Professional Documents
Culture Documents
C H A P T E R
Layout Strategies
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
DISCUSSION
QUESTIONS
1. The seven layout
strategies are:
Fixed position or
project layout
Processoriented
use of general purpose
equipment.
Workinprocess
inventories tend to
be high.
4. Most organizations have
9
Individual workloads
can usually be made to
be
equivalent.
relatively
It usually results in low
variable cost per
unit.
7. Three types of work
cells are the small work cell
within a plant, focused work
center, and focused factory.
8. The advantages of work
cells are:
some procedure for Reduction in work
layout documenting movement of It tends to keep inprocess inventory
Warehouse layout material handling
their product. For instance, a Reduction in required
Retail layout costs relatively low.
hospital has doctor’s orders floor space
Product indicating the tests and It reduces workin Reduced raw material
oriented/repetitive procedures that a patient is to process inventories. and finished goods
layout undergo. A machine shop has It makes training and
inventory
Office layout routing documents indicating supervision easier than Reduced direct labor
Work cells the operations that an order is with other layout cost
2. Fixed position layouts to follow as the product strategies. Heightened sense of
are complicated by: limited moves through the shop. And The disadvantages are: employee
space an auto repair shop knows participation
at virtually all sites; at what repairs, parts, and labor High volume is
Increased utilization
different stages of the are used on a particular job required because of
the large investment of equipment and
process, different materials and as a result where the job machinery
are needed; and the volume of was done and the trips made needed to set up the
Reduced investment
materials needed is necessary. process.
in machinery and
dynamic. In each of the above Work stoppage at any
equipment
examples a matrix would be point ties up the
3. The advantages of a The disadvantages are:
made showing the number of whole operation.
process layout are: Similar to a product
trips. And the distance (or There is a lack of
It can simultaneously flexibility in handling layout
time or cost) of each trip
handle a wide variety a variety of products High volume is
would be determined.
of products or or production rates. required because of
services, especially in 5. The advantages of a the large investment
product layout are: 6. Preconditions for high
terms of “batches” or needed to set up the
volume, lowvariety products
“job lots.” The use of special process
are:
It has considerable purpose equipment There is a lack of
can make the overall 1. Volume is adequate flexibility in handling
flexibility with respect
process more efficient. for high equipment a variety of products
to equipment and
utilization or production rates
labor assignments.
2. Product demand is Requires the use of
The disadvantages of a stable enough to group technology
process layout are: justify high Requires a high level
The use of general investment in of training and
purpose rather than specialized flexibility on the part
special purpose equipment of employees
equipment tends to 3. The product is Either considerable
make the overall standardized or staff support or
process somewhat less approaching a phase imaginative
efficient. of its life cycle that employees are
Orders take more time justifies investment needed for the initial
and money to move in specialized development of the
through the system equipment work cells
because of the difficult 4. Supplies of raw
scheduling, setting up material and
the process for a wide components are
variety of orders, and adequate and of
considerable material uniform quality to
handling. ensure that they will
work with the
Labor skill
specialized
requirements tend to
equipment.
be high because of the
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall. 118
CHAPTER 9 L AYO U T S T R AT E G I E S 119
9. The requirements for a of staples at corners of store New product Some points for class
focused work center or (fruit/meat/dairy/bakery). proliferation (a discussion:
focused factory are 15. “Random stocking” is grocer may handle Slotting fees mean
identification of a large family placing a unit (product) only 30,000 of that the small new
of similar products, a stable anywhere in a warehouse that 100,000 SKUs company has trouble
demand, and adequate volume is open (available) for use. available, a book getting products on
to justify the capital This is the opposite of seller has a similar the shelf.
investment. “static” storage where every problem) Slotting fees tend to
10. Two major trends SKU has its own allotted High rate of new reinforce the position
influencing office layout are space. product failure of the strong/ major
dynamic needs for Increase in retailer companies.
16. Random stocking works
space/services, technology power (the retailer as The retailer is
best with sophisticated
and virtual companies. “channel interested in products
information systems that
captain”) that will sell and pro
11. Some of the layout rapidly identify items by bar
variables you might want to codes (or other scannable vide margin—a
consider as particularly IDs), and place them strong inducement for
important in an office where randomly in a warehouse. any good product—if
computer programs are to be That requires profitable, shelf space
written are: (1) open location, (2) accurate will be found.
records, (3) efficient “picking” As a practical
Ease of
sequencing, (4) combining matter, slotting fees
communication
orders, and (5) minimizing can take so many
Provision of privacy
distance to “pick” high usage forms (discounts,
and a quiet work
items. advertising fees,
environment
tasting stations,
Lighting—especially 17. Crossdocking means
return policies, etc.)
as it related to glare on that units are never put in
that real control is
computer screens storage in an intermediate
probably impossible.
Consideration of storage facility (warehouse).
Slotting fees are the
ergonomic or human Units are accurately labeled
inevitable result of
factor issues in prior to shipment with the
the free market at
equipment layout and information needed to
work, one more item
construction identify the final destination
in the give and take
12. Some drugstore and so that when they arrive at an
between buyer and
grocery chains now allow only intermediate warehouse or
seller.
limited routes through the distribution point, they are
Slotting fees may
store. This (a) allows a high immediately moved to the
make up half of the
traffic volume to be handled shipping dock for transmittal
profit of a grocer.
more readily, and (b) forces to that final destination.
Since the fees are
each customer to be exposed 18. A heuristic is a “rule of revenue for the
to all merchandise. There are thumb” method of problem retailers, the fees
now Internet kiosks in solving. Line balancing allow lower prices.
shopping malls. heuristics include: longest U.S. District Judge
13. Retail store layout task time, most following Gene Carter held in
variables that a manager can tasks, ranked positional 2001, in Maine, that
manipulate are: weights, shortest task time, slotting fees in a
and least number of following news company
Overall arrangement
tasks. distribution case
or pattern through the
store were not illegal.
ETHICAL DILEMMA
The allocation of The authors see no problem
Slotting fees refer to
space to individual with the ethics of slotting fees
payments by manufacturers
products but would encourage firms
for retail shelf space—
14. Each student will sketch not to hide the nature of the
although the term can mean
the layout of a local payments.
display or other support—
supermarket. They should such as a tasting station—for
observe the long aisles, power a product. They are the result ACTIVE MODEL
items at aisle caps, and spread of: EXERCISE
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
120 CHAPTER 9 L AYO U T S T R AT E G I E S
ACTIVE MODEL 9.1: (d) Plan B is the lowest
Process Layout Movement–Distance Calcula
9.2 (a) Plan A movements = (20 �6) + (12 �18) + (8 �2) M W: 125 20 2,500
1. What is the current total
cost? + (6 �4) + (10 �2) + (4 �18) =
$570 M D: 75 40 3,000
= 120 + 216 + 16 + 24 + 20 + 72 =
2. Assembly (A) and
= 468 (in 100s) = 46,800 M G: 50 20 1,000
Machine Shop (M) have the
=
highest degree of interaction. Cost = 46,800 �$0.50 = $23,400 M B: 60 20 1,200
Would it be better to swap
(b) Plan B movements = (20 �6) + (8 �18) + (12 �2) =
(A) and Painting or (M) and
W L: 75 20 1,500
Painting in order to get (A) + (10 �4) + (6 �2) + (4 �18) =
and (M) shop next to each
= 120 + 144 + 24 + 40 + 12 + 72 D G: 150 20 3,000
other?
=
Swapping Assembly = 412 (in 100s) = 41,200
D B: 20 20 400
and Painting lowers the
Cost = 41,200 �$0.50 = $20,600 =
cost, while swapping
L G: 20 20 400
Assembly and Machine (c) Plan C movements = (20 �6) + (10 �18) + (6 �2)
=
shop raises the cost. + (8 �4) + (12 �2) + (4 �18) 13,000 = Min
3. Use the Swap button one movement
= 120 + 180 + 12 + 32 + 24 + 72
swap at a time. If the swap (symmetric
helps, move to the next pair. = 440 (in 100s)
If not, click Swap to put the 9.5
= 44,000
departments back. What is the Interstation Activity Matrix
minimum total cost after all Cost = 44,000 �$0.50 = $22,000
Pick Up Pick Up Verification
swaps have been tried? Paperwor Advising Class of Status
The cost drops to $510. cost, at $20,600. k
4. Look at the two data 9.3 (23 10) + (32 5) + and Forms Station Cards and
tables and use the yellow (20 8) = 230 + 160 + 160 = Payment
shaded column to put 550 (A) (B) (C) (D)
processes in rooms. What Paperwork/ 0 450 550 50
C
room assignments lead to the Forms (A)
o Advising (B) 350 0 200 0
minimum cost? What is this st Class Cards (C) 0 0 0 750
cost? = Verification/ 0 0 0 0
Putting the processes in 5 Payment (D)
rooms 1,4,2,5,6,3 5
respectively (yellow shaded 0
area) has a minimum total
cost of $460. (Other layouts $
will have the same cost.) 2
=
END-OF-CHAPTER $
PROBLEMS 1,
9.1 Movements = (4 �8) + (9 �7) + (7 �4) + (6 �3) + (8 �2) + (10 � 1 6)
0 or
= 32 + 63 + 28 + 18 + 16 + 60 = 217 (in 100s) 0
= 21,700 9.4 This matrix includes
Cost = 21,700 �$1 = $21,700 movements in both
directions:
M W D L G B
M — 125 75 0 50 60
W — 0 75 0 0
D — 0 150 20
L — 20 0
G — 0
B —
Here are two optimal layouts:
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
CHAPTER 9 L AYO U T S T R AT E G I E S 121
1 2 3Layout
Interstation Distance Matrix—Original 4 5 1
Interstation Distance Matrix—Improved Layout 1 0 8 13 0 0 1 0
Pick Up Pick Up Verification
Pick Up Pick Up Verification 2 5 0 3 3 8 2 4
Paperwor Advising Class of Status
Paperwor Advising Class of Status 3 3 12 0 4 0 3 8
k
k 4 3 0 0 0 5 4 12
and Forms Station Cards and
and Forms Station Cards and 5 0 8 4 10 0 5 14
Payment
Payment (A) (B) (C) (D)
(A) (B) (C) (D)
Paperwork/ 0 30 60 90
Paperwork/ 0 30 30 60 Forms (A)
Forms (A) Advising (B) 30 0 30 60
Advising (B) 30 0 60 90 Class Cards (C) 60 30 0 30
Class Cards (C) 30 60 0 30 Verification/ 90 60 30 0
Verification/ 60 90 30 0 Payment (D)
Payment (D)
Tij Dij = 560 (if
areas are fixed)
9.8 (a) Layout 4:
Load Distance
A B: 450 30 = 13,500 Load Distance
A C: 550 60 = 33,000 A B: 450 30 = 13,500
A D: 50 90 = 4,500 A C: 550 30 = 16,500
B A: 350 30 = 10,500 A D: 50 60 = 3,000
B C: 200 30 = 6,000 B A: 350 30 = 10,500 Trip Matrix Distance Matrix
C D: 750 30 = 22,50 B C: 200 60 = 12,000 1 2 3 4 5 1 2 3 4 5
0 C D: 750 30 = 22,500
1 0 8 13 0 0 1 0 5 8 11 13
90,000 78,002 5 0 3 3 8 2 5 0 4 8 11
0 3 3 12 0 4 0 3 8 4 0 4 8
Note: Work areas are “fixed” if
using the software to reach this 4 3 0 0 0 5 4 11 8 4 0 5
(b) Improved layout: 5 0 8 4 10 0 5 13 11 8 5 0
initial answer.
(a) Initial layout:
Trip Matrix
1 2 3 4 5
9.6 (a) Layout 1: 1 0 8 13 0 0
2 5 0 3 3 8
3 3 12 0 4 0
4 3 0 0 0 5
5 0 8 4 10 0
Tij Dij = 602 (if areas are
Trip Matrix
fixed; 566 if not; 595 if the
1 2 3 4 5 sink is fixed in one location)
1 0 8 13 0 0
9.7 Layout 3:
2 5 0 3 3 8
3 3 12 0 4 0
4 3 0 0 0 5
5 0 8 4 10 0
Tij Dij = 600 with work Tij Dij = 609
areas fixed (504 if not fixed;
560 if the sink is fixed in one
location)
(b) Layout 2:
Trip Matrix
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
122 CHAPTER 9 L AYO U T S T R AT E G I E S
49 minutes
(b) Layout 5: (c) The cleaning (g) Efficiency =
operation is 8 stations �8.0 minutes*
9.12 Performance Timeor
Trip Matrix Distance Task (in minutes)
Matrix Effici
A 4
1 2 3 4 5 1 2 3 4 5
ency
B 7
C 6
=76.6
ref-1 0 8 13 0 0 ref-1 0 4 12 12 4
D 5 %
coun-2 5 0 3 3 8 coun-2 4 0 3 4 4
sink-3 3 12 0 4 0 sink-3 12 3 0 4 4 E 6 *Longest operation time
F 7
stor-4 3 0 0 0 5 stor-4 12 4 4 0 3 �task times
G 8 9.13
(a) Theoretical minimum number of stations =
stov-5 0 8 4 10 0 stov-5 4 4 4 3 0
H 6 cycle time
Tij Dij = 478 49
substantially 60
Solution: Refrig. in Area 3 Cycle time = = 12 minutes. So minimum number of
(where sink was); Counter in longer than the (a, d) 5
Area 4 (where storage was); others so it 48
warrants special stations = = 4 stations
Sink in Area 2 (where counter 12
was); Storage in Area 1 consideration to
(where Refrig. was); Stove in ensure that a
Area 5 (no change) smooth flow can be
maintained. A
9.9 B and C should be machine
adjacent, because they have constrained task or
the most trips. Traffic is next lack of cross
heaviest between A and D, so training may
they should be adjacent. suggest that more
Continuing in this fashion, F traditional
should be adjacent to D and A assembly line
should be next to F, but the balancing
latter two have already been techniques be
placed. Finally, E should be used.
placed next to F. Thus, we are 480 minutes
(b) Cycle time = = 9.6 minu tes
left with 9.11 (a) Cycle time = (60)(60 sec) 50 units
180 PLAs (c) Theoretical minimum = �ti 49
(a) Heuristic solutions: = = 5.1 = 6 stations
number of stations cycle time 9.6
B C A D F E =47,900. 3,600
= = 20 seconds per PLA
180 Note that the theoretical
or
minimum �
(b) Theoretical minimum of workstations =
task time
could not be
A D F E B C =44,440.
achieved. cycle time
(Note: These are not (e) Total idle
60 time/cycle
the optimal solution.) = = 3
= 4 + 1 + 2 + 3 + 2 + 1 +
20
(b) Better layout: 2 = 15 min.
(c) Yes, it is feasible. Station 1 with A and C;
per cycle 60
A D F C B E =43,880.
cycles = 15 idle hours
9.10 (a) Takt time = Station 2 with B and D; and Station 3 with E. per day.
Minutes available
(f) Total idle time/day.
per day/Units
Since there are 480
demanded per day
minutes, and each
=
chair takes 8
420/25
minutes (which is
0 =
the longest
1.68
operation time),
minute
there are 480/8 = 60
s
cycles/day.
(b) Number of cross
Total idle time =
trained
15 minutes/cycle 60 cycles
employees =
(1.1 + 1.1 + 1.7 =
+ 3.1 + 1.0)/1.68 15 hours
= 8.0/1.68 =
4.76 5
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
CHAPTER 9 L AYO U T S T R AT E G I E S 123
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
124 CHAPTER 9 L AYO U T S T R AT E G I E S
400 minutes 400 minutes
Cycle time = 13 minutes
Cycle time = = 0.78
60 units (b) Theoretical Efficiency =
5 stations �3.33 minutes 60 units
= 6.67 minutes unit = 6.67 minutes unit
or Efficiency =78%
�ti 25 with a cycle time of �ti 13
Minimum number of stations = = Minimum number of stations = =
Cycle time 6.67 Cycle time 6.675
13
= 3.75 or 4 workstations 200 Actual efficiency = = 0.867 or 86.7% = 1.95 or 2 workstations
5 �3
Cycle time = = 3.33min
60
Note: Four stations with
(a) 3.33. Multiple layouts
a 7minute cycle time is
with this efficiency
possible; Efficiency
exist.
would become:
25
= 89.3% (c) Theoretical minimum number of �ti 13
4 7 = = = 3.9 �4
work stations Cycle time 3.33
but production drops to
57 from the required 60
units. One fivestation (d) Idle time = 1 (at
solution (there are station 3) + 1 (at station 5) = 2
multiple answers) is: min per boat
9.18 (a) Resolving Problem
9.17 with a
production time of 300 minutes
Cycle time =
300 minutes per 60 units
day: = 5 minutes unit
� ti 13 13 minutes
Minimum number of stations = = = 3 stations 6.67 minutes =
Efficiency
Cycle time 5
or Efficiency = 64.9%.
= 2.6, or 3 workstations
Multiple layouts with
this efficiency exist.
(c) Theoretical: 13
Actual Efficiency = = 0.722 or 72
3 �6
25 minutes
Efficiency = = 0.937 = 93.7% 9.19 The assemblyline
4 stations �6.67 minutes
activities are:
Actual: Time Ready
Task (in Predecess Tasks
25 minutes minutes) ors
Efficiency = = 0.833 �83%
5 stations �6.00 minutes A 3 None A, B
(d) Idle time = 1 + 1 + 1 B 6 None C, D, E
+ 2 = 5 min per cycle C 7 A D, E, F
D 5 A, B
9.17 Performance Time E 2 B F, G, H,
I
Task (in minutes) F 4 C
13 minutes
(b) Efficiency = G = 0.867
5 F J, H, I, K
A 1 3 stations �5 minutes
H 7 D, E
B 1
or Efficiency I 1 H K, J
C 2
=86.7%. Multiple J 6 E
D 1
layouts with this K 4 G, I, J
E 3
efficiency exist. 5
F 1
0
G 1
H 2 (c) Resolving (a, g)
I 1 Problem 9.17 with
1 a production time
3 of 400 minutes
per day:
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
CHAPTER 9 L AYO U T S T R AT E G I E S 125
Time needed per unit
(e) Efficiency =
Time allocated per unit
Total task time
=
(Cycle time) (Number of stations)
50 28 28
= Efficiency = = = 0.80
(10)(6) 5 �7 35
50
= or
60 Efficiency =80%
= .8333, or 83.33%
(f) Idle time =ime
alloca
ted
per
unit
im
e
neede
d per
unit
=60
50
=10min/cycle
(g) Best assignment is
shown in part (a)
(b) The throughput is
9.20 with the efficiency
3.75 patients per hour.
shown in part (e)
(i.e., 83.33%) (c) The bottleneck is
at the medical
Performance Time exam station—16
Task (in minutes) minutes.
A 5 (d) Paramedics are
B 3 idle 2 minutes,
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
126 CHAPTER 9 L AYO U T S T R AT E G I E S
Precedence
diagram:
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
CHAPTER 9 L AYO U T S T R AT E G I E S 127
Cottrell Bicycle10
Co. D7 72
B3 72
Longest Operation Time (b) Using a 41hour
Cottrell Bicycle Co.
11 B7 18
A2 72 Shortest Operation week:
Station Task Time 12 A3 114 Time Cottrell Bicycle C
1 K3 60
Time allocated (cyc sta) = Station Task Time Time Left
J1 66 Fewest Following Cyc
J3 3 1728; Min (theoretical) # of 1 J3 3 Tasks
2 K9 27 stations = 11 F7 21
Statio Task Time Time
G5 29 Time needed (sum task) = 1462; K3 60
n Left
K4 24 Efficiency = 84.61%; J2 22
J2 22 Idle time (allocneeded) =266 1 J3 3 144.60
F3 32 seconds per cycle K4 24 F7 21 123.60
2 K9 27 C1 78 45.60
3 E3 109 2 B5 108 39.60
Cottrell Bicycle Co. F3 32
F7 21
J1 66 3 A2 72 75.60
4 F4 92 Ranked Positional
3 G5 29 A1 52 23.60
E2 18 Weight
5 G4 79 E2 18 4 K3 60 87.60
D6 53 Station Task Time Time Left C1 78 K4 24 63.60
6 F9 126 1 K3 60 4 G4 79 K9 27 36.60
7 C1 78 J2 22 5 F4 92 J2 22 14.60
D9 37 6 D6 53 5 G4 79 68.60
8 B5 108 D9 37 J1 66 2.60
K9 27
9 D8 78 7 B5 108 6 F9 126 21.60
J3 3
A1 52 7 G5 29 118.60
F7 21 8 A1 52
10 D7 72
2 C1 78 A2 72 F4 92 26.60
A2 72
F3 32 9 E3 109 8 D6 53 94.60
11 B3 72
B7 18 K4 24 10 D8 78 D9 37 57.60
12 A3 114 3 G4 79 11 F9 126 F3 32 25.60
4 F4 92 12 D7 72 E2 18 7.60
Time allocated (cyc sta) = 9 E3 109 38.60
5 E3 109 B3 72
1728; Min (theoretical) # of 10 D7 72 75.60
6 F9 126 13 B7 18
stations = 11 11 D8 78 69.60
7 J1 66 A3 114
Time needed (sum task) = 1462; 12 B3 72 75.60
D6 53 Time allocated (cyc sta) =
Efficiency =84.61%; B7 18 57.60
8 B5 108 1872; Min (theoretical) # of
Idle time (allocneeded) = 266 13 A3 114 33.60
G5 29 stations = 11
seconds per cycle
9 E2 18 Time needed (sum task) = 1462; Time allocated (cyc sta) =
Cottrell Bicycle Co. D8 78 Efficiency = 78.10%; 1918.80; Min (theoretical) # of
Most Following Tasks D9 37 Idle time (allocneeded) =410 stations = 10
Station Task Time 10 D7 72 seconds per cycle Time needed (sum task) =
1 K3 60 B3 72 1462.00; Efficiency = 76.19%;
Summary:
J2 22 11 A1 52 Idle time (allocneeded) = 456.80
B7 18 seconds per cycle
J3 3 A2 72 Algorithm
12 A3 114 Fewest following tasks
K9 27
Time allocated (cyc sta) = Longest operation time
F3 32
1728; Min (theoretical) # of Most following tasks
2 F7 21
K4 24 stations = 11 Ranked positional weight
J1 66 Time needed (sum task) = 1462; Shortest operation time
G5 29 Efficiency = 84.61%; The longest operation
3 F4 92 Idle time (allocneeded) = 266 time, most following
E2 18 seconds per cycle
4 C1 78
tasks, and ranked
D6 53 positional weight
5 E3 109 algorithms gave equal
6 G4 79 efficiencies of 84.61%.
D9 37
7 F9 126
8 B5 108
9 D8 78
A1 52
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
128 CHAPTER 9 L AYO U T S T R AT E G I E S
Cottrell Bicycle Co. Cottrell Bicycle Co. Cottrell Bicycle Co. Cottrell Bicycle Co.
Longest Operation Ranked Positional Shortest Operation Cycle Time
Most Following
Time Weight Time Seconds
Tasks
Statio Task Time Time Left
Statio Task Time Statio Task Time Time Statio
Left Task Time
n n n
n
1 K3 60 1 K3 60 1 J3 3 144.60 K
1 K3 60
J1 66 J2 22 F7 21 123.60 K
J2 22
J3 3 K3 60 63.60 C
J3 3
2 K9 27 K9 27 J2 22 41.60 C
G5 29 J3 3 F
K9 27
K4 24 F7 21 K4 24 17.60 C
F3 32
J2 22 2 C1 78 2 K9 27 120.60 C
2 F7 21
F3 32 F3 32 F3 32 88.60 C
K4 24
K4 24 J1 66 22.60 C
J1 66
3 E3 109 3 G4 79 3 G5 29 118.60 C
G5 29
F7 21 J1 66 E2 18 100.60 C
3 F4 92
4 F4 92 4 F4 92 C1 78 22.60 F
D6 53
D6 53 D6 53 4 G4 79 68.60 F
4 C1 78
5 E3 109 5 F4 92 55.60 E
E2 18
5 G4 79 G5 29 D6 53 2.60 E
D9 37
6 F9 126 6 D9 37 110.60 E
5 E3 109
D9 37 E2 18 B5 108 2.60 E
6 G4 79
E2 18 7 B5 108 7 A1 52 95.60 E
7 F9 126
6 F9 126 D9 37 A2 72 23.60 E
8 B5 108
7 C1 78 8 D8 78 8 E3 109 38.60 F
9 D8 78
8 B5 108 A1 52 9 D8 78 69.60 F
A1 52
9 D8 78 9 D7 72 10 F9 126 21.60 D
10 D7 72
A1 52 B3 72 11 D7 72 75.60 B
B3 72
10 D7 72 10 B7 18 129.60 B3 72 3.60 B
11 B7 18
A2 72 A3 114 12 B7 18 129.60 A
A2 72
11 B3 72 11 A2 72 A3 114 15.60
12 A3 114
B7 18 Time allocated (cyc sta) =
Time allocated (cyc sta) = Time allocated (cyc sta) =
12 A3 114 1771.20; Min (theoretical) # of
1771.20; Min (theoretical) # of 1623.60; Min (theoretical) # of
stations = 10
Time allocated (cyc sta) = stations = 10 stations = 10
Time needed (sum task) =
1771.20; Min (theoretical) # of Time needed (sum task) Time needed (sum task) =
1462.00; Efficiency = 82.54%;
stations = 10 =1462.00; Efficiency =82.54%; 1462.00; Efficiency = 90.05%;
Idle time (allocneeded) = 309.20
Time needed (sum task) = Idle time (allocneeded) =309.20 Idle time (allocneeded) = 161.60
seconds per cycle
1462.00; Efficiency = 82.54%; seconds per cycle seconds per cycle
Summary:
Idle time (allocneeded) = 309.20
seconds per cycle Number of
Algorithm Workstation
Fewest following tasks 13
Longest operation time 12
Most following tasks 12
Ranked positional 11
weight
Shortest operation time 12
The ranked positional
weight algorithm gave the
highest efficiency—90.05%.
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
CHAPTER 9 L AYO U T S T R AT E G I E S 129
ADDITIONAL B 1 (b) H 6
C 4 400 minutes I 7
HOMEWORK D 1 Cycle time = = 5 minutes / u nit
J 5
80 units
PROBLEMS E 2 K 4
F 4 (c) L 15
Here are the answers to
1 9
additional homework 3 Minimum number = ti = 13 = 2.6 3 stations 7
problems that are located on of stations CT 5
our Companion Web site, at (a) & (d)
www.myomlab.com.
9.24
Current layout:
Entrance 1 Exam I 2
Lab, EKG 5 O.R. 6
Patient movement =6,700
feet
Improved layout:
Entrance 1 Exam I 2 (e)
13 minutes
Exam II 3 Xray 4 Efficiency = = 0.65 = 65%
4 stations 5 minutes
Patient movement Multiple layouts
=4,800 feet are possible.
Improved layout: 9.26 (a)
Entrance 1 Exam I 2
Exam II 3 Xray 4
Patient movement =4,700
feet
More improved layout
(with Exam rooms swapped):
Entrance 1 Exam II 3
(b) There are multiple
Exam I 2 Xray 4
alternatives. Here
Patient movement =4,500 is one that does
feet not violate any
procedures.
Note that this final
solution reflects “common Station Tasks
sense,” or the result of one’s
1 A, D
intuition. We simply allocate
2 B, G
the spaces in the order in 3 C, F
which the tasks are usually 4 H, E
performed. We usually start
at the “entrance,” proceed to (c) Each alternative
an examination room; from has an overall
the examination room, efficiency of 92.5%.
proceed for either xrays or
lab tests, then (a) leave the 9.27 Performance Time
facility, (b) go to get a cast Task (in minutes)
put on, or (c) go for surgery. A 13
B 4
9.25 Performance Time C 10
D 10
Task (in minutes) E 6
F 12
A 1
G 5
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
130 CHAPTER 9 L AYO U T S T R AT E G I E S
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.
132 CHAPTER 9 L AYO U T S T R AT E G I E S
Copyright © 2011 Pearson Education, Inc. publishing as Prentice Hall.