You are on page 1of 20

JMauricio

CRONOGRAMA DE EJECUCION FINANCIERO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

01 TRABAJOS PROVISIONALES

01.01 CARTEL DE OBRA DE 5.40 x 3.60m 797.67 S/. 797.67

01.02 ALQUILER DE OFICINA TECNICA, ALMACEN Y CASETA DE GUARDIANIA 450.00 S/. 450.00

01.03 POZA DE AGUA PARA LA CONSTRUCCION 200.00 S/. 200.00

01.04 CERCO DE PROTECCION CON ARPILLERA 1,227.42 S/. 1,227.42

01.05 INSTALACION PROVISIONAL DE AGUA, DESAGUE Y ELECTRICAS 560.00 S/. 560.00

02 OBRAS PRELIMINARES

02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 3,000.00 S/. 1,500.00 S/. 1,500.00

02.02 LIMPIEZA DE TERRENO MANUAL 1,268.06 S/. 1,268.06

02.03 TRAZO Y REPLANTEO PRELIMINAR 1,100.75 S/. 1,100.75

03 CANCHA DE GRASS SINTETICO

03.01 MOVIMIENTO DE TIERRAS

03.01.01 CORTE DE TERRENO COMPACTO C/MAQUINARIA 252.83 S/. 252.83

03.01.02 EXCAVACION MASIVA C/MAQUINARIA EN TERRENO NORMAL 3,974.13 S/. 1,987.07 S/. 1,987.07

03.01.03 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 674.23 S/. 674.23

03.01.04 NIVELACION INTERIOR Y APISONADO MANUAL 1,636.20 S/. 1,636.20

03.01.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO 223.24 S/. 223.24

03.01.06 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 183.57 S/. 183.57

03.01.07 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 7,434.96 S/. 7,434.96

03.02 CAPA DE SUSTRATO P/GRASS SINTETICO

03.02.01 RELLENO Y COMPACTADO C/AFIRMADO PARA BASE e=6'' 4,001.40 S/. 2,000.70 S/. 2,000.70

03.02.02 RELLENO Y COMPACTADO C/PIEDRA CHANCADA DE 1/2'' e=4'' 5,902.20 S/. 2,951.10 S/. 2,951.10

03.02.03 RELLENO Y COMPACTADO C/ARENA GRUESA e=4'' 5,805.00 S/. 2,902.50 S/. 2,902.50

03.02.04 SUMINISTRO E INSTALACION DE GRASS SINTETICO 39,889.80 S/. 19,944.90 S/. 19,944.90

03.03 OBRAS DE CONCRETO SIMPLE

03.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 1,259.60 S/. 1,259.60

03.04 OBRAS DE CONCRETO ARMADO

03.04.01 ZAPATAS

03.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS 4,245.70 S/. 4,245.70

03.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 1,532.23 S/. 1,532.23

03.04.02 COLUMNAS

03.04.02.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 5,019.17 S/. 2,509.59 S/. 2,509.59

03.04.02.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS 4,470.48 S/. 2,235.24 S/. 2,235.24

03.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 6,011.69 S/. 3,005.85 S/. 3,005.85

03.05 ENSAYOS DE LABORATORIO

03.05.01 PRUEBA DE COMPACTACION DE SUELOS (PROCTOR MODIFICADO - DENSIDAD DE CAM 225.00 S/. 225.00

03.05.02 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) 275.00 S/. 275.00

03.05.03 DISEÑO DE MEZCLA F'C=140, 175 y 210KG/CM2 720.00 S/. 360.00 S/. 360.00

03.06 REVOQUES, ENLUCIDOS Y MOLDURAS

03.06.01 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm 3,101.70 S/. 3,101.70

03.07 PINTURAS

03.07.01 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS 1,376.90 S/. 1,376.90

03.08 CARPINTERIA METALICA

03.08.01 VIGA METALICA PRINCIPAL VMP-001 11,184.74 S/. 3,728.25 S/. 3,728.25 S/. 3,728.25

03.08.02 VIGA DE AMARRE VA-001 7,355.76 S/. 3,677.88 S/. 3,677.88

03.08.03 VIGUETA METALICA VM-001 14,581.92 S/. 7,290.96 S/. 7,290.96

03.08.04 VIGUETA METALICA VM-002 1,480.70 S/. 1,480.70

03.08.05 TEMPLADOR P/DILATACION CON FIERRO Ø 1/2'' 1,965.83 S/. 1,965.83

03.08.06 CANALETA DE F°G° P/ EVACUACION AGUAS PLUVIALES 1,629.44 S/. 1,629.44

03.08.07 MONTANTE DE Ø 4'' P/EVACUACION AGUAS PLUVIALES 623.28 S/. 623.28

03.09 COBERTURA DE TECHO

03.09.01 COBERTURA METALICA TR-4 CURVO-PRECOR INC. ACCESORIOS 32,268.90 S/. 32,268.90

03.09.02 COBERTURA TECHO FIBRAFORTE TRANSPARENTE POLICARBONATO 6mm 11,078.77 S/. 11,078.77

03.10 SISTEMA DE ILUMINACION

03.10.01 SUMINISTRO E INST. DE MEDIDOR DE EE.EE. (A CARGO DE EMPRESA DE SERVICIO) 500.00 S/. 500.00

03.10.02 EXCAVACION MANUAL DE ZANJAS PARA CABLE SUBTERRANEO 22.58 S/. 22.58

03.10.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO 12.56 S/. 12.56

03.10.04 TABLERO GENERAL 456.42 S/. 456.42

03.10.05 POZO DE PUESTA A TIERRA 463.77 S/. 463.77

03.10.06 CABLE NYY 3x1x25mm2 907.19 S/. 907.19

03.10.07 REFLECTOR DE HALOGENURO DE 250 WATTS 1,764.60 S/. 1,764.60

03.11 SISTEMA DE DRENAJE

03.11.01 EXCAVACION MANUAL DE ZANJAS PARA TUBERIAS 597.53 S/. 597.53

03.11.02 RELLENO Y APISONADO MANUAL EN ZANJAS DE TUBERIAS 298.29 S/. 298.29

03.11.03 INSTALACION DE TUBERIA DE DRENAJE DE Ø 4'' 1,377.79 S/. 1,377.79


JMauricio

CRONOGRAMA DE EJECUCION FINANCIERO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

03.11.04 INSTALACION DE TUBERIA DE DRENAJE DE Ø 6'' 590.67 S/. 590.67

03.11.05 SISTEMA DE DRENAJE HORIZONTAL CON GEOCOMPUESTO MAC DRAIN 3,345.98 S/. 3,345.98

03.11.06 CAJA DE REGISTRO DE DESAGUE DE 24'' x 24'' 1,694.45 S/. 1,694.45

03.11.07 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIAS 130.56 S/. 130.56

03.12 EQUIPAMIENTO

03.12.01 SUMINISTRO E INSTALACION DE PORTERIA (ARCOS DE METAL) 1,817.12 S/. 1,817.12

03.12.02 SUMINISTRO E INSTALACION DE MALLA NYLON HILO N° 36 2,295.00 S/. 2,295.00

04 VEREDAS DE CONCRETO

04.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS 72.74 S/. 72.74

04.02 CONCRETO EN VEREDA F'C=140KG/CM2 INC. ACABADO Y BRUÑADO 566.67 S/. 283.34 S/. 283.34

04.03 JUNTAS ASFALTICAS 24.55 S/. 24.55

05 TRIBUNAS

05.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 295.94 S/. 295.94

05.02 NIVELACION INTERIOR Y APISONADO MANUAL 214.52 S/. 214.52

05.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 188.68 S/. 188.68

05.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 385.15 S/. 385.15

05.05 ENCOFRADO Y DESENCOFRADO EN TRIBUNAS 4,703.28 S/. 4,703.28

05.06 CONCRETO F'C=140KG/CM2 EN TRIBUNAS 18,265.00 S/. 9,132.50 S/. 9,132.50

05.07 TARRAJEO PULIDO Y COLOREADO C/OCRE ROJO EN TRIBUNAS 4,096.83 S/. 4,096.83

06 SARDINEL PERDIDO

06.01 OBRAS PRELIMINARES

06.01.01 LIMPIEZA DE TERRENO MANUAL 55.30 S/. 55.30

06.01.02 TRAZO Y REPLANTEO PRELIMINAR 48.00 S/. 48.00

06.02 MOVIMIENTO DE TIERRAS

06.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 321.02 S/. 160.51 S/. 160.51

06.02.02 NIVELACION INTERIOR Y APISONADO MANUAL 116.35 S/. 116.35

06.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 204.67 S/. 204.67

06.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 417.79 S/. 417.79

06.03 OBRAS DE CONCRETO SIMPLE

06.03.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL PERDIDO 1,999.87 S/. 999.94 S/. 999.94

06.03.02 CONCRETO F'C=140KG/CM2 EN SARDINEL PERDIDO 1,908.00 S/. 954.00 S/. 954.00

06.04 REVOQUES, ENLUCIDOS Y MOLDURAS

06.04.01 TARRAJEO EN INTERIORES CON IMPERMEABILIZANTE 2,057.47 S/. 2,057.47

07 PORTICO DE INGRESO (01 UND)

07.01 OBRAS PRELIMINARES

07.01.01 LIMPIEZA DE TERRENO MANUAL 7.06 S/. 7.06

07.01.02 TRAZO Y REPLANTEO PRELIMINAR 6.13 S/. 6.13

07.02 MOVIMIENTO DE TIERRAS

07.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 143.17 S/. 143.17

07.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO 39.02 S/. 39.02

07.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 48.29 S/. 48.29

07.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 98.57 S/. 98.57

07.03 OBRAS DE CONCRETO SIMPLE

07.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 311.15 S/. 311.15

07.03.02 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS CORRIDOS 200.47 S/. 200.47

07.03.03 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 35.72 S/. 35.72

07.03.04 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 33.41 S/. 33.41

07.04 OBRAS DE CONCRETO ARMADO

07.04.01 ZAPATAS

07.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS 842.40 S/. 842.40

07.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 200.06 S/. 200.06

07.04.02 VIGAS DE CONEXION

07.04.02.01 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CONEXION 83.23 S/. 83.23

07.04.02.02 CONCRETO F'C=210KG/CM2 EN VIGAS DE CONEXION 99.97 S/. 99.97

07.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 180.54 S/. 180.54

07.04.03 COLUMNAS

07.04.03.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 457.96 S/. 457.96

07.04.03.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS 394.72 S/. 394.72

07.04.03.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 633.53 S/. 633.53

07.04.04 VIGAS

07.04.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS 181.34 S/. 181.34

07.04.04.02 CONCRETO F'C=210KG/CM2 EN VIGAS 197.78 S/. 197.78

07.04.04.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 244.94 S/. 244.94

07.05 ALBAÑILERIA

07.05.01 MURO DE LADRILLO KK AMARRE TIPO CABEZA CON C:A 1:4 e=1.5cm 529.40 S/. 529.40
JMauricio

CRONOGRAMA DE EJECUCION FINANCIERO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

07.06 REVOQUES, ENLUCIDOS Y MOLDURAS

07.06.01 TARRAJEO EN MUROS INTERIORES Y EXTERIORES MEZCLA C:A 1:4 e=1.5cm 378.76 S/. 378.76

07.06.02 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm 244.65 S/. 244.65

07.06.03 TARRAJEO EN VIGAS MEZCLA C:A 1:4 e=1.5cm 160.15 S/. 160.15

07.07 PINTURAS

07.07.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 02 MANOS 202.47 S/. 202.47

07.07.02 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS 162.70 S/. 162.70

07.08 CARPINTERIA DE MADERA Y METALICA

07.08.01 PUERTA METALICA SEGUN DISEÑO INC. COLOCACION, PINTADO Y ACCESORIOS (BISA 1,760.09 S/. 1,760.09

08 CERCO PERIMETRICO TIPO M-001 LONG.=80.60ml

08.01 OBRAS PRELIMINARES

08.01.01 LIMPIEZA DE TERRENO MANUAL 69.64 S/. 69.64

08.01.02 TRAZO Y REPLANTEO PRELIMINAR 60.45 S/. 60.45

08.02 MOVIMIENTO DE TIERRAS

08.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 707.47 S/. 353.74 S/. 353.74

08.02.02 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 451.13 S/. 451.13

08.02.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 920.88 S/. 920.88

08.03 OBRAS DE CONCRETO SIMPLE

08.03.01 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS CORRIDOS 7,969.18 S/. 3,984.59 S/. 3,984.59

08.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 1,919.41 S/. 959.71 S/. 959.71

08.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 1,102.65 S/. 1,102.65

08.04 REVOQUES, ENLUCIDOS Y MOLDURAS

08.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm 987.67 S/. 987.67

08.05 PINTURAS

08.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS 527.97 S/. 527.97

08.06 CERCO DE MALLA OLIMPICA

08.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA 5,187.42 S/. 2,593.71 S/. 2,593.71

08.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES 7,154.66 S/. 3,577.33 S/. 3,577.33

09 CERCO PERIMETRICO TIPO M-002 LONG.=34.60ml

09.01 OBRAS PRELIMINARES

09.01.01 LIMPIEZA DE TERRENO MANUAL 49.82 S/. 49.82

09.01.02 TRAZO Y REPLANTEO PRELIMINAR 43.25 S/. 43.25

09.02 MOVIMIENTO DE TIERRAS

09.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 1,240.21 S/. 620.11 S/. 620.11

09.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO 196.42 S/. 196.42

09.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 574.04 S/. 574.04

09.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 1,171.78 S/. 1,171.78

09.03 OBRAS DE CONCRETO SIMPLE

09.03.01 CONCRETO CICLOPEO F'C=140KG/CM2 + 70% P.G. EN MURO DE CONTENCION 7,416.71 S/. 3,708.36 S/. 3,708.36

09.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 823.96 S/. 823.96

09.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 473.87 S/. 473.87

09.04 REVOQUES, ENLUCIDOS Y MOLDURAS

09.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm 423.99 S/. 423.99

09.05 PINTURAS

09.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS 226.65 S/. 226.65

09.06 CERCO DE MALLA OLIMPICA

09.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA 2,226.86 S/. 1,113.43 S/. 1,113.43

09.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES 3,130.16 S/. 1,565.08 S/. 1,565.08

10 LIMPIEZA DE OBRA

10.01 LIMPIEZA FINAL DE OBRA 748.51 S/. 748.51

11 FLETE TERRESTRE

11.01 FLETE TERRESTRE 6,000.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00

12 CAPACITACION (CURSO Y TALLER)

12.01 CAPACITACION (CURSO Y TALLER) 3,000.00 S/. 1,500.00 S/. 1,500.00

13 MITIGACION E IMPACTO AMBIENTAL

13.01 MITIGACION E IMPACTO AMBIENTAL 5,000.00 S/. 2,500.00 S/. 2,500.00

COSTO DIRECTO 308,887.05 S/. 74,278.38 S/. 130,960.74 S/. 103,647.93

GASTOS GENERALES (9% C.D.) 27,799.83 6,685.05 11,786.47 9,328.31

SUPERVISION (5% C.D.) 15,444.35 3,713.92 6,548.04 5,182.40

EXPEDIENTE TECNICO (3.5% C.D.) 10,811.05 2,599.74 4,583.63 3,627.68

PRESUPUESTO TOTAL DE OBRA 26,255.40 S/. 6,313.66 S/. 11,131.66 S/. 8,810.08

PORCENTAJE DE AVANCE 24.05% 42.40% 33.56%


JMauricio

CION FINANCIERO DE OBRA

PPTO
S/.

S/. 797.67

S/. 450.00

S/. 200.00

S/. 1,227.42

S/. 560.00

S/. 0.00

S/. 3,000.00

S/. 1,268.06

S/. 1,100.75

S/. 0.00

S/. 0.00

S/. 252.83

S/. 3,974.13

S/. 674.23

S/. 1,636.20

S/. 223.24

S/. 183.57

S/. 7,434.96

S/. 0.00

S/. 4,001.40

S/. 5,902.20

S/. 5,805.00

S/. 39,889.80

S/. 0.00

S/. 1,259.60

S/. 0.00

S/. 0.00

S/. 4,245.70

S/. 1,532.23

S/. 0.00

S/. 5,019.17

S/. 4,470.48

S/. 6,011.69

S/. 0.00

S/. 225.00

S/. 275.00

S/. 720.00

S/. 0.00

S/. 3,101.70

S/. 0.00

S/. 1,376.90

S/. 0.00

S/. 11,184.74

S/. 7,355.76

S/. 14,581.92

S/. 1,480.70

S/. 1,965.83

S/. 1,629.44

S/. 623.28

S/. 0.00

S/. 32,268.90

S/. 11,078.77

S/. 0.00

S/. 500.00

S/. 22.58

S/. 12.56

S/. 456.42

S/. 463.77

S/. 907.19

S/. 1,764.60

S/. 0.00

S/. 597.53

S/. 298.29

S/. 1,377.79
JMauricio

CION FINANCIERO DE OBRA

PPTO
S/.

S/. 590.67

S/. 3,345.98

S/. 1,694.45

S/. 130.56

S/. 0.00

S/. 1,817.12

S/. 2,295.00

S/. 0.00

S/. 72.74

S/. 566.67

S/. 24.55

S/. 0.00

S/. 295.94

S/. 214.52

S/. 188.68

S/. 385.15

S/. 4,703.28

S/. 18,265.00

S/. 4,096.83

S/. 0.00

S/. 0.00

S/. 55.30

S/. 48.00

S/. 0.00

S/. 321.02

S/. 116.35

S/. 204.67

S/. 417.79

S/. 0.00

S/. 1,999.87

S/. 1,908.00

S/. 0.00

S/. 2,057.47

S/. 0.00

S/. 0.00

S/. 7.06

S/. 6.13

S/. 0.00

S/. 143.17

S/. 39.02

S/. 48.29

S/. 98.57

S/. 0.00

S/. 311.15

S/. 200.47

S/. 35.72

S/. 33.41

S/. 0.00

S/. 0.00

S/. 842.40

S/. 200.06

S/. 0.00

S/. 83.23

S/. 99.97

S/. 180.54

S/. 0.00

S/. 457.96

S/. 394.72

S/. 633.53

S/. 0.00

S/. 181.34

S/. 197.78

S/. 244.94

S/. 0.00

S/. 529.40
JMauricio

CION FINANCIERO DE OBRA

PPTO
S/.

S/. 0.00

S/. 378.76

S/. 244.65

S/. 160.15

S/. 0.00

S/. 202.47

S/. 162.70

S/. 0.00

S/. 1,760.09

S/. 0.00

S/. 0.00

S/. 69.64

S/. 60.45

S/. 0.00

S/. 707.47

S/. 451.13

S/. 920.88

S/. 0.00

S/. 7,969.18

S/. 1,919.41

S/. 1,102.65

S/. 0.00

S/. 987.67

S/. 0.00

S/. 527.97

S/. 0.00

S/. 5,187.42

S/. 7,154.66

S/. 0.00

S/. 0.00

S/. 49.82

S/. 43.25

S/. 0.00

S/. 1,240.21

S/. 196.42

S/. 574.04

S/. 1,171.78

S/. 0.00

S/. 7,416.71

S/. 823.96

S/. 473.87

S/. 0.00

S/. 423.99

S/. 0.00

S/. 226.65

S/. 0.00

S/. 2,226.86

S/. 3,130.16

S/. 0.00

S/. 748.51

S/. 0.00

S/. 6,000.00

S/. 0.00

S/. 3,000.00

S/. 0.00

S/. 5,000.00

S/. 308,887.05

27,799.83

15,444.35

10,811.05

S/. 26,255.39

100.00%
JMauricio

CRONOGRAMA DE EJECUCION FISICO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

01 TRABAJOS PROVISIONALES

01.01 CARTEL DE OBRA DE 5.40 x 3.60m 797.67 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

01.02 ALQUILER DE OFICINA TECNICA, ALMACEN Y CASETA DE GUARDIANIA 450.00 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

01.03 POZA DE AGUA PARA LA CONSTRUCCION 200.00 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

01.04 CERCO DE PROTECCION CON ARPILLERA 1,227.42 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

01.05 INSTALACION PROVISIONAL DE AGUA, DESAGUE Y ELECTRICAS 560.00 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

02 OBRAS PRELIMINARES

02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 3,000.00 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

02.02 LIMPIEZA DE TERRENO MANUAL 1,268.06 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

02.03 TRAZO Y REPLANTEO PRELIMINAR 1,100.75 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03 CANCHA DE GRASS SINTETICO

03.01 MOVIMIENTO DE TIERRAS

03.01.01 CORTE DE TERRENO COMPACTO C/MAQUINARIA 252.83 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.02 EXCAVACION MASIVA C/MAQUINARIA EN TERRENO NORMAL 3,974.13 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.03 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 674.23 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.04 NIVELACION INTERIOR Y APISONADO MANUAL 1,636.20 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO 223.24 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.06 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 183.57 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.01.07 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 7,434.96 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02 CAPA DE SUSTRATO P/GRASS SINTETICO

03.02.01 RELLENO Y COMPACTADO C/AFIRMADO PARA BASE e=6'' 4,001.40 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.02 RELLENO Y COMPACTADO C/PIEDRA CHANCADA DE 1/2'' e=4'' 5,902.20 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.03 RELLENO Y COMPACTADO C/ARENA GRUESA e=4'' 5,805.00 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.04 SUMINISTRO E INSTALACION DE GRASS SINTETICO 39,889.80 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00%

03.03 OBRAS DE CONCRETO SIMPLE

03.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 1,259.60 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04 OBRAS DE CONCRETO ARMADO

03.04.01 ZAPATAS

03.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS 4,245.70 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 1,532.23 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.02 COLUMNAS

03.04.02.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 5,019.17 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.02.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS 4,470.48 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 6,011.69 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.05 ENSAYOS DE LABORATORIO

03.05.01 PRUEBA DE COMPACTACION DE SUELOS (PROCTOR MODIFICADO - DENSIDAD DE CAM 225.00 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.05.02 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) 275.00 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.05.03 DISEÑO DE MEZCLA F'C=140, 175 y 210KG/CM2 720.00 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06 REVOQUES, ENLUCIDOS Y MOLDURAS

03.06.01 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm 3,101.70 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.07 PINTURAS

03.07.01 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS 1,376.90 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08 CARPINTERIA METALICA

03.08.01 VIGA METALICA PRINCIPAL VMP-001 11,184.74 0.00% 0.00% 0.00% 33.33% 33.33% 33.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.02 VIGA DE AMARRE VA-001 7,355.76 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.03 VIGUETA METALICA VM-001 14,581.92 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.04 VIGUETA METALICA VM-002 1,480.70 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.05 TEMPLADOR P/DILATACION CON FIERRO Ø 1/2'' 1,965.83 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.06 CANALETA DE F°G° P/ EVACUACION AGUAS PLUVIALES 1,629.44 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.07 MONTANTE DE Ø 4'' P/EVACUACION AGUAS PLUVIALES 623.28 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.09 COBERTURA DE TECHO

03.09.01 COBERTURA METALICA TR-4 CURVO-PRECOR INC. ACCESORIOS 32,268.90 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

03.09.02 COBERTURA TECHO FIBRAFORTE TRANSPARENTE POLICARBONATO 6mm 11,078.77 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

03.10 SISTEMA DE ILUMINACION

03.10.01 SUMINISTRO E INST. DE MEDIDOR DE EE.EE. (A CARGO DE EMPRESA DE SERVICIO) 500.00 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.02 EXCAVACION MANUAL DE ZANJAS PARA CABLE SUBTERRANEO 22.58 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO 12.56 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.04 TABLERO GENERAL 456.42 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.05 POZO DE PUESTA A TIERRA 463.77 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.06 CABLE NYY 3x1x25mm2 907.19 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.10.07 REFLECTOR DE HALOGENURO DE 250 WATTS 1,764.60 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%

03.11 SISTEMA DE DRENAJE

03.11.01 EXCAVACION MANUAL DE ZANJAS PARA TUBERIAS 597.53 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.11.02 RELLENO Y APISONADO MANUAL EN ZANJAS DE TUBERIAS 298.29 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.11.03 INSTALACION DE TUBERIA DE DRENAJE DE Ø 4'' 1,377.79 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
JMauricio

CRONOGRAMA DE EJECUCION FISICO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

03.11.04 INSTALACION DE TUBERIA DE DRENAJE DE Ø 6'' 590.67 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.11.05 SISTEMA DE DRENAJE HORIZONTAL CON GEOCOMPUESTO MAC DRAIN 3,345.98 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.11.06 CAJA DE REGISTRO DE DESAGUE DE 24'' x 24'' 1,694.45 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.11.07 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIAS 130.56 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

03.12 EQUIPAMIENTO

03.12.01 SUMINISTRO E INSTALACION DE PORTERIA (ARCOS DE METAL) 1,817.12 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

03.12.02 SUMINISTRO E INSTALACION DE MALLA NYLON HILO N° 36 2,295.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%

04 VEREDAS DE CONCRETO

04.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS 72.74 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

04.02 CONCRETO EN VEREDA F'C=140KG/CM2 INC. ACABADO Y BRUÑADO 566.67 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00%

04.03 JUNTAS ASFALTICAS 24.55 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

05 TRIBUNAS

05.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 295.94 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

05.02 NIVELACION INTERIOR Y APISONADO MANUAL 214.52 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

05.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 188.68 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

05.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 385.15 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

05.05 ENCOFRADO Y DESENCOFRADO EN TRIBUNAS 4,703.28 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

05.06 CONCRETO F'C=140KG/CM2 EN TRIBUNAS 18,265.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00%

05.07 TARRAJEO PULIDO Y COLOREADO C/OCRE ROJO EN TRIBUNAS 4,096.83 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%

06 SARDINEL PERDIDO

06.01 OBRAS PRELIMINARES

06.01.01 LIMPIEZA DE TERRENO MANUAL 55.30 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.01.02 TRAZO Y REPLANTEO PRELIMINAR 48.00 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.02 MOVIMIENTO DE TIERRAS

06.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 321.02 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.02.02 NIVELACION INTERIOR Y APISONADO MANUAL 116.35 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 204.67 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 417.79 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.03 OBRAS DE CONCRETO SIMPLE

06.03.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL PERDIDO 1,999.87 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.03.02 CONCRETO F'C=140KG/CM2 EN SARDINEL PERDIDO 1,908.00 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00%

06.04 REVOQUES, ENLUCIDOS Y MOLDURAS

06.04.01 TARRAJEO EN INTERIORES CON IMPERMEABILIZANTE 2,057.47 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

07 PORTICO DE INGRESO (01 UND)

07.01 OBRAS PRELIMINARES

07.01.01 LIMPIEZA DE TERRENO MANUAL 7.06 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.01.02 TRAZO Y REPLANTEO PRELIMINAR 6.13 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.02 MOVIMIENTO DE TIERRAS

07.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 143.17 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO 39.02 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 48.29 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 98.57 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.03 OBRAS DE CONCRETO SIMPLE

07.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 311.15 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.03.02 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS CORRIDOS 200.47 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.03.03 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 35.72 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.03.04 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 33.41 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.04 OBRAS DE CONCRETO ARMADO

07.04.01 ZAPATAS

07.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS 842.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 200.06 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

07.04.02 VIGAS DE CONEXION

07.04.02.01 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CONEXION 83.23 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.04.02.02 CONCRETO F'C=210KG/CM2 EN VIGAS DE CONEXION 99.97 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 180.54 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

07.04.03 COLUMNAS

07.04.03.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 457.96 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.04.03.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS 394.72 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.04.03.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 633.53 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

07.04.04 VIGAS

07.04.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS 181.34 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.04.04.02 CONCRETO F'C=210KG/CM2 EN VIGAS 197.78 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.04.04.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 244.94 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

07.05 ALBAÑILERIA

07.05.01 MURO DE LADRILLO KK AMARRE TIPO CABEZA CON C:A 1:4 e=1.5cm 529.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%
JMauricio

CRONOGRAMA DE EJECUCION FISICO DE OBRA

PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL DISTRITO DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

PERIODO
Nº PARTIDA PARCIAL 1º MES 2º MES 3º MES
1 2 3 4 1 2 3 4 1 2 3 4

07.06 REVOQUES, ENLUCIDOS Y MOLDURAS

07.06.01 TARRAJEO EN MUROS INTERIORES Y EXTERIORES MEZCLA C:A 1:4 e=1.5cm 378.76 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.06.02 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm 244.65 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.06.03 TARRAJEO EN VIGAS MEZCLA C:A 1:4 e=1.5cm 160.15 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00%

07.07 PINTURAS

07.07.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 02 MANOS 202.47 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%

07.07.02 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS 162.70 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%

07.08 CARPINTERIA DE MADERA Y METALICA

07.08.01 PUERTA METALICA SEGUN DISEÑO INC. COLOCACION, PINTADO Y ACCESORIOS (BISA 1,760.09 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%

08 CERCO PERIMETRICO TIPO M-001 LONG.=80.60ml

08.01 OBRAS PRELIMINARES

08.01.01 LIMPIEZA DE TERRENO MANUAL 69.64 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.01.02 TRAZO Y REPLANTEO PRELIMINAR 60.45 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.02 MOVIMIENTO DE TIERRAS

08.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 707.47 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.02.02 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 451.13 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.02.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 920.88 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.03 OBRAS DE CONCRETO SIMPLE

08.03.01 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS CORRIDOS 7,969.18 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 1,919.41 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 1,102.65 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.04 REVOQUES, ENLUCIDOS Y MOLDURAS

08.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm 987.67 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

08.05 PINTURAS

08.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS 527.97 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%

08.06 CERCO DE MALLA OLIMPICA

08.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA 5,187.42 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00%

08.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES 7,154.66 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00% 0.00%

09 CERCO PERIMETRICO TIPO M-002 LONG.=34.60ml

09.01 OBRAS PRELIMINARES

09.01.01 LIMPIEZA DE TERRENO MANUAL 49.82 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.01.02 TRAZO Y REPLANTEO PRELIMINAR 43.25 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.02 MOVIMIENTO DE TIERRAS

09.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION 1,240.21 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO 196.42 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 574.04 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA 1,171.78 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.03 OBRAS DE CONCRETO SIMPLE

09.03.01 CONCRETO CICLOPEO F'C=140KG/CM2 + 70% P.G. EN MURO DE CONTENCION 7,416.71 0.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS 823.96 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS 473.87 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.04 REVOQUES, ENLUCIDOS Y MOLDURAS

09.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm 423.99 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.05 PINTURAS

09.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS 226.65 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

09.06 CERCO DE MALLA OLIMPICA

09.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA 2,226.86 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00%

09.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES 3,130.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00% 0.00%

10 LIMPIEZA DE OBRA

10.01 LIMPIEZA FINAL DE OBRA 748.51 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00%

11 FLETE TERRESTRE

11.01 FLETE TERRESTRE 6,000.00 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33%

12 CAPACITACION (CURSO Y TALLER)

12.01 CAPACITACION (CURSO Y TALLER) 3,000.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 0.00% 0.00% 0.00% 50.00%

13 MITIGACION E IMPACTO AMBIENTAL

13.01 MITIGACION E IMPACTO AMBIENTAL 5,000.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 50.00%

COSTO DIRECTO 308,887.05 S/. 74,278.38 S/. 130,960.74 S/. 103,647.93

GASTOS GENERALES (9% C.D.) 27,799.83 6,685.05 11,786.47 9,328.31

SUPERVISION (5% C.D.) 15,444.35 3,713.92 6,548.04 5,182.40

EXPEDIENTE TECNICO (3.5% C.D.) 10,811.05 2,599.74 4,583.63 3,627.68

PRESUPUESTO TOTAL DE OBRA 26,255.40 S/. 6,313.66 S/. 11,131.66 S/. 8,810.08

PORCENTAJE DE AVANCE 24.05% 42.40% 33.56%


JMauricio

ECUCION FISICO DE OBRA

PPTO
S/.

S/. 797.67

S/. 450.00

S/. 200.00

S/. 1,227.42

S/. 560.00

S/. 0.00

S/. 3,000.00

S/. 1,268.06

S/. 1,100.75

S/. 0.00

S/. 0.00

S/. 252.83

S/. 3,974.13

S/. 674.23

S/. 1,636.20

S/. 223.24

S/. 183.57

S/. 7,434.96

S/. 0.00

S/. 4,001.40

S/. 5,902.20

S/. 5,805.00

S/. 39,889.80

S/. 0.00

S/. 1,259.60

S/. 0.00

S/. 0.00

S/. 4,245.70

S/. 1,532.23

S/. 0.00

S/. 5,019.17

S/. 4,470.48

S/. 6,011.69

S/. 0.00

S/. 225.00

S/. 275.00

S/. 720.00

S/. 0.00

S/. 3,101.70

S/. 0.00

S/. 1,376.90

S/. 0.00

S/. 11,184.74

S/. 7,355.76

S/. 14,581.92

S/. 1,480.70

S/. 1,965.83

S/. 1,629.44

S/. 623.28

S/. 0.00

S/. 32,268.90

S/. 11,078.77

S/. 0.00

S/. 500.00

S/. 22.58

S/. 12.56

S/. 456.42

S/. 463.77

S/. 907.19

S/. 1,764.60

S/. 0.00

S/. 597.53

S/. 298.29

S/. 1,377.79
JMauricio

ECUCION FISICO DE OBRA

PPTO
S/.

S/. 590.67

S/. 3,345.98

S/. 1,694.45

S/. 130.56

S/. 0.00

S/. 1,817.12

S/. 2,295.00

S/. 0.00

S/. 72.74

S/. 566.67

S/. 24.55

S/. 0.00

S/. 295.94

S/. 214.52

S/. 188.68

S/. 385.15

S/. 4,703.28

S/. 18,265.00

S/. 4,096.83

S/. 0.00

S/. 0.00

S/. 55.30

S/. 48.00

S/. 0.00

S/. 321.02

S/. 116.35

S/. 204.67

S/. 417.79

S/. 0.00

S/. 1,999.87

S/. 1,908.00

S/. 0.00

S/. 2,057.47

S/. 0.00

S/. 0.00

S/. 7.06

S/. 6.13

S/. 0.00

S/. 143.17

S/. 39.02

S/. 48.29

S/. 98.57

S/. 0.00

S/. 311.15

S/. 200.47

S/. 35.72

S/. 33.41

S/. 0.00

S/. 0.00

S/. 842.40

S/. 200.06

S/. 0.00

S/. 83.23

S/. 99.97

S/. 180.54

S/. 0.00

S/. 457.96

S/. 394.72

S/. 633.53

S/. 0.00

S/. 181.34

S/. 197.78

S/. 244.94

S/. 0.00

S/. 529.40
JMauricio

ECUCION FISICO DE OBRA

PPTO
S/.

S/. 0.00

S/. 378.76

S/. 244.65

S/. 160.15

S/. 0.00

S/. 202.47

S/. 162.70

S/. 0.00

S/. 1,760.09

S/. 0.00

S/. 0.00

S/. 69.64

S/. 60.45

S/. 0.00

S/. 707.47

S/. 451.13

S/. 920.88

S/. 0.00

S/. 7,969.18

S/. 1,919.41

S/. 1,102.65

S/. 0.00

S/. 987.67

S/. 0.00

S/. 527.97

S/. 0.00

S/. 5,187.42

S/. 7,154.66

S/. 0.00

S/. 0.00

S/. 49.82

S/. 43.25

S/. 0.00

S/. 1,240.21

S/. 196.42

S/. 574.04

S/. 1,171.78

S/. 0.00

S/. 7,416.71

S/. 823.96

S/. 473.87

S/. 0.00

S/. 423.99

S/. 0.00

S/. 226.65

S/. 0.00

S/. 2,226.86

S/. 3,130.16

S/. 0.00

S/. 748.51

S/. 0.00

S/. 6,000.00

S/. 0.00

S/. 3,000.00

S/. 0.00

S/. 5,000.00

S/. 308,887.05

27,799.83

15,444.35

10,811.05

S/. 26,255.39

100.00%
PRESUPUESTO DE OBRA
PROYECTO : MEJORAMIENTO DE LOS SERVICIOS DEPORTIVOS CON GRASS SINTETICO EN EL CENTRO POBLADO DE CHECCHE, DEL D
DE JOSE MARIA ARGUEDAS, PROVINCIA DE ANDAHUAYLAS - APURIMAC

Item Descripción Und. Metrado Precio S/. Parcial S/.


01 TRABAJOS PROVISIONALES
01.01 CARTEL DE OBRA DE 5.40 x 3.60m und 1.00 797.67 797.67
01.02 ALQUILER DE OFICINA TECNICA, ALMACEN Y CASETA DE GUARDI mes 3.00 150.00 450.00
01.03 POZA DE AGUA PARA LA CONSTRUCCION glb 1.00 200.00 200.00
01.04 CERCO DE PROTECCION CON ARPILLERA m 120.10 10.22 1,227.42
01.05 INSTALACION PROVISIONAL DE AGUA, DESAGUE Y ELECTRICAS glb 1.00 560.00 560.00
02 OBRAS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS VJE 1.00 3,000.00 3,000.00
02.02 LIMPIEZA DE TERRENO MANUAL m2 880.60 1.44 1,268.06
02.03 TRAZO Y REPLANTEO PRELIMINAR m2 880.60 1.25 1,100.75
03 CANCHA DE GRASS SINTETICO
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO COMPACTO C/MAQUINARIA m3 34.73 7.28 252.83
03.01.02 EXCAVACION MASIVA C/MAQUINARIA EN TERRENO NORMAL m3 221.40 17.95 3,974.13
03.01.03 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 32.26 20.90 674.23
03.01.04 NIVELACION INTERIOR Y APISONADO MANUAL m2 540.00 3.03 1,636.20
03.01.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 18.48 12.08 223.24
03.01.06 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 17.22 10.66 183.57
03.01.07 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 341.68 21.76 7,434.96
03.02 CAPA DE SUSTRATO P/GRASS SINTETICO
03.02.01 RELLENO Y COMPACTADO C/AFIRMADO PARA BASE e=6'' m2 540.00 7.41 4,001.40
03.02.02 RELLENO Y COMPACTADO C/PIEDRA CHANCADA DE 1/2'' e=4'' m2 540.00 10.93 5,902.20
03.02.03 RELLENO Y COMPACTADO C/ARENA GRUESA e=4'' m2 540.00 10.75 5,805.00
03.02.04 SUMINISTRO E INSTALACION DE GRASS SINTETICO m2 540.00 73.87 39,889.80
03.03 OBRAS DE CONCRETO SIMPLE
03.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 m2 20.16 62.48 1,259.60
03.04 OBRAS DE CONCRETO ARMADO
03.04.01 ZAPATAS
03.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS m3 10.08 421.20 4,245.70
03.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 328.10 4.67 1,532.23
03.04.02 COLUMNAS
03.04.02.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 117.60 42.68 5,019.17
03.04.02.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS m3 10.08 443.50 4,470.48
03.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 1,287.30 4.67 6,011.69
03.05 ENSAYOS DE LABORATORIO
03.05.01 PRUEBA DE COMPACTACION DE SUELOS (PROCTOR MODIFICA und 1.00 225.00 225.00
03.05.02 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) und 5.00 55.00 275.00
03.05.03 DISEÑO DE MEZCLA F'C=140, 175 y 210KG/CM2 und 3.00 240.00 720.00
03.06 REVOQUES, ENLUCIDOS Y MOLDURAS
03.06.01 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm m2 98.00 31.65 3,101.70
03.07 PINTURAS
03.07.01 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS m2 98.00 14.05 1,376.90
03.08 CARPINTERIA METALICA
03.08.01 VIGA METALICA PRINCIPAL VMP-001 und 7.00 1,597.82 11,184.74
03.08.02 VIGA DE AMARRE VA-001 und 12.00 612.98 7,355.76
03.08.03 VIGUETA METALICA VM-001 und 102.00 142.96 14,581.92
03.08.04 VIGUETA METALICA VM-002 und 34.00 43.55 1,480.70
03.08.05 TEMPLADOR P/DILATACION CON FIERRO Ø 1/2'' m 164.78 11.93 1,965.83
03.08.06 CANALETA DE F°G° P/ EVACUACION AGUAS PLUVIALES m 64.00 25.46 1,629.44
03.08.07 MONTANTE DE Ø 4'' P/EVACUACION AGUAS PLUVIALES pto 4.00 155.82 623.28
03.09 COBERTURA DE TECHO
03.09.01 COBERTURA METALICA TR-4 CURVO-PRECOR INC. ACCESORIOS m2 351.36 91.84 32,268.90
03.09.02 COBERTURA TECHO FIBRAFORTE TRANSPARENTE POLICARBO m2 273.28 40.54 11,078.77
03.10 SISTEMA DE ILUMINACION
03.10.01 SUMINISTRO E INST. DE MEDIDOR DE EE.EE. (A CARGO DE EMPR glb 1.00 500.00 500.00
03.10.02 EXCAVACION MANUAL DE ZANJAS PARA CABLE SUBTERRANEO m3 1.04 21.71 22.58
03.10.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 1.04 12.08 12.56
03.10.04 TABLERO GENERAL und 1.00 456.42 456.42
03.10.05 POZO DE PUESTA A TIERRA und 1.00 463.77 463.77
03.10.06 CABLE NYY 3x1x25mm2 m 67.10 13.52 907.19
03.10.07 REFLECTOR DE HALOGENURO DE 250 WATTS und 6.00 294.10 1,764.60
03.11 SISTEMA DE DRENAJE
03.11.01 EXCAVACION MANUAL DE ZANJAS PARA TUBERIAS m 95.30 6.27 597.53
03.11.02 RELLENO Y APISONADO MANUAL EN ZANJAS DE TUBERIAS m 95.30 3.13 298.29
03.11.03 INSTALACION DE TUBERIA DE DRENAJE DE Ø 4'' m 73.60 18.72 1,377.79
03.11.04 INSTALACION DE TUBERIA DE DRENAJE DE Ø 6'' m 21.70 27.22 590.67
03.11.05 SISTEMA DE DRENAJE HORIZONTAL CON GEOCOMPUESTO MACm 95.30 35.11 3,345.98
03.11.06 CAJA DE REGISTRO DE DESAGUE DE 24'' x 24'' pza 5.00 338.89 1,694.45
03.11.07 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIAS m 95.30 1.37 130.56
03.12 EQUIPAMIENTO
03.12.01 SUMINISTRO E INSTALACION DE PORTERIA (ARCOS DE METAL) und 2.00 908.56 1,817.12
03.12.02 SUMINISTRO E INSTALACION DE MALLA NYLON HILO N° 36 m2 1,020.00 2.25 2,295.00
04 VEREDAS DE CONCRETO
04.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2.02 36.01 72.74
04.02 CONCRETO EN VEREDA F'C=140KG/CM2 INC. ACABADO Y BRUÑ m2 12.70 44.62 566.67
04.03 JUNTAS ASFALTICAS m 4.40 5.58 24.55
05 TRIBUNAS
05.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 14.16 20.90 295.94
05.02 NIVELACION INTERIOR Y APISONADO MANUAL m2 70.80 3.03 214.52
05.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 17.70 10.66 188.68
05.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 17.70 21.76 385.15
05.05 ENCOFRADO Y DESENCOFRADO EN TRIBUNAS m2 115.22 40.82 4,703.28
05.06 CONCRETO F'C=140KG/CM2 EN TRIBUNAS m3 64.42 283.53 18,265.00
05.07 TARRAJEO PULIDO Y COLOREADO C/OCRE ROJO EN TRIBUNAS m2 190.02 21.56 4,096.83
06 SARDINEL PERDIDO
06.01 OBRAS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO MANUAL m2 38.40 1.44 55.30
06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 38.40 1.25 48.00
06.02 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 15.36 20.90 321.02
06.02.02 NIVELACION INTERIOR Y APISONADO MANUAL m2 38.40 3.03 116.35
06.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 19.20 10.66 204.67
06.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 19.20 21.76 417.79
06.03 OBRAS DE CONCRETO SIMPLE
06.03.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL PERDIDO m2 57.60 34.72 1,999.87
06.03.02 CONCRETO F'C=140KG/CM2 EN SARDINEL PERDIDO m3 9.60 198.75 1,908.00
06.04 REVOQUES, ENLUCIDOS Y MOLDURAS
06.04.01 TARRAJEO EN INTERIORES CON IMPERMEABILIZANTE m2 57.60 35.72 2,057.47
07 PORTICO DE INGRESO (01 UND)
07.01 OBRAS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.90 1.44 7.06
07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.90 1.25 6.13
07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 6.85 20.90 143.17
07.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 3.23 12.08 39.02
07.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 4.53 10.66 48.29
07.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 4.53 21.76 98.57
07.03 OBRAS DE CONCRETO SIMPLE
07.03.01 CONCRETO EN SOLADO DE 4'' MEZCLA C:H 1:12 m2 4.98 62.48 311.15
07.03.02 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS COR m3 0.73 274.61 200.47
07.03.03 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 0.90 39.69 35.72
07.03.04 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS m3 0.11 303.76 33.41
07.04 OBRAS DE CONCRETO ARMADO
07.04.01 ZAPATAS
07.04.01.01 CONCRETO F'C=210KG/CM2 EN ZAPATAS m3 2.00 421.20 842.40
07.04.01.02 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 42.84 4.67 200.06
07.04.02 VIGAS DE CONEXION
07.04.02.01 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CONEXION m2 1.95 42.68 83.23
07.04.02.02 CONCRETO F'C=210KG/CM2 EN VIGAS DE CONEXION m3 0.24 416.53 99.97
07.04.02.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 38.66 4.67 180.54
07.04.03 COLUMNAS
07.04.03.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 10.73 42.68 457.96
07.04.03.02 CONCRETO F'C=210KG/CM2 EN COLUMNAS m3 0.89 443.50 394.72
07.04.03.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 135.66 4.67 633.53
07.04.04 VIGAS
07.04.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 3.86 46.98 181.34
07.04.04.02 CONCRETO F'C=210KG/CM2 EN VIGAS m3 0.45 439.50 197.78
07.04.04.03 ACERO DE REFUERZO F'Y=4200KG/CM2 GRADO 60 kg 52.45 4.67 244.94
07.05 ALBAÑILERIA
07.05.01 MURO DE LADRILLO KK AMARRE TIPO CABEZA CON C:A 1:4 e=1 m2 7.47 70.87 529.40
07.06 REVOQUES, ENLUCIDOS Y MOLDURAS
07.06.01 TARRAJEO EN MUROS INTERIORES Y EXTERIORES MEZCLA C:A 1 m2 17.00 22.28 378.76
07.06.02 TARRAJEO EN COLUMNAS MEZCLA C:A 1:4 e=1.5cm m2 7.73 31.65 244.65
07.06.03 TARRAJEO EN VIGAS MEZCLA C:A 1:4 e=1.5cm m2 3.86 41.49 160.15
07.07 PINTURAS
07.07.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 02 MAN m2 17.00 11.91 202.47
07.07.02 PINTURA LATEX EN COLUMNAS Y VIGAS 02 MANOS m2 11.58 14.05 162.70
07.08 CARPINTERIA DE MADERA Y METALICA
07.08.01 PUERTA METALICA SEGUN DISEÑO INC. COLOCACION, PINTAD m2 5.28 333.35 1,760.09
08 CERCO PERIMETRICO TIPO M-001 LONG.=80.60ml
08.01 OBRAS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 48.36 1.44 69.64
08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 48.36 1.25 60.45
08.02 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 33.85 20.90 707.47
08.02.02 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 42.32 10.66 451.13
08.02.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 42.32 21.76 920.88
08.03 OBRAS DE CONCRETO SIMPLE
08.03.01 CONCRETO CICLOPEO C:H 1:10 + 30% P.G. EN CIMIENTOS COR m3 29.02 274.61 7,969.18
08.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 48.36 39.69 1,919.41
08.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS m3 3.63 303.76 1,102.65
08.04 REVOQUES, ENLUCIDOS Y MOLDURAS
08.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm m2 44.33 22.28 987.67
08.05 PINTURAS
08.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS m2 44.33 11.91 527.97
08.06 CERCO DE MALLA OLIMPICA
08.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA m2 161.20 32.18 5,187.42
08.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES m 73.60 97.21 7,154.66
09 CERCO PERIMETRICO TIPO M-002 LONG.=34.60ml
09.01 OBRAS PRELIMINARES
09.01.01 LIMPIEZA DE TERRENO MANUAL m2 34.60 1.44 49.82
09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 34.60 1.25 43.25
09.02 MOVIMIENTO DE TIERRAS
09.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMENTACION m3 59.34 20.90 1,240.21
09.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 16.26 12.08 196.42
09.02.03 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 53.85 10.66 574.04
09.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 53.85 21.76 1,171.78
09.03 OBRAS DE CONCRETO SIMPLE
09.03.01 CONCRETO CICLOPEO F'C=140KG/CM2 + 70% P.G. EN MURO m3 31.83 233.01 7,416.71
09.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 20.76 39.69 823.96
09.03.03 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. EN SOBRECIMIENTOS m3 1.56 303.76 473.87
09.04 REVOQUES, ENLUCIDOS Y MOLDURAS
09.04.01 TARRAJEO EN SOBRECIMIENTOS MEZCLA C:A 1:4 e=1.5cm m2 19.03 22.28 423.99
09.05 PINTURAS
09.05.01 PINTURA LATEX EN SOBRECIMIENTOS 02 MANOS m2 19.03 11.91 226.65
09.06 CERCO DE MALLA OLIMPICA
09.06.01 CERCO DE MALLA OLIMPICA DE 2'' x 2'' GALVANIZADA m2 69.20 32.18 2,226.86
09.06.02 TUBERIA DE F°G° DE Ø 2'' P/PARANTES m 32.20 97.21 3,130.16
10 LIMPIEZA DE OBRA
10.01 LIMPIEZA FINAL DE OBRA m2 880.60 0.85 748.51
11 FLETE TERRESTRE
11.01 FLETE TERRESTRE glb 1.00 6,000.00 6,000.00
12 CAPACITACION (CURSO Y TALLER)
12.01 CAPACITACION (CURSO Y TALLER) glb 1.00 3,000.00 3,000.00
13 MITIGACION E IMPACTO AMBIENTAL
13.01 MITIGACION E IMPACTO AMBIENTAL glb 1.00 5,000.00 5,000.00
COSTO DIRECTO
GASTOS GENERALES (9% C.D.)
SUPERVISION (5% C.D.)
EXPEDIENTE TECNICO (3.5% C.D.)
====
PRESUPUESTO TOTAL DE OBRA
DEL DISTRITO

Sub total S/.


3,235.09

5,368.81

196,658.88
14,379.16

55,598.40

1,259.60

21,279.27
5,777.93

15,501.34

1,220.00

3,101.70

1,376.90

38,821.67

43,347.67

4,127.12
8,035.27

4,112.12

663.96

28,149.40

7,128.47
103.30

1,059.83

3,907.87

2,057.47

7,877.68
13.19

329.05

580.75

3,516.47
1,042.46

363.74

1,486.21
624.06

529.40

783.56

365.17

1,760.09

27,058.53
130.09

2,079.48

10,991.24

987.67

527.97

12,342.08

17,997.72
93.07

3,182.45

8,714.54

423.99

226.65

5,357.02

748.51

6,000.00

3,000.00

5,000.00

308,887.05
27,799.83
15,444.35
10,811.05
==========
362,942.28

You might also like