ESTIMATE

................................................................
................................................................
...........

NO L B H Qty Unit Rate Amount


1 Earth work excavation

1 7.8 10.4 2.5 202.8


Column 14 1.2 1.2 0.6 12.096
214.9 m3 925 198,778.80
2 P.C.C 1:4:8 using 40 mm
broken stone for foundation
including all cost of materials
and labour etc complet
1 7.8 10.4 0.1 8.112 m3 6000 48,672.00
3 Reinforced cement concrete 1:1.5:3
for Footing Using 20mm brockan
materials and labour etc. Complete.
Column Footing 14 1.2 1.2 0.6 12.096
Wall footing 1 30 1.5 0.45 20.25
32.346 m3 9000 291,114.00

4 Reinforced cement concrete 1:1.5:3 for


Raft .Using 20mm brockan stone .

Including the cost of all materials and


labour etc. complete. But excluding
the cost of reinforcement.
1 7.7 10.4 0.3 24.024
24.024 m3 9000 216,216.00

5 Reinforced cement concrete 1:1.5:3 for

column .Using 20mm brockan stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
column 14 0.2 0.4 3 3.36
3.36 m3 9000 30,240.00

6 Reinforced cement concrete 1:1.5:3 for


beam and lintel .Using 20mm brockan
stone .

Including the cost of all materials and

S3 1/12
ESTIMATE

labour etc. complete. But excluding


the cost of reinforcement.
out side lintel 2 7.9 0.2 0.6 1.896
2 10.4 0.2 0.45 1.8886
2 7.9 0.2 0.45 1.422
1 7 0.2 0.3 0.42
5.6266 m3 9000 50,639.76

7 Reinforced cement concrete 1:1.5:3 for


slab .Using 20mm brockan stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
slab 1 8 11 0.12 10.56
stair 1 9 1.2 0.12 1.296
11.856 m3 9000 106,704.00
Reinforcement for R.C.C works
8 bent,tied
and placed in position . Using HYSD
steel

including the cost of binding wair, all


materal and labour etc.complet.
Say item no 3,6,9,11 and 12 .Qty 77.213 m3
Say 28.937 m3/120.00 kg 7721.3 kg 60 463,275.84

9 Wall plastring CM 1:4.Using good

quality sand including the cost of

all materials and labour etc. complete.


inside
Retaining wall 1 37 3.3 122.1
column 14 1.3 3.3 60.06
beam 2 7.9 1.2 18.96
2 10.4 0.9 18.72
2 7.9 0.9 14.22
1 7 0.6 4.2
slab 1 8 11 88
326.26 m2 410 133,766.60

GROUND FLOOR

10 Reinforced cement concrete 1:1.5:3 for

column .Using 20mm brockan stone .

S3 2/12