Project Folder

Table of Contents

I Invitation to Bid
II Bid Proposal
III Notice to Proceed /Award
IV Contract
V Gantt Chart with Accomplishment Report
VI Methodology
VII Project Action Plan
VIII Inspection and Test Plan
IX Safety and Health Plan
X Table of Organization
XI Compiled Progress Reports
XII Accomplished Inspection and Test Plans (ITP)
XIII Proj Progress Documents / Photos
Project: INSTN OF 1 CU.M. INSTRUMENT AIR RECEIVER TANK FOR NEW SULFUR BLOWER (BL-0506-CP-01)
Location: Progress Report as of: _________________________
Proj Duration: 15 calendar days Date Start:

Work dys 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

ays
WORK SCOPE

cc
t
%W

%A
Cal days

#d
1 Mobilization of temporary facilities, manpower 5.0% Plan
and tools /eqpt at site. 0.0% Actual

2 Excavation for the concrete foundation of the 5.0% Plan


Tank 0.0% Actual

3 Concreting of foundation. Provide for anchor 5.0% Plan


bolts 0.0% Actual

4 Pre-fab piping, tubings, supports. NO HOT WORK 15.0% Plan


at the Oxygen Plant 0.0% Actual
5.0% Plan
5 Test weld joints with DPT (Pasar)
0.0% Actual

6 Install Air Receiver Tank and its accessories 20.0% Plan


(valves). 0.0% Actual
25.0% Plan
7 Install piping, tubing and supports
0.0% Actual

8 Painting Surface preparation. Prime coat within 10.0% Plan


10hrs. Paint 3 coats: 125/100/125microns. 0.0% Actual
5.0% Plan
9 Assist in commissioning work
0.0% Actual
5.0% Plan
10 Housekeeping
0.0% Actual
Total Weighted Accomplishment = ###
Total Project Accomplishment = 0.0%

Prepared by / Date: Reviewed by / Date: Approved by / Date:

EMAI Site Supervisor EMAI Project In-Charge PASAR Representative


Project: INSTN OF 1 CU.M. INSTRUMENT AIR RECEIVER TANK FOR NEW SULFUR BLOWER (BL-0506-CP-01)
Location: Progress Report as of: _________________________
Proj Duration: 15 calendar days Date Start:

Work dys 19 20

Ending
ays
WORK SCOPE

cc
t
%W

%A

Acc
Cal days

#d
1 Mobilization of temporary facilities, manpower 5.0% Plan
and tools /eqpt at site. 0.0% Actual

2 Excavation for the concrete foundation of the 5.0% Plan


Tank 0.0% Actual

3 Concreting of foundation. Provide for anchor 5.0% Plan


bolts 0.0% Actual

4 Pre-fab piping, tubings, supports. NO HOT WORK 15.0% Plan


at the Oxygen Plant 0.0% Actual
5.0% Plan
5 Test weld joints with DPT (Pasar)
0.0% Actual

6 Install Air Receiver Tank and its accessories 20.0% Plan


(valves). 0.0% Actual
25.0% Plan
7 Install piping, tubing and supports
0.0% Actual

8 Painting Surface preparation. Prime coat within 10.0% Plan


10hrs. Paint 3 coats: 125/100/125microns. 0.0% Actual
5.0% Plan
9 Assist in commissioning work
0.0% Actual
5.0% Plan
10 Housekeeping
0.0% Actual
Total Weighted Accomplishment = ###
Total Project Accomplishment = 0.0%

Prepared by / Date: Reviewed by / Date:

EMAI Site Supervisor EMAI Project In-Charge


DAILY ACTIVITY REPORT as of: ______________
Project:
Location:
Date: ______________ Day: Report No.:

WEATHER Sunny Cloudy Windy Rainy HeavyRain Typhoon


A.M. ____ ____ ____ ____ ____ ____
P.M. ____ ____ ____ ____ ____ ____
Remarks:

MANPOWER:
Eng'rs Supvr Safety Foremen Leadmen Skilled Helpers
____ ____ ____ ____ ____ ____ ____
Total Manpower = ____

ACTIVITIES:

Problems Encountered:

SAFETY CONCERNS:

SPECIAL EVENTS (Inspections, Visitors, etc)

Prepared by /Date: Noted by / Date:


METHODOLOGY

I. MOBILIZE
Organize in a folder the copy of the Notice To Proceed (NTP) or of the Contract
Prepare copies of the Plans and Specifications.
Prepare the project Table of Organization.
Hiring of the needed work force (skilled and helpers)
Prepare the detailed Work Schedule (Gantt or PERT-CPM)
Prepare the Accomplishment Report format
Prepare the Materials, Tools and Equipment and Budget
Prepare the workers PPE's as well.
Acquire the work permits: Safety, Security, etc.
Do the work sites Job Safety Analysis.
Prepare the safety barricades, warning signages, fire extinguishers, etc. for the job site.
Prepare the Log Book for the Daily Progress reporting.
Prepare the Temporary Facilities: field office/bodega; food, water, electical supply.

II. PROJECT EXECUTION.


Conduct regular Tool Box meetings to enhance safety consciousness in the workplace.
Provide safety barricades, safety warning signs and fire extinguishers when needed.
Document daily activities and progress accomplishments. Follow the provided forms.
Monitor progress accomplishments to satisfy quality of work and completion time.
Document inspection reports. Provide photographs, if feasible.
Conduct daily housekeeping works.

an example to follow re proj "thinned-out fuel line replacement"


Cut and clear the vegetations obstructing the work.
Bring to the job sites the draining materials such as drums, etc.
Close the valves, drain the fuel lines and purge it with compressed air.
Check for any hazardous liquid and gas leaks that may cause fire and physical irritations.
Repair the pipe supports and deteriorating concrete of the pedestals.
Lay-out, Cut, Remove the thinned-out pipes for replacement.
Layout, cut and prepare the replacement pipes, bevel joints. Sand blast prior to painting.
Fit-up and weld pipe joints
Tig welding for root pass and hot pass.
SMAW for capping weld
Inspect the root pass using "Dye Penetration Test" (DPT)
Full weld all joints
Conduct Hydrostastic testing for any possible leaks of joints.
Liquid Pressure and Time Duration of application to be set by Pasar.

III. TURN-OVER of COMPLETED WORK.


Invite owner's representative for joint inspection of the completed work.
Correct any observed deficiencies.
Submit final accomplishment report duly signed by owner's site representative.
Seek the release of the owner's Final Certificate of Acceptance.
Submit the Guarantee Bond as stipulated in the Contract.
IV. DEMOBILIZE
Return all excess materials to where it came from
Dispose scrap materials properly and accordingly.
Return all tools and equipment
Dismantle all temporary facilities.
General clean up.
PROJECT ACTION PLAN
Project:
Location: Prepared by:
Objectives / Activities Specific Tasks Success Criteria Time Frame Resources

(what to do to meet your (when to do the (Responsible persons and the Resources needed for
(List of Objectives.) (measure of success)
objectives) Tasks) each Tasks)

Documents and Site Permits and JSA docs


preparations

Barricading, Posting Work


Signage & warnings

Mobilization
INSPECTION and TEST PLAN
Project:
Location:

Legend of Activity Codes: A-100% Inspection; H-Hold point; R-Random; R1-Review; W-Witness; App-Approval
Responsibility of
EMAI PASAR
Item Acceptance Activity Activity
Activities Items / Parts Inspected Test Inspection Frequency Remarks
No. Criteria Code Code
Prepared by / Date: Reviewed by / Date: Approved by / Date:

_____________________________
EMAI Site Supervisor EMAI Project In-Charge PASAR Representative
SAFETY and HEALTH PLAN.

New employees to attend and pass Health and Safety Orientation


Standardize Reporting and Investigating forms
Provide First Aid kits
Regular Toolbox meetings
"No Smoking" and no open flame within the vicinity of the Petron depot.
List of Responsible Persons.
Proj In-Charge / Supervisor --
Safety Officer / Coordinator --
Identification and Control of Hazards at the job site
Job Safety Analysis Report
Required PPE's
Engineering controls
Administrative controls
Emergency and Accident Response
Record keeping
PROJECT TABLE OF ORGANIZATION

Proj-In-Charge

Safety Officer

Field Engineer /QC

Gen Foreman

Layouter-Fabricator Welder Leadman Civil Works Leadman