 Organization chart for the construction project, along with nature of job for

each manpower.

Rajesh
brahmabhat
Owner - B Safal

Ankit Shah
Project managing
consultant (PMC)

Nilesh
Nipesh shah
Trivedi
Senior Engineer Senior Engineer

Tapan Patel Akhil Mithia


Junior Engineer Safety engineer
Viral shah
Owner - H.V.
Infrabild

Saurabh
Shah
Project managing
consultant (PMC)

Sohil
Dhaval Patel Devisingh
Marwadi
Complete block - A complete block -B Total casting & RMC

Mahesh Gaurang
Desai Rathod
Supervisor Supervisor
 List of drawings referred at construction project site.
Working drawing A & B block -1 level
A & B block -2 level
A & B block -3 level
Structural layout A & B block -1 level
A & B block -2 level
A & B block -3 level
Beam slab layout A block -2 level
B block ground level
Stair case architectural drawing A block -3 basement lower level
Bblock -1 basement lower level
Stair case structural drawing A block -3 basement lower level
Bblock -1 basement lower level
Sectional cutout A – A Structural detail of flush tank, raw
sewage tank and sheer wall
Structural details of pt slab Block A part -4
Bottom steel continuous
Extra bottom steel
Extra top steel x direction
Extra top steel y direction
Structural details of beam nd slab Block B ground level

 List of Architect, Consultants, and other agencies involved. Also indicate their
role and responsibilities.

Architect Vitan architects


Sundar Nagar, Naryanpura, Ahmedabad, Gujarat
380013
Structural designer Ducon Consultants Private Limited
A3 - A4, Third floor, SafalProfitaire, Corporate
Road,, Prahladnagar, Corporate Rd, Prahlad
Nagar, Ahmedabad, Gujarat 380015
Concrete supply Hindustan RMC
Supply of rmc at site as per preodered qty
and desired quality
Sp ring road , bopalsanad section,
ahmedabad
Lead contractor for construction h.v. infrabuild
No-12, Fourth Floor, Ashirvad Complex, Nr.
Sardar Patel SevaSamaj Hall, Beside Aditya
Complex, Mithakhli Six Road, C.G. Road,
Ahmedabad, Gujarat 380006

 Laboratory testing facilities available at construction project site. Also indicate


other quality testing arrangements.
Automatic digital Compression testing machine
Slump testing

 Details / List of Equipments and plants being used or proposed to be used at


construction project site.
Schwing concrete pump
Ace 45m long boom Crane
Ridgid rod Threading machine
Rod cutters—2
Halogen lights
Wooden ply cutter
Concrete breaker – 2
Grouting equipment – 1
Stress generating equipment in slab
Arc Welding equipment
 Details of infrastructure facilities provided at construction project site.
(Electricity, Water, Transport, Canteen, Labour colony, Medical facilities etc.)
A 3 phase electricity connection
Borewell
Government water supply
Washroom different for company members, contractor members, and for 5 washrooms
workers
Store room for material storage
Site Office
Guard cabin and quarters
 first aid
basic first aid kit and easy reach to nearby hospital
 safety requirement.
For crane operations everyone given helmets
Harness for points at height and critical locations
Gum boots for workers in concreting
Safety glass for welders
Safety boots
2.3 SCOPE OF WORK
The scope of Lakhani’s La Riveria project is to provide affordable homes with
mordern amenities making it an all-round package for a customer. Also focusing on
a project location, Lakhani La Riveria is a Riverside project offering serenity &
nature’s embrace with its apartments strategically located in heart of Panvel city.
The Project intends to focus on:
Using high and good quality materials and equipment which are highly
maintained and taken care off.

Reducing the wastage of the project while execution thus saving the overall
execution cost.

A belief of doing the work – “First time correct” because rectifications are
possible but a quite costly in execution.

All round time saving by proper coordinated approach with other contractors in
order to maintain the time schedule of the project.

A safer approach for all the execution activities, keeping in view of all the
labourers and the site engineers.

A dedicated system of working which bring utmost transparency and high


efficiency in work.

The project highly focuses on – Quality, Cost, Time, the three most important
parameters of a project.

Working with high class and quality keeping in view the schedule time, saves a
lot of Cost of execution thus making the overall project a SUCCESS.
A site which fully secured 24*7, making the labourer and the materials safe all
the time.

Also, focuses on a proper flow of command and decision making which makes it
easier for a contractor to work without any confusion.

1.3 Scope of Work:


Study of all the architectural and structural drawings available at site.
Supervision of various activities being done at the site.
Productivity for various activities based on quantity, time and man
power employed.
Line out work.
Erection of cables in Post Tensioning Slab
Quantity estimation and rate analysis for all the activities observed
Shuttering, reinforcement & concreting of staircases.
Shuttering, Reinforcement & concreting of slab & beam.
Shuttering, reinforcement & concreting of lifts cabin.
Shuttering, reinforcement & concreting of columns.
Shuttering, reinforcement & concreting of footings.
Shuttering, reinforcement & concreting of PT slab.

2.5 DRWAINGS AVILABLE AT SITE


Following drawings are available at site.
Details of Tie Beams
Typical Floor Plan
Tie-Beam layout and detail
Details of Combined and Raft Footing Sections
Details of Lift Plan
Foundation Plan
Centerline Plan – Columns
Beam detail at slab over Ground Level
Structural Layout at slab over ground level and other floors
Details of beam over first floor and other floors
Staircase Detail
2.6 INFRASTRUCTURE FACILITIES AT SITE

2.7.1 SITE OFFICE


 Site office of contractor is available near the client office.
 Office for engineers is provided to study the drawing.
 Facilitate with attached toilet and wash room.

2.7.2LABOUR COLONY
 Labour colony is located on site.
 The Labour colonies provide accommodation for more than 150 labours.
 It is facilitate with common bathroom and toilets.

2.7.3 WATER SUPPLY


 Water is made available on site by tube well.

2.7.4ELECTRICITY
 Towers are erected to provide light through halogen bulbs for work to be
carried out at night.
 Electricity connection is provided by Gujarat electricity board
 Electric bill of the 2 month is around 80,000-90,000rs

2.7.5 STOREROOM
 All required materials and tools other than major construction materials are
stored in storeroom and they are issued as per requirement.
 Store room is available near the contractor office.

2.7.6 MEDICAL FACILITY


 First aid box always present at site for an emergency.

2.7.7 QUALITY CONTROL


 Regular concrete block test are done using compression testing machine.
 Quality of works is given primary significance for this project.
 To ensure quality of works method statements for all construction activities
are prepared and various checklists are designed to monitor the quality of
construction at every stage.
 Various tests are also carried out at site.

2.7.8 SAFETY MANAGEMENTS


 Safety Net: Safety nets are provided on extreme boundary of building, where
the work of reinforcement, formwork or concreting of extreme outer portion
is going on.
 Helmet for Staff: Helmets provided to all staff member. It was of white colour
for staff only.
 Helmet for Mechanic: Mechanics are provided helmets of Blue colour.
 Helmet for Electrician: Electricians are provided helmets of Red colour.
 Helmet for Workers: Workers are provided helmet of yellow colour.
 Helmet for Visitors: Visitors are provided helmets of white colour.
 Safety Shoe: All staff members and workers also provided safety shoes. They
are acid and oil resistant. Even they prevent slipping off on wet surface,
green concrete, etc. They also reduce accident due to steel bars or any other
sharp material on site.
 Safety Goggles: Safety goggles are provided to bar cutter, welder and the
workers working on concrete batching plant.
 Hand Gloves: Hand gloves are provided to workers working on concreting
and oiling on formwork

2.8 Scope of Work

 Study of drawings available at site.


 Study of tools and equipment.
 Quantity estimation of Steel used.
 Quantity Estimation for concrete and Brick masonry.
 Lineout/ Setting out for footing.
 Checking of reinforcement work.
 Checking of concreting, brick masonry.

2.9 LIST OF DRAWING AVAILABLE ON SITE


 Site plan
 Floor plan
 Details of the column
 Details of the beam
 Details of slab
 Details of staircase
 Details of PT beams
 Details of shear wall
 Details of raft footing
 Details of foundation
Elevation of building

http://www.bsafal.com/ongoing-projects/?cat=2-commercial b safal details


http://www.bsafal.com/organization/the-organisation/ vision and mission