Princess Noura Bint Abdulrahman University for Women Project Joint venture

Riyadh, Kingdom of Saudi Arabia El Seif/CCC


part / package: package 3 - Utillity area references: time: date:
department: ENGINEERING 1:58 PM 1/16/2018
calcs by: Aleksandar Jankovic sr.str.eng

THE SUPPORT POSTS FOR 500 mm PIPE

The worst case is taken in to consideration assuming maximum pipe diameter and the
maximum center pipe line distance from the tunnel wall.
The maximum diameter pipe 500 mm
The maximum pipe offset from the tunnel base is 3657 mm

Building / area: Chiller building rev: CHILLER BUILDING Sheet:


issued for: APPROVAL 0 pipe supports 0 2 6

Princess Noura Bint Abdulrahman University for Women Project Joint venture
Riyadh, Kingdom of Saudi Arabia El Seif/CCC
part / package: package 3 - Utillity area references: time: date:
department: ENGINEERING 1:58 PM 1/16/2018
calcs by: Aleksandar Jankovic sr.str.eng

1. INPUT DATA
1.1 Distance between two supports (pipe load)……..……..Ld= 8 meter
1.2 The density of fluid………………..…………………..…...γf= 10 kN/m3
1.3 Steel grade as per ASTM A36………………………..…Py= 245 N/mm2
1.4 The electreode classification number (strength).Feex=Py= 245 N/mm2
1.5 The strength of fillet weld as per AISC is 60% of Feex,Pyw= 147 N/mm2
1.6. The compressive strength of concrete after 28 days… fc'= 37 N/mm2
1.7 The desnity of the steel...………………………….….....γs= 7860 kg/m3
1.8 The density of the stainless steel…………………..…..γss= 7860 kg/m3
1.9 The density of the teflon…………………………………...γt= 2200 kg/m3
1.10 The density of the PU insulation as per MAR-M0005… γi= 71 kg/m3
1.11 The density of the HDPE jacket as per MAR-M0005….γj= 960 kg/m3

2.0 THE CONCEPT


The concept is based prior to esier process of erection of steel brackets and easier
process of loading/maintenance of insulated steel pipes.
Building / area: Chiller building rev: CHILLER BUILDING Sheet:
issued for: APPROVAL 0 pipe supports 0 2 7

Princess Noura Bint Abdulrahman University for Women Project Joint venture
Riyadh, Kingdom of Saudi Arabia El Seif/CCC
part / package: package 3 - Utillity area references: time: date:
department: ENGINEERING 1:58 PM 1/16/2018
calcs by: Aleksandar Jankovic sr.str.eng

STRUCTURAL COMMENT:

Since from output STAAD file is clear that forces (reactions and beam end forces)
are less then forces calculated for 600 mm pipe post, the desifned details for 600 mm
pipe post are applicable for 500 mm pipe post as well and there is no need for
additional calculations.

5.0. THE DESIGN DETAILS OVERVIEW

For clear the overview of all designed details please follow the sketch on the
following page.
Building / area: Chiller building rev: CHILLER BUILDING Sheet:
issued for: APPROVAL 0 pipe supports 0 3 7

Princess Noura Bint Abdulrahman University for Women Project Joint venture
Riyadh, Kingdom of Saudi Arabia El Seif/CCC
part / package: package 3 - Utillity area references: time: date:
department: ENGINEERING 1:58 PM 1/16/2018
calcs by: Aleksandar Jankovic sr.str.eng

ATTACHMENTS
Building / area: Chiller building rev: CHILLER BUILDING Sheet:
issued for: APPROVAL 0 pipe supports 0 3 9