0 15.5 2.5
2 P2 21.4 21.4 9935.0 8.0 Béton 70.0 0.001% 1.5 2.6 0.6 30.7 0.3 8.0 15.5 2.5
3 P3 66.7 88.1 9935.0 8.0 Béton 70.0 0.001% 1.5 2.6 0.6 30.7 0.3 8.0 15.5 2.5
4 P4 D1/C1+VC-1 52.9 141.0 9935.0 8.0 Béton 70.0 0.001% 1.5 2.6 0.6 30.7 0.3 8.0 15.5 2.5
5 P5 17.9 158.8 7545.0 8.0 Béton 70.0 0.001% 1.5 2.2 0.6 25.2 0.3 8.0 15.5 2.5
6 P6 17.6 176.4 7545.0 8.0 Béton 70.0 0.001% 1.5 2.2 0.6 25.2 0.3 8.0 15.5 2.5
7 P7 97.0 273.4 7545.0 8.0 Béton 70.0 0.001% 1.5 2.2 0.6 25.2 0.3 8.0 15.5 2.5
8 P8 D2/C1+VC-2 97.8 371.1 7545.0 8.0 Béton 70.0 0.001% 1.5 2.2 0.6 25.2 0.3 8.0 15.5 2.5
S1
9 P9 31.3 402.4 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
10 P10 98.6 501.0 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
11 P11 102.5 603.5 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
12 P12 99.7 703.2 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
13 P13 86.8 790.0 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
14 P14 86.4 876.4 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
15 P15 D-1 51.7 928.1 5750.0 8.0 Béton 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
16 P16 D3/C1+VC-3 17.0 945.1 5750.0 8.0 en terre 70.0 0.001% 1.5 1.9 0.6 20.8 0.3 8.0 15.5 2.5
17 P17 24.2 969.3 3705.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 27.4 0.1 7.0 14.5 2.5
18 P18 M1/C1 87.5 1056.7 3705.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 27.4 0.1 7.0 14.5 2.5
19 P19 104.2 1161.0 3645.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 27.1 0.1 7.0 14.5 2.5
20 P20 98.7 1259.6 3645.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 27.1 0.1 7.0 14.5 2.5
21 P21 M2/C1 34.3 1293.9 3645.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 27.1 0.1 7.0 14.5 2.5
22 P22 36.3 1330.1 3600.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.9 0.1 7.0 14.5 2.5
23 S2 P23 95.9 1426.0 3600.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.9 0.1 7.0 14.5 2.5
24 P24 99.4 1525.4 3600.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.9 0.1 7.0 14.5 2.5
25 P25 M3/C1 94.9 1620.3 3600.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.9 0.1 7.0 14.5 2.5
26 P26 93.1 1713.5 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
27 P27 99.1 1812.6 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
28 P28 93.4 1906.0 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
29 P29 49.1 1955.1 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5

Groupement MCG / SAFI 136


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
30 P30 109.3 2064.4 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
31 P31 96.5 2160.9 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
32 P32 93.7 2254.6 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
33 P33 15.2 2269.8 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
34 P34 16.4 2286.1 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
35 P35 M4/C1 61.7 2347.8 3540.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.5 0.1 7.0 14.5 2.5
36 P36 33.0 2380.9 3470.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.2 0.1 7.0 14.5 2.5
37 P37 M5/C1 40.2 2421.0 3470.0 7.0 en terre 30.0 0.001% 1.5 2.5 0.6 26.2 0.1 7.0 14.5 2.5
38 P38 59.9 2480.9 3315.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.3 0.1 7.0 14.5 2.5
39 P39 96.2 2577.1 3315.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.3 0.1 7.0 14.5 2.5
40 P40 M5 bis/C1 69.8 2646.9 3315.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.3 0.1 7.0 14.5 2.5
41 P41 103.2 2750.0 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
42 P42 96.1 2846.1 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
43 P43 97.3 2943.4 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
44 P44 94.3 3037.7 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
45 P45 66.1 3103.8 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
46 P46 M6/C1 11.2 3115.0 3255.0 7.0 en terre 30.0 0.001% 1.5 2.4 0.6 25.0 0.1 7.0 14.5 2.5
47 P47 13.0 3128.0 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
48 P48 D-2 16.3 3144.3 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
49 P49 97.5 3241.9 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
50 P50 89.4 3331.3 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
51 P51 91.5 3422.8 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
52 P52 99.0 3521.8 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
S3
53 P53 M7/C1 59.7 3581.6 2875.0 6.0 en terre 30.0 0.001% 1.5 2.4 0.6 22.6 0.1 6.0 13.5 2.5
54 P54 41.0 3622.6 2705.0 6.0 en terre 30.0 0.001% 1.5 2.3 0.6 21.6 0.1 6.0 13.5 2.5
55 P55 83.8 3706.4 2705.0 6.0 en terre 30.0 0.001% 1.5 2.3 0.6 21.6 0.1 6.0 13.5 2.5
56 P56 104.6 3811.0 2705.0 6.0 en terre 30.0 0.001% 1.5 2.3 0.6 21.6 0.1 6.0 13.5 2.5
57 P57 24.5 3835.5 2705.0 6.0 en terre 30.0 0.001% 1.5 2.3 0.6 21.6 0.1 6.0 13.5 2.5
58 P58 M8/C1 10.5 3846.0 2705.0 6.0 en terre 30.0 0.001% 1.5 2.3 0.6 21.6 0.1 6.0 13.5 2.5
59 P59 11.4 3857.4 2205.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.2 0.1 4.0 11.5 2.5
60 S4 P60 54.6 3912.0 2205.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.2 0.1 4.0 11.5 2.5
61 P61 M9/C1 11.2 3923.2 2205.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.2 0.1 4.0 11.5 2.5

Groupement MCG / SAFI 137


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
62 P62 16.6 3939.8 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
63 P63 97.9 4037.7 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
64 P64 97.1 4134.8 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
65 P65 94.0 4228.8 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
66 P66 99.4 4328.2 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
67 P67 49.9 4378.2 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
68 P68 M10/C1 19.4 4397.5 2155.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 17.9 0.1 4.0 11.5 2.5
69 P69 47.3 4444.9 2110.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.6 0.1 4.0 11.5 2.5
70 P70 48.7 4493.6 2110.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.6 0.1 4.0 11.5 2.5
71 P71 M11/C1 99.9 4593.5 2110.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.6 0.1 4.0 11.5 2.5
72 P72 90.2 4683.7 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
73 P73 90.4 4774.1 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
74 P74 19.8 4794.0 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
75 P75 OF-1 12.6 4806.6 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
76 P76 8.4 4815.0 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
77 P77 15.9 4830.8 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
78 P78 32.3 4863.1 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
79 P79 23.0 4886.2 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
80 P80 36.2 4922.4 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
81 P81 80.9 5003.3 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
82 P82 24.0 5027.3 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
83 P83 92.8 5120.0 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
84 P84 105.8 5225.8 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
85 P85 M12/C1 102.8 5328.6 2050.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.3 0.1 4.0 11.5 2.5
86 P86 23.0 5351.6 1835.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 15.9 0.1 4.0 11.5 2.5
87 P87 M13/C1 29.9 5381.5 1835.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 15.9 0.1 4.0 11.5 2.5
88 P88 M14/C1 93.1 5474.5 1805.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 15.7 0.1 4.0 11.5 2.5
89 P89 96.8 5571.3 1705.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 15.1 0.1 4.0 11.5 2.5
90 P90 105.0 5676.4 1705.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 15.1 0.1 4.0 11.5 2.5
91 P91 M15/C1 73.1 5749.5 1705.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 15.1 0.1 4.0 11.5 2.5
92 P92 30.8 5780.2 1370.0 2.0 en terre 30.0 0.001% 1.5 2.3 0.6 12.6 0.1 2.0 9.5 2.5
S5
93 P93 M16/C1 99.3 5879.5 1370.0 2.0 en terre 30.0 0.001% 1.5 2.3 0.6 12.6 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 138


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
94 P94 106.7 5986.1 1220.0 2.0 en terre 30.0 0.001% 1.5 2.2 0.6 11.6 0.1 2.0 9.5 2.5
95 P95 92.7 6078.8 1220.0 2.0 en terre 30.0 0.001% 1.5 2.2 0.6 11.6 0.1 2.0 9.5 2.5
96 P96 101.6 6180.4 1220.0 2.0 en terre 30.0 0.001% 1.5 2.2 0.6 11.6 0.1 2.0 9.5 2.5
97 P97 99.3 6279.7 1220.0 2.0 en terre 30.0 0.001% 1.5 2.2 0.6 11.6 0.1 2.0 9.5 2.5
98 P98 M17/C1 76.5 6356.2 1220.0 2.0 en terre 30.0 0.001% 1.5 2.2 0.6 11.6 0.1 2.0 9.5 2.5
99 P99 M18/C1 22.7 6379.0 1020.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.1 0.1 2.0 9.5 2.5
100 P100 29.9 6408.9 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
101 P101 69.0 6477.8 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
102 P102 58.3 6536.2 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
103 P103 35.4 6571.5 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
104 P104 7.0 6578.5 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
105 P105 8.7 6587.3 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
106 P106 M19/C1 17.6 6604.9 1000.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 10.0 0.1 2.0 9.5 2.5
107 P107 62.7 6667.6 960.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.7 0.1 2.0 9.5 2.5
108 P108 M20/C1 23.0 6690.6 960.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.7 0.1 2.0 9.5 2.5
109 P109 23.0 6713.6 930.0 2.0 en terre 30.0 0.001% 1.5 1.9 0.6 9.5 0.1 2.0 9.5 2.5
110 P110 57.7 6771.3 930.0 2.0 en terre 30.0 0.001% 1.5 1.9 0.6 9.5 0.1 2.0 9.5 2.5
111 P111 23.2 6794.4 930.0 2.0 en terre 30.0 0.001% 1.5 1.9 0.6 9.5 0.1 2.0 9.5 2.5
112 P112 M21/C1 106.7 6901.1 930.0 2.0 en terre 30.0 0.001% 1.5 1.9 0.6 9.5 0.1 2.0 9.5 2.5
113 P113 25.5 6926.5 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
114 P114 49.5 6976.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
115 P115 51.3 7027.4 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
116 P116 56.8 7084.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
117 P117 53.2 7137.4 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
118 P118 58.6 7196.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
119 P119 69.0 7265.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
120 P120 58.0 7323.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
121 P121 61.2 7384.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
122 P122 57.9 7442.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
123 P123 59.1 7501.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
124 P124 55.4 7556.6 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
125 P125 39.7 7596.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 139


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
126 P126 52.7 7649.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
127 P127 12.1 7661.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
128 P128 53.3 7714.5 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
129 P129 29.4 7743.9 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
130 P130 29.2 7773.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
131 P131 29.7 7802.8 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
132 P132 41.5 7844.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
133 P133 40.6 7884.9 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
134 P134 44.4 7929.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
135 P135 52.3 7981.6 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
136 P136 52.5 8034.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
137 P137 38.4 8072.5 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
138 P138 57.9 8130.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
139 P139 46.8 8177.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
140 P140 53.5 8230.7 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
141 P141 49.2 8279.8 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
142 P142 53.2 8333.0 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
143 P143 48.6 8381.6 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
144 P144 54.4 8436.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
145 P145 47.1 8483.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
146 P146 52.9 8536.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
147 P147 44.2 8580.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
148 P148 19.0 8599.3 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
149 P149 2.8 8602.1 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
150 P150 3.3 8605.4 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
151 P151 M22/C1 16.8 8622.2 700.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.7 0.1 2.0 9.5 2.5
152 P152 12.6 8634.8 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
153 P153 132.5 8767.3 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
154 P154 137.1 8904.4 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
155 P155 248.4 9152.8 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
156 P156 149.7 9302.5 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
157 P157 112.9 9415.4 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 140


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit Coef b h
N° Section Tab. Ouvrage Pente m Yn Revanche Section V
Partielle Cumulée (l/s) b (m) Nature Mannin retenue B(m) retenu
(m/m) (m/m) (m) (m) (m²) (m/s)
g (m) e
158 P158 141.2 9556.6 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
159 P159 131.8 9688.4 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
160 P160 144.0 9832.4 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
161 P161 110.3 9942.7 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
162 P162 157.1 10099.7 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
163 P163 63.3 10163.0 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5
164 P164 M23/C1 9.3 10172.3 315.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 4.2 0.1 2.0 9.5 2.5

Tableau n° 77 : Récapitulatif de dimensionnement du canal principal C -2


Distance Section projetée
Sectio Débit Coef m b h
N° Tab. Ouvrage Pente Yn Revanch Section V
n Partielle Cumulée (l/s) b (m) Nature Manni (m/m retenue B(m) retenu
(m/m) (m) e (m) (m²) (m/s)
ng ) (m) e
1 P1 D1/C1 0.0 0.0 2390.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.3 0.1 4.0 11.5 2.5
2 P2 113.7 113.7 2390.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.3 0.1 4.0 11.5 2.5
3 P3 M1/C2 18.2 131.8 2390.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.3 0.1 4.0 11.5 2.5
4 P4 79.1 211.0 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
5 P5 90.3 301.3 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
6 P6 95.1 396.4 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
7 P7 91.7 488.0 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
8 P8 95.8 583.8 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
9 S1 P9 M2/C2 40.3 624.1 2330.0 4.0 en terre 30.0 0.001% 1.5 2.5 0.6 19.0 0.1 4.0 11.5 2.5
10 P10 26.4 650.6 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
11 P11 95.2 745.8 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
12 P12 97.8 843.6 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
13 P13 96.5 940.1 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
14 P14 92.3 1032.4 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
15 P15 M3/C2 42.6 1075.0 2275.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.6 0.1 4.0 11.5 2.5
16 P16 65.1 1140.1 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
17 P17 100.9 1240.9 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5

Groupement MCG / SAFI 141


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Sectio Débit Coef m b h
N° Tab. Ouvrage Pente Yn Revanch Section V
n Partielle Cumulée (l/s) b (m) Nature Manni (m/m retenue B(m) retenu
(m/m) (m) e (m) (m²) (m/s)
ng ) (m) e
18 P18 98.0 1339.0 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
19 P19 96.5 1435.4 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
20 P20 99.6 1535.0 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
21 P21 106.9 1641.9 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
22 P22 M4/C2 49.2 1691.1 2180.0 4.0 en terre 30.0 0.001% 1.5 2.4 0.6 18.1 0.1 4.0 11.5 2.5
23 P23 114.1 1805.2 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
24 P24 108.4 1913.6 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
25 P25 95.3 2008.9 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
26 P26 91.5 2100.4 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
27 P27 99.0 2199.4 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
28 P28 98.8 2298.2 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
29 P29 D-3 11.4 2309.6 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
30 P30 M5/C2 26.9 2336.5 2030.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.1 0.1 4.0 11.5 2.5
31 P31 57.3 2393.8 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
32 P32 98.9 2492.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
33 P33 94.8 2587.5 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
34 P34 98.3 2685.8 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
35 P35 98.9 2784.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
36 P36 36.5 2821.2 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
37 P37 55.2 2876.3 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
38 P38 102.7 2979.0 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
39 P39 96.7 3075.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
40 P40 86.8 3162.5 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
41 P41 11.0 3173.5 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
42 P42 16.0 3189.6 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
43 P43 102.7 3292.3 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
44 P44 11.1 3303.4 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
45 P45 15.3 3318.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
46 P46 110.6 3429.3 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
47 P47 113.4 3542.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
48 P48 M6/C2 103.0 3645.7 1945.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.6 0.1 4.0 11.5 2.5
49 S2 P49 103.3 3749.0 1805.0 3.0 en terre 30.0 0.001% 1.5 2.4 0.6 15.6 0.1 3.0 10.5 2.5

Groupement MCG / SAFI 142


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Sectio Débit Coef m b h
N° Tab. Ouvrage Pente Yn Revanch Section V
n Partielle Cumulée (l/s) b (m) Nature Manni (m/m retenue B(m) retenu
(m/m) (m) e (m) (m²) (m/s)
ng ) (m) e
50 P50 96.9 3845.9 1805.0 3.0 en terre 30.0 0.001% 1.5 2.4 0.6 15.6 0.1 3.0 10.5 2.5
51 P51 M7/C2 69.4 3915.3 1805.0 3.0 en terre 30.0 0.001% 1.5 2.4 0.6 15.6 0.1 3.0 10.5 2.5
52 P52 102.5 4017.8 1750.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.2 0.1 3.0 10.5 2.5
53 P53 100.7 4118.5 1750.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.2 0.1 3.0 10.5 2.5
54 P54 M8/C2 17.6 4136.1 1750.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.2 0.1 3.0 10.5 2.5
55 P55 86.1 4222.2 1725.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.1 0.1 3.0 10.5 2.5
56 P56 97.7 4319.9 1725.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.1 0.1 3.0 10.5 2.5
57 P57 M9/C2 66.1 4385.9 1725.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 15.1 0.1 3.0 10.5 2.5
58 P58 M10/C2 7.2 4393.2 1705.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.9 0.1 3.0 10.5 2.5
59 P59 13.3 4406.4 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
60 P60 97.0 4503.4 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
61 P61 98.4 4601.8 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
62 P62 101.9 4703.7 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
63 P63 D-4 88.8 4792.5 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
64 P64 14.8 4807.3 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
65 P65 M11/C2 15.2 4822.5 1655.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.6 0.1 3.0 10.5 2.5
66 P66 M12/C2 9.5 4832.1 1625.0 3.0 en terre 30.0 0.001% 1.5 2.3 0.6 14.4 0.1 3.0 10.5 2.5
67 P67 71.5 4903.5 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
68 P68 97.0 5000.5 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
69 P69 85.2 5085.7 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
70 P70 96.7 5182.4 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
71 P71 97.3 5279.7 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
72 P72 103.9 5383.6 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
73 P73 M13/C2 27.2 5410.8 1525.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.8 0.1 3.0 10.5 2.5
74 P74 M14/C2 10.0 5420.8 1095.0 3.0 en terre 30.0 0.001% 1.5 1.9 0.6 10.8 0.1 3.0 10.5 2.5
75 P75 73.8 5494.6 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
76 P76 103.9 5598.5 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
77 P77 99.7 5698.2 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
78 S3 P78 56.5 5754.6 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
79 P79 102.8 5857.5 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
80 P80 99.3 5956.8 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5
81 P81 M15/C2 85.2 6042.0 995.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.9 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 143


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Sectio Débit Coef m b h
N° Tab. Ouvrage Pente Yn Revanch Section V
n Partielle Cumulée (l/s) b (m) Nature Manni (m/m retenue B(m) retenu
(m/m) (m) e (m) (m²) (m/s)
ng ) (m) e
82 P82 M16/C2 17.4 6059.4 750.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 8.1 0.1 2.0 9.5 2.5
83 P83 99.5 6158.9 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
84 P84 99.2 6258.1 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
85 P85 99.4 6357.5 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
86 P86 109.1 6466.6 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
87 P87 105.3 6571.9 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
88 P88 104.1 6676.0 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
89 P89 110.5 6786.6 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
90 P90 M17/C2 35.0 6821.6 650.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.2 0.1 2.0 9.5 2.5
91 P91 44.3 6865.9 270.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 3.8 0.1 2.0 9.5 2.5
92 P92 42.8 6908.7 270.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 3.8 0.1 2.0 9.5 2.5
93 P93 66.9 6975.6 270.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 3.8 0.1 2.0 9.5 2.5
94 P94 M18/C2 40.7 7016.2 270.0 2.0 en terre 30.0 0.001% 1.5 1.1 0.6 3.8 0.1 2.0 9.5 2.5
95 P95 19.8 7036.1 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
96 P96 68.2 7104.3 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
97 P97 77.5 7181.8 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
98 P98 80.9 7262.6 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
99 P99 74.3 7336.9 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
100 P100 68.8 7405.6 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
101 P101 78.3 7484.0 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
102 P102 42.9 7526.9 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
103 P103 48.9 7575.8 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
104 P104 79.3 7655.0 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
105 P105 73.9 7728.9 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
106 P106 82.1 7811.1 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
107 P107 71.5 7882.6 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
108 P108 72.2 7954.8 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
109 P109 66.8 8021.6 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
110 P110 23.0 8044.7 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
111 P111 148.7 8193.3 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5
112 P112 M19/C2 24.8 8218.1 235.0 2.0 en terre 30.0 0.001% 1.5 1.0 0.6 3.4 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 144


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 78 : Récapitulatif de dimensionnement du canal principal C -3


Distance Section projetée
Débit b
N° Tab. Section Ouvrage b Coef Pente m Yn Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) Manning (m/m) (m/m) (m) (m²) (m/s) retenue
(m)
1 P1 D2/C1 0.0 0.0 1795.0 4.0 en terre 30.0 0.001% 1.5 2.2 15.7 0.1 4.0 11.5 2.5
2 P2 M1/C3 112.9 112.9 1795.0 4.0 en terre 30.0 0.001% 1.5 2.2 15.7 0.1 4.0 11.5 2.5
3 P3 21.8 134.7 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
4 P4 61.1 195.8 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
5 P5 89.3 285.1 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
6 P6 95.1 380.2 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
7 P7 92.8 473.0 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
8 P8 18.2 491.2 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
9 P9 94.0 585.2 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
10 P10 95.0 680.2 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
11 P11 S1 M2/C3 97.0 777.3 1755.0 4.0 en terre 30.0 0.001% 1.5 2.1 15.4 0.1 4.0 11.5 2.5
12 P12 73.3 850.6 1650.0 4.0 en terre 30.0 0.001% 1.5 2.1 14.7 0.1 4.0 11.5 2.5
13 P13 M3/C3 89.8 940.4 1650.0 4.0 en terre 30.0 0.001% 1.5 2.1 14.7 0.1 4.0 11.5 2.5
14 P14 101.8 1042.2 1570.0 4.0 en terre 30.0 0.001% 1.5 2.0 14.2 0.1 4.0 11.5 2.5
15 P15 62.4 1104.5 1570.0 4.0 en terre 30.0 0.001% 1.5 2.0 14.2 0.1 4.0 11.5 2.5
16 P16 111.8 1216.3 1570.0 4.0 en terre 30.0 0.001% 1.5 2.0 14.2 0.1 4.0 11.5 2.5
17 P17 95.6 1311.9 1570.0 4.0 en terre 30.0 0.001% 1.5 2.0 14.2 0.1 4.0 11.5 2.5
18 P18 M4/C3 52.3 1364.2 1570.0 4.0 en terre 30.0 0.001% 1.5 2.0 14.2 0.1 4.0 11.5 2.5
19 P19 26.9 1391.1 1480.0 4.0 en terre 30.0 0.001% 1.5 2.0 13.6 0.1 4.0 11.5 2.5
20 P20 105.2 1496.3 1480.0 4.0 en terre 30.0 0.001% 1.5 2.0 13.6 0.1 4.0 11.5 2.5
21 P21 M5/C3 82.9 1579.2 1480.0 4.0 en terre 30.0 0.001% 1.5 2.0 13.6 0.1 4.0 11.5 2.5
22 P22 18.6 1597.8 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
23 P23 98.8 1696.6 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
24 P24 93.6 1790.2 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
25 P25 S2 90.1 1880.3 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
26 P26 83.1 1963.3 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
27 P27 M6/C3 105.6 2068.9 1460.0 3.0 en terre 30.0 0.001% 1.5 2.1 13.3 0.1 3.0 10.5 2.5
28 P28 93.3 2162.2 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5

Groupement MCG / SAFI 145


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit b
N° Tab. Section Ouvrage b Coef Pente m Yn Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) Manning (m/m) (m/m) (m) (m²) (m/s) retenue
(m)
29 P29 98.3 2260.5 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5
30 P30 109.9 2370.4 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5
31 P31 91.2 2461.6 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5
32 P32 97.5 2559.1 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5
33 P33 M7/C3 31.6 2590.7 1350.0 3.0 en terre 30.0 0.001% 1.5 2.1 12.6 0.1 3.0 10.5 2.5
34 P34 15.9 2606.6 1260.0 3.0 en terre 30.0 0.001% 1.5 2.0 11.9 0.1 3.0 10.5 2.5
35 P35 96.7 2703.4 1260.0 3.0 en terre 30.0 0.001% 1.5 2.0 11.9 0.1 3.0 10.5 2.5
36 P36 80.3 2783.7 1260.0 3.0 en terre 30.0 0.001% 1.5 2.0 11.9 0.1 3.0 10.5 2.5
37 P37 D-5 100.4 2884.0 1260.0 3.0 en terre 30.0 0.001% 1.5 2.0 11.9 0.1 3.0 10.5 2.5
38 P38 M8/C3 36.5 2920.5 1260.0 3.0 en terre 30.0 0.001% 1.5 2.0 11.9 0.1 3.0 10.5 2.5
39 P39 38.8 2959.4 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
40 P40 102.2 3061.5 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
41 P41 92.6 3154.1 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
42 P42 88.8 3242.9 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
43 P43 103.6 3346.5 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
44 P44 36.0 3382.4 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
45 P45 M9/C3 35.2 3417.6 1190.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.5 0.1 3.0 10.5 2.5
46 P46 65.6 3483.2 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
47 P47 96.7 3579.9 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
48 P48 44.4 3624.3 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
49 P49 44.0 3668.2 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
50 P50 27.3 3695.5 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
51 P51 M10/C3 19.8 3715.3 1130.0 3.0 en terre 30.0 0.001% 1.5 1.9 11.0 0.1 3.0 10.5 2.5
52 P52 21.2 3736.5 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
53 P53 46.6 3783.1 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
54 P54 95.3 3878.4 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
55 P55 104.7 3983.1 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
56 P56 104.0 4087.2 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
57 P57 91.5 4178.7 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
58 P58 88.0 4266.7 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
59 P59 M11/C3 20.8 4287.5 790.0 3.0 en terre 30.0 0.001% 1.5 1.6 8.5 0.1 3.0 10.5 2.5
60 P60 14.4 4301.9 745.0 3.0 en terre 30.0 0.001% 1.5 1.5 8.1 0.1 3.0 10.5 2.5

Groupement MCG / SAFI 146


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit b
N° Tab. Section Ouvrage b Coef Pente m Yn Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) Manning (m/m) (m/m) (m) (m²) (m/s) retenue
(m)
61 P61 97.1 4399.0 745.0 3.0 en terre 30.0 0.001% 1.5 1.5 8.1 0.1 3.0 10.5 2.5
62 P62 99.6 4498.6 745.0 3.0 en terre 30.0 0.001% 1.5 1.5 8.1 0.1 3.0 10.5 2.5
63 P63 M12/C3 34.4 4533.0 745.0 3.0 en terre 30.0 0.001% 1.5 1.5 8.1 0.1 3.0 10.5 2.5
64 P64 67.6 4600.6 690.0 2.0 en terre 30.0 0.001% 1.5 1.7 7.6 0.1 2.0 9.5 2.5
65 P65 93.7 4694.3 690.0 2.0 en terre 30.0 0.001% 1.5 1.7 7.6 0.1 2.0 9.5 2.5
66 P66 100.2 4794.5 690.0 2.0 en terre 30.0 0.001% 1.5 1.7 7.6 0.1 2.0 9.5 2.5
67 P67 99.8 4894.3 690.0 2.0 en terre 30.0 0.001% 1.5 1.7 7.6 0.1 2.0 9.5 2.5
68 P68 M13/C3 101.9 4996.2 690.0 2.0 en terre 30.0 0.001% 1.5 1.7 7.6 0.1 2.0 9.5 2.5
69 P69 40.7 5036.9 640.0 2.0 en terre 30.0 0.001% 1.5 1.6 7.2 0.1 2.0 9.5 2.5
70 P70 20.0 5056.9 640.0 2.0 en terre 30.0 0.001% 1.5 1.6 7.2 0.1 2.0 9.5 2.5
71 P71 102.4 5159.3 640.0 2.0 en terre 30.0 0.001% 1.5 1.6 7.2 0.1 2.0 9.5 2.5
72 P72 94.7 5254.0 640.0 2.0 en terre 30.0 0.001% 1.5 1.6 7.2 0.1 2.0 9.5 2.5
73 P73 M14/C3 42.4 5296.4 640.0 2.0 en terre 30.0 0.001% 1.5 1.6 7.2 0.1 2.0 9.5 2.5
74 P74 24.8 5321.2 455.0 2.0 en terre 30.0 0.001% 1.5 1.4 5.6 0.1 2.0 9.5 2.5
75 P75 61.1 5382.3 455.0 2.0 en terre 30.0 0.001% 1.5 1.4 5.6 0.1 2.0 9.5 2.5
76 P76 37.3 5419.6 455.0 2.0 en terre 30.0 0.001% 1.5 1.4 5.6 0.1 2.0 9.5 2.5
77 P77 50.1 5469.6 455.0 2.0 en terre 30.0 0.001% 1.5 1.4 5.6 0.1 2.0 9.5 2.5
78 P78 S3 M15/C3 31.6 5501.2 455.0 2.0 en terre 30.0 0.001% 1.5 1.4 5.6 0.1 2.0 9.5 2.5
79 P79 98.1 5599.3 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
80 P80 52.5 5651.7 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
81 P81 63.9 5715.6 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
82 P82 49.5 5765.1 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
83 P83 29.0 5794.2 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
84 P84 99.7 5893.9 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
85 P85 98.0 5991.9 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
86 P86 58.3 6050.2 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
87 P87 M16/C3 57.1 6107.4 425.0 2.0 en terre 30.0 0.001% 1.5 1.3 5.3 0.1 2.0 9.5 2.5
88 P88 42.9 6150.3 380.0 2.0 en terre 30.0 0.001% 1.5 1.3 4.9 0.1 2.0 9.5 2.5
89 P89 56.4 6206.7 380.0 2.0 en terre 30.0 0.001% 1.5 1.3 4.9 0.1 2.0 9.5 2.5
90 P90 24.0 6230.6 380.0 2.0 en terre 30.0 0.001% 1.5 1.3 4.9 0.1 2.0 9.5 2.5
91 P91 M17/C3 37.3 6267.9 380.0 2.0 en terre 30.0 0.001% 1.5 1.3 4.9 0.1 2.0 9.5 2.5
92 P92 72.2 6340.1 330.0 2.0 en terre 30.0 0.001% 1.5 1.2 4.4 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 147


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit b
N° Tab. Section Ouvrage b Coef Pente m Yn Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) Manning (m/m) (m/m) (m) (m²) (m/s) retenue
(m)
93 P93 21.9 6362.0 330.0 2.0 en terre 30.0 0.001% 1.5 1.2 4.4 0.1 2.0 9.5 2.5
94 P94 20.0 6382.0 330.0 2.0 en terre 30.0 0.001% 1.5 1.2 4.4 0.1 2.0 9.5 2.5
95 P95 93.9 6475.9 330.0 2.0 en terre 30.0 0.001% 1.5 1.2 4.4 0.1 2.0 9.5 2.5
96 P96 M18/C3 69.5 6545.4 330.0 2.0 en terre 30.0 0.001% 1.5 1.2 4.4 0.1 2.0 9.5 2.5
97 P97 33.1 6578.6 295.0 2.0 en terre 30.0 0.001% 1.5 1.1 4.0 0.1 2.0 9.5 2.5
98 P98 98.5 6677.1 295.0 2.0 en terre 30.0 0.001% 1.5 1.1 4.0 0.1 2.0 9.5 2.5
99 P99 87.9 6765.0 295.0 2.0 en terre 30.0 0.001% 1.5 1.1 4.0 0.1 2.0 9.5 2.5
100 P100 M19/C3 47.5 6812.5 295.0 2.0 en terre 30.0 0.001% 1.5 1.1 4.0 0.1 2.0 9.5 2.5

Tableau n° 79 : Récapitulatif de dimensionnement du canal principal C -4


Distance Section projetée
Cote
Débit b
N° Section Tab. Ouvrage TN b Coef Pente m Yn Revanche Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) (m) Manning (m/m) (m/m) (m) (m) (m²) (m/s) retenue
(m)
1 P1 D3/C1 0.0 0.0 0.5 2045.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.2 0.1 4.0 11.5 2.5
2 P2 M1/C4 46.2 46.2 2.6 2045.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.2 0.1 4.0 11.5 2.5
3 P3 82.9 129.2 0.6 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
4 P4 92.4 221.6 0.7 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
5 P5 102.7 324.3 0.4 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
6 P6 71.8 396.1 0.8 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
7 P7 97.1 493.2 0.5 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
8 P8 95.6 588.8 0.7 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
S1
9 P9 96.3 685.2 0.6 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
10 P10 97.7 782.9 0.7 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
11 P11 106.5 889.3 0.9 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
12 P12 26.8 916.2 0.8 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
13 P13 87.9 1004.1 0.5 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
14 P14 76.1 1080.2 0.6 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
15 P15 23.2 1103.4 0.8 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
16 P16 15.9 1119.3 0.6 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5

Groupement MCG / SAFI 148


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote
Débit b
N° Section Tab. Ouvrage TN b Coef Pente m Yn Revanche Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) (m) Manning (m/m) (m/m) (m) (m) (m²) (m/s) retenue
(m)
17 P17 M2/C4 81.7 1201.0 2.5 2005.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 17.0 0.1 4.0 11.5 2.5
18 P18 25.5 1226.5 0.7 1970.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.8 0.1 4.0 11.5 2.5
19 P19 98.1 1324.6 0.5 1970.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.8 0.1 4.0 11.5 2.5
20 P20 M3/C4 90.3 1414.9 0.7 1970.0 4.0 en terre 30.0 0.001% 1.5 2.3 0.6 16.8 0.1 4.0 11.5 2.5
21 P21 16.7 1431.5 0.7 1925.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 16.5 0.1 4.0 11.5 2.5
22 P22 12.9 1444.5 0.6 1925.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 16.5 0.1 4.0 11.5 2.5
23 P23 M4/C4 96.4 1540.9 0.8 1925.0 4.0 en terre 30.0 0.001% 1.5 2.2 0.6 16.5 0.1 4.0 11.5 2.5
24 P24 102.0 1642.9 1.1 1695.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 15.0 0.1 4.0 11.5 2.5
25 P25 M5/C4 43.5 1686.4 1.8 1695.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 15.0 0.1 4.0 11.5 2.5
26 P26 61.3 1747.6 0.9 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
27 P27 96.8 1844.4 0.8 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
28 P28 93.2 1937.6 0.7 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
29 P29 96.7 2034.3 0.6 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
30 P30 91.8 2126.1 0.8 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
31 P31 97.0 2223.0 0.7 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
32 P32 98.0 2321.0 0.7 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
33 P33 M6/C4 98.6 2419.6 0.7 1655.0 4.0 en terre 30.0 0.001% 1.5 2.1 0.6 14.8 0.1 4.0 11.5 2.5
34 P34 101.4 2521.1 0.7 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
35 P35 96.9 2618.0 0.7 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
36 P36 93.1 2711.2 0.7 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
37 P37 OF-2 18.6 2729.8 2.3 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
38 P38 26.9 2756.7 0.8 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
39 P39 105.7 2862.4 0.6 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
40 P40 90.7 2953.2 0.7 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
41 S2 P41 M7/C4 39.1 2992.2 1.9 1565.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 14.0 0.1 3.0 10.5 2.5
42 P42 60.8 3053.0 0.6 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
43 P43 93.5 3146.5 0.6 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
44 P44 49.3 3195.8 0.6 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
45 P45 9.8 3205.7 0.7 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
46 P46 11.1 3216.7 0.8 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
47 P47 94.2 3310.9 0.6 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
48 P48 93.3 3404.2 0.7 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5

Groupement MCG / SAFI 149


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote
Débit b
N° Section Tab. Ouvrage TN b Coef Pente m Yn Revanche Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) (m) Manning (m/m) (m/m) (m) (m) (m²) (m/s) retenue
(m)
49 P49 M8/C4 60.3 3464.5 0.8 1505.0 3.0 en terre 30.0 0.001% 1.5 2.2 0.6 13.6 0.1 3.0 10.5 2.5
50 P50 17.0 3481.5 0.7 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
51 P51 11.1 3492.5 0.5 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
52 P52 105.3 3597.8 0.6 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
53 P53 87.9 3685.8 0.6 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
54 P54 98.8 3784.6 0.7 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
55 P55 45.7 3830.3 0.7 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
56 P56 28.0 3858.3 0.7 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
57 P57 M9/C4 34.8 3893.1 0.8 1390.0 3.0 en terre 30.0 0.001% 1.5 2.1 0.6 12.8 0.1 3.0 10.5 2.5
58 P58 39.8 3932.9 1.0 1300.0 3.0 en terre 30.0 0.001% 1.5 2.0 0.6 12.2 0.1 3.0 10.5 2.5
59 P59 M10/C4 9.5 3942.4 1.6 1300.0 3.0 en terre 30.0 0.001% 1.5 2.0 0.6 12.2 0.1 3.0 10.5 2.5
60 P60 87.5 4029.9 1.2 1145.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 11.0 0.1 2.0 9.5 2.5
61 P61 108.6 4138.5 0.8 1145.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 11.0 0.1 2.0 9.5 2.5
62 P62 M11/C4 80.4 4218.9 2.1 1145.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 11.0 0.1 2.0 9.5 2.5
63 P63 32.1 4250.9 0.7 1105.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 10.8 0.1 2.0 9.5 2.5
64 P64 99.3 4350.2 0.6 1105.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 10.8 0.1 2.0 9.5 2.5
65 P65 104.0 4454.2 0.7 1105.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 10.8 0.1 2.0 9.5 2.5
66 P66 M12/C4 94.5 4548.7 0.7 1105.0 2.0 en terre 30.0 0.001% 1.5 2.1 0.6 10.8 0.1 2.0 9.5 2.5
67 P67 52.9 4601.6 0.8 975.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.8 0.1 2.0 9.5 2.5
68 P68 M13/C4 10.5 4612.1 0.9 975.0 2.0 en terre 30.0 0.001% 1.5 2.0 0.6 9.8 0.1 2.0 9.5 2.5
69 P69 13.9 4625.9 0.7 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
70 S3 P70 96.5 4722.5 0.7 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
71 P71 94.5 4816.9 0.7 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 2.0 9.5 2.5
72 P72 96.9 4913.9 0.6 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
73 P73 105.1 5019.0 0.6 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
74 P74 74.2 5093.2 0.6 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
75 P75 M14/C4 18.5 5111.8 1.8 785.0 2.0 en terre 30.0 0.001% 1.5 1.8 0.6 8.3 0.1 2.0 9.5 2.5
76 P76 80.3 5192.1 0.7 725.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.9 0.1 2.0 9.5 2.5
77 P77 M15/C4 61.9 5254.0 0.7 725.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.9 0.1 2.0 9.5 2.5
78 P78 23.9 5277.9 0.7 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
79 P79 10.8 5288.7 0.7 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
80 P80 98.9 5387.5 0.6 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5

Groupement MCG / SAFI 150


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote
Débit b
N° Section Tab. Ouvrage TN b Coef Pente m Yn Revanche Section V h
Partielle Cumulée (l/s) Nature retenue B(m)
(m) (m) Manning (m/m) (m/m) (m) (m) (m²) (m/s) retenue
(m)
81 P81 93.5 5481.1 0.6 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
82 P82 94.1 5575.2 0.5 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
83 P83 102.4 5677.5 0.6 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
84 P84 100.5 5778.0 0.6 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
85 P85 111.9 5889.9 0.7 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
86 P86 M16/C4 16.8 5906.7 0.9 685.0 2.0 en terre 30.0 0.001% 1.5 1.7 0.6 7.5 0.1 2.0 9.5 2.5
87 P87 16.3 5923.1 0.8 635.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.1 0.1 2.0 9.5 2.5
88 P88 107.4 6030.4 0.9 635.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.1 0.1 2.0 9.5 2.5
89 P89 31.2 6061.6 0.6 635.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.1 0.1 2.0 9.5 2.5
90 P90 96.8 6158.5 0.7 635.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.1 0.1 2.0 9.5 2.5
91 P91 M17/C4 29.6 6188.1 2.2 635.0 2.0 en terre 30.0 0.001% 1.5 1.6 0.6 7.1 0.1 2.0 9.5 2.5
92 P92 69.2 6257.3 0.4 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
93 P93 32.7 6290.0 0.5 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
94 P94 14.7 6304.7 0.5 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
95 P95 25.7 6330.4 0.6 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
96 P96 100.8 6431.2 0.4 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
97 P97 M18/C4 38.6 6469.7 2.2 535.0 2.0 en terre 30.0 0.001% 1.5 1.5 0.6 6.3 0.1 2.0 9.5 2.5
98 P98 49.4 6519.1 0.7 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5
99 P99 106.7 6625.8 0.7 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5
100 P100 30.0 6655.8 0.7 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5
101 P101 64.9 6720.7 0.6 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5
102 P102 89.7 6810.4 0.6 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5
103 P103 M19/C4 57.4 6867.8 1.0 400.0 2.0 en terre 30.0 0.001% 1.5 1.3 0.6 5.1 0.1 2.0 9.5 2.5

Tableau n° 80 : Récapitulatif de dimensionnement des canaux secondaires (C-1)


b h Cote de Cote Cote
Canal Linéaire Débit Coef Pente m Yn Revanche V B C1 C2
b (m) retenue retenue calage Yn plafond
secondaire (ml) (l/s) Manning (m/m) (m/m) (m) (m) (m/s) (m) (m) (m)
(m) (m) (m) (m) (m)
C1.2 1660.0 45 0.30 30.00 0.1% 1.50 0.30 0.30 0.2 0.30 2.40 0.70 2.53 2.83 3.23 0.30 0.30
C1.5 205.0 155 0.50 30.00 0.1% 1.50 0.47 0.30 0.3 0.50 2.60 0.70 2.10 2.57 2.80 0.30 0.30
C1.5 bis 225.0 60 0.30 30.00 0.1% 1.50 0.34 0.30 0.2 0.30 2.40 0.70 1.91 2.26 2.61 0.30 0.30

Groupement MCG / SAFI 151


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote Cote


Canal Linéaire Débit Coef Pente m Yn Revanche V B C1 C2
b (m) retenue retenue calage Yn plafond
secondaire (ml) (l/s) Manning (m/m) (m/m) (m) (m) (m/s) (m) (m) (m)
(m) (m) (m) (m) (m)
C1.6 150.0 380 1.00 30.00 0.1% 1.50 0.59 0.30 0.3 1.00 3.70 0.90 1.68 2.27 2.58 0.50 0.50
C1.8 530.0 500 1.50 30.00 0.1% 1.50 0.59 0.30 0.4 1.50 4.20 0.90 1.77 2.35 2.67 0.30 0.30
C1.9 515.0 50 0.30 30.00 0.1% 1.50 0.32 0.30 0.2 0.30 2.10 0.60 2.06 2.37 2.66 0.30 0.30
C1.10 105.0 45 0.30 30.00 0.1% 1.50 0.30 0.30 0.2 0.30 2.10 0.60 1.75 2.05 2.35 0.30 0.30
C1.13 507.0 30 0.30 30.00 0.1% 1.50 0.25 0.30 0.2 0.30 2.10 0.60 1.85 2.10 2.45 0.30 0.30
C1-14 695.0 100 0.50 30.00 0.1% 1.50 0.38 0.30 0.2 0.50 2.30 0.60 1.75 2.13 2.35 0.30 0.30
C1.18 525.0 20 0.30 30.00 0.1% 1.50 0.20 0.30 0.2 0.30 2.10 0.60 1.86 2.07 2.46 0.30 0.30
C1.19 940.0 40 0.30 30.00 0.1% 1.50 0.28 0.30 0.2 0.30 2.10 0.60 2.07 2.35 2.67 0.30 0.30
C1.20 850.0 30 0.30 30.00 0.1% 1.50 0.25 0.30 0.2 0.30 2.10 0.60 2.13 2.37 2.73 0.30 0.30

Tableau n° 81 : Récapitulatif de dimensionnement des canaux tertiaires (C-1)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.1.1 375.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.69 1.94 2.19 0.30 0.30
C1.1.2 550.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.88 2.12 2.38 0.30 0.30
C1.3.1 275.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.74 1.99 2.24 0.30 0.30
C1.3.2 275.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.74 1.99 2.24 0.30 0.30
C1.4.1 390.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.70 1.94 2.20 0.30 0.30
C1.4.2 315.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.66 1.86 2.16 0.30 0.30
C1.4.3 470.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.74 1.94 2.24 0.30 0.30
C1.5.1 1200.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.40 2.65 2.90 0.30 0.30
C1.5.2 160.0 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.88 2.06 2.38 0.30 0.30
C1.5.3 140.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.07 2.27 2.57 0.30 0.30
C1.5.4 250.0 90 0.50 30.00 0.1% 1.50 0.36 0.20 0.2 0.50 2.00 0.50 2.03 2.39 2.53 0.30 0.30
C1.5 bis-1 875.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.24 2.46 2.74 0.30 0.30
C1.5 bis-2 1040.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.32 2.59 2.82 0.30 0.30
C1.6.2 178.0 190 0.50 30.00 0.1% 1.50 0.52 0.20 0.3 0.50 2.60 0.70 1.69 2.21 2.39 0.30 0.30
C1.6.1 540.0 190 0.50 30.00 0.1% 1.50 0.52 0.20 0.3 0.50 2.60 0.70 1.67 2.19 2.37 0.30 0.30
C1.7.1 1550.0 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 2.48 2.79 2.98 0.30 0.30
C1.7.2 700.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.05 2.30 2.55 0.30 0.30

Groupement MCG / SAFI 152


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.7.3 325.0 65 0.30 30.00 0.1% 1.50 0.36 0.20 0.2 0.30 1.80 0.50 1.86 2.22 2.36 0.30 0.30
C1.7.4 900.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.95 2.18 2.45 0.30 0.30
C1.8.1 590.0 435 1.50 30.00 0.1% 1.50 0.55 0.20 0.3 1.50 3.60 0.70 1.80 2.34 2.50 0.50 0.50
C1.8.2 320.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.46 1.66 1.96 0.30 0.30
C1.8.3 285.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.34 1.57 1.84 0.30 0.30
C1.8.4 400.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.60 1.80 2.10 0.30 0.30
C1.9.1 285.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.64 1.85 2.14 0.30 0.30
C1.9.2 890.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.25 2.49 2.75 0.30 0.30
C1.10.1 290.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.75 1.97 2.25 0.30 0.30
C1.10.2 730.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.07 2.27 2.57 0.30 0.30
C1.11.1 480.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.54 1.74 2.04 0.30 0.30
C1.11.2 220.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.41 1.61 1.91 0.30 0.30
C1.11.3 450.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.63 1.83 2.13 0.30 0.30
C1.12.1 695.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.95 2.15 2.45 0.30 0.30
C1.12.2 660.0 110 0.50 30.00 0.1% 1.50 0.40 0.20 0.2 0.50 2.30 0.60 2.23 2.63 2.83 0.30 0.30
C1.12.3 301.0 85 0.30 30.00 0.1% 1.50 0.40 0.20 0.2 0.30 2.10 0.60 1.85 2.25 2.45 0.30 0.30
C1.14.1 180.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.49 1.76 1.99 0.30 0.30
C1.14.2 100.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.25 1.50 1.75 0.30 0.30
C1.14.3 650.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.33 1.59 1.83 0.30 0.30
C1.15.1 220.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.71 1.91 2.21 0.30 0.30
C1.15.2 1380.0 280 1.00 30.00 0.1% 1.50 0.51 0.20 0.3 1.00 3.10 0.70 2.19 2.70 2.89 0.50 0.50
C1.15.3 520.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.56 1.83 2.06 0.30 0.30
C1.16.1 250.0 120 0.50 30.00 0.1% 1.50 0.42 0.20 0.3 0.50 2.30 0.60 2.03 2.44 2.63 0.30 0.30
C1.16.2 860.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.43 2.68 2.93 0.30 0.30
C1.17.1 375.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.79 2.04 2.29 0.30 0.30
C1.17.2 695.0 170 0.50 30.00 0.1% 1.50 0.49 0.20 0.3 0.50 2.60 0.70 1.95 2.44 2.65 0.50 0.50
C1.21.1 1100.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.95 2.20 2.45 0.30 0.30
C1.21.2 840.0 65 0.30 30.00 0.1% 1.50 0.36 0.20 0.2 0.30 1.80 0.50 2.12 2.48 2.62 0.30 0.30
C1.21.3 530.0 105 0.30 30.00 0.1% 1.50 0.44 0.20 0.2 0.30 2.10 0.60 2.27 2.71 2.87 0.30 0.30
C1.21.4 595.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.80 2.05 2.30 0.30 0.30
C1.22.1 330.0 80 0.30 30.00 0.1% 1.50 0.39 0.20 0.2 0.30 1.80 0.50 1.87 2.26 2.37 0.30 0.30
C1.22.2 830.0 270 0.50 30.00 0.1% 1.50 0.61 0.20 0.3 0.50 2.90 0.80 2.32 2.92 3.12 0.30 0.30
C1.22.3 855.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.43 2.69 2.93 0.30 0.30

Groupement MCG / SAFI 153


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.23.1 700.0 270 0.50 30.00 0.1% 1.50 0.61 0.20 0.3 0.50 2.90 0.80 2.05 2.66 2.85 0.50 0.50
C1.23.2 715.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 2.06 2.36 2.56 0.30 0.30

Tableau n° 82 : Récapitulatif de dimensionnement des canaux quaternaires (C-1)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.5.4.1 220.0 70 0.30 30.00 0.1% 1.50 0.37 0.20 0.2 0.30 2.10 0.60 1.91 2.28 2.51 0.30 0.30
C1.5.4.2 965.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.28 2.49 2.78 0.30 0.30
C1.6.2.1 265.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.73 2.02 2.23 0.30 0.30
C1.6.2.2 590.0 115 0.50 30.00 0.1% 1.50 0.41 0.20 0.3 0.50 2.30 0.60 1.80 2.20 2.40 0.30 0.30
C1.6.2.3 300.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.35 1.58 1.85 0.30 0.30
C1.6.1.1 260.0 10 0.30 30.00 0.1% 1.50 0.14 0.20 0.1 0.30 1.80 0.50 1.33 1.47 1.83 0.30 0.30
C1.6.1.2 280.0 70 0.30 30.00 0.1% 1.50 0.37 0.20 0.2 0.30 2.10 0.60 1.14 1.51 1.74 0.30 0.30
C1.6.1.3 217.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.31 1.54 1.81 0.30 0.30
C1.6.1.4 425.0 85 0.30 30.00 0.1% 1.50 0.40 0.20 0.2 0.30 2.10 0.60 1.61 2.01 2.21 0.30 0.30
C1.7.2.1 270.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.84 2.10 2.34 0.30 0.30
C1.7.2.2 575.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.89 2.14 2.39 0.30 0.30
C1.8.1.1 480.0 175 1.00 30.00 0.1% 1.50 0.40 0.20 0.3 1.00 2.80 0.60 1.74 2.14 2.34 0.30 0.30
C1.8.1.2 453.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.43 1.71 1.93 0.30 0.30
C1.8.1.3 560.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.58 1.86 2.08 0.30 0.30
C1.8.1.4 450.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.43 1.69 1.93 0.30 0.30
C1.8.1.5 830.0 145 0.50 30.00 0.1% 1.50 0.46 0.20 0.3 0.50 2.30 0.60 1.82 2.27 2.42 0.30 0.30
C1.12.2.1 390.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.90 2.10 2.40 0.30 0.30
C1.12.2.2 515.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.06 2.31 2.56 0.30 0.30
C1.12.2.3 600.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.00 2.23 2.50 0.30 0.30
C1.12.2.4 755.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.28 2.54 2.78 0.30 0.30
C1.12.3.1 545.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.97 2.27 2.47 0.30 0.30

Groupement MCG / SAFI 154


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.12.3.2 960.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 2.18 2.46 2.68 0.30 0.30
C1.15.2.1 281.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.64 1.87 2.14 0.30 0.30
C1.15.2.2 385.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.49 1.76 1.99 0.30 0.30
C1.15.2.3 330.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.47 1.71 1.97 0.30 0.30
C1.15.2.4 340.0 115 0.50 30.00 0.1% 1.50 0.41 0.20 0.3 0.50 2.30 0.60 1.37 1.78 1.97 0.30 0.30
C1.15.2.5 1410.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.81 2.07 2.31 0.30 0.30
C1.15.2.6 370.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.29 1.57 1.79 0.30 0.30
C1.16.1.1 860.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.23 2.48 2.73 0.30 0.30
C1.16.1.2 1070.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 2.44 2.72 2.94 0.30 0.30
C1.16.1.3 1160.0 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 2.48 2.80 2.98 0.30 0.30
C1.17.2.1 264.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.73 1.96 2.23 0.30 0.30
C1.17.2.2 490.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.45 1.71 1.95 0.30 0.30
C1.17.2.3 1010.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.31 1.55 1.81 0.30 0.30
C1.17.2.4 350.0 55 0.30 30.00 0.1% 1.50 0.33 0.20 0.2 0.30 1.80 0.50 1.28 1.60 1.78 0.30 0.30
C1.17.2.5 230.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 0.92 1.14 1.42 0.30 0.30
C1.21.2.1 505.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.95 2.24 2.45 0.30 0.30
C1.21.2.2 605.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.00 2.23 2.50 0.30 0.30
C1.21.3.1 480.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.84 2.09 2.34 0.30 0.30
C1.21.3.2 440.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.92 2.17 2.42 0.30 0.30
C1.21.3.3 430.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.22 2.44 2.72 0.30 0.30
C1.21.3.4 530.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.07 2.27 2.57 0.30 0.30
C1.22.1.1 405.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.90 2.20 2.40 0.30 0.30
C1.22.1.2 405.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.90 2.17 2.40 0.30 0.30
C1.22.2.1 800.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 2.30 2.58 2.80 0.30 0.30
C1.22.2.2 770.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.99 2.21 2.49 0.30 0.30
C1.22.2.3 315.0 80 0.30 30.00 0.1% 1.50 0.39 0.20 0.2 0.30 2.10 0.60 1.66 2.05 2.26 0.30 0.30
C1.22.2.4 650.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.83 2.05 2.33 0.30 0.30
C1.22.2.5 620.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.81 2.01 2.31 0.30 0.30
C1.22.2.6 595.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.80 2.02 2.30 0.30 0.30
C1.22.2.7 490.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.75 1.99 2.25 0.30 0.30
C1.22.2.8 750.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.98 2.20 2.48 0.30 0.30
C1.23.1.1 620.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.01 2.26 2.51 0.30 0.30
C1.23.1.2 720.0 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 2.06 2.38 2.56 0.30 0.30

Groupement MCG / SAFI 155


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.23.1.3 615.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 2.01 2.29 2.51 0.30 0.30
C1.23.1.4 615.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 2.01 2.31 2.51 0.30 0.30
C1.23.1.5 318.0 75 0.30 30.00 0.1% 1.50 0.38 0.20 0.2 0.30 2.10 0.60 1.86 2.24 2.46 0.30 0.30
C1.23.1.6 850.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.13 2.37 2.63 0.30 0.30

Tableau n° 83 : Récapitulatif de dimensionnement des canaux quinquénaires (C-1)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quinquénaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C1.5.4.1.1 185.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.89 2.10 2.39 0.30 0.30
C1.5.4.1.2 250.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.93 2.17 2.43 0.30 0.30
C1.5.4.1.3 600.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.10 2.30 2.60 0.30 0.30
C1.6.2.2.1 302.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.55 1.82 2.05 0.30 0.30
C1.6.2.2.2 730.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.37 1.59 1.87 0.30 0.30
C1.6.2.2.3 305.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.65 1.90 2.15 0.30 0.30
C1.6.2.2.4 115.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.46 1.68 1.96 0.30 0.30
C1.6.1.2.1 460.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.03 1.30 1.53 0.30 0.30
C1.6.1.2.2 510.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.26 1.52 1.76 0.30 0.30
C1.6.1.4.1 460.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.43 1.71 1.93 0.30 0.30
C1.6.1.4.2 410.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.61 1.90 2.11 0.30 0.30
C1.8.1.1.1 575.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.79 1.99 2.29 0.30 0.30
C1.8.1.1.2 513.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.56 1.86 2.06 0.30 0.30
C1.8.1.1.3 440.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.72 1.97 2.22 0.30 0.30
C1.8.1.1.4 845.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.72 1.97 2.22 0.30 0.30
C1.8.1.1.5 425.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.51 1.76 2.01 0.30 0.30
C1.8.1.1.6 610.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.51 1.71 2.01 0.30 0.30
C1.8.1.3.1 250.0 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.33 1.50 1.83 0.30 0.30
C1.8.1.3.2 252.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.43 1.65 1.93 0.30 0.30
C.1.8.1.5.1 200.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.40 1.65 1.90 0.30 0.30
C.1.8.1.5.2 590.0 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 1.70 2.01 2.20 0.30 0.30
C.1.8.1.5.3 265.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.03 1.30 1.53 0.30 0.30

Groupement MCG / SAFI 156


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quinquénaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C.1.8.1.5.4 425.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.51 1.76 2.01 0.30 0.30
C1.15.2.4.1 660.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.33 1.58 1.83 0.30 0.30
C1.15.2.4.2 600.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.40 1.70 1.90 0.30 0.30
C1.15.2.4.3 800.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.60 1.88 2.10 0.30 0.30
C1.17.2.4.1 330.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.27 1.47 1.77 0.30 0.30
C1.17.2.4.2 480.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.44 1.69 1.94 0.30 0.30
C1.22.2.3.1 430.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.82 2.04 2.32 0.30 0.30
C1.22.2.3.2 405.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.80 2.03 2.30 0.30 0.30
C1.22.2.3.3 650.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.93 2.15 2.43 0.30 0.30
C1.23.1.5.1 440.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.92 2.15 2.42 0.30 0.30
C1.23.1.5.2 450.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.83 2.05 2.33 0.30 0.30
C1.23.1.5.3 650.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.83 2.05 2.33 0.30 0.30

Tableau n° 84 : Récapitulatif de dimensionnement des canaux secondaire (C-3)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
secondaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C3.1 380.0 40 0.30 30.00 0.1% 1.50 0.28 0.30 0.2 0.30 1.80 0.50 1.69 1.97 2.19 0.30 0.30
C3.5 510.0 20 0.30 30.00 0.1% 1.50 0.20 0.30 0.2 0.30 1.80 0.50 1.86 2.06 2.36 0.30 0.30
C3.10 700.0 340 1.00 30.00 0.1% 1.50 0.56 0.30 0.3 1.00 3.40 0.80 2.05 2.61 2.85 0.50 0.50
C3.11 1100.0 45 0.30 30.00 0.1% 1.50 0.30 0.30 0.2 0.30 2.10 0.60 1.95 2.25 2.55 0.30 0.30
C3.13 480.0 50 0.30 30.00 0.1% 1.50 0.32 0.30 0.2 0.30 2.10 0.60 1.74 2.06 2.34 0.30 0.30
C3.15 310.0 30 0.30 30.00 0.1% 1.50 0.25 0.30 0.2 0.30 2.10 0.60 1.06 1.30 1.66 0.30 0.30
C3.17 460.0 50 0.30 30.00 0.1% 1.50 0.32 0.30 0.2 0.30 2.10 0.60 1.88 2.20 2.48 0.30 0.30
C3.18 300.0 35 0.30 30.00 0.1% 1.50 0.27 0.30 0.2 0.30 2.10 0.60 1.45 1.72 2.05 0.30 0.30

Tableau n° 85 : Récapitulatif de dimensionnement des canaux tertiaires (C-3)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)

Groupement MCG / SAFI 157


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C3.2.1 460.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.73 2.00 2.23 0.30 0.30
C3.2.2 640.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.62 1.89 2.12 0.30 0.30
C3.2.3 440.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.87 2.14 2.37 0.30 0.30
C3.3.1 660.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.93 2.20 2.43 0.30 0.30
C3.3.2 1050.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.98 2.27 2.48 0.30 0.30
C3.4.1 270.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.74 1.96 2.24 0.30 0.30
C3.4.2 325.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.61 1.90 2.11 0.30 0.30
C3.4.3 250.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.53 1.75 2.03 0.30 0.30
C3.6.1 345.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.42 1.67 1.92 0.30 0.30
C3.6.2 305.0 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 1.30 1.62 1.80 0.30 0.30
C3.6.3 310.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.56 1.80 2.06 0.30 0.30
C3.7.1 670.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.84 2.08 2.34 0.30 0.30
C3.7.2 920.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.46 1.71 1.96 0.30 0.30
C3.7.3 600.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.60 1.85 2.10 0.30 0.30
C3.8.1 520.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.56 1.83 2.06 0.30 0.30
C3.8.2 490.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.75 2.01 2.25 0.30 0.30
C3.9.1 390.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.70 1.94 2.20 0.30 0.30
C3.9.2 380.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.69 1.94 2.19 0.30 0.30
C3.10.1 510.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.66 1.92 2.16 0.30 0.30
C3.10.2 1480.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.44 2.69 2.94 0.30 0.30
C3.10.3 550.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.83 2.07 2.33 0.30 0.30
C3.10.4 430.0 85 0.30 30.00 0.1% 1.50 0.40 0.20 0.2 0.30 2.10 0.60 1.82 2.22 2.42 0.30 0.30
C3.10.5 360.0 115 0.50 30.00 0.1% 1.50 0.41 0.20 0.3 0.50 2.30 0.60 1.38 1.79 1.98 0.30 0.30
C3.10.6 1430.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 2.12 2.41 2.62 0.30 0.30
C3.12.1 365.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.58 1.83 2.08 0.30 0.30
C3.12.2 365.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.68 1.91 2.18 0.30 0.30
C3.14.1 460.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.63 1.88 2.13 0.30 0.30
C3.14.2 485.0 120 0.50 30.00 0.1% 1.50 0.42 0.20 0.3 0.50 2.30 0.60 1.44 1.86 2.04 0.30 0.30
C3.14.3 250.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.28 1.54 1.78 0.30 0.30
C3.16.1 290.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.45 1.69 1.95 0.30 0.30
C3.16.2 115.0 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.46 1.63 1.96 0.30 0.30
C3.17.1 270.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.79 2.05 2.29 0.30 0.30
C3.17.2 180.0 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.39 1.57 1.89 0.30 0.30

Groupement MCG / SAFI 158


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C3.19.1 830.0 130 0.50 30.00 0.1% 1.50 0.43 0.20 0.3 0.50 2.30 0.60 1.72 2.15 2.32 0.30 0.30
C3.19.2 120.0 165 0.50 30.00 0.1% 1.50 0.49 0.20 0.3 0.50 2.60 0.70 1.46 1.95 2.16 0.50 0.50

Tableau n° 86 : Récapitulatif de dimensionnement des canaux quaternaires (C-3)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C3.4.2.1 275.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.59 1.79 2.09 0.30 0.30
C3.4.2.2 260.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.23 1.43 1.73 0.30 0.30
C3.6.2.1 325.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.26 1.49 1.76 0.30 0.30
C3.6.2.2 325.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.31 1.54 1.81 0.30 0.30
C3.10.4.1 1640.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 2.32 2.60 2.82 0.30 0.30
C3.10.4.2 890.0 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 2.05 2.34 2.55 0.30 0.30
C3.10.5.1 535.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.47 1.75 1.97 0.30 0.30
C3.10.5.2 960.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.68 1.96 2.18 0.30 0.30
C3.10.5.3 850.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.63 1.89 2.13 0.30 0.30
C3.14.2.1 300.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.35 1.60 1.85 0.30 0.30
C3.14.2.2 305.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.20 1.45 1.70 0.30 0.30
C3.14.2.3 490.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.30 1.54 1.80 0.30 0.30
C3.14.2.4 405.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.00 1.25 1.50 0.30 0.30
C3.19.1.1 330.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.37 1.63 1.87 0.30 0.30
C3.19.1.2 445.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.37 1.64 1.87 0.30 0.30
C3.19.1.3 680.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.49 1.77 1.99 0.30 0.30
C3.19.1.4 370.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.49 1.69 1.99 0.30 0.30
C3.19.2.1 375.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.44 1.72 1.94 0.30 0.30
C3.19.2.2 470.0 85 0.30 30.00 0.1% 1.50 0.40 0.20 0.2 0.30 1.80 0.50 1.24 1.64 1.74 0.30 0.30
C3.19.2.3 295.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.55 1.83 2.05 0.30 0.30

Tableau n° 87 : Récapitulatif de dimensionnement des canaux quinquénaires (C-3)

Groupement MCG / SAFI 159


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quinquénaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C3.19.2.2.1 240.0 45.0 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.02 1.32 1.52 0.30 0.30
C3.19.2.2.2 385.0 40.0 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.19 1.48 1.69 0.30 0.30

Tableau n° 88 : Récapitulatif de dimensionnement des canaux secondaires (C-2)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
secondaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C2.1 119.6 60 0.30 30.00 0.1% 1.50 0.34 0.30 0.2 0.30 2.10 0.60 1.66 2.00 2.26 0.30 0.30
C2.6 171.7 140 0.50 30.00 0.1% 1.50 0.45 0.30 0.3 0.50 2.60 0.70 1.69 2.14 2.39 0.50 0.50
C2.8 268.7 25 0.30 30.00 0.1% 1.50 0.23 0.30 0.2 0.30 1.80 0.50 1.63 1.86 2.13 0.30 0.30
C2.9 428.8 20 0.30 30.00 0.1% 1.50 0.20 0.30 0.2 0.30 1.80 0.50 1.71 1.92 2.21 0.30 0.30
C2.11 266.3 30 0.30 30.00 0.1% 1.50 0.25 0.30 0.2 0.30 2.10 0.60 1.73 1.98 2.33 0.30 0.30
C2.13 231.4 430 1.50 30.00 0.1% 1.50 0.54 0.30 0.3 1.50 4.20 0.90 2.12 2.66 3.02 0.50 0.50
C2.15 628.0 245 0.50 30.00 0.1% 1.50 0.58 0.30 0.3 0.50 3.20 0.90 2.11 2.70 3.01 0.50 0.50
C2.18 1073.1 35 0.30 30.00 0.1% 1.50 0.27 0.30 0.2 0.30 2.10 0.60 2.04 2.30 2.64 0.30 0.30

Tableau n° 89 : Récapitulatif de dimensionnement des canaux tertiaires (C-2)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 2.1-1 401.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.86 2.09 2.36 0.30 0.30
C 2.1-2 1060.6 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.44 2.71 2.94 0.30 0.30
C2.2.1 468.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.93 2.14 2.43 0.30 0.30
C2.2.2 313.8 10 0.30 30.00 0.1% 1.50 0.14 0.20 0.1 0.30 1.80 0.50 1.74 1.88 2.24 0.30 0.30
C2.2.3 471.1 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.74 1.96 2.24 0.30 0.30
C 2.3.1 210.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.71 1.93 2.21 0.30 0.30
C 2.3.2 296.4 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.55 1.85 2.05 0.30 0.30
C 2.3.3 197.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.65 1.88 2.15 0.30 0.30
C 2.4.1 356.2 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.58 1.84 2.08 0.30 0.30

Groupement MCG / SAFI 160


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 2.4.2 362.6 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.68 1.97 2.18 0.30 0.30
C 2.4.3 445.5 75 0.30 30.00 0.1% 1.50 0.38 0.20 0.2 0.30 2.10 0.60 1.72 2.10 2.32 0.30 0.30
C 2.5.1 250.8 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.57 1.81 2.07 0.30 0.30
C 2.5.2 662.3 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.63 1.88 2.13 0.30 0.30
C 2.5.3 390.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.40 1.62 1.90 0.30 0.30
C2.6.1 1557.9 125 0.50 30.00 0.1% 1.50 0.43 0.20 0.3 0.50 2.00 0.50 2.58 3.00 3.08 0.30 0.30
C2.6.2 369.4 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.78 1.96 2.28 0.30 0.30
C2.7.1 471.9 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.64 1.92 2.14 0.30 0.30
C2.7.2 240.7 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.52 1.70 2.02 0.30 0.30
C2.10.1 613.1 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.41 1.63 1.91 0.30 0.30
C2.10.2 161.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.58 1.81 2.08 0.30 0.30
C 2.12.1 0.0 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.40 1.67 1.90 0.30 0.30
C 2.12.2 333.0 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.27 1.55 1.77 0.30 0.30
C 2.12.3 197.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.40 1.63 1.90 0.30 0.30
C 2.13.1 1915.6 250 0.50 30.00 0.1% 1.50 0.59 0.20 0.3 0.50 2.90 0.80 2.96 3.55 3.76 0.50 0.50
C2.13.2 1176.4 180 0.50 30.00 0.1% 1.50 0.51 0.20 0.3 0.50 2.60 0.70 2.39 2.89 3.09 0.50 0.50
C 2.14.1 203.1 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.40 1.63 1.90 0.30 0.30
C 2.14.2 276.1 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 1.29 1.60 1.79 0.30 0.30
C 2.14.3 179.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.64 1.87 2.14 0.30 0.30
C 2.15.1 490.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.89 2.14 2.39 0.30 0.30
C 2.15.2 404.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.80 2.03 2.30 0.30 0.30
C 2.15.3 457.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.85 2.08 2.35 0.30 0.30
C 2.15.4 746.6 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.17 2.38 2.67 0.30 0.30
C 2.15.5 736.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.17 2.37 2.67 0.30 0.30
C 2.15.6 646.7 60 0.30 30.00 0.1% 1.50 0.34 0.20 0.2 0.30 1.80 0.50 2.12 2.47 2.62 0.30 0.30
C 2.15.7 642.9 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.12 2.39 2.62 0.30 0.30
C 2.15.8 894.2 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.25 2.49 2.75 0.30 0.30
C 2.16.1 174.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.49 1.71 1.99 0.30 0.30
C 2.16.2 269.9 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 1.28 1.60 1.78 0.30 0.30
C 2.16.3 174.4 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.49 1.71 1.99 0.30 0.30
C 2.17.1 568.1 155 0.50 30.00 0.1% 1.50 0.47 0.20 0.3 0.50 2.30 0.60 1.68 2.16 2.28 0.30 0.30
C 2.17.2 622.3 190 0.50 30.00 0.1% 1.50 0.52 0.20 0.3 0.50 2.60 0.70 1.81 2.33 2.51 0.50 0.50
C 2.17.3 407.1 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.60 1.87 2.10 0.30 0.30

Groupement MCG / SAFI 161


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 2.19.1 902.1 210 0.50 30.00 0.1% 1.50 0.54 0.20 0.3 0.50 2.60 0.70 1.85 2.39 2.55 0.50 0.50
C 2.19.2 982.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.89 2.12 2.39 0.30 0.30

Tableau n° 90 : Récapitulatif de dimensionnement des canaux quaternaires (C-2)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 2.3.2.1 191.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.40 1.60 1.90 0.30 0.30
C 2.3.2.2 203.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.50 1.73 2.00 0.30 0.30
C 2.4.3.1 343.5 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.67 1.96 2.17 0.30 0.30
C 2.4.3.2 343.8 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.67 1.94 2.17 0.30 0.30
C 2.6.1.1 132.6 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.72 1.89 2.22 0.30 0.30
C 2.6.1.2 519.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.93 2.13 2.43 0.30 0.30
C 2.6.1.3 466.3 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.03 2.24 2.53 0.30 0.30
C 2.6.1.4 448.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.92 2.13 2.42 0.30 0.30
C 2.6.1.5 454.9 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.03 2.23 2.53 0.30 0.30
C 2.6.1.6 410.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.01 2.21 2.51 0.30 0.30
C 2.6.1.7 511.6 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 2.06 2.23 2.56 0.30 0.30
C 2.12.2.1 186.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.13 1.34 1.63 0.30 0.30
C 2.12.2.2 181.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.19 1.39 1.69 0.30 0.30
C 2.13.1.1 499.6 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.95 2.20 2.45 0.30 0.30
C 2.13.1.2 350.9 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.68 1.92 2.18 0.30 0.30
C 2.13.1.3 383.7 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.89 2.14 2.39 0.30 0.30
C 2.13.1.4 194.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.60 1.80 2.10 0.30 0.30
C 2.13.1.5 231.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.82 2.04 2.32 0.30 0.30
C 2.13.1.6 159.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.78 2.01 2.28 0.30 0.30
C 2.13.1.7 963.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.18 2.39 2.68 0.30 0.30
C 2.13.1.8 80.6 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.94 2.12 2.44 0.30 0.30
C 2.13.1.9 263.7 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.93 2.18 2.43 0.30 0.30
C 2.13.1.10 566.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.28 2.51 2.78 0.30 0.30
C 2.13.2.1 275.5 70 0.30 30.00 0.1% 1.50 0.37 0.20 0.2 0.30 2.10 0.60 1.94 2.31 2.54 0.30 0.30

Groupement MCG / SAFI 162


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 2.13.2.2 94.5 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.65 1.95 2.15 0.30 0.30
C 2.13.2.3 244.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.92 2.15 2.42 0.30 0.30
C 2.13.2.4 250.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.93 2.13 2.43 0.30 0.30
C 2.13.2.5 480.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.04 2.24 2.54 0.30 0.30
C 2.14.2.1 179.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.19 1.42 1.69 0.30 0.30
C 2.14.2.2 179.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.24 1.47 1.74 0.30 0.30
C 2.15.6.1 276.1 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.94 2.14 2.44 0.30 0.30
C 2.15.6.2 311.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.96 2.16 2.46 0.30 0.30
C 2.15.6.3 308.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.95 2.16 2.45 0.30 0.30
C 2.16.2.1 194.3 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.25 1.47 1.75 0.30 0.30
C 2.16.2.2 192.9 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.25 1.47 1.75 0.30 0.30
C 2.17.1.1 275.2 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.29 1.54 1.79 0.30 0.30
C 2.17.1.2 287.5 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.39 1.66 1.89 0.30 0.30
C 2.17.1.3 385.3 60 0.30 30.00 0.1% 1.50 0.34 0.20 0.2 0.30 1.80 0.50 1.46 1.81 1.96 0.30 0.30
C 2.17.1.4 345.1 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.57 1.82 2.07 0.30 0.30
C 2.17.2.1 514.8 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.76 2.04 2.26 0.30 0.30
C 2.17.2.2 1005.6 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 1.90 2.22 2.40 0.30 0.30
C 2.17.2.3 545.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.57 1.80 2.07 0.30 0.30
C 2.17.2.4 516.5 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.56 1.82 2.06 0.30 0.30
C 2.17.2.5 791.6 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.70 1.98 2.20 0.30 0.30
C 2.19.1.1 805.9 45 0.30 30.00 0.1% 1.50 0.30 0.20 0.2 0.30 1.80 0.50 1.80 2.10 2.30 0.30 0.30
C 2.19.1.2 514.5 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.66 1.92 2.16 0.30 0.30
C 2.19.1.3 735.6 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.77 1.99 2.27 0.30 0.30
C 2.19.1.4 778.2 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.79 1.97 2.29 0.30 0.30
C 2.19.1.5 791.4 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.80 2.02 2.30 0.30 0.30
C 2.19.1.6 799.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.80 2.00 2.30 0.30 0.30
C 2.19.1.7 817.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.81 2.01 2.31 0.30 0.30
C 2.19.1.8 656.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.73 1.95 2.23 0.30 0.30

Tableau n° 91 : Récapitulatif de dimensionnement des canaux quinquénaires (C-2)


Canal Linéaire Débit b (m) Coef Pente m Yn (m) Revanche V b B (m) h Cote de Cote Cote C1 (m) C2 (m)

Groupement MCG / SAFI 163


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

quinquénaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) retenue retenue calage Yn (m) plafond
(m) (m) (m) (m)
C 2.13.2.1.1 746.6 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.17 2.38 2.67 0.30 0.30
C 2.13.2.1.2 746.8 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 2.17 2.35 2.67 0.30 0.30
C 2.13.2.1.3 724.1 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 2.16 2.34 2.66 0.30 0.30
C 2.13.2.1.4 814.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.21 2.41 2.71 0.30 0.30
C 2.13.2.2.1 393.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.80 2.00 2.30 0.30 0.30
C 2.13.2.2.2 687.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.94 2.17 2.44 0.30 0.30
C 2.17.1.3.1 160.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.35 1.60 1.85 0.30 0.30
C 2.17.1.3.2 322.9 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.31 1.56 1.81 0.30 0.30

Tableau n° 92 : Récapitulatif de dimensionnement des canaux secondaires (C-4)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
secondaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C4.3 276.2 45 0.30 30.00 0.1% 1.50 0.30 0.30 0.2 0.30 2.10 0.60 1.29 1.59 1.89 0.30 0.30
C 4-8 724.8 115 0.50 30.00 0.1% 1.50 0.41 0.30 0.3 0.50 2.30 0.60 2.06 2.47 2.66 0.30 0.30
C4-9 501.2 90 0.30 30.00 0.1% 1.50 0.41 0.30 0.2 0.30 2.10 0.60 1.80 2.21 2.40 0.30 0.30
C4-12 912.1 130 0.50 30.00 0.1% 1.50 0.43 0.30 0.3 0.50 2.30 0.60 2.11 2.54 2.71 0.30 0.30
C4-14 341.9 60 0.30 30.00 0.1% 1.50 0.34 0.30 0.2 0.30 2.40 0.70 1.87 2.21 2.57 0.50 0.50
C4-17 655.1 100 0.50 30.00 0.1% 1.50 0.38 0.30 0.2 0.50 2.60 0.70 2.13 2.51 2.83 0.50 0.50
C4-18 946.9 135 0.50 30.00 0.1% 1.50 0.44 0.30 0.3 0.50 2.60 0.70 2.17 2.62 2.87 0.50 0.50

Tableau n° 93 : Récapitulatif de dimensionnement des canaux tertiaires (C-2)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 C2
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 4-1-1 724.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.96 2.17 2.46 0.30 0.30
C 4-1-2 577.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.99 2.19 2.49 0.30 0.30

Groupement MCG / SAFI 164


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 C2
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 4-2-1 312.5 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.16 1.33 1.66 0.30 0.30
C 4-2-2 310.6 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.21 1.41 1.71 0.30 0.30
C4.3.1 404.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.35 1.58 1.85 0.30 0.30
C4.3.2 223.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.26 1.47 1.76 0.30 0.30
C4.4.1 361.5 60 0.30 30.00 0.1% 1.50 0.34 0.20 0.2 0.30 1.80 0.50 1.83 2.17 2.33 0.30 0.30
C4.4.2 281.4 115 0.50 30.00 0.1% 1.50 0.41 0.20 0.3 0.50 2.30 0.60 1.74 2.15 2.34 0.30 0.30
C4.4.3 1122.5 55 0.30 30.00 0.1% 1.50 0.33 0.20 0.2 0.30 1.80 0.50 2.36 2.69 2.86 0.30 0.30
C 4-5-1 289.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.79 2.00 2.29 0.30 0.30
C 4-5-2 330.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.67 1.87 2.17 0.30 0.30
C 4-6-1 444.6 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.72 1.90 2.22 0.30 0.30
C 4-6-2 435.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.52 1.74 2.02 0.30 0.30
C 4-6-3 189.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.39 1.60 1.89 0.30 0.30
C 4-6-4 519.1 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.26 1.51 1.76 0.30 0.30
C 4-7-1 194.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.20 1.40 1.70 0.30 0.30
C 4-7-2 256.3 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.23 1.43 1.73 0.30 0.30
C 4-7-3 417.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.21 1.41 1.71 0.30 0.30
C4-8-1 470.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.64 1.86 2.14 0.30 0.30
C4-8-2 791.3 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.85 2.07 2.35 0.30 0.30
C4-8-3 466.7 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.73 1.98 2.23 0.30 0.30
C4-8-4 596.5 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.00 2.26 2.50 0.30 0.30
C4-9-1 504.8 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.65 1.92 2.15 0.30 0.30
C4-9-2 488.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.74 1.99 2.24 0.30 0.30
C4-9-3 635.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.87 2.09 2.37 0.30 0.30
C4-10-1 840.1 50 0.30 30.00 0.1% 1.50 0.32 0.20 0.2 0.30 1.80 0.50 2.07 2.39 2.57 0.30 0.30
C4-10-2 440.6 105 0.50 30.00 0.1% 1.50 0.39 0.20 0.2 0.50 2.00 0.50 1.87 2.26 2.37 0.30 0.30
C4-11-1 355.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.28 1.48 1.78 0.30 0.30
C4-11-2 359.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.08 1.28 1.58 0.30 0.30
C 4-12-1 351.0 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.58 1.80 2.08 0.30 0.30
C 4-12-2 313.8 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.81 1.98 2.31 0.30 0.30
C 4-12-3 389.8 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.84 2.05 2.34 0.30 0.30
C 4-12-4 394.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.80 2.00 2.30 0.30 0.30
C 4-12-5 398.7 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.80 2.00 2.30 0.30 0.30
C 4-12-6 565.0 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.88 2.13 2.38 0.30 0.30

Groupement MCG / SAFI 165


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 C2
tertiaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C4-13-1 442.0 65 0.30 30.00 0.1% 1.50 0.36 0.20 0.2 0.30 1.80 0.50 1.22 1.58 1.72 0.30 0.30
C4-13-2 321.7 25 0.30 30.00 0.1% 1.50 0.29 0.20 0.1 0.30 1.80 0.50 1.46 1.75 1.96 0.30 0.30
C4-13-3 417.8 40 0.30 30.00 0.1% 1.50 0.28 0.20 0.2 0.30 1.80 0.50 1.41 1.69 1.91 0.30 0.30
C4-13-4 452.6 60 0.30 30.00 0.1% 1.50 0.34 0.20 0.2 0.30 1.80 0.50 1.23 1.57 1.73 0.30 0.30
C4-14-1 437.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.77 1.97 2.27 0.30 0.30
C4-14-2 585.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.99 2.22 2.49 0.30 0.30
C4-14-3 844.1 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 2.12 2.30 2.62 0.30 0.30
C4-15-1 217.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.31 1.51 1.81 0.30 0.30
C4-15-2 342.0 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.42 1.62 1.92 0.30 0.30
C4-16-1 189.5 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.49 1.72 1.99 0.30 0.30
C4-16-2 337.2 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.62 1.85 2.12 0.30 0.30
C 4-17-1 213.0 10 0.30 30.00 0.1% 1.50 0.14 0.20 0.1 0.30 1.80 0.50 1.31 1.45 1.81 0.30 0.30
C 4-17-2 134.3 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.37 1.57 1.87 0.30 0.30
C 4-17-3 300.1 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.60 1.80 2.10 0.30 0.30
C 4-17-4 500.8 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.95 2.18 2.45 0.30 0.30
C 4-17-5 750.3 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.18 2.40 2.68 0.30 0.30
C 4-18-1 179.1 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.69 1.89 2.19 0.30 0.30
C 4-18-2 284.4 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.74 1.97 2.24 0.30 0.30
C 4-18-3 374.9 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.84 2.04 2.34 0.30 0.30
C 4-18-4 261.3 15 0.30 30.00 0.1% 1.50 0.18 0.20 0.2 0.30 1.80 0.50 1.78 1.96 2.28 0.30 0.30
C 4-18-5 370.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.89 2.11 2.39 0.30 0.30
C 4-18-6 606.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.95 2.20 2.45 0.30 0.30
C 4.19-1 382.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.39 1.64 1.89 0.30 0.30
C 4.19-2 1061.9 225 0.50 30.00 0.1% 1.50 0.56 0.20 0.3 0.50 2.60 0.70 1.73 2.29 2.43 0.50 0.50
C 4.19-3 748.6 145 0.30 30.00 0.1% 1.50 0.51 0.20 0.3 0.30 2.40 0.70 2.27 2.78 2.97 0.50 0.50

Tableau n° 94 : Récapitulatif de dimensionnement des canaux quaternaires (C-4)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 4-4-1-1 1126.1 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.16 2.39 2.66 0.30 0.30
C 4-4-1-2 1103.2 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.20 2.47 2.70 0.30 0.30

Groupement MCG / SAFI 166


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quaternaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 4-4-2-1 1131.1 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.17 2.37 2.67 0.30 0.30
C 4-4-2-2 1087.2 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.99 2.24 2.49 0.30 0.30
C 4-4-2-3 1152.4 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 2.13 2.39 2.63 0.30 0.30
C 4-4-2-4 1125.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 2.16 2.41 2.66 0.30 0.30
C4-10-2-1 848.3 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.87 2.08 2.37 0.30 0.30
C4-10-2-2 865.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.08 2.29 2.58 0.30 0.30
C4-10-2-3 842.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.92 2.12 2.42 0.30 0.30
C4-10-2-4 625.5 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.81 2.02 2.31 0.30 0.30
C4-10-2-5 764.3 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.93 2.16 2.43 0.30 0.30
C 4-13-1-1 307.6 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.15 1.42 1.65 0.30 0.30
C 4-13-1-2 306.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.10 1.35 1.60 0.30 0.30
C4-13-4-1 258.1 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.13 1.38 1.63 0.30 0.30
C4-13-4-2 385.5 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.19 1.44 1.69 0.30 0.30
C 4.19-2-1 591.1 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.50 1.74 2.00 0.30 0.30
C 4.19-2-2 598.7 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.45 1.68 1.95 0.30 0.30
C 4.19-2-3 549.2 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.42 1.63 1.92 0.30 0.30
C 4.19-2-4 703.1 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.45 1.68 1.95 0.30 0.30
C 4.19-2-5 743.4 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.52 1.79 2.02 0.30 0.30
C 4.19-2-6 606.9 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.40 1.67 1.90 0.30 0.30
C 4.19-2-7 451.9 30 0.30 30.00 0.1% 1.50 0.25 0.20 0.2 0.30 1.80 0.50 1.33 1.57 1.83 0.30 0.30
C 4.19-2-8 654.4 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 1.53 1.75 2.03 0.30 0.30
C 4.19-3-1 610.2 55 0.30 30.00 0.1% 1.50 0.33 0.20 0.2 0.30 1.80 0.50 2.21 2.53 2.71 0.30 0.30
C 4.19-3-2 420.4 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 1.91 2.11 2.41 0.30 0.30
C 4.19-3-3 388.1 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.54 1.81 2.04 0.30 0.30
C 4.19-3-4 294.7 35 0.30 30.00 0.1% 1.50 0.27 0.20 0.2 0.30 1.80 0.50 1.50 1.76 2.00 0.30 0.30

Tableau n° 95 : Récapitulatif de dimensionnement des canaux quinquénaire(C-4)


b h Cote de Cote
Canal Linéaire Débit Coef Pente m Revanche V Cote
b (m) Yn (m) retenue B (m) retenue calage plafond C1 (m) C2 (m)
quinquénaire (ml) (l/s) Manning (m/m) (m/m) (m) (m/s) Yn (m)
(m) (m) (m) (m)
C 4.19-3-1-1 420.9 25 0.30 30.00 0.1% 1.50 0.23 0.20 0.2 0.30 1.80 0.50 2.01 2.24 2.51 0.30 0.30

Groupement MCG / SAFI 167


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

C 4.19-3-1-2 234.6 20 0.30 30.00 0.1% 1.50 0.20 0.20 0.2 0.30 1.80 0.50 2.02 2.22 2.52 0.30 0.30
C 4.19-3-1-3 236.5 10 0.30 30.00 0.1% 1.50 0.14 0.20 0.1 0.30 1.80 0.50 1.92 2.06 2.42 0.30 0.30

Groupement MCG / SAFI 168


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.4 OUVRAGE SUR CANAUX D’IRRIGATION

Actions de réhabilitation retenues

L’opération de réhabilitation des ouvrages sur les canaux d’irrigation concerne tous les ouvrages du
réseau. Les actions retenues touchent aussi bien le génie civil et les équipements et sont comme suit :

 Renouvellement des tous les ouvrages sur le réseau,

 Implantation des nouveaux ouvrages de contrôle et de distribution.

Ouvrage sur canaux principaux

Les ouvrages sur canaux d'irrigation sont :

- Ouvrages de répartitions,

- Partiteurs modulés,

- Ouvrages de transitions,

- Ouvrages de franchissements,

- Vanne de control,

- Ouvrages de traversée.

6.4.2.1 Ouvrage Partiteur

Les partiteurs principaux sont situés aux points de départ des canaux principaux C-2, C-3 et C-4. Le
partiteur principal est un ouvrage en forme de dalot et les dimensions de la caisse sont indiquées ci-
après :

Tableau n° 96 : Coordonnées des ouvrages partiteurs


Coordonnées
Ouvrage
X(m) Y(m)
D1/C1 381287.1 1806184.8
D2/C1 381431.4 1806005.6
D3/C1 381969.0 1805806.2

Tableau n° 97 : Dimension des partiteurs principaux


Débit Largeur Hauteur Longueur
Canal Ouvrage Equipement
(l/s) (m) (m) (m)
C-2 D1/C1 2390.0 4 2 4 Vanne murale 2(2x1.0)
C-3 D2/C1 1795.0 4 2 4 Vanne murale 2(2x1.0)
C-4 D3/C1 2045.0 4 2 4 Vanne murale 2(2x1.0)

Groupement MCG / SAFI 169


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Groupement MCG / SAFI 170


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

7-Localisation OP (A4)

Groupement MCG / SAFI 171


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.4.2.2 Ouvrage partiteur modulé

Les ouvrages modulés sont des ouvrages de distribution et de contrôle de débit, ils sont implantés au
niveau des canaux principaux. Le contrôle de débit est assuré par des module a masque en amont et
en aval de l’ouvrage

Les coordonnées et les dimensions des ouvrages modulés sont présentés dans les tableaux suivant :

Tableau n° 98 : Ouvrages modulés sur canal C-1


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
M1/C1 382069.0 1805756.6 M12/C1 384724.9 1804341.6
M2/C1 382281.8 1805652.1 M13/C1 384773.1 1804354.2
M3/C1 382604.5 1805639.6 M14/C1 384865.6 1804343.8
M4/C1 383149.7 1805260.1 M15/C1 385129.0 1804265.0
M5/C1 383140.3 1805187.5 M16/C1 385253.2 1804226.7
M5 bis/C1 383107.1 1804964.2 M17/C1 385708.9 1804086.7
M6/C1 382904.5 1804544.1 M18/C1 385730.6 1804079.9
M7/C1 383259.9 1804242.7 M19/C1 385922.9 1804173.4
M8/C1 383465.7 1804080.1 M20/C1 385953.7 1804253.3
M9/C1 383505.7 1804144.9 M21/C1 386031.9 1804448.8
M10/C1 383973.9 1804210.6 M22/C1 386934.6 1805875.3
M11/C1 384149.2 1804122.9 M23/C1 387803.7 1807132.0

Tableau n° 99 : Ouvrages modulés sur canal C-2


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
M1/C2 381402.7 1806244.5 M11/C2 384293.2 1807498.8
M2/C2 381847.8 1806454.6 M12/C2 384301.4 1807503.6
M3/C2 382112.0 1806819.9 M13/C2 384795.1 1807805.4
M4/C2 382383.4 1807372.6 M14/C2 384803.5 1807811.0
M5/C2 382763.2 1807894.4 M15/C2 385285.8 1808196.1
M6/C2 383513.9 1807952.3 M16/C2 385300.7 1808205.1
M7/C2 383593.6 1807694.8 M17/C2 385998.3 1808509.3
M8/C2 383734.0 1807524.4 M18/C2 386171.3 1808597.7
M9/C2 383892.1 1807330.9 M19/C2 387223.5 1809118.1
M10/C2 383899.1 1807328.9

Tableau n° 100 : Ouvrages modulés sur canal C-3


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
M1/C3 381383.9 1805902.9 M11/C3 380786.9 1802197.9
M2/C3 381228.0 1805261.2 M12/C3 381032.3 1802205.1
M3/C3 381223.8 1805098.1 M13/C3 381495.3 1802219.3
M4/C3 381106.4 1804698.2 M14/C3 381764.7 1802342.7
M5/C3 381013.7 1804504.2 M15/C3 381945.4 1802263.5
M6/C3 380789.7 1804068.7 M16/C3 382162.0 1801742.1
M7/C3 380663.3 1803562.5 M17/C3 382189.1 1801592.9
M8/C3 380635.4 1803234.6 M18/C3 382451.9 1801533.9

Groupement MCG / SAFI 172


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
M9/C3 380456.9 1802772.0 M19/C3 382718.7 1801522.1
M10/C3 380313.6 1802517.0

Tableau n° 101 : Ouvrages modulés sur canal C-4


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
M1/C4 382018.1 1805815.2 M11/C4 385562.0 1806289.7
M2/C4 383099.0 1806161.9 M12/C4 385546.6 1806619.2
M3/C4 383246.1 1806317.2 M13/C4 385549.7 1806681.8
M4/C4 383369.2 1806316.8 M14/C4 386021.5 1806840.6
M5/C4 383513.8 1806300.6 M15/C4 386140.2 1806918.6
M6/C4 384243.0 1806223.6 M16/C4 386471.1 1807476.0
M7/C4 384812.3 1806162.5 M17/C4 386727.9 1807401.2
M8/C4 385158.8 1805906.8 M18/C4 386924.0 1807481.1
M9/C4 385570.6 1805964.5 M19/C4 387258.1 1807672.4
M10/C4 385575.1 1806013.6

Tableau n° 102 : Dimensionnement des ouvrage modulé sur C-1


Buse
Calibre B (m) H (m) Calibre
d'entrée
Ouvrage de de
D
masque L masque
entrée B1 B2 B3 B4 H1 H2 H3 H4
nominale (m) nominal
(mm)
XX1-30
M1/C1 XX1-60 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-30
M2/C1 XX1-40 300 10 0.3 - - 0.7 - -
XX1-30
M3/C1 XX1-60 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-30
XX1-30
M4/C1 XX1-70 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20
XX1-20
M5/C1 XX1-150 500 10 0.5 - - - 0.7 - - - -
M5
XX1-60 300 10 0.3 - - - 0.7 - - - -
bis/C1
M6/C1 XX1-380 600 10 1 - - - 0.9 - - - -
XX1-50
XX1-30
M7/C1 XX1-170 500 10 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-60
XX1-20
M8/C1 L1-500 700 1.5 - - - 0.9 - - - -
M9/C1 XX1-50 300 10 0.3 - - - 0.6 - - - -
M10/C1 XX1-40 300 10 0.3 - - - 0.6 - - - -
XX1-20
M11/C1 XX1-60 300 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20
XX1-20
XX1-20
M12/C1 XX1-210 500 10 0.3 0.5 0.3 - 0.5 0.6 0.6 - XX1-110
XX1-80
M13/C1 XX1-30 300 10 0.3 - - - 0.6 - - - -
M14/C1 XX1-100 400 10 0.5 - - - 0.6 - - - -
M15/C1 XX1-330 600 10 0.3 0.5 0.3 - 0.5 0.7 0.5 - XX1-20

Groupement MCG / SAFI 173


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Buse
Calibre B (m) H (m) Calibre
d'entrée
Ouvrage de de
D
masque L masque
entrée B1 B2 B3 B4 H1 H2 H3 H4
nominale (m) nominal
(mm)
XX1-280
XX1-30
XX1-120
M16/C1 XX1-150 500 10 0.5 0.3 - - 0.6 0.5 - -
XX1-30
XX1-30
M17/C1 XX-200 500 10 0.3 0.5 - - 0.5 0.7 - -
XX1-170
M18/C1 XX1-20 300 10 0.3 - - - 0.6 - - - -
M19/C1 XX1-40 300 10 0.3 - - - 0.6 - - - -
M20/C1 XX1-30 300 10 0.3 - - - 0.6 - - - -
XX1-30
XX1-60
M21/C1 XX1-230 500 10 0.3 0.3 0.3 0.3 0.5 0.5 0.6 0.5
XX1-100
XX1-30
XX1-80
M22/C1 XX1-380 600 10 0.3 0.5 0.3 - 0.5 0.8 0.5 - XX1-270
XX1-30
XX1-270
M23/C1 XX-310 600 10 0.5 0.3 - - 0.8 0.5 - -
XX1-40

Tableau n° 103 : Dimensionnement des ouvrage modulé sur C-2


Buse
Calibre B (m) H (m) Calibre
d'entrée
de de
Ouvrage D
masque L masque
entrée B1 B2 B3 B4 H1 H2 H3 H4
nominal (m) nominal
(mm)
M1/C2 XX1-60 300 10 0.3 - - - 0.6 - - -
XX1-20
M2/C2 XX1-50 300 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20
XX1-20
XX1-20
M3/C2 XX1-95 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-40
XX1-20
XX1-30
M4/C2 XX1-150 500 10 0.3 0.3 0.3 - 0.5 0.5 0.6 - XX1-40
XX1-70
XX1-30
M5/C2 XX1-80 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30
XX1-20
M6/C2 XX1-140 400 10 0.5 - - - 0.7 - - - -
XX1-40
M7/C2 XX1-50 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M8/C2 XX1-20 300 10 0.3 - - - 0.5 - - - -
M9/C2 XX1-20 300 10 0.3 - - - 0.5 - - - -
XX1-20
M10/C2 XX1-50 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M11/C2 XX1-30 300 10 0.3 - - - 0.6 - - - -
XX1-30
M12/C2 XX1-100 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-40
XX1-20
M13/C2 XX1-430 700 10 1.5 - - - 0.9 - - - -
M14/C2 XX1-100 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20

Groupement MCG / SAFI 174


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Calibre Buse Calibre


B (m) H (m)
Ouvrage de d'entrée de
masque D L B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal entrée (m) nominal
XX1-50
(mm) XX1-20
M15/C2 XX1-240 500 10 0.5 - - - 0.9 - - - -
XX1-20
M16/C2 XX1-100 400 10 0.3 0.3 0.3 0.5 0.5 0.5 XX1-50
XX1-20
XX-150
M17/C2 XX1-380 600 10 0.5 0.5 0.3 - 0.6 0.7 0.5 - XX1-190
XX1-30
M18/C2 XX1-30 300 10 0.3 - - - 0.6 - - - -
XX1-210
M19/C2 XX1-230 500 10 0.5 0.3 - - 0.7 0.5 - -
XX1-20

Tableau n° 104 : Dimensionnement des ouvrage modulé sur C-3


Buse
Calibre B (m) H (m) Calibre
d'entrée
de de
Ouvrage D
masque L masque
entrée B1 B2 B3 B4 H1 H2 H3 H4
nominal (m) nominal
(mm)
M1/C3 XX1-40 300 10 0.3 - - - 0.5 - - - -
XX1-30
M2/C3 XX1-100 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30
XX1-30
XX1-30
M3/C3 XX1-80 400 10 0.3 0.3 - - 0.5 0.5 - -
XX1-40
XX1-20
M4/C3 XX1-90 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-40
XX1-20
M5/C3 XX1-20 300 10 0.3 - - - 0.5 - - - -
XX1-30
M6/C3 XX1-110 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-50
XX1-30
XX1-30
M7/C3 XX1-90 400 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30
XX1-30
XX1-30
M8/C3 XX1-70 400 10 0.3 0.3 - - 0.5 0.5 - -
XX1-30
XX1-30
M9/C3 XX1-60 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-30
M10/C3 XX1-340 600 10 0.7 - - - 0.8 - - - -
M11/C3 XX1-40 300 10 0.3 - - - 0.6 - - - -
XX1-30
M12/C3 XX1-50 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M13/C3 XX1-50 300 10 0.3 - - - 0.6 - - - -
XX1-30
M14/C3 XX1-180 500 10 0.3 0.5 0.3 - 0.5 0.6 0.5 - XX1-120
XX1-30
M15/C3 XX1-30 300 10 0.3 - - - 0.6 - - - -
XX1-30
M16/C3 XX1-40 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20

Groupement MCG / SAFI 175


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Calibre Buse Calibre


B (m) H (m)
Ouvrage de d'entrée de
masque D L B1 B2 B3 B4 H1 H2 H3 H4 masque
M17/C3 nominal
XX1-50 entrée
300 (m)
10 0.3 - - - 0.6 - - - nominal
-
M18/C3 XX1-30 (mm)
300 10 0.3 - - - 0.6 - - - -
XX1-130
M19/C3 XX1-290 600 10 0.5 0.5 - - 0.6 0.7 - -
XX1-160

Tableau n° 105 : Dimensionnement des ouvrage modulé sur C-4

Buse
Calibre B (m) H (m) Calibre
d'entrée
de de
Ouvrage D
masque L masque
entrée B1 B2 B3 B4 H1 H2 H3 H4
nominal (m) nominal
(mm)
XX1-20
M1/C4 XX1-40 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
XX1-20
M2/C4 XX1-30 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M3/C4 XX1-40 300 10 0.3 - - - 0.6 - - - -
XX1-60
M4/C4 XX1-230 500 10 0.3 0.5 0.3 - 0.5 0.6 0.5 - XX1-110
XX1-50
XX1-20
M5/C4 XX1-40 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
XX1-20
XX1-20
M6/C4 XX1-90 400 10 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-20
XX1-30
XX1-20
M7/C4 XX1-60 300 10 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20
XX1-20
M8/C4 XX1-110 400 10 0.5 - - - 0.6 - - - -
M9/C4 XX1-90 400 10 0.3 - - - 0.6 - - - -
XX1-50
M10/C4 XX1-150 500 10 0.3 0.5 - - 0.5 0.5 - -
XX1-100
XX1-20
M11/C4 XX1-40 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M12/C4 XX1-130 400 10 0.5 - - - 0.6 - - - -
XX1-60
XX1-20
M13/C4 XX1-190 500 10 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-40
XX1-60
M14/C4 XX1-60 300 10 0.3 - - - 0.7 - - - -
XX1-20
M15/C4 XX1-40 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
XX1-20
M16/C4 XX1-50 300 10 0.3 0.3 - - 0.5 0.5 - -
XX1-20
M17/C4 XX1-100 400 10 0.5 - - - 0.7 - - - -
M18/C4 XX1-130 400 10 0.5 - - - 0.7 - - - -
XX1-30
M19/C4 XX1-400 600 10 0.3 0.3 0.3 - 0.5 0.7 0.7 - XX1-220
XX1-140

Groupement MCG / SAFI 176


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.4.2.3 Ouvrage de transition

Un ouvrage de transition sera projeté en aval de la station de pompage, les coordonnées de cet
ouvrage sont comme suit :

Tableau n° 106 : Coordonnées d’ouvrage de transition


Coordonnées
Ouvrage Nom Technique
X(m) Y(m)
TR-1 Ouvrage de transition 381196.5 1806292.7
6.4.2.4 Ouvrage de franchissement

Deux ouvrages principaux de franchissement sont situés au niveau des canaux C-1 (croisement avec
le drain Kassack) et C-4 (croisement avec le canal de drainage D-1). Les coordonnées et les
dimensions de ces ouvrages de franchissement sont données dans les tableaux suivant :

Tableau n° 107 : Coordonnées des ouvrages de franchissement


Coordonnées
Ouvrage
X(m) Y(m)
OF-1 384340.9 1804030.2
OF-2 384551.4 1806191.1

Tableau n° 108 : Dimension ouvrage de franchissement


Canal Ouvrage Canal Drain Observation
C1 OF-1 Canal (4x2) 4 dalots (2x1.5) irrigation (4x2) sur drain kassack (8x1.5)
C4 OF-2 Canal (3x2) 4 dalots (2x1.0) irrigation (3x2) sur drain D-1(8x1)

Groupement MCG / SAFI 177


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

8-Localisation OF (A4)

Groupement MCG / SAFI 178


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.4.2.5 Vanne de contrôle

Trois vannes de contrôle seront projetées sur le canal principale C-1 au niveau des partiteurs
principaux afin d’améliorer la gestion du périmètre et la maitrise d’eau.

Le rôle joué par la vanne est le suivant;

 Isolation d’un ou de plusieurs canaux,

 Distribution normale d’eau,

 Contrôle du surplus d'eau refoulée,

 Maintenance et travaux de réparations pour le canal à l’aval.

Tableau n° 109 : Coordonnées des vannes de contrôle


Coordonnées
Ouvrage
X(m) Y(m)
VC-1 381298.6 1806171.2
VC-2 381431.4 1806005.6
VC-3 381969.0 1805806.2

Tableau n° 110 : Dimensions des vannes de contrôle


Débit Largeur
Canal Ouvrage Hauteur (m) Equipement
(l/s) (m)
C1 VC-1 9935.0 6.0 1.5 Vanne murale 3(2x1.5)
C1 VC-2 7545.0 6.0 1.5 Vanne murale 3(2x1.5)
C1 VC-3 5750.0 6.0 1.5 Vanne murale 3(2x1.5)

6.4.2.6 Ouvrages de traversée

Cinq ouvrages de traversée en dalot seront projetés : deux sur le canal principal C-1, deux sur le canal
principal C-2 et un sur le canal principal C-3, les coordonnées de ces ouvrages ainsi que les
dimensions sont présentés ci-après :

Tableau n° 111 : Coordonnées des ouvrage de traversées


Coordonnées
Ouvrage
X(m) Y(m)
D-1 381953.0 1805811.8
D-2 382925.5 1804524.3
D-3 382747.4 1807872.7
D-4 384266.5 1807485.3
D-5 380643.5 1803270.2

Débit Largeur Hauteur Longueur


Canal Ouvrage Dimension
(l/s) (m) (m) (m)
D-1 5750.0 8.0 2.5 12.0 2x (4x2.5)
C1
D-2 2875.0 6.0 2.5 10.0 2x (3x2.5)

Groupement MCG / SAFI 179


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Débit Largeur Hauteur Longueur


Canal Ouvrage Dimension
(l/s) (m) (m) (m)
D-3 2030.0 4.0 2.5 8.0 2x (2x2.5)
C2
D-4 1655.0 3.0 2.5 6.0 (3x2.5)
C3 D-5 1260.0 2.0 2.5 6.0 (2x2.5)

Groupement MCG / SAFI 180


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

9-Localisation OT (A4)

Groupement MCG / SAFI 181


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Ouvrage sur canaux d’ordre secondaire

Les ouvrages sur les canaux d’ordre secondaires sont :

 Ouvrage partiteur modulé : ce sont des ouvrages implantés à la tête des canaux d’ordre
secondaire assure le passage d’une main d’eau vers un quartier hydraulique,

 Ouvrage de prise parcellaire : ce sont des ouvrages de type TOR, implantés pour chaque
parcelle formés par des vannette et des conduites en PVC.

Tableau n° 112 : Coordonnées des ouvrages projetés sur canaux d’ordre secondaires (secteur
Grande Digue)
Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
G1 381 331 1 806 352 G48 387 596 1 809 004
G2 382 359 1 806 612 G49 387 705 1 808 968
G3 382 782 1 807 106 G50 387 788 1 808 944
G4 383 703 1 807 974 G51 387 877 1 808 913
G5 383 715 1 808 050 G52 387 979 1 808 877
G6 383 491 1 808 710 G53 383 364 1 806 581
G7 383 599 1 808 815 G54 383 443 1 805 948
G8 383 669 1 808 889 G55 383 404 1 806 220
G9 383 736 1 808 962 G56 383 411 1 806 171
G10 383 872 1 809 108 G57 383 417 1 806 134
G11 384 465 1 807 181 G58 385 117 1 805 687
G12 384 683 1 808 019 G59 385 120 1 805 677
G13 384 236 1 807 846 G60 385 122 1 805 637
G14 384 245 1 807 887 G61 385 638 1 805 693
G15 384 272 1 808 088 G62 385 628 1 805 462
G16 384 314 1 808 327 G63 385 716 1 805 939
G17 384 318 1 808 378 G64 385 782 1 805 956
G18 384 338 1 808 474 G65 385 881 1 805 988
G19 384 352 1 808 580 G66 385 972 1 806 015
G20 384 397 1 808 870 G67 385 563 1 806 602
G21 384 458 1 809 149 G68 385 870 1 806 426
G22 384 813 1 808 561 G69 386 004 1 806 211
G23 384 911 1 808 578 G70 386 055 1 806 122
G24 384 999 1 808 595 G71 386 154 1 805 949
G25 385 083 1 808 611 G72 385 123 1 806 888
G26 384 815 1 808 653 G73 385 519 1 807 153
G27 384 721 1 808 628 G74 386 175 1 806 684
G28 384 826 1 808 928 G75 386 252 1 806 572
G29 384 834 1 809 146 G76 386 652 1 807 263
G30 384 961 1 807 551 G77 386 547 1 807 084
G31 385 271 1 808 374 G78 386 598 1 806 848
G32 385 260 1 808 585 G79 387 107 1 807 350
G33 385 282 1 808 650 G80 387 408 1 806 989
G34 385 381 1 808 664 G81 387 338 1 806 907
G35 385 438 1 808 674 G82 387 250 1 806 805

Groupement MCG / SAFI 182


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
G36 385 442 1 808 832 G83 387 338 1 807 787
G37 385 443 1 808 976 G84 387 439 1 807 909
G38 385 452 1 808 676 G85 387 543 1 808 030
G39 385 455 1 807 933 G86 387 643 1 808 149
G40 386 056 1 807 748 G87 387 745 1 808 265
G41 386 325 1 808 010 G88 387 847 1 808 377
G42 386 187 1 808 567 G89 387 947 1 808 487
G43 386 276 1 808 601 G90 387 279 1 807 681
G44 386 363 1 808 633 G91 387 558 1 807 655
G45 386 591 1 808 719 G92 387 833 1 807 642
G46 387 238 1 809 132 G93 387 892 1 807 639
G47 387 425 1 809 062 G94 387 423 1 807 850

Tableau n° 113 : Coordonnées des ouvrages projetés sur canaux d’ordre secondaires (secteur
Tellel)
Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
T1 383 356 1 805 187 T37 385 717 1 803 913
T2 383 601 1 805 177 T38 385 713 1 803 680
T3 383 803 1 805 161 T39 386 006 1 803 684
T4 383 332 1 804 907 T40 386 060 1 803 339
T5 382 835 1 804 422 T41 386 706 1 804 686
T6 382 661 1 804 507 T42 386 081 1 804 541
T7 382 127 1 804 776 T43 386 151 1 804 716
T8 382 584 1 803 926 T44 386 234 1 804 946
T9 382 297 1 803 982 T45 387 128 1 806 147
T10 382 505 1 803 523 T46 387 089 1 805 801
T11 383 089 1 803 943 T47 387 285 1 805 685
T12 383 614 1 803 633 T48 387 311 1 805 670
T13 383 603 1 803 611 T49 387 499 1 805 556
T14 383 664 1 803 249 T50 387 663 1 805 456
T15 383 882 1 803 165 T51 387 374 1 805 769
T16 384 014 1 803 109 T52 387 484 1 805 937
T17 384 099 1 803 067 T53 388 038 1 806 860
T18 383 494 1 803 067 T54 388 236 1 806 630
T19 383 116 1 803 131 T55 388 255 1 806 608
T20 382 797 1 802 888 T56 388 172 1 806 527
T21 383 708 1 804 492 T57 388 018 1 806 397
T22 383 270 1 802 541 T58 381 415 1 804 555
T23 383 983 1 804 315 T59 381 104 1 804 001
T24 384 698 1 804 497 T60 380 199 1 802 367
T25 384 905 1 804 710 T61 380 174 1 802 325
T26 385 010 1 804 892 T62 380 035 1 802 046
T27 384 863 1 804 611 T63 379 983 1 801 935
T28 384 437 1 804 031 T64 379 971 1 801 910
T29 384 386 1 803 892 T65 380 380 1 801 770
T30 385 123 1 804 003 T66 380 110 1 801 855
T31 385 122 1 803 701 T67 380 308 1 801 781

Groupement MCG / SAFI 183


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
T32 384 932 1 803 044 T68 381 498 1 802 717
T33 384 992 1 802 952 T69 381 736 1 801 463
T34 385 103 1 802 751 T70 383 524 1 801 722
T35 385 380 1 804 219 T71 382 721 1 801 652
T36 385 545 1 804 165

Tableau n° 114 : Dimensionnement des ouvrage modulé (C-1)


Calibre B (m) H (m) Calibre
Canal de de
Ouvrage Canal aval
amont masque B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal nominal
XX1-30 C1.5.1
XX1-20 C1.5.2
T1 C1.5 - 0.3 0.3 0.3 - 0.5 0.5 0.5 -
XX1-20 C1.5.3
XX1-90 C1.5.4
XX1-70 C1.5.4.1
T2 C1.5.4 - 0.3 0.3 - - 0.6 0.5 - -
XX1-20 C1.5.4.2
XX1-20 C1.5.4.1.1
T3 C1.5.4.1 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30 C1.5.4.1.2
XX1-20 C1.5.4.1.3
XX1-20 C1.5 bis-1
T4 C1.5 bis - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.5 bis-2
XX1-190 C1.6.2
T5 C1.6 - 0.5 0.5 - - 0.7 0.7 - -
XX1-190 C1.6.1
XX1-40 C1.6.2.1
T6 C1.6.2 - 0.3 0.3 0.3 0.3 0.5 0.6 0.5 0.6 XX1-110 C1.6.2.2
XX1-20 C1.6.2.3
XX1-30 C1.6.2.2.1
XX1-20 C1.6.2.2.2
T7 C1.6.2.2 - 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-30 C1.6.2.2.3
XX1-20 C1.6.2.2.4
XX1-20 C1.6.1.1
XX1-70 C1.6.1.2
T8 C1.6.1 - 0.3 0.3 0.3 0.3 0.5 0.6 0.5 0.6
XX1-20 C1.6.1.3
XX1-80 C1.6.1.4
XX1-30 C1.6.1.2.1
T9 C1.6.1.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.6.1.2.2
XX1-40 C1.6.1.4.1
T10 C1.6.1.4 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C1.6.1.4.2
XX1-30 C1.7.2.1
T11 C1.7.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.7.2.2
XX1-20 C1.8.2
T12 C1.8 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-20 C1.8.3
XX1-20 C1.8.4
T13 C1.8 XX1-430 1 - - - 0.7 - - - - C1.8.1
T14 C1.8.1 XX-170 0.5 - - - 0.6 - - - - C1.8.1.1
T15 C1.8.1.1 - 0.3 - - - 0.5 - - - XX1-20 C1.8.1.1.1
T16 C1.8.1.1 - 0.3 - - - 0.5 - - - XX1-40 C1.8.1.1.2
XX1-30 C1.8.1.1.3
XX1-30 C1.8.1.1.4
T17 C1.8.1.1 - 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-30 C1.8.1.1.5
XX1-20 C1.8.1.1.6

Groupement MCG / SAFI 184


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Canal Calibre B (m) H (m) Calibre


Ouvrage Canal aval
amont de B1 B2 B3 B4 H1 H2 H3 H4 de
masque masque
XX1-40 C1.8.1.2
nominal nominal
XX1-40 C1.8.1.3
T18 C1.8.1 - 0.3 0.3 0.3 0.5 0.5 0.5 0.5 0.6
XX1-30 C1.8.1.4
XX1-140 C1.8.1.5
XX1-30 C.1.8.1.5.1
T19 C1.8.1.5 - 0.3 0.3 - - 0.5 0.5 - -
XX1-50 C.1.8.1.5.2
XX1-30 C.1.8.1.5.3
T20 C1.8.1.5 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C.1.8.1.5.4
XX1-20 C1.8.1.3.1
T21 C1.8.1.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.8.1.3.2
XX1-20 C1.9.1
T22 C1.9 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.9.2
XX1-20 C1.10.1
T23 C1.10 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.10.2
T24 C1.12.2 - 0.3 - - - 0.5 - - - XX1-20 C1.12.2.1
T25 C1.12.2 - 0.3 - - - 0.5 - - - XX1-30 C1.12.2.2
XX1-20 C1.12.2.3
T26 C1.12.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.12.2.4
XX1-40 C1.12.3.1
T27 C1.12.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C1.12.3.2
T28 C1-14 - 0.3 - - - 0.5 - - - XX1-30 C1.14.1
XX1-30 C1.14.2
T29 C1-14 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.14.3
T30 C1.15.2 - 0.3 - - - 0.5 - - - XX1-20 C1.15.2.1
XX1-30 C1.15.2.2
T31 C1.15.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.15.2.3
XX1-110 C1.15.2.4
T32 C1.15.2 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30 C1.15.2.5
XX1-40 C1.15.2.6
T33 C1.15.2.4 - 0.3 - - - 0.5 - - - XX1-30 C1.15.2.4.1
XX1-40 C1.15.2.4.2
T34 C1.15.2.4 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C1.15.2.4.3
T35 C1.16.1 - 0.3 - - - 0.5 - - - XX1-30 C1.16.1.1
XX1-40 C1.16.1.2
T36 C1.16.1 - 0.3 0.3 - - 0.5 0.5 - -
XX1-50 C1.16.1.3
T37 C1.17.2 - 0.3 - - - 0.5 - - - XX1-20 C1.17.2.1
T38 C1.17.2 - 0.3 - - - 0.5 - - - XX1-30 C1.17.2.2
XX1-30 C1.17.2.3
T39 C1.17.2 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-50 C1.17.2.4
XX1-20 C1.17.2.5
XX1-20 C1.17.2.4.1
T40 C1.17.2.4 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.17.2.4.2
XX1-40 C1.21.2.1
T41 C1.21.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.21.2.2
T42 C1.21.3 - 0.3 - - - 0.5 - - - XX1-30 C1.21.3.1
T43 C1.21.3 - 0.3 - - - 0.5 - - - XX1-30 C1.21.3.2
XX1-20 C1.21.3.3
T44 C1.21.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.21.3.4
XX1-40 C1.22.1.1
T45 C1.22.1 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C1.22.1.2
T46 C1.22.2 - 0.3 - - - 0.5 - - - XX1-40 C1.22.2.1
T47 C1.22.2 - 0.3 - - - 0.5 - - - XX1-20 C1.22.2.2
T48 C1.22.2 - 0.3 - - - 0.6 - - - XX1-80 C1.22.2.3
T49 C1.22.2 - 0.3 0.3 - - 0.5 0.5 - - XX1-20 C1.22.2.4

Groupement MCG / SAFI 185


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Canal Calibre B (m) H (m) Calibre


Ouvrage Canal aval
amont de B1 B2 B3 B4 H1 H2 H3 H4 de
masque masque
XX1-20 C1.22.2.5
nominal nominal
XX1-20 C1.22.2.6
T50 C1.22.2 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-30 C1.22.2.7
XX1-20 C1.22.2.8
T51 C1.22.2.3 - 0.3 - - - 0.5 - - - XX1-20 C1.22.2.3.1
XX1-20 C1.22.2.3.2
T52 C1.22.2.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.22.2.3.3
T53 C1.23.1 - 0.3 - - - 0.5 - - - XX1-30 C1.23.1.1
T54 C1.23.1 - 0.3 - - - 0.5 - - - XX1-50 C1.23.1.2
XX1-40 C1.23.1.3
XX1-40 C1.23.1.4
T55 C1.23.1 - 0.3 0.3 0.3 0.3 0.5 0.5 0.6 0.5
XX1-70 C1.23.1.5
XX1-30 C1.23.1.6
T56 C1.23.1.5 - 0.3 - - - 0.5 - - - XX1-20 C1.23.1.5.1
XX1-20 C1.23.1.5.2
T57 C1.23.1.5 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C1.23.1.5.3

Tableau n° 115 : Dimensionnement des ouvrage modulé (C-2)


Calibre B (m) H (m) Calibre
Canal de de
Ouvrage Canal aval
amont masque B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal nominal
XX1-20 C 2.1-1
G1 C2.1 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 2.1-2
XX1-20 C 2.3.2.2
G2 C 2.3.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.3.2.1
XX1-40 C 2.4.3.1
G3 C 2.4.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 2.4.3.2
XX1-120 C2.6.1
G4 C2.6 - 0.5 0.3 - - 0.5 0.5 - -
XX1-20 C2.6.2
G5 - 0.3 - - - 0.5 - - - XX1-20 C 2.6.1.1
G6 - 0.3 - - - 0.5 - - - XX1-20 C 2.6.1.2
G7 - 0.3 - - - 0.5 - - - XX1-20 C 2.6.1.3
G8 C2.6.1 - 0.3 - - - 0.5 - - - XX1-20 C 2.6.1.4
G9 - 0.3 - - - 0.5 - - - XX1-20 C 2.6.1.5
- XX1-20 C 2.6.1.6
G10 0.3 0.3 - - 0.5 0.5 - -
- XX1-20 C 2.6.1.7
XX1-20 C 2.12.2.1
G11 C 2.12.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.12.2.2
G12 XX1-250 C 2.13.1
C2.13 - 0.5 0.5 - - 0.8 0.7 - -
XX1-180 C2.13.2
G13 - 0.3 - - - 0.5 - - - XX1-30 C 2.13.1.1
G14 - 0.3 - - - 0.5 - - - XX1-30 C 2.13.1.2
G15 - 0.3 - - - 0.5 - - - XX1-30 C 2.13.1.3
G16 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.1.4
G17 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.1.5
C 2.13.1
G18 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.1.6
G19 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.1.7
G20 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.1.8
- XX1-30 C 2.13.1.9
G21 0.3 0.3 - - 0.5 0.5 - -
- XX1-20 C 2.13.1.10
G22 - 0.3 - - - 0.5 - - - XX1-70 C 2.13.2.1
G26 C2.13.2 - 0.3 - - - 0.5 - - - XX1-40 C 2.13.2.2
G28 - 0.3 - - - 0.5 - - - XX1-20 C 2.13.2.3

Groupement MCG / SAFI 186


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Canal Calibre B (m) H (m) Calibre


Ouvrage Canal aval
amont de B1 B2 B3 B4 H1 H2 H3 H4 de
masque
- masque
XX1-20 C 2.13.2.4
G29 nominal 0.3 0.3 - - 0.5 0.5 - - nominal
- XX1-20 C 2.13.2.5
XX1-20 C 2.14.2.1
G30 C 2.14.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.14.2.2
G31 - 0.3 - - - 0.5 - - - XX1-30 C 2.15.1
- XX1-20 C 2.15.2
G32 0.3 0.3 - - 0.5 0.5 - -
- XX1-20 C 2.15.3
C2.15
G33 - 0.3 - - - 0.5 - - - XX1-20 C 2.15.4
G34 - 0.3 - - - 0.5 - - - XX1-20 C 2.15.5
G35 - 0.3 - - - 0.5 - - - XX1-60 C 2.15.6
G36 - 0.3 - - - 0.5 - - - XX1-20 C 2.15.6.1
C 2.15.6 XX1-20 C 2.15.6.2
G37 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.15.6.3
XX1-30 C 2.15.7
G38 C2.15 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 2.15.8
XX1-20 C 2.16.2.1
G39 C 2.16.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.16.2.2
XX1-30 C 2.17.1.3.1
G40 C 2.17.1.3 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 2.17.1.3.2
- 0.3 - - - 0.5 - - - XX1-30 C 2.17.1.1
- 0.3 - - - 0.5 - - - XX1-30 C 2.17.1.2
G41 C 2.17.1
- 0.3 - - - 0.5 - - - XX1-60 C 2.17.1.3
- 0.3 - - - 0.5 - - - XX1-30 C 2.17.1.4
G42 - 0.3 - - - 0.5 - - - XX1-40 C 2.17.2.1
G43 - 0.3 - - - 0.5 - - - XX1-50 C 2.17.2.2
G44 C 2.17.2 - 0.3 - - - 0.5 - - - XX1-20 C 2.17.2.3
XX1-30 C 2.17.2.4
G45 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C 2.17.2.5
G46 - 0.3 - - - 0.5 - - - XX1-40 C 2.19.1.1
G47 - 0.3 - - - 0.5 - - - XX1-30 C 2.19.1.2
G48 - 0.3 - - - 0.5 - - - XX1-20 C 2.19.1.3
G49 - 0.3 - - - 0.5 - - - XX1-20 C 2.19.1.4
C 2.19.1
G50 - 0.3 - - - 0.5 - - - XX1-20 C 2.19.1.5
G51 - 0.3 - - - 0.5 - - - XX1-20 C 2.19.1.6
XX1-20 C 2.19.1.7
G52 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 2.19.1.8

Tableau n° 116 : Dimensionnement des ouvrage modulé (C-3)


Calibre B (m) H (m) Calibre
Canal de de
Ouvrage Canal aval
amont masque B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal nominal
XX1-20 C3.4.2.1
T58 C3.4.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C3.4.2.2
XX1-20 C3.6.2.1
T59 C3.6.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C3.6.2.2
T60 C3.10 - 0.3 - - - 0.5 - - - XX1-30 C3.10.1
T61 C3.10 - 0.3 - - - 0.5 - - - XX1-30 C3.10.2
T62 C3.10 - 0.3 - - - 0.5 - - - XX1-30 C3.10.3
T63 C3.10 - 0.3 - - - 0.6 - - - XX1-80 C3.10.4
XX1-110 C3.10.5
T64 C3.10 - 0.5 0.3 - - 0.6 0.5 - -
XX1-40 C3.10.6
XX1-40 C3.10.4.1
T65 C3.10.4 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C3.10.4.2

Groupement MCG / SAFI 187


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Calibre B (m) H (m) Calibre


Canal de de
Ouvrage Canal aval
amont masque B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal nominal
T66 C3.10.5 - 0.3 - - - 0.5 - - - XX1-40 C3.10.5.1
XX1-40 C3.10.5.2
T67 C3.10.5 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C3.10.5.3
XX1-30 C3.14.2.1
XX1-30 C3.14.2.2
T68 C3.14.2 - 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-30 C3.14.2.3
XX1-30 C3.14.2.4
XX1-30 C3.17.1
T69 C3.17 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C3.17.2
XX1-30 C3.19.1.1
XX1-30 C3.19.1.2
T70 C3.19.1 - 0.3 0.3 0.3 0.3 0.5 0.5 0.5 0.5
XX1-40 C3.19.1.3
XX1-20 C3.19.1.4
XX1-40 C3.19.2.1
T71 C3.19.2 - 0.3 0.3 0.3 - 0.5 0.5 0.5 - XX1-80 C3.19.2.2
XX1-40 C3.19.2.3
XX1-40 C3.19.2.2.1
T72 C3.19.2.2 - 0.3 0.3 - - 0.5 0.5 - -
XX1-40 C3.19.2.2.2

Tableau n° 117 : Dimensionnement des ouvrage modulé (C-4)


Calibre B (m) H (m) Calibre
Canal de de
Ouvrage Canal aval
amont masque B1 B2 B3 B4 H1 H2 H3 H4 masque
nominal nominal
- 0.3 - - - 0.5 - - - XX1-20 C4.3.1
G53 C4.3
- 0.3 - - - 0.5 - - - XX1-20 C4.3.2
- 0.3 - - - 0.5 - - - XX1-20 C 4-4-1-1
G54 C4.4.1
- 0.3 - - - 0.5 - - - XX1-30 C 4-4-1-2
G55 - 0.3 - - - 0.5 - - - XX1-20 C 4-4-2-1
G56 - 0.3 - - - 0.5 - - - XX1-30 C 4-4-2-2
C4.4.2
XX1-30 C 4-4-2-3
G57 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 4-4-2-4
G58 - 0.3 - - - 0.5 - - - XX1-20 C4-8-1
G59 - 0.3 - - - 0.5 - - - XX1-20 C4-8-2
C 4-8
XX1-30 C4-8-3
G60 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C4-8-4
G61 - 0.3 - - - 0.5 - - - XX1-30 C4-9-1
C4-9 XX1-30 C4-9-2
G62 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C4-9-3
G63 - 0.3 - - - 0.5 - - - XX1-20 C4-10-2-1
G64 - 0.3 - - - 0.5 - - - XX1-20 C4-10-2-2
G65 C4-10-2 - 0.3 - - - 0.5 - - - XX1-20 C4-10-2-3
XX1-20 C4-10-2-4
G66 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C4-10-2-5
G67 - 0.3 - - - 0.5 - - - XX1-20 C 4-12-1
G68 - 0.3 - - - 0.5 - - - XX1-20 C 4-12-2
G69 - 0.3 - - - 0.5 - - - XX1-20 C 4-12-3
C4-12
G70 - 0.3 - - - 0.5 - - - XX1-20 C 4-12-4
XX1-20 C 4-12-5
G71 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 4-12-6
XX1-30 C 4-13-1-1
G72 C4-13-1 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 4-13-1-2

Groupement MCG / SAFI 188


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Canal Calibre B (m) H (m) Calibre


Ouvrage Canal aval
amont de B1 B2 B3 B4 H1 H2 H3 H4 de
masque masque
XX1-30 C4-13-4-1
G73 C4-13-4 -
nominal 0.3 0.3 - - 0.5 0.5 - - nominal
XX1-30 C4-13-4-2
G74 - 0.3 - - - 0.5 - - - XX1-20 C4-14-1
C4-14 XX1-20 C4-14-2
G75 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C4-14-3
XX1-20 C 4-17-1
G76 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 4-17-2
G77 C4-17 - 0.3 - - - 0.5 - - - XX1-20 C 4-17-3
XX1-20 C 4-17-4
G78 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 4-17-5
- XX1-20 C 4-18-1
G79 0.3 0.3 - - 0.5 0.5 - -
- XX1-20 C 4-18-2
G80 - 0.3 - - - 0.5 - - - XX1-20 C 4-18-3
C4-18
G81 - 0.3 - - - 0.5 - - - XX1-20 C 4-18-4
XX1-20 C 4-18-5
G82 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 4-18-6
G83 - 0.3 - - - 0.5 - - - XX1-30 C 4.19-2-1
G84 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-2-2
G85 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-2-3
G86 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-2-4
C 4.19-2
G87 - 0.3 - - - 0.5 - - - XX1-30 C 4.19-2-5
G88 - 0.3 - - - 0.5 - - - XX1-30 C 4.19-2-6
XX1-30 C 4.19-2-7
G89 - 0.3 0.3 - - 0.5 0.5 - -
XX1-20 C 4.19-2-8
G90 C4.19.3 - 0.3 - - - 0.5 - - - XX1-50 C 4.19-3-1
G91 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-3-1-1
G92 C 4.19-3-1 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-3-1-2
G93 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-3-1-3
G94 - 0.3 - - - 0.5 - - - XX1-20 C 4.19-3-2
C4.19.3 XX1-30 C 4.19-3-3
G95 - 0.3 0.3 - - 0.5 0.5 - -
XX1-30 C 4.19-3-4

Groupement MCG / SAFI 189


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

10-Plan réseau irrigation (A3)

Groupement MCG / SAFI 190


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.5 REHABILITATION DU RESEAU DE DRAINAGE


Le réseau de drainage du périmètre irrigué est conçu de façon à recueillir les réseaux de ruissellement
provenant des pluies, des surplus d’irrigation, de la vidange des casiers rizicoles et en cas de pluie
exceptionnelle, de permettre l’accès aux différentes parcelles à l’intérieur du périmètre.

L’évacuation des surplus d’eau est assurée par un réseau de drainage composé de fossés ouverts.

Actions de réhabilitation retenues

Les actions prévues pour la réhabilitation du réseau de drainage sont les suivantes :

 Calage et reprofilage des drains d’ordre primaire, secondaire et tertiaire,

 Création des ouvrages de rejet vers les drains de manière à permettre une évacuation rapide
des eaux et faciliter l’entretien des ouvrages.

 Renouvellement des tous les ouvrages de traversée,

Drains principaux et superficie drainée

Le système de drainage est le même que le système actuel. Toute l'eau excédentaire de la surface
existante est drainée vers les drains principaux D-1, D-2 et D-3. Les trois drains sont connectés au
drain de Kassack existant. La station d’exhaure est située au sud du périmètre

Tableau n° 118 : Drain et superficie drainée


Drain principal Superficie (ha) Linéaires (m)
D-1 787.9 5216.7
D-2 116.1 1039.9
D-2 1261.8 5723.0
Drainage direct dans Lampsar/ 2052.0 -
zone de dépression

Débit du projet

Pour le dimensionnement du réseau de drainage, deux débits par unité de surface ont été calculés.

 Le premier est le débit de drainage par unité de surface en supposant que 75mm de pluies
tombées en un jour sont drainées en 3 jours.

𝑄(𝑚3 /ℎ𝑎)
𝑞=
𝐷(𝑠)

Avec :

- Q : Débit de drainage de la pluie par hectare

- D : Nombre de jours pour drainer les eaux excédentaires (3 jours)

Groupement MCG / SAFI 191


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Le second est le débit de drainage par unité de surface pour drainer les eaux excédentaires
venant de l’irrigation en saison sèche avec une profondeur de la mare de stockage de
100mm.

Puisque le débit de drainage par unité de surface pour drainer les eaux excédentaires d'irrigation en
saison sèche est plus grand que le débit calculé en supposant que 75mm de pluies en un jour sont
drainées en 3 jours, 3.8 l/s/ha a été choisi pour la conception.

Profil en long des drains

La pente longitudinale du canal est fixée en prenant en compte les critères d'étude de la SAED et du
résultat de l’étude topographique effectuée dans le cadre de ce projet, le tableau ci-après présente les
pentes longitudinales utilisées pour le calage et le dimensionnement du réseau de drainage

Tableau n° 119 : Pente longitudinale des canaux


Canal pente
Drain principal et secondaire 0.1‰
Drain tertiaire 1‰

Groupement MCG / SAFI 192


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

11-Schéma de drainage (A4)

Groupement MCG / SAFI 193


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 120 : Calage de drain principal D-1


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote plafond
Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
P1 0.0 0.0 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.6 1.5
P2 68.7 68.7 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.6 1.5
P3 103.1 171.8 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.6 1.5
P4 OT1 94.0 265.8 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.6 1.5
P5 61.8 327.5 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.6 1.5
P6 148.4 475.9 -0.5 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.5 0.5 1.5
P7 OR1 144.5 620.4 -0.6 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.6 0.5 1.4
P8 OR2 188.8 809.2 -0.6 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.6 0.5 1.4
P9 OT2 152.6 961.9 -0.6 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.6 0.5 1.4
P10 OR3 287.9 1249.8 -0.6 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.6 0.5 1.4
P11 213.2 1462.9 -0.6 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.6 0.4 1.4
P12 136.6 1599.5 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P13 OT5 27.6 1627.1 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P14 OR4 86.6 1713.7 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P15 122.2 1835.9 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P16 136.0 1971.9 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P17 10.0 1981.9 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P18 72.4 2054.3 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P19 95.0 2149.3 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P20 OT9 15.7 2165.0 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P21 63.0 2228.0 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P22 134.5 2362.4 -0.7 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.7 0.4 1.3
P23 204.6 2567.0 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P24 169.6 2736.6 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P25 175.5 2912.1 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P26 51.1 2963.2 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P27 OR9 123.0 3086.2 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P28 5.2 3091.5 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P29 103.8 3195.2 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P30 31.4 3226.6 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2

Groupement MCG / SAFI 194


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote plafond
Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
P31 OT11 12.7 3239.3 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P32 104.5 3343.8 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.3 1.2
P33 139.5 3483.3 -0.8 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.8 0.2 1.2
P34 99.0 3582.3 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P35 OT26 22.9 3605.2 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P36 95.0 3700.2 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P37 47.2 3747.4 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P38 104.1 3851.5 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P39 151.1 4002.5 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P40 152.7 4155.2 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P41 140.8 4296.0 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P42 158.7 4454.8 -0.9 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -0.9 0.2 1.1
P43 131.0 4585.8 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P44 154.9 4740.7 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P45 110.5 4851.3 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P46 149.3 5000.6 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P47 119.3 5119.9 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P48 2.0 5122.0 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P49 5.7 5127.7 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P50 16.4 5144.1 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P51 10.8 5154.8 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P52 54.1 5208.9 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0
P53 OR12 7.7 5216.7 -1.0 8.0 0.01% 1.1 0.5 0.3 0.0 0.0 -1.0 0.1 1.0

Tableau n° 121 : Calage de drain principal D-2


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote plafond
N° Tab. Ouvrage b m Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 OR31 0.0 0.0 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5
2 P2 69.5 69.5 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5
3 P3 113.8 183.4 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5

Groupement MCG / SAFI 195


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote plafond
N° Tab. Ouvrage b m Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
4 P4 OR13 41.1 224.5 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5
5 P5 94.9 319.4 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5
6 P6 62.3 381.7 -0.5 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.5 -0.1 1.5
7 P7 150.8 532.5 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.1 1.4
8 P8 188.1 720.6 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4
9 P9 8.0 728.6 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.1 1.4
10 P10 73.7 802.3 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4
11 P11 124.7 927.0 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4
12 P12 17.2 944.1 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4
13 P13 49.0 993.1 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4
14 P14 OR14 46.7 1039.9 -0.6 6.0 1.5 0.4 0.5 0.2 0.0 0.0 -0.6 -0.2 1.4

Tableau n° 122 : Calage de drain principal D-3


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 1.0 1.5
2 P2 OR16 50.3 50.2875 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 0.9 1.5
3 P3 113.6 163.876 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 0.9 1.5
4 P4 30.9 194.8193 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 0.9 1.5
5 P5 OR17 92.4 287.1825 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 0.9 1.5
6 P6 121.8 408.943 -0.5 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.5 0.9 1.5
7 P7 163.6 572.5196 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
8 P8 OR18 294.1 866.6277 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
9 P9 31.8 898.4698 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
10 P10 OR19 13.9 912.3972 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
11 P11 8.9 921.3462 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
12 P12 36.4 957.7439 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
13 P13 10.7 968.4143 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.9 1.4
14 P14 98.0 1066.385 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
15 P15 OT28 78.0 1144.405 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4

Groupement MCG / SAFI 196


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
16 P16 77.8 1222.198 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
17 P17 152.8 1375.007 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
18 P18 105.8 1480.84 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
19 P19 OT30 18.0 1498.872 -0.6 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.6 0.8 1.4
20 P20 88.3 1587.163 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.8 1.3
21 P21 131.3 1718.511 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.8 1.3
22 P22 161.2 1879.713 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.8 1.3
23 P23 129.5 2009.213 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
24 P24 60.3 2069.555 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
25 P25 5.8 2075.353 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
26 P26 OT31/OT32 10.5 2085.849 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
27 P27 25.5 2111.303 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
28 P28 31.6 2142.948 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
29 P29 49.4 2192.359 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
30 P30 32.1 2224.49 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
31 P31 11.2 2235.645 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
32 P32 22.0 2257.617 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
33 P33 OR33 4.3 2261.902 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
34 P34 35.4 2297.272 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
35 P35 51.0 2348.258 -0.7 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.7 0.7 1.3
36 P36 OR22 226.6 2574.863 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.7 1.2
37 P37 OR34 58.4 2633.281 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.7 1.2
38 P38 176.2 2809.466 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.7 1.2
39 P39 196.8 3006.28 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.6 1.2
40 P40 153.2 3159.491 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.6 1.2
41 P41 123.9 3283.383 -0.8 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.8 0.6 1.2
42 P42 258.4 3541.801 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.6 1.1
43 P43 OR30 68.0 3609.783 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.6 1.1
44 P44 50.0 3659.749 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.6 1.1
45 P45 156.4 3816.187 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.6 1.1
46 P46 105.0 3921.17 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.6 1.1
47 P47 141.7 4062.842 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.5 1.1
48 P48 OR26 114.1 4176.925 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.5 1.1

Groupement MCG / SAFI 197


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
49 P49 17.1 4194.046 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.5 1.1
50 P50 87.0 4281.037 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.5 1.1
51 P51 182.6 4463.59 -0.9 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -0.9 0.5 1.1
52 P52 121.9 4585.471 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.5 1.0
53 P53 142.1 4727.575 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.5 1.0
54 P54 176.7 4904.28 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
55 P55 129.0 5033.294 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
56 P56 OT42 28.5 5061.747 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
57 P57 OT43 122.6 5184.337 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
58 P58 23.7 5207.988 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
59 P59 111.3 5319.305 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
60 P60 158.5 5477.811 -1.0 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.0 0.4 1.0
61 P61 118.9 5596.746 -1.1 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.1 0.4 0.9
62 P62 84.4 5681.127 -1.1 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.1 0.4 0.9
63 P63 OT45 41.9 5722.983 -1.1 8.0 0.01% 1.5 0.5 0.3 0.0 0.0 -1.1 0.4 0.9

Tableau n° 123 : Calage de drain principal D1-1


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
2 P2 54.5 54.5 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
3 P3 OR5 48.1 102.6 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
4 P4 OR6 82.6 185.3 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
5 P5 159.9 345.1 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.4 1.7
6 P6 142.7 487.8 -0.3 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.3 0.4 1.7
7 P7 265.7 753.5 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
8 P8 OR7 17.3 770.8 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
9 P9 123.3 894.1 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
10 P10 OT8 144.6 1038.6 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6

Groupement MCG / SAFI 198


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

11 P11 16.5 1055.1 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
12 P12 105.7 1160.8 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
13 P13 OT9 77.6 1238.5 -0.4 2.0 0.01% 0.8 0.5 0.2 0.0 0.0 -0.4 0.4 1.6

Tableau n° 124 : Calage de drain principal D1-2


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.7 1.8
2 P2 OT13 21.7 21.7 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.7 1.8
3 P3 65.7 87.4 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.7 1.8
4 P4 116.6 204.0 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.7 1.8
5 P5 PT15 54.9 258.9 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.7 1.8
6 P6 104.5 363.3 -0.2 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.2 0.6 1.8
7 P7 169.8 533.1 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
8 P8 113.5 646.6 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
9 P9 166.0 812.7 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
10 P10 173.1 985.8 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
11 P11 50.2 1036.1 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
12 P12 126.4 1162.5 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
13 P13 107.1 1269.6 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
14 P14 OT17 27.2 1296.8 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
15 P15 14.3 1311.1 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.6 1.7
16 P16 9.8 1320.9 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
17 P17 36.8 1357.7 -0.3 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.3 0.5 1.7
18 P18 180.1 1537.8 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
19 P19 OR10 186.3 1724.0 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
20 P20 19.2 1743.3 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
21 P21 15.3 1758.6 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
22 P22 144.0 1902.6 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
23 P23 OT21 132.4 2035.0 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
24 P24 31.5 2066.5 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6
25 P25 120.5 2187.0 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.5 1.6

Groupement MCG / SAFI 199


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
26 P26 171.6 2358.5 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
27 P27 OT22 18.7 2377.2 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
28 P28 117.5 2494.7 -0.4 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.4 0.4 1.6
29 P29 OR11 182.6 2677.3 -0.5 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.5 0.4 1.5
30 P30 74.8 2752.1 -0.5 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.5 0.4 1.5
31 P31 158.3 2910.5 -0.5 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.5 0.4 1.5
32 P32 OT25 154.7 3065.1 -0.5 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.5 0.4 1.5
33 P33 OT26 17.1 3082.2 -0.5 6.0 0.01% 0.9 0.5 0.2 0.0 0.0 -0.5 0.4 1.5

Tableau n° 125 : Calage de drain principal D2-1


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.2 1.7
2 P2 46.3 46.3 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.2 1.7
3 P3 62.1 108.4 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.2 1.7
4 P4 70.2 178.6 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
5 P5 68.0 246.6 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
6 P6 68.3 314.9 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
7 P7 65.3 380.2 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
8 P8 65.0 445.2 -0.3 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
9 P9 60.6 505.7 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
10 P10 82.0 587.7 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
11 P11 66.9 654.6 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
12 P12 56.1 710.7 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
13 P13 61.6 772.3 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
14 P14 55.8 828.1 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
15 P15 57.1 885.1 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
16 P16 15.6 900.8 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
17 P17 59.8 960.6 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.1 1.6
18 P18 144.8 1105.5 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.0 1.6

Groupement MCG / SAFI 200


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

19 P19 72.0 1177.5 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.0 1.6
20 P20 40.4 1217.9 -0.4 2.0 0.01% 0.5 0.5 0.1 0.0 0.0 -0.4 0.0 1.6

Tableau n° 126 : Calage de drain principal D2-2


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.3 1.7
2 P2 15.4 15.4 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.3 1.7
3 P3 119.9 135.3 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.2 1.7
4 P4 152.4 287.6 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.2 1.7
5 P5 91.0 378.6 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.2 1.7
6 P6 113.6 492.3 -0.3 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.3 0.2 1.7
7 P7 141.4 633.7 -0.4 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.4 0.2 1.6
8 P8 159.1 792.8 -0.4 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.4 0.2 1.6
9 P9 134.7 927.5 -0.4 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.4 0.1 1.6
10 P10 115.3 1042.7 -0.4 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.4 0.1 1.6
11 P11 113.3 1156.0 -0.4 2.0 0.01% 0.6 0.5 0.2 0.0 0.0 -0.4 0.1 1.6

Tableau n° 127 : Calage de drain principal D2-3


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
2 P2 47.1 47.1 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
3 P3 78.8 125.9 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
4 P4 109.9 235.8 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
5 P5 35.0 270.8 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
6 P6 20.6 291.4 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
7 P7 43.4 334.8 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
8 P8 53.7 388.5 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
9 P9 3.0 391.5 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8
10 P10 54.3 445.8 -0.2 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.2 0.1 1.8

Groupement MCG / SAFI 201


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
11 P11 57.7 503.4 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
12 P12 28.4 531.8 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
13 P13 15.8 547.7 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.1 1.7
14 P14 54.8 602.5 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
15 P15 52.7 655.2 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
16 P16 26.4 681.6 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
17 P17 144.8 826.4 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
18 P18 141.1 967.4 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
19 P19 148.9 1116.3 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
20 P20 167.2 1283.5 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
21 P21 149.7 1433.2 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
22 P22 142.8 1576.0 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
23 P23 78.6 1654.6 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
24 P24 OR32 33.5 1688.1 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
25 P25 132.5 1820.6 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
26 P26 123.9 1944.5 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
27 P27 49.5 1994.0 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
28 P28 88.1 2082.2 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
29 P29 16.2 2098.4 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
30 P30 52.4 2150.8 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
31 P31 59.7 2210.5 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
32 P32 60.9 2271.4 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
33 P33 47.7 2319.1 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
34 P34 OR15 76.6 2395.7 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6

Tableau n° 128 : Calage de drain principal D2-4


Distance Section projetée Perte de charge
Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
1 P1 0.0 0.0 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
2 P2 7.2 7.2 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7

Groupement MCG / SAFI 202


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée Perte de charge


Cote Cote fond Cote Yn Cote
N° Tab. Ouvrage b Pente Yn Revanche V Canal Ouvrage Totale
Partielle Cumulée Projet canal (m) (m) plafond (m)
(m) (m/m) (m) (m) (m/s) (m) (m) (m)
3 P3 28.6 35.8 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
4 P4 73.5 109.3 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
5 P5 53.8 163.1 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
6 P6 89.0 252.1 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
7 P7 43.3 295.4 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
8 P8 72.6 367.9 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
9 P9 109.9 477.9 -0.3 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.3 0.0 1.7
10 P10 46.7 524.6 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 0.0 1.6
11 P11 54.5 579.1 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 0.0 1.6
12 P12 46.7 625.8 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
13 P13 109.5 735.3 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
14 P14 45.7 780.9 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
15 P15 50.3 831.2 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
16 P16 46.6 877.8 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
17 P17 51.0 928.8 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
18 P18 55.5 984.3 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
19 P19 25.7 1010.0 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6
20 P20 OT48 45.4 1055.4 -0.4 1.0 0.01% 0.3 0.5 0.1 0.0 0.0 -0.4 -0.1 1.6

Groupement MCG / SAFI 203


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Dimensionnement du réseau de drainage

Les calculs hydrauliques de la section des drains sont faits sur la base de la surface drainée et des
normes pour la conception du système de drainage .La formule de Manning est utilisée pour le
dimensionnement des canaux.

Q  K S R 2/3
H i1/2
Avec :

 Q : débit en m3/s,
 K : coefficient de Manning-Strickler,
 S : la section mouillée,
 RH : rayon hydraulique,
 i : pente longitudinale en m/m.
Les détails du calcul et du dimensionnement des différents drains sont présentés en annexe.

Figure 15. Coupe type d’une section transversale de drain

Revanche

La revanche dans un drain dépend de la profondeur du canal et de la vitesse d’écoulement, elles sont
prises comme suit :

 Drains principaux et secondaires : 50 cm,

 Drains tertiaires : 30 cm.

Groupement MCG / SAFI 204


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 129 : Récapitulatif de dimensionnement du drain principal D-1


Distance Section projetée
Débit
Tab. Ouvrage Coef Pente m Yn Revanche Section b retenue
Partielle Cumulée (l/s) b (m) Nature V (m/s) B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m)
P1 0.0 0.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P2 68.7 68.7 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P3 103.1 171.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P4 OT1 94.0 265.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P5 61.8 327.5 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P6 148.4 475.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P7 OR1 144.5 620.4 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P8 OR2 188.8 809.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P9 OT2 152.6 961.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P10 OR3 287.9 1249.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P11 213.2 1462.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P12 136.6 1599.5 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P13 OT5 27.6 1627.1 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P14 OR4 86.6 1713.7 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P15 122.2 1835.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P16 136.0 1971.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P17 10.0 1981.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P18 72.4 2054.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P19 95.0 2149.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P20 OT9 15.7 2165.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P21 63.0 2228.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P22 134.5 2362.4 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P23 204.6 2567.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P24 169.6 2736.6 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P25 175.5 2912.1 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P26 51.1 2963.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P27 OR9 123.0 3086.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P28 5.2 3091.5 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P29 103.8 3195.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P30 31.4 3226.6 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P31 OT11 12.7 3239.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0

Groupement MCG / SAFI 205


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit
Tab. Ouvrage Coef Pente m Yn Revanche Section b retenue
Partielle Cumulée (l/s) b (m) Nature V (m/s) B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m)
P32 104.5 3343.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P33 139.5 3483.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P34 99.0 3582.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P35 OT26 22.9 3605.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P36 95.0 3700.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P37 47.2 3747.4 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P38 104.1 3851.5 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P39 151.1 4002.5 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P40 152.7 4155.2 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P41 140.8 4296.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P42 158.7 4454.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P43 131.0 4585.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P44 154.9 4740.7 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P45 110.5 4851.3 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P46 149.3 5000.6 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P47 119.3 5119.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P48 2.0 5122.0 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P49 5.7 5127.7 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P50 16.4 5144.1 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P51 10.8 5154.8 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P52 54.1 5208.9 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0
P53 OR12 7.7 5216.7 2994.0 8.0 en terre 30.0 0.01% 1.5 1.1 0.5 10.7 0.3 8.0 14.0

Tableau n° 130 : Récapitulatif de dimensionnement du drain principal D-2


Distance Section projetée
Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée (l/s) b (m) Nature B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 OR31 0.0 0.0 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
2 P2 69.5 69.5 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
3 P3 113.8 183.4 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
4 P4 OR13 41.1 224.5 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
5 P5 94.9 319.4 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0

Groupement MCG / SAFI 206


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée (l/s) b (m) Nature B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
6 P6 62.3 381.7 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
7 P7 150.8 532.5 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
8 P8 188.1 720.6 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
9 P9 8.0 728.6 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
10 P10 73.7 802.3 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
11 P11 124.7 927.0 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
12 P12 17.2 944.1 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
13 P13 49.0 993.1 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0
14 P14 OR14 46.7 1039.9 441.0 6.0 en terre 30.0 0.01% 1.5 0.4 0.5 2.8 0.2 6.0 12.0

Tableau n° 131 : Récapitulatif de dimensionnement du drain principal D-3


Distance Section projetée
Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section b retenue
Partielle Cumulée (l/s) b (m) Nature V (m/s) B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m)
1 P1 0.0 0 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
2 P2 OR16 50.3 50.2875 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
3 P3 113.6 163.876 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
4 P4 30.9 194.8193 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
5 P5 OR17 92.4 287.1825 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
6 P6 121.8 408.943 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
7 P7 163.6 572.5196 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
8 P8 OR18 294.1 866.6277 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
9 P9 31.8 898.4698 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
10 P10 OR19 13.9 912.3972 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
11 P11 8.9 921.3462 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
12 P12 36.4 957.7439 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
13 P13 10.7 968.4143 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
14 P14 98.0 1066.385 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
15 P15 OT28 78.0 1144.405 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
16 P16 77.8 1222.198 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
17 P17 152.8 1375.007 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
18 P18 105.8 1480.84 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0

Groupement MCG / SAFI 207


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section b retenue
Partielle Cumulée (l/s) b (m) Nature V (m/s) B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m)
19 P19 OT30 18.0 1498.872 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
20 P20 88.3 1587.163 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
21 P21 131.3 1718.511 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
22 P22 161.2 1879.713 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
23 P23 129.5 2009.213 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
24 P24 60.3 2069.555 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
25 P25 5.8 2075.353 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
26 P26 OT31/OT32 10.5 2085.849 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
27 P27 25.5 2111.303 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
28 P28 31.6 2142.948 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
29 P29 49.4 2192.359 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
30 P30 32.1 2224.49 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
31 P31 11.2 2235.645 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
32 P32 22.0 2257.617 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
33 P33 OR33 4.3 2261.902 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
34 P34 35.4 2297.272 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
35 P35 51.0 2348.258 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
36 P36 OR22 226.6 2574.863 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
37 P37 OR34 58.4 2633.281 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
38 P38 176.2 2809.466 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
39 P39 196.8 3006.28 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
40 P40 153.2 3159.491 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
41 P41 123.9 3283.383 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
42 P42 258.4 3541.801 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
43 P43 OR30 68.0 3609.783 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
44 P44 50.0 3659.749 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
45 P45 156.4 3816.187 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
46 P46 105.0 3921.17 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
47 P47 141.7 4062.842 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
48 P48 OR26 114.1 4176.925 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
49 P49 17.1 4194.046 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
50 P50 87.0 4281.037 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
51 P51 182.6 4463.59 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0

Groupement MCG / SAFI 208


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section b retenue
Partielle Cumulée (l/s) b (m) Nature V (m/s) B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m)
52 P52 121.9 4585.471 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
53 P53 142.1 4727.575 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
54 P54 176.7 4904.28 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
55 P55 129.0 5033.294 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
56 P56 OT42 28.5 5061.747 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
57 P57 OT43 122.6 5184.337 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
58 P58 23.7 5207.988 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
59 P59 111.3 5319.305 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
60 P60 158.5 5477.811 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
61 P61 118.9 5596.746 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
62 P62 84.4 5681.127 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0
63 P63 OT45 41.9 5722.983 4795.0 8.0 en terre 30.0 0.01% 1.5 1.5 0.5 14.8 0.3 8.0 14.0

Tableau n° 132 : Récapitulatif de dimensionnement du drain secondaire D1-1


Distance Section projetée
Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
2 P2 54.5 54.5 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
3 P3 OR5 48.1 102.6 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
4 P4 OR6 82.6 185.3 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
5 P5 159.9 345.1 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
6 P6 142.7 487.8 -0.3 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
7 P7 265.7 753.5 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
8 P8 OR7 17.3 770.8 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
9 P9 123.3 894.1 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
10 P10 OT8 144.6 1038.6 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
11 P11 16.5 1055.1 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
12 P12 105.7 1160.8 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0
13 P13 OT9 77.6 1238.5 -0.4 481.0 2.0 en terre 30.0 0.01% 1.5 0.8 0.5 1.3 2.5 0.2 2.0 8.0

Groupement MCG / SAFI 209


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 133 : Récapitulatif de dimensionnement du drain secondaire D1-2


Distance Section projetée
Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
2 P2 OT13 21.7 21.7 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
3 P3 65.7 87.4 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
4 P4 116.6 204.0 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
5 P5 PT15 54.9 258.9 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
6 P6 104.5 363.3 -0.2 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
7 P7 169.8 533.1 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
8 P8 113.5 646.6 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
9 P9 166.0 812.7 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
10 P10 173.1 985.8 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
11 P11 50.2 1036.1 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
12 P12 126.4 1162.5 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
13 P13 107.1 1269.6 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
14 P14 OT17 27.2 1296.8 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
15 P15 14.3 1311.1 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
16 P16 9.8 1320.9 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
17 P17 36.8 1357.7 -0.3 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
18 P18 180.1 1537.8 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
19 P19 OR10 186.3 1724.0 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
20 P20 19.2 1743.3 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
21 P21 15.3 1758.6 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
22 P22 144.0 1902.6 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
23 P23 OT21 132.4 2035.0 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
24 P24 31.5 2066.5 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
25 P25 120.5 2187.0 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
26 P26 171.6 2358.5 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
27 P27 OT22 18.7 2377.2 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
28 P28 117.5 2494.7 -0.4 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
29 P29 OR11 182.6 2677.3 -0.5 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
30 P30 74.8 2752.1 -0.5 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
31 P31 158.3 2910.5 -0.5 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0

Groupement MCG / SAFI 210


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
32 P32 OT25 154.7 3065.1 -0.5 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0
33 P33 OT26 17.1 3082.2 -0.5 1535.0 6.0 en terre 30.0 0.01% 1.5 0.9 0.5 1.4 6.5 0.2 6.0 12.0

Tableau n° 134 : Récapitulatif de dimensionnement du drain secondaire D2-1


Distance Section projetée
Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
2 P2 46.3 46.3 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
3 P3 62.1 108.4 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
4 P4 70.2 178.6 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
5 P5 68.0 246.6 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
6 P6 68.3 314.9 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
7 P7 65.3 380.2 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
8 P8 65.0 445.2 -0.3 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
9 P9 60.6 505.7 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
10 P10 82.0 587.7 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
11 P11 66.9 654.6 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
12 P12 56.1 710.7 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
13 P13 61.6 772.3 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
14 P14 55.8 828.1 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
15 P15 57.1 885.1 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
16 P16 15.6 900.8 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
17 P17 59.8 960.6 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
18 P18 144.8 1105.5 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
19 P19 72.0 1177.5 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0
20 P20 40.4 1217.9 -0.4 188.0 2.0 en terre 30.0 0.01% 1.5 0.5 0.5 1.0 1.3 0.1 2.0 8.0

Tableau n° 135 : Récapitulatif de dimensionnement du drain secondaire D2-2

Groupement MCG / SAFI 211


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
2 P2 15.4 15.4 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
3 P3 119.9 135.3 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
4 P4 152.4 287.6 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
5 P5 91.0 378.6 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
6 P6 113.6 492.3 -0.3 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
7 P7 141.4 633.7 -0.4 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
8 P8 159.1 792.8 -0.4 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
9 P9 134.7 927.5 -0.4 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
10 P10 115.3 1042.7 -0.4 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0
11 P11 113.3 1156.0 -0.4 253.0 2.0 en terre 30.0 0.01% 1.5 0.6 0.5 1.1 1.6 0.2 2.0 8.0

Tableau n° 136 : Récapitulatif de dimensionnement du drain secondaire D2-3


Distance Section projetée
Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
2 P2 47.1 47.1 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
3 P3 78.8 125.9 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
4 P4 109.9 235.8 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
5 P5 35.0 270.8 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
6 P6 20.6 291.4 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
7 P7 43.4 334.8 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
8 P8 53.7 388.5 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
9 P9 3.0 391.5 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
10 P10 54.3 445.8 -0.2 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
11 P11 57.7 503.4 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
12 P12 28.4 531.8 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
13 P13 15.8 547.7 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
14 P14 54.8 602.5 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0

Groupement MCG / SAFI 212


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
15 P15 52.7 655.2 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
16 P16 26.4 681.6 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
17 P17 144.8 826.4 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
18 P18 141.1 967.4 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
19 P19 148.9 1116.3 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
20 P20 167.2 1283.5 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
21 P21 149.7 1433.2 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
22 P22 142.8 1576.0 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
23 P23 78.6 1654.6 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
24 P24 OR32 33.5 1688.1 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
25 P25 132.5 1820.6 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
26 P26 123.9 1944.5 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
27 P27 49.5 1994.0 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
28 P28 88.1 2082.2 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
29 P29 16.2 2098.4 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
30 P30 52.4 2150.8 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
31 P31 59.7 2210.5 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
32 P32 60.9 2271.4 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
33 P33 47.7 2319.1 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
34 P34 OR15 76.6 2395.7 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0

Tableau n° 137 : Récapitulatif de dimensionnement du drain secondaire D2-4


Distance Section projetée
Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
1 P1 0.0 0.0 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
2 P2 7.2 7.2 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
3 P3 28.6 35.8 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
4 P4 73.5 109.3 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
5 P5 53.8 163.1 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
6 P6 89.0 252.1 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
7 P7 43.3 295.4 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0

Groupement MCG / SAFI 213


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Distance Section projetée


Cote Débit
N° Tab. Ouvrage Coef Pente m Yn Revanche Section V b retenue
Partielle Cumulée Projet (l/s) b (m) Nature Yn+R B(m)
Manning (m/m) (m/m) (m) (m) (m²) (m/s) (m)
8 P8 72.6 367.9 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
9 P9 109.9 477.9 -0.3 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
10 P10 46.7 524.6 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
11 P11 54.5 579.1 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
12 P12 46.7 625.8 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
13 P13 109.5 735.3 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
14 P14 45.7 780.9 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
15 P15 50.3 831.2 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
16 P16 46.6 877.8 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
17 P17 51.0 928.8 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
18 P18 55.5 984.3 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
19 P19 25.7 1010.0 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0
20 P20 OT48 45.4 1055.4 -0.4 50.0 1.0 en terre 30.0 0.01% 1.5 0.3 0.5 0.8 0.5 0.1 1.0 7.0

Groupement MCG / SAFI 214


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.6 OUVRAGES SUR RESEAU DRAINAGE

Actions de réhabilitation retenues

Les actions prévues pour la réhabilitation des ouvrages sur le réseau de drainage sont les suivantes :

 Renouvellement des tous les ouvrages de traversée,

 Implantation des ouvrages de rejet.

6.6.1.1 Dimensionnement des ouvrages de traversées

Les coordonnées des ouvrages de traversée sont données par le tableau suivant :

Tableau n° 138 : Coordonnées des ouvrages de traversées


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
OT1 381 772.55 1 806 196.12 OT25 384 625.48 1 806 821.02
OT2 382 383.27 1 806 200.67 OT26 384 617.28 1 806 800.33
OT3 382 682.04 1 806 321.43 OT27 381 586.93 1 805 445.01
OT4 382 387.70 1 806 978.58 OT28 381 939.61 1 805 040.96
OT5 382 906.06 1 806 591.86 OT29 381 523.19 1 804 822.46
OT6 383 073.62 1 806 524.15 OT30 381 777.85 1 804 728.61
OT7 382 770.74 1 807 533.09 OT31 381 601.14 1 804 176.49
OT8 383 271.15 1 807 213.53 OT32 381 548.29 1 804 181.78
OT9 383 211.71 1 807 022.35 OT33 381 755.87 1 803 950.87
OT10 384 140.79 1 807 104.02 OT34 381 079.25 1 803 689.08
OT11 384 265.93 1 806 900.94 OT35 381 905.65 1 803 600.49
OT12 386 746.38 1 808 196.26 OT36 381 020.18 1 802 677.98
OT13 386 903.84 1 807 941.17 OT37 381 015.60 1 802 701.13
OT14 386 813.40 1 807 688.98 OT38 381 376.79 1 803 218.69
OT15 386 693.88 1 807 841.20 OT39 382 285.78 1 802 891.36
OT16 385 848.44 1 807 001.57 OT40 382 469.55 1 802 303.33
OT17 385 855.26 1 807 241.90 OT41 382 645.15 1 802 422.92
OT18 385 985.65 1 808 161.74 OT42 383 492.44 1 802 341.81
OT19 385 701.16 1 808 170.04 OT43 383 613.55 1 802 363.62
OT20 385 804.35 1 808 019.64 OT44 384 134.24 1 802 386.02
OT21 385 383.42 1 807 483.17 OT45 384 140.19 1 802 371.50
OT22 385 092.79 1 807 302.09 OT46 384 169.10 1 802 384.72
OT23 385 103.33 1 806 615.34 OT47 384 194.82 1 802 026.45
OT24 384 785.36 1 806 753.91

Groupement MCG / SAFI 215


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Les coordonnées des ouvrages de rejet sont données par le tableau suivant :

Tableau n° 139 : Coordonnées des ouvrages de rejet


Coordonnées Coordonnées
Ouvrage Ouvrage
X(m) Y(m) X(m) Y(m)
OR1 382 103.05 1 806 078.83 OR18 382 098.18 1 805 237.12
OR2 382 292.46 1 806 079.33 OR19 382 056.30 1 805 240.35
OR3 382 611.44 1 806 425.21 OR20 382 164.71 1 804 183.48
OR4 382 961.31 1 806 642.99 OR21 381 265.00 1 804 320.43
OR5 383 093.35 1 808 040.87 OR22 381 725.47 1 803 722.94
OR6 383 107.12 1 807 966.14 OR23 381 479.24 1 803 229.19
OR7 383 374.68 1 807 457.28 OR24 381 819.02 1 803 285.92
OR8 384 093.88 1 806 674.01 OR25 382 471.71 1 802 323.03
OR9 384 110.78 1 806 871.72 OR26 382 618.16 1 802 412.89
OR10 385 642.98 1 807 620.78 OR27 383 620.02 1 802 951.87
OR11 384 830.73 1 807 140.74 OR28 384 022.19 1 803 735.89
OR12 384 437.62 1 805 206.04 OR29 384 177.52 1 802 017.65
OR13 384 905.04 1 803 167.59 OR30 382 230.08 1 802 825.47
OR14 384 335.01 1 802 757.45 OR31 385 120.95 1 803 199.10
OR15 384 278.24 1 802 635.85 OR32 384 798.76 1 803 019.53
OR16 382 712.00 1 804 811.18 OR33 381 647.51 1 803 937.59
OR17 382 616.41 1 805 015.93 OR34 381 798.69 1 803 586.34

Groupement MCG / SAFI 216


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 140 : Dimensionnement des ouvrages de traversés


yn H b Q V
Canal OT Q(l/s) Froude Ecoulement Section
(m) (m) (m) m3/s m/s
D1001 OT1 23 0.06 1.00 1 0.02 0.31 0.41 fluvial Dalot (1.0x1.0)
D1004 OT2 99 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1005 OT3 40 0.09 1.00 1 0.04 0.40 0.43 fluvial Dalot (1.0x1.0)
D1006 OT4 176 0.21 1.00 1 0.18 0.65 0.45 fluvial Dalot (1.0x1.0)
D1006 OT5 176 0.21 1.00 1 0.18 0.65 0.45 fluvial Dalot (1.0x1.0)
D1007 OT6 58 0.11 1.00 1 0.06 0.46 0.43 fluvial Dalot (1.0x1.0)
D1104 OT7 170 0.20 1.00 1 0.17 0.64 0.45 fluvial Dalot (1.0x1.0)
D1104 OT8 170 0.20 1.00 1 0.17 0.64 0.45 fluvial Dalot (1.0x1.0)
D1.1 OT9 481 0.36 1.00 1 0.48 0.86 0.46 fluvial Dalot (1.0x1.0)
D1010 OT10 97 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1010 OT11 97 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1201.1 OT12 48 0.10 1.00 1 0.05 0.43 0.43 fluvial Dalot (1.0x1.0)
D1201 OT13 186 0.22 1.00 1 0.19 0.66 0.45 fluvial Dalot (1.0x1.0)
D1202 OT14 78 0.13 1.00 1 0.08 0.50 0.44 fluvial Dalot (1.0x1.0)
D1202 OT15 78 0.13 1.00 1 0.08 0.50 0.44 fluvial Dalot (1.0x1.0)
D1203 OT16 86 0.14 1.00 1 0.09 0.52 0.44 fluvial Dalot (1.0x1.0)
D1203 OT17 86 0.14 1.00 1 0.09 0.52 0.44 fluvial Dalot (1.0x1.0)
D1204-1 OT18 100 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1204 OT19 100 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1204-1 OT20 100 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D1205 OT21 140 0.18 1.00 1 0.14 0.60 0.45 fluvial Dalot (1.0x1.0)
D1206 OT22 110 0.16 1.00 1 0.11 0.56 0.44 fluvial Dalot (1.0x1.0)
D1208-1 OT23 61 0.11 1.00 1 0.06 0.46 0.43 fluvial Dalot (1.0x1.0)
D1208 OT24 212 0.23 1.00 1 0.21 0.68 0.45 fluvial Dalot (1.0x1.0)
D1208 OT25 212 0.23 1.00 1 0.21 0.68 0.45 fluvial Dalot (1.0x1.0)
D1.2 OT26 1535 0.66 1.00 1 1.54 1.18 0.46 fluvial Dalot (1.0x1.0)
D3001-1 OT27 94 0.14 1.00 1 0.09 0.52 0.44 fluvial Dalot (1.0x1.0)
D3002 OT28 55 0.11 1.00 1 0.06 0.46 0.43 fluvial Dalot (1.0x1.0)

Groupement MCG / SAFI 217


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

yn H b Q V
Canal OT Q(l/s) Froude Ecoulement Section
(m) (m) (m) m3/s m/s
D3003 OT29 132 0.18 1.00 1 0.13 0.59 0.45 fluvial Dalot (1.0x1.0)
D3003 OT30 132 0.18 1.00 1 0.13 0.59 0.45 fluvial Dalot (1.0x1.0)
D3005 OT31 191 0.22 1.00 1 0.19 0.66 0.45 fluvial Dalot (1.0x1.0)
D3004 OT32 140 0.18 1.00 1 0.14 0.60 0.45 fluvial Dalot (1.0x1.0)
D3006 OT33 60 0.11 1.00 1 0.06 0.46 0.43 fluvial Dalot (1.0x1.0)
D3007-1 OT34 41 0.09 1.00 1 0.04 0.40 0.43 fluvial Dalot (1.0x1.0)
D3008 OT35 107 0.16 1.00 1 0.11 0.56 0.44 fluvial Dalot (1.0x1.0)
D3011 OT36 161 0.20 1.00 1 0.16 0.62 0.45 fluvial Dalot (1.0x1.0)
C3009.1 OT37 95 0.15 1.00 1 0.10 0.54 0.44 fluvial Dalot (1.0x1.0)
D3009 OT38 301 0.28 1.00 1 0.30 0.75 0.45 fluvial Dalot (1.0x1.0)
D3010 OT39 177 0.21 1.00 1 0.18 0.65 0.45 fluvial Dalot (1.0x1.0)
D3011-1 OT40 189 0.22 1.00 1 0.19 0.66 0.45 fluvial Dalot (1.0x1.0)
D3012 OT41 136 0.18 1.00 1 0.14 0.60 0.45 fluvial Dalot (1.0x1.0)
D3013 OT42 215 0.24 1.00 1 0.22 0.69 0.45 fluvial Dalot (1.0x1.0)
D3014 OT43 240 0.25 1.00 1 0.24 0.71 0.45 fluvial Dalot (1.0x1.0)
D3015 OT44 417 0.34 1.00 1 0.42 0.83 0.46 fluvial Dalot (1.0x1.0)
D3 OT45 4752 0.91 1.50 2 4.75 1.54 0.52 fluvial Dalot (2.0x1.5)
D2.4 OT46 44 0.09 1.00 1 0.04 0.40 0.43 fluvial Dalot (1.0x1.0)
D3017 OT47 66 0.12 1.00 1 0.07 0.48 0.44 fluvial Dalot (1.0x1.0)

Groupement MCG / SAFI 218


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

12-Plan réseau drainage (A3)

Groupement MCG / SAFI 219


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

6.7 REHABILITATION DU RESEAU DE PISTES


Les deux cavaliers des canaux d’irrigation et de drainage principaux seront aménagés comme pistes.
La piste du côté droit sera une piste pour l'entretien du canal et la piste du côté gauche sera une piste
d'exploitation générale.

Les pistes d'entretien le long des canaux principaux d’irrigation et de drainage serviront comme
pistes principales comprenant aussi d’autres pistes d’exploitation. En plus des pistes d’exploitation
existantes, de nouvelles pistes d’exploitation seront construites le long des canaux latéraux de
d’irrigation ou de drainage.

Actions de réhabilitation retenues

Les actions prévues pour la réhabilitation du réseau de piste sont les suivantes :

 La reprise des tronçons de pistes dégradés par des opérations de surfaçage et d’apport
de remblai,

 Le nettoyage des pistes par l’abattage et l’élimination d’arbres et d’arbustes,

 Le revêtement de toutes les pistes principales par une couche latéritique.

Dimensionnement de la structure des pistes :

Le dimensionnement de la structure de piste est effectué à l’aide du Logiciel de dimensionnement des


routes de LCPC-SETRA sous normes Françaises.

Ce dimensionnement est effectué comme suit :

6.7.2.1 Hypothèses de dimensionnement

 Trafic moyen journalier : 700 véhicules par sens de circulation pour la voie la plus chargée

 Durée de vie 15 ans,

 Taux de croissance : 3%,

 Coefficient d’agressivité moyenne : 0.4.

6.7.2.2 Modélisation de la structure avec le logiciel ALIZE

Alizé-LCPC met en œuvre la méthode rationnelle de dimensionnement des structures de chaussées


développée par le LCPC et le SETRA, de France.

Ce logiciel permet de dimensionner les structures de chaussée par des données du trafic bien précises
et d’optimiser les épaisseurs de chaussée au maximum selon une méthode rationnelle de calcul et de

Groupement MCG / SAFI 220


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

comparer les contraintes σ et les déformations ε obtenues aux contraintes et déformations admissibles
par les matériaux utilisés

6.7.2.3 Sol support

Il sera retenu pour le dimensionnement un sol support de classe S3 avec un CBR compris entre 12%
et 20%. La classe sera confirmée par les investigations géotechniques in situ.

Les couches en graveleux latéritiques naturelles présentent les caractéristiques suivantes :

 Module d’élasticité : E=1500 bars (CBR supérieur à 30 % pour la couche de Roulement en


Latérite),

 Coefficient de poisson : Γ=0 .35.

Conception géométrique des pistes

La conception géométrique des différentes pistes s’est basée sur les tracés des pistes importantes
existants sur le site.

Un levé topographique sur toutes les emprises des pistes a été effectué par une brigade topographique
en tenant compte de toute la configuration de terrain traversé.

Après l’habillage des levés, des plans côtés, utilisables pour la conception des pistes, ont été réalisés
à l’aide du Logiciel Covadis V13, sous support d’AutocadMap3D V12.

Ces plans cotés étaient ensuite transférés dans l’environnement du Logiciel Géomensura, très
convivial pour la réalisation des projets des pistes.

Dans Géomensura, des tracés en plan et leurs profils en long projetés sont réalisés en tenant compte
de la norme française ARP R60 2 voies >= 6m, répondant aux spécificités ci-après :

6.7.3.1 Vue en plan

 Dévers en alignement droit : 3%,

 Dévers maximal en courbe : 7.00%,

 Rayon minimal : 120.00m,

 Rayon au dévers minimal : 450.00m,

 Rayon non déversé : 600.00m.

6.7.3.2 Profil en long

 Déclivité maximale : 8.00%,

 Rayon minimal saillant : 1500.00m,

Groupement MCG / SAFI 221


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Rayon minimal rentrant : 1500.00m.

Mais, s’agissant de la réhabilitation des pistes comme le cas de celles du périmètre en question, il a
fallu s’adapter à certains tracés existants où certains critères de la norme citée ne seront pas respectés.

Le profil en travers type ci-dessous a été adopté comme coupe type de piste définitive.

Ce profil type a servi à la détermination des diverses dimensions et quantités (emprises et volumes
des déblais et remblais) obtenues.

Figure 16. Profil en travers type

6.8 NIVELLEMENT DES PARCELLES


Certaines parcelles sont mal ou difficilement irriguées. Ces parcelles ont des cotes supérieures à 2 m
IGN, nous avons prévu un nivellement de ces parcelles à la cote 2.0 m IGN

Ci-après la carte localisation des parcelles à niveler.

Groupement MCG / SAFI 222


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

13-Carte Parcelle haute (A4)

Groupement MCG / SAFI 223


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

7. AVANT-METRES ET DEVIS QUANTITATIF DES TRAVAUX

Les quantitatifs des aménagements par périmètres sont présentés dans les tableaux suivant :

Tableau n° 141 : Avant métrés et devis quantitatif du périmètre Tellel


DESIGNATION UNITE QUANTITE
Canal principal C-1
Travaux de terrassement du canal principal
Déblais mise en remblais m3 14 348
Remblais d'apport m3 434 399
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 850
Béton armé (350Kg/m3) m3 3800
Travaux de terrassement des canaux secondaires, tertiaires, quaternaires et quinquénaires
Déblais mise en remblais m3 68 328
Remblais d'apport m3 130 343
Echelle limnimétrique U 3
Planage des parcelles (Côte >2 m) m3 443 863
Canal principal C-3
Travaux de terrassement du canal principal
Déblais mise en remblais m3 2 431
Remblais d'apport m3 292 540
Travaux de terrassement des canaux secondaires, tertiaires, quaternaires et quinquénaires
Déblais mise en remblais m3 25 136
Remblais d'apport m3 49 021
Echelle limnimétrique U 3
Ouvrages sur canal principal C-1
Ouvrage de transition
Travaux de terrassement
Déblais mise en remblais m3 94
Déblais mis en dépôt m3 76
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 29
Chape béton m3 17
Béton armé (350Kg/m3) m3 139
Ouvrages partiteur
Travaux de terrassement
Déblais mise en remblais m3 38
Déblais mis en dépôt m3 25
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 9
Chape béton m3 36
Béton armé (350Kg/m3) m3 96
Equipements

Groupement MCG / SAFI 224


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Vanne murale (2x1.0) U 6
Vanne de contrôle
Travaux de terrassement
Déblais mise en remblais m3 140
Déblais mis en dépôt m3 93
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 10
Chape béton m3 32
Béton armé (350Kg/m3) m3 107
Equipements
Vanne murale (2x1.5) U 9
Partiteur modulé
Travaux de terrassement
Déblais mise en remblais m3 2
Remblais d'apport m3 12
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 4
Chape béton m3 8
Béton armé (350Kg/m3) m3 93
Equipements
Module à masque XX1-20 U 1
Module à masque XX1-30 U 2
Module à masque XX1-40 U 3
Module à masque XX1-50 U 1
Module à masque XX1-60 U 4
Module à masque XX1-70 U 1
Module à masque XX1-100 U 1
Module à masque XX1-150 U 2
Module à masque XX1-170 U 2
Module à masque XX1-200 U 1
Module à masque XX1-210 U 1
Module à masque XX1-230 U 1
Module à masque XX1-310 U 1
Module à masque XX1-330 U 1
Module à masque XX1-380 U 2
Module à masque XX1-435 U 1
Module à masque L1-500 U 1
Buse d'entrée 300 ml 110
Buse d'entrée  400 ml 20
Buse d'entrée  500 ml 60
Buse d'entrée 600 ml 40
Buse d'entrée  700 ml 10
Ouvrage de traversée
Travaux de terrassement

Groupement MCG / SAFI 225


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Déblais mise en remblais m3 97
Déblais mis en dépôt m3 41
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 22
Chape béton m3 35
Béton armé (350Kg/m3) m3 106
Ouvrage de franchissement
Travaux de terrassement
Déblais mise en remblais m3 80
Déblais mis en dépôt m3 53
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 15
Chape béton m3 18
Béton armé (350Kg/m3) m3 144
Partiteur modulé sur canaux secondaires, tertiaires, quaternaires et quinquénaires
Travaux de terrassement
Déblais mise en remblais m3 3
Remblais d'apport m3 26
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 10
Chape béton m3 16
Béton armé (350Kg/m3) m3 186
Equipements
Module à masque XX1-20 U 41
Module à masque XX1-30 U 36
Module à masque XX1-40 U 17
Module à masque XX1-50 U 4
Module à masque XX1-70 U 3
Module à masque XX1-80 U 2
Module à masque XX1-90 U 1
Module à masque XX1-110 U 2
Module à masque XX1-140 U 1
Module à masque XX1-190 U 2
Ouvrages sur canal principal C-3
Partiteur modulé
Travaux de terrassement
Déblais mise en remblais m3 1
Remblais d'apport m3 9
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 3
Chape béton m3 6
Béton armé (350Kg/m3) m3 66
Equipements
Module à masque XX1-20 U 1

Groupement MCG / SAFI 226


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Module à masque XX1-30 U 2
Module à masque XX1-40 U 3
Module à masque XX1-50 U 3
Module à masque XX1-60 U 1
Module à masque XX1-70 U 1
Module à masque XX1-80 U 1
Module à masque XX1-90 U 2
Module à masque XX1-100 U 1
Module à masque XX1-110 U 1
Module à masque XX1-180 U 1
Module à masque XX1-290 U 1
Module à masque XX1-340 U 1
Buse d'entrée 300 ml 100
Buse d'entrée  400 ml 60
Buse d'entrée  500 ml 10
Buse d'entrée  600 ml 20
Ouvrage de traversée
Travaux de terrassement
Déblais mise en remblais m3 27
Déblais mis en dépôt m3 12
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 7
Chape béton m3 11
Béton armé (350Kg/m3) m3 31
Partiteur modulé sur canaux secondaires, tertiaires, quaternaires et quinquénaires
Travaux de terrassement
Déblais mise en remblais m3 1
Remblais d'apport m3 7
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 3
Chape béton m3 4
Béton armé (350Kg/m3) m3 49
Equipements
Module à masque XX1-20 U 6
Module à masque XX1-30 U 11
Module à masque XX1-40 U 10
Module à masque XX1-80 U 2
Module à masque XX1-110 U 1
Prise parcellaire
Vannette (30x60) U 3942
Conduite PVC DE 300 ml 7884
Béton armé (350Kg/m3) m3 217
Béton de propreté (150Kg/m3) m3 30
Drain principal D2

Groupement MCG / SAFI 227


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Travaux de terrassement
Déblais mis en dépôt m3 5 122
Drain principal D3
Travaux de terrassement
Déblais mis en dépôt m3 101 519
Drains secondaires
Déblais mis en dépôt m3 17 149
Drains tertiaires
Déblais mis en dépôt m3 50 608
Ouvrages sur réseau de Drainage
Ouvrages de traversé
Travaux de terrassement
Déblais mise en remblais m3 63
Remblais d'apport m3 38
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 5
Béton armé (350Kg/m3) m3 96
Ouvrage de rejet
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 13.5
Chape béton m3 4
Béton armé (350Kg/m3) m3 27
Travaux de piste
Déblais mis en dépôt m3 21 389
Remblais d'apport m3 23 870

Fourniture et mise en œuvre du grave latéritique pour la couche de


m3 24 045
roulement d'une épaisseur de 20cm

Planage des parcelles


Planage des parcelles ha 591

Groupement MCG / SAFI 228


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Tableau n° 142 : Avant métrés et devis quantitatif du périmètre Grande Digue


DESIGNATION UNITE QUANTITE
Canal principal C-2
Travaux de terrassement du canal principal
Déblais mise en remblais m3 5 122
Remblais d'apport m3 369 449
Travaux de terrassement des canaux secondaires, tertiaires, quaternaires et quinquénaires
Déblais mise en remblais m3 42 281
Remblais d'apport m3 83 438
Echelle limnimétrique U 3
Canal principal C-4
Travaux de terrassement du canal principal
Déblais mise en remblais m3 2 582
Remblais d'apport m3 305 147
Travaux de terrassement des canaux secondaires, tertiaires, quaternaires et quinquénaires
Déblais mise en remblais m3 37 907
Remblais d'apport m3 75 497
Echelle limnimétrique U 3
Planage des parcelles (Côte >2 m) m3 190 227
Ouvrages sur canal principal C-2
Ouvrage de traversée
Travaux de terrassement
Déblais mise en remblais m3 67
Déblais mis en dépôt m3 29
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 16
Chape béton m3 26
Béton armé (350Kg/m3) m3 75
Partiteur modulé
Travaux de terrassement
Déblais mise en remblais m3 2
Remblais d'apport m3 9
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 3
Chape béton m3 6
Béton armé (350Kg/m3) m3 72
Equipements
Module à masque XX1-20 U 2
Module à masque XX1-30 U 2
Module à masque XX1-50 U 3
Module à masque XX1-60 U 1
Module à masque XX1-80 U 1
Module à masque XX1-95 U 1
Module à masque XX1 100 U 3

Groupement MCG / SAFI 229


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Module à masque XX1-140 U 1
Module à masque XX1-150 U 1
Module à masque XX1-230 U 1
Module à masque XX1-240 U 1
Module à masque XX1-380 U 1
Module à masque XX1-430 U 1
Buse d'entrée 300 ml 80
Buse d'entrée 400 ml 60
Buse d'entrée  500 ml 30
Buse d'entrée600 ml 10
Buse d'entrée  700 ml 10
Partiteur modulé sur canaux secondaires, tertiaires, quaternaires et quinquénaires
Travaux de terrassement
Déblais mise en remblais m3 0
Remblais d'apport m3 19
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 5
Chape béton m3 14
Béton armé (350Kg/m3) m3 146
Equipements
Module à masque XX1-120 U 1
Module à masque XX1-180 U 1
Module à masque XX1-20 U 40
Module à masque XX1-250 U 1
Module à masque XX1-30 U 16
Module à masque XX1-40 U 5
Module à masque XX1-50 U 1
Module à masque XX1-60 U 2
Module à masque XX1-70 U 1
Ouvrages sur canal principal C-4
Ouvrage de franchissement
Travaux de terrassement
Déblais mise en remblais m3 74
Déblais mis en dépôt m3 50
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 13
Chape béton m3 16
Béton armé (350Kg/m3) m3 119
Partiteur modulé
Travaux de terrassement
Déblais mise en remblais m3 17
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 20
Chape béton m3 21

Groupement MCG / SAFI 230


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Béton armé (350Kg/m3) m3 80
Equipements
Module à masque XX1-30 U 1
Module à masque XX1-40 U 5
Module à masque XX1-50 U 1
Module à masque XX1-60 U 2
Module à masque XX1-90 U 2
Module à masque XX1-100 U 1
Module à masque XX1-110 U 1
Module à masque XX1-130 U 2
Module à masque XX1-150 U 1
Module à masque XX1-190 U 1
Module à masque XX1-230 U 1
Module à masque XX1-400 U 1
Buse d'entrée 300 ml 90
Buse d'entrée  400 ml 60
Buse d'entrée  500 ml 30
Buse d'entrée600 ml 10
Partiteur modulé sur canaux secondaires, tertiaires, quaternaires et quinquénaires
Travaux de terrassement
Remblais d'apport m3 16
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 4
Chape béton m3 12
Béton armé (350Kg/m3) m3 127
Equipements
Module à masque XX1-20 U 38
Module à masque XX1-30 U 20
Module à masque XX1-50 U 1
Prise parcellaire
Vannette (30x60) U 3186
Conduite PVC DE 300 ml 6372
Béton armé (350Kg/m3) m3 175
Chape béton m3 24
Drain principal D1
Travaux de terrassement
Déblais m3 97015
Drains secondaires
Déblais m3 27 215
Drains tertiaires
Déblais m3 27 395
Ouvrages sur le réseau de drainage
Ouvrages de traversé
Travaux de terrassement

Groupement MCG / SAFI 231


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

DESIGNATION UNITE QUANTITE


Déblais m3 78
Remblais d'apport m3 47
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 5
Béton armé (350Kg/m3) m3 114
Ouvrage de rejet
Travaux de génie civil
Béton de propreté (150Kg/m3) m3 6.5
Chape béton m3 3
Béton armé (350Kg/m3) m3 13
Tavaux de piste
Déblai m3 11 691
Remblais d'apport m3 14 446

Fourniture et mise en œuvre du grave latéritique pour la couche de


m3 14 277
roulement d'une épaisseur de 20cm

Planage des parcelles


Planage des parcelles ha 478

Groupement MCG / SAFI 232


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

8. MESURES D’ACCOMPAGNEMENT

Cette composante a pour objet de spécifier les besoins du projet en actions complémentaires
permettant de résoudre les problèmes de base rattachés et ou conditionnant la mise en valeur des
périmètres.

L’essentiel des actions portera sur :

 L’amélioration des conditions de vie des femmes ;

 Le renforcement de capacité des producteurs ;

 L’amélioration de l’intégration de la recherche-développement ;

 Le renforcement du système de suivi et d’évaluation du projet ;

 La contribution à la promotion de la commercialisation des produits agricoles.

8.1 AMELIORATION DES CONDITIONS DE VIE DES FEMMES


En dépit de leur participation efficace dans les activités agricoles, les femmes n’ont pas accès à la
terre et ne sont pratiquement pas concernées par les programmes de formation et d’appui.
Actuellement le nombre de femmes –exploitantes est très faible, leur insertion dans la vie
économique est recommandée notamment à travers l’intégration de petits élevages, la pratique de la
culture maraîchère et la commercialisation des produits.

Ainsi des actions d’appui aux femmes sont proposées pour la réalisation d’Activités Génératrices de
Revenus (AGR), notamment dans le domaine du maraîchage, du petit élevage (aviculture et élevage
de petits ruminants). Les appuis porteront sur :

 La sensibilisation sur leur rôle d’acteurs économiques importants ;

 La formation en maraîchage, élevage, crédit, organisation et gestion ;

 L’attribution de parcelles destinées au maraîchage dans les zones d’extension pour les
femmes

 L’aménagement de périmètres maraichers des femmes au voisinage des villages ;

 La création de fermes avicoles.

8.2 FORMATION ET RENFORCEMENT DES CAPACITES


Le renforcement des capacités à travers la formation ciblée des organisations de producteurs et de
celle des producteurs au niveau individuel et collectif devra constituer un des objectifs prioritaires du

Groupement MCG / SAFI 233


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

projet de réhabilitation et de modernisation des aménagements afin de leur permettre d’évoluer et


d’améliorer le niveau de mise en valeur agricole et du niveau de vie..

Organisation des exploitants

Pour permettre de renforcer les capacités des organisations de producteurs (OP) et les amener à gérer
efficacement les infrastructures à mettre en place avec la réhabilitation des infrastructures, il est
recommandé de réaliser les actions suivantes :

 Constitution de groupements d’intérêt économique (GIE) reconnus à la place des


groupements existants ;

 Constitution d’unions de GIE, avec une union par secteur hydraulique ;

 Recrutement de personnel technique compétent (pompistes et aide- gardiens),

 Formation du personnel technique en gestion et en exploitation des équipements et


matériels agricoles ;

 Apurement et sécurisation fonciers des terres :

 Organisation des OP pour fournir des prestations à ses membres (labour, semis, moisson,
battage, approvisionnement en intrants..).

Amélioration des conditions d’accès aux crédits

Une fois que les exploitants seront organisés en structures juridiquement reconnues et officielles, le
projet interviendra pour l’appui au montage des dossiers de crédit des premières campagnes de mise
en valeur après la réhabilitation. Les crédits de campagne à demander couvriront la redevance
hydraulique (frais d’énergie et maintenance), les semences, engrais et herbicides et une partie des
frais de la main d’œuvre et de la mécanisation conformément aux normes d’usage actuelles.

Formation des exploitants et des organisations paysannes

Selon les résultats des contacts effectués avec les structures existantes et les exploitants, la majorité
de ces acteurs a exprimé le besoin de formation en vue de renforcer leurs capacités, notamment dans
le domaine de la gestion de leurs organisations et de maîtrise des techniques culturales.

Les catégories de producteurs ciblés pour la formation et les principaux thèmes de formation à
développer sont comme suit :

8.2.3.1 Dirigeants des organisations paysannes :

 Gestion des structures paysannes, tenue des documents administratifs et financiers :


comptabilité, établissement et publication de bilans annuels ;

Groupement MCG / SAFI 234


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Gestion technique et maintenance ;

 Gestion des crédits agricoles ;

 Organisation des approvisionnements en intrants ;

 Organisation de la commercialisation des produits agricoles ;

 Coordination et coopération entre les différentes structures : organisations paysannes /


services techniques, de recherche et administratifs ;

 Collecte, stockage, conditionnement, conservation et transformation des produits ;

 Intégration des activités agricoles et d’élevage ;

 Programmation, choix et emploi des outils et machines agricoles

 Implication et participation des acteurs à l’analyse des campagnes agricoles ;

 Organisation de manifestations sectorielles de développement des filières : journée


d’information, foires…

8.2.3.2 Exploitants :

 Entretien des infrastructures et des équipements ;

 Techniques de production et incitation à l’intensification des cultures ;

 Nécessité de développer la comptabilité de l’exploitation : calcul des coûts, valorisation


des sous-produits, intérêt des organisations paysannes ;

 Protection de l’aménagement contre l’incursion du bétail : modes et techniques de clôture,


plantation et entretien de haies vives, etc.

 Opérations de post-récolte liées à la commercialisation ou aux travaux culturaux


(déchaumage, ramassage des pailles…).

Tableau n° 143 : Le coût de cette intervention est ventilé comme suit :


Types d’actions Intervenant Profil Durée Année Coûts ( 106 FCFA)
Const. OP consultant institut -socio 3 ans x 6 mois 1-2-3 54
Formation OP Consultants  communicat. 2 ans x 2 mois 1-2 12
 Organisat 1 an x 2 mois 1 3
 gestion 3 ans x 2 mois 1-2-3 18
Formation consultants/ vulgarisation, 3ans x 3 mois x 1-2-3 81
Exploitants vulgarisateurs 3 animateurs
Expo / foires appui 5 ans 1-2-3-4-5 75

Groupement MCG / SAFI 235


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Renforcement de la recherche-développement

Eu égard à la série de contraintes et dysfonctionnement rencontrées dans la mise en valeur actuelle de


l’aménagement rizicole de la digue Tilleul (envahissement des canaux par le typha, stabilisation voire
régression des rendements, quasi-abandon de la campagne d’hivernage, semis direct…), cette
composante revêt une grande importance pour la durabilité et la pérennisation de la mise en valeur
ainsi que l’intégration des différentes actions : élevage pisciculture...

A travers cette composante le projet contribuera à promouvoir la recherche /développement des


systèmes culturaux suivis. Il s’agit d’un appui aux programmes de l’Institut de Recherche
agronomique Sénégalais.

Les principaux axes se composent de :

 Suivi de la fertilité du sol ;

 Amélioration des itinéraires techniques ;

 L’introduction de la technique rizicole SRI ;

 Amélioration du drainage et promotion de la campagne d’hivernage ;

 Intégration d’autres activités agricoles connexes et valorisant les sous-produits : petit


élevage, pisciculture. ;

 Choix des équipements adéquats de travail du sol et d’une mécanisation rationnelle


adaptée;

 Reprise du repiquage en remplacement au semis direct à la volée ;

 Emploi de l’énergie solaire pour le pompage du drainage,

 La lutte contre l’adventice typha qui envahit les canaux d’irrigation et de drainage.

Le cout de cette action est ventilé comme suit :

Tableau n° 144 : Coûts de la composante recherche développement


Nb Personnel Personnel Investissem F.fonctiont/ an Honoraire/ an
Action Equipements
années cadre Appui (10.6 FCFA) (10.6 FCFA) (10.6 FCFA)
1 véhicule TT 37,5 12
Suivi fertilité sol 5 2 4 22
matériel labo 10 5
2 véhicules TT 75 12
22
matériels 45 5
Amél It Tech 5 2 4
parcelle de
15 3 6
démonstration
lutte typha 5 0,5 1 5,5
1 véhicule TT 35 5
mécanisation 5 1 3 13,5
matériels 45 5

Groupement MCG / SAFI 236


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

8.3 EQUIPEMENTS D’APPUI


Les équipements d'appui suivants sont proposés pour améliorer les effets du projet. Ils amélioreront
le cadre de vie des résidents et 1'environnement de production des agriculteurs.

 Magasin pour machines agricoles et équipements d’usinage des produits agricoles,

 Des équipements pour l’amélioration du cadre de vie et du cadre sanitaire,

 Bâtiments pour le stockage de produits agricoles.

Maison Communautaire (Maison du Village)

La maison communautaire sera située dans le village de Ross-Bethio. Les autres localités de la zone
du projet sont éloignées de l’endroit où vivent la plupart des paysans. Les dimensions de la maison
communautaire sont de 70x20 m.

Magasin

Le magasin sera construit pour stocker des produits agricoles. Les dimensions du magasin sont de
15x50 m.

Magasin pour Machines Agricoles

Le plan du magasin pour machines agricoles est préparé en considérant la ligne de mouvement la
plus courte et l'efficience spatiale. Les dimensions du plan sont de 70x30 m.

Rizerie

Une rizerie sera fournie pour les agriculteurs riziers. Les dimensions de la rizerie sont de 30x20m.

Département PR

Le département PR sera situé à côté de la Chambre de Contrôle. Ce sera une salle d’exhibition pour
la promotion des relations publiques dans le cadre du Projet. Le bâtiment du département PR sera
équipé de vidéo et de documents. Les dimensions du Département PR et de la chambre de contrôle
sont respectivement de 12x12 rn et 18x12 rn.

Chambre du Concierge

La chambre du concierge sera située près de la station de pompage sur la gauche de la station de
pompage existante. Cela empêchera le vol dans des équipements comme la station de pompage, les
générateurs solaires et offrir un bon cadre pour le gérant. Les dimensions de la chambre du concierge
sont de 10x6 m.

Groupement MCG / SAFI 237


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Le tableau suivant récapitule les besoins en construction

Tableau n° 145 : Equipements d’appui aux agriculteurs


Equipement Dimensions (m) Nbre Surface (m2)
Maison communautaire 20x70 1 1400
Magasin 15x50 2 1500
Magasin pour machines agricoles 30x70 1 2100
Rizerie 20x30 1 600
Département PR 12x30 1 360
Chambre concierge 6x10 1 60

Groupement MCG / SAFI 238


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

9. SPECIFICATIONS TECHNIQUES DU PROJET DE REHABILITATION

9.1 EQUIPEMENTS HYDROMECANIQUES ET PIECES SPECIALES

Remise en état des pièces à conserver

Les travaux de remise en état des pièces spéciales et équipements hydromécaniques à conserver dans
les ouvrages existants sur le réseau comprennent :

 Nettoyage et brossage des pièces spéciales et des équipements,

 Mise en œuvre de peinture (2 couches) antirouille et anticorrosion,

 Démontage de ces pièces avec changement des joints et boulonneries si ces derniers sont
irrécupérables.

Remplacement des pièces défectueuses

Les pièces spéciales et tout appareillage défectueux seront remplacés par des nouvelles pièces. Les
travaux comprennent :

 Le démontage des pièces spéciales et robinetterie,

 Le montage des nouvelles pièces,

 Le remplacement des joints d’étanchéité défectueux entre les pièces démontées,

 Le remplacement des boulons défectueux.

9.2 RESEAU D’IRRIGATION

Canaux bétonnés

Les canaux en béton armé peuvent être coulés sur place ou préfabriqués. Afin de réaliser ces travaux
les actions suivantes sont nécessaires.

9.2.1.1 Déblai

Il comprend :

 Le débroussaillement comprenant l’enlèvement des arbres et arbustes quelle que soit la


circonférence du tronc, l’arrachage des souches, le nivellement du terrain et la mise en tas
de la végétation à l’extérieur du périmètre,

 Le déblai en tout terrain et quelques soit la profondeur,

 L'obtention des autorisations diverses,

Groupement MCG / SAFI 239


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Le levé du profil en long du terrain naturel, le piquetage dans l’implantation du canal,

 L’aménagement éventuel des accès, le dégagement de l’emprise nécessaire à l’exécution


du travail,

 Les sujétions de rencontre de réseaux divers enterrés de toute nature, de fouille à la main si
l'encombrement du sous-sol l'exige, d'utilisation d'engins et de matériels adaptés au terrain,

 Le réglage des déblais extraits mis en cordon en une couche unique de 0,20 m, y compris
l’enlèvement et la mise en tas des grosses pierres, des débris de branches, des souches et
nivellement,

 Le réglage du fond de fouille et des pentes aux cotes du projet, le talutage au fruit défini
par le projet.

9.2.1.2 Remblai

La hauteur de remblai est calculée comme suit la différence entre le niveau d’assise du futur canal
moins la cote initiale. Cette cote moyenne est estimée à partir d’un profil en travers tous les 20 m
pour l’application de plus-values pour rehaussement de canal.

Les terrassements excédentaires par rapport aux profils ne seront pas pris en compte par
l’administration dans le calcul des volumes à régler par l’Entrepreneur.

9.2.1.3 Construction des canaux

Les prix de construction de canaux incluent :

 Les travaux préparatoires (levé topographique, mise en dépôt de la terre végétale,


décapage, débroussaillage, dessouchage,),

 La fourniture, le transport et la pose du béton armé ainsi que son réglage altimétrique,

 La fourniture et l’installation de joint tous les 10 mètres au minimum,

 La remise en état des zones de travaux.

Canaux en terre

Les travaux de réhabilitation des canaux en terre se diffèrent selon le degré de réhabilitation :

9.2.2.1 Canaux à renouveler

Les canaux caractérisés par une dégradation importante nécessitent une reprise totale de la section
initiale. Les actions nécessaires sont les suivantes :

 Décapage total des parties existantes du canal jusqu’à la cote du projet,

Groupement MCG / SAFI 240


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Réalisation d’un nouveau canal.

Il est à noter que les canaux du périmètre à renouveler totalement sont essentiellement:

 Les tronçons avals des canaux à l’extrémité du périmètre,

 Les canaux de la zone totalement envahie par la végétation.

9.2.2.2 Canaux à réhabiliter

La remise en état consiste à rétablir la section initiale du projet des canaux primaires et secondaires.
Cette action nécessite les interventions suivantes :

 Le curage des canaux aux cotes de calage du projet,

 La remise en état des talus par l’apport du remblai.

La remise en état des talus des canaux consiste en un renforcement partiel à la cote du projet.

Avant la mise de remblai de comblement, le remblai existant doit être décapé sur une hauteur
minimale de 20 cm. Des précautions spécifiques sont à prendre dans ce cas de travaux : préparation
de la plateforme, compactage des matériaux pour remblaiement, vérification de la stabilité des
matériaux posés.

9.2.2.3 Caractéristiques des canaux

Les canaux d’ordre primaires et ceux d’ordre secondaires en terre ont une section trapézoïdale de
pente des talus de 3/2. Les caractéristiques des canaux sont présentées par le tableau suivant :

Tableau n° 146 : Caractéristiques des canaux d’ordre primaire et secondaire


Canal Longueur (m)
Canal principal C-1 10 190
Canal principal C-2 8274
Canal principal C-3 6790
Canal principal C-4 6866
Canaux d’ordre secondaires 218 668

9.3 DRAINS

Travaux prévus

Les travaux de réhabilitation à engager sur le réseau des drains sont :

 Les levés des profils en long et en travers des drains,

 Le calage de la ligne du projet,

 Le débroussaillement comprenant l’enlèvement des arbres et arbustes quel que soit la


circonférence de tronc, l’arrachage des souches, le nivellement du terrain et la mise en

Groupement MCG / SAFI 241


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

dépôt ou évacuation en décharge des arbustives et matériaux décapés selon les directives
de l’Administration,

 Le déblai en tout terrain et quel que soit la profondeur,

 l’aménagement éventuel des accès, le dégagement de l’emprise nécessaire à l’exécution


des travaux

 Les travaux de terrassement à la main ou par engins et de matériels adaptés au terrain,

 le réglage du fond de fouille et des pentes aux cotes du projet, le talutage au fruit défini par
le projet,

 l'étaiement éventuel des ouvrages.

Drain à renouveler

1. Les drains caractérisés par une dégradation importante nécessitent une reprise totale de la
section initiale. Les actions nécessaires sont les suivantes :
 Décapage total des parties existantes du canal jusqu’à la cote du projet,

 Réalisation d’un nouveau canal.

Le tableau ci-dessous récapitule les longueurs des collecteurs de drainage.

Tableau n° 147 : Caractéristiques des collecteurs de drainage


Collecteur Longueur (m)
Drain principal D1 5217
Drain principal D2 1040
Drain principal D3 5723.0
Drain secondaire D1.1 1238
Drain secondaire D1.2 3082
Drain secondaire D2.1 1218
Drain secondaire D2.2 1156
Drain secondaire D2.3 2396
Drain secondaire D2.4 1055
Tous les drains tertiaires 31 201

9.4 PISTES
Les travaux de réhabilitation des pistes nécessitent le recharge des points particuliers en latérites
conformément au profil en travers type. Une attention particulière est à apporter au drainage des eaux
de pluies. Les devers des pistes doivent être correctement exécutés de manière à faciliter l’évacuation
des eaux excédentaires. Les eaux de drainage des pistes doivent être collectées par un fossé latéral en
terre puis évacuées vers le rejet le plus proche (drains dépression, cours d’eau).

Groupement MCG / SAFI 242


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

9.5 OUVRAGES COURANTS


La remise en état du génie civil de chaque ouvrage endommagé comprend :

 le repiquage des parois jusqu’au niveau béton,

 fourniture et mise en place d’une couche de mortier étanche pour enduit sur les faces
intérieures et extérieures de l’ouvrage.

Ces travaux comprennent la reprise de fissure sur les ouvrages en béton armé. Il s’agit de nettoyage
et approfondissement de la fissure, application du mortier avec adjuvant à base de Sika et lissage.

Groupement MCG / SAFI 243


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

10. RECOMMANDATIONS COMMUNES POUR LA GESTION DU PERIMETRE

10.1 CONTROLE DES NIVEAUX D’EAU


La gestion des différentes composantes du système nécessite un contrôle continu des niveaux d’eau.
Ainsi il est nécessaire de suivre le niveau d’eau dans le Lampsar, (juste en amont de la station) ainsi
que dans les différents canaux principaux. La connaissance des niveaux d’eau permet au gestionnaire
de décider quant à l’irrigation et à la disponibilité en eau. Le suivi du niveau d’eau dans chaque canal
peut être réalisé par l’installation d’échelles limnimétriques installées en amont, au milieu et en aval.

Sur le terrain, un réseau d’échelles limnimétriques aux points clés de chaque canal permet les relevés
des niveaux d’eau et par suite des débits disponibles et de détecter les pertes d’eau importantes.

Ces échelles permettent de connaître l’état de chaque canal en temps réel plusieurs fois par jour. Elles
constituent donc l’outil de base pour la gestion du réseau ;

10.2 CONTROLE DES DEBITS


Le contrôle des débits dans chaque axe peut se faire aussi par la mesure du niveau d’eau. Les débits
peuvent être déduits des courbes de tarage de chaque canal.

10.3 GESTION HYDRAULIQUE DE LA STATION DE POMPAGE


Afin d’assurer une exploitation optimale de la station de pompage certains principes sont à prendre
en compte à savoir :

 La connaissance par anticipation des apports du Fleuve est un paramètre incontournable.


En effet, le Lampsar, source d’alimentation du périmètre, est sous l’influence hydraulique
du barrage Diama, notamment en hivernage, période où la demande est la plus importante.
Il est donc nécessaire de connaître la cote de consigne définie pour Diama et le type de
gestion des niveaux. La connaissance de prévisions de crue et de pluviométrie sur le bassin
versant du Fleuve Sénégal est également opportune pour les gestionnaires.

 Il est donc nécessaire de renforcer et formaliser la communication des informations


concernant le niveau du fleuve afin de connaître avant et pendant la campagne les débits
disponibles en tête de réseau.

 La connaissance du niveau d’eau dans le Lampsar permet de décider quant à l’irrigation


gravitaire. Ceci permettra de profiter du niveau d’eau afin de réduire les frais d’énergie
engendrés par le pompage. La courbe de tarage du canal d’alimentation gravitaire doit être
fournie au pompiste.

Groupement MCG / SAFI 244


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

10.4 ENTRETIEN

Entretien des canaux et collecteur de drainage

Les travaux d’entretien sur les canaux et drains primaires visent à :

 Maintenir la capacité des infrastructures pour véhiculer les débits;

 Maintenir la praticabilité des pistes.

Pour ce faire, les travaux d’entretien périodique suivants sont nécessaires :

 Faucardage manuel [m2]

 Faucardage mécanique [m2]

 Curage [m3]

 Recharge et renfort d’endiguement [m3]

 Nivelage des cavaliers [m2]

 Cantonnage des cavaliers [m3]

 Débroussaillage [m2]

Tous ces travaux sont classés en entretien périodique. Le tableau ci-dessous présente les fréquences
normatives de ces interventions comme présentées dans l’Etude pour la Mise en Place d’un Fonds de
Maintenance des Aménagements Hydro-agricoles dans la Vallée du Fleuve Sénégal.

Tableau n° 148 : Fréquences standards des travaux d’entretien périodique


TRAVAUX UNITE FREQUENCE
Faucardage manuel m2 1/5
Faucardage mécanique m2 1/5
Curage m3 1/20
Recharge endiguement m3 1/5
Nivelage cavaliers m2 1/5
Cantonnage cavaliers m3 4/5
Débroussaillage m2 1/20

Entretien des ouvrages

Les différents travaux de maintenance des ouvrages et de leurs équipements hydromécaniques sont
classés selon le caractère courant, périodique ou exceptionnel de ces interventions.

Tableau n° 149 : Opérations de maintenance des ouvrages civils et des structures métalliques
Nettoyage de l’ouvrage et de ses abords
Entretien courant Nettoyage des équipements hydromécaniques
Ragréage et rebouchage de trous
Entretien périodique
Groupement MCG / SAFI 245
ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

Traitement anti-corrosion des éléments métalliques


Réparation des systèmes de levage et des glissières
Réparation des fissures et de toute autre dégradation sur le
béton armé
Travaux de confortement, de protection et éventuellement
de substitution aux niveaux des affouillements, des perrés
Entretien exceptionnel et des gabions
Remplacement, redressement et renforcement des éléments
défectueux des structures métalliques et hydromécaniques
En ce qui concerne les éléments hydromécaniques tels que les crics de levage ou autres, il est
conseillé de suivre les critères d’entretien recommandés par le fabricant. Lors de la mise en place de
ce type d’équipement, l’Entrepreneur devra remettre au maître d’ouvrage le guide d’utilisation et
d’entretien de ces appareils.

Groupement MCG / SAFI 246


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

11. CONDITIONS DE REALISATION DES TRAVAUX

11.1 REPARTITION EN LOTS


Les travaux seront répartis comme suit :

 Lot 1 : Travaux de terrassement et de Génie Civil pour la réhabilitation et l’extension du


périmètre de Tellel.

 Lot 2 : Travaux de terrassement et de Génie Civil pour la réhabilitation et l’extension du


périmètre de Grande Digue.

 Lot 3: Fourniture et installation des équipements électriques et électromécaniques. Ce lot


comportera tous les postes de fourniture et d’installation des équipements électriques, et
électromécaniques de la station de pompage de Grande Digue Tellel prévue pour irriguer
3600 ha.

Les travaux du réseau d’irrigation peuvent être réalisés en période d’irrigation mais ils doivent être
coordonnés avec le tour d’eau afin que les périodes d’irrigation ne soient pas perturbées.

Les travaux du réseau de drainage et de piste seront réalisés en parallèle avec les travaux du réseau
d’irrigation.

Il est recommandé de regrouper les travaux de même nature, ce qui permettra de mieux rentabiliser la
préfabrication d’éléments en béton et d’assurer une meilleure qualité des ouvrages construits. Les
travaux pourront donc aussi être regroupés par secteur géographique.

11.2 PROGRAMMATION DES TRAVAUX


Il convient de programmer les travaux de manière à porter le moins de préjudice possible à
l’exploitation. Les travaux peuvent être réalisés hors saison de pluie, toutefois, il est préférable de les
commencer juste après la période hivernale afin de finaliser une partie du périmètre avant le début de
la campagne.

Les travaux devront ainsi être planifiés de manière à limiter la durée de non exploitation du
périmètre. Les travaux peuvent être planifiés de la manière suivante.

 Réhabilitation de la station de pompage,

 Réalisation des travaux des canaux principaux,

 Réalisation de travaux des canaux secondaires, tertiaires quaternaires et quinquénaires,

 Exécution des ouvrages courants (ouvrage modulé, ouvrage partiteur, ouvrage traversée,
vannes, prises,…),

Groupement MCG / SAFI 247


ETUDES D'AVANT PROJET DETAILLE (APD) ET DE DOSSIER D'APPEL
D'OFFRES (DAO) POUR LES TRAVAUX DE REHABILITATION ET Rapport APD
L'EXTENSION DU PERIMETRE GRANDE DIGUE-TELLE (3600 HA) ET LES
TRAVAUX DE REHABILITATION DE LA STATION DE POMPAGE DE
GRANDE DIGUE-TELLEL (3600 HA

 Réalisation des travaux du réseau de drainage en commençant par l’aval, (de l’exutoire
jusqu’aux parcelles),

 Réalisation des pistes.