Wind World India Ltd

BEED VCB AUDIT/ INSPECTION REPORT


Stage of Audit/ Inspection :- Final
Date: 18/06/2016
Site:- BEED section (Khandke site)
Auditors:
SIQA SERVICE
Wind World India Ltd.
EED VCB AUDIT/ INSPECTION REPORT
ge of Audit/ Inspection :- Final
te: 18/06/2016
e:- BEED section (Khandke site)
Manish Singh & Anant Jagtap (SIQA Representative)
Kanifnath Karale (WWIL Project Representative)
Tushar Bhand (WWIL Service Representative)

Observation

PG Clamp need to be used instead of binding In Incomers and outgoing side

Isolator Assembly Missing

Water accumulated around the panel


One disc of R-phase VCB found damage

Gravels spreading not uniform also not up to the level

VCB panel cover and lock missing

VCB Manual spring charger section metal plate cover found in the control panel

Earth pit chamber cover missing


CT & PT cover earthing and missing
Some hardware are loose and missing at CT & PT
Boundary Net hardware missing
VCB relay setting need to be done
SIQA SERVICE
.