ID WBS Task Name Duration 04

Start
Dec '17 08 Jan '18 12 Feb '18 19 Mar '18 23 Apr '18 28 May '18
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
1 A Start 0 hrs Mon 01/01/18 01/01
2 B Planning of Oil Palm replantation is made 0.5 days Mon 01/01/18
3 C Collect form from MPOB and complete the form 1 day Mon 01/01/18
4 D MPOB form is submitted and seedling subsidi form is submitted as well 1 day Tue 02/01/18

5 E Official visit by officer from Malaysia Palm Oil Board to inspect the land. 7 days Wed 03/01/18
Visit done after one week from submission
6 F Approval received from MPOB and Land Department to proceed with tree 1 day Fri 12/01/18
cutting and replanting.
7 G Machineries mobilized at site. ( Lorry, bulldozer, chainsaw) 2 days Mon 15/01/18
8 H Order for young oil palm tree made to authorized planter 7 days Mon 15/01/18
9 I Tree cutting is started from one end 21 days Wed 17/01/18
10 J Top soil which has many debris is exported outside of the area 5 days Thu 15/02/18
11 K Surveyor does land measurement to determine the actual borders of the 3 days Thu 15/02/18
land that correponds to the municipal council's designation
12 L Additional soil is imported to introduce new fertile soil 5 days Thu 22/02/18
13 M Irrigation cannal and drainage system are improved if neccesary 5 days Thu 01/03/18
14 N Access roads are repaired or prepared if necessary 5 days Thu 01/03/18
15 O New fencing are installed to keep wild animals and intruders away 3 days Thu 08/03/18
16 P Young sapling trees are brought from the approved contractors 3 days Thu 08/03/18
17 Q Using surveyor and a planner the optimum distance from each tree is 3 days Thu 08/03/18
calculated and marked
18 R Soil is dug to be prepared to receive new tree 5 days Tue 13/03/18
19 S Trees are planted 3 wks Tue 20/03/18
20 T Fertilizer are applied 2 days Tue 10/04/18
21 U Finish 0 hrs Thu 12/04/18 12/04

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Critical
Date: Tue 02/01/18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress