You are on page 1of 8

Transmission Expansion Planning Considering

Economic and Reliability Criteria


Y. Gu, Member, IEEE, M. Ni, Senior Member, IEEE, and Rui Bo, Senior Member, IEEE

eij.max Upper bound on the energy flowing from node i to


Abstract--This paper presents a transmission expansion node j
planning model which combines the advantages of both the eij.min Lower bound on the energy flowing from node i to
traditional reliability-based transmission planning model and node j
economic (also known as value-based, economics-based, or
mij(t) Number of lines invested in year t
market-based) transmission planning model. Reliability-based
transmission planning tries to install new lines at minimal cost nij(t) Total number of in-service new lines by the end of
while fulfilling system reliability criteria. Economic transmission year t
planning, on the other hand, seeks investment opportunities so ηij Efficiency parameter associated with the arc
that network expansions can generate more economic benefits
than the costs. Benders decomposition technique is employed to connecting node i to node j
separate the planning problem into one master problem, which lol Load curtailment penalty factor
makes investment decisions, and two sets of sub-problems, which λi Locational marginal price at node i
evaluate the reliability and economic performance of the electric ri(t) Load curtailment at node i during time t
system, respectively. The proposed model is illustrated on a 5-bus
system. r Discount rate
Index Terms—Reliability, market, Benders decomposition,
transmission expansion planning II. INTRODUCTION

I. NOMENCLATURE B efore the deregulation of the electric industry, vertically


integrated utilities made planning decisions for both the
generation system and the transmission system within
T Set of time periods
their service areas based on various reliability criteria.
M Arcs in the fuel transportation network
Interconnections between neighboring systems were
M’ Arcs in the existing electric transmission network developed primarily for reliability reasons. The advent of
Mn’ Arcs that represent potential lines electricity markets together with organizational restructuring
m Arcs that represent power generation processes have resulted in an unbundling of the long-term planning
d Arcs that represent the electric demand function for generation and transmission systems. In the
N Nodes in the fuel transportation network deregulated world, transmission planning is different from that
in the regulated environment. On one hand there are more
N’ Nodes in the electric transmission network
uncertainties under the restructured market; on the other hand
Bi The set of nodes adjacent to node i the objectives of the two transmission planning approaches are
Gi The set of generator nodes connected to node i different as planning and decision making for generation and
bij Susceptance of branch between node i and node j transmission are carried out by different organizations now
t The tth time period [ 1 ]. What is more, driven by public policies such as
eij(t) Energy flowing from node i to node j through Renewable Portfolio Standards (RPS), there have been major
existing line during period t increases in generation projects located far from load centers,
which outgrows traditional planning standards that focus on
enij(t) Energy flowing from node i to node j through
meeting local demand.
candidate line during period t There are significant transmission bottlenecks in the control
cij(t) Per-unit cost of the energy flowing from node i to areas of Independent System Operator/Regional Transmission
node j during period t Organization (ISO/RTO) in the United States as a result of
dj(t) Supply (if positive) or demand (if negative) at node growths in certain generation technologies, lack of
j, during time t transmission investment, and increased regional interchange
[ 2 ]. Congestions in the transmission system impair the
physical security of the electric system, reduce grid reliability
and prevent the efficient operation of the electric market [3].
Y. Gu, M. Ni, and R. Bo are with the Midwest Independent Transmission Congestions not only reduce the reliability of the system, but
System Operator (MISO), Inc., St. Paul, MN 55108 USA (e-mail: also cause losses in economic value. Inexpensive energy won’t
ygu@misoenergy.org, mni@misoenergy.org, rbo@misoenergy.org). be transferred to locations where energy prices are higher
Disclaimer: The views expressed in this paper are solely of the authors and
do not necessarily represent those of MISO.
because of bottlenecks in the transmission system. In
reliability-based transmission planning, the economic benefits planning studies, based on different transmission planning
of new lines and the economic effects of congestions are criteria, the resulted investment plans might be largely
usually ignored. different. A transmission project designed solely based on
As the congestion level increases, economic transmission economic criteria might not be able to fix the reliability
expansion planning becomes attractive to alleviate the excess problems, while a purely reliability-based project might yield
cost of it, see [4], [5], [6], [7], [8]. In FERC Order No. 890 low economic benefits. In this article, a new transmission
issued in 2007, economic transmission planning study is planning method is proposed which considers both the
required in each RTO and TO (Transmission Owner)’s reliability and economic criteria simultaneously. By
planning process. Unlike traditional planning approach which incorporating the two planning criteria, the proposed planning
seeks to find the least-cost way to expand the system while model can find the trade-off between satisfying reliability
satisfying the reliability constraints during peak-load hours, needs and maximizing the economic value of candidate lines.
economic transmission planning models try to find the The proposed planning model considers wholesale
optimum expansion plan for economic justification of network electricity markets with double-sided auctions. The
investment costs with the economic benefits that network fundamental economic impacts of a transmission upgrade
expansions incur. Since then, many ISO/RTOs started to include promoting competition and enabling the system
implement various economic transmission planning operator to dispatch the generation resources in a more
methodologies in their regional planning [9] [10] [11]. For efficient and economical way. Based on economic theory,
example, Midwest Independent Transmission System social surplus is a good indicator of how efficiently the market
Operator (MISO) initiated a seven-step planning process in is working. Thus, it can be used to quantify the economic
2006 which includes economic studies as a key component benefits of transmission expansions. The proposed economic
[12]. In 2011, FERC issued Order No. 1000 which requires transmission planning model will calculate the sum of the
each region to develop a regional transmission plan using a social surplus at each hour of the planning horizon and find a
process that complies with Order No. 890 principles and trade-off between investment costs and the increase in social
coordinate with neighboring regions to identify potential surplus incurred by network expansions. Besides maximizing
interregional facilities that may be more efficient or cost the economic value of the investment, transmission additions
effective. This order, again, will promote the adoption of also need to ensure the reliability of the system. The planning
economic transmission planning among planning authorities. model adopts the N-1 contingency reliability criterion, which
Most of the transmission expansion projects are justified on requires that the transmission system has enough excess
the ground of enhanced system reliability level or induced capacity to withstand one major facility outage during peak
economic benefits. For example, many transmission additions hours without thermal violations. N-1 contingency criterion
at the low voltage or distribution levels are mainly for has been widely used in reliability-driven transmission
reliability purpose, while some HVAC and HVDC inter- expansion planning models as well as system reliability
regional interconnections are designed to bring economic evaluation models [13] [14].
benefits to multi-regional electric system. However, there is The economic transmission expansion planning problem is
no clear distinction between economic projects and reliability a large-scale mixed-integer non-linear optimization problem
project since transmission expansions inevitably enhance both that requires large computation efforts. In this paper, Benders
the economic and reliability performance to some extent. decomposition approach is employed to reduce the
While many transmission investments focus on one aspect of computation time. Benders decomposition was first introduced
system performance improvement, studies have been made to by J. F. Benders in 1962 to solve mixed-integer programming
assess a new class of transmission expansion projects that not (MIP) problems [15]. A. M. Geoffrion later generalized this
only enhances the system reliability level, but also brings method so it can be applied to solve mixed-integer nonlinear
significant economic value to the system as well. For instance, planning (MINLP) problems under some convex and
MISO has implemented a new Multi-Value Project (MVP) regularity assumptions [ 16 ]. The Benders decomposition
Cost Allocation methodology to address the appropriate match method, as well as the combination of decomposition
of beneficiaries and costs over time. The MVP projects are technique with other approaches, has been used in
transmission additions that provide regional benefits in transmission planning with success [1], [7], [ 17 ]. In this
response to energy policies, and/or by providing multiple model, the overall optimization problem is decomposed into a
regional-level benefits such as increased reliability level master problem, which makes investment decisions; and
and/or economic value [12]. multiple slave problems, which implement the expansion
As the notion of economic transmission planning becomes plans suggested by the master problem and give feedbacks to
popular, transmission planners begin to capture the economic the master problem about the system’s operating conditions.
value of new transmission lines in their planning process. The remaining sections are organized as follows. Section III
However, until now, most planning methodologies evaluate presents the market structure and how the two planning
the reliability of the system after an economic transmission criteria are derived. Section IV describes the procedures of
project is identified or evaluate the economic value of a transmission expansion planning with both reliability and
transmission addition after it is selected based on reliability economic criteria. Section V provides a numerical example to
criteria. Evaluating the economic values and reliability highlight the benefits of the methodology proposed. The
impacts of the candidate transmission lines separately will conclusions drawn from the study are provided in section VI.
generate less-than-optimal investment plan as the decision-
making is biased toward one planning criteria. In many
III. MARKET STRUCTURE AND OPERATION since producers get paid more than their total production cost.
In this paper, the ISO-managed day-ahead market is The social surplus is the sum of consumer surplus and
considered, meaning that all transactions are carried out by an producer surplus, which is essentially area S3 plus S4. For a
ISO which clears the market for both the generation market that has multiple participants, we can get the total
companies (GenCos) and load-serving entities (LSEs) [18]. social surplus on the figure of the cumulative demand curve
At the beginning of each day, each GenCo submits an and cumulative supply curve.
incremental cost and the amount of energy it is willing to sell
and each LSE submits a decremental cost and the amount of
energy it is willing to buy. After receiving offers and bids for
the next day, the ISO then conducts an optimal power flow
based on offers/bids and determines the hourly dispatch
schedules and locational marginal prices (LMPs). In this
paper, we assume that all generators are bidding according to
their marginal cost curves, so strategic bidding is not
considered.
The generator’s cost is generally comprised of three parts: Fig. 2. Supply- and Demand-side bidding curves
fuel cost, emission cost, and variable O&M (operation and
maintenance) cost. The fuel cost is decided by the heat rate of The energy system is modeled using the generalized
the generator, the fuel price at trading point, and the costs to network flow method [19].The basic generalized network flow
transport and store the fuel. In generalized network flow problem can be described as follows. Given a network
model, fuel cost can be expressed as the cost of transferring consisting of a number of nodes and capacitated arcs, we want
the flows (fuel) from the supply nodes to the generator. The to find the optimal routing plan to transfer flows from the
marginal cost of generators normally grows with the increase source nodes (supply nodes) to the destination nodes (demand
of power output. The marginal cost curves can usually be nodes) at minimum cost without violating the capacity limits.
adequately approximated using piecewise linear functions or There are four basic properties associated with each arc: cost
step functions. Fig. 1 shows the generator marginal cost curve coefficient c, flow efficiency η, lower bound emin, and upper
and its major components. The marginal fuel cost can be bound emax. Besides these four properties, many other
described using a step function, while the O&M cost is the properties can also be defined such as generators’ ramp
average cost over a long period of time so it is fixed. As up/down time, start up/shut down costs, investment cost, lead
shown in the figure, when the generator output is x MW, the time, etc. The convex quadratic cost function of the arc flow
production cost is the sum of areas S0, S1 and S2, which are can be linearized by a piecewise linear function or a step
variable O&M cost, emission cost, and fuel cost, respectively. function. Then a single arc can be substituted by multiple arcs,
each representing one segment of the function. In the proposed
model, both the electric system and fuel system are considered
in order to capture the fuel cost of generators directly. In the
proposed model, one generator node is split into a pair of
generator nodes so that operating constraints and O&M costs
can be expressed as the properties of the arc connecting the
two nodes. Generator maximum and minimum output limits
are enforced by constraining the energy flow between the
paired generator nodes.

Fig. 1. Generator marginal cost curve IV. TRANSMISSION PLANNING MODEL


Fig. 2 shows the case where there is only one seller and A. Transmission Planning Considering Two Criteria
one buyer in the market. L1 is the demand curve for the The iteration procedures of the new planning model are
consumer, while L2 is the marginal cost curve for the shown in Fig. 3. First, the master problem is solved based on
generator. The elasticity of electric demand is considered, the existing system conditions. At the beginning of the
which means that customers are sensitive to the price at which planning process, the master problem is solved without any
electric power is sold and will not buy it if the price exceeds constraint from the slave problems. The output of the master
what they expect. In other words, consumers will pay a certain problem is the investment decisions about when, where and
price, or a certain range of prices, for electric power. In Fig. 2, which lines should be built which will be sent to the sub-
the market reached an economic equilibrium at quantity x and problems. After the investment plan is selected, the economic
price y. In economics theory, consumer surplus is the area benefits evaluation sub-problem is updated based on the
above the price level and below the demand curve, since the transmission investment plan proposed by the master problem.
price that consumers pay is equal to the value of the last unit Then the problem is solved to simulate the operations of the
of energy (the marginal value). In contrast, producer surplus is market throughout the whole planning scope. A benders
the area below the price level and above the supply curve, optimality check is conducted to check if the current
investment plan is optimal (in terms of economic benefits) or investments are justified on the grounds of reliability
not. If not, an optimality cut will be added to the master requirements. In reliability-based transmission planning, the
problem. investment decision is made based on snapshots of some
After the economic evaluation sub-problem is done, the operating conditions, such as peak-load hours, or shoulder
reliability evaluation sub-problems are also updated based on load hours and under various contingencies. In this paper, an
the transmission investment plan selected by the master N-1 contingency reliability criterion is adopted. The N-1
problem. The reliability evaluation sub-problems check the contingency criterion means that the system should withstand
adequacy of the electric supply under various contingencies the outage of one major element, such as a line, generator or
for the whole planning horizon. If there is a violation in any transformer. In this paper, we only consider transmission line
slave problem, a Benders feasibility cut is generated and outages.
added to the master problem. 2) Reliability Evaluation sub-problem
If no optimality cut or feasibility cut is added to the master In the slave problem, the impact of the transmission
problem, the current investment plan is optimal and the expansion plan is assessed under worse-case scenarios to
program stops, otherwise the master problem is updated and ensure the system is designed and operated to a certain level of
solved and the iteration continues. In the next iteration, the reliability. As the N-1 contingency criterion is adopted, the
master will be solved with the cuts generated from previous transmission investment must ensure that, under the loss of
iterations. any single equipment, the system won’t have any load
curtailment during peak hours throughout the planning horizon.
Thus, each slave problem is a feasibility check problem, which
checks the reliability of the system under an N-1 contingency.
In each round of iteration, there are w sub-problems, each
representing the outage of one major element in the system.
rj(t) is the slack variable in constraint (2), which balances the
total energy input and total energy output for node j at time t.
If rj(t)>0, it means that there is not enough power to supply
the electric demand. In this case, a portion of the demand
cannot be satisfied and a violation occurs. Zrw is the sum of all
slack variables, and if Zrw >0, it means that violations occur
during the wth contingency. Thus, a feasibility cut is added to
the master problem in order to eliminate the violations. If
Zrw=0, then there are no violations and there is no feedback to
the master problem.
w
Min Zr = ∑ ∑ r j (t ) (1)
t∈T ∀j∈N ∪N '
subject to
∑ ηij eij (t ) − ∑ ( e jk ( t ) + en (t )) + r (t ) = 0 ∀j ∈ N ∪ N ',
jk j
∀i ∀k (2)
∀(ij ) ∈ M ∪ M '∪ Mn ', ∀( jk ) ∈ M ∪ M '∪ Mn '∪ d
w
e (t ) − b h (θ (t ) − θ ( t )) = 0
ij ij ij i j
∀(ij ) ∈ M ' (3)
k w
en (t ) − n (t ) h ( t ) b (θ (t ) − θ ( t )) = 0
ij ij ij ij i j
∀( ij ) ∈ Mn ' (4)
e
ij.min
≤ e (t ) ≤ e
ij ij.max
∀(ij ) ∈ M ∪ M '∪ d (5)
k k
n (t )e
ij ij .min
≤ en ( t ) ≤ n (t ) e
ij ij ij .max
∀ (ij ) ∈ Mn ' (6)
−π ≤ θ ≤ π
i
∀i ∈ N ' (7)
w
where h is 0 if (i, j) is the wth line; otherwise it’s 1.
ij
The operation sub-problem is modeled using the
generalized network flow method. The electric power
Fig. 3. Transmission planning considering both economic benefits and generation/transfer are considered as energy flows in the
reliability requirement
system. The prices of different kinds of fuels at the fuel
B. Reliability Evaluation Sub-problem production side, such as wellhead natural gas prices and spot
1) Reliability-based Transmission Planning prices of coal in different coal-producing regions, are included
The objective of the reliability-based transmission in the cost properties of transportation arcs. Equation (2)
expansion planning is to find the least-cost alternative to serve shows that for each node, the sum of flows into the node
the loads of all existing and future customers reliably. Capital minus the flows out of the node equals the demand (or supply
if negative) of the node. Equations (3) and (4) calculate the will generate a feasibility cut only when its optimal objective
flow in existing and newly installed lines, respectively. Arc value is higher than zero.
flows and power angles must be within constraints, as shown
Min Z = ∑ (1+ r )−t ( ∑ r j (t )lol
in constraints (5), (6) and (7). Constraint (5) exerts constraints t∈T ∀j∈N ∪ N '
on flows in the existing network; Constraint (6) exerts (8)
constraints on flows in the potential lines. If no new line is + ∑ Sij ( eij (t )) − ∑ Dij ( eij (t )))
installed in time t, nij(t) is 0, then enij(t) is also 0. For the fuel (i , j )∈m (i , j )∈d
transportation network, arc flows should be larger than or e (t ) − b (θ (t ) − θ (t )) = 0 ∀(ij ) ∈ M ' (9)
equal to zero, whereas in the transmission network, arc flow ij ij i j
can be negative to account for the bidirectional nature of the k
en (t ) − n (t )b (θ (t ) − θ (t )) = 0 ∀(ij ) ∈ Mn ' (10)
power flow. ij ij ij i j
k k
C. Economic Benefits Evaluation Sub-problem n (t )e
ij ij .min
≤ en ( t ) ≤ n (t ) e
ij ij ij .max
∀ (ij ) ∈ Mn ' (11)
1) Economic Transmission Planning
∑ ηij eij (t ) − ∑ (e jk (t ) + en (t )) + r (t ) = 0 ∀j ∈ N ∪ N ',
The principle of economic transmission investment is based ∀i ∀k
jk j (12)
on the premise that an efficient investment might yield ∀(ij ) ∈ M ∪ M '∪ Mn ', ∀ ( jk ) ∈ M ∪ M '∪ Mn '∪ d
sufficient economic benefit. In many economic planning
models, in order to capture the fundamental economic benefits e
ij.min
≤ e (t ) ≤ e
ij ij.max
∀(ij ) ∈ M ∪ M '∪ d (13)
of circuit installations, various expansion criteria are defined, (14)
−π ≤ θ ≤ π ∀i ∈ N '
such as production costs [5], flatness of price profile [1], i
congestion rent [4], redispatch cost, etc. According to [8], As shown in Fig. 2, if we assume the intercept and slope of
promoting market efficiency is one of the major objectives of consumer bidding curve for ( i , j ) ∈ d are pij and qij
the electric market framework. In the proposed planning respectively, the total consumer benefit Dij(eij(t)) is:
model, social surplus is used as the economic evaluation 2
criterion as it is the primal measure of the efficiency of a D ( e ( t )) = p e (t ) + q e (t ) / 2
ij ij ij ij ij ij
(15)
market. From the social welfare perspective, a transmission In the same way, the total production cost Sij(t) can also be
investment can be justified economically if the total social expressed as a function of eij(t). Note that in Fig. 2, the
surplus increase caused by the investment is higher than the consumer bidding curve and generator marginal cost curve are
cost of the investment itself. However, the two values are hard expressed as a linear function and a step function,
to compare in that while investment cost is incurred at a respectively. However, as long as the total consumer payment
certain time and can be considered as present value at the and generation cost are quadratic functions, the problem can
beginning of the planning horizon, social surplus occurs at be solved, e.g. the consumer bidding curve can be a piece-wise
every time step. So in the economic benefits evaluation sub- linear curve or step curve.
problem, social surplus must be calculated at every time step In order to encapsulate the load duration characteristics of
throughout the planning horizon, and then be converted to the the demand, load is represented as yearly load duration curves
present value for comparison purpose. (LDCs). An LDC plots the number of hours (percentage of
2) Economic Benefits Evaluation sub-problem hours per year) that the load equals or exceeds a given level of
The economic benefits evaluation sub-problem tries to demand. Compared to simulating the system chronologically,
minimize {social cost plus loss of load penalties}, where LDC helps to reduce the computation time.
social cost is the negative of social surplus.
The major differences between the economic benefits D. Master problem
evaluation sub-problem and the reliability evaluation sub- In the planning problem, while generally more circuit
problem are that: (1) The former tries to minimize the social expansions will promote the efficient operation of the electric
costs by conducting optimal power flow (OPF), while the market and increase the social surplus, they also means more
latter tries to check if there is any load curtailment; (2) The investment cost. The master problem tries to find a trade-off
former needs to calculate the economic value introduced by between high investment cost and increase in social surplus.
circuit additions throughout the planning horizon, which The objective function is the minimization of social costs
means it needs to optimize the operations of system either (investment costs minus social surplus), which is the same as
chronologically or under a set of typical conditions that can maximization of social surplus minus investment costs.
approximate the hour-by-hour load levels, while the latter only Constraint (18) is the optimality cut from the economic
needs to check violations during some snapshot hours of each benefits evaluation sub-problem; while constraint (19) is the
year; (3) The former is a quadratic programming problem as feasibility cut from the reliability evaluation sub-problem.
the double-sided bidding is considered, while the latter is a These two types of constraints force the master problem to
linear programming problem; (4) There is only one slave select an economic transmission investment plan that satisfies
problem in economic planning, while there are w slave the reliability criteria. Equation (20) updates the total number
problems in reliability-based planning, each representing a of lines between i and j.
contingency in the system; and (5) The economic benefits −t ∗
Min ∑ ∑ (1+ r ) Iij mij (t ) + Z (16)
evaluation sub-problem will generate an optimality cut to the t∈T ( ij )∈Mn '
master problem, while each reliability evaluation sub-problem

Z ≤ 0 (17)
∗ k TABLE I
k k
Z ≥ ∑ ∑ δij (t )(nij (t )−nij (t )) + Z (18) INVESTMENT PLANS MADE BY THE THREE PLANNING METHODS
t∈T (ij )∈Mn '
kw k kw
∑ ∑ δij (t )(nij (t )−nij (t )) + Zr ≤0 (19)
t∈T (ij )∈Mn '
n (t ) = n (t − 1) + m (t − a )
ij ij ij (20)
0 ≤ m (t ) ≤ mij
ij (21)
0 ≤ n (t ) ≤ nij
ij (22)
k
where Z is the optimal value of the slave problem in the kth In order to reduce the present value of investment cost,
iteration and δij is the sensitivity of the optimum value Z with reliability-based planning will not invest new lines until they
respect to the decision variable nij derived by Romero and are needed for reliability purpose. Because of the discount
Monticelli [20]. δij can be expressed as (23). rate, the later the investment is made, the smaller the present
value of the investment is. Economic planning, however, tries
δ ij (t ) = − Bij (θi (t ) − θ j (t ))(λi (t ) − λ j (t )) to find the opportunities to invest new circuits that can bring
(23) more social surplus than their costs. The test system is highly
congested, so economic planning model tends to build new
V. ILLUSTRATIVE EXAMPLES lines at the beginning of the planning horizon in order to get
To evaluate the methodology presented above, a 5-bus more economic benefits. Line 4-5 and line 3-4 are the only
system has been considered. Fig. 4 shows the network diagram two lines connecting bus 4 with the rest of the system. As the
of the integrated energy system, which has three integrated capacity of the generator in bus 4 is much lower than the
gasification combined cycle (IGCC) power plants, one natural demand, a lot of electric power needs to be transferred from
gas combined cycle (NGCC) power plant and an oil-fueled the other buses. So the two lines become congested as the load
power plant. The fuel subsystem which includes four fuel grows over time and new lines need to be installed in order to
suppliers and eight fuel transportation lines is also considered. supply the demand. The LMP in bus 2 is the lowest in the
Fuel transportation arcs X5 and X6 do not exist at the system. However, the low-cost energy from generator 2
beginning of the planning horizon. They will come into use at cannot be transferred to bus 4 in that line 1-2 and line 3-4 are
year 2 and year 5, respectively. The network data for this highly congested. Thus, the economic transmission planning
system is given in [21]. Emission cost is not considered. model will invest new lines on arcs 1-2 and 3-4 in order to
relieve congestion, reduce congestion cost, and as a
consequence, increase social surplus. Note that the candidate
line 3-4 is selected by both the reliability-based planning and
economic planning which shows that there is no clear
distinction between reliability projects and economic projects.
The main drawback of economic transmission planning
method is that no rigorous reliability constraint is considered.
The proposed planning model, however, can maximize the
economic value of transmission investment while satisfying
the reliability criteria.
TABLE II
Fig. 4. Five-bus system COMPARISON OF THE RESULTS OF THE TWO PLANNING METHODS

The expected values of the natural gas price and oil price
escalate at a rate of 4% per year, while the coal price has a
growth rate of 2% per year. The coal price is determined
mainly by long-term contracts, and coal supply is less
dependent on import than oil and natural gas, so the coal price
tends to be stable. As shown in Table II, all three planning methods increase
The transmission expansion planning is carried out on this the social surplus as all of them reduce the congestion in the
system for a planning horizon of 10 years. Annual LDC curves system. Economic transmission planning has a smaller
are used to reduce the computation time. Investment decisions investment cost than that of reliability-based planning, yet it
can only be made at the beginning of each year. generates a higher social surplus. The proposed planning
In order to illustrate the differences between the proposed model considers a trade-off between two planning criteria so
planning model and reliability-based/economic planning the total {social surplus – investment cost} is higher than that
models, all three models are applied on this test system. The of the reliability-based planning and lower than that of the
simulation results generated by the three planning methods are economic planning.
shown in Table I. The test system is highly congested, so there are many
investment opportunities. What is more, as the system is benefits.
small, most candidate lines are beneficial in terms of both
system reliability and economic value. In some large systems, VII. REFERENCE
economic transmission planning often selects high-capacity
long-distance transmission backbones to deliver low cost [1] M. Buygi, G. Balzer, H. Shanechi, and M. Shahidehpour,
energy from one area to another; while reliability-based “Market-based transmission expansion planning,” IEEE
planning often selects low-cost lines to fix the local reliability Transactions on Power Syst., vol. 19, no. 4, November 2004.
violations. Generally speaking, economic transmission [2] Department of Energy, National Transmission Grid Study.
projects are more expensive than reliability projects. As the May 2002. Available online:
http://disgen.epri.com/downloads/issuepapers_screen.pdf
proposed planning method combines both the “top-down” and
[ 3 ] U.S. Department of Energy, Transmission Bottleneck
the “bottom-up” planning approaches, a mixed portfolio of
Project Report. March 2003. Available online:
reliability projects and economic projects will be invested. http://www.doe.gov/oe/downloads/transmission-bottleneck-project-
While intensive studies have been done on expanding the report-march-19-2003
electric transmission system, how congestions in the fuel [4] G. B. Shrestha and P. A. J. Fonseka, “Congestion-driven
delivery network interact with those in the electric system has transmission expansion in competitive power market,” IEEE
not been given enough attention. Just like congestions in the Transactions on Power Syst., vol. 19, no. 3, August 2004.
electric system, congestions in the fuel transportation lines [ 5 ] Sevin Sozer, Chan S. Park, and Jorge Valenzuela,
will also cause differences in nodal prices and prevent the “Economic analysis of electric power transmission
efficient transportation of fuel resources. Because of economic expansion,” The Engineering Economist, 53:293--317, 2008.
interdependencies between the fuel system and electric [ 6 ] S. Wang, J. Zhu, L. Trinh, and J. Pan, “Economic
system, investments in the fuel system will have a profound assessment of HVDC project in deregulated energy markets,”
impact on the electric system. So it makes sense to include DRPT, April 2008.
fuel transportation network investments as decision variables [ 7 ] J. Roh, M. Shahidehpour, and L. Wu, “Market-based
in the overall planning problem. This model can help decision generation and transmission planning with uncertainties,”
makers carry out analyses on this issue and get a better IEEE Transactions on Power Syst., vol. 24, no. 3, August
2009.
understanding of it.
[8] Consortium of Electric Reliability Technology Solutions,
Economic evaluation of transmission interconnection in a
VI. CONCLUSION
restructured market, California ISO, June 2004.
In this paper, a new transmission planning model which [ 9 ] California Independent System Operator, Transmission
considers both the economic value of the transmission Economic Assessment Methodology, June 2004. Available
investment and the reliability of the system is proposed. online:
Currently, many planning entities conduct reliability-based http://www.caiso.com/docs/2004/06/03/2004060313241622985.pdf
planning and economic planning separately. While various [10] PJM, PJM 2010 Regional Transmission Expansion Plan,
methodologies are employed to capture the economic value of Feb. 2011. Available online:
the candidate transmission lines in their planning process, the http://www.pjm.com/documents/reports/rtep-report.aspx
[11] Southwest Power Pool, Integrated Transmission Planning
reliability evaluation is not conducted simultaneously with the
Process Document, Oct. 2010. Available online:
economic evaluation. The candidate line with the highest http://www.spp.org/publications/ITP_Process_Final_20091029.pdf
economic value might have little or even negative impact on [12] MISO, Midwest ISO Transmission expansion plan 2010,
system reliability. On the other hand, in reliability-based Jan. 2011. Available online:
planning, the objective is to address reliability requirement in https://www.midwestiso.org/Library/Repository/Study/MTEP/MTEP
a minimal-cost way. The lowest-cost option might not bring 10/MTEP10%20Report.pdf
the highest economic value and the lowest overall cost in the [13] C. Jaeseok, T.D. Mount, and R.J. Thomas, “Transmission
long run. For example, up-sizing reliability projects or Expansion Planning Using Contingency Criteria,” IEEE
selecting more expensive alternatives might capture extra Transactions on Power Syst., vol. 22, no. 4, Nov. 2007.
economic benefits, such as congestion reduction, renewable [14] H. Ren, I.Dobson, and B.A. Carreras, “Long-Term Effect
integration, enhanced market efficiency, etc. The proposed of the n-1 Criterion on Cascading Line Outages in an Evolving
planning model can evaluate a whole set of candidate line Power Transmission Grid,” IEEE Transactions on Power
based on both economic criterion and reliability criterion, and Syst., vol. 23, no. 3, August 2008.
select a hybrid transmission investment plan that fulfills [15] J. F. Benders, “Partitioning procedures for solving mixed-
variables programming problems,” Journal Numerische
reliability constraints while maximizing the economic value.
Mathematik, vol. 4, no. 1, pp. 238–252, Dec. 1962.
As most transmission additions have both reliability and
[16] A. M. Geoffrion, “Generalized benders decomposition,”
economic impacts on the system, the proposed planning model Journal of Optimization Theory and Applications, vol. 10, no.
can find candidate lines that are trade-offs between the two 4, pp. 237–260, Oct. 1972.
aspects, i.e. those candidate lines that are neither the lowest- [ 17 ] Y. Li and J. McCalley, “A General Benders
cost reliability projects nor the most valuable economic Decomposition Structure for Power System Decision
projects might be selected by the proposed model as they
provide the best combinations of reliability and economic
Problems,” IEEE International Conference on
Electro/Information Technology, EIT 2008.
[18] J. Nicolaisen, V. Petrov, and L. Tesfatsion, “Market
Power and Efficiency in a Computational Electricity Market
With Discriminatory Double-Auction Pricing,” IEEE
Transactions on Evolutional Computation, vol. 5, no. 5,
October 2001.
[19] A. Quelhas, E. Gil, J. D. McCalley, and S. Ryan, “A
multiperiod generalized network flow model of the U.S.
integrated energy system part I- model description,” IEEE
Transactions on power syst., vol. 22, no. 2, 2007.
[20] R. Romero, A. Monticelli, “A hierarchical decomposition
approach for transmission network expansion planning,” IEEE
Trans. on Power Syst., vol. 9, no. 1, Feburary 1994.
[21] Y. Gu and J. McCalley, “Market-based Transmission
Expansion Planning,” in Proc. IEEE PES Power Systems
Conference & Exhibition (PSCE), Phoenix, Arizona, March
2011.
XI. BIOGRAPHIES
Yang Gu (S’07, M’11) received the B.S. degree in Electrical
Engineering from Shandong University, Jinan, China, in 2007, and
the Ph.D. degree in Electrical Engineering from Iowa State
University, Ames, IA, in 2011. He is currently an Economic Studies
Engineer at MISO. His main areas of interest are power system
capacity expansion planning, optimization theories, power system
operation, balancing, day-ahead, and ancillary services markets.

Ming Ni (M’ 1998, SM’ 2005) received his B.S. and Ph.D. degrees
in Electrical Engineering in 1991 and 1996 respectively, from
Southeast University of P.R. China. He is now the Manager of
Economic Studies in MISO. His primary responsibilities involve the
economic assessment of transmission upgrade, and other electricity
market related economic analysis.

Rui Bo (SM’10) received the B.S. and M.S. degrees in electric power
engineering from Southeast University (China) in 2000 and 2003,
respectively, and then his Ph.D. degree from University of
Tennessee, Knoxville, TN in 2009. He worked at ZTE Corporation
and Shenzhen Cermate Inc. from 2003 to 2005, respectively. Since
2009, he has been employed at MISO as an Economic Studies
Engineer.

You might also like