Professional Documents
Culture Documents
each manpower.
Rajesh
brahmabhat
Owner - B Safal
Ankit Shah
Project managing
consultant (PMC)
Nilesh
Nipesh shah
Trivedi
Senior Engineer Senior Engineer
Saurabh
Shah
Project managing
consultant (PMC)
Sohil
Dhaval Patel Devisingh
Marwadi
Complete block - A complete block -B Total casting & RMC
Mahesh Gaurang
Desai Rathod
Supervisor Supervisor
List of drawings referred at construction project site.
Working drawing A & B block -1 level
A & B block -2 level
A & B block -3 level
Structural layout A & B block -1 level
A & B block -2 level
A & B block -3 level
Beam slab layout A block -2 level
B block ground level
Stair case architectural drawing A block -3 basement lower level
Bblock -1 basement lower level
Stair case structural drawing A block -3 basement lower level
Bblock -1 basement lower level
Sectional cutout A – A Structural detail of flush tank, raw
sewage tank and sheer wall
Structural details of pt slab Block A part -4
Bottom steel continuous
Extra bottom steel
Extra top steel x direction
Extra top steel y direction
Structural details of beam nd slab Block B ground level
List of Architect, Consultants, and other agencies involved. Also indicate their
role and responsibilities.
Reducing the wastage of the project while execution thus saving the overall
execution cost.
A belief of doing the work – “First time correct” because rectifications are
possible but a quite costly in execution.
All round time saving by proper coordinated approach with other contractors in
order to maintain the time schedule of the project.
A safer approach for all the execution activities, keeping in view of all the
labourers and the site engineers.
The project highly focuses on – Quality, Cost, Time, the three most important
parameters of a project.
Working with high class and quality keeping in view the schedule time, saves a
lot of Cost of execution thus making the overall project a SUCCESS.
A site which fully secured 24*7, making the labourer and the materials safe all
the time.
Also, focuses on a proper flow of command and decision making which makes it
easier for a contractor to work without any confusion.
2.7.2LABOUR COLONY
Labour colony is located on site.
The Labour colonies provide accommodation for more than 150 labours.
It is facilitate with common bathroom and toilets.
2.7.4ELECTRICITY
Towers are erected to provide light through halogen bulbs for work to be
carried out at night.
Electricity connection is provided by Gujarat electricity board
Electric bill of the 2 month is around 80,000-90,000rs
2.7.5 STOREROOM
All required materials and tools other than major construction materials are
stored in storeroom and they are issued as per requirement.
Store room is available near the contractor office.