Professional Documents
Culture Documents
building construction
N. Minea, S.H. Waib, T.C. Limc and W. Kangd
ab
Faculty of Engineering and Green Technology, University of Tunku Abdul Rahman, Malaysia
c
(retired) Faculty of Engineering and Green Technology, University of Tunku Abdul Rahman, Malaysia
d
Faculty of Environmental Engineering, The University of Kitakyushu, Japan
E-mail: naoto@utar.edu.my, waish@utar.edu.my, bobbylim08@yahoo.com, kang@kitakyu-u.ac.jp
Table 5. Results of multiple regression analysis between project characteristics and total man-hours
Independent Average Average
Constr. Storey Formwork
Variable quantity
Cycle time age of experience
floor area height of workers
Item workers
Constructed floor area 1.000
Partial correlation
Manhours (man-minute/story)
Table 6. Results of regression analysis between work 10
quantity and man-hour A
O
L
Correlation Variance
Process Proportion C G
coefficient ration1)
F M
Marking 0.096 0.009 0.10
5
Pre-fabrication 0.444 0.197 2.70 H D y = -1.65 ×10 4 + 44.92X
E
Hoisting 0.891 0.794 50.20** I B ( r = 0.990 )
Transportation 0.866 0.750 39.00** N
Column 0.948 0.899 116.08**
Erection
Table 7 shows the results of a statistical analysis of The multiple correlation coefficient is 0.988. This
the unit requirement for each process. The coefficient of illustrates that collectively the independent variables are
variation of unit requirement for the erection processes excellent predictors of the unit requirement as
are relatively low, from 0.26 to 0.47, while others are dependent variable. As for the partial correlation
from 0.45 to 0.83. coefficients between unit requirement and the
independent variables, notably: (1) constructed floor
60 area is correlated at 0.779; (2) (storey
K
height×constructed floor area) is correlated at 0.746;
and (3) (formwork quantity×constructed floor area) at -
Unit requirement (man-minutes/m2 )
J
50 A 0.724. These correlations are the largest. The
L
relationship between constructed floor area and unit
H requirement is shown in Figure 6. The unit requirement
C
40 E O G increases according to increase of constructed floor
F areas. As the work area increases, movement of workers
B
N and transportation distance increase which lower the
D M
30 work efficiency.
y = 29.8+0.018X Figure 7 shows the relationship between (storey
I ( r = 0.779 )
height × constructed floor area) and unit requirement.
20 There is a positive (should be negative) correlation
0 500 1000 1500 2000 between these variables This also results from a larger
Constructed f loor area ( m 2 /story )
work area, but also because the difficulty of work
Figure 6. Relationship between constructed floor area
increases as storey height increases.
and unit requirement
5.3.3 Unit requirement for each building element
5.3.2 Relationship between project characteristics
and unit requirement Considering the maximum, minimum, and mean
values shown in Table 7 and from the viewpoint of
Taking unit requirement as the dependent variable, building elements, the unit requirement for slab erection
multiple regression analysis was performed on the is comparatively small relative to other building
relationship between the usual six independent variables elements. To verify the difference in the mean values of
and the additional three variables such as (i) formwork unit requirement among building elements, the analysis
quantity / constructed floor area, (ii) storey of variance was conducted. Table 9 shows the results.
height×constructed floor area, and (iii) formwork As shown in the Table 9, there is a significant difference
quantity / (storey height×constructed floor area). The between the unit requirement among building elements
results of the analysis are shown in Table 8.
at 1% level of significance. Furthermore, to verify the (storey height×constructed floor area) are similarly
difference in the mean values for unit requirement for excellent predictors of unit requirement as dependent
other building elements except for slab, the analysis of variable.
variance was conducted. Table 10 shows the results. As
shown in the Table, no significant difference was Acknowledgement
obtained at 1% level of significance.
60 We would like to express our gratitude to Mr Ando
K
y = 65.80 - 28.53X
and his colleagues at Shimizu Corporation Ltd. who
carried out the project site observations .
Unit requirement (man-minute/m2)
( r = 0.724 )
J
50
A References
H L
O
C [1] Moselhi, O. and Khan, Z. Analysis of labour
40 E productivity of formwork operations in building
G
B F construction, Construction Innovation, 10 (3): 286
N – 303, 2010 construction, Construction Innovation,
M
30
D 10 (3): 286 – 303, 2010
I [2] Narita, M. Measuring the time on formwork
erection work in a building project, In Proceedings
20 of Architectural Institute of Japan Annual Meeting,
0.4 0.6 0.8 1.0 1.2 1.4 1.6 301-302, Hokkaido, Japan, 1969
Quantity of f ormwork (m-1 )
Story height×Constructed f loor area [3] Thomas, H. R. and Zavrski, I. Construction
Baseline Productivity: Theory and Practice, Journal
Figure 7 Relationship between formwork of Construction Engineering and Management, 125
quantity/(storey height × constructed floor area) and (5): 295-303, 1999
unit requirement [4] Portas, J. and Rizk, S. A. Neural Network Model
for Estimating Construction Productivity. Journal
of Construction Engineering and Management, 123
Table 9. Results of analysis of variance (mean value of (4): 399-410, 1997
unit requirement for each building element)
Sum of Degree of Variance
[5] Sonmez, R. and Rowings, J. E. Construction
sequences freedom
Variance
ratio 1) Labour Productivity Modeling with Neural
Networks. Journal of Construction Engineering
Between subgroup 2,199 4 549.8 65.3**
and Management, 124(6): 498–504, 1998
Within subgroup 5,893 70 84.2
TOTAL 8,092 74 [6] Elazounil, A. M., Ali, A. E. and , Abdel-Razek, R.
Note 1) **: Significance level 1% significant H. Estimating the Acceptability of New Formwork
Systems Using Neural Networks. Journal of
Table. 10. Analysis of variance results excluding slab Construction Engineering and Management, 131(1):
(mean value of unit requirement for each element) 33–41, 2005
Sum of Degree of Variance
sequences freedom
Variance
ratio
[7] Song, L. and AbouRizk, S. M. Measuring and
Between subgroup 398 3 132.5 1.36
Modeling Labour Productivity Using Historical
Data. Journal of Construction Engineering and
Within subgroup 5,469 56 97.7 Management, 134 (10): 786-794, 2008
TOTAL 5,867 59
[8] Dikmena, S. U. and Sonmezb, M. An Artificial
Neural Networks Model for the Estimation of
6 Conclusion Formwork. Journal of Civil Engineering and
Management, 17 (3): 340-347, 2011
The paper has demonstrated a methodology to
predict man-hours and unit requirement related to [9] EBAWE home page. Lattice girder floor. On-line:
formwork construction on project sites. Selected project http://www.ebawe.de/en/anwendungen/elementdec
characteristics such as constructed floor area, storey ke/index.php?pageid=, Accessed: 17/12/ 2014.
height, formwork quantity, cycle time, average age of [10] Okamoto construction Co. Ltd. On-line. Formwork
workers and experience of workers have been shown to construction. On-line:http://www.okamoto-
have strong predictive power of man-hours as co.jp/construction/FormWork-construction.html,
dependent variable. The foregoing six project Accessed: 10/11/2014.
characteristics together with additional three variables [11]Thomas H. R., Mathews C. T. and Ward J. G.
such formwork quantity / constructed floor area, (storey Learning Curve Models of Construction
height×constructed floor area), and formwork quantity / Productivity. Journal of Construction Engineering
and Management, 112 (2): 245–258, 1986