1) The plain conductor of the line wire is to be connected to


a) Ring side binding post of the cable terminal
b) Tip side binding post of the cable terminal
c) Either side of the assigned cable pair binding post
d) Any binding post in the assigned cable terminal

2) The minimum height of the station protector installation from the ground is
a) At eye level of the installer
b) 6 feet above the ground
c) 5 feet above the ground
d) 4 feet above the ground

3) For proper identification of the individual conductors of a parallel wire, a lobe is provided on one of
the conductors which is referred to
a) Tip conductor
b) Ring conductor
c) Tracer conductor
d) Letters b and c of the above

4) The drive hook installation for pole to pole wire run is to be placed
a) 4 inches above the cable or messenger
b) 4 inches below the cable or messenger
c) 6 inches above the cable or messenger
d) 6 inches below the cable or messenger

5) Technology that enables high bandwith over normal telephone copper pairs
a) ADSL
b) IDSL
c) VDSL
d) RADSL

6) For proper identification of the individual conductors of an Aerial Service wire, The blue insulator of
one of the conductors is referred to as
a) Tip conductor
b) Ring conductor
c) Strength Membrane
d) None of the above

1
7) E1 lease lines, telco transport application over one copper cable pair is for what type of DSL?
a) RADSL
b) VDSL
c) HSDSL
d) IDSL

8) To avoid occurrence of trouble due to conductor termination, there should be allowed distance
between the binding post and the insulator of the conductor a clearance of
a) ½ of an inch
b) 1/3 of an inch
c) 1/5 of an inch
d) 1/8 of an inch

9) To provide climbing space, the drive hook should not be driven at the
a) Side of the pole
b) Face (front side) of the pole
c) Back of the pole
d) Any place on the pole

10) The downward drooping of the line wire due to weight is called the
a) Sag
b) Span
c) Drop wire
d) Line wire

11) The distance between two supports is called


a) Sag
b) Span
c) Drop wire
d) Line wire

12) Average inside wire consumption per installation


a) 10 feet
b) 25 feet
c) 35 feet
d) None of the above

13) Interactive multimedia, fast internet access, remote office LAN and SOHO application is for what
type of DSL?
a) SHDSL
b) RADSL
c) VDSL
d) HSDSL

14) In installing ground rods, to avoid water pipes, electrical conduits and wall foundation, ground rods
should have______________distance from the wall
a) 2 feet
b) 3 feet
c) 6 inches
d) 12 to 18 inches

2
15) The telephone wire ran beneath the cable or messenger wire and is usually coded as “R” is called
the
a) Drop wire
b) Ground wire
c) Line wire
d) Jumper wire

16) On the Disposition ABC, the second character B stands for:


a) General Location of trouble
b) Type of complain.
c) Responsible Group
d) Diagnostic

17) The maximum length of AWG # 12 ground wire allowed for the installation at the station protector is
a) 14 feet
b) 2 feet
c) 6 feet
d) 20 feet

18) CAS will show which of the following:


a) Action Taken
b) Diagnostic
c) Probable Cause
d) All of the above

19) If you are to use an 8 feet ladder, the distance of the ladder foot from the wall or any vertical
support to work safely is
a) 1 foot
b) 2 feet
c) 3 feet
d) None of the above

20) The disadvantage of this internet connection is, it is not for residential subscriber
a) ADSL
b) HDSL
c) Cable modem
d) Analog modem

21) To test a conductor for BX


a) Disconnect it first completely
b) Connect one conductor of the pair to ground
c) Every conductor to be tested is to be connected to a definite potential source
d) Not any of the above is correct

22) To avoid line wire stress in LINE wire AWG # 22 it is required to install additional support in every
a) 100 feet
b) 150 feet
c) 200 feet
d) None of the above

3
23) There are four causes of troubles in telephone conductors and to test for X , the test handset is to be
connected to
a) Battery potential source
b) Ground potential source
c) Across the pair of conductors
d) None of the above

24) It is the type of wiring that starts from the telephone protector with a single cable through the first
connecting block then run another cable from first cbk to the next cbk.
a) Cluster wiring
b) Chain wiring
c) Cluster and chain wiring
d) None of the above

25) Avoid making a sharp curve in the wire run by issuing_____ intermediate supports to every curve
a) One
b) Two
c) Three
d) Four

26) To test for Y


a) Connect the Tips of the Pairs
b) Connect the rings of the pairs
c) Connect telset on the ground
d) None of the above

27) To change the direction of line wire, and to avoid private properties and any sort of obstruction, the
installer should use a
a) Ground clamp
b) Ground rod
c) PS-6 clamp
d) Span clamp

28) To test for Z


a) Disconnect the conductor completely
b) Connect the pair on the far end
c) Connect every connector/conductor to a definite potential source

29) In a protector, trace side of the line wire should be connected on


a) Right binding post
b) Left binding post
c) Left or right binding post
d) None of the above

30) In placing jacketed wire in a protector, red conductor should be connected to


a) Right binding post
b) Left binding post
c) Left and right binding post
d) None of the above

4
31) It is not a loop qualification issue
a) Loop length
b) Guage
c) Weather
d) Load coil

32) When replacing an Aerial Service Wire, the Disposition (DIS) should be:
a) 452
b) 45Z
c) 45B
d) None of the above

33) The drive hook is to be driven deep into the plow side until the hook is approximately
a) 1 inch apart from the pole
b) 2 inches away from the pole
c) 2 ½ inches from the pole
d) ½ inch away from the pole

34) Maximum number of protectors that we can utilize if we will use AWG#12 ground wire
a) 1 protector
b) 2 protectors
c) 4 protectors
d) 6 protectors

35) Blue conductors of AWG # 22 line wire should be connected to the _________ .
a) Right binding post
b) Left binding post
c) Left or right binding post
d) None of the above

36) Which of the following in not a disadvantage of analog modem connection?


a) Low speed (9.6 to 50 kbps)
b) Shared bandwidth
c) No telephone service during surfing
d) Ties up with PSTN

37) The proper installation of conductors in the protector should be placed between
a) Binding post
b) Washers
c) Ground binding post
d) Not one of the above

38) The top of the ground rod should be at least _______the ground surface of the hard floor.
a) 12 inches above
b) 3 inches above
c) 6 inches below
d) 3 inches below

5
39) While driving a ground rod in standing position in a hard surface, you are allowed to drive ground
rod in a slanting position but should not exceed of more than
a) 45 degrees
b) 50 degrees
c) 65 degrees
d) 80 degrees
40) The maximum number of P-clamps to be attached on one drive hook should be
a) 5 P-clamps
b) 7 p- clamps
c) 8 p-clamps
d) 10 p-clamps

41) The Modified House Bracket replaces the:


a) House Bracket
b) S-Knob
c) Stove Bolt
d) All of the above
e) None of the above

42) In every corner of the block wiring should be provided with two intermediate support to avoid
a) Sharp bends
b) sag
c) Change of direction
d) All of the above

43) Standard spacing of staple arrow in inside wiring installation


a) 12 to 15 inches
b) 24 inches
c) 30 inches
d) All of the above

44) The micro filter is a low pass filter designed to block


a) Voice transmission
b) Data transmission
c) Noise
d) None of the above

45) It could be used for video services over existing phone line
a) ADSL
b) IDSL
c) HSDSL
d) VDSL

46) Q is the international code for


a) Junction box
b) Distribution point
c) Jumper wire
d) Inside wire

6
47) The previous advantage of this is low cost and market availability
a) Cable modem
b) HDSL
c) Analog modem
d) ADSL

48) In installing copper clad line wire, if the span reaches 150 feet, a _______is needed for additional
support.
a) Jacketted Wire
b) P-Clamp
c) Mid-Span Clamp
d) Drive Hook

49) It achieve broadband speeds over most universal network media in the world which primarily use an
ordinary phone wire
a) DSL technology
b) SDSL Technology
c) HDSL Technology
d) ADSL Technology

50) Which of the following is not a limitation of ADSL


a) Loading coils
b) Data rate dependent on distance
c) Copper cable subject to cable pre-qualified test
d) High speed connection

51) There are ________sections in a subs-loop


a) 6
b) 4
c) 3
d) 5

52) T, U, and G can be found in the _______ section of the subs-loop


a) First
b) Second
c) Third
d) Fourth

53) The CAS of void warranty Modem KASDA KW5819 4P (Disposition=M76) which was replaced by the
same brand and model is
a) 214
b) M76
c) V76
d) 007

7
54) NCLSP stands for:
a) New Customer & Local Services Project
b) Network & Local Support Project
c) Network & Customer Line Services Provision
d) New Customer Line Station Provisioning

55) Flexible cable network is a cable installation which extends:


a) ..from Central Office to Distribution Point
b) ..from Vertical Frame to Horizontal frame
c) ..from Central office to Cross Connect Cabinet to Distribution Point
d) ..from underground cable to riser pole.

56) Station protector is now replaced by


a) Junction Box
b) Distribution Point
c) Cable Terminal
d) Connecting block

57) Is driven to the soil to make electrical contact to earth.


a) Bolt machine
b) Ground Rod
c) Concrete Pole
d) Anchor Rod

58) Trouble Index (TI) is measured by the number of Fault Tickets per..
a) Number of repaired tickets in a month
b) Number of installed SO in a month
c) Number of working lines in an area
d) Number of sub-standard Installation

59) One Time Quality Check means..


a) Checking of all possible source of trouble in a subs-loop
b) Make sure trouble will not repeat on same location
c) Replace the line wire immediately
d) Restore the service immediately

60) At the end of working day, this form/s should be fully filled-up and submitted by FRM Technician
a) DCWR
b) PLD 615
c) RSO
d) EASF

61) This number identifies the Installer and Technician in PLDT system
a) Access Pass
b) Technician ID
c) Fiberhome ID
d) None of the above

8
62) The Disposition of OpSim / Subs-Loop /Drop wire is:
a) 451
b) 452
c) 458
d) None of the above

63) Enumerate five DON’TS IN RELATION TO THE CUSTOMER (1 point each)


a) _____________
b) _____________
c) _____________
d) _____________
e) _____________

64) Draw and explain the self test procedure for foreign battery (BX)

Answer:

Two (2) points for each correct step.., total 6 points.

9
65) Draw the complete subs-loop including sections and codes of each part.

Answer:

two (2) points for correct section Total=8points

two (2) points for each correct code and meaning Total 16 points:

One (1) point for each Total 4 points:

Total=28 points

OVERALL: 67 + 6 + 28 = 101 (passing=75)