Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks

1 SUPER STRUCTURE (GROUDN


FLOOR)
1.1 EARTHWORK
Site clearance & Lay-out / Setting 4,032.00 sft.
out of the Building.
1 4,032.00 sft. 4,032.00
Earthwork in excavation 9,183.45 cft.
Foundation
F1 19 4.50 4.50 5.00 1,923.75
F2 15 5.00 5.00 5.00 1,875.00
F3 12 5.50 5.50 5.00 1,815.00
CF1 2 5.00 6.25 5.00 312.50
CF2 1 5.75 4.50 5.00 129.38
49
Foundation Beam
Along Grid 7-7 1 75.00 2.00 3.17 475.00
Along Grid 6-6 1 70.75 2.00 3.17 448.56
Along Grid 5-5 1 74.25 2.00 3.17 470.75
Along Grid 4-4 1 11.25 2.00 3.17 71.33
Along Grid 3-3 1 11.25 2.00 3.17 71.33
Along Grid 2-2 1 11.25 2.00 3.17 71.33
Along Grid 1-1 1 11.25 2.00 3.17 71.33
Along Grid A-A 1 12.33 2.00 3.17 78.19
Along Grid B-B 1 11.25 2.00 3.17 71.33
Along Grid C-C 1 11.25 2.00 3.17 71.33
Along Grid D-D 1 11.25 2.00 3.17 71.33
Along Grid E-E 1 11.25 2.00 3.17 71.33
Along Grid F-F 1 11.25 2.00 3.17 71.33
Along Grid G-G 1 11.25 2.00 3.17 71.33
Along Grid H-H 1 11.25 2.00 3.17 71.33
Along Grid I-I 1 11.75 2.00 3.17 74.50
Along Grid J-J 1 11.75 1.63 3.17 60.53
Along Grid K-K 1 11.75 1.63 3.17 60.53
Along Grid L-L 1 29.75 2.00 3.17 188.62
Along Grid M-M 1 37.00 2.00 3.17 234.58
Along Grid N-N 1 39.75 2.00 3.17 252.02
Earthwork in Filling 11,415.87 cft.

60%of
Foundation pits 1 5,510.07 5,510.07 excava
tion

Classrooms 1 1,994.23 1.58 3,150.88


Balcony 1 1,263.74 1.58 1,996.71
Toilet 1 273.42 1.58 432.00
Staircase lobby 1 206.45 1.58 326.19
2 CONCRETE WORK
2.1 Lean Concrete P.C.C. 302.78 cft.

Providiing, laying, compacting and


curing plain cement concrete M10
(1:3:6) in foundation with cement,
sand and stone ballast 20mm
gauge finishing to approved level,
lines and dimensions all complete
as per drawings, specifications
and instruction of site engineer.

Foundation
Pumori Engineering Services (Pvt.) Ltd. 1 of 89
Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
F1 19 4.50 4.50 0.25 96.1875
F2 15 5.00 5.00 0.25 93.75
F3 12 5.50 5.50 0.25 90.75
CF1 2 5.00 6.25 0.25 15.625
CF2 1 4.50 5.75 0.25 6.46875

Providiing, laying, compacting and


curing plain cement concrete M15
(1:2:4) in foundation with cement,
sand and stone ballast 20mm 934.46 cft.
gauge finishing to approved level,
lines and dimensions all complete
as per drawings, specifications
and instruction of site engineer.

Classrooms 1 1,994.23 sft 0.25 498.56


Balcony 1 1,263.74 sft 0.25 315.94
Toilet 1 273.42 sft 0.25 68.36
Staircase lobby 1 206.45 sft 0.25 51.61
2.2 P.C.C. for R.C.C
2.2.1 P.C.C. for R.C.C (M20) 5,439.49 cft.
Foundations
F1 19 16.87 8.71 486.03
F2 15 20.83 10.75 473.66
F3 12 25.20 13.04 458.89
CF1 2 57.28 114.56
CF2 1 47.43 47.43
Foundation Beam&Plinth Beam
Along Grid 7-7 2 118.75 0.75 0.75 133.59
Along Grid 6-6 2 118.75 0.75 0.75 133.59
Along Grid 5-5 2 120.50 0.75 0.75 135.56
Along Grid 4-4 2 19.58 0.75 0.75 22.03
Along Grid 3-3 2 19.58 0.75 0.75 22.03
Along Grid 2-2 2 19.58 0.75 0.75 22.03
Along Grid 1-1 2 19.58 0.75 0.75 22.03
Along Grid A-A 2 19.58 0.75 0.75 22.03
Along Grid B-B 2 19.58 0.75 0.75 22.03
Along Grid C-C 2 19.58 0.75 0.75 22.03
Along Grid D-D 2 19.58 0.75 0.75 22.03
Along Grid E-E 2 19.58 0.75 0.75 22.03
Along Grid F-F 2 19.58 0.75 0.75 22.03
Along Grid G-G 2 19.58 0.75 0.75 22.03
Along Grid H-H 2 19.58 0.75 0.75 22.03
Along Grid I-I 2 19.58 0.75 0.75 22.03
Along Grid J-J 2 19.58 0.75 0.75 22.03
Along Grid K-K 2 19.58 0.75 0.75 22.03
Along Grid L-L 2 44.75 0.75 0.75 50.34
Along Grid M-M 2 63.25 0.75 0.75 71.16
Along Grid N-N 2 63.25 0.75 0.75 71.16
First Floor Slab 1 4,299.56 sft. 0.42 1,791.48

Pumori Engineering Services (Pvt.) Ltd. 2 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
First Floor Beam
Along Grid 7-7 1 118.75 0.75 0.75 66.80
Along Grid 6-6 1 118.75 0.75 0.75 66.80
Along Grid 5-5 1 120.50 0.75 0.75 67.78
Along Grid 4-4 1 19.58 0.75 0.75 11.02
Along Grid 3-3 1 19.58 0.75 0.75 11.02
Along Grid 2-2 1 19.58 0.75 0.75 11.02
Along Grid 1-1 1 19.58 0.75 0.75 11.02
Along Grid A-A 1 19.58 0.75 0.75 11.02
Along Grid B-B 1 19.58 0.75 0.75 11.02
Along Grid C-C 1 19.58 0.75 0.75 11.02
Along Grid D-D 1 19.58 0.75 0.75 11.02
Along Grid E-E 1 19.58 0.75 0.75 11.02
Along Grid F-F 1 19.58 0.75 0.75 11.02
Along Grid G-G 1 19.58 0.75 0.75 11.02
Along Grid H-H 1 19.58 0.75 0.75 11.02
Along Grid I-I 1 19.58 0.75 0.75 11.02
Along Grid J-J 1 19.58 0.75 0.75 11.02
Along Grid K-K 1 19.58 0.75 0.75 11.02
Along Grid L-L 1 44.75 0.75 0.75 25.17
Along Grid M-M 1 63.25 0.75 0.75 35.58
Along Grid N-N 1 63.25 0.75 0.75 35.58
Staircase
First Flight
Waist slab 1 5.08 5.08 0.42 10.75
Steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Second flight
Waist slab 1 6.10 5.17 0.42 13.25
steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Third Flight
Waist slab 1 5.08 5.17 0.42 11.04
Steps 5 Area= 0.19 5.17 4.91
Sill and Lintel Band
W(6) 24 7.00 0.75 0.42 105.84
W(3) 4 4.00 0.75 0.42 10.08
V(3) 5 4.00 0.75 0.42 12.60
V(2.5) 1 3.50 0.75 0.42 2.21
D(3) 6 4.00 0.75 0.42 7.56
D(2.5) 8 3.50 0.75 0.42 8.82
Entry stairs
Waist slab 7 9.50 0.42 27.93
Steps 2 0.19 4.75 12.64
Columns
Column(12"X12") 36 1.00 1.00 9.33 335.88
Column(9"X9") 16 0.75 0.75 9.33 83.97
52

Pumori Engineering Services (Pvt.) Ltd. 3 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
3 Formwork 12,181.80 sft.
Foundation 874.87 sft.
F1 19 4.50 4.50 0.83 285.00
F2 15 5.00 5.00 0.83 250.00
F3 12 5.50 5.50 0.83 220.00
CF1 2 5.00 6.25 1.83 82.35
CF2 1 4.50 5.75 1.83 37.52
Foundation & Plinth Beam 3,703.50 sft.
Along Grid 7-7 2 118.75 0.75 3.00 534.38
Along Grid 6-6 2 118.75 0.75 3.00 534.38
Along Grid 5-5 2 120.50 0.75 3.00 542.25
Along Grid 4-4 2 19.58 0.75 3.00 88.13
Along Grid 3-3 2 19.58 0.75 3.00 88.13
Along Grid 2-2 2 19.58 0.75 3.00 88.13
Along Grid 1-1 2 19.58 0.75 3.00 88.13
Along Grid A-A 2 19.58 0.75 3.00 88.13
Along Grid B-B 2 19.58 0.75 3.00 88.13
Along Grid C-C 2 19.58 0.75 3.00 88.13
Along Grid D-D 2 19.58 0.75 3.00 88.13
Along Grid E-E 2 19.58 0.75 3.00 88.13
Along Grid F-F 2 19.58 0.75 3.00 88.13
Along Grid G-G 2 19.58 0.75 3.00 88.13
Along Grid H-H 2 19.58 0.75 3.00 88.13
Along Grid I-I 2 19.58 0.75 3.00 88.13
Along Grid J-J 2 19.58 0.75 3.00 88.13
Along Grid K-K 2 19.58 0.75 3.00 88.13
Along Grid L-L 2 44.75 0.75 3.00 201.38
Along Grid M-M 2 63.25 0.75 3.00 284.63
Along Grid N-N 2 63.25 0.75 3.00 284.63
First floor beam sft.
Along Grid 7-7 1 118.75 0.75 2.00 178.13
Along Grid 6-6 1 118.75 0.75 2.00 178.13
Along Grid 5-5 1 120.50 0.75 2.00 180.75
Along Grid 4-4 1 19.58 0.75 2.00 29.38
Along Grid 3-3 1 19.58 0.75 2.00 29.38
Along Grid 2-2 1 19.58 0.75 2.00 29.38
Along Grid 1-1 1 19.58 0.75 2.00 29.38
Along Grid A-A 1 19.58 0.75 2.00 29.38
Along Grid B-B 1 19.58 0.75 2.00 29.38
Along Grid C-C 1 19.58 0.75 2.00 29.38
Along Grid D-D 1 19.58 0.75 2.00 29.38
Along Grid E-E 1 19.58 0.75 2.00 29.38
Along Grid F-F 1 19.58 0.75 2.00 29.38
Along Grid G-G 1 19.58 0.75 2.00 29.38
Along Grid H-H 1 19.58 0.75 2.00 29.38
Along Grid I-I 1 19.58 0.75 2.00 29.38
Along Grid J-J 1 19.58 0.75 2.00 29.38
Along Grid K-K 1 19.58 0.75 2.00 29.38
Along Grid L-L 1 44.75 0.75 2.00 67.13
Along Grid M-M 1 63.25 0.75 2.00 94.88
Along Grid N-N 1 63.25 0.75 2.00 94.88

Pumori Engineering Services (Pvt.) Ltd. 4 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
First Floor Slab 1 3,901.43 sft. 3,901.43
slab peripheri 1 357.00 0.42 149.94
Staircase
First Flight
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
1 10.16 0.42 4.27
Second flight -
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
Third Flight
Waist slab 1 5.08 5.08 25.82
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Columns
Column(12"X12") 36 1.00 4.00 9.33 1,343.52
Column(9"X9") 16 0.75 4.00 9.33 447.84
Lintel & sill
W(6) 24 7.00 0.42 2.00 141.12
W(3) 4 4.00 0.42 2.00 13.44
V(3) 5 4.00 0.42 2.00 16.80
V(2.5) 1 3.50 0.42 2.00 2.94
D(3) 6 4.00 0.42 2.00 20.16
D(2.5) 8 3.50 0.42 2.00 23.52
Entry stairs
7 Area= 9.50 sft 66.50
Steps 2 6.00 0.58 7.00 48.72
4 Reinforcement Bars - TMT 29.83 MT
5 BRICK WORK
5.1 9" Wall(Stone Masonry) 4,845.94 cft.
Between Foundation tie & plinth tie 2,160.38 cft.
Along Grid 7-7 1 118.75 0.75 3.50 311.72
Along Grid 6-6 1 118.75 0.75 3.50 311.72
Along Grid 5-5 1 120.50 0.75 3.50 316.31
Along Grid 4-4 1 19.58 0.75 3.50 51.41
Along Grid 3-3 1 19.58 0.75 3.50 51.41
Along Grid 2-2 1 19.58 0.75 3.50 51.41
Along Grid 1-1 1 19.58 0.75 3.50 51.41
Along Grid A-A 1 19.58 0.75 3.50 51.41
Along Grid B-B 1 19.58 0.75 3.50 51.41
Along Grid C-C 1 19.58 0.75 3.50 51.41
Along Grid D-D 1 19.58 0.75 3.50 51.41
Along Grid E-E 1 19.58 0.75 3.50 51.41
Along Grid F-F 1 19.58 0.75 3.50 51.41
Along Grid G-G 1 19.58 0.75 3.50 51.41
Along Grid H-H 1 19.58 0.75 3.50 51.41
Along Grid I-I 1 19.58 0.75 3.50 51.41
Along Grid J-J 1 19.58 0.75 3.50 51.41
Along Grid K-K 1 19.58 0.75 3.50 51.41
Along Grid L-L 1 44.75 0.75 3.50 117.47
Along Grid M-M 1 63.25 0.75 3.50 166.03
Along Grid N-N 1 63.25 0.75 3.50 166.03

Pumori Engineering Services (Pvt.) Ltd. 5 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
From plinth to First floor 2,685.57 cft.
Along Grid 7-7 1 118.75 0.75 9.33 830.95
Along Grid 6-6 1 118.75 0.75 9.33 830.95
Along Grid 5-5 1 13.75 0.75 9.33 96.22
Along Grid 4-4 0 13.75 0.75 9.33 -
Along Grid 3-3 1 13.75 0.75 9.33 96.22
Along Grid 2-2 0 13.75 0.75 9.33 -
Along Grid 1-1 1 13.75 0.75 9.33 96.22
Along Grid A-A 1 13.75 0.75 9.33 96.22
Along Grid C-C 1 13.75 0.75 9.33 96.22
Along Grid E-E 1 13.75 0.75 9.33 96.22
Along Grid G-G 1 13.75 0.75 9.33 96.22
Along Grid I-I 1 13.75 0.75 9.33 96.22
Along Grid J-J 1 13.75 0.75 9.33 96.22
Along Grid K-K 1 13.75 0.75 9.33 96.22
Along Grid M-M 1 61.75 0.75 9.33 432.10
Along Grid N-N 1 61.75 0.75 9.33 432.10
Deduction for opening
W(6) 24 6.00 5.00 0.75 540.00
W(3) 4 3.00 13.00 0.75 117.00
V(3) 5 3.00 2.50 0.75 28.13
V(2.5) 1 2.50 2.50 0.75 4.69
D(3) 6 3.00 7.00 0.75 94.50
Opening(3.5) 1 3.50 7.00 0.75 18.38
5.2 Half Brickwork 1 63.92 9.33 596.37 456.37 sft
Deduction of opening
D(2.5) 8 7.00 2.50 140.00
6 DOORS/WINDOWS
6.1 Chaukhat 78.79 cft
D(3) 6 7.00 3.00 8.42
D(2.5) 8 7.00 2.50 10.89
W(6) 24 6.00 5.00 43.56
W(3) 4 3.00 13.00 10.56
V(3) 5 3.00 2.50 4.54
V(2.5) 1 2.50 2.50 0.83
6.2 Providing, making & fixing 38mm
thick water proof flush door
shutter including hinges , tower
bolts , approved good quality
mortise lock, door stopper and 266.00 sft
other accessories as per design
drawings, specifications &
instructions of engineer.
D(3) 6 3.00 7.00 126.00
D(2.5) 8 2.50 7.00 140.00
6.3

Providing, making & fixing 38mm


thick glazed window shutter with
5mm thk. Tinted glass including
hinges , tower bolts,eye-hooks 919.75 sft
and other accessories as per
design drawings, specifications &
instructions of engineer.

W(6) 24 6.00 5.00 720.00


W(3) 4 3.00 13.00 156.00
V(3) 5 3.00 2.50 37.50
V(2.5) 1 2.50 2.50 6.25

Pumori Engineering Services (Pvt.) Ltd. 6 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
6.4 Providing, making & fixing 4.5 x
20mm MS grill with accessories as
per design drawings, 919.75 sft
specifications & instructions of
engineer.
7 FLOORING WORK
7.1 Screeding 3,737.84 sft.
Classrooms 1 1,994.23 sft 1,994.23
balcony 1 1,263.74 sft 1,263.74
toilet 1 273.42 sft 273.42
staircase lobby 1 206.45 sft 206.45
7.2 Punning 3,464.42 sft
Classrooms 1 1,994.23 sft 1,994.23
balcony 1 1,263.74 sft 1,263.74
staircase lobby 1 206.45 sft 206.45
7.3 Tiles for bathroom floor 1 273.42 sft 273.42 273.42 sft
7.4 Dado tiles 1 147.75 5.00 738.75 738.75 sft 5'ht
8 PLASTERING WORK
8.1 Plaster Work 1:5 on Wall 7,476.56 sft.
Wall Surfaces
9"wall 2 Area= 3264.5639 6,529.13
5"wall 2 Area= 473.7181 947.44
8.2 Plaster Work 1:3 on Concrete 5,446.50 sft.
Surface
Slab 1 Area= 4,032.00 4,032.00
Beam
Along Grid 7-7 2 118.75 0.75 178.13
Along Grid 6-6 2 118.75 0.75 178.13
Along Grid 5-5 2 120.50 0.75 180.75
Along Grid 4-4 2 19.58 0.75 29.38
Along Grid 3-3 2 19.58 0.75 29.38
Along Grid 2-2 2 19.58 0.75 29.38
Along Grid 1-1 2 19.58 0.75 29.38
Along Grid A-A 2 19.58 0.75 29.38
Along Grid B-B 2 19.58 0.75 29.38
Along Grid C-C 2 19.58 0.75 29.38
Along Grid D-D 2 19.58 0.75 29.38
Along Grid E-E 2 19.58 0.75 29.38
Along Grid F-F 2 19.58 0.75 29.38
Along Grid G-G 2 19.58 0.75 29.38
Along Grid H-H 2 19.58 0.75 29.38
Along Grid I-I 2 19.58 0.75 29.38
Along Grid J-J 2 19.58 0.75 29.38
Along Grid K-K 2 19.58 0.75 29.38
Along Grid L-L 2 44.75 0.75 67.13
Along Grid M-M 2 63.25 0.75 94.88
Along Grid N-N 2 63.25 0.75 94.88

Pumori Engineering Services (Pvt.) Ltd. 7 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity T. QTY' Unit Rmks
Columns
Column(12"X12") 36 1.000 1.000 4.00 144.00
Column(9"X9") 16 0.75 0.75 4.00 36.00
9 PAINTING WORKS
9.1 External Surface 1 Area= 1,663.74 sft 1,663.74 1,663.74 sft.
9.2 Internal Surface 11,259.33 sft.

10 MISCELLANEOUS WORKS
waterproofing 1 Area= 273.42 sft. 273.42 sft.

Pumori Engineering Services (Pvt.) Ltd. 8 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
CONCRETE WORK(FIRST
1 FLOOR)
Second Floor Slab 1 4,299.56 sft. 0.42 1,791.48
Second Floor Beam
Along Grid 7-7 1 118.75 0.75 0.75 66.80
Along Grid 6-6 1 118.75 0.75 0.75 66.80
Along Grid 5-5 1 120.50 0.75 0.75 67.78
Along Grid 4-4 1 19.58 0.75 0.75 11.02
Along Grid 3-3 1 19.58 0.75 0.75 11.02
Along Grid 2-2 1 19.58 0.75 0.75 11.02
Along Grid 1-1 1 19.58 0.75 0.75 11.02
Along Grid A-A 1 19.58 0.75 0.75 11.02
Along Grid B-B 1 19.58 0.75 0.75 11.02
Along Grid C-C 1 19.58 0.75 0.75 11.02
Along Grid D-D 1 19.58 0.75 0.75 11.02
Along Grid E-E 1 19.58 0.75 0.75 11.02
Along Grid F-F 1 19.58 0.75 0.75 11.02
Along Grid G-G 1 19.58 0.75 0.75 11.02
Along Grid H-H 1 19.58 0.75 0.75 11.02
Along Grid I-I 1 19.58 0.75 0.75 11.02
Along Grid J-J 1 19.58 0.75 0.75 11.02
Along Grid K-K 1 19.58 0.75 0.75 11.02
Along Grid L-L 1 44.75 0.75 0.75 25.17
Along Grid M-M 1 63.25 0.75 0.75 35.58
Along Grid N-N 1 63.25 0.75 0.75 35.58
Staircase
First Flight
Waist slab 1 5.08 5.08 0.42 10.75
Steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Second flight
Waist slab 1 6.10 5.17 0.42 13.25
steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Third Flight
Waist slab 1 5.08 5.17 0.42 11.04
Steps 5 Area= 0.19 5.17 4.91
Sill and Lintel Band
W(6) 24 7.00 0.75 0.42 105.84
W(3) 1 4.00 0.75 0.42 2.52
V(3) 5 6.00 0.75 0.42 18.90
V(2.5) 1 3.50 0.75 0.42 2.21
D(3) 7 4.00 0.75 0.42 8.82
D(2.5) 8 3.50 0.75 0.42 8.82

Pumori Engineering Services (Pvt.) Ltd. 9 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
Columns
Column(12"X12") 36 1.00 1.00 13.33 479.88
Column(9"X9") 16 0.75 0.75 13.33 119.97
52

Pumori Engineering Services (Pvt.) Ltd. 10 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
2 Formwork
Along Grid 7-7 1 118.75 0.75 178.13
Along Grid 6-6 1 118.75 0.75 178.13
Along Grid 5-5 1 120.50 0.75 180.75
Along Grid 4-4 1 19.58 0.75 29.38
Along Grid 3-3 1 19.58 0.75 29.38
Along Grid 2-2 1 19.58 0.75 29.38
Along Grid 1-1 1 19.58 0.75 29.38
Along Grid A-A 1 19.58 0.75 29.38
Along Grid B-B 1 19.58 0.75 29.38
Along Grid C-C 1 19.58 0.75 29.38
Along Grid D-D 1 19.58 0.75 29.38
Along Grid E-E 1 19.58 0.75 29.38
Along Grid F-F 1 19.58 0.75 29.38
Along Grid G-G 1 19.58 0.75 29.38
Along Grid H-H 1 19.58 0.75 29.38
Along Grid I-I 1 19.58 0.75 29.38
Along Grid J-J 1 19.58 0.75 29.38
Along Grid K-K 1 19.58 0.75 29.38
Along Grid L-L 1 44.75 0.75 67.13
Along Grid M-M 1 63.25 0.75 94.88
Along Grid N-N 1 63.25 0.75 94.88
Second Floor Slab 1 3,901.43 sft. 3,901.43
Slab peripheri 1 357.00 0.42 149.94
Staircase
First Flight
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
1 10.16 0.42 4.27
Second flight -
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
Third Flight
Waist slab 1 5.08 5.08 25.82
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Columns -
Column(12"X12") 36 1.00 4.00 9.33 1,343.52
Column(9"X9") 16 0.75 4.00 9.33 447.84

Pumori Engineering Services (Pvt.) Ltd. 11 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
Lintel & sill
W(6) 24 7.00 0.42 141.12
W(3) 1 4.00 0.42 3.36
V(3) 5 4.00 0.42 16.80
V(2.5) 1 3.50 0.42 2.94
D(3) 7 4.00 0.42 11.76
D(2.5) 8 3.50 0.42 11.76
3 Reinforcement Bars - TMT
4 BRICK WORK
4.1 9" Wall
upto second floor
Along Grid 7-7 1 118.75 0.75 9.33 830.95
Along Grid 6-6 1 118.75 0.75 9.33 830.95
Along Grid 5-5 1 13.50 0.75 9.33 94.47
Along Grid 4-4 0 13.50 0.75 9.33 -
Along Grid 3-3 1 13.50 0.75 9.33 94.47
Along Grid 2-2 0 13.50 0.75 9.33 -
Along Grid 1-1 1 13.50 0.75 9.33 94.47
Along Grid A-A 1 13.42 0.75 9.33 93.91
Along Grid C-C 1 13.42 0.75 9.33 93.91
Along Grid E-E 1 13.42 0.75 9.33 93.91
Along Grid G-G 1 13.42 0.75 9.33 93.91
Along Grid I-I 1 13.42 0.75 9.33 93.91
Along Grid J-J 1 13.42 0.75 9.33 93.91
Along Grid K-K 1 13.42 0.75 9.33 93.91
Along Grid M-M 1 61.75 0.75 9.33 432.10
Along Grid N-N 1 61.75 0.75 9.33 432.10
Deduction for opening
W(6) 24 6.00 5.00 0.75 540.00
W(3) 1 3.00 5.00 0.75 11.25
V(3) 5 3.00 2.50 0.75 28.13
V(2.5) 1 2.50 2.50 0.75 4.69
D(3) 7 3.00 7.00 0.75 110.25
Opening(3.5) 1 3.50 7.00 0.75 18.38
4.2 Half Brickwork 1 63.92 9.33 596.37
Deduction of opening
D(2.5) 8 7.00 2.50 140.00
5 DOORS/WINDOWS
5.1 Chaukhat
D(3) 7 7.00 3.00 9.82
D(2.5) 8 7.00 2.50 10.89
W(6) 24 6.00 5.00 43.56
W(3) 1 3.00 5.00 1.32
V(3) 5 3.00 2.50 4.54
V(2.5) 1 2.50 2.50 0.83

Pumori Engineering Services (Pvt.) Ltd. 12 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity

Providing, making & fixing


38mm thick water proof flush
door shutter including hinges ,
tower bolts , approved good
5.2 quality mortise lock, door
stopper and other accessories
as per design drawings,
specifications & instructions of
engineer.

D(3) 7 3.00 7.00 147.00


D(2.5) 8 2.50 7.00 140.00

Providing, making & fixing


38mm thick glazed window
shutter with 5mm thk. Tinted
glass including hinges , tower
5.3 bolts,eye-hooks and other
accessories as per design
drawings, specifications &
instructions of engineer.

W(6) 24 6.00 5.00 720.00


W(3) 1 3.00 5.00 15.00
V(3) 5 3.00 2.50 37.50
V(2.5) 1 2.50 2.50 6.25

Providing, making & fixing 4.5 x


20mm MS grill with accessories
5.4 as per design drawings,
specifications & instructions of
engineer.

W(6) 24 6.00 5.00 720.00


W(3) 1 3.00 5.00 15.00
V(3) 5 3.00 2.50 37.50
V(2.5) 1 2.50 2.50 6.25
6 FLOORING WORK
6.1 Screeding
Classrooms 1 1,994.23 sft
balcony 1 1,168.55 sft
toilet 1 273.42 sft

Pumori Engineering Services (Pvt.) Ltd. 13 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
staircase lobby 1 75.88 sft

Pumori Engineering Services (Pvt.) Ltd. 14 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
6.2 Punning
Classrooms 1 1,994.23 sft
balcony 1 1,168.55 sft
Store Room 1 221.14 sft
staircase lobby 1 75.88 sft
6.3 Tiles for bathroom floor 1 273.42 sft
6.4 Dado tiles 1 147.75 5.00
7 PLASTERING WORK
7.1 Plaster Work 1:5 on Wall
Wall Surfaces
9"wall 2 Area= 3264.56 sft 6,529.13
5"wall 2 Area= 473.72 sft 947.44
Plaster Work 1:3 on Concrete
7.2 Surface
Slab 1 Area= 4,032.00 4,032.00
Beam
Along Grid 7-7 2 118.75 0.75 178.13
Along Grid 6-6 2 118.75 0.75 178.13
Along Grid 5-5 2 120.50 0.75 180.75
Along Grid 4-4 2 19.58 0.75 29.38
Along Grid 3-3 2 19.58 0.75 29.38
Along Grid 2-2 2 19.58 0.75 29.38
Along Grid 1-1 2 19.58 0.75 29.38
Along Grid A-A 2 19.58 0.75 29.38
Along Grid B-B 2 19.58 0.75 29.38
Along Grid C-C 2 19.58 0.75 29.38
Along Grid D-D 2 19.58 0.75 29.38
Along Grid E-E 2 19.58 0.75 29.38
Along Grid F-F 2 19.58 0.75 29.38
Along Grid G-G 2 19.58 0.75 29.38
Along Grid H-H 2 19.58 0.75 29.38
Along Grid I-I 2 19.58 0.75 29.38
Along Grid J-J 2 19.58 0.75 29.38
Along Grid K-K 2 19.58 0.75 29.38
Along Grid L-L 2 44.75 0.75 67.13
Along Grid M-M 2 63.25 0.75 94.88
Along Grid N-N 2 63.25 0.75 94.88
Columns
Column(12"X12") 36 1.000 1.00 4.00 144.00
Column(9"X9") 16 0.75 0.75 4.00 36.00
8 PAINTING WORKS
8.1 External Surface 1 Area= 1,663.74 sft 1,663.74
8.2 Internal Surface 1 Area= 11,259.33 11,259.33
9 MISCELLANEOUS WORKS
waterproofing 1 Area= 273.42 273.42

Pumori Engineering Services (Pvt.) Ltd. 15 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

3,072.48 cft M20

1,791.48 cft
1,281.00 cft.

Pumori Engineering Services (Pvt.) Ltd. 16 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

Pumori Engineering Services (Pvt.) Ltd. 17 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks
7,457.98 sft.

1,791.36 sft

Pumori Engineering Services (Pvt.) Ltd. 18 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

16.09 MT

2,754.15 cft.

456.37 sft

70.95 cft

Pumori Engineering Services (Pvt.) Ltd. 19 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

287.00 sft.

778.75 sft

778.75 sft

3,512.08 sft.

Pumori Engineering Services (Pvt.) Ltd. 20 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

Pumori Engineering Services (Pvt.) Ltd. 21 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks
3,383.92 sft

273.42 sft
738.75 sft

7,476.56 sft.

5,446.50 sft.

1,663.74 sft.
11,259.33 sft.
273.42 sft.

Pumori Engineering Services (Pvt.) Ltd. 22 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity

1 CONCRETE WORK(SECOND FLOOR)

second Floor Slab 1 4,299.56 sft. 0.42 1,791.48


Second Floor Beam
Along Grid 7-7 1 118.75 0.75 0.75 66.80
Along Grid 6-6 1 118.75 0.75 0.75 66.80
Along Grid 5-5 1 120.50 0.75 0.75 67.78
Along Grid 4-4 1 19.58 0.75 0.75 11.02
Along Grid 3-3 1 19.58 0.75 0.75 11.02
Along Grid 2-2 1 19.58 0.75 0.75 11.02
Along Grid 1-1 1 19.58 0.75 0.75 11.02
Along Grid A-A 1 19.58 0.75 0.75 11.02
Along Grid B-B 1 19.58 0.75 0.75 11.02
Along Grid C-C 1 19.58 0.75 0.75 11.02
Along Grid D-D 1 19.58 0.75 0.75 11.02
Along Grid E-E 1 19.58 0.75 0.75 11.02
Along Grid F-F 1 19.58 0.75 0.75 11.02
Along Grid G-G 1 19.58 0.75 0.75 11.02
Along Grid H-H 1 19.58 0.75 0.75 11.02
Along Grid I-I 1 19.58 0.75 0.75 11.02
Along Grid J-J 1 19.58 0.75 0.75 11.02
Along Grid K-K 1 19.58 0.75 0.75 11.02
Along Grid L-L 1 44.75 0.75 0.75 25.17
Along Grid M-M 1 63.25 0.75 0.75 35.58
Along Grid N-N 1 63.25 0.75 0.75 35.58
Staircase
First Flight
Waist slab 1 5.08 5.08 0.42 10.75
Steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Second flight
Waist slab 1 6.10 5.17 0.42 13.25
steps 5 Area= 0.19 5.17 4.91
Landing 1 5.00 5.08 0.42 10.67
Third Flight
Waist slab 1 5.08 5.17 0.42 11.04
Steps 5 Area= 0.19 5.17 4.91
Sill and Lintel Band
W(6) 24 7.00 0.75 0.42 105.84
W(3) 1 4.00 0.75 0.42 2.52
V(3) 5 4.00 0.75 0.42 12.60
V(2.5) 1 3.50 0.75 0.42 2.21
D(3) 7 4.00 0.75 0.42 8.82
D(2.5) 8 3.50 0.75 0.42 8.82
Columns

Pumori Engineering Services (Pvt.) Ltd. 23 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
Column(12"X12") 36 1.00 1.00 13.33 479.88
Column(9"X9") 16 0.75 0.75 13.33 119.97
2 Formwork
Along Grid 7-7 1 118.75 0.75 178.13
Along Grid 6-6 1 118.75 0.75 178.13
Along Grid 5-5 1 120.50 0.75 180.75
Along Grid 4-4 1 19.58 0.75 29.38
Along Grid 3-3 1 19.58 0.75 29.38
Along Grid 2-2 1 19.58 0.75 29.38
Along Grid 1-1 1 19.58 0.75 29.38
Along Grid A-A 1 19.58 0.75 29.38
Along Grid B-B 1 19.58 0.75 29.38
Along Grid C-C 1 19.58 0.75 29.38
Along Grid D-D 1 19.58 0.75 29.38
Along Grid E-E 1 19.58 0.75 29.38
Along Grid F-F 1 19.58 0.75 29.38
Along Grid G-G 1 19.58 0.75 29.38
Along Grid H-H 1 19.58 0.75 29.38
Along Grid I-I 1 19.58 0.75 29.38
Along Grid J-J 1 19.58 0.75 29.38
Along Grid K-K 1 19.58 0.75 29.38
Along Grid L-L 1 44.75 0.75 67.13
Along Grid M-M 1 63.25 0.75 94.88
Along Grid N-N 1 63.25 0.75 94.88
Top Floor Slab 1 3,899.73 sft. 3,899.73
Slab peripheri 1 357.00 0.42 149.94
Staircase
First Flight
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
1 10.16 0.42 4.27
Second flight -
Waist slab 1 5.08 5.08 25.81
1 5.08 1.00 5.08
steps 5 0.58 5.08 14.82
Landing 1 5.08 5.08 25.81
Third Flight
Waist slab 1 5.08 5.08 25.82
1 5.08 1.00 5.08
Steps 5 0.58 5.08 14.82
Columns -
Column(12"X12") 36 1.00 4.00 9.33 1,343.52
Column(9"X9") 16 0.75 4.00 9.33 447.84

Pumori Engineering Services (Pvt.) Ltd. 24 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
Lintel & sill
W(6) 24 7.00 0.42 141.12
W(3) 1 4.00 0.42 3.36
V(3) 5 4.00 0.42 16.80
V(2.5) 1 3.50 0.42 2.94
D(3) 7 4.00 0.42 11.76
D(2.5) 8 3.50 0.42 11.76
3 Reinforcement Bars - TMT
4 BRICK WORK
4.1 9" Wall
upto second floor
Along Grid 7-7 1 118.75 0.75 9.33 830.95
Along Grid 6-6 1 118.75 0.75 9.33 830.95
Along Grid 5-5 1 13.50 0.75 9.33 94.47
Along Grid 4-4 1 13.50 0.75 9.33 94.47
Along Grid 3-3 1 13.50 0.75 9.33 94.47
Along Grid 2-2 1 13.50 0.75 9.33 94.47
Along Grid 1-1 1 13.50 0.75 9.33 94.47
Along Grid A-A 1 13.42 0.75 9.33 93.91
Along Grid C-C 1 13.42 0.75 9.33 93.91
Along Grid E-E 1 13.42 0.75 9.33 93.91
Along Grid G-G 1 13.42 0.75 9.33 93.91
Along Grid I-I 1 13.42 0.75 9.33 93.91
Along Grid J-J 1 13.42 0.75 9.33 93.91
Along Grid K-K 1 13.42 0.75 9.33 93.91
Along Grid M-M 1 61.75 0.75 9.33 432.10
Along Grid N-N 1 61.75 0.75 9.33 432.10
Deduction for opening
W(6) 24 6.00 5.00 0.75 540.00
W(3) 1 3.00 5.00 0.75 11.25
V(3) 5 3.00 2.50 0.75 28.13
V(2.5) 1 2.50 2.50 0.75 4.69
D(3) 7 3.00 7.00 0.75 110.25
Opening(3.5) 1 3.50 7.00 0.75 18.38
4.2 Half Brickwork 1 63.92 9.33 596.37
Deduction of opening
D(2.5) 8 7.00 2.50 140.00
5 DOORS/WINDOWS
5.1 Chaukhat
D(3) 7 7.00 3.00 9.82
D(2.5) 8 7.00 2.50 10.89
W(6) 24 6.00 5.00 43.56
W(3) 1 3.00 5.00 1.32
V(3) 5 3.00 2.50 4.54
V(2.5) 1 2.50 2.50 0.83

Pumori Engineering Services (Pvt.) Ltd. 25 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
5.2

Providing, making & fixing 38mm


thick water proof flush door shutter
including hinges , tower bolts ,
approved good quality mortise lock,
door stopper and other accessories
as per design drawings,
specifications & instructions of
engineer.

D(3) 7 3.00 7.00 147.00


D(2.5) 8 2.50 7.00 140.00

Providing, making & fixing 38mm


thick glazed window shutter with
5mm thk. Tinted glass including
5.3 hinges , tower bolts,eye-hooks and
other accessories as per design
drawings, specifications &
instructions of engineer.

W(6) 24 6.00 5.00 720.00


W(3) 1 3.00 5.00 15.00
V(3) 5 3.00 2.50 37.50
V(2.5) 1 2.50 2.50 6.25

Providing, making & fixing 4.5 x


20mm MS grill with accessories as
5.4 per design drawings, specifications
& instructions of engineer.

W(6) 24 6.00 5.00 720.00


W(3) 1 3.00 5.00 15.00
V(3) 5 3.00 2.50 37.50
V(2.5) 1 2.50 2.50 6.25
6 FLOORING WORK
6.1 Screeding
Principal Room 1 327.25 sft. 327.25
Meeting Room 1 320.88 sft. 320.88
Store Room 1 153.19 sft. 153.19
Teacher Room 1 326.97 sft. 326.97
Account Section 1 237.82 sft. 237.82
Library 1 331.42 sft. 331.42
Laboratory 1 334.25 sft. 334.25
balcony 1 1,168.55 sft 1,168.55
toilet 1 273.42 sft 273.42
staircase lobby 1 75.88 sft 75.88
6.2 Punning
Classrooms 1 1,994.23 sft

Pumori Engineering Services (Pvt.) Ltd. 26 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
balcony 1 1,168.55 sft
staircase lobby 1 75.88 sft
6.3 Tiles for bathroom floor 1 273.42 sft
6.4 Dado tiles 1 147.75 5.00
7 PLASTERING WORK
7.1 Plaster Work 1:5 on Wall
Wall Surfaces
9"wall 2 Area= 3264.5639 6,529.13
5"wall 2 Area= 473.7181 947.44

Pumori Engineering Services (Pvt.) Ltd. 27 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


SN Description of Works No. Length Breadth Height Quantity
Plaster Work 1:3 on Concrete
7.2 Surface
Slab 1 Area= 4,025.28 4,025.28
Beam
Along Grid 7-7 2 118.75 0.75 178.13
Along Grid 6-6 2 118.75 0.75 178.13
Along Grid 5-5 2 120.50 0.75 180.75
Along Grid 4-4 2 19.58 0.75 29.38
Along Grid 3-3 2 19.58 0.75 29.38
Along Grid 2-2 2 19.58 0.75 29.38
Along Grid 1-1 2 19.58 0.75 29.38
Along Grid A-A 2 19.58 0.75 29.38
Along Grid B-B 2 19.58 0.75 29.38
Along Grid C-C 2 19.58 0.75 29.38
Along Grid D-D 2 19.58 0.75 29.38
Along Grid E-E 2 19.58 0.75 29.38
Along Grid F-F 2 19.58 0.75 29.38
Along Grid G-G 2 19.58 0.75 29.38
Along Grid H-H 2 19.58 0.75 29.38
Along Grid I-I 2 19.58 0.75 29.38
Along Grid J-J 2 19.58 0.75 29.38
Along Grid K-K 2 19.58 0.75 29.38
Along Grid L-L 2 44.75 0.75 67.13
Along Grid M-M 2 63.25 0.75 94.88
Along Grid N-N 2 63.25 0.75 94.88
Columns
Column(12"X12") 36 1.000 1.000 4.00 144.00
Column(9"X9") 16 0.75 0.75 4.00 36.00
8 PAINTING WORKS
8.1 External Surface 1 Area= 1,663.74 sft 1,663.74

8.2 Internal Surface 1 Area= 11,252.61 sft.


9 MISCELLANEOUS WORKS
waterproofing 1 Area= 273.42 sft.

Pumori Engineering Services (Pvt.) Ltd. 28 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

3,066.18 cft M20

1,791.48 cft
674.85 cft.

Pumori Engineering Services (Pvt.) Ltd. 29 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

7,456.28 sft.

1,791.36 sft

Pumori Engineering Services (Pvt.) Ltd. 30 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

16.09 MT

2,961.46 cft

456.37 sft

70.95 cft

Pumori Engineering Services (Pvt.) Ltd. 31 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

287.00 sft.

778.75 sft

778.75 sft

3,549.62 sft.

3,238.66 sft

Pumori Engineering Services (Pvt.) Ltd. 32 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

273.42 sft
738.75 sft

7,476.56 sft.

Pumori Engineering Services (Pvt.) Ltd. 33 of 89


Detailed Qty' Estimate Siddeshwor Educational Public Campus

SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)


T. QTY' Unit Rmks

5,439.78 sft.

1,663.74 sft.

11,252.61 sft.
273.42 sft

Pumori Engineering Services (Pvt.) Ltd. 34 of 89


CIVIL WORKS(SIDDESHWOR EDUCATIONAL PUBLIC CAMPUS)
SN Description of Works No. Length Breadth Height Quantity

1 CONCRETE WORK(SECOND FLOOR)

Staircase Cover Slab 1 24.25 20.50 0.42 207.14


Second Floor Beam
Along Grid 7-7 1 14.00 0.75 0.75 7.88
Along Grid 6-6 1 14.00 0.75 0.75 7.88
Along Grid K-K 1 13.75 0.75 0.75 7.73
Along Grid M-M 1 13.75 0.75 0.75 7.73
Sill and Lintel Band
W(6) 1 7.00 0.75 0.42 4.41
Columns
Column(12"X12") 4 1.00 1.00 13.33 53.32
2 Formwork
Along Grid 7-7 1 14.00 0.75 21.00
Along Grid 6-6 1 14.00 0.75 21.00
Along Grid K-K 1 13.75 0.75 20.63
Along Grid M-M 1 13.75 0.75 20.63

Top Floor Slab 1 24.25 20.50 497.13


Slab peripheri 1 101.00 0.42 42.42
Columns -
Column(12"X12") 4 1.00 4.00 9.33 149.28
Lintel & sill
W(6) 1 7.00 0.42 5.88
3 Reinforcement Bars - TMT
4 BRICK WORK
4.1 9" Wall
upto second floor
Along Grid 7-7 1 14.00 0.75 9.33 97.97
Along Grid 6-6 1 14.00 0.75 9.33 97.97
Along Grid K-K 1 13.75 0.75 9.33 96.22
Along Grid M-M 1 13.75 0.75 9.33 96.22
Deduction for opening
W(6) 1 6.00 5.00 0.75 22.50
D(3) 1 3.00 7.00 0.75 15.75
4.2 Half Brickwork
Deduction of opening
5 DOORS/WINDOWS
5.1 Chaukhat
D(3) 1 7.00 3.00 1.40
W(6) 1 6.00 5.00 1.82
5.2

Providing, making & fixing 38mm


thick water proof flush door shutter
including hinges , tower bolts ,
approved good quality mortise lock,
door stopper and other accessories
as per design drawings,
specifications & instructions of
engineer.

D(3) 1 3.00 7.00 21.00

Providing, making & fixing 38mm


thick glazed window shutter with
5mm thk. Tinted glass including
5.3 hinges , tower bolts,eye-hooks and
other accessories as per design
drawings, specifications &
instructions of engineer.

W(6) 1 6.00 5.00 30.00

Providing, making & fixing 4.5 x


20mm MS grill with accessories as
5.4 per design drawings, specifications
& instructions of engineer.

Flooring Work
Screeding 1 Area= 4,032.00
Punning 1 Area= 4,032.00

7 PLASTERING WORK
7.1 Plaster Work 1:5 on Wall
Wall Surfaces
9"wall 2 Area= 466.815 933.63
Plaster Work 1:3 on Concrete
7.2 Surface
Slab 1 Area= 497.13 497.13
Beam
Along Grid 7-7 1 14.00 0.75 10.50
Along Grid 6-6 1 14.00 0.75 10.50
Along Grid K-K 1 13.75 0.75 10.31
Along Grid M-M 1 13.75 0.75 10.31
Columns
Column(12"X12") 4 1.000 1.000 4.00 16.00
8 PAINTING WORKS
8.1 External Surface 1 Area= 471.48 sft 471.48
8.2 Internal Surface 1 Area= 471.48 sft.
9 MISCELLANEOUS WORKS
waterproofing 1 Area= 4,032.00 sft.
PUS)
T. QTY' Unit Rmks

242.76 cft M20

207.14 cft
35.63 cft.

777.96 sft.

149.28 sft

1.34 MT

350.11 cft
6.07

3.22 cft
21.00 sft.

30.00 sft

30.00 sft

4,032.00 sft
4,032.00 sft

933.63 sft.

554.75 sft.

471.48 sft.
471.48 sft.
4,032.00 sft
Sn DESCRIPTION UNIT GF
1.00 EARTHWORK
1.01

Clearing the site of all the vegetation, roots and other unuseful
materials including excavation of top soil to a depth of 15 cm,
removing bushes, trees and levelling the Site for stacking the useful
items in specified space and disposing other item as per instruction
of the site engineer all complete including layout of buildings, roads
and ancillary services. sq.ft. 4,032.00
1.02 Earthwork in excavation

Earthwork in excavation in trenches, foundation etc. in all kinds of


soil including timbering and pumping out water from the basement
(if necessary) dressing of sides, ramming of bottom, lift upto 3.5m, as
per specification, drawings & instruction of site engineer. cu.ft. 9,183.45
1.03
Filling with associated Earth in 150mm layers including compaction
with tamping rammer as per specification & instruction of engineer. cu.ft. 11,415.87
2.00 CONCRETE WORKS
2.01 Lean Concrete
a)

Providiing, laying, compacting and curing plain cement concrete M10


(1:3:6) in foundation with cement, sand and stone ballast 20mm
gauge finishing to approved level, lines and dimensions all complete
as per drawings, specifications and instruction of site engineer. cu.ft. 302.78
b)

Providiing, laying, compacting and curing plain cement concrete M15


(1:2:4) in foundation with cement, sand and stone ballast 20mm
gauge finishing to approved level, lines and dimensions all complete
as per drawings, specifications and instruction of site engineer. cu.ft. 934.46
2.02 PCC for RCC Works
a)

Providing, laying , compacting & curing plain cement Concrete M20


(1 : 1.5 : 3) for RCC footings, Raft foundation ,slab, columns, beams,
tie beam, retaining walls and all kinds of R.C.C. works with cement,
sand & stone ballast 40mm down finishings to approved level, lines
& dimensions all complete as per drawings, specifications &
instructions of site engineer. cu.ft. 5,439.49
2.03 Formworks
Centering and shuttering with steel or water proof plywood material
for all kinds of work including all necessary propping, scaffolding,
staging, supporting etc. all complete as per drawing, specification,
and instruction of site engineer.
a)Footing,Column,Beam,Slab, Shearwalls etc. sq.ft. 12,181.80
2.04 Reinforcement
a)

Reinforcement work including straightening, cleaning, cutting,


bending, binding with 20 SWG annealed wire & fixing in position as
per drawing, bar bending schedule for raft foundation column,
beam, wall, stair, slab in all R.C.C. works as per specification, drawing
& instruction of site engineer.
a) TMT Bars MT 29.83
3.00 STONE MASONRY WORK
3.01

Providing & laying locally available dressed stone masonry work of


specific size in cement, sand mortar (1:6) in superstructure finished
in perfect line & level including wetting the bricks, packing the joints
& curing the work complete in all thickness of walls as per drawings,
a) For Foundation cu.ft. 2,160.38
a) For superstructure cu.ft. 2,685.57
3.02

Providing & laying locally availablebrick masonry work of specific size


in cement, sand mortar (1:4) in superstructure finished in perfect
line & level including wetting the bricks, packing the joints & curing
the work complete in all thickness of walls as per drawings,
a) For superstructure sq.ft. 456.37
3.03
Providing & laying one layer of Brick flat soling in foundation and
floor with approved quality local chimney made brick including
voids filling with sand all complete as per instruction of the site
engineer.
a) On Floor & Foundation sq.ft. 9,247.92
4.00 DOORS/WINDOWS WORKS
4.01 Providing, making & fixing frames for door & windows made of well
seasoned sal wood including 6 hold fast for each frame as per design
drawings, specifications & instructions of engineer.

cu.ft. 78.79
4.02 Providing, making & fixing 38mm thick water proof flush door
shutter including hinges , tower bolts , approved good quality
mortise lock, door stopper and other accessories as per design
drawings, specifications & instructions of engineer.

sq.ft. 266.00
4.03 Providing, making & fixing 38mm thick glazed window shutter with
5mm thk. Tinted glass including hinges , tower bolts,eye-hooks and
other accessories as per design drawings, specifications &
instructions of engineer.

sq.ft. 919.75
4.04 Providing, making & fixing 4.5 x 20mm MS grill with accessories as
per design drawings, specifications & instructions of engineer.
sq.ft. 919.75
5.00 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing average 20 mm thick
screed with 1:4 cement sand mortar in perfect lines & level as per
design, specification and instruction of the site engineer.

sq.ft. 3,737.84
b) Punning sq.ft. 3,464.42
5.02

Providing & laying glazed/semi glazed non skid ceramic,


porcelain/granamite wall & floor tiles in 1:4 cement sand mortar in
perfect lines & level finishing the joint with white cement with or
without pigments where necessary all complete as per design
drawings, patterns, specifications and instruction of the site
engineer.
a) Glazed tiles for dado of bathroom(basic cost of tiles
:NRs.600.00/sq.m) sq.ft. 738.75
b) Semi glazed tile for floors of bathrooms (basic cost of tiles:
NRs.650.00/sq.m.) sq.ft. 273.42
5.03

Providing, mixing & applying polymer modified hydraulically setting


water proofing coat of approved make on floor/roof slab/wall as per
manufacturer's specification and instruction of site engineer. sq.ft. 273.42
6.00 PLASTERING/FINISHING WORKS
6.01

Providing, laying & curing cement sand (1:5) Plastering on internal &
external walls to perfect plumb, lines & level icluding raking the
mortar joints and wetting the masonry surface all complete as per
design drawings, specifications and instrcution of the site engineer
all complete:
a) 12.5mm thk. sq.ft. 947.44
b) 20mm thk. sq.ft. 6,529.13
6.02

Providing, laying & curing 12 mm thick cement sand (1:3) plastering


in ceiling, beams and column surfaces including chipping & wetting
the concrete surfaces finished in perfect plumb, lines and level as
per drawings, specifications and instructions of the site engineer. sq.ft. 5,446.50
7.00 PAINTING WORK
7.01

Providing and painting two coats of washable distemper over one


coat of cement primer of approved brand and colour over plastered
wall surfaces and ceiling as per specifications and instrcutions of site
engineer, all complete.
a)External Surface sq.ft. 1,663.74
b) InternalSurface sq.ft. 11,259.33
7.01

Providing and painting two or more coats of enamel paint of


approved brand over wooden surfaces as per specifications and
instrcutions of site engineer, all complete. sq.ft. 1279.015
8.00 MISCELLANEOUS WORKS
8.01

Providing, fabricating and fixing staircase railing made of 1" dia 18


gauge stainless steel pipe balustrade in each tread including 2" dia
stainless steel handrail (18 gauge) with all necessary fittings all
complete as per design, specification and instruction of sit engineer. r.ft. 19.33
8.02

Providing, fabricating and fixing Parapet Railing of 9" height with 2"
dia. 16 gauge MS pipe hand-rail and 2x1.5"dia. vertical supports @
1.20m c/c with all necessary fittings ang enamel paint finish all
complete as per design, specification and instruction of sit engineer. r.ft.
8.03

Providing, fabricating and fixing collapsible gate with all necessary


fittings ang enamel paint finish all complete as per design,
specification and instruction of site engineer. sq. ft. 127.44
8.04 Providing Underground RCC Water Tank of 25000 Litres Capacity
with all necessary fittings all complete Ltrs
8.05

Construction of Stone Masonry Boundary Wall of 7'-6" height (above


ground level) including metal railing works of 3'-6" over 4'-0"
Masonry Wall with all necessary plastering on both sides and
paintings all complete as per drawing all complete r.ft.
8.06 Providing, fabricating and Fittings Boundary metal main gate with all
necessary fittings all complete. sq. ft.
8.07 Providing, mixing & applying polymer modified hydraulically setting
water proofing coat of approved make on floor/roof slab/wall as per
manufacturer's specification and instruction of site engineer.

sq. ft.
8.08 Providing and Constructing Septic tank and Soak Pit with necessary
fittings all complete as per design, specification and instruction of
site engineer all complete

Nos.
8.09

Providing, fabricating and fixing 16 gauge Iron Main gate with all
necessary fittings ang enamel paint finish all complete as per design,
specification and instruction of site engineer. sq.ft.
FF SF TERRACE TOTAL

4,032.00
-

9,183.45

11,415.87
-
-

302.78

934.46
-

3,072.48 3,066.18 242.76 11,820.91


-
-
7,457.98 7,456.28 777.96 27,874.02
-

-
16.09 16.09 1.34 63.35
-

-
2,160.38
2,754.15 2,754.15 350.11 8,543.99

-
456.37 456.37 1,369.12

-
9,247.92
-

78.79 78.79 3.22 239.58

266.00 266.00 21.00 819.00


919.75 919.75 30.00 2,789.25

919.75 919.75 30.00 2,789.25


-

3,737.84 3,737.84 4,032.00 15,245.53


3,464.42 3,464.42 4,032.00 14,425.27

738.75 738.75 2,216.25

273.42 273.42 820.26

273.42 273.42 4,032.00 4,852.26


-

-
947.44 947.44 2,842.31
6,529.13 6,529.13 933.63 20,521.01

5,446.50 5,446.50 554.75 16,894.25


-
-
1,663.74 1,663.74 466.82 5,458.02
11,259.33 11,259.33 466.82 34,244.80

1279.015 1279.015 279 4,116.05


-

19.33 19.33 19.33 77.32

174.5 174.5 382 731.00

127.44 127.44 382.32

-
-
Bill Of Quantity Siddeshwor Educational Public Campus

Amount
I/No. Description of Works Unit Quantity Rate (NPR) (NPR)
A. CIVIL WORKS
1.00 EARTHWORK
1.01

Clearing the site of all the vegetation, roots


and other unuseful materials including
excavation of top soil to a depth of 15 cm,
removing bushes, trees and levelling the Site
for stacking the useful items in specified space
and disposing other item as per instruction of
the site engineer all complete including layout
of buildings, roads and ancillary services. sq.ft. 4,032.00 4.73 19,071.36
1.02 Earthwork in excavation

Earthwork in excavation in trenches,


foundation etc. in all kinds of soil including
timbering and pumping out water from the
basement (if necessary) dressing of sides,
ramming of bottom, lift upto 3.5m, as per
specification, drawings & instruction of site
engineer. cu.ft. 9,183.45 12.76 117,207.10
1.03

Filling with associated Earth in 150mm layers


including compaction with tamping rammer as
per specification & instruction of engineer. cu.ft. 11,415.87 1.95 22,260.94
2.00 CONCRETE WORKS
2.01 Lean Concrete
a)

Providiing, laying, compacting and curing plain


cement concrete M10 (1:3:6) in foundation
with cement, sand and stone ballast 20mm
gauge finishing to approved level, lines and
dimensions all complete as per drawings,
specifications and instruction of site engineer. cu.ft. 302.78 507.45 153,647.75
b)

Providiing, laying, compacting and curing plain


cement concrete M15 (1:2:4) in foundation
with cement, sand and stone ballast 20mm
gauge finishing to approved level, lines and
dimensions all complete as per drawings,
specifications and instruction of site engineer. cu.ft. 934.46 593.79 554,875.80

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus
2.02 PCC for RCC Works
a)

Providing, laying , compacting & curing plain


cement Concrete M20 (1 : 1.5 : 3) for RCC
footings, Raft foundation ,slab, columns,
beams, tie beam, retaining walls and all kinds
of R.C.C. works with cement, sand & stone
ballast 40mm down finishings to approved
level, lines & dimensions all complete as per
drawings, specifications & instructions of site
engineer. cu.ft. 11,820.91 697.62 8,246,492.68
2.03 Formworks

Centering and shuttering with steel or water


proof plywood material for all kinds of work
including all necessary propping, scaffolding,
staging, supporting etc. all complete as per
drawing, specification, and instruction of site
engineer.

a)Footing,Column,Beam,Slab, Shearwalls etc. sq.ft. 27,874.02 56.00 1,561,041.15


2.04 Reinforcement
a)

Reinforcement work including straightening,


cleaning, cutting, bending, binding with 20
SWG annealed wire & fixing in position as per
drawing, bar bending schedule for raft
foundation column, beam, wall, stair, slab in all
R.C.C. works as per specification, drawing &
instruction of site engineer.
a) TMT Bars MT 63.35 121,949.00 7,725,469.15
3.00 STONE MASONRY WORK
3.01

Providing & laying locally available dressed


stone masonry work of specific size in cement,
sand mortar (1:6) in superstructure finished in
perfect line & level including wetting the
bricks, packing the joints & curing the work
complete in all thickness of walls as per
drawings,
a) For Foundation cu.ft. 2,160.38 132.90 287,107.98
a) For superstructure cu.ft. 9,988.00 132.90 1,327,378.12

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus
3.02

Providing & laying 5" brick work of specific size


in cement, sand mortar (1:4) in superstructure
finished in perfect line & level including
wetting the bricks, packing the joints & curing
the work complete in all thickness of walls as
per drawings,
a) For superstructure sq.ft. 1,500.00 140.00 210,000.00
3.03

Providing & laying one layer of Brick flat soling


in foundation and floor with approved quality
local chimney made brick including voids
filling with sand all complete as per instruction
of the site engineer.
a) On Floor & Foundation sq.ft. 9,623.00 130.76 1,258,323.51
4.00 DOORS/WINDOWS WORKS
4.01 Providing, making & fixing frames for door &
windows made of well seasoned sal wood
including 6 hold fast for each frame as per
design drawings, specifications & instructions
of engineer.

cu.ft. 239.58 6,592.00 1,579,311.36


4.02 Providing, making & fixing 38mm thick water
proof flush door shutter including hinges ,
tower bolts , approved good quality mortise
lock, door stopper and other accessories as per
design drawings, specifications & instructions
of engineer.

sq.ft. 819.00 1,016.08 832,167.94


4.03 Providing, making & fixing 38mm thick glazed
window shutter with 5mm thk. Tinted glass
including hinges , tower bolts,eye-hooks and
other accessories as per design drawings,
specifications & instructions of engineer.

sq.ft. 2,789.25 698.98 1,949,623.54


4.04 Providing, making & fixing 4.5 x 20mm MS grill
with accessories as per design drawings,
specifications & instructions of engineer.

sq.ft. 2,789.25 179.55 500,820.72


5.00 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing
average 20 mm thick screed with 1:4 cement
sand mortar in perfect lines & level as per
design, specification and instruction of the site
engineer.

sq.ft. 15,245.53 50.65 772,186.24


Pumori Engineering Services (Pvt.)Ltd.
Bill Of Quantity Siddeshwor Educational Public Campus
b) Punning sq.ft. 14,425.27 20.07 289,515.23

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus
5.02

Providing & laying glazed/semi glazed non skid


ceramic, porcelain/granamite wall & floor tiles
in 1:4 cement sand mortar in perfect lines &
level finishing the joint with white cement with
or without pigments where necessary all
complete as per design drawings, patterns,
specifications and instruction of the site
engineer.
a)
Glazed tiles for dado of bathroom(basic cost of
tiles :NRs.600.00/sq.m) sq.ft. 2,216.25 216.26 479,286.23
b)
Semi glazed tile for floors of bathrooms (basic
cost of tiles: NRs.650.00/sq.m.) sq.ft. 820.26 219.14 179,751.78
5.03

Providing, mixing & applying polymer modified


hydraulically setting water proofing coat of
approved make on floor/roof slab/wall as per
manufacturer's specification and instruction of
site engineer. sq.ft. 4,852.26 53.44 259,304.77
6.00 PLASTERING/FINISHING WORKS
6.01

Providing, laying & curing cement sand (1:5)


Plastering on internal & external walls to
perfect plumb, lines & level icluding raking the
mortar joints and wetting the masonry surface
all complete as per design drawings,
specifications and instrcution of the site
engineer all complete:
a) 12.5mm thk. sq.ft. 2,942.31 33.09 97,361.04
b) 20mm thk. sq.ft. 20,425.34 45.26 924,450.89
6.02

Providing, laying & curing 12 mm thick cement


sand (1:3) plastering in ceiling, beams and
column surfaces including chipping & wetting
the concrete surfaces finished in perfect
plumb, lines and level as per drawings,
specifications and instructions of the site
engineer. sq.ft. 19,944.87 37.73 752,519.95

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus
7.00 PAINTING WORK
7.01

Providing and painting two coats of washable


distemper over one coat of cement primer of
approved brand and colour over plastered wall
surfaces and ceiling as per specifications and
instrcutions of site engineer, all complete.
a)External Surface sq.ft. 5,400.00 8.55 46,170.00
b) InternalSurface sq.ft. 36,999.86 8.55 316,348.80
7.01

Providing and painting two or more coats of


enamel paint of approved brand over wooden
surfaces as per specifications and instrcutions
of site engineer, all complete. sq.ft. 4,116.05 20.91 86,066.50
8.00 MISCELLANEOUS WORKS
8.01

Providing, fabricating and fixing staircase


railing made of 1" dia 18 gauge stainless steel
pipe balustrade in each tread including 2" dia
stainless steel handrail (18 gauge) with all
necessary fittings all complete as per design,
specification and instruction of sit engineer. r.ft. 77.32 2,286.00 176,753.52
8.02

Providing, fabricating and fixing Parapet Railing


of 9" height with 2" dia. 16 gauge MS pipe
hand-rail and 2x1.5"dia. vertical supports @
1.20m c/c with all necessary fittings ang
enamel paint finish all complete as per design,
specification and instruction of sit engineer. r.ft. 731.00 128.05 93,604.55
8.03

Providing, fabricating and fixing collapsible


gate with all necessary fittings ang enamel
paint finish all complete as per design,
specification and instruction of site engineer. sq. ft. 384.86 374.07 143,965.52
8.04
Providing Underground RCC Water Tank of
25000 Litres Capacity with all necessary fittings
all complete Ltrs 25,000.00 35.00 875,000.00
8.05

Construction of Stone Masonry Boundary Wall


of 7'-6" height (above ground level) including
metal railing works of 3'-6" over 4'-0" Masonry
Wall with all necessary plastering on both sides
and paintings all complete as per drawing all
complete r.ft. 575.00 1,850.00 1,063,750.00

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus
8.06
Providing, fabricating and Fittings Boundary
metal main gate with all necessary fittings all
complete. sq. ft. 84.00 650.00 54,600.00
8.07

Providing, mixing & applying polymer modified


hydraulically setting water proofing coat of
approved make on floor/roof slab/wall as per
manufacturer's specification and instruction of
site engineer. sq. ft. 4,852.26 45.00 218,351.70
8.08 Providing and Constructing Septic tank and
Soak Pit with necessary fittings all complete as
per design, specification and instruction of site
engineer all complete

Nos. 1.00 250,000.00 250,000.00


8.09

Providing, fabricating and fixing 16 gauge Iron


Main gate with all necessary fittings ang
enamel paint finish all complete as per design,
specification and instruction of site engineer. sq.ft. 160.00 935.91 149,745.60
Total Amount (Civil) 33,573,531.42
Contigencies(4%) 1,342,941.26
VAT(13%) 4,364,559.08
Total 39,281,031.76

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Rmks

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Bill Of Quantity Siddeshwor Educational Public Campus

Pumori Engineering Services (Pvt.)Ltd.


Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
A. CIVIL WORKS
1.00 EARTHWORK
1.01

Clearing the site of all the vegetation,


roots and other unuseful materials
including excavation of top soil to a
depth of 15 cm, removing bushes, trees
and levelling the Site for stacking the
useful items in specified space and
disposing other item as per instruction
of the site engineer all complete
including layout of buildings, roads and
ancillary services. sq.ft. 4,032.00 3,903.48 4.73
1.02 Earthwork in excavation

Earthwork in excavation in trenches,


foundation etc. in all kinds of soil
including timbering and pumping out
water from the basement (if necessary)
dressing of sides, ramming of bottom,
lift upto 3.5m, as per specification,
drawings & instruction of site engineer. cu.ft. 9,183.45 10,384.64 12.76
1.03

Filling with associated Earth in 150mm


layers including compaction with
tamping rammer as per specification &
instruction of engineer. cu.ft. 11,415.87 5,298.57 6.70
2.00 CONCRETE WORKS
2.01 Lean Concrete
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
a)

Providiing, laying, compacting and


curing plain cement concrete M10
(1:3:6) in foundation with cement, sand
and stone ballast 20mm gauge finishing
to approved level, lines and dimensions
all complete as per drawings,
specifications and instruction of site
engineer. cu.ft. 302.78 598.44 507.45
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
b)

Providiing, laying, compacting and


curing plain cement concrete M15
(1:2:4) in foundation with cement, sand
and stone ballast 20mm gauge finishing
to approved level, lines and dimensions
all complete as per drawings,
specifications and instruction of site
engineer. cu.ft. 934.46 1,103.45 593.79
2.02 PCC for RCC Works
a)

Providing, laying , compacting & curing


plain cement Concrete M20 (1 : 1.5 : 3)
for RCC footings, Raft foundation ,slab,
columns, beams, tie beam, retaining
walls and all kinds of R.C.C. works with
cement, sand & stone ballast 40mm
down finishings to approved level, lines
& dimensions all complete as per
drawings, specifications & instructions
of site engineer. cu.ft. 11,820.91 12,642.05 697.62
2.03 Formworks

Centering and shuttering with steel or


water proof plywood material for all
kinds of work including all necessary
propping, scaffolding, staging,
supporting etc. all complete as per
drawing, specification, and instruction of
site engineer.
a)Footing,Column,Beam,Slab,
Shearwalls etc. sq.ft. 27,874.02 32,285.72 56.00
2.04 Reinforcement
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
a)

Reinforcement work including


straightening, cleaning, cutting, bending,
binding with 20 SWG annealed wire &
fixing in position as per drawing, bar
bending schedule for raft foundation
column, beam, wall, stair, slab in all
R.C.C. works as per specification,
drawing & instruction of site engineer.
a) TMT Bars MT 63.35 33.82 121,949.00
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
3.00 STONE MASONRY WORK
3.01

Providing & laying locally available


dressed stone masonry work of specific
size in cement, sand mortar (1:6) in
superstructure finished in perfect line &
level including wetting the bricks,
packing the joints & curing the work
complete in all thickness of walls as per
drawings,
a) For Foundation cu.ft. 2,160.38 6,494.41 132.90
a) For superstructure cu.ft. 9,988.00 8,632.64 132.90
3.02

Providing & laying 5" brick work of


specific size in cement, sand mortar
(1:4) in superstructure finished in
perfect line & level including wetting the
bricks, packing the joints & curing the
work complete in all thickness of walls
as per drawings,
a) For superstructure sq.ft. 1,500.00 2,712.18 200.00
3.03

Providing & laying one layer of Brick flat


soling in foundation and floor with
approved quality local chimney made
brick including voids filling with sand all
complete as per instruction of the site
engineer.
a) On Floor & Foundation sq.ft. 9,623.00 7,745.71 130.76
4.00 DOORS/WINDOWS WORKS
4.01 Providing, making & fixing frames for
door & windows made of well seasoned
sal wood including 6 hold fast for each
frame as per design drawings,
specifications & instructions of engineer.

cu.ft. 239.58 251.55 6,592.00


Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
4.02 Providing, making & fixing 38mm thick
water proof flush door shutter including
hinges , tower bolts , approved good
quality mortise lock, door stopper and
other accessories as per design
drawings, specifications & instructions
of engineer.

sq.ft. 819.00 716.24 1,016.08


Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
4.03 Providing, making & fixing 38mm thick
glazed window shutter with 5mm thk.
Tinted glass including hinges , tower
bolts,eye-hooks and other accessories
as per design drawings, specifications &
instructions of engineer.

sq.ft. 2,789.25 1,601.81 698.98


4.04 Providing, making & fixing 4.5 x 20mm
MS grill with accessories as per design
drawings, specifications & instructions
of engineer.

sq.ft. 2,789.25 1,601.81 179.55


5.00 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and
curing average 20 mm thick screed with
1:4 cement sand mortar in perfect lines
& level as per design, specification and
instruction of the site engineer.

sq.ft. 15,245.53 16,571.54 50.65


b) Punning sq.ft. 14,425.27 15,666.52 20.07
5.02

Providing & laying glazed/semi glazed


non skid ceramic, porcelain/granamite
wall & floor tiles in 1:4 cement sand
mortar in perfect lines & level finishing
the joint with white cement with or
without pigments where necessary all
complete as per design drawings,
patterns, specifications and instruction
of the site engineer.
a)
Glazed tiles for dado of bathroom(basic
cost of tiles :NRs.600.00/sq.m) sq.ft. 2,216.25 2,088.24 216.26
b)
Semi glazed tile for floors of bathrooms
(basic cost of tiles: NRs.650.00/sq.m.) sq.ft. 820.26 835.70 219.14
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
5.03

Providing, mixing & applying polymer


modified hydraulically setting water
proofing coat of approved make on
floor/roof slab/wall as per
manufacturer's specification and
instruction of site engineer. sq.ft. 4,852.26 5,535.61 53.44
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)

6.00
PLASTERING/FINISHING WORKS
6.01

Providing, laying & curing cement sand


(1:5) Plastering on internal & external
walls to perfect plumb, lines & level
icluding raking the mortar joints and
wetting the masonry surface all
complete as per design drawings,
specifications and instrcution of the site
engineer all complete:
a) 12.5mm thk. sq.ft. 2,942.31 11,804.39 33.09
b) 20mm thk. sq.ft. 20,425.34 27,543.58 45.26
6.02

Providing, laying & curing 12 mm thick


cement sand (1:3) plastering in ceiling,
beams and column surfaces including
chipping & wetting the concrete
surfaces finished in perfect plumb, lines
and level as per drawings, specifications
and instructions of the site engineer. sq.ft. 19,944.87 16,248.14 37.73
7.00 PAINTING WORK
7.01

Providing and painting two coats of


washable distemper over one coat of
cement primer of approved brand and
colour over plastered wall surfaces and
ceiling as per specifications and
instrcutions of site engineer, all
complete.
a)External Surface sq.ft. 5,400.00 13,212.63 8.55
b) InternalSurface sq.ft. 36,999.86 42,383.49 8.55
7.01

Providing and painting two or more


coats of enamel paint of approved brand
over wooden surfaces as per
specifications and instrcutions of site
engineer, all complete. sq.ft. 4,116.05 6,464.81 20.91
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
8.00 MISCELLANEOUS WORKS
8.01

Providing, fabricating and fixing staircase


railing made of 1" dia 18 gauge stainless
steel pipe balustrade in each tread
including 2" dia stainless steel handrail
(18 gauge) with all necessary fittings all
complete as per design, specification
and instruction of sit engineer. r.ft. 77.32 78.00 2,286.00
8.02

Providing, fabricating and fixing Parapet


Railing of 9" height with 2" dia. 16 gauge
MS pipe hand-rail and 2x1.5"dia. vertical
supports @ 1.20m c/c with all
necessary fittings ang enamel paint
finish all complete as per design,
specification and instruction of sit
engineer. r.ft. 731.00 336.00 128.05
8.03

Providing, fabricating and fixing


collapsible gate with all necessary
fittings ang enamel paint finish all
complete as per design, specification
and instruction of site engineer. sq. ft. 384.86 384.86 374.07
8.04

Providing Underground RCC Water Tank


of 25000 Litres Capacity with all
necessary fittings all complete Ltrs 25,000.00 25,000.00 35.00
8.05

Construction of Stone Masonry


Boundary Wall of 7'-6" height (above
ground level) including metal railing
works of 3'-6" over 4'-0" Masonry Wall
with all necessary plastering on both
sides and paintings all complete as per
drawing all complete r.ft. 575.00 575.00 1,850.00
Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
8.06

Providing, fabricating and Fittings


Boundary metal main gate with all
necessary fittings all complete. sq. ft. 84.00 84.00 650.00
8.08 Providing and Constructing Septic tank
and Soak Pit with necessary fittings all
complete as per design, specification
and instruction of site engineer all
complete

Nos. 1.00 1.00 250,000.00


Comparision Sheet

Quantity
I/No. Description of Works Unit Quantity (Previous) Rate (NPR)
8.09

Providing, fabricating and fixing 16


gauge Iron Main gate with all necessary
fittings ang enamel paint finish all
complete as per design, specification
and instruction of site engineer. sq.ft. 160.00 160.00 935.91
Total Amount (Civil) 33,499,405.08
VAT(13%)
Total 37,854,327.74
Comparision Sheet

Amount
(NPR) Rmks

19,071.36

117,207.10

76,486.30
Comparision Sheet

Amount
(NPR) Rmks

153,647.75
Comparision Sheet

Amount
(NPR) Rmks

554,875.80

8,246,492.68

1,561,041.15
Comparision Sheet

Amount
(NPR) Rmks

7,725,469.15
Comparision Sheet

Amount
(NPR) Rmks

287,107.98
1,327,378.12

300,000.00

1,258,323.51

1,579,311.36
Comparision Sheet

Amount
(NPR) Rmks

832,167.94
Comparision Sheet

Amount
(NPR) Rmks

1,949,623.54

500,820.72

772,186.24
289,515.23

479,286.23

179,751.78
Comparision Sheet

Amount
(NPR) Rmks

259,304.77
Comparision Sheet

Amount
(NPR) Rmks

97,361.04
924,450.89

752,519.95

46,170.00
316,348.80

86,066.50
Comparision Sheet

Amount
(NPR) Rmks

176,753.52

93,604.55

143,965.52

875,000.00

1,063,750.00
Comparision Sheet

Amount
(NPR) Rmks

54,600.00

250,000.00
Comparision Sheet

Amount
(NPR) Rmks

149,745.60
33,499,405.08
4,354,922.66
37,854,327.74
903
1928.6784
318.5
121.25 44.75
727.5 268.5 996
676.1475
287.7664 22.58333 48.16667 1087.764
22.58333 131.25 2964.063
4051.826
3276.875
1151.5
Slab Area 4428.375 4203.375
Plaster in 9' wall 3580.76
Staircase area 128.82