You are on page 1of 8

International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

Case Study on Design and Construction of Tunnel


M.S.Rahul
Undergraduate Scholar, Hyderabad

Abstract —A tunnel may be for foot or vehicular road traffic, for Canal to existing Flood Flow canal to feed Mid Mannair
rail traffic, or for irrigation purposes. Some tunnels are aqueducts Reservoir with the components such as Lined Gravity canal, CM
to supply water for consumption or for hydroelectric stations or & CD works, lifts, pressure mains and lined tunnels with all
sewers. Utility tunnels are used for routing steam, chilled water, associate civil, Hydro Mechanical & Electro Mechanical works
and electrical power. The tunnel is relatively long and narrow; in
was entrusted to “MEIL-SEW-MAYTAS-BHEL
general the length is more than twice the diameter The Dr. B.R.
Ambedkar Pranahitha Chevella Sujala Sravanthi Lift Irrigation (CONSORTIUM)”,
scheme’s objective is to irrigate 16.40 Lakh Acres of command area
in the drought prone areas of Telangana region viz., Adilabad, II. Scope of Work
Karimnagar, Medak, Nalgonda, Nizambad, Warangal and Ranga
Reddy districts of Telangana state. The scheme envisages The package starts from Kakatiya Canal @D-83 in Ragampet
construction of barrage across Pranahitha River, a major tributary (V) to existing Flood Flow canal near Shanagar (V).
of Godavari River at Tummidihetti (V) in Koutla (M) of Adilabad a. Site investigation report(s).
district and 160 TMC of water from Pranahitha River is proposed b. Brief review of Geological and Geotechnical
to be diverted to Sripada Yellampally Project from where it is
investigation.
carried to command areas through lift irrigation schemes, gravity
canals, tunnels, Modernization of tanks and reservoirs for c. Approach by Adit tunnel 8 m dia D-Shaped and 1.609
irrigation total Ayacut of 16.40 Lakh Acres and providing drinking km in length with 1 in 12 slope
water facility to villages and also providing required water to d. Twin tunnel from the Kakatiya canal @D-83 in
industries. Ragampet (V) to surge pool at lakshmipuram (v) for
about 4.133 km with 10.0 m dia and 7.5 m dia.
Keywords— Tunnel, Investigation, Excavation, Drilling, Portals, e. Underground Surge pool 350 x 20 x 56 m D-shaped.
seepage control, Grouting, Measures f. Underground Pump house 205 x 25x64 Mts with a lift of
about 109.10 Mts
I. Introduction g. Delivery cistern
The Dr.B.R.Ambedkar Pranahitha Chevella Sujala Sravanthi h. The length of Gravity Canal is 4.060 Km from delivery
Lift Irrigation Scheme (Dr.BRAPCSSLIS) is being constructed cistern to Mothevagu reservoir.
having the 22 lifts. The project envisages irrigation of about i. Foreshore of Mothevagu reservoir to Flood Flow Canal
16,40,000 acres of uplands in the six districts and the total lift length of link canal is 1.900 Km
height from the river Pranahitha at RL+150.00m to Chevella
reservoir at RL+635.00m, i.e., 493M These are carried out by III. Site Investigation
multiple stages lifting and conveying through tunnels and
gravity canals. The total length of system is divided into two
parts, length of Gravity canal and length of the Tunnel. Length
of the Gravity canal is 849 km (approx.) and Length of the
Tunnel is 206 km (approx.). The total number of lifts is 22. The
total power required for this lift is 3375 MW; estimated time for
completion is 48 Months. The entire project is divided into
several packages to facilitate execution of the work
simultaneously. There are 28 packages under this project. In this
study, analysis is done on Dr.B.R.Ambedkar Pranahitha-
Chevella Sujala Sravanthi package 8. The work of “Pranahitha
Chevella Sujala Sravanthi lift irrigation scheme-link-II-package-
08” detailed investigation, designs and execution of lift
irrigation scheme for drawl and lifting of 114.24 TMC of water
from Ragampet
(v), near Kakatiya canal, Choppadandi (M), Karimnagar District
to Mothevagu Reservoir and carrying by a gravity

ISSN: 2231-5381 http://www.ijettjournal.org Page 373


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

IV. Geological and Geotechnical Investigation soil classification, which facilitate to design of various
components of the tunnel, strata expected to encounter during
Design and construction of tunnels in rock require thought the excavation etc.
processes and procedures that are in many ways different from
other design and construction projects, because the principal D. Vertical Electrical Sounding (VES)
construction material is the rock mass itself rather than an
engineered material. Uncertainties persist in the properties of the VES is conducted along the alignment axis at 100m intervals.
rock materials and in the way the rock mass and the ground The interpreted data of the VES gives various sub-surface layer
water will behave. All these uncertainties must be overcome by thickness, its nature and depth to the massive rock.
sound –flexible design and redundancies and safeguards during
construction. The design of tunnels must involve selection or V.Tunnel Design
anticipation of method of construction. Geology plays a
dominant role in many major decisions made in designing and The layout of tunnels depend on the grade, clearance required,
construction of a t unn el. In tunnels, unlike other structures, the alignment etc. wherever possible, from the standpoint of general
ground acts not only for the loading mechanism, but as t h e alignment and cost, tunnel alignment should be straight to
primary supporting medium as w e l l . When the excavation is facilitate construction. Curved tunnels have been used on many
made, the strength of the ground keeps the excavated hole open railroad, water conveying tunnels, and highways, particularly in
until the supports are i n s t a l l e d . Even after supports are in mountainous areas. As per the geological report made available,
place, the ground pr ovi des a substantial percentage of the the entire stretch of tunnel from Km. 0.0 to Km. 4.133 passes
load-carrying capacity. Thus, for a tunnel, the rock or soil through grey and pink granites rock strata.
surrounding a tunnel is a construction material. Its engineering
characteristics are as important as those of the concrete or steel The total length of the tunnel is approximately 4133m due to
used into the aspects of the work. length of tunnel (4.133 Km), and the entry exit of the tunnel
cannot be approached without shafts or construction of Adit, it is
A. Seismicity necessary to establish a construction adit to provide two working
faces in each tunnel to complete the work in the schedule period.
According to GSHAP the state of Telangana falls in a region
with low 10 moderate seismic hazards. As per the 2002 Bureau A. Geometry of the Tunnel
of Indian Standards (BIS) map, this state also falls in zones II
and III. Historically, parts of this have experienced seismic Methods and sequence of excavation affect the loads and
activity in the M 5.0-6.0 range. The Godavari river valley, displacements, which must be resisted by initial and permanent
adjustment to the site is within the NW-SE trending faults. ground supports. The basic shape of an excavated opening must
These faults still show moderate seismicity occasionally. The be selected for practicality of construction. IS 4880 part II 1976,
Godavari graven area is in seismic zone II. In this zone an lays down general guidance in regard to shape of the various
earthquake of magnitude of 6 or intensity VIII may be expected. sections generally use in tunnels. However, the said IS code has
The earthquake of magnitude 5.3 was measured at left the choice of particular shape on designer’s judgment based
Bhadrachalam in 1969. on prevailing conditions at site. The first step in the design of a
As per IS-4880 (part-V), the tunnel lining is not designed foe tunnel is the determination of the cross section required for the
seismic force unless the tunnel crosses an active fault. In which trouble free operation.
case, some flexibility is provided at that section to all for some
movement in case of earthquake. However, at locations where These selections of the tunnel cross-section influenced by:
studies in indicate that seismic forces will be significant they o The clearances specified in view of the vehicles and
shall be catered for in the design. materials transported in the tunnel,
o Geological conditions,
B. Field Work o The method of driving the tunnel and the materials
strength of tunneling.
The site of package-8 is located in Karimnagar district of
Telangana state. Six boreholes were drilled in the alignment of D-SHAPED tunnels are best suited in ‘conventional drilling and
the proposed tunnel, varying depth of 100.0 m to 130.0 m. The blasting method of construction point of view in good rock
subsurface investigation is carried out by boreholes and electro- strata, as they have flater invert. In Pranahitha-Chevella lift
resistivity method (ERM) for suitability of the proposed site for irrigation scheme Package-8, tunnel is proposed with a 10.3m
the construction of tunnel. diameter D-Shaped Tunnel in right tube and 7.75m D-shaped
tunnel in left tube. The hydraulic loss due to the D-shape tunnel
C. Electric Restivity Method (ERM) is negligible in this case, compare with a circular tunnel of same
cross sectional area, hence we can use D-shaped tunnel as
Resistivity surveys have been conducted along the alignment of mentioned above without losing any advantage of circular
tunnel for 4.133 KM of the package-8, to assess the sub –surface tunnel.

ISSN: 2231-5381 http://www.ijettjournal.org Page 374


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

B. Shotcrete and Rock Bolt Initial  Precision Survey and setting out of the tunnel
alignment. Open excavation for portal or excavation for
As the tunnels generally passes through different types of rock shaft.
formations, it is necessary to work out alternative cross sections  Arrangement for collection of surface water and its
if the tunnel depicting other acceptable types of support systems. drainage by gravity flow or pumping.
The shotcrete in combination with rockbolt and wire mesh  Access roads to mucking areas.
provide a good and fast solution for both initial and permanent  Erecting or winching and hauling equipment.
rock supports. Being ductile it can absorb considerable  Establishments of field workshop, compressors and air
deformation before failure lines, pumps, water lines, ventilation fans and ducts,
lighting, concreting arrangements, supports erection
VI. Construction arrangements, etc.
The basic components of underground construction include the
following: D. Precision Survey
 Excavation, by blasting or by mechanical means.
 Initial ground support. The precision survey and setting out of the tunnel alignment
 Final ground support. shall consist of transferring the obligatory points like portal
Other important components of construction include the points, shaft/adit location, etc., from topographical
following: maps/detailed design drawings to the actual site of construction.
 Site preparation. This is done either by “Direct Setting Out” or by
 Surveying. “Triangulation”. In the mountainous regions it is extremely rare
 Portal preparation possibility that both the ends of the tunnel will be visible from
 Ventilation of the underground works each other and hence “Triangulation has to be invariably
 Drainage and water control adopted for setting out the alignment. The levels of the various
 Hazard prevention portals along the tunnel are fixed accurately by means of Total
 Controlling environment effects etc. Station or using “Reciprocal Leveling”.

A. Sequence of Excavation For Tunnel E. Methods of Underground Excavation

The excavation and portal of the adit tunnel is established first. The underground excavation for tunnels shall be carried out in
Main tunnel excavation for left tube and right tube is carried out conformity with IS: 5878 Part II / Section-1 or other relevant
through the adit tunnel from both face in each tunnel reference mentioned as per the tender documents Tunneling soft
simultaneously by full face or heading and benching method strata shall conform to IS: 5878 part III other relevant references
depending upon the strata encountering and the machines using mentioned as per the tender documents. The actual operations
at site. The design team should specify or approve the proposed for underground excavations may vary with the type and size of
method of excavation. This tunnel is proposed to excavate using tunnel, method of excavation, type of geological formation
conventional drill and blast method encountered, equipment available, and the overall economics.
Following are the methods commonly adopted for excavation of
B. General Procedure of Underground Excavation tunnel.

Tunnels can be driven through almost any material in nature, but 1. Full and Partial Face Advance
the methods used and costs differ radically. Thus, the method Most tunnels are advanced using full-face excavation. The entire
used in tunneling in earth, soft sediments or crushed weathered tunnel face is drilled and blasted in one round. Blast holes are
rock depends chiefly on the bridge action period of the material usually drilled to a depth somewhat shorter than the dimension
above the roof of the tunnel and the position of water table, of the opening, and the blast “pulls” a round a little shorter than
whereas the method used for tunneling through hard, intact rock the length of the blast holes. The depth pulled by typical rounds
requiring little or no supports depends upon the strength and is 2 to 4 m in depth. Partial face blasting is sometimes more
condition of rock, because of great longitudinal extent of the practical or may be required by ground conditions or equipment
work, many different kinds of conditions are encountered, which limitations.
for maximum economy should be excavated and supported
differently. 2. Full Face Attack
In this method, the entire cross-section area of the tunnel to be
C. Preliminary Works excavated is attacked simultaneously. This method is generally
recommended for small size tunnels in good rock conditions
The preliminary works required commencing the excavation of a where major rock falls are not anticipated.
tunnel consists of the following:

ISSN: 2231-5381 http://www.ijettjournal.org Page 375


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

3. Top Heading And Benching


This is the most common method, where the top part of the
tunnel is blasted first, at full width, followed by blasting of the
remaining bench. The bench can be excavated using horizontal
holes or using vertical holes similar to quarry blasting.

4. Drift Method
In driving large tunnel or tunnel in very poor strata it may be
economical to drive a small tunnel called drift or a pilot tunnel
prior to excavating the full face. Depending upon the nature of
rock and other parameters, a drift may be excavated in the
center, side, bottom or top.

In this package 8, Top Heading and Benching method is adopted


for underground tunnel excavation.

The other methods used are:

1. Cut and cover methods


2. Mechanized means such as Tunnel Boring
Machines or Continuous miners Drilling, Charging and Priming Patterns
3. Tunneling with aid of a protective shield.
Blasting Design

An important step in tunnels is Blasting. Blast design that will


produce desired rock fragmentation results and low vibration
levels. They specify explosive quantities and design borehole
drill patterns including size, depth, and spacing. These factors
vary based on the geology and location of the blast site.
Different rock types require different kinds or amounts of
explosives and different borehole spacing. Blasts are also
designed to produce fragmentation, or rock size.

Trial Blast

Trial blasting will be performed at the beginning of the works in


order to optimize blast design and drilling patterns. The
As per the geological report, this tunnel passes through sound
granite strata. Hence in this tunnel, it is proposed to execute purposed of this trial blasts is as follows:
adopting ‘conventional drilling and blasting method’ with
drilling boomers. Since the size of the tunnel is more than 8m it  Estimation of blast design parameters suitable to the
is proposed to execute the tunnel by heading and benching due site
to the bigger size of the tunnel. If any fracture zone encountered  Suitability evaluation of the approved blast design.
during the execution of the project, it is proposed to execute the  Checking the blast vibration level.
same by heading and benching with rock supports.
H. Loading Explosives and Blasting
F. Marking of Tunnel Profile
The center of the tunnel and its level is marked on the face of Explosives used in blasting are generally of emulsions type
the tunnel with the help of the precision survey instrument made of varying percentage of strength. Before loading is
before each blast and from that center line point the designed started, each hole is blown with high-pressure air jet or with
shape of the tunnel is marked on the face. water. A primer cartridge containing the detonator pointing
towards the bottom of the hole and is tamped well into the
G. Setting up and Drilling Holes bottom with the help of wooden or plastic pole. Finally, the
remainder of the hole is filled with inert material (like damp
The blast patterns shall include the following: mixture of sand and clay) and tightly clamped. The holes are
- Drilling patterns then blasted from the safe distance. Adequate safety precautions
- Charging patterns are taken during drilling and blasting operations in conformity
- Priming Pattern with IS: 4081 and other relevant guidelines.

ISSN: 2231-5381 http://www.ijettjournal.org Page 376


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

or suitable attachment. Manual scaling may not be advisable or


practical in safety point of view.
L. Removal of the Muck

The material removed as a result of blasting is loaded into


dumpers or mine cars, as the case may, and is taken out of the
tunnel. In principle, tire or crawler mounted loaders/excavators
and suitable dumpers are used for mucking operation. Removal
of muck from underground excavations shall be in conformity
with IS: 5878 Part – II/Section-2 and other tender provisions.
The excavated materials (rock, soil etc.) from the tunnel shall be
I. De-Fuming or Removal of Foul Gases by Ventilation transported to the specified dumping area. A haul road of slope
not greater than 1 in 10 shall be constructed for the hauling of
Ventilation is an important aspect, which has to be duly taken excavated muck.
care of for efficient underground excavation of the tunnel.
Adequate ventilation must be provided to make the working
space safe for workers, by keeping the air fresh and breathable,
free from harmful obnoxious gases and dust. Minimum
requirements of purity of air, dust control and volume of air are
in accordance with IS: 4756.

The tunnel can be ventilated either by blowing air in or


exhausting it out through a duct. In the blowing mode, fresh air
enters from the surface through a vent pipe to a point near the
face. This mode has advantage of constantly supplying fresh air
to work space. In exhaust mode, the foul air is exhausted
through the vent line. While this method creates a better
environment along the tunnel, any heat, moisture, dust and Dumper
smoke generated along the tunnel is delivered to the vicinity of
the face. VII. Initial Ground Reinforcement (Rock Bolts)

Initial ground reinforcement consists of; Un-tensioned rock


dowels and occasionally, tensioned rock bolts. These are
referred to as ground reinforcement, because their function is to
help the rock mass support itself and mobilize the inherent
strength of the rock as opposed to supporting the full load of the
rock. It is much more economical to reinforce the rock mass
than to support it. Rock bolt is the general term that includes
rock dowels and cable tendons. Specifically, bolts are pre
tensioned, while dowels are initially unstressed. The installation
process is simple: drill the hole insert the requisite number of
cartridges insert the steel bar with a spinning action and continue
Ventilation ducts.
spinning for about 60 seconds to ensure complete mixing.

J. Checking Misfires In these tunnels the rock bolts considered most appropriate are
reinforcing steel bars, typically 25 mm diameter, 12 tons proven
Immediately after the tunnel has been de-fumed and ventilated, capacity. For 25 mm passive bolts, holes of 32 mm to 38 mm are
the blasted face is checked carefully for any misfires. For this, required. The hole is filled from the bottom with cement
an experienced and competent Forman enters the tunnel, capsules and the bolt is inserted as per the designs. Care must be
removes the loose rock carefully from the face and makes sure taken to ensure that the hole is filled up to full depth. The bolts
that all cartridges have been fired. are threaded outside. When the grout is set, a washer plate is
placed against the rock and secured in position with a nut. When
K. Scaling The Loose Material shotcrete is used, the washer should be outside the main layer of
shotcrete.
After the checking of the misfire is over, the scaling operation
will be carried out by use of excavators with hydraulic hammer

ISSN: 2231-5381 http://www.ijettjournal.org Page 377


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

DRILLING FOR ROCK BOLTS

SURFACE PREPARATION

Good adhesion to the ground with the initial layer and good
bond between successive layers are prerequisites of good
shotcrete. This can best be accomplished with a high-pressure
combination air-water jet applied with a long jet pipe nozzle
ROCK BOLTS held relatively close to the surface.

VIII. Seepage control A. Dry-Mix Aggregate Preparation

The process of Tunneling is always disrupted with the presence When dry-mix aggregate storage is on-site, protection from the
of Ground water table in its path and also the local seepage of elements is necessary. Stock piling by size groups should
water. This is taken care by the use of Shotcrete and drilling prevent sub size segregation. For best result, an aggregate
Ground water drainage holes dampness of 3% to 6% should be maintained. Less will absorb
too much mix water; more will result in too high water cement
IX. Shotcrete ratio.

Shotcrete today plays a vital role in most of the tunnel and shaft B. The Mix
construction in rock because of its versatility, adaptability and The mix design shall be as per the IS standards. The mixing of
economy. Desirable characteristics of shotcrete include its materials shall be done using a suitable capacity batching plant.
ability to be applied immediately to freshly excavated rock Inclusion of steel fibers will require little or no change from the
surfaces and to complex shapes such as shaft and tunnel plain shotcrete mix. The principle effect will be increased. Over
intersections, enlargements, crossovers and bifurcations and the all, the mix design should keep water cement ratio and the
ability to have applied thickness and mix formulation varied to cement factor as low as possible and the coarse aggregate
suit variations in ground behavior. fraction as large as practicable.

Shotcrete is not just “pneumatically applied concrete”. Although C. Nozzle


the basic materials (cement, aggregate, water) are the same and
meet the same Indian Standards, additives (e.g.: accelerators, The best shotcrete “on the wall” is produced when the nozzle is
micro silica and steel fibers) change its character to make kept within 3 to 5 feet of the surface being shot and
shotcrete unique and usable in quite a different fashion than perpendicular to the surface or within 15 degrees of the same.
concrete. Deviation from this will result in less compaction and more
rebound. Considering the particles in shotcrete stream is
In this package 8, Wet mix procedure has been adopted. The wet travelling at 170 to 340 mph. In package 8, a remotely controlled
mix process consists of mixing measured quantities of nozzle at the end of a long bottom has been adopted.
aggregates, cement, and water and introducing the resulting mix
into a vessel for discharge pneumatically or mechanically D. Curing
through a hose to final delivery from a nozzle. It has the
advantage of rigidly controlling the water/cement ratio of the Curing of the shotcrete shall be taken up by spraying water jet
product. Existing equipment can handle maximum aggregate on the surface.
size of 3/4 inches.
X. Backfill Concrete
On tunnel supports and tunnel lining respectively, the job of the
tunnel support or tunnel lining does not end with the
installations of a support system (steel ribs, rock bolts, shotcrete)

ISSN: 2231-5381 http://www.ijettjournal.org Page 378


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

and provision of lining. It is necessary to backfill the space XII. Tunnel Lining
between the support system and the excavated surface, for
arresting the displacements and movement of the strata around The lining of the tunnel will be taken up when the excavation of
an excavated and supported system and the excavated surface. the tunnel, has been completed. Keeping in view that three faces
The back filling is done by means of placing tightly packed M20 are available for concreting it is proposed to use three
concrete behind the supports. conveniently designed shutters for lining of the tunnel to
complete the lining as per the Construction Schedule. In the
XI. Grouting sections, where excavations of benching of tunnel are
completed, shall be concreted with the help of specially
In order to ensure complete of concrete lining and the rock designed shutters for overt and sidewall. The shutters will be
behind it, contact grouting with cement grout will be done after 10.5 to 12.5 meter long, which will enable the concrete lining of
the lining concrete has matured for at least twenty-one days (21). whole overt section of 10 to 12 meter length in one go. These
shutters give an average lining progress of 150
Grouting in tunnels is of two types: meter/month/shutter.

A. Back fill or contact grouting


B. Pressure grouting or consolidation grouting

A. Contact Grouting The main purpose of contact grouting


is that it fills up all voids and cavities between the
concrete lining and the rock. Contact grouting also
known as low pressure grouting or back fill grouting.
Back fill grouting shall be done at a pressure not
exceeding 5 kg/cm2 and shall be considered as a part of
concreting. The normal varies from 2 kg/cm2 to
5kg/cm2. It shall be done throughout the length of the Tunnel Lining
concrete lining not earlier than 21 days after placement
after the concrete in the lining has cooled off. A concrete pump of 30 cum capacity or equivalent shall
accomplish the Placements of concrete behind the shutter. The
B. Pressure Grouting or Consolidation Grouting concrete shall be produced by suitable capacity concrete batch
plant installed at the entrance and adit of the tunnel.
In the conventional drilling and blasting method of tunnel
excavation and blasting method of tunnel excavation, the rock XIII. Ground Water Drainage Holes
around the cavity gets shattered to a certain depth depending
upon the depth of blast holes and type of rock. The aim of As per IS: 4880 (Part V)-1972 drainage holes may often provide
consolidation grouting is to consolidate the shattered rock by in other than water conveying tunnels to relieve external
filling up the joints and discontinuities in the rock, which got pressure, if any, caused by seepage along the outside of the
opened out during blasting operations. As a result of pressure tunnel lining. It is recommended that drainage holes may be
grouting, the rock quality gets improved thus increasing the spaced at 3m centers, at intermediate locations between the
resistance of the rock to carry internal water passage. The grout rings. At successive sections, one vertical hole may be
consolidation grouting is done after back fill grouting is drilled near the crown alternating with two drilled holes, one in
completed in a length of at least 60 m ahead of the point of each side wall. Drainage holes extend to a minimum of 15cm
grouting. Pressure grouting shall be done all around the cavity beyond the back of the lining or grouted zone. Since this is a
and for a uniform radial distance equal to least 0.75 times the water-conveying tunnel and the ground water table is below the
finished diameter of tunnel from the finished concrete face. The tunnel bed level, it is proposed not to provide any water drainage
normal range of pressure grouting shall be 7 to 10 kg/cm 2. hole
Process of Grouting
XIV. Safety Measures

Safety is of utmost importance during the construction of


Testing of
Cleaning grouted tunnels. Provision of Helmets, Masks and Work wear is
Drilling and Grouting zone for
holes washing
Testing
holes efficancy mandatory for the work force
holes
holes of
grouting

ISSN: 2231-5381 http://www.ijettjournal.org Page 379


International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014

REFERENCES

Code Books

o IS 4880:1972

Part I General design

Part II Geometric design

Part III Hydraulic design

Part IV Structural design of concrete lining in rock

Part V Structural design of concrete lining in soft strata and


soils

o IS 5878:1971

XV. Conclusion Part I Precision survey and setting out


The tunnel carries water from Pranahitha-Chevella Tank through
tunnels. This enables us to lift water from lower region to higher Part II Underground excavation in rock
region through hydraulic pumps and drop the water in gravity  Section I: Drilling and blasting.
canals from which the water is distributed to the irrigated lands.  Section II: Ventilation, lighting, mucking and
Our project is Study of the construction of tunnels that are a sub- dewatering.
part of the PCLIS, which is package-8 situated at Laxmipur,  Section III: Tunneling method for steeply inclined
RamaduguMandal. The use of tunnel irrigation reduces the need tunnels, shafts and underground powerhouses.
of LAND ACQISTION, which usually takes up most of the
allotted budget to the project. The tunnels also have a low Part III Underground excavation in soft strata
Operation and Maintenance of them. It is both effective and
economical with use of Tunnel system. Part IV Tunnel supports

The project has Twin D-shaped tunnels of diameter more than Part V Concrete lining
10.0m; in such case a pilot tunnel is excavated first followed by
slashing on both the sides of the pilot tunnel.  Introduction to Tunnel Construction
By David Chapman, Nicole Metje, Alfred Stärk
A. Concrete Lining is provided depending upon the rock  Design of Reinforced Concrete Structures
class encountered during the excavation, in the By S.Ramamrutham.
following way:

Class I- No rock supports are required, but as per agreement


provisions 500mm M20 plain cement concrete lining is
provided.
Class II- No support is required except spot bolt at some points
and also as per agreement 500mm M20 plain cement concrete
lining is provided.
Class III- Initial rock support shall take the entire load and there
is no need of final concrete lining. As per agreement 500mm
M20 plain cement concrete lining is provided.
Class IV- Initial ground support shall be provided with 50mm
thick shotcrete immediately after excavation with steel supports,
lagging, backfill concrete and grouting.
Class V- Initial ground support shall be provided with 100mm
thick shotcrete immediately after excavation with steel supports,
lagging, backfill concrete and grouting.

ISSN: 2231-5381 http://www.ijettjournal.org Page 380

You might also like