Professional Documents
Culture Documents
The expected values of the natural gas price and oil price
escalate at a rate of 4% per year, while the coal price has a
growth rate of 2% per year. The coal price is determined
mainly by long-term contracts, and coal supply is less
dependent on import than oil and natural gas, so the coal price
tends to be stable. As shown in Table II, all three planning methods increase
The transmission expansion planning is carried out on this the social surplus as all of them reduce the congestion in the
system for a planning horizon of 10 years. Annual LDC curves system. Economic transmission planning has a smaller
are used to reduce the computation time. Investment decisions investment cost than that of reliability-based planning, yet it
can only be made at the beginning of each year. generates a higher social surplus. The proposed planning
In order to illustrate the differences between the proposed model considers a trade-off between two planning criteria so
planning model and reliability-based/economic planning the total {social surplus – investment cost} is higher than that
models, all three models are applied on this test system. The of the reliability-based planning and lower than that of the
simulation results generated by the three planning methods are economic planning.
shown in Table I. The test system is highly congested, so there are many
investment opportunities. What is more, as the system is benefits.
small, most candidate lines are beneficial in terms of both
system reliability and economic value. In some large systems, VII. REFERENCE
economic transmission planning often selects high-capacity
long-distance transmission backbones to deliver low cost [1] M. Buygi, G. Balzer, H. Shanechi, and M. Shahidehpour,
energy from one area to another; while reliability-based “Market-based transmission expansion planning,” IEEE
planning often selects low-cost lines to fix the local reliability Transactions on Power Syst., vol. 19, no. 4, November 2004.
violations. Generally speaking, economic transmission [2] Department of Energy, National Transmission Grid Study.
projects are more expensive than reliability projects. As the May 2002. Available online:
http://disgen.epri.com/downloads/issuepapers_screen.pdf
proposed planning method combines both the “top-down” and
[ 3 ] U.S. Department of Energy, Transmission Bottleneck
the “bottom-up” planning approaches, a mixed portfolio of
Project Report. March 2003. Available online:
reliability projects and economic projects will be invested. http://www.doe.gov/oe/downloads/transmission-bottleneck-project-
While intensive studies have been done on expanding the report-march-19-2003
electric transmission system, how congestions in the fuel [4] G. B. Shrestha and P. A. J. Fonseka, “Congestion-driven
delivery network interact with those in the electric system has transmission expansion in competitive power market,” IEEE
not been given enough attention. Just like congestions in the Transactions on Power Syst., vol. 19, no. 3, August 2004.
electric system, congestions in the fuel transportation lines [ 5 ] Sevin Sozer, Chan S. Park, and Jorge Valenzuela,
will also cause differences in nodal prices and prevent the “Economic analysis of electric power transmission
efficient transportation of fuel resources. Because of economic expansion,” The Engineering Economist, 53:293--317, 2008.
interdependencies between the fuel system and electric [ 6 ] S. Wang, J. Zhu, L. Trinh, and J. Pan, “Economic
system, investments in the fuel system will have a profound assessment of HVDC project in deregulated energy markets,”
impact on the electric system. So it makes sense to include DRPT, April 2008.
fuel transportation network investments as decision variables [ 7 ] J. Roh, M. Shahidehpour, and L. Wu, “Market-based
in the overall planning problem. This model can help decision generation and transmission planning with uncertainties,”
makers carry out analyses on this issue and get a better IEEE Transactions on Power Syst., vol. 24, no. 3, August
2009.
understanding of it.
[8] Consortium of Electric Reliability Technology Solutions,
Economic evaluation of transmission interconnection in a
VI. CONCLUSION
restructured market, California ISO, June 2004.
In this paper, a new transmission planning model which [ 9 ] California Independent System Operator, Transmission
considers both the economic value of the transmission Economic Assessment Methodology, June 2004. Available
investment and the reliability of the system is proposed. online:
Currently, many planning entities conduct reliability-based http://www.caiso.com/docs/2004/06/03/2004060313241622985.pdf
planning and economic planning separately. While various [10] PJM, PJM 2010 Regional Transmission Expansion Plan,
methodologies are employed to capture the economic value of Feb. 2011. Available online:
the candidate transmission lines in their planning process, the http://www.pjm.com/documents/reports/rtep-report.aspx
[11] Southwest Power Pool, Integrated Transmission Planning
reliability evaluation is not conducted simultaneously with the
Process Document, Oct. 2010. Available online:
economic evaluation. The candidate line with the highest http://www.spp.org/publications/ITP_Process_Final_20091029.pdf
economic value might have little or even negative impact on [12] MISO, Midwest ISO Transmission expansion plan 2010,
system reliability. On the other hand, in reliability-based Jan. 2011. Available online:
planning, the objective is to address reliability requirement in https://www.midwestiso.org/Library/Repository/Study/MTEP/MTEP
a minimal-cost way. The lowest-cost option might not bring 10/MTEP10%20Report.pdf
the highest economic value and the lowest overall cost in the [13] C. Jaeseok, T.D. Mount, and R.J. Thomas, “Transmission
long run. For example, up-sizing reliability projects or Expansion Planning Using Contingency Criteria,” IEEE
selecting more expensive alternatives might capture extra Transactions on Power Syst., vol. 22, no. 4, Nov. 2007.
economic benefits, such as congestion reduction, renewable [14] H. Ren, I.Dobson, and B.A. Carreras, “Long-Term Effect
integration, enhanced market efficiency, etc. The proposed of the n-1 Criterion on Cascading Line Outages in an Evolving
planning model can evaluate a whole set of candidate line Power Transmission Grid,” IEEE Transactions on Power
based on both economic criterion and reliability criterion, and Syst., vol. 23, no. 3, August 2008.
select a hybrid transmission investment plan that fulfills [15] J. F. Benders, “Partitioning procedures for solving mixed-
variables programming problems,” Journal Numerische
reliability constraints while maximizing the economic value.
Mathematik, vol. 4, no. 1, pp. 238–252, Dec. 1962.
As most transmission additions have both reliability and
[16] A. M. Geoffrion, “Generalized benders decomposition,”
economic impacts on the system, the proposed planning model Journal of Optimization Theory and Applications, vol. 10, no.
can find candidate lines that are trade-offs between the two 4, pp. 237–260, Oct. 1972.
aspects, i.e. those candidate lines that are neither the lowest- [ 17 ] Y. Li and J. McCalley, “A General Benders
cost reliability projects nor the most valuable economic Decomposition Structure for Power System Decision
projects might be selected by the proposed model as they
provide the best combinations of reliability and economic
Problems,” IEEE International Conference on
Electro/Information Technology, EIT 2008.
[18] J. Nicolaisen, V. Petrov, and L. Tesfatsion, “Market
Power and Efficiency in a Computational Electricity Market
With Discriminatory Double-Auction Pricing,” IEEE
Transactions on Evolutional Computation, vol. 5, no. 5,
October 2001.
[19] A. Quelhas, E. Gil, J. D. McCalley, and S. Ryan, “A
multiperiod generalized network flow model of the U.S.
integrated energy system part I- model description,” IEEE
Transactions on power syst., vol. 22, no. 2, 2007.
[20] R. Romero, A. Monticelli, “A hierarchical decomposition
approach for transmission network expansion planning,” IEEE
Trans. on Power Syst., vol. 9, no. 1, Feburary 1994.
[21] Y. Gu and J. McCalley, “Market-based Transmission
Expansion Planning,” in Proc. IEEE PES Power Systems
Conference & Exhibition (PSCE), Phoenix, Arizona, March
2011.
XI. BIOGRAPHIES
Yang Gu (S’07, M’11) received the B.S. degree in Electrical
Engineering from Shandong University, Jinan, China, in 2007, and
the Ph.D. degree in Electrical Engineering from Iowa State
University, Ames, IA, in 2011. He is currently an Economic Studies
Engineer at MISO. His main areas of interest are power system
capacity expansion planning, optimization theories, power system
operation, balancing, day-ahead, and ancillary services markets.
Ming Ni (M’ 1998, SM’ 2005) received his B.S. and Ph.D. degrees
in Electrical Engineering in 1991 and 1996 respectively, from
Southeast University of P.R. China. He is now the Manager of
Economic Studies in MISO. His primary responsibilities involve the
economic assessment of transmission upgrade, and other electricity
market related economic analysis.
Rui Bo (SM’10) received the B.S. and M.S. degrees in electric power
engineering from Southeast University (China) in 2000 and 2003,
respectively, and then his Ph.D. degree from University of
Tennessee, Knoxville, TN in 2009. He worked at ZTE Corporation
and Shenzhen Cermate Inc. from 2003 to 2005, respectively. Since
2009, he has been employed at MISO as an Economic Studies
Engineer.