Professional Documents
Culture Documents
1.0.0 INTRODUCTION
1.1.0 Summary of requirements
1.2.0 Preconditions
1.3.0 Auxiliaries
Stage 2
5.1.5 Membrane Element Loading
2
5.1.6 Stage 3 Membrane Element Flushing
3
4
5
6.2.0 Flushing & Commissioning of Anti scalant Dosing
System
6.2.1 Precondition for flushing of the Filling pumps
6.2.2 Procedure
6.2.3 Pre-condition for flushing
6.2.4 Procedure
6.2.5 Pre-condition for commissioning
6.2.6 Procedure
6.2.7 Coagulant Dosing and Preparation
6.2.8 Solution preparation - determination of
concentration
6.4.2 Procedure
6.4.3 Pre-condition for commissioning
6.4.4 Procedure
6.4.5 Coagulant Dosing and Preparation
6.4.6 Preparation of SMB solution for the first filling
6.4.7 Preparation of SMB solution during normal
operation
7
9.0.6 Preconditions 9.0.7
Flushing Procedure 9.0.8 Low Pressure
Flushing 9.0.9 High Pressure Flushing
9.0.10 Procedure 9.0.11 Flushing and
st
Commissioning of 1 Pass RO
Flushing System
9.0.12 Procedure 9.0.13 Flushing of the 2nd Pass RO Train Feed
and Brine
Manifolds, Headers and HPP
9.0.14 Procedure 9.0.15 Low Pressure Flushing 9.0.16
High Pressure Flushing 9.0.17 Procedure
APPENDIXES
8
1.0.0 INTRODUCTION
The following document summarizes the procedures required for Al Jubail SWRO
Desalination plant-Phase 2, plant flushing & process commissioning. It assumes a
number of pre-conditions (which are listed in each section) and is based on the
possibility of proper flushing & commissioning the plant. Detailed plant sequences
are not included in this document as they are in the single equipment Operating &
Maintenance Manual, produced by equipment manufacturers. These procedures
are referred to throughout this document.
1.3.0 Auxiliaries
To enable efficient flushing as well as commissioning the following list of auxiliary
temporary equipment if required:
• Temporary pipe connections for the flushing
• Hand held laboratory equipment necessary for commissioning
• Walkie - talkie set
9
2.0.0 FLUSHING AND COMMISSIONING
Once all necessary preparations have been made and the required temporary
equipment is available flushing of the equipment & commissioning can
commence.
Detailed stepwise procedures for the manual flushing and commissioning of each sub-
system are provided in the manufacturer’s single equipment O & M, and to be
strictly followed.
A full logbook of activities and difficulties encountered should be maintained. This
should be supplemented by the completion of the relevant datasheets and test
record sheets which require signing by the commissioning engineer and
the client.
Any errors in the manufacturers O&M manual shall be noted and corrected to
submission of the final document.
All centrifugal pumps shall be started against closed or only crack opened
discharge valve when downstream pipes are only partially full or completely
empty. It is recommended to fill the pipes with water by small pump or service
water system prior start up of the pumps.
3.1.0 Preconditions
• MCC is commissioned, energized and in correct working condition
10
• Local control station and pushbutton pendant connections are checked,
commissioned and energized
• PLC and VDU is working (preferred operation is via PLC and VDU, but the
flushing process will be carried out manually due to temporary connections in
place for circulation process).
• All VFD drives and motors are set and tested, ready for operation
• Manual test run with disconnected motor (turning just motor cooling fan) shall
be carried out, (few turns) to check alignment and manual run without load.
11
• All electrical connections and wiring is checked
• Gear unit for the screens is correctly fitted, the solid plugs has been removed
from the filler point and the correct filler/breather are fitted
• Gearbox oil level is correct
• Personnel are aware that Bar Screen and Drum Screen are about to start
3.3.0 Procedure
• carry out one manual raking operation
12
• Level transmitters in Screening Area and forebay have been commissioned •
Gear unit is correctly fitted, the fixings plug has been removed from the filler
point and the correct filler/breather is fitted
• If OK , than start the screen on low speed (if double speed motor) and check
that it rotates smoothly and in the correct direction
• Check that the drum is rotating aligned and no excessive friction appears
towards the civil works.
• Check that the motor Amps do not exceed those quoted on the motor
nameplate
• Repeat these checks at high speed if screen is equipped with double speed
motor
13
• Turn on wash water pumps and check that all wash water jets nozzles operate
correctly and that jet pipe pressure is correct as per manufacturer and design
recommendation
• Change to high speed operation and run for next 15 minutes. Check that
screen runs smoothly
• Check correct automatic / PLC operation
Screen is ready for operation.
Note: Study and be familiar with the installation, operation and maintenance
instructions for Seawater Intake Pumps and Motors provided by pumps
manufacturer.
Pre-conditions
• Seawater Intake including Distribution Chamber is cleaned and flooded.
• Intake pumps cooling water supply unit (strainers) is installed and tested as per
manufacturer / vendor package recommendations and ready to use. Use of
temporary pump for pipe filling before Intake pump start up is
recommended!
• The Intake pumps motor and rotor rotation by hand has been checked
14
• All guards preventing accidental contact has been mounted in areas of coupling
and thrust bearing.
• Check if bearings have been filled with specified level of lubricant, if applicable.
• Motors for Intake pumps shall be greased prior to start up, tested and direction
of rotation checked as per motor Instruction Manual.
• All Intake motors & pumps temperature and vibration measurement shall be
checked and adjusted
15
Sea water stop gates in Screening area, Forebay and Distribution Chambers are
reoved.
• Sea water Bar Screens and Drum Screens have been commissioned
• Main header towards Roughing Filters shall be filled with sea water prior to
start up of the Intake Pumps (VFD) by use of Wash Water pumps with
temporary connections, or any other temporary pump and all shall be vented.
DN100 by pass line valves to be used for filling.
• Safety valve at the top of the Surge vessel shall be set and tested. • All Drain
• Non Return Valves if hydraulic type, are to be preliminary set; final setting will
be carried out during commissioning.
16
•
• Ferric dosing to be cold commissioned before the start up which is explained in
detail in other section – Dosing Systems. Ferric dosing system will be used
during commissioning ONLY and shall not be used with seawater intake pumps
flushing procedure.
• Check that the shut – off elements in the discharge pipe is closed.
• All valves at RF are tested (open/close signal) and ready for operation
• Slowly open recirculation valve to its operational position and check the
discharge pressure of the running pump. Pump shall be now running at
minimum flow as per pump curve.
• Check piping for proper venting. When system is vented, close the Seawater
Intake Discharge header manual vent valves.
• Water is directed into inlet piping and subsequently via RF BW outlet valves to
Culvert, following the DN800 line and finally dumped back to the sea. Water
from RF rinsing valves is passing into a culvert.
Observe the behavior of the Intake pump for unusual sounds, vibrations,
discharge pressure or leaks
17
• Flush the system and run trial run for 2 hours for each pump. Check for lubricant
level, bearing temperature, tightness, and vibrations and sliding noises of the
shaft seals.
• Stop the running Intake pump. Start the second pump (VFD), repeating the set
procedures as outlined. When system is vented, close the Seawater Intake
Discharge header manual vent valve.
• Start third and fourth Intake pumps (SS), if possible for necessary period of the
time, flow shall be limited with control valves downstream of the SS pumps.
• Observe the behavior of the pumps for unusual sounds, vibrations, discharge
pressure or leaks.
• Stop all running Seawater Intake pump when testing and flushing is completed
• After all flushing has been completed; all RF shall be opened and cleaned above
and under the nozzle floors from GRP piping parts, dust and or possible debris
forgotten in the piping during erection.
• RF filtration system consists from 12 nos. of roughing filters, each with capacity
of 1000 m3/h.
18
•
Note: Study and be familiar with the installation, operation and
maintenance instructions for BW pumps and motors. Check all
requested points as they are described in these instructions.
• Study and be familiar with the operation manuals water and air flow meters at
the RF’s inlet lines.
• Study and be familiar with the operation manuals for butterfly valves and
actuators from BRAY.
• Upon initial start up or following works or periods where any access may have
been gained to upstream pipe work, temporary rough strainers should be
installed to the backwash pump suctions to prevent possible ingress of debris.
Familiarize yourself with exact location of all emergency stop push buttons and
safety showers.
All valves at RF are tested (open/close signal) and ready for operation
19
• Drain system for backwash outlet water is ready and connected to Settling tank
/ brine outlet pipe.
• Backwash Pumps Flow Control Valves are set to minimum required backwash
flow (525 m3h)
4.2.0 Procedure
• Fill the Backwash Tank with Service Water or Filtered Seawater.
• Open Backwash Flow Control Valve. Open Backwash Pump Header Vent
isolation valve and observe until Backwash header is correctly vented. Then
close.
• Close Backwash Flow Control Valve and open RF Backwash Outlet valve for 2
nos. of RF
• Crack open Backwash Pumps discharge valve and Backwash Flow Control
Valve
• Continue with opening of Backwash Pump outlet isolation valve until flow is ~
800 m³/hr. Flush for 15 minutes.
20
•
• Close RF Backwash Inlet isolation valve
• Repeat the above procedure for the remaining RF’s using both of the
backwash pumps in turn.
• Upon completion of the flushing of all RF, drain down the Backwash Tank, the
Backwash Pumps and the associated backwash header pipes, and remove the
temporary Backwash Pump suction strainers and check for any possible debris
inside of the filters brought by flushing water.
• RF are now ready for air distribution test and filtration media filling.
Check again the internals of the backwash tank to ensure that it is free of
debris
4.4.0 Commissioning of the Air Scour Blowers and Air Distribution Test
Note: Filtered seawater may be used for this operation, however
service water is preferred. If seawater is used, filter must be flushed
21
with service water after test completion to avoid formation of salt
deposits in filter vessel.
Preconditions
• Air scour blowers are pre-commissioned as per manufacturer O&M Instruction
Manual and ready for operation.
• Ensure all the air distribution nozzles have been installed, leveled (plus – minus
2 mm) and the retaining nuts tightened using the recommended torque limits.
4.5.0 Procedure
• Close the lower manhole for the selected RF.
• Open RF Lower vent valve until water passes without interruption , then close
the valve
• Observe the level of the water within the RF through the top manhole and
close water inlet when the water covers the air distribution nozzles up to
50100 mm above the nozzles.
• As the air enters the underside of the nozzle plate the water level will gradually
rise until the air has cleared a sufficient volume to allow it to pass via the
nozzle shafts. The water within the upper section should be observed to
ensure an even distribution of air across the nozzle plate. If there are any
22
•
blank areas the test should be stopped, the filter drained, the nozzles suitably
adjusted and the test repeated.
• Open Air Scour Header Drain valve and at the same time close RF Air inlet valve
• Open Drain/Rinse isolation valve and rinse header drain valve until the filter is
empty, and then close. Use temporary drain connection if necessary.
• Flush filter vessel with service water if seawater was used for test
• Supporting layer and filtration media sand / pumice of proper size and quantity
are available.
23
4.7.0 FILLING OF SUPPORTING LAYER AND FILTRATION SAND.
• Insert supporting layer of the fine gravel through the upper manhole by means
of a crane or by using man power and fill up to 150 mm above nozzle floor.
Level and start backwashing with flow 1500 m3/h of the gravel layer, until
water from BW outlet is clear.
• Insert sand through the upper RF manhole by means of a crane, any available
device or man power.
• Level sand roughly inside chamber by using manual man power and check
beneath nozzle floor if sand drops through nozzles.
• If sand leaks through nozzles remove affected nozzles and reinsert having
checked their quality. Replace if necessary.
• Continue with sand filling up to level 150+400 mm above nozzle floor in all RF
filters.
• RF Backwash pumps and flow meter have been pre-commissioned and are
ready for operation
• Air scour blowers have been pre-commissioned and are ready for operation
• All relevant valves and instrumentation have been commissioned and are ready
for operation
24
• All relevant pipe work (from Intake to RF’s and Backwash Tank to RF’s) have
been commissioned, flushed and is ready for operation.
• Fill the Backwash Tank with Service Water or Filtered Seawater up to the
half of its volume. As the tank fills:
• Open Backwash Pump Header Manual Vent isolation valve and observe until
Backwash header is correctly vented. Then close.
• Open RF Backwash Inlet valve and allow the water to pass from the
Backwash Tank via the Backwash Pumps, and into RF. Continue to fill the
backwash tank with service water to maintain the level.
• Open RF nozzle floor vent valve until water passes without interruption ,
then close
• Observe the level of the water within the RF and close Backwash Inlet valve
when the water starts to overflow through the RF Backwash outlet valve.
Close Backwash Pump Outlet Flow Control valve
• Open Backwash Pump Outlet Flow Control valve and adjust flow to 1500
m3/hr. Check flow at FT.
Attention: The removal of sand fines should be observed both via the
upper manhole and within the RF trench in the discharge flow. Adjust
25
the backwash water flow such way that only sand fines are flushed
out and not sand.
• After ~15 minutes from commencement of the backwash close the
Backwash inlet valve
• When the water level drops to just under the upper surface of the sand,
close RF rinse valve
• Close Air Scour Drain valve and at the same time open RF Air inlet valve
• As the air enters the underside of the nozzle plate the water level will
gradually raise until the air has cleared a sufficient volume to allow it to pass
via the nozzles. The water within the upper section should be observed to
ensure an even distribution of air across the nozzle plate.
Initially the discharge from the RF will be cloudy. This will clear over the course
of the backwash as the water starts to channel within the sand. The purpose of
the Air Scour is to break up the channeling and resettle the bed in preparation
for the next backwash. Gradually the time taken for the backwash discharge to
clear will reduce. A period of 2 to 3 minutes to clear is required before
commencing pumice installation.
26
The effluent should be checked on a regular basis during the backwash. The
quality of the discharge can be checked visually for quality. Where required
turbidity meter should be used, where levels of 5 NTU and less would be
deemed acceptable. When sufficient backwashing has been completed, such
that the final discharge meets the above parameters, go to next step.
• Install / fill in Pumice of delivered size by means of a mobile crane or any other
filling device or man power. Pumice should be leveled to 1150 mm, (150 mm
gravel + 400 mm sand + 600 mm pumice) above the nozzle floor.
NOTE: as not all pumice may be watered there might be an initial loss of
material for app. 50 mm.
• Take regular samples of Pumice and mark them for reference and possible
laboratory investigation.
The RF shall be filled with water via gravity feed from the Backwash Tank by
opening of the backwash inlet valve app. 300 mm above the sand layer.
• Fill the pumice and then raise the water level until the pumice is raised to 100
mm below the BW channel again from the backwash tank
27
Caution: Do not overfill the RF with water as Pumice will float prior to proper
wetting.
• Remove the inspection pipe and close over the upper manhole
• Keep pumice 3-5 days depending from quality covered under water for soaking
• When only a view cm are left floating careful BW may be started with reduced
flow of 800 m³/h.
• Pumice has been kept minimum 3-5 days (depending from quality) under water
or the time until is completely soaked and settled down.
• Water level in the RF has been raised until overflowing into the discharge
trough the Backwash outlet valve
• Open air scour header drain valve, air scour inlet isolating valve, RF rinse/drain
valve
• Observe the lowering level of the water within the RF and record the time
taken to lower to 200 mm below the upper surface of the media. This level can
be observed by digging a small crater into the media. Close RF rinse valve and
air scour header drain valve to maintain this level.
• Wait until water has lowered through the goose neck drain and water flow has
stopped
28
• Close air scour goose neck drain valve and air scour inlet valve
• Open RF air scour inlet valve and close air scour drain valve
Note: During this period may the blower relief valve shortly lift and pass
• Air scour for ten minutes
• Close air scour inlet valve, open air scour drain valve , open air scour goose
neck drain valve and close air scour valve
• Adjust Backwash Pump Flow Control valve to achieve flow of ~500 m3/hr.
Check flow. Keep backwashing until water started to be clear. Over the period
of time increase backwash flow gradually (600-700 m3/h) by adjusting Flow
Control valve and also higher as long as no pumice is carried over to the BW
channel.
• Close and open RF backwash inlet isolating valve 10 times during backwash
time of 15 min. After a couple of open/close cycles,
29
• During the backwash, the effluent water should be monitored and PUMICE IS
NOT CARRIED OUT BY BACKWASH FLOW!!! The level of the expanded pumice
should be observed through the upper manhole. Where the top of the
expanded media bed is high or low, adjust the Backwash Pump Flow Control
valve to increase or reduce the flow.
Initially the discharge from the RF will be cloudy. This will clear over
the course of the backwash as the water starts to channel within the
sand. The purpose of the Air Scour is to break up the channeling and
resettle the bed in preparation for the next backwash. Gradually the
time taken for the backwash discharge to clear will reduce. A period
of 1 to 2 minutes to clear is acceptable.
• Continue with air scour and backwash cycles until acceptable results are
obtained
30
• Ensure that upper manhole is secured before commencing final backwash
4.14.0 PRODUCTION OF THE FILTERED SEA WATER FOR BACKWASH OF OTHER RF's
Precondition
• All pre-treatment systems and equipment have been commissioned
• Two – three RF filled with sand and pumice is backwashed and in standby
condition
• Coagulant dosing set is calibrated and ready for use (if required by seawater
quality). JAR tests executed and preliminary specific dose evaluated
• All impulse line primary and local isolating valves for pressure transmitters and
gauges are opened
31
• RF Dump valve is open and set to approximately 60% of opening to keep
required back pressure in the system, to be re-set if required.
Warning: Remember basic rule for start of centrifugal pump - start the pump
against closed or very slightly opened discharge valve if the pipes are empty!!! It
is recommended to fill the pipes with water prior start up of the pumps.
• Once the pump is running - slowly open the Intake Pump discharge valve
• Check if water is passing from Intake Pumps discharge header manual vent
valve. If yes, check the color of the water from the pipe - it should be colorless
and transparent. A milky or white color indicates air in the system.
• Check system pressure via pressure gauge. Adjust the system pressure to ~ 4.0
bar by opening the intake pump discharge valve
• Open RF inlet valves “first" RF’s which has been filled with dual media and
backwashed.
• Ensure that water is passing from the RF’s top vent valve. If not, wait until
water appear on the valve outlet and leave it flow for ~ 3 minutes. Check the
color of the water for air presence.
• Open RF rinse/drain valve and rinse RF for 30 minutes. During this time the
vent valve should be closed
• Once you are sure that the pipes are filled with water, complete the opening of
RF’s treated water outlet valve
• Than open and then close RF Outlet valves on the remaining RFs filled with
media to vent the pipes
32
• Close vent valve
• Intake equipment and RF’s have been commissioned and at least 2-3 RF are in
operation running to drain through rinse line
The first RF is now producing filtered water. To improve the quality of filtered
water, start sulphuric acid and coagulant dosing (if required by seawater quality)
and chlorination (intake and/or pre-treatment) for disinfection of the system.
33
Functionality of the UF system software is tested by means of a Factory
Acceptance Test (FAT) and complies with the functional requirements.
UF system is mechanically and electrically complete;
All associated pipe work and equipment is installed, connected, pressure tested
and flushed. All electrical devices are installed and cabled and power is on the
MCC.
Automation system, I/O’s are tested. This includes amongst others:
• All I/O connections are checked (including any associated external signals).
• All initial software parameter set-points, alarms, PID loop settings, timers,
etc… are set.
Drinking water (or water with similar quality) is required for membrane
element flushing and optional during commissioning without membranes.
• UF membrane elements are available;
• UF membrane elements are available on site or delivery has been planned.
Membrane elements will be required during membrane element loading.
• CEB / Neutralization chemicals are available;
• Chemicals for CEB and neutralization (if applicable) are available on site or
delivery has been planned. Chemicals will be required during commissioning
with membranes.
34
• UF system filling, venting and flushing;
Water is introduced into the UF system and the complete UF system is filled,
vented and flushed. In principle UF feed water can be used for this purpose.
Since low-grade UF feed water is (normally) available already, this is generally
the most convenient water source. However, disadvantage of UF feed water is
that the complete permeate section of the UF system (UF units, backwash
tank, backwash pumps/strainers, permeate/backwash pipe work) need to be
drained and flushed with drinking water quality after commissioning without
membranes. This is required for thoroughly cleaning this section prior to
membrane loading. For this reason it may be considered to use drinking water
(or water with similar quality). In order to limit drinking water consumption,
circulation loops may be established during commissioning without
membranes. For filling, venting and flushing the chemical dosing units,
drinking water (or water with similar quality) should be available.
35
The following main process units can be distinguished:
UF feed unit : feed strainer(s)
UF unit(s) : skid(s) with membrane housings filled with membrane
elements, feed flow control valves, airflow integrity test
equipment 1)
Backflush unit: backflush tank, variable speed backflush pump(s),
backflush strainer(s), CEB chemical dosing units
1) If applicable
36
Stage 2: Membrane element loading;
37
Return of concentrate back to the backwash tank, making use of
temporary connections between the normal backflush concentrate and
CEB concentrate line and the backflush tank.
5.1.4.4 Overall plant operation:
Produced permeate is collected in the backflush tank and backflush waste is
returned to the UF feed tank. Change settings to allow continuous UF system
operation.
During some of the backflushes, concentrate leaving the UF unit will be
discharged to the culvert. During CEB, chemically loaded concentrate leaving
the UF unit is discharged to the Neutralization tank (if applicable) and finally
discharged to the culvert. Backwash and CEB duration and flow can be reduced
to limit concentrate production and the loss of water.
5.1.4.5 Software functionality testing
• All initial software parameter set-points, alarms, PID loop settings, timers, etc,
are set and software functionality and controls are tested by running and
checking the automatic programs. This is done to check and debug the
software and set-up and tune the initial settings that have to prevent flow and
pressure peaks. This includes the following main activities:
• All PID control loops are set/tested (e.g. Pump ramping-up and down and FCV
controls)
38
5.1.4.6 Cleaning UF system
The water used during software functionality testing can be chlorinated (2-5
ppm chlorine) to prevent growth and perform a limited disinfection.
After software functionality testing the UF system has to be cleaned. Backflush
tanks are typically cleaned with a power washer and used to store clean water
that will be used to flush and clean the remainder of the UF system. UF system
disinfection is not mandatory at this stage, but is advised.
5.1.4.7 Strainers
At the end of software functionality testing all feed and backflush strainers
have to be inspected and cleaned. Damaged strainers have to be repaired or
replaced. Debris from damaged strainers can cause damage to the
membranes.
5.1.4.8 Filling chemical dosing units
After successful software testing, the chemical dosing units are filled with
chemicals. Once the membranes have been loaded, these chemicals are
required for CEB and neutralization (if applicable).
5.1.5 Stage 2 - Membrane element loading
39
• Membrane element flushing is required for flushing out the preservation
chemicals (sodium bisulphite / glycerine = BOD) and expelling air from the UF
unit. For detailed description of membrane element flushing, reference is
made to the related documents (section
1.2)
Main points of attention during membrane element flushing
are listed below:
• UF unit filling:
After membrane element loading, an automatic or manual filling program shall
be executed for smoothly filling the UF unit with water and expelling the air
from the membranes. UF unit filling is performed at minimum feed flows, i.e.
• During this period, final disinfection of the UF system is performed after which
the UF system is taken into automatic operation and fine-tuned.
40
• The permeate side of the UF system (UF units, backwash tank,
backwash pumps/strainers, permeate/backwash pipe work) is
disinfected after membrane flushing:
• The UF system is taken into automatic operation. This means that operation of
the UF system is controlled by the automation system. During this period the
most relevant process data are collected and reviewed and the UF settings are
fine-tuned to optimize system performance.
5.1.7.3 Training
• At the end of the process commissioning period, the UF system is taken over
by the customer. Specific details will be discussed and agreed between the
customer and Pentair. A process commissioning report will be generated
covering the process commissioning period.
41
• No pressure and/or flow peaks, that can damage the membranes, are
expected. All program functionality’s, e.g. CEB’s, are working.
• The bases for these tests are derived from the control and design
documents, Process description and Process Control Philosophy or
Automation System Description.
• Finishing the pre-commissioning is a milestone and hold point after which the
actual commissioning starts. A pre-commissioning document has to be made.
For this the Process commissioning checklist can be used.
• No more works such as grinding, cutting and welding on parts of the plant
that involve or affect the UF plant.
42
• I/O tests are finished.
• Initial software tests are done, the plant can run on software. Trending and
alarm logs are available
• PLC communication network is healthy.
• PC communication is healthy.
• All supporting systems such as, backwash unit, chemical dosing and
neutralization are commissioned. (tested, calibrated and operative)
• The software FAT has been completed satisfactory and all comments on the
FAT are worked out / implemented.
5.2.2. Water supply and routing
• Choose creative settings that will reduce water use and / or optimize the re-
use of water.
5.2.2.1 Chlorination
• If the water is circulated it is advised, if possible, to add 2 to 5 ppm of chlorine to
the water. This prevents microbiological growth and work as a “disinfecting
step”.
43
because will allow microbiological growth in the piping and membrane
housings!!!
5.2.2.3 Strainers
• The strainers will catch off a lot of matter, such as sand and cutting and
grinding debris, which has to be removed from the system.
• When the wet testing without membranes period has finished the
strainers have to be checked for any damages that could have occurred
during the tests.
Smooth operation without water hammer and pressure and flow peaks
44
5.2.4 Start up auto run
For large plants it would not be possible to just push the start button and start
running in auto. Too much would happen at the same time and errors might not
be traceable and / or cause start-up problems.
• Activate backflushes.
• Start and set-up venting/filling program. Start and set-up Air-flow test
program.
• The plant is running in auto and all programs are available and testing can
begin.
Before starting to run in auto the system (test) settings have to be
determined and set.
45
Process Description, Process Control Philosophy or Automation System
Description.
All start settings have to be listed in a setting list. The setting list will leave
space for filling in settings changes during commissioning.
• The BF tank is equipped with level transmitters and switches. The level
transmitters and switches are used to protect the BF pumps and prevent air
ingress into the UF units.
• The level switch has a fixed height and will cause immediate pump and
possible plant shutdown. A level switch cannot be used for controlling. It is a
safety feature.
• A level transmitter can be used for controlling and avoid plant shutdown on
the level switch.
46
• The tank levels have to be set-up. The level settings have to be set such that
a vortex is avoided and the system can react fast enough to avoid plant
shutdown.
5.2.5.3 Feed flow control
• Feed flow control takes place with intake pumps and it is on plant level.
• Duty / Stand-by pumps connected to a common header and unit control
valves.
• Independent from the feed flow is the available number of membrane
units. Taking units off-line and on-line is a good test for changing the
maximum plant capacity. These tests have to be done.
• Flow control valves are more difficult to set-up. The control valve throttles
a flow, valve positions change. If one control valve changes position on a
common header with several control valves, it will cause the other valves
to react / control as well.
• The flow has to be limited to the max. flux and should be distributed within
a dead band over all the units. This can be affected by the hydraulic profile
of the UF plant. At large plant this can mean that maximum valve open
position differ 20%, e.g. from 60 % open to 80 % open.
47
5.2.5.5 Duty / stand-by
• The duty / stand-by changeover of pumps, if applicable, has to be tested. If
the feed system is set-up with assist pumps the change over is more
difficult and feed flows can change very rapidly if stand-by pumps are
started or stopped when taking over from an assist or duty pump. The
changeover has to be smooth, starting and stopping the pump has to be
tested thoroughly. The control must be set up avoiding erratic control
causing pressure and flow peaks.
• The backflush tank is equipped with level transmitters and switches. Air ingress
into the backflush lines and UF units must be avoided.
• The level switch has a fixed height and will cause immediate pump and unit
shutdown. A level switch cannot be used for controlling. It is a safety feature.
• Level transmitter has adjustable settings and can be used for more adequate
control.
• The tank levels have to be set-up. The level settings have to be set such that a
vortex is avoided.
48
5.2.6.2 Backflush flow control
• Backflush flow control takes place with VFD driven backflush pumps. A
backflush pump will only wash one unit at a time. The set-point can differ,
regular backflush, CEB in or venting backflush.
• The backflush flow control has to be set up to avoid pressure and flow peaks
and erratic control of flow. The ramp-up and -down times have to be in the
range of 5 to 10 seconds.
• The intermediate step where two units change over from one unit to the next.
The unit coming out a backflush closes its route and the recirculation valve
opens. Only then the next unit can do a backflush and the route through the
unit is open (open signals from the valves).
The chemical dosing systems are calibrated and ready to run. The dosing
systems are used for: Chlorinating pre or post membranes, pre-dosing can
have ammonia oxidizing function:
• Coagulant dosing
• Dosing CEB chemicals
• Dosing CIP chemicals
These systems can cause (indirect) membrane damage, due to:
• Upsetting flow meters, if dosing is too pulsating
• Unsatisfactory chemical strength causing high Trans Membrane
Pressure and unstable running.
• Tank levels have to be set and checked.
49
• The dosing systems have to be calibrated, by measuring the chemical
concentration in the stream in which it has been dosed.
• The air supply consists out of a filter set and an air-pressure regulator. The
air-pressure has to be set at 1 bar (g). The maximum pressure offset of the
air-pressure is plus or minus 0.2 bars. The air pressure has a direct relation
with the air-flow rate. Therefore the air-pressure has to be monitored.
Besides monitoring the pressure for checking the results the air pressure
is monitored for membrane protection.
• The larger plants are equipped with stand-by air-flow measure panels.
The changeover to these panels has to be tested.
50
5.2.9. Sequence and functionality test
Testing the different sequences has to be done with the Process Control
Philosophy or Automation System Description. In the document each sequence
and functionality is described.The sequences have to be tested, but at the
same time settings for these sequences are optimized.
• The sequences and functionality’s are the basis for the plant, but it all has
to work as one. To see if it works as described, one has to pay attention to:
• Reliability
5.2.9.1 Filtration
5.2.9.2 Backflush
51
Conditions, controls and alarm parameters. (Refer to this section)
All of these have to be tested and settings optimized.
5.2.9.4 membrane integrity test
• In the Process Control Philosophy or Automation System Description all software
functionalities are described, such as: valve sequences, start, stop and step
conditions, controls and alarm parameters. (Refer to this section)
• The goal of the emergency stop is to stop the plant as quick and safe as
possible. This means that even with an emergency stop not all valves should
be shut directly. Shutting valves could also cause dangerous situations, such as
water hammering.
• Therefore the emergency stop sequence has to be set-up such that no other
dangerous situations are created.
52
5.2.9.7 Power failure
• A power failure is an undesired stop and can happen at any time. The system
design and software have to be able to coop with these power failures without
causing pressure and flow peaks.
• The plant has to be brought back on-line after a power failure. This is the
second part of testing power failures. There are two different scenarios for
this:
• A power failure with UPS and the PLC has been on-line for the duration of the
power-failure.
• A power without a UPS or the UPS power supply died and the PLC did not stay
on-line during the power failure.
• Both situations have to be tested.
• An emergency stop has as goal to stop the plant as quick and safe as possible.
This means that even with an emergency stop not all valves should be shut
directly. Shutting valves could also cause dangerous situations, such as water
hammer.
• Therefore the emergency stop sequence has to be set-up such that no other
dangerous situations are created.
• An emergency stop has to be tested.
• If the instrument air-supply fails the plant has to be shut-down in the same
way as an emergency stop. A pressure switch monitors the instrument air
pressure.
5.2.9.9 Data collection changes - Trending and logging
• Trending and logging, of process data and alarm messages, is needed for
monitoring the plant during testing, membrane flushing and running with
membranes.
53
• The trending and logging system helps fault finding during the wet
commissioning without membranes. Wet testing without membranes can only
be started if trending and logging is available.
• Start settings have to be listed in a setting list. The setting list will leave space
for filling in settings changes during commissioning.
• Complete software modifications through which functionality changes have to
be approved by the Process Engineer of Pentair. These changes have to be
properly documented, so that they can be used to up-date the as build
Automation System Design or Process Control Philosophy.
• UF plant permeate piping, backwash piping and backwash tank are clean, no
debris, sand or organic sediment, etc.
54
• Membrane elements and loading materials and facilities are available at site.
• Water for membrane element flushing will be available. For water quality, see
‘Procedure Membrane Element Flushing’ in related documents.
2 Facilities
1 UF unit Draining
55
2 Membrane housing cleaning 5 Using water hose and foam
cleaning pig.
56
Newly delivered connectors are not fitted with O-rings. The O-rings have to be
fitted before membrane element loading. All connectors have to be checked
for cracks when the O-rings are fitted. Cracked connectors cannot be used.
Before usage the connectors must be cleaned and kept in a bucket with 10 to
20 ppm free chlorine solution for disinfecting.
NOTE: Read sodium hypochlorite material safety data sheet 5.3.4.2 Materials and
facilities
Materials and facilities needed for membrane element loading can be found in
the tables below.
3 Membrane housing cleaning Foam cleaning pig, pig support, rope ,bucket and
water hose
57
5 Membrane housing assembling Spanners, Allen-keys, shims and glycerin
• Membrane elements are packed in cardboard boxes (one element per box) or
wooden crates (Maximum 20 elements per crate). A Pallet-truck or fork-lift
truck is needed to move the wooden crates.
• For cleaning of the membrane housings a foam pig is required. A rope with
foam pig support is needed to pull the pig through the membrane housing.
The foam pig support will be pushed through the foam pig after which a rope
will be connected to the front of the foam pig. The foam pig needs to be
wetted before pushing it in the membrane housing. The foam pig has to be
cleaned after it has been pulled through the membrane housing. A large
bucket can be used for wetting and cleaning of the foam pig. A water-hose is
needed to re-fill the bucket and flush-out the membrane housings.
Figure 2-2: Foam pig and foam pig support
58
59
• Each membrane element has its own serial number, see figure below. The
serial number is used for recording the position of each membrane element in
the UF unit. During membrane element loading glycerin is used to lubricate
connector O-rings. This will prevent damage or displacement of O-rings.
• The UF unit has to be drained before dismantling. The UF unit can be drained
manually or automatically, if drain program is part of the plant software.
• If the UF unit is drained all manual drain valves have to be closed, the UF
unit has to be made inactive/off-line in SCADA and instrument air supply to
the UF unit has to be disconnected.
60
• After UF unit draining and isolation the membrane housing end-caps can be
removed. A 90° elbow is connecting the membrane housing end-cap with
the permeate header. The membrane housing end-cap and the 90°elbow
have to be removed as one piece. Both membrane housing endcaps (from
both sides) have to be removed.
• Pull a wet foam pig through each membrane housing. A foam pig can
be used for approximately 40 membrane housings.
• Flush membrane housings with clean water after swab or foam pig
cleaning.
61
sheet’.
62
• Record membrane element serial number.
• Remove membrane element packing.
• Keep the previously loaded membrane in
place and slide the second membrane
element over the lubricated inter-
connector, make sure that the connector
nipples touch the membrane element.
• Note: Keep the membrane elements aligned, to prevent the connector from
breaking.
make sure that the connector nipples touch the membrane element.
Note: Keep the membrane elements aligned, to prevent the connector from
breaking.
63
• Insert up to 4/5 of the membrane element into membrane housing.
• Take an inter-connector and lubricate O- rings on both sides with Glycerin.
• Keep the newly loaded membrane element in place and insert the lubricated
inter-connector into membrane element; make sure that the connector nipples
touch the membrane element.
Note: Keep the membrane elements aligned, to prevent the connector from
breaking.
Step 5: Install the first set of membrane housing end-caps, both sides of
membrane housing.
64
• Position one, two, three or four membrane
elements in the centre of the membrane
housing. Make sure that the distance from
the edge of the membrane housing to the
first membrane element is more or less equal
for both sides of the membrane housing.
Note: Keep the membrane housing end- cap aligned, to prevent the end-
connector from breaking.
65
• Push long leg of end-connector, with shims, into membrane housing end- cap.
• Make sure that the connector nipples touch the membrane housing end-cap.
Note: Keep the membrane housing end- cap aligned, to prevent the end-
connector from breaking.
Software testing, operation of the plant with water has been completed.
Membranes are loaded.
No mechanical, electrical and / or software changes are scheduled and needed.
Especially mechanical changes can be hazardous for membrane damage due to
foreign matter. Software changes can impact on plant operation and undo
completed software test results. Tank cleaning and inspection is completed
and if necessary action has been taken.
Flush water is available.
Temporary connections are available and installed.
66
The duration of flushing 1 unit continuous and uninterrupted is approximately
1 hour.
Flushing team
Supervisor Norit 1
Software engineer 1
Commissioning engineer 1-3
Flushing requires good teamwork between the members of the team. The
software engineer operates the system, the supervisor controls the flushing
and the others will perform the manual actions.
The average BOD level increase of the total flush water volume will be
between 20 and 30 mg/l. See Table 2:
If the average BOD level increase is too high to discharge, it is advised to insert
a minimum soak period of 2 hours after step 1 and arrange separate discharge
for step 2 and 3. During step 3 an average BOD level of 300 mg/l can be
67
reached. The average BOD level will be between 3 and 7 mg/l of the totaled
flush water volume after step 3 taking into account the initial flush water does
not contain BOD.
NOTE : Effluent from a membrane flush step can not be used for
other membrane flushing steps.
Preventing flush water to be re-used and supplying the plant with fresh flush
water generally requires temporary connections and piping and / or hoses.
68
Table 2: Characteristics of membrane flushing
Notes:
1. according to the Process Control Philosophy, unit fill has to e performed at 20
50m³/h. Independent of unit size.
2. The table is based on flushing 10 UFC M5 membranes with 40 m² each.
3. There are no safety margins in this table, adding 10% extra volume is
recommended.
Following table 2, the following overall water volumes are required membrane
flushing:
69
Mandatory step (1-5) 0.67m3 / element
70
duration the vent valves should be opened halfway of the backflush and just
for 10 seconds.
Vent valves have to stay closed during steps with chemicals (11a – 11d).
NOTE : Be aware of chlorine washout of stage 11d and make sure that it
is routed to the right tank or sewer, were it can be either neutralized or
disposed.
With stage 11b a 200 ppm chlorine mixture has to be washed into the unit. The
backwash is performed at 125 lmh, and chlorine has to be dosed into the
backwash stream. It is no problem if the concentration is higher, as long as
chlorine concentrations are below 500 ppm.
The dosing time and backwash time is 60 seconds. If the dosing system is not
close to the unit(s) the backwash time has to be extended. By extending the
backwash time the chemicals will be transported into the unit.
During the backwash with chemicals the vent valves should not be opened.
When the chemicals are washed into the unit, step 11c, soak, is started.
During the soak a sample has to be taken from the unit. The sample is taken
to determine the concentration of chlorine in the unit.
The chemicals are washed out with stage 11d. Concentrate from this backwash
has a high chlorine concentration.
5.4.8 Calculations
71
=>> 3 (skids) x 11 (membrane housings) x 4 (elements per housing) = 132
membrane elements
=>> (132 / 10) x 14.6 m³ (total filtration volume from table 1) = 193 m³
For calculating the flush flow the membrane area of the unit needs to be
calculated first.
In general, the flow (m3/h) for the various stages is calculated as:
=>> (flux x available area) /1000
72
5.4.10 Flushing instructions and restrictions - Venting
It is very important that the unit is regularly vented during the different flush
stages. Especially for units with the flush outlet on the bottom. If the vent
valves are not used air will accumulate and compress in the top of the unit.
Air in the top of the unit reduces the effective membrane area. With a
reduced membrane area and compressed air in the unit can lead to possible
membrane damage.
NOTE : Vent valves on feed or permeate side can only be opened if the
minimum pressure on that side, in the top of the unit, is 0.05 bar.
If pressure in the top of the units isn’t high enough there is a possibility
that air is introduced into the unit.
During flushing the units are filled with a water / air mixture. It is therefore
very difficult to control a pump or control valve on a flow set point. It is
advised to use a fixed pump speed or
Hand / control valve conditions.
NOTE : All flow rates, for filtration and backwashing, have to be manually
controlled.
e.g. fixed pump speeds and fixed, control, valve positions.
Pressure shocks and flow peaks have to be avoided at al times. Pressure shocks
and flow peaks can occur when:
• A unit flush is started
• A unit flush is stopped
• Pump rump-up
• A fast flow set-point change
73
NOTE : Avoid pressure shock and flow peaks with proper operation
during the flush steps.
Pressure shocks and flow peaks can damage the membranes.
NOTE : Operations to avoid pressure shocks and flow peaks can increase
the chance of, partially, unit draining. This has to be avoided, since
reintroducing air from flush step to flush step will make the flush less
effective and the chance of membrane damage increases with the
increasing flows.
NOTE : The maximum flow for a flush stage shall not be exceeded. A
lower flow for a flush stage is allowed. This will result in longer
stage duration to meet the required flush volume.
NOTE : Air ingress, e.g. due to cavitations, can cause membrane damage.
Units can not be pressurized, flow control has to take place up- stream of
the unit.
74
5.4.14 Trans membrane pressure
NOTE : During flushing the maximum filtration TMP of 1.0 bar and the
maximum backwash TMP of 2.0 bar shall not be exceeded.
It is unusual that the maximum TMP values are exceeded during flushing, since
relatively clean water is used. Normally high TMP are expected when the fouling
load of the water is very high or when air ingress takes place. Exceeding the high
TMP is therefore a very good indication that flushing is not done properly.
5.4.15 Permeability
Each flush stage has to be recorded. Normally a SCADA system will log the
data, but a written record is required as well.
On this log sheet the following has to be recorded:
75
5.4.17 Flushed units
When a unit is flushed the unit can be taken into operation. If the unit is not
taken directly in to operation the unit has to be flushed, with flush water,
every 24 hours. This can be repeated as long as needed.
If the unit has to stay off-line for a long period, due to circumstances, it might
not be desired to keep flushing the units. For these cases a Shutdown and
Storage procedure is available.
NOTE : Flushed membrane units can not be kept isolated for more than
24 hours.
Optionally the permeate side of the UF system (UF units, backwash tank,
backwash pumps/strainers, permeate/backwash pipe work) is disinfected
after membrane flushing:
Disinfection is executed according to the customer requirements.
Requirements and routing of disinfection waste water is determined by the
customer. Last disinfection step can be execution of a normal chlorine CEB
program.
Unit fill 20 - 50
Filtration
Backwash
76
Filtration
Backwash
Filtration
Backwash
Filtration
Backwash
Filtration
Backwash
Backwash + Cl-
dosing (100 ppm)
Filtration*
Backwash
Comments:
77
The goal of this period is to get the plant to operate according design
specifications. This means that plant operation has to be monitored and plant
data will be used to review and change settings, if needed.
Main plant performance parameters that need to be monitored are:
• Filtration permeability
• Chemical Enhanced Backwashes
• Coagulation process
• Membrane integrity
With above measurements (and the applicable membrane area) the flux, TMP,
permeability etc can be calculated in the SCADA system. Calculations are
described in the Process Control Philosophy or Automation Document.
Membrane unit performance can vary, due to either membrane fouling or feed
water temperature. Both will result in increase or decrease of Trans
Membrane Pressure, head-loss over the membrane. The throughput, unit flow,
also affects the Trans Membrane Pressure.
78
The permeability is normally automatically calculated and logged. The logged
permeability data is used for plant performance evaluation. The representative
permeability data is measured 3 minutes after the start of the first filtration
cycle after a primary CEB, the most frequent CEB.
The chemical cloud has to be washed into the unit. The chemical cloud is
transported into the unit by setting the post dosing time. If the post dosing
time is too short the chemical cloud will not reach or completely reach the
unit. If the post dosing time is too long the chemical cloud can pass the unit.
The dosing time also has to be properly set; otherwise the chemical cloud can
be too small or large.
79
During the soak period of a CEB the pH or the chemical concentration has to be
checked. Measuring the chemical concentrations in both the concentrate and
permeate can be used to check the position of the chemical cloud.
80
• Coagulated feed water pH.
• Coagulant passing the membrane, permeate samples have to be taken from a
unit and not from a tank collecting permeate
• The flow output of the chemical dosing pumps has to be checked weekly.
• Feed water:
• Turbidity
• TOC
• Color
PERMEATE
• Bacteriology
• Color
• Al or Fe concentration
Water quality data results can be used as a reference for plant performance
evaluation, for future optimization, reacting on water quality changes and
trouble-shooting.
81
5.5.8 Sample Frequency
Parameters that are not measured in-line have to be sampled on daily basis
during the first week after start-up. After the first week without excursions in
the sample results, the sample frequency can be reduced to once per week.
5.5.11 Settings
Optimizing the system can only be done by changing settings. Setting changes
have to be recorded. Setting records can be used to evaluate the effects of
setting changes.
When settings are changed the old and new settings have to be recorded with
the time, date and person who changed the setting.
Settings changes have to be recorded in a dedicated log book that is available
for everybody who is allowed to change settings.
When, after take over by client, uncontrolled changes to operating conditions,
software functionality or software settings might negatively impact UF plant
performance and consequently performance and membrane lifetime. If the
customer proposes to make changes to operating conditions, software
functionality or software settings which might impact performance of the
82
UF/NF membrane units, Pentair shall be informed about the intended change.
This shall be done preferably prior to, but not more than 24 hours after the
change by fax.
Pentair will advise the Customer that the change is or is not accepted.
• Local control station and push button pendant connections are checked,
commissioned and energized.
• The vent valves at the self cleaning strainers, UF inlet & outlet headers to
be in open position.
83
• The UF feed flow meter FIT shall be pre-commissioned.
5.5.13 Procedure
• One pump at Intake station and few Roughing filters are in operation
• Filtrated water is passing via dump valve into a culvert
• Open inlet valves at the UF strainers following manufacturer O&M
Instruction manual. Take care for proper de-aeration.
• When the priming is completed, close all manual vent valves.
• Monitor the diff pressure of self cleaning strainers. If the DP crosses its
allowed limit, manually start strainer back flush sequence from local control
panel.
• Water is now passing via UF inlet and outlet headers by pass spools and via
DN 450 dump line to culvers.
84
•
• UF Cleaning Pumps are pre-commissioned and ready for operation (dry run
protection is activated).
• Flushing spools for UF CIP inlet and UF CIP outlet are installed.
85
•
• Dry run protection for CIP mixer and CIP pumps is set and tested
5.6.2 Procedure
86
•
• Check UF Cleaning Cartridge Filter vent valve
• Close inlet / outlet piping of UF rack to be flushed and set the following
valves:
Note: The UF rack to be flushed should be the one, which is most far
from the UF Cleaning System. The purpose of such selection is to flush
full length of the feed and return cleaning pipes.
• Close UF Chemical Cleaning Pump discharge isolation valve. This valve can
be left crack opened.
• Slowly open Cleaning Pump recirculation valve and adjust pump discharge
pressure to xx bars as stated at the pump name plate
87
•
• Slowly start to open UF Cleaning Cartridge Filter outlet isolation valve and at
the same time start to close Cleaning Pump recirculation valve.
• After 2 minutes slowly open UF Cleaning Tank concentrate CIP return valve.
• Increase the flow to 300 m3/h, either using UF Cleaning Cartridge Filter
outlet isolation valve or UF Cleaning Tank outlet return valve.
88
• Re-circulate water for 60 minutes and then:
Warning: Do not close UF Cleaning Tank outlet return valve fully!!! Flow
through UF filtrate CIP return line shall not exceed 30m3 / hr.
• At the end of recirculation period stop the CIP pumps and close the UF rack
Cleaning Product return valve.
• Open UF Cleaning Tank outlet dump valve and at the same time close UF
Cleaning Tank outlet return valve.
• This will allow the content of the UF Chemical Cleaning Tank to be drained
down. The level of the tank should be observed and the following actions
undertaken prior to the pump tripping on low level:
Note: Take sample of water from Cleaning Tank via drain valve before
the Cleaning Pump is stopped. If the sample is particularly dirty,
consideration should be given to draining the system completely and
repeating flushing.
5.7.1 Preconditions
• Drain system (culvert) is commissioned and ready to take waste water
89
• UF Back wash tanks and Pump Chambers are clean from any construction
debris and filled with service water or filtered seawater.
5.7.2 Procedure
Warning: start the pump against closed or very slightly opened
discharge valve if the pipes are empty!!!
90
• Start back flush Pump.
• Slowly open the pump discharge isolation valve and adjust to the
predetermined flow. Check the flow on flow meter.
• Check the water flow from back wash line manual vent valve. It should be
clear without of air bubbles. Cloudy water indicates air presence in the water.
Close the valve if water is clear and system free of air.
• Flushing water is passing now via BW piping and temporary spool to the
culvert
• Stop the pump before water level in the Back flush Tank drops to minimum
• Refill the Back flush Tank and repeat the procedure with second Back flush
Pump
• Drain down the back flush Tank, the back flush Pumps and the associated back
flush header pipes, and remove the temporary back flush Pump suction
strainers.
For safety of the work study and follow attached ASC safety data sheet.
91
6.1.1 Precondition for flushing of the Filling pumps.
• Discharge piping from Filling pumps to the Ferric Dosing Tanks is opened
6.1.2 Procedure:
• Read and consider O&M Instruction Manual from Filling pumps manufacturer.
• The pumps are pre-commissioned, oil level checked, power supply and control
cables connected and tested.
NOTE: There is no DRY RUN PROTECTION FOR THE FeCl3 FILLING PUMPS
AVAILABLE. Dry run protection depend from operator, to switch off the filling
pumps in right time, immediately when Tanker is empty or latest when suction
of the pump will be aerated.
• Start Filling pump and open discharge valve at discharge piping to the NaOH
Dosing Tanks. Run the pump as per operational curve, obtained in the O&M
Instruction Manual.
• Observe the behavior of the Filling pump for unusual sounds, vibrations,
discharge pressure or leaks. When everything is OK, stop filling pump and
repeat the test with second filling pump.
Filling pumps are Commissioned and ready to receive NaOH solution
92
• Potable water is available in ferric storage tank.
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
6.1.4 Procedure
• Disconnect the suction piping from both dosing pump and flush the line.
Connect piping back and open Dosing Pump inlet isolation valves.
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. Afterwards
increase capacity and speed to 50%, 75% and to the 98-100% setting. This may
require the discharge pipe to be vented by unscrewing a connection of the
discharge pipe.
• Run the pump in maximum stroke and speed for 2 hours observe for unusual
sound and behavior.
93
• Ensure that pressure relieve valve back to the tank and pressure sustaining
valve at dosing line are properly set to required pressures to avoid damage/
overloading of the pumps.
• When completed, stop the pump and start the next unit. Ensure on completion
that all connections are secure.
• Ensure that the flushing water from the dosing pump, piping & from the
storage tank is drained completely.
• Ensure that dry run protection for the pumps has been tested during test and
minimum level is set.
Warning: Stroke length of the pump can be adjusted only when the
pump is in operation !!!!!
• Process liquid is continuously available for the feed headers & carrier water
piping for the commissioning.
• The dosing pumps are flushed and calibrated as per manufactures O&M
instruction manual.
• The piping to the dosing location is flushed (upstream of Roughing filters and &
upstream of UF dosing point).
• All instruments and signals from Roughing Ph2 and RF turbidity are installed,
checked & pre-commissioned.
• Whenever low level alarm (LL) in solution tank is indicated, the tank must be
re-filled with fresh solution immediately.
94
6.1.6 Procedure
• Start one dosing pump, adjust its stroke and speed (refer to supplier
instructions) Taking to consideration also operational conditions of the plant
(dosing rate and media flow) and allow pump to prime. Keep in operation in
automatic mode of operation for required time.
• Once first pump is commissioned, stop the pump and start the next unit.
Ensure on completion that all connections are secure.
Warning: Stroke length of the pump can be adjusted only when the
pump is in operation !!!!!
6.1.7 Coagulant Dosing and Preparation.
95
Concentration in tank: 40 % = 567, 2 g/l as FeCl3
the factor for recalculation Fe / FeCl3 is 2, 9
The dosing rate has to be checked regularly and adjusted when the water
condition is changing.
• Discharge piping from Filling pumps to the ASC Dosing Tanks is opened
6.2.2 Procedure:
• The pumps are pre-commissioned, oil level checked, power supply and control
cables connected and tested.
96
NOTE: There is no DRY RUN PROTECTION FOR THE ASC FILLING PUMPS
AVAILABLE. Dry run protection depend from operator, to switch off the filling
pumps in right time, immediately when Tanker is empty or latest when suction
of the pump will be aerated.
• Start Filling pump and open discharge valve at discharge piping to the ASC
Dosing Tanks. Run the pump as per operational curve, obtained in the O&M
Instruction Manual.
• Observe the behavior of the Filling pump for unusual sounds, vibrations,
discharge pressure or leaks. When everything is OK, stop filling pump and
repeat the test with second filling pump.
• The anti scalant tank (ASC) is thoroughly cleaned and filled with service water.
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
• ASC tanks mixers are wired, oil level is checked and are pre-commissioned
• Dry run protection level indicators at the ASC tanks are installed and tested
• Pressure indicators (PI) and flow switches (FS) are installed, wired and tested.
97
6.2.4 Procedure
• Start ASC tank mixer in both tanks, observe for unusual noise and vibration
• Disconnect the suction piping from both dosing pump, flush the lines, and
check the strainers.
• Connect piping back and open ASC storage tank outlet valve
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. Afterwards
increase capacity and speed to 50%, 75% and to the maximum setting. This
may require the discharge pipe to be vented by unscrewing a connection of the
discharge pipe.
• Run the pump in maximum stroke for 2 hours observe for unusual sound and
behavior.
• Ensure that pressure relieve valve back to the tank and pressure sustaining
valve at dosing line are properly set to required pressures to avoid damage/
overloading of the pumps.
• When completed, stop the pump and start the next unit. Ensure on completion
that all connections are secure.
• Ensure that the flushing water from the dosing pump, piping & from the
storage tank is drained completely.
• Ensure that dry run protection for the pumps has been tested and minimum
level set.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
98
6.2.5 Pre-condition for commissioning
• Process liquid is continuously available for the SWRO and BWRO feed headers
for the commissioning.
• The piping to the dosing location is flushed (upstream of SWRO feed & BWRO
pumps).
• Whenever low level alarm (LL) in solution tank is indicated, the tank must be
refilled with fresh solution immediately.
6.2.6 Procedure
• Start one dosing pump, adjust its stroke and speed (refer to supplier
instructions) Taking to consideration also operational conditions of the plant
(dosing rate and media flow) and allow pump to prime. Keep in operation in
automatic mode of operation for required operational time.
• Once first pump is commissioned, stop the pump and start the next unit.
Ensure on completion that all connections are secure.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
99
6.2.7 Coagulant Dosing and Preparation.
• The dosing of Anti scalant (ASC) shall ensure that the scaling potential in the RO
brine is below the solubility limits of sparingly soluble salts in case of no acid is
dosed in the pre treatment. At pH values of below 7, 5 usually no ASC is
required.
• Anti scalant is usually delivered as a liquid in the plastic drums or barrels is size
depending from its manufacturer and order. If using a powder trade product,
dosing of ASC requires the operation of the utility water pumps – one in operation,
the second standby, which feed the mixing tanks with permeate from the permeate
tanks.
In manual mode, the dosing of the chemicals is controlled by adjustment of the dosing
rate from the operator panel on the relevant dosing pump.
Mixers in the dosing tanks are only operated manually during preparation of the
solution. Usually ASC is overdosed by approx. 20% for safety reason.
• The ASC is usually dosed as trade product undiluted, but also powder-trade
products are available, for with a dilution with permeate by carrier water
pumps is necessary.
100
6.3.1 Pre-condition for flushing
• The Biocide tanks are thoroughly cleaned and filled with service water.
• Read and consider O&M Instruction Manual from dosing pumps manufacturer.
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
• Biocide tanks mixers are wired, oil level is checked and are pre-commissioned
• Dry run protection level indicators at the Biocide tanks are installed and tested
• Start Biocide tank mixer in both tanks, observe for unusual noise and vibration
• Disconnect the suction piping from both dosing pump, flush the lines, and
check the strainers.
• Connect piping back and open Biocide storage tank outlet valve
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. Afterwards
increase capacity and speed to 50%, 75% and to the maximum setting. This
101
may require the discharge pipe to be vented by unscrewing a connection of
the discharge pipe.
• Run the pump with maximum stroke adjustment for 2 hours observe for
unusual sound and behavior.
• Ensure that pressure relieve valve back to the tank and pressure sustaining
valve at dosing line are properly set to required pressures to avoid damage/
overloading of the pumps.
• When completed, stop the pump and start the next unit. Ensure on
completion that all connections are secure.
• Ensure that the flushing water from the dosing pump, piping & from the
storage tank is drained completely.
• Ensure that dry run protection for the pumps has been tested and minimum
level set.
Warning: Stroke length of the pump can be adjusted only when the
pump is in operation !!!!!
• Process liquid is available for the Flushing Pumps and Back wash line Ph2+Ph3
for the commissioning.
102
•
The dosing pumps inlet strainers are installed and free of debris.
• Whenever low level alarm (LL) in solution tank is indicated, the tank must be
re-filled with fresh solution immediately.
6.3.4 Procedure
• Start one dosing pump, adjust its stroke and speed (refer to supplier
instructions) as per process requirement taking to consideration operational
conditions of the plant (dosing rate and media flow) and allow pump to prime.
Keep in operation in automatic mode of operation for required operational
time. When required change specific dosing rate and frequency at VFD when
in manual mode.
• Once first pump is commissioned, stop the pump and start the next unit.
Ensure on completion that all connections are secure.
Warning: Stroke length of the pump can be adjusted only when the
pump is in operation !!!!!
6.3.5 Biocide Dosing and Preparation.
The Biocide is dosed normally once per week in order to prevent bio-fouling
caused by the effects of chlorination.
103
• Dosing is carried out for a certain time period (some minutes - hours) with a
concentration of 15 – 20 ppm (for detailed info see data of trade-product
manufacturer).
• The SMB tanks are thoroughly cleaned and filled with service water.
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
• SMB tanks mixers are wired, oil level is checked and are pre-commissioned
• Dry run protection level indicators at the SMB tanks are installed and tested
104
•
•
• Dampener at the discharge piping of the SMB Dosing pumps are
precommissioned and charged with air or nitrogen to required operational
pressure.
6.4.2 Procedure
• Start SMB tank mixer in both tanks, observe for unusual noise and vibration
• Disconnect the suction piping from both dosing pump, flush the lines, and
check the strainers.
• Connect piping back and open SMB storage tank outlet valve
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. Afterwards
increase capacity and speed to 50%, 75% and to the maximum setting. This
may require the discharge pipe to be vented by unscrewing a connection of
the discharge pipe.
• Run the pump with maximum stroke adjustment for 2 hours observe for
unusual sound and behavior.
105
• Ensure that pressure relieve valve back to the tank and pressure sustaining
valve at dosing line are properly set to required pressures to avoid damage/
overloading of the pumps.
• When completed, stop the pump and start the next unit. Ensure on
completion that all connections are secure.
• Ensure that the flushing water from the dosing pump, piping & from the
storage tank is drained completely.
• Ensure that dry run protection for the pumps has been tested and minimum
level set.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
• Ventilation above the dosing and preparation tanks is active and working.
• The dosing pumps inlet strainers are installed and free of debris.
• Whenever low level alarm (LL) in solution tank is indicated, the tank must be
re-filled with fresh solution immediately.
6.4.4 Procedure
106
•
•
• Open the dosing Pump discharge isolation valves.
• Start one dosing pump, adjust its stroke and speed (refer to supplier
instructions) as per process requirement taking to consideration operational
conditions of the plant (dosing rate and media flow) and allow pump to prime.
Keep in operation in automatic mode of operation for required operational
time. When in manual mode of operation and required, change specific dosing
rate at dosing pump and frequency at VFD manually.
Observe for proper operations of the pump, pressure relive valves (PRV) and
pressure sustaining valves (PSV).
• Once first pump is commissioned, stop the pump and start the next unit
following above mentioned procedure. Ensure on completion that all
connections are secure.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
6.4.5 Coagulant Dosing and Preparation.
• The dosing of Sodium-Meta-Bisulfate (SMB) = Na2S2O5 shall ensure that the
free chlorine content does never exceed 0.1 mg/l or a corresponding value of
ORP of the feed water.
107
Free oxygen content is reduced according to the reaction
2 SO32− + O2 ⇔ 2 SO24−
• The SMB is dosed flow proportional to the sum of the flow of RO 1st pass Trains
• Fill the clean tank with 500 liter water. Start the mixer and add the content of 2
bags SMB (25 kg each) for a solution of 10%.
• Continue mixing for about 15 minutes until the SMB is dissolved completely.
Stop the mixer and the solution can be used.
• At level alarm low the tank shall be changed over to the standby tank which
was prepared as described before.
• Add the necessary amount of water to have the tank filled with 500 liters. Start
the mixer and add the content of x bags SMB (25 kg each) in order to get a 10%
solution. (E.g.: If 400 liters added, 40 kg SMB shall be added.)
• Continue mixing for about 15 minutes until the SMB is dissolved completely.
Stop the mixer and the solution can be used.
108
•
•
Concentration Concentration Solution
SMB SMB density in
in [%] in [kg/l] [g/l]
5% 0,051 1,03
10% 0,106 1,06
15% 0,165 1,10
109
Adjustment of dosing rate - Example Calculation
Specific dosing rate: 5 mg/l as Na2S2O5
Flow rate: 1480 m³ / hour
Concentration in tank: 10% = 106 g/l
The chlorine dosing system is divided into three parts and shall be commissioned
before start up of the Sea Water Intake pumps:
2. Chlorination CEB-1
detection leak sensors and extraction fans are ready and pre-commissioned •
Filtered water is available for Pre-chlorination booster pumps
• Local control station and push button pendant connections are checked,
commissioned and energized
110
• Automatic change over device is wired, tested and ready for operation
• The CEB 1 booster pumps are installed and ready for pre-commissioning as per
manufacturer O&M Instruction Manual.
6.5.2 Procedure
Note: Be familiar with operation and maintenance manuals of the Service Water
System as per manufacturer O&M Instruction Manual.
• Crack open PRE chlorination booster water pump suction inlet isolation valve.
111
• Slightly unscrew the BOOSTER Pump vent screw and observe water flow
through the vent. When there is no air in the water, tight the vent screw.
• Reinstall the plug and fully open the Booster Water Pump suction inlet isolation
valve. Repeat above procedure on remaining Pre-chlorination /
Postchlorination (POST) Booster Water Pumps
Depending on the pressure in RF outlet line, the system will be filled with
filtered water and air removed from pipes.
• Run the pump for 2-3 hours and check for unusual noise, vibrations,
temperature.
• The PRE-chlorination booster pump system is now checked and ready for
operation.
• CEB 1 chlorination booster pumps open isolation valve from UF Filtrate line •
Open CEB 1 Booster Pumps suction isolation valves, vent pumps both pumps
112
• Slowly open the CEB 1 Booster Water Pumps discharge isolation valve and
adjust discharge pressure.
• Run the pump for 2-3 hours and check for unusual noise, vibrations,
temperature.
• The CEB 1 chlorination booster pump system is now checked and ready for
operation.
• Open isolation valve for Permeate water from Product water pump station •
Open Booster Water Pumps suction isolation valves, vent pumps both pumps
• Slowly open the POST Booster Water Pumps discharge isolation valve and
adjust discharge pressure.
• Run the pump for 2-3 hours and check for unusual noise, vibrations,
temperature.
• The POST chlorination booster pump system is now checked and ready for
operation.
113
• Local control station and Change over device are checked, commissioned and
energized
• The chlorine dosing piping is installed, flushed & pressure tested with
nitrogencommissioned.
• All valves, catch pot / expansion chamber and instrumentation are connected
and ready for operation
• All chlorinators are installed, valve limit switches adjusted, energized, ready
for commissioning.
• Service water system, chlorine detector, extraction fans and sprinkling system
are ready for commissioning.
• Change over valves is in position for one of the drums No.1 or No2.
114
• Open outlet valve from selected drum, check pressure at PI
• Open inlet and outlet valves at selected Pre-chlorinator and adjust flow of
chlorine gas to required process flow.
• Open inlet and outlet valves at selected CEB 1 chlorinator and adjust flow of
chlorine gas to required process flow.
• Open inlet and outlet valves at selected Post-chlorinator and adjust flow of
chlorine gas to required process flow.
• Repeat the same for all remaining chlorinators for Pre-chlorination, CEB 1
chlorination and Post-Chlorination.
Chlorine is dosed proportionally to the sea water inlet flow, CEB 1 flow to UF
and product water flow for post-chlorination.
• Hydrochloric acid is mainly used for CEB of the UF plant. Acid is directly drawn
from delivery IBC’s tanks. Since the Hydrochloric acid is 31% concentrated,
make sure that all piping is completed & pre-commissioned.
115
• It is not recommended to flush the acid with potable water due to the
chemical properties of hydrochloric acid and exothermic reaction. Therefore,
flushing with potable water cannot be carried out. For cleaning purposes
instrument or service air shall be used and all piping shall be blow up for at
least 20 minutes.
• The dosing piping from dosing pumps to RO CIP, UF CIP, Neutralization, and UF
units 1-13 is pre-commissioned.
• Review the O&M Instruction Manual from piston dosing pump manufacturer.
• Start one of piston dosing pump (UF_RO CIP + Neutralization), adjust its
stroke and speed (refer to supplier instructions) as per process requirement
taking to consideration operational conditions of the plant (dosing rate and
media flow) and allow pump to prime using personal protection equipment.
On completion of priming ensure that all connections are secure.
• Observe for proper operations of the pump, pressure relive valves (PRV) and
pressure sustaining valves (PSV).
116
• Once first pump is commissioned, stop the pump and start the next unit
following above mentioned procedure. Ensure on completion that all
connections are secure.
• Make sure the pump stops automatically when the IBC tank level reaches LSLL
level. If not, immediately stop the pump manually.
• When pumps to CIP and Neutralization are commissioned follow the same
procedure for HCL dosing pumps with second set of the dosing pumps for CEB
to UF Units 1-13 (CEB).
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
• Since the NaOH is 49-50% concentrated, make sure that all piping is
completed & pre-commissioned.
• It is not recommended to flush the acid with potable water due to the
chemical properties of NaOH and exothermic reaction. Therefore, flushing
with potable water cannot be carried out. For cleaning purposes instrument or
service air shall be used and all piping shall be blow up for at least 20 minutes.
• The dosing piping from dosing pumps to RO CIP, UF CIP, Neutralization, and UF
units 1-13 is pre-commissioned.
117
• Review the O&M Instruction Manual from dosing pump manufacturer.
• Discharge piping from Filling pumps to the NaOH Dosing Tanks is opened
6.7.2 Procedure:
• The pumps are pre-commissioned, oil level checked, power supply and control
cables connected and tested.
• NOTE: There is no DRY RUN PROTECTION FOR THE NaOH FILLING PUMPS
AVAILABLE. Dry run protection depend from operator, to switch off the filling
pumps in right time, immediately when IBC is empty or latest when suction of
the pump will be aerated.
• Start Filling pump and open discharge valve at discharge piping to the NaOH
Dosing Tanks. Run the pump as per operational curve, obtained in the O&M
Instruction Manual and continue with filling of the NaOH tanks.
• Observe the behavior of the Filling pump for unusual sounds, vibrations,
discharge pressure or leaks. When everything is OK, stop filling pump and
repeat the test with second filling pump.
• Read and consider O&M Instruction Manual from dosing pumps manufacturer.
118
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
• NaOH tanks mixers are wired, oil level is checked and are pre-commissioned
• Dry run protection level indicators (mixers – dosing pumps) at the NaOH tanks
are installed and tested
• Dampener at the discharge piping of the NaOH Dosing pumps (if installed) are
pre-commissioned and charged with air or nitrogen to required operational
pressure.
• Heating system in the NaOH Dosing Tanks is installed, wired, tested and ON.
6.7.4 Procedure
• Start NaOH tank mixer in both tanks, depending from level of NaOH in the
tans, observe for unusual noise and vibration
• Disconnect the suction piping from both dosing pump, flush the lines, and
check the strainers.
• Connect piping back and open NaOH storage tank outlet valve
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. This may
require the discharge pipe to be vented by unscrewing a connection of the
discharge pipe Afterwards increase capacity and speed to 50%, 75% and to the
119
maximum setting. Run pump for certain time, if all OK set pump to operational
conditions controlled by neutralization and CIP pH and continue operation,
observe for unusual sound and behavior.
• Ensure that pressure relieve valve back to the tank and pressure sustaining
valve at dosing line are properly set to required pressures to avoid damage/
overloading of the pumps.
• When completed, stop the pump and start the next unit. Ensure on
completion that all connections are secure.
• Ensure that dry run protection for the pumps has been tested and minimum
level set.
• When RO CIP, UF CIP and Neutralization NaOH dosing system are flushed
continue with Dosing to SWRO fee line, BWRO feed line UF unit 1-13 and UF
unit 14-26, following instruction above.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
• Do not swallow.
• The Anionic polymer tank (AP) is thoroughly cleaned and filled with service
water.
120
• Permeate water is available in the storage tank.
• The dosing pumps are pre-commissioned, oil level checked, power supply and
control cables connected and tested.
• AP tanks mixers are wired, oil level is checked and are pre-commissioned
• Dry run protection level indicators at the ASC tanks are installed and tested
• Pressure indicators (PI) and flow switches (FS) are installed, wired and tested.
6.8.2 Procedure
• Start AP tank mixer in both tanks, observe for unusual noise and vibration
• Disconnect the suction piping from both dosing pump, flush the lines, and
check the strainers.
• Connect piping back and open APE mixing tank outlet valve
• Start one dosing pump, adjust its stroke (refer to supplier instructions) and
speed slowly to 25% capacity and flow and allow pump to prime. Afterwards
increase capacity and speed to 50%, 75% and to the maximum setting. This
may require the discharge pipe to be vented by unscrewing a connection of the
discharge pipe.
• Run the pump in maximum stroke for 2 hours observe for unusual sound and
behavior.
• Ensure that pressure relieve valve back to the tank is properly set to required
pressures to avoid damage/ overloading of the pumps.
121
• When completed, stop the pump and start the next unit. Ensure on completion
that all connections are secure.
• Ensure that the flushing water from the dosing pump, piping & from the
storage tank is drained completely.
• Ensure that dry run protection for the pumps has been tested and minimum
level set.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
• Process liquid is continuously available for the SWRO and BWRO feed headers
for the commissioning.
• The piping to the dosing location Settling Tank is flushed • All instruments (PIS,
• Whenever low level alarm (LL) in solution tank is indicated, the tank must be
re-filled with fresh solution immediately.
6.8.4 Procedure
122
• Start one dosing pump, adjust its stroke and speed (refer to supplier
instructions) Taking to consideration also operational conditions of the plant
(dosing rate and media flow) and allow pump to prime. Keep in operation in
automatic mode of operation for required operational time.
• Once first pump is commissioned, stop the pump and start the next unit.
Ensure on completion that all connections are secure.
Warning: Stroke length of the pump can be adjusted only when the pump is in
operation !!!!!
6.8.5 ASC Dosing and Preparation.
• The dosing of Antiscalant (ASC) shall ensure that the scaling potential in the
RO brine is below the solubility limits of sparingly soluble salts in case of no
acid is dosed in the pre treatment. At pH values of below 7, 5 usually no ASC is
required.
• The ASC is usually dosed as trade product undiluted, but also powder-trade
products are available, for with a dilution with permeate from Flushing Tanks
by Service Water pumps is necessary.
123
• In manual mode, the dosing of ASC is controlled by adjustment of the dosing
rate from the operator panel on the relevant dosing pump. The mixers in the
dosing tanks are also operated manually during preparation of the solution.
• For automatic operation via PLC system the relevant dosing pump has to be
set for remote control from the switchboard first. Furthermore one out of two
dosing tanks has to be selected for operation by a selector switch on the
dosing on the control PC screen. The PE is dosed flow proportional to the inlet
flow.
• Refill the relevant APE vessel when level alarm low shown on PLC / SCADA.
124
• The flushing of booster pump & associated piping can be performed by the
same procedure mentioned for carrier water flushing.
• CO2 gas in the CO2 storage tank is required to perform the above
commissioning.
• Please refer to manufacturers O&M Instruction manual for the details of
flushing & commissioning of CO2 storage tanks and its associated
equipments.
• For commissioning, Permeate transfer pumps shall be in operation to
identify the dosing requirements.
Be familiar with manufacturer’s O&M Instruction Manual for Lime Silos, Lime
Milk Pumps, Lime Circulation Pumps and Lime Saturated Water Pumps
following
Preconditions
Note: Service water for Lamellae Separators is required only for first
start up of the system. When RO Trains are in operation, permeate
will be used to feed the Separators.
• Dosing line is connected to dosing point at Static Mixer
• Permeate water is available
• VFD for the Lime Slurry pumps is set and tested
7.0.2 Procedure:
125
• Open permeate water suction and discharge isolation valves for circulation
pumps
• Open permeate water isolation valves to Slurry make up tanks and to Lime
Mixing tanks
• Adjust permeate water flow to Lime Slurry Make-up Tank to e.g. 5 m3/h via
126
• Open Mixing Tank inlet flow control valve and adjust service water flow to
tank to e.g.~ 25 m3/h
127
• Slowly open the Saturated Lime Water Pump discharge valve
• Check lime saturated water flow on FIT and adjust it to e.g. ~ 25 m3/h via
Note: Over the time of operation, lime sludge will be formed in Lamellae
Separators. Sludge quantity depends on purity of hydrated lime (90 –
95%) and lime solubility in water. Lime solubility is a function of water
temperature. The lower the temperature, the higher the solubility. Each
Lamellae Separator has conical bottom where sludge will be collected.
Worked Example:
Permeate water flow 1,118 m3/h
Lime dosing rate 32 mg/l
Lime purity 95%
Lime slurry concentration 105.7 g/l (10% slurry)
Lime solubility 1.47 g/l @ 35 degC
128
Slurry pump running time 356 l/h / 2,500 l/h = 0.14 h x 60 = 8.5 min/h
Number of running cycles 60/5 = 12 (each 5 minutes)
Running time per cycle 8.5 / 12 = 0.7 min
8.0.1 Preconditions
• Neutralization chamber is ready to receive dumping water.
• Neutralization Sump is commissioned, clear of any construction debris and
filled with service water or filtered seawater.
• Neutralization Pumps are pre-commissioned as per O&M manual and ready
for operation.
• Drain system is commissioned and ready to receive waste water
• Submerged recirculation pumps are pre-commissioned
• pH analyzers are commissioned
8.0.2 Procedure
129
• Slowly open Neutralization pumps discharge pressure gauge isolation
valves and check discharge pressure. Release air if necessary.
• Check water quality (pH) and start alkali or acid dosing if necessary.
• Continue with dosing until water quality is within prescribed limits
• When water quality is acceptable for disposal, then:
• Open Neutralization pumps dump valve and divert water to culver
• Close Neutralization pumps recirculation valve
• Stop the Neutralization Pump when sump is empty
• Repeat above operation under automatic mode and check system
performance.
• Neutralization system is commissioned and ready for operation.
Each actuated valve can be operated manually from local panel via dedicated
pneumatic solenoid valve.
9.0.1 Preconditions
Note: Study and be familiar with operation and maintenance instruction manual
for RO Chemical Cleaning Pumps and Motors provided pump manufacturer.
130
• Culvert is ready to receive the dumping water from RO cleaning, RO permeate
overflow tank.
• Overflow piping is available, RO Cleaning tank is cleaned, flushed and fully filled
with Flushing water or RO permeate.
• Study and familiarize yourself with Material Safety Data Sheets of all
chemicals used on site.
9.0.2 Procedure
• RO Cleaning tank 60m3 is cleaned, flushed and filled with Flushing water or RO
permeate (do not use water from Treated Water Tank which contains free
chlorine, which will cause oxidation of RO membranes!!! If used always add 25
kg of Sodium Metabisulphite (SMB) to the tank during filling with service
water. Or use Cleaning Chemicals Preparation System to transfer SMB solution
to Cleaning Tank)
• RO Cleaning Pumps A/B/C are pre-commissioned and ready for operation (dry
run protection is activated.) Follow O&M Instruction manual for RO CIP
pumps!
131
• All RO pressure vessels are connected (plugs are installed at feed & permeate
side of the pressure vessels??)
• Cleaning feed movable spool pieces are installed or if valves installed all must
be opened on 1st Pass Feed Branch
• Both CIP valves at inlet side / Feed side ( from CIP system) of the RO train are
opened
• Both CIP plug valves at inlet side / Feed side of the RO train are closed
• Cleaning reject return movable spool pieces are installed on 1 st Pass Brine
Branch
• CIP valve at inlet side / Brine side (Brine CIP return) of the RO train is opened
• CIP plug valve at outlet side / Brine side of the RO train is closed
• Both valves from 1st and 2nd Pass to Neutralization are closed
132
9.0.3 RO CIP Flushing Procedures – Low pressure flushing
• Flushing water is now circulating from CIP tank via pressure vessels of the 1st
and 2nd pass trains back to the CIP tank, keep in operation for 1 hour, or time
• Open both valves from 1st and 2nd pass to neutralization and dump all dirty
water
• When pumps are stopped by CIP Tank dry run protection, drain / empty CIP
tank to neutralization
133
9.0.4 Flushing & Commissioning of the RO CIP System
• Difference between the flushing and normal operation / cleaning of the train is:
Cartridge filters are installed in both CF and flushed with permeate water
• Chemical cleaning solution is prepared in the RO CIP Tank depending from kind
of cleaning procedure used or recommended by membrane manufacturer,
acidic or alkaline.
• Heater is switched on when required
• pH measurement and conductivity instrumentation is in operation
Each actuated valve can be operated manually from local panel via dedicated pneumatic
solenoid valve.
Note: Study and be familiar with O&M Instruction manuals of the following
equipment:
• Pressure Vessels
• Membrane service bulletin for flushing of the pressure vessels
134
9.0.6 Preconditions
Preconditions
• High pressure piping within 1st Pass RO Train is clean and free of dirt
• Temporary in-line strainer is installed on the suction of the HP pumps
• Lube Oil System is commissioned
• Cooling water supply is available for Lube Oil System and HPP Motor
• Pretreatment is commissioned and in operation
• All instruments, valves and piping have been commissioned
• Permeate outlet ports of membrane pressure vessels are plugged using special
PVC plugs
• Remove vent and drain plugs from HP Pumps and from HP Booster Pumps
Note: If starting the pump set for the first time after installation or overhaul,
disconnect the flexible coupling between the pump and motor and turn the pump
by hand to ensure freedom of rotation. Than re-connect the coupling.
135
• Intake station is in operation
• All RO pressure vessels are connected and plugs at feed & permeate side
installed
• High pressure piping within RO Train is clean and free of any dirt.
• ‘Crack’ open HP Pump inlet valve. Care must be taken in opening this valve to
prevent water surge
• This will allow the seawater to pass into the HP Pump. The flow should be
controlled such, that a generous flow is seen from each of the vent and drain
ports on the pump. The pump shaft should be rotated few times to release
136
trapped air and dirt. The plugs should be gradually installed and the flow
reduced accordingly.
• This will allow the seawater to pass into the membrane stages and through
the HP Pump. The flow should be controlled such, that a generous flow is seen
from each of the vent and drain ports on the pump. The pump shaft should be
rotated few times to release trapped air and dirt. The plugs should be
gradually installed and the flow reduced accordingly.
• When HP Pump is de-aerated, set the inlet flow to ~ 150 m3/hr. Check flow on
flow meter.
• Check the pressure on the suction of the HP pump. It should be approx.~ 2.0 –
2.5 bar.
• Check the flow from feed vent valve. When this is clear and without
interruption the vent valves should be closed.
• Flush the train using low-pressure seawater for 30 minutes. As the Train
flushes, pass over the system opening and closing all the sample points
• Once low pressure flushing is over, proceed to the next step – high-pressure
flushing.
Note: Don’t forget that service water from Treated Water Tank contains free
chlorine, which will cause oxidation of RO membranes!!! Always add 20 litres of
15% SMBS solution to the tank during filling with service water. Use Cleaning
Chemicals Preparation System to transfer SMBS solution to Cleaning Tank.
137
• The actions and preconditions set out in Section 9.0.7 have been complied with
9.0.10 Procedure
The train is now ready for first start of HP Pump and high pressure flushing.
• Check that MCC is set for local/manual operation of the HP Pump and VFD
• Start the main lube oil pump and check pressure is greater than 1.5 bar g
• Start HP pump and slowly increase speed of the motor via VFD to ~ 2,500 –
2,900 RPM
WARNING : Variable Speed Drives are located in High Voltage area with access
restricted to authorized personnel only. Only authorized person can operate the
drive !!!!!
• Once the pump is running at above speed, check the flow at FT‘s . The flow
should be adjusted as per pump capacity and curve.
138
• Observe the behavior of the HP Pump and ensure there are no leaks on pipe
connections or valves
• Slowly increase the flow, but do not exceed maximum flow. The flow is limited
by brine pipe sizing and ERT
• Continue with flushing for 4 hours. Observe behavior of the HP Pump, electric
motors and VFD.
Preconditions
• Associated pipe work, valves and instrumentation are commissioned and ready
for operation
139
Warning: Remember basic rule for start of centrifugal pump -
start the pump against closed or very slightly opened discharge
valve if downstream pipes are empty.
9.0.12 Procedure
• Leave system to fill with water under hydrostatic pressure from Flushing Tanks
and check flow through vent valves. When flow is steady without air bubbles,
close the vent valve.
• Close the Flushing Pump discharge isolation valve (the valve can be crack
opened)
140
• Slowly open the Flushing Pump discharge isolation valve and adjust discharge
pressure to pump curve performance data.
• Check flow on FT
• Observe pump behavior for unusual noise, vibrations and system leaks
• Flushing system is now commissioned and ready for use with 1st Pass RO
Trains.
• Flush out all the salty water from 1st pass train with fresh water or permeate
9.0.13 Flushing of the 2nd Pass RO Trains feed and brine manifolds, headers and
high pressure pumps
Preconditions
• High pressure piping within 2nd Pass RO Train is clean and free of dirt
141
• Pretreatment and UF are commissioned and in operation
142
Permeate outlet ports of membrane pressure vessels are plugged using special
PVC plugs
143
•
• “Crack” open 2nd PFP outlet valve. Care must be taken in opening this valve to
• This will allow 1st Pass permeate to pass into the 2nd Pass FP. The flow should
be controlled such, that a generous flow is seen from each of the vent and
drain ports on the pump. The pump shaft should be rotated few times to
release trapped air and dirt. The plugs should be gradually installed and the
flow reduced accordingly.
• Slowly open 2nd PFP outlet isolation valve until sufficient flow is established
• Open 2nd PFP discharge flow control valve and adjust flow
• This will allow the seawater to pass into the membrane stages
• Check the pressure on the suction of the 2nd PFP. It should be at least 1.5 bar.
• Check the flow from 1st Stage feed vent valve and 2nd Stage feed vent valve.
When this is clear and without interruption the vent valves should be closed.
Flush the train using low-pressure seawater for 30 minutes. As the Train
flushes, pass over the system opening and closing all the sample points
144
• Once low pressure flushing is over, proceed to the next step – high-pressure
flushing.
Preconditions
• RO Cleaning system is commissioned
• Neutralization system is commissioned
• 2nd PFP is pre-commissioned and ready for operation
• Temporary orifice plate is installed in spool piece on cleaning reject return line
from 1st stage pressure vessels (Orifice must be installed to limit the flow and
reduce pressure in reject return line)
• 1st Pass RO permeate retain valves (One of the 1st Pass RO Trains is in
operation. Product water from running train flows through the Flushing Tanks
and to drain via temporary dump connection on combined product line)
145
•
Flushing Tank outlet valve
9.0.17 Procedure
• Fully close 2nd PFP Discharge valve. The time between fully closed and fully
opened position of the valve check with C&I engineer. It is recommended that
the operator practice the gradual opening and closing of the valve at this time.
Adjust the valve afterwards to 15 % open position.
• The train is now ready for first start of the 2nd PFP and high pressure flushing.
• Start HP pump
Once the pump is running at full rotations check and adjust the flow at FT.
146
• Gradually open 2nd PFP Discharge valve.
Observe the behavior of the pump and ensure there are no leaks on pipe
connections or valves.
Important Note: Always close the feed vent valve before brine
vent valve when starting the Train !!!
• Check the feed pressure and flow. Increase the flow if necessary.
• Continue with flushing for 4 hours - test of the 2nd PFP and motor
• When the flushing is over, reduce the flow by throttling of HP Pump discharge
valve.
• Once the flow is low, open the Train brine outlet vent valve
Important Note: Always open the brine vent valve before the
feed vent valve when stopping the Train !!!
• Once the brine outlet vent valve is open, open the feed vent valve.
• Repeat the procedure for the next Train until all 2nd Pass Trains have been
flushed
11.0.1 Preconditions
• Permeate water, chlorine free water is available in Flushing Tank.
147
•
• Service Water Pumps are pre-commissioned as per O&M Instruction manual
and ready for operation.
• Slightly unscrew the Service Water Pump vent screw /vent valve and observe
water flow through the vent. When there is no air in the water, tight the vent
screw.
• Reinstall the plug/ or close the valve and fully open the Service Water Pump
inlet isolation valve. Repeat above procedure on remaining Service Water
Pumps
148
• Depending on the water level in Product Water Tank, the system will be by
gravity filled with service water and air removed from pipes.
• Slowly open utility water valve on each user point (one at a time) and leave
water flow for necessary minutes to de-aerate piping
• Close utility Water Accumulator Tank vent valve ( if available) when water is
free from air bubbles
• Partially open Service Water inlet valves for filling of the Chemical Dosing tanks
and Settling tank
• Slowly open the Service Water Pumps discharge isolation valve and adjust
discharge pressure as per pump manufacturer curve.
• Run the pump for 1-2 hours and check for unusual noise or vibrations and
problems.
• During operation, slowly open service water valve on all 27 user points (onetwo
at a time) and leave water flow for necessary time until piping is not properly
de-aerated.
The Service Water System is now flushed, commissioned and ready for operation.
12.0.1 Pre-condition
149
•
• The compressor system is installed and pre-commissioned as per O&M.
• Power supply and control cables are connected
• Compressors shall have sufficient oil level.
• The air-receivers on plant are pre-commissioned, cleaned.
12.0.2 Procedure
150
13.0.0 FLUSHING & COMMISSIONING OF THE PRODUCT WATER
PUMPING STATION
• The product Water tanks) are pre-commissioned and are filled with product
water.
• All related pipe work is installed & pre-commissioned.
• The PWFPS main header vent valve is open
• All inlet & outlet valves for Product Water Pumps are in closed position.
13.2.0 Procedure
• Open the inlet valve of VFD driven pump & crack open its discharge valve.
• Start the pump
• Gradually increase frequency and slowly open the discharge valve
• Monitor any abnormal behavior of pumps such as sound, vibration, high
temp etc.
• Flush the system for 3 ~ 4 hrs
• If the flushing process is satisfied, stop the pump and close the inlet & outlet
valve.
• Repeat the above for the remaining pumps.
• Apply the same procedure for all Product water pumps.
151
• All dosing sets as a Lime dosing , Chlorine dosing and CO2 dosing are
precommissioned
• Product Water Pumps are pre-commissioned.
13.0.4 Procedure:
• All inlet & outlet valves of Product Water pumps are in closed position.
• Open the inlet valve for VFD driven product water pump & crack open its
discharge valve.
• Start the pump
• Gradually increase frequency and open the discharge valve
• Start all dosing skids one by one, CO2, Lime and chlorine and adjust specific
dosing rate in accordance with flow
152