EPCC Services for Improvement for Security Defense of CPF1 & Ev. Ponds
SYSTEM No :
F&C: PCH
4. Instrumental 8. Others
Security Department
2.2 The GRE main piping system netwrok for ditch filling . A
2.3 The GRE piping system branhcing netwrok for ditch filling . B
3.0 ELECTRICAL
3.19 Identification tags shall be provided for all MCBs and other B SAN
components inside the LDBs.
3.20 LV cable from pole transformer to OPF distribution board to A SAN
be laid and connected.
3.21 Lighting pole earthing to be installed A SAN
3.22 Lighting pole LV cable connections to be completed A SAN
3.23 Cable route markers to be installed along the route of B SAN
lighting cable.
3.24 Guard room No.1 DB main cable to be terminated A SAN
3.25 Guard room No. 1 earthing inspection pits to be installed. A SAN
3.26 All lighting switches and sockets in guard towers and gurad B SAN
rooms to be sealed properly
3.27 power cable for Gate motor to be laid and connected A SAN
3.28 Outdoor DB door not closing properly to be rectified B SAN
3.29 Search Light for guard towers to be provided and installed B SAN
5.0 5- CIVIL
5.1 Guard tower red tile roof openings to be closed / repair B SAN
5.14 Guard tower spetic tanks vent pipe to be installed (All) B SAN
5.15 Guard tower water tank structure paint to be repaired (All) B SAN
5.25 Bearm cut for drain water to be repaired (conection and B SAN
slope)
5.28 to provide T wall both side of patrol road at flare pipe rack B SAN
5.29 Asphalt road joints not smooth, need to repair B SAN
5.30 maintain proper slope for asphalt road at intersections with B SAN
the concrete road to evaporation bond area.
5.37 complete the level up the area between south asphalt road B SAN
and CPF1 fence
5.38 level up the area around guard tower No.7 B SAN
5.39 complete installation of steel fence above CPF1 brick wall B SAN
5.40 complete wall cap, plastering, and painting B SAN
5.41 repair wall cracked area and repaint. B SAN
5.42 complete grout of OHTL Poles B SAN
5.40 complete grout of light poles B SAN
5.41 backfill around OTHL pole foundation at east side B SAN
6.0 6-HSE
6.1 Asphalt and construction waste to clear from site B SAN
6.2 Fire extinguisher at guard tower to be in place B SAN
6.4 Signage and road sign along the new road B SAN
* Legend
Category A: Shall be completed and accepted before PA
Category B: May be completed and accepted after PA, but prior to FA
UNCH LIST
f CPF1 & Ev. Ponds
DATE
27 Feb. 2017
27 Feb. 2017
27 Feb. 2017
27 Feb. 2017
REMARKS