Professional Documents
Culture Documents
although offering the advantage of simplicity, was not the best at, PHASE
method to employ. Rather, it was noted that switching-surge 1t2
line design should be based on a probability of switching-surge
flashover or, preferably, the line insulation design should be t2-4
based on the probability of line outage-a combination of light-
t3
ning and switching-surge flashover probabilities [1]. 7AP
Previous estimates of UHV transmission line design have -/ts >-1& PHASE 3
employed the selection criterion as discussed previously [2], [3]. t'o
However, the importance of the use of probability methods in
switching-surge design is accentuated at UHV. It is believed Fig. 2. Random selection of closing times for aiming point to;
At are Gaussian deviates about to.
that the present switching-surge flashover probability for 550-kV
lines is extremely low. If this assumption is shown to be correct
by operating records, then increases in the design probability of distribution of occurrence is only composed of the absolute case
flashover could be made. peak voltages; i.e., the maximum surge voltage on any of three
Investigations into the estimates of switching-surge flashover phases irrespective of its polarity. That is, the surge voltages
probabilities have been performed by many noted investigators appearing on the other two phases were assumed to be sufficiently
[4]-[7]. However, a need exists for a simple, accurate method low in magnitude that they would not significantly contribute to
[8]. the total line flashover probability. It has also been tacitly
This paper presents a method to estimate the probability of assumed that surge voltages appearing later or earlier in time,
switching-surge flashovers on transmission lines. However, but on the same phase as the absolute peak voltage, did not
any simplified method requires two obvious assumptions: 1) significantly alter the total line flashover probability, either.
the frequency of occurrence of switching-surge voltages, and 2) Therefore, a miniature system study was performed to in-
the probability of flashover of tower insulation as a function of vestigate the probability distribution and the validity of the
voltage. Although the switching-impulse flashover probability above assumptions. The results of this study were then used
has been shown to approximate a cumulative Gaussian distri- to produce sets of curves from which estimates of the switching-
bution to at least 4or below the CFO voltage [9], the frequency surge flashover probability can be obtained.
function of the occurrence of a switching surge is not known with
a similar degree of accuracy. MINIATURE SYSTEM STUDY
In addition, it has been common practice to assume that the To investigate the frequency of occurrence of switching-surge
voltages, a 125-mile 1100-kV line was set up on the ANACOM
Paper 70 TP 38-PWR, recommended and approved by the Trans- as shown in Fig. 1. A single line-to-ground fault was placed at the
mission and Distribution Committee of the IEEE Power Group for end of the opened line, resulting in a trapped charge voltage of
presentation at the IEEE Winter Power Meeting, New York, N. Y., i 1.0 pu on the unfaulted phases when the breakers were opened.
January 2.5-30, 1970. Manuscript submitted September 16, 1969;
made available for printing December 3, 1969. The breaker was then reclosed onto the line with the fault re-
A. R. Hilemen and P. R. Leblanc are with the Westinghouse moved. The 1-pu voltage reference was chosen as the peak line-
Electric Corporation, East Pittsburgh, Pa. 15112. to-ground steady-state voltage on the line side of the transformer
G. W. Brown is with the University of Pittsburgh, Pittsburgh,
Pa. 15213. with the line connected but unloaded. Under this condition
1456 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, SEPTEMBER/OCTOBER 1970
the voltage at the end of the line was 1.035 pu. With the line
disconnected the voltage on the line side of the transformer
was 0.90 pu. ~-3.0
Two cases were studied: 1) a circuit breaker with no resistor 2.8
inserted in the closing stroke, and 2) a circuit breaker with a w
. Ms
first breaker contact were assumed to be normally distributed >t'
cr
2.2
CLOSING
't 00 Ms 't
about uniformly random aiming points to over a 16.67-ms in- zo
terval, as shown in Fig. 2, where At,, /t2, and At3 are Gaussian
deviations from the aiming point for each phase. For the case cao
where a 450-ohm resistor was used, the second breaker contact 1.8
was assumed to close 10 ms after the first contact. No prestrike
of the breaker contacts was assumed.
6 4' i2' i4'6/
1.0
there are 343 combinations of closing times for the three phases.
J
ao,p, percent
Maximum voltage
TABLE I
SUMMARY OF RESULTS-NO-INSERTION RESISTOR
a,.
4
t>
, 28-
0
co
ef
34
3.2
r%.
tA
_ ,~ ~ I.
+
T~~~~~~~~~~~~
:1-1
ILI .I.I. I.L
I _I
I~~~~~I I'
1457
43 _I I
1.2 1.6
1.4 Is 2.0 2.2 2.4
NEXT HIGHEST PEAK OF SAME POLARITY ON PEAK PHASE,PU VOLTS
(a)
<3.4 _-1'
0 32 --- 4 -__ - -
0~
I-.
4.
,'1B
1.6 EXT 2P
2.0 Z4 L T VO L a
:1
99.9
99s
with means and standard deviation as shown, where l/L is the CO 99.-
IOOCASES SES
per-unit line length as measured from the sending end. The 50 CASES, / 5 CASES
results are summarized in Table I.
I-
2 Q
> 95
98-
-
I/7 '
/I .
It can be seen that the mean and the standard deviation are
C-
Cl) i 90 -
fairly linear with per-unit distance l/L; that oo/IL ranges between ,, 80
10 and 11 percent; and that the upper truncation, the point Ir 70
50
above the mean throughout the length of line considered. 2.0 2.2 2.4 2.6
ABSOLUTE PEAK OVERVOLTAGE
2.8 3.0 3.2 34
z
Z 60
lr
a P.j . 0
4
y
c
0 CLe
_
_- _
1
1.4
U)
-- i
& r- I, . u
IL) L~ L4 l U
1.2 1.3 1.4 L5 1.6 1.7
-I -I
ABSOLUTE PEAK VOLTAGE, P U 0
CD AC - - -
4n
(a)
j)
b
(b)
Fig. 11. Scatter diagrams for single-step resistor cases. (a) Absolute
case peak voltage versus second highest peak voltage of same
polarity on same phase. (b) Absolute case peak voltage versus sec-
ond highest phase peak of same polarity.
CUMULATIVE PROBABILITY, PER CENT
Fig. 10. Extreme value regression lines representing cumulative of 0.7 ms; actual closing times were permitted to vary 42at
probability of occurrence for four points on line (1/L = 0, 1/3,
2/3, 1) for single-step resistor breaker. from the aiming point;
3) a constant resistor insertion time of 10 ms was chosen.
A resistor value of 450 ohms was used, and prestrike was
TABLE II ignored for the reasons mentioned earlier. Absolute peaks were
SUMMARY OF RESULTS-SINGLE-STEP RESISTOR obtained in the same manner as the above no-resistor case, with
the exception that the sending-end absolute peaks were also
Per-unit line length, 1/L 0 1/3 2/3 1 recorded. The resulting histograms for the four points on the
Mode, u 1.17 1.23 1.29 1.33 line illustrate a marked skewness to the high end. The receiving-
Slope 0.072 0.083 0.086 0.091 end histogram is shown in Fig. 9. Since the normal curve will
pl/u,yercent 6.1
1.6
6.8 6.7
1.70
6.8
1.70 not fit this type of distribution, the application of the extreme
Maximum voltage 1.65
Upper truncation 5.8 5.1 4.8 4.1 value function was examined. This is a cumulative probability
points, number of B's function of the form
above mode
P(y) = e-e-Y (2)
where y is a reduced variate defined by
value of 3.05 pu. Therefore, it appears that at least 200 random
cases should be used to obtain a reasonable tail-end fit for a Y=
(x -
u) (3)
distribution with the range of values of 1.2 to 3.3 pu. The number
of cases required will decrease with a decreased range of possible
values. where x is the true variable, per-unit voltage, u the mode, and ,3
the slope on extreme probability paper.
Breakers with Single-Step Insertion Resistor These two quantities can be related to the mean and standard
One method for limiting switching-surge overvoltage is by the deviation of the distribution as follows:
insertion of a resistor for a short period of time (8-10 ms), before / = u + 7(3
the main breaker contacts are closed. Two hundred cases were
generated for this study as follows: -'
1) aiming points for resistor contact were uniform random 0,0= -
(4)
numbers between 0 and 16.66 ms;
2) closing times of the resistor contacts are random normal where -y is Euler's constant, equal to 0.57722. Fig. 10 shows
deviates about this aiming point with a standard deviation the application of extreme value theory to the distribution of
HILEMAN et al.: ESTIMATING SWITCHING-SURGE PERFORMANCE 1459
z
0 z
4
z
U lr
L
a:
I
I-
4
4
A
a:
0
w
a:
ot
(a) -i (a)
U.
J
1-
am
co
S
z
w
a.
>
a:
tD
Di
0.
:
a
U/LCFO /L / CFO
(b) (b)
Fig. 13. Probability of switching-surge flashover for Gaussian Fig. 14. Probability of switching-surge flashover for Gaussian
distribution of switching-surge voltages. distribution of switching-surge voltages.
HILEMAN et al.: ESTIMATING SWITCHING-SURGE PERFORMANCE 1461
o 2t / // / 0 2
° / °2 A/ lN,Q%
t
0- 4t,
6 '/
b,
5.;
/ z w ,/1 'I/I
i
/< 2
_ /x t.Lo __Lflt
2 / 1/ I 6
4 2( 1) / * 4/ (
d 41 1/l l l 4I '
>owN7L,/ 1I I/
85%I -JU.
CD 6
C6 CFO
0.708A 6 .50607:
CFO
04 _4- -I IF 0 C_F
I I I' - ~~~~~~~~~~~~~~~~~~~~~~~~~~N.500
I -~~~~~~~~~~~~~~~~~~~~~~~~~- - 2000
2-
5-. t
CFf-CFF- 1{ t >- 1- t1t1
2o 2-A
w /
0 (L~~~~~~~~~~~~~~~~~~~~~~~~
IX16k -~~~~~-3 __
4; i
4
~~~~~~~21~~~~~~~~~~ Jf~~~.
07080 0.A0
Fig. 15. Probability of switching-surge flashover for Gaussian Fig. 16. Probability of switching-surge flashover for extreme value
distribution of switching-surge voltages, distribution of switchin-surge voltages.
1462 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, SEPTEMBER/OCTOBER 1970
2
/~~~~~~~~~~~~
z -z
o ,/ I 0
/ *~~~~~.r:0%if,
0>I Ie l0
z / / -w-0/
o 2
4 Ix I
-J
4~~~~~~~~~~~~~~~~~~ --_
1
I
I - ~~~~~~~~~~~~~~~~~~~~N:50
~~~~~~~~~~~~~~~---Nd.200
2~~~-
FO.8
4--
08% /
/Ur.O.6 .//
a: 4 --- 4---
er 0/,-/~~5% ccI
w
I.j~~~~ ,
~~~~~~~
> I>-
/~~~~~~~~~~~~~~~ 2
0~~~~~~~~ 6
< 6-~~1
0: It~
II
0.4- 0.060. . . .
/.L/CFO
1FO1-.L/CFO50
(b) (b)~~ -- -20
insulation dimensions can be obtained from laboratory test insulation dimensions significantly. For example, assuming a
data such as shown in [3]. Alternatively, for an existing tower Gaussian distribution of switching-surge voltages, a o0o4 of
design the probability of flashover can be found. 10 percent and a u of 1.5 pu would give a maximum voltage of
2.1 pu at u + 4o-o. Using the previous design rules would result
DISCUSSION OF RESULTS in a CFO of 2.39 pu for a af/CFO of 4 percent. Using Fig. 14(a)
for a probability of 1 X 10-2, the resulting ,/CFO is 0.755 for
Several items in this paper require further discussion, but n = 500. The CFO should therefore be set at 1.99 pu. Assuming a
chief among these is the observation that the results of a minia- linear relation between the CFO and tower strike distance, a
ture system study on a specific system were used to establish the 16.7-percent decrease in insulation distance would be indicated.
assumptions and parameters of the estimating method. Criticism At UHV transmission, control of the maximum switching-
of the miniature system study is justified in that it did not en- surge voltage to 1.5 pu or less has been proposed. As the maxi-
compass various line lengths, sources, fault locations, etc., and mum per-unit over-voltage is decreased, ai (or u) will decrease
did not include the prestrike characteristics of breakers. For and from Figs. 13-18, assuming constant probability, aO/lq
example, additional studies may reveal distributions other (or p3/u) will increase. Therefore, the required CFO voltage will
than the Gaussian or the extreme value are more representative. decrease, as would be expected. However, this decrease in CFO
It should also be noted that the value of o, was fixed at 0.7 ms voltage as determined from these curves should be compared
and the procedure used only permits deviation around the aiming with the decrease in required CFO voltage if it is assumed that
point of 42o-t. Increasing this range may have produced a the CFO voltage decreases in a direct proportion to the per-unit
distribution different from that shown in Fig. 5. It is hoped that overvoltage. Sample calculations, assuming that both CFO volt-
the parameters presented have sufficient variation that the es- ages are equal at 2.0 pu for 1100-kV transmission showed that
timating method will be useful in future studies. the required CFO voltage using the probability method was
The authors employed a "brute force" method of attack in an about 4 percent higher than the CFO voltage for the simple ratio
attempt to determine an exact distribution of occurrence for the method when the maximum voltage decreased from 2.0 to 1.4 pu.
no-insertion-resistor case. Then a 200-case random sampling This is amplified to 7 percent when the strike distances are
method was used for the single-resistor case. However, the compared as a result of the shape of the curve of CFO voltage
"brute force" method suffers from the exhaustive time required, versus strike distance.
whereas the limited random sample method does not produce the Also, it appears that as the maximum voltage is decreased the
exact distribution and may vary depending upon the random ratio of uJdr (or u,/u,) increases. This factor would increase
numbers used. Since only the tail of the distribution is of im- the required CFO voltage. Sample calculations showed that the
portance, alternate methods should be considered. For example, a required CFO voltage is increased by an additional 2 percent
short search at various aiming points could produce a curve over that calculated above. That is, considering the increase of
such as that of Fig. 3. This could be followed by a topological 141,4 the decrease of ao4, and the decrease of u, the probability
search at these aiming points such as illustrated in Fig. 4. method calculations indicated a CFO voltage about 6 percent
From these figures, the distribution could be accurately esti- higher than that calculated using the simple ratio method. This
mated. It was recently noted that H. Glavitsch of CIGRE Work- again is amplified to about 9 percent when the strike distances
ing Group 33.02 independently proposed a similar method. are compared.
It presently appears that a large magnitude of effort has been
and is being devoted to the determination of tower insulation
flashover characteristics, whereas the effort devoted to the SUMMARY AND CONCLIJSIONS
determination of the probability distribution of occurrence and 1) The results of a miniature system study showed that the
its variables has been at a low level. It is hoped that other frequency distribution of absolute case peak voltage approximates
investigators will perform studies to adequately determine this either a Gaussian or an extreme value distribution.
distribution and its parameters. Field studies would also help to 2) Analysis of the above results indicated that for the system
determine the probability distribution. studied, the voltages on the other two phases and the voltage
Using the curves of Figs. 13-18 gives an estimate of the prob- peaks (other than the absolute peak voltage) on the same phase
ability of switching-surge flashover per breaker operation. do not significantly contribute to the total line flashover prob-
However, the primary design criterion is outage rate, which ability.
is a function of both the lightning and switching-surge flashover 3) From the results of the above study, parameters were
probabilities. If, for example, the lightning flashover rate is 1 assumed for the frequency of occurrence of switching-surge
per year for a 100-mile line and the switching-surge flashover voltages and combined with the probability of flashover of
probability when reclosing after a lightning flashover is 1 X 10-2 tower insulation to obtain curves that can be used to estimate
per switching operation, then the outage probability for this the probability of switching-surge flashover of a transmission
case is 1 X 10-2 or 1 in 100 years for a 100-mile line. Considering line.
UHV transmission design, it appears that the lightning flash- 4) "Brute force" and random sampling methods were used to
over rate may decrease, and therefore a higher switching-surge obtain the probability of occurrence frequency distribution.
flashover rate could be permitted to achieve the same outage Since only the tail of the distribution is important, other methods
rate. are suggested to accurately obtain the distribution in this
The curves of Figs. 13-18 indicate that the switching-surge probability area.
flashover rates using the design criterion of maximum switching- 5) Maintaining a constant probability of switching-surge
surge equals CFO -3f are extremely low. Therefore, if this flashover, decreasing the maximum switching-surge voltage
observation is verified by operating experience at 550 kV, does not produce a proportional decrease in the required CFO
consideration should be given to using a design probability of voltage or the tower strike distance.
switching-surge flashover in the range of 1 X 10-2 or per 100 6) Switching-surge design criterion used at 550 kV results in
breaker operations. This could decrease the required tower probabilities of switching-surge flashover of less than 1 in 1000
1464
APPENDIX I
SIGNIFICANCE OF SECONDARY VOLTAGE PEAKS
Only the absolute peak voltage, the highest voltage that
occurred on any of the three phases after the switching operation,
was considered in the calculation of line flashover probability.
Fig. 19 shows how the total probability is accumulated as the
deviation above the mean A or mode B increases toward the
maximum overvoltage at 4o0O or 5t. Various probability levels
were obtained by varying both the location of the CFO and the
value of its standard deviation (4-8 percent). In the case of the
no-resistor breaker, the highest secondary peak on the same
phase and of the same polarity as the absolute peak was at the
-0.5-ro level, and it is obvious from Fig. 19(a) that these may be
neglected. Regarding the next highest phase peak, only one of the
remaining two phases will have a peak of the same polarity
of significant value. Since this peak is at most equal to the
absolute peak, the total flashover probability will no more than
double when the effect of its probability is included. However,
for cases where the overall probability of flashover is very low
(i.e., 1 per 1000) and the standard deviation of the CFO is small
(4 percent), the assumption of using only absolute peaks results
in very little error.
For example, as stated earlier, the second highest phase peak
had a maximum of 2.7 pu, or 1.50o above the mean. Since
nothing is known about the distribution of these peaks, it is
assumed that for all absolute peaks less than 2.7 pu, the next
highest phase peak is of equal magnitude; for all absolute peaks
greater than 2.7 pu, let it be equal to 2.7 pu. Consider the case in
Fig. 19(a) with a probability of 1.8 X 10-3. The probability of
3
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, SEPTEMBER/OCTOBER 1970
z
w
U
w
a.
c
(0
Co um
ak:
> tu
Jo
LLI
>h
0\
(L
-J
LOX
cr:
LJ
o:
100
60
DEVIATION ABOVE THE MEAN,MULTIPLES OF°o
CU *-07
N.500
O--'wi-"Yv0
I.0 .0
(a)
f/CFO -O04
'f/CFO.0S/'
3D 4ID
_
P.L3xt5e
t
(b)
Fig. 19. Accumulation of line flashover probability P. (a) For no-
,resistor breaker case using Gaussian distribution. (b) For single-
step resistor breaker case using extreme value distribution.
APPENDIX II
PROBABILITY OF LINE FLASHOVER
0
A
line flashover accumulated up to the 1.5ao point is only 0.1 INCLUDING ALL PEAK VOLTAGES
percent of the total or 1.8 X 10-6. This is so small in comparison
with the total that it may be ignored. The probability of occur- The significant parameters of a given surge that will affect
rence for values greater than 1.5ao is 0.06681, and the probability the probability that the surge will cause flashover are the
of flashover at 2.7 pu, determined from the CFO and o,a is 4.3 X voltage magnitude, voltage polarity, and waveshape. For a given
10-6. Assuming also that the 2.7-pu secondary peak is present tower structure, surge voltage, polarity, and waveshape, it can
across the entire line, 500 towers, the contribution to the total be assumed with reasonable confidence [9] that the relation
probability is between voltage magnitude and flashover probability is the
cumulative normal distribution, with parameters CFO and 07f.
P = (500) (0.06681) (4.3 X 10-6) = 1.4 X 10-4. Both of these parameters will be dependent on polarity and
The probability based on only absolute peaks was 1.8 X 10-3, waveshape. If it is assumed that one parameter w is sufficient to
so there is a difference of more than an order of magnitude be- describe waveshape, the probability of flashover of a given tower
tween the two. Therefore, based upon these very conservative structure can be expressed
assumptions, the error would be no more than 10 percent. A P(V,w).
similar calculation was performed for a crf of 8 percent and a
flashover probability of 4.5 X 10-3 with the additional assump- A surge voltage VI at tower 1 on a given line will yield prob-
tion that the 2.7-pu secondary phase peak decreased linearly abilities
across the line with 1.9 pu at the sending end. This resulted in a
P(V1,W1),P(V2,W2), ' * * 2 P(VkiWk)i * *P(Vn,wn) ...
l-j
14 Discussion
_yr
TABLE III
INDICATION OF MAXIMUM LIKELY ERROR IN TOWER WINDOW CLEARANCE OBTAINED BY USING FIG. 22
With the surge distribution defined the flashover probability can REFERENCES
be written as a function of the assumed maximum surge voltage [10] N. D. Reppen, "Significance of assumptions in switching-surge
Vmax and CFO: flashover calculations," Paper 70 CP 39, presented at the
IEEE Winter Power Meeting, New York, N. Y., January
PFO = F" V(ax 25-30, 1970.
[11] S. Annestrand, E. F. Bossuyt, and N. D. Reppen, "Insulation
analysis of a 500-kV transmission line design," IEEE Trans.
Fig. 21 shows three switching-surge distributions representing Power Apparatus and Systems, vol. PAS-89, pp. 429-437,
three classes of different surge distribution severity. This may March 1970.
seem like a rather rough classification but up till now very few
investigations, if any, have succeeded in establishing the composite
surge distribution with an accuracy requiring a finer classification.
Fig. 22 shows the probability curves for the three classes of surge
distribution severity. These curves were evaluated from the base A. J. McElroy (American Electric Power Service Corporation,
case of [10] and include the following assumptions. New York, N. Y.): The authors have prepared a thought-provoking
1) On the average the surge voltages decrease with 0.4 percent paper on a timely subject. From their list of references it would
per mile from the receiving end. The relative surge magnitude along appear that the overvoltage probability aspect of transmission line
the line is later referred to as the surge profile. switching-surge reliability has remained dormant for some 3
2) The effects of air density and humidity are included using the years. Perhaps in the interim period it has proven a more simple
results of a weather based analysis for Portland, Oreg. [11]. The and direct task to publish laboratory data on transmission tower
weather correction statistics for Portland are typical for sea-level flashover behavior than to come to grips with what the authors have
locations with moderate humidity. again demonstrated to be a highly complex problem in overall
To the extent that these assumptions are not representative for line design.
the particular transmission line considered, the flashover prob- The authors present a plethora of original ideas based on the
abilities will be in error. Since the significance of a certain deviation exhaustive study of a particular transmission system. By presenting
in the flashover probabilities is not always apparent, the investiga- a self-criticism they acknowledge that the validity of their results
tion described in [10] gives the effect of erroneous assumptions in may be restricted in application to an extent yet unknown. There-
terms of tower window clearance. fore, many questions this discusser might raise are best withheld
Table III contains an indication of the error in tower window until the other investigations the authors call for are carried out.
dimensions resulting when the estimating curves in Fig. 22 are used Perhaps the authors would consider the following specific ques-
and the differences between actual and assumed surge profiles and tions. With what statistical confidence do the Gaussian and their
weather correction statistics are quite extreme [101. The surge distri- extreme value distributions fit the data of Figs. 5 and 9, respec-
bution column indicates the maximum possible clearance error, tively? Since the overvoltage distribution functions must be sub-
assuming that the proper distribution severity class is used. It can ject to a cutoff (truncation), then by what approximate factor will
be concluded from this table that: the probability of flashover per switching operation be modified by
1) the significance of misjudgments increases with the maximum assuming a smooth (continuous second derivative) functional
surge voltage and the voltage level; transition between either the Gaussian or their extreme value dis-
2) assuming that the surge distribution is correctly classified in tribution and the voltage level of truncation?
one of the three classes, the surge profile and the weather correction In the text the authors suggest that consideration be given to
are at least as critical as the surge distribution itself; designing a transmission line for 1 switching-surge flashover per 100
3) the curves should be quite adequate for 345 kV and below, and breaker operations. This significant suggestion is however apparently
may be used for preliminary investigations at 500-kV, 765-kV, and obscured in their summary and conclusions where they call upon a
UHV voltages. rather different arguement, i.e., that of 1 flashover per 100 years or
The use of the curves may be best illustrated by an example. less. Based on [6] the discusser suggests that the following reliability
Consider a 500-kV line 3000 feet (915 meters) above sea level. criterion be considered: with 99.9-percent confidence require that
What is the required tower window CFO voltage that will produce the number of flashovers be no more than 1 per 100 breaker oper-
1-percent probability of flashover if the maximum surge (Vmax) is ations; on this basis specify the mean flashover rate, the precise
2.0 pu and the composite surge distribution is classified as moderately level being established by suitable statistical procedures once an
severe? It is seen that V1max/CFO = 0.87 and with Vmax = 2.0 X appropriate density function is established-in [6] a Poisson func-
500 X V/2/3 = 816 kV, a CFO of 816/0.87 = 940 kV is required. tion is assumed whereby the mean flashover rate for the present
This value may now be corrected to sea-level conditions and the example would be significantly reduced to 1 per 500 breaker opera-
proper clearances evaluated based on flashover test data. Table III tions. Once the adjusted mean is established, the procedure sug-
indicates that in the worst case the clearance estimated is not likely gested in the paper might be pursued. (In this regard would the
to be off by more than 1 foot (0.3 meter), and less than one-half of authors define the meaning of s and 1ii.)
this would be on account of the switching-surge distribution; 1 In conclusion, the discusser notes with great interest the authors'
foot is thus a proper safety adder for the tower window clearance. suggestion of a topological search. Relations should be established
The authors have presented a very interesting paper and it is to- obtain the overvoltage probability density function directly
hoped that they, as well as other investigators having access to a from the constant voltage contours of Fig. 4, once a breaker closing
transient network analyzer, will continue to use these tools for this probability function, even in its most general form, has been as-
type of general studies and that results will be reported in this signed.
TRANSACTIONS. What is particularly needed in the future is some
investigation of distributions composed from several system condi-
tions and some thinking on how distributions will change with time. Manuscript received April 9, 1970.
~~
1468 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, SEPTEMBER/OCTOBER 1970
TABLE IV
500-KV DESIGN DEMONSTRATION
distribution and a reasonable ratio of 0.8 between sending and and above. In this regard, the authors feel that a comment on dis-
receiving ends is only about 10 times that of the normal distribution tribution severity is in order. It seems clear that above 500 kV,
with level voltage. Therefore, either one of these combinations increasing efforts will be made to reduce the maximum switching
appears reasonable for future coordination work. surge by use of preinsertion resistors and/or controlled closing of the
This is truly a fine and most imnportant paper. breaker. Such measures will reduce absolute maximums, but will
result in more "moderately high" voltage surges. That is, the slope of
REFERENCES Fig. 21 will be reduced and the meaning of distribution severity
[12] EHV Transmission Line Reference Book. New York: Edison becomes less clear.
Electric Institute, 1969, ch. 6. In contrast to Mr. Reppen, the authors are of the opinion that the
tail of the overvoltage distribution is of prime importance and
methods are needed to describe this portion of the curve more
accurately. We agree with Mr. Reppen that the variation of weather
conditions is of importance and must be considered in the line in-
sulation design. The discusser's approach appears to be to employ a
Andrew R. Hileman, P. R. Leblanc, and Gordon W. Brown: The statistical distribution of all hourly weather observations. However,
authors are indebted to the discussers for their excellent critiques of since as assumed in the paper, the majority of high-speed-reclose
the paper, which add greatly to its usefulness. breaker operations occurred during and as a result of lightning, it
As mentioned in the paper, Mr. Glavitsch has proposed a method would be logical to segregate weather distributions into two classes;
for determining the tail of the frequency distribution of switching- i.e., those conditions that may produce high-speed circuit-breaker
surge magnitudes. This method is similar to that referred to as a reclose operations that produce the higher values of overvoltage
topological search technique in the paper. We are indebted to Mr. and those weather conditions during which no high-speed reclosing
Glavitsch for his further discussion of his proposal. will be employed. Of these two conditions, the first is of major
In answer to Dr. Clerici and Dr. Colombo, equal aiming points importance in assessing the system's reliability and therefore should
were assumed for the three circuit breakers. That is, a class of be separately analyzed for its outage probability.
breaker was assumed instead of specific breakers on a particular Mr. Reppen's comment on the effects of multiple peaks is well
line, in which case, each of the three breakers could possess different made. The effect of previous voltage surges on the flashover prob-
aiming points. ability of the surges is not well known. The effect of an opposite
From Fig. 19 it is noted that only 2 to 4 percent of the tail of the polarity bias voltage has been investigated with conflicting results,
frequency distribution is of importance in determining the prob- and therefore at 500 kV most designers neglected this effect. In this
ability of line flashover. The problem then is to determine a method paper, the second peak was assumed to be independent of the first
that can be used to determine this part of the distribution curve peak. However, additional laboratory investigations of this param-
with sufficient accuracy. The most important single value is the eter are needed.
maximum overvoltage. This value can be found easily but its The authors agree fully with Mr. Reppen's last comment about
probability of occurrence is difficult. As shown in Fig. 8, even 200 the need for a composite distribution and an assessment of its
cases appears questionable with regard to an adequate description of possible changes with time.
the frequency distribution when the maximum overvoltage is 3.3 Regarding Dr. McElroy's first question, for the Gaussian case
pu. However, the number of random cases required tends to decrease Fig. 6 shows the assumed normal curve (dashed line) superimposed
as the maximum overvoltage decreases. In this paper, the "brute over a curve fit through the actual data points, and the corre-
force" or systematic method was used to develop the frequency spondence appears to be fairly good above the 80-percent probability
distribution when no preinsertion resistors were used in the breaker. level. Confidence intervals were used, however, for the extrerme value
This laborious method is certainly not suggested for normal use. distribution based on 200 cases. Nearly all data fell within 1 standard
We hope that other methods, such as the topological search, can be error of the extreme value regression line, except where the reading
developed. If sufficient cases are taken, the random method can be error (± .025 pu) exceeded the standard error.
employed. Dr. McElroy also wishes to know how the probability of flashover
In answer to Dr. Clerici and Dr. Colombos' third question, in this will change if a smooth transition from the assumed distribution to
paper it is assumed that the negative polarity insulation strength is the truncation voltage. This of course is dependent on the kind of
sufficiently greater than that for positive polarity that its effect may tapering that is used and at what point it should begin. Also, the
be neglected in the line flashover calculations. Or in other words, difference will be most evident when the probability of line flashover
V-string insulators are assumed. For vertical string, the negative wet is small (Fig. 19).
strength is equal to or less than the positive wet strength. There- Regarding Dr. McElroy's final point, the probability of flashover
fore, the maximum overvoltage of the three phase voltages was read. per switching operation must be brought into the correct perspective
Assuming this to be positive polarity, the maximum positive polarity by accounting for the number of breaker operations per year. One
voltages on the other two phases were obtained, and the positive operation per year was assumed in the conclusions of the paper,
polarity overvoltage subsequent to or preceding the maximum over- but it is actually quite dependent on environmental conditions,
voltage is recorded. particularly the frequency of lightning storms. Also, the authors
It is agreed that the wavefront of the switching surge is of im- feel that the 99.9-percent confidence suggested by Dr. McElroy
portance in determining the line insulation design. For 1200-1800-Is is much too high for practical purposes.
"smooth" wavefronts,-the CFO voltage increases by 11 to 21-percent One final point is that I,r and ys were not properly defined in the
[3]. However, shorter front voltage spikes on top of the "smooth" paper. The subscripts s and r denote the sending and receiving ends
wave decreases the insulation strength significantly. In this study no of the line, respectively, so that ,S//IT is a measure of the voltage
large variation of wavefronts occurred for the higher magnitude variation along the line.
overvoltages. The authors would like to particularly thank Mr. Price for his
-Mr. Reppen has proposed a simplified method of probability gracious discussion and to also thank him for placing in dramatic
estimation based on average conditions. Although not stated, it perspective the financial advantage of the use of probability methods
in line insulation design. In 1968, when Mr. Price and G. G. Sauv6
appears that Mr. Reppen has assumed a 100-mile line with 5 towers presented [13], the discusser developed his TPROB program to
per mile and a Gaussian frequency distribution of switching-surge determine the required line insulation strength using probability
magnitudes. Average weather conditions are assumed based on analysis.
historical data from Portland at an elevation 30 feet above sea level. Again the authors wish to thank the discussers, all of whom are
Also, it appears that Mr. Reppen has assumed V-strong insulators, recognized experts in this and related fields. Their encouragement and
thus neglecting wind swing and discounting the effects of negative probing comments are appreciated.
polarity flashover.
The method is simple and direct and therefore could be used for
preliminary investigations at 500 kV and above. It is agreed that a REFERENCES
more thorough study of the parameters should be made at 500 kV [131 W. S. Price and G. G. Sauve, "Insulation coordination and
conductor selection for the Churchill Falls 735-kV transmission
lines," presented at the IEEE EHV Conference, Montreal,
Manuscript received April 6, 1970; revised April 16, 1970. P. Q., Canada, September 30-October 2, 1968.