You are on page 1of 2

“Triple” Gold Card© EVM in Perspective Organization

Quick Reference Guide for Define the Control Accounts


Critical Thinking. Solutions Delivered.

Earned Value Management (EVM) EVM does not exist in isolation. It must be employed in the •F  ocus for Cost/Schedule/Tech Mgmt
­execution of some work to create or produce something of • A CA Manager is assigned
is provided as a quick reference and checklist. It addresses Cost,
www.mcri.com (703) 506-4600

­value (a project or service with the attributes of cost, schedule, and • Analysis should be done
Schedule, and Performance (thus TRIPLE) while touching on all
­technical) with a clear start and stop related to the p
­ roduct/ at this level or lower
5 major areas of EVMS. You can obtain a PDF version of the
service. EVM integrates various project components.
CARD at www.mcri.com The Performance Measurement Baseline (PMB) represents
Earned Value Management is a methodology that considers the time phased, costed technical performance.
a ­discrete project’s scope (performance), time (networked schedule),
­resources (people and materials), and their related uncertainties (risks)
in an integrated system which meets intent of the ANSI/
EIA-748 Earned Value Management System (EVMS) Standard.
The Standard guidelines are grouped into five major categories:
1. Organization – define work (WBS), organization (OBS),
and related integrated processes…
2. Planning, Scheduling, and Budgeting – develop a discrete
time-phased budget baseline which identifies work with physi-
cal products, milestones, performance goals, and other indica-
tors of progress…
3. Accounting Considerations – valid, timely,
and auditable information...
4. Analysis and Management Reports – at least monthly at
Planning, Scheduling and Budgeting
MCR’s “TRIPLE” GOLD CARD©

control account and other levels…


5. Revisions and Data Maintenance – authorized changes Planning, Scheduling and Budgeting
are controlled, timely… Plan the work by breaking the control accounts into work packages
which can be “easily” executed.
Schedule the work using a Critical Path Methodology schedule.
Budget the work by assigning resources to the schedule elements.
Earned Value Techniques (suggested implementations)
A - Level of Effort (Work that is impossible or impractical to measure)
References
Office of Management and Budget www.omb.gov Performance Assessment/Analysis B - Weighted Milestones (At least one milestone per month)
C - Percent Complete (Subjective estimate of performance; 3 – 6 months)
Circular A-11, Supplement to Part 7 – Capital Programming Guide
MCR’s LCAA - Linked CREST Assessment and Analysis is used D - Units Complete (Production lots; each item is assigned an equivalent cost)
Federal Acquisition Regulations www.acquisition.gov/far/ in MCR’s LENS & SNA Software’s Proteus Envision Tool Suite
52.234-2 Notice of EVM System - Pre-Award IBR. E - 50/50 (Fixed formula 50% to start,50% to finish; not more than 2 months)
A four gate process which assist PM teams in capturing ­fundamentals
52.234-3 Notice of EVM System - Post Award IBR of Integrated Program Management (IPM) to exploit the synergy F - 0/100 (Fixed formula 0% to start, 100% to finish; not more than 1 month)
52.234-4 Earned Value Management System ­generated by linking CREST knowledge areas utilizing long- G - 100/0 (Fixed formula 100% to start, 0% to finish; not more than 1 month)
MCR, LLC

Data Item Descriptions (DIDs) https://assist.dla.mil/ standing quantitative disciplines at the Control Account level (or lowest H - User Defined (User defined fixed formula; not more than 2 months)
CWBS DI-MGMT-81334 level available). This process produces robust, ­statistically ­developed,
quantified cost and schedule views that cut through the fog to provide I - Apportioned Effort (Performance is based upon another control account)
CPR DI-MGMT-81466
clear actionable information to the program m ­ anagement team. J - Planning Package (Future work that is planned at a high level)
IMS DI-MGMT-81650
IPMR DI-MGMT-81861 Cost Estimating and Basis of Estimate Analysis K - BE% Complete (Budget element percent complete; subjective estimate)
Risk / Opportunity Assessment Analysis L - Calculated Apportioned (Performance based on percentage of other CA)
Guidance www.ansi.org www.gao.gov www.ndia.org/ipmd
ANSI/EIA-748 Earned Value Management Systems Earned Value Assessment and Analysis
Earned Value techniques should reflect the control account
GAO-09-3SP GAO Cost Estimating and Assessment Guide Schedule Assessment and IMS Analysis ­technical performance measures and risk profile
Earned Value Management Systems Intent Guide Technical Performance Measurement and Analysis
Earned Value Management Systems Application Guide
Reproduction of this material must be in whole, all rights reserved.
Copyright 2006, 2007, 2010, 2014 Version 5.0
Establish the Performance Report the Data and Analyze the Variances Earned Value Management Best Practice
Variances – Favorable is Positive, Unfavorable is Negative
Measurement Baseline Cost Variance CV = BCWP – ACWP CV% = (CV / BCWP) * 100
Organization
Schedule Variance SV = BCWP – BCWS SV% = (SV / BCWS) * 100
q WBS top level clearly describes one end-product or deliverable
Variance at Completion VAC = BAC – EAC
qW BS represents the entire technical scope and represents products and not
budget categories, organizations, personnel, tasks, functions, or project
Performance Indices – Favorable is >1, Unfavorable is <1 phases
Cost Efficiency CPI = BCWP / ACWP q Each WBS subordinate element has only one parent
Schedule Efficiency SPI = BCWP / BCWS q E ach subcontracted effort is assigned to a single WBS element
(unless subcontractor is responsible for multiple components)
Overall Status
%Schedule = (BCWSCUM / BAC) * 100 q The Control Account (CA) is the point of management control and analysis
% Complete = (BCWPCUM / BAC) * 100 Planning, Scheduling, and Budgeting
% Spent = (ACWPCUM / BAC) * 100 q All tasks have unique names with milestones representing key events
Estimate At Completion q Work Packages are not identified as WBS elements
EAC (LRE) = Actuals to Date + [(Remaining Work) / (Efficiency Factor)] q Work Packages average less than 90 days
EAC CPI = ACWPCUM + [(BAC – BCWPCUM ) / CPICUM ] = BAC / CPI q P lanning Packages are usually less than one year and most often are tied to a
Rolling Wave; the Rolling Waves are tied to significant project events
EAC COMPOSUTE = ACWPCUM + [(BAC – BCWPCUM ) / (CPICUM * SPICUM )]
qM
 ethods selected to measure work accomplished against plan must be ­
To Complete Performance Index (TCPI) objective and meaningful based upon Technical Performance Measures
TCPI = Work Remaining / Cost Remaining = BAC – BCWPCUM ) / (EAC – ACWPCUM ) q Schedule tasks are derived from a product-based WBS
Variance Analysis q Schedule networks are created by linking lowest level tasks only
Accounting Considerations Variances that exceed thresholds must be analyzed and explanations provided: q E ach schedule task has at least one predecessor and at least one successor
Problem, Root Cause, Impact, Corrective Action, and Get Well Date (Exceptions: first and last task or external milestones)
q Record / reconcile costs with accounting system at the q U se of schedule lags/leads is minimal; a lag/lead may be injected into the
control account or lower Address: P
 oorPlanning,RateVariances,TechnicalProblems,Risks,EffectonControl schedule n­ etwork only for a specific purpose, not as shortcuts to identifying
q Record and allocate indirect costs in accordance with Account, and Effect on Contract logical sequences of events or to override event sequencing
established procedures
q Record costs for work performed in same period that q Use of task constraints is minimal, usually only for key contractual milestones
earned value is measured q Stakeholders validate Schedule, Scope, Task Logic, and Durations
q Baseline is set, then an Integrated Baseline Review (IBR) is conducted
Revisions and Data Maintenance q Management Reserve (MR) is based on risks in baseline risk register
q Incorporate changes in a timely manner, prior or with start of effort Accounting Considerations
q Control retroactive changes and control revisions to the baseline qW
 BS lowest elements are broken down into convenient ‘work packages’ which
Analysis and Management Reports are used to group, summarize/monitor elements of cost (e.g., labor, material)
Measure and Report Performance Monthly q Estimated actuals are used to assure realistic actual costs in a timely manner
Glossary Analysis and Management Reports
q Reporting is at lowest WBS level necessary for effective management
ACWP - Actual Cost forWork Performed; Cost of work accomplished = ACTUAL COST (AC) q LOE is extracted when evaluating actual progress and performance
BCWP - B udgetedCostofWorkPerformed;Valueofworkaccomplished=EARNEDVALUE(EV) q Cost, Schedule, Technical along with risks and opportunities are tracked
BCWS - B udgetedCostofWorkScheduled;Valueofworkplannedtoaccomplish=PLANNEDVALUE(PV) q V ariances are analyzed, they are neither good nor bad, but variations that
BAC - Budget at Completion; Total budget for total contract through any given level ­indicate areas that might need management action
CA - C
 ontrol Account; Lowest CWBS element assigned to a single focal point to plan q EAC analysis is based on time/cost estimates adjusted for risks/opportunity
and control technical / cost / risk / schedule q Project MR ‘burn down’ rates with assumptions regarding potential distribution
CBB - Contract Budget Base; Sum of all work scope assigned to a designated contract q Network critical path (plus some float) focus of schedule/SPI analysis
EAC - EstimateatComplete;Thebestestimateofthetotalcostatthecompletionoftheprogram q Track schedule metrics to assess goodness of schedule, include start/finish
LRE - Latest Revised Estimate; Contractor’s EAC or EAC slips, tasks near critical path, float/slack, etc.
MR - Management Reserve; Budget withheld by Ktr PM for unknowns / risk management q Pessimistic/Most Likely/Optimistic estimates are made for costs and time
PMB - Performance Measurement Baseline; Program time–phased budget plan
PP - Planning Package; Far-term CA activities not yet defined into WPs Revisions and Data Maintenance
SLPP - Summary Level Planning Package; Far-term activities not yet defined into CAs q CCB approval is required for changes to scope, schedule or budget
TAB - Total Allocated Budget; Sum of all budgets for work on contract = NCC, CBB, or OTB q D evelop realistic CA EACs integrated with technical, cost, and schedule
risks/opportunities
TCPI-ToCompletePerformanceIndex;EfficiencyneededfromtimenowtoachieveanEAC
UB - Undistributed Budget; Broadly defined activities not yet distributed to CAs q Mitigation plans have triggers, are included in PMB, and are tied to metrics
WP - Work Package; Near-term, detail-planned activities within a CA q P M should re-plan as necessary within scope or reprogram to new scope so
plan and/or estimate represents the real planned effort

You might also like