You are on page 1of 5

烟台慧泽矿山工程技术有限公司

YANTAI HUIZE MINING ENGINEERING CO., LTD.


BUSINESS DOCUMENT PROPOSAL S/N:2017018

10 TPH GOLD CIL PROJECT

ATTACHMENT 3
REQUIRED DOCUMENT FROM BUYER FOR DESIGN

Buyer: GOLD PYRAMID GROUP


Project Number: HZ2017018
Rev: 00
Date: 22/10/2017

Add: No.2304 Tianhe Building, No.163 Yingchun Street, Laishan District, Yantai, China
Mobile: +86-18754545952, 13336382899 Tel: +86-535-6722230
E-mail: ythuize@vip.sina.com
1
烟台慧泽矿山工程技术有限公司
YANTAI HUIZE MINING ENGINEERING CO., LTD.
BUSINESS DOCUMENT PROPOSAL S/N:2017018

1 CIVIL CONSTRUCTION
1.1 Topographical features of the site

1.2 Hydrological geology data, and the 《geotechnical survey report》necessary for design

1.3 Local architectural style, structural style and the usual practice of waterproof and heat
preservation.

1.4 Local construction material supply including transportation, price etc, such as gravel, brick
block, plank, steel and cement etc.

1.5 Main construction structural style and main building style

2 ELECTRIC POWER
2.1 Power supply around the mine, including:

--Transformer substation available power supply or power supply line that can be connected
according to T type

--Voltage class, frequency and distance of power supply

--Topography and landform between the site and power supply

--Basic situations of transformer substation


--Requirements of local Electricity Board on the users such as: power factor, power supply mode
and start mode of large electric equipments.
2.2 Local grounding for lightening requirements

2.3 Communication method to outside and local communication situations

3 MINERAL PROCESSING
Add: No.2304 Tianhe Building, No.163 Yingchun Street, Laishan District, Yantai, China
Mobile: +86-18754545952, 13336382899 Tel: +86-535-6722230
E-mail: ythuize@vip.sina.com
2
烟台慧泽矿山工程技术有限公司
YANTAI HUIZE MINING ENGINEERING CO., LTD.
BUSINESS DOCUMENT PROPOSAL S/N:2017018
3.1 Topographic map of the plant 1:500, 1:1000

3.2 Water, electricity, tailings reservoir, environmental protection around the site

3.3 Investment ideas of client

4 WATER SUPPLY AND DRAINAGE


4.1 Water supply for production and living: amount of water, water quality, if there is low water and
water interception phenomena, if emergency sources of water is adopted in low water period,
selection of building for getting water and mode of getting water

4.2 Drainage system: drainage mode and discharge outlet selection of living and production
wastewater

4.3 The largest altitude difference and the transmission distance between Water sources and water
points, and whether dual pipes are necessary or not.

5 LAYOUT AND TRANSPORTATION


5.1 Geographic and topographic data

-- Name and geographic position of construction project location


--Direction relationship and distance between construction project location and nearby town, main
lines of communication and rivers

--Topographic map: 1:10000,1:2000 (Used for site location selection and plans comparison);

--1:1000, 1:500(used for construction)

5.2 Socio-economic conditions

--Name of villages near the site,No. of homes, number of people and labors

Add: No.2304 Tianhe Building, No.163 Yingchun Street, Laishan District, Yantai, China
Mobile: +86-18754545952, 13336382899 Tel: +86-535-6722230
E-mail: ythuize@vip.sina.com
3
烟台慧泽矿山工程技术有限公司
YANTAI HUIZE MINING ENGINEERING CO., LTD.
BUSINESS DOCUMENT PROPOSAL S/N:2017018
-- Agricultural production and local land utilization conditions

-- Local water supply and drainage, power supply and possibility cooperating with adjacent
enterprises

-- Local construction materials manufacture and supply conditions.

5.3 Meteorology

-- Microclimate characters on the site

-- Frequency of wind direction, wind rose map, maximum and average wind speed

-- Maximum,average snowfall and rainfall over the years

-- Annual absolute air temperature etc.

5.4 Flood

-- Survey data of historical maximum flood level near the site

-- Maximum,minimum flow, catchments area of the river near the site near the site

-- Water loss and soil erosion, water and soil protection and planning conditions of the upper
reaches of the site

5.5 Engineering geology and hydrologic geology

-- Unfavorable geological conditions affecting stability of geologic structure and stratum and the
site stability such as fault age, landslide, collapse and debris flow

-- soil type, soil property and allowable bearing capacity of foundation soil

-- Earthquake and destruction of the building

-- PH value, depth and rise and fall of groundwater

Add: No.2304 Tianhe Building, No.163 Yingchun Street, Laishan District, Yantai, China
Mobile: +86-18754545952, 13336382899 Tel: +86-535-6722230
E-mail: ythuize@vip.sina.com
4
烟台慧泽矿山工程技术有限公司
YANTAI HUIZE MINING ENGINEERING CO., LTD.
BUSINESS DOCUMENT PROPOSAL S/N:2017018
5.6 Traffic condition

Existing road and railway conditions near the site such as transport capacity, equipment
configurations, engineering factors, limit grade and repair and maintenance of bridge and tunnel,
loading and unloading facilities and transportation cost etc.

Add: No.2304 Tianhe Building, No.163 Yingchun Street, Laishan District, Yantai, China
Mobile: +86-18754545952, 13336382899 Tel: +86-535-6722230
E-mail: ythuize@vip.sina.com