ERC Refinery - roads and fence Start Date 12-Apr-17

Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17


Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

ERC Project
Equipment
Eq-Vibrator
A1050 Shoring and Plain concrete 56 05-May-17 21-Jul-17
A1060 Shoring -RC foundation- Insulation 56 15-May-17 31-Jul-17
A1070 Col Neck and Ground Beams- 51 24-May-17 02-Aug-17
Insulation
A1100 Columns 45 23-Jun-17 24-Aug-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1040 Blast Walls 66 04-May-17 03-Aug-17
A1520 Shoring and Plain concrete 40 30-May-17 24-Jul-17
A1530 Shoring -RC foundation- Insulation 40 02-Jun-17 27-Jul-17
A1540 Col Neck and Ground Beams- 34 14-Jun-17 31-Jul-17
Insulation
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1570 Columns 34 07-Jul-17 23-Aug-17
A1340 Watching Towers 79 12-Jun-17 28-Sep-17

Subtotal 106 04-May-17 28-Sep-17

Eq-Crane
A1330 Gates 131 04-May-17 02-Nov-17
A1040 Blast Walls 66 04-May-17 03-Aug-17

Subtotal 131 04-May-17 02-Nov-17

Eq-Compactor

Page 1 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17


A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1370 Compaction 50 04-May-17 12-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1420 Backfill 33 29-May-17 12-Jul-17

Subtotal 83 27-Apr-17 21-Aug-17

Eq-Truk
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1630 Remove Temperory fence 7 06-Oct-17 16-Oct-17
A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1410 Exavation 45 19-May-17 20-Jul-17
A1420 Backfill 33 29-May-17 12-Jul-17
A1430 Geotextile and Backfill 34 05-Jun-17 20-Jul-17

Page 2 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1500 Demolishing and disposal 23 19-May-17 20-Jun-17

Subtotal 134 12-Apr-17 16-Oct-17

Eq-Truk 4Ton
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Eq-Compressor
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17

Subtotal 44 20-Apr-17 20-Jun-17

Eq-Jack hammer
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17

Subtotal 44 20-Apr-17 20-Jun-17

Eq-JCP
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1350 Excavation 33 12-Apr-17 26-May-17

Page 3 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1410 Exavation 45 19-May-17 20-Jul-17

Subtotal 72 12-Apr-17 20-Jul-17

Eq-Excavator
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1410 Exavation 45 19-May-17 20-Jul-17

Subtotal 72 12-Apr-17 20-Jul-17

Eq-Loader
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1410 Exavation 45 19-May-17 20-Jul-17

Page 4 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1420 Backfill 33 29-May-17 12-Jul-17


A1430 Geotextile and Backfill 34 05-Jun-17 20-Jul-17
A1490 Pits 30 16-May-17 26-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17

Subtotal 94 12-Apr-17 21-Aug-17

Eq-Water Tank
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Manpower
MP-Labour
A1480 Temperoray Fence Installation 16 15-May-17 05-Jun-17
A1000 Temperoray Fence Installation 24 12-Apr-17 15-May-17
A1010 Pits 28 13-Apr-17 22-May-17
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1040 Blast Walls 66 04-May-17 03-Aug-17
A1050 Shoring and Plain concrete 56 05-May-17 21-Jul-17
A1060 Shoring -RC foundation- Insulation 56 15-May-17 31-Jul-17
A1070 Col Neck and Ground Beams- 51 24-May-17 02-Aug-17
Insulation

Page 5 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1080 Underground Masonary works 50 01-Jun-17 09-Aug-17


A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17
A1100 Columns 45 23-Jun-17 24-Aug-17
A1110 Masonary Works 56 03-Jul-17 18-Sep-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1130 Plastering 56 25-Jul-17 10-Oct-17
A1140 Painting 55 14-Aug-17 27-Oct-17
A1150 Install Barbed Wires 52 16-Aug-17 26-Oct-17
A1160 Remove Temperory fence 6 27-Oct-17 03-Nov-17
A1490 Pits 30 16-May-17 26-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1520 Shoring and Plain concrete 40 30-May-17 24-Jul-17
A1530 Shoring -RC foundation- Insulation 40 02-Jun-17 27-Jul-17
A1540 Col Neck and Ground Beams- 34 14-Jun-17 31-Jul-17
Insulation
A1550 Underground Masonary works 9 19-Jun-17 29-Jun-17
A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1570 Columns 34 07-Jul-17 23-Aug-17
A1580 Masonary Works 40 13-Jul-17 06-Sep-17
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1600 Plastering 40 28-Jul-17 21-Sep-17
A1610 Painting 41 09-Aug-17 04-Oct-17
A1620 Install Barbed Wires 39 15-Aug-17 06-Oct-17
A1630 Remove Temperory fence 7 06-Oct-17 16-Oct-17
A1330 Gates 131 04-May-17 02-Nov-17

Page 6 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1340 Watching Towers 79 12-Jun-17 28-Sep-17


A1350 Excavation 33 12-Apr-17 26-May-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1370 Compaction 50 04-May-17 12-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1410 Exavation 45 19-May-17 20-Jul-17
A1420 Backfill 33 29-May-17 12-Jul-17
A1430 Geotextile and Backfill 34 05-Jun-17 20-Jul-17
A1440 Drain Installation 33 13-Jun-17 27-Jul-17
A1450 Drain Finshing 34 20-Jun-17 04-Aug-17
A1460 Drain Testing 17 20-Jul-17 11-Aug-17
A1470 Drain Modification 6 14-Aug-17 21-Aug-17

Subtotal 148 12-Apr-17 03-Nov-17

MP-Surveyor
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

MP-Schafolder
A1100 Columns 45 23-Jun-17 24-Aug-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1130 Plastering 56 25-Jul-17 10-Oct-17

Page 7 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1140 Painting 55 14-Aug-17 27-Oct-17


A1150 Install Barbed Wires 52 16-Aug-17 26-Oct-17
A1570 Columns 34 07-Jul-17 23-Aug-17
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1600 Plastering 40 28-Jul-17 21-Sep-17
A1610 Painting 41 09-Aug-17 04-Oct-17
A1620 Install Barbed Wires 39 15-Aug-17 06-Oct-17
A1040 Blast Walls 66 04-May-17 03-Aug-17

Subtotal 127 04-May-17 27-Oct-17

MP-Carpenter
A1040 Blast Walls 66 04-May-17 03-Aug-17
A1050 Shoring and Plain concrete 56 05-May-17 21-Jul-17
A1060 Shoring -RC foundation- Insulation 56 15-May-17 31-Jul-17
A1070 Col Neck and Ground Beams- 51 24-May-17 02-Aug-17
Insulation
A1100 Columns 45 23-Jun-17 24-Aug-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1520 Shoring and Plain concrete 40 30-May-17 24-Jul-17
A1530 Shoring -RC foundation- Insulation 40 02-Jun-17 27-Jul-17
A1540 Col Neck and Ground Beams- 34 14-Jun-17 31-Jul-17
Insulation
A1570 Columns 34 07-Jul-17 23-Aug-17
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1340 Watching Towers 79 12-Jun-17 28-Sep-17

Page 8 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

Subtotal 106 04-May-17 28-Sep-17

MP-Steel Fixer
A1000 Temperoray Fence Installation 24 12-Apr-17 15-May-17
A1480 Temperoray Fence Installation 16 15-May-17 05-Jun-17
A1040 Blast Walls 66 04-May-17 03-Aug-17
A1060 Shoring -RC foundation- Insulation 56 15-May-17 31-Jul-17
A1070 Col Neck and Ground Beams- 51 24-May-17 02-Aug-17
Insulation
A1100 Columns 45 23-Jun-17 24-Aug-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1150 Install Barbed Wires 52 16-Aug-17 26-Oct-17
A1160 Remove Temperory fence 6 27-Oct-17 03-Nov-17
A1530 Shoring -RC foundation- Insulation 40 02-Jun-17 27-Jul-17
A1540 Col Neck and Ground Beams- 34 14-Jun-17 31-Jul-17
Insulation
A1570 Columns 34 07-Jul-17 23-Aug-17
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1620 Install Barbed Wires 39 15-Aug-17 06-Oct-17
A1630 Remove Temperory fence 7 06-Oct-17 16-Oct-17
A1340 Watching Towers 79 12-Jun-17 28-Sep-17

Subtotal 148 12-Apr-17 03-Nov-17

MP-Concrete worker
A1050 Shoring and Plain concrete 56 05-May-17 21-Jul-17
A1060 Shoring -RC foundation- Insulation 56 15-May-17 31-Jul-17

Page 9 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1070 Col Neck and Ground Beams- 51 24-May-17 02-Aug-17


Insulation
A1100 Columns 45 23-Jun-17 24-Aug-17
A1120 Upper Beam 56 10-Jul-17 25-Sep-17
A1520 Shoring and Plain concrete 40 30-May-17 24-Jul-17
A1530 Shoring -RC foundation- Insulation 40 02-Jun-17 27-Jul-17
A1540 Col Neck and Ground Beams- 34 14-Jun-17 31-Jul-17
Insulation
A1570 Columns 34 07-Jul-17 23-Aug-17
A1590 Upper Beam 40 18-Jul-17 11-Sep-17
A1340 Watching Towers 79 12-Jun-17 28-Sep-17
A1040 Blast Walls 66 04-May-17 03-Aug-17

Subtotal 106 04-May-17 28-Sep-17

MP-Masonary
A1340 Watching Towers 79 12-Jun-17 28-Sep-17
A1580 Masonary Works 40 13-Jul-17 06-Sep-17
A1550 Underground Masonary works 9 19-Jun-17 29-Jun-17
A1110 Masonary Works 56 03-Jul-17 18-Sep-17
A1080 Underground Masonary works 50 01-Jun-17 09-Aug-17

Subtotal 86 01-Jun-17 28-Sep-17

MP-Painter
A1140 Painting 55 14-Aug-17 27-Oct-17
A1610 Painting 41 09-Aug-17 04-Oct-17

Page 10 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1340 Watching Towers 79 12-Jun-17 28-Sep-17

Subtotal 100 12-Jun-17 27-Oct-17

MP-Loader Operator
A1010 Pits 28 13-Apr-17 22-May-17
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17
A1490 Pits 30 16-May-17 26-Jun-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1410 Exavation 45 19-May-17 20-Jul-17
A1420 Backfill 33 29-May-17 12-Jul-17
A1430 Geotextile and Backfill 34 05-Jun-17 20-Jul-17

Subtotal 94 12-Apr-17 21-Aug-17

MP-Jcp Operator
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17

Page 11 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

A1030 Excavation 45 28-Apr-17 29-Jun-17


A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1410 Exavation 45 19-May-17 20-Jul-17

Subtotal 72 12-Apr-17 20-Jul-17

MP-Truck Driver
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17
A1020 Demolishing and disposal 34 20-Apr-17 06-Jun-17
A1030 Excavation 45 28-Apr-17 29-Jun-17
A1090 Foundation Backfilling 51 08-Jun-17 17-Aug-17
A1500 Demolishing and disposal 23 19-May-17 20-Jun-17
A1510 Excavation 30 24-May-17 04-Jul-17
A1560 Foundation Backfilling 34 22-Jun-17 08-Aug-17
A1350 Excavation 33 12-Apr-17 26-May-17
A1360 Backfill 50 27-Apr-17 05-Jul-17
A1380 First Sub-base 28 13-Jul-17 21-Aug-17
A1390 Second Sub-Base 17 20-Jul-17 11-Aug-17
A1410 Exavation 45 19-May-17 20-Jul-17
A1420 Backfill 33 29-May-17 12-Jul-17
A1430 Geotextile and Backfill 34 05-Jun-17 20-Jul-17
A1400 Base 17 28-Jul-17 21-Aug-17
A1630 Remove Temperory fence 7 06-Oct-17 16-Oct-17

Page 12 of 13
ERC Refinery - roads and fence Start Date 12-Apr-17
Report Date 29-Apr-17 08:38 Finish Date 03-Nov-17
Data Date 12-Apr-17

RC-01 Resource Control Report

Resource ID Name
Activity ID Activity Name Original Start Finish
Duration

Subtotal 148 12-Apr-17 03-Nov-17

MP-Elctrical Tech.
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

MP-Mechanical Tech
A1660 Project Overall Resources 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Subtotal 148 12-Apr-17 03-Nov-17

Total 148 12-Apr-17 03-Nov-17