CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY REPORTS

CLIENT: Abu Dhabi Sewerage Services Company Date: 09 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sectors W2, W4, W6 & W7
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
* Sector W2 Excavation and Dewatering bet H25 to H25/1 , Backfilling Bet H25/3 to H25/2 , H25/2 to H25/1 , H27/8 to
H27/8/1 and bet H27/8 to H27/8/2 . Hydro test Bet H25/6 to H25/1 and H27/8/1 to H27/8 .
* Sector W4,– Dewatering for lines 6,4, 9 & 10. At Line 6 : Fixing of shuttering and support for D53/13/25N/1 , Excavation
up to Blinding formation level for D53/13/19N . At line 4 : Excavation and exposing of ext 15o mm GRP bet D53/12/1
to D53/12 Ongoing . At Line 3 : Removal of asphalt and interlock ongoing . At Line 8 : rectification of Interlock Ongoing .
at Line 9 :Chipping of GRP Port for 200mm at D53/26 ongoing . At Line 10 : Excavation from CH 48 to 54 bet D53/23/2
to D53/23/1 for Line 10 .
Gravel Surrounded for Pipe bet D53/13/25/1 to D53/13/19N Completed , MH Base + Shaft Completed for
D53/13/25N , Excavation and Formation at MH D53/13/19N Done .
* Sector W6– Line 2 : Excavation & sheet Pilling at BD H3/A. Line 10 : Demolishing and Removal of Ext Sewer Duct bet
H19/5 to H19/4 ( 40 m Done ) . at line 9 & 8 : Asphalt cutting .
* Sector W7 – at Line 11 : Fixing of Dewatering System . Concreting of Pipe bet H9/2 to H9/3 ( 38 m Done ) . bet H9/1 to
H9/5 Demolishing of ext Sewer duct and Fixing of S.O.P system .

Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Secretary 01 Charge Hand* 08
Project Manager 01 Time keeper 01 Asst. Surveyor* 01
Dy. Project Manager 01 CAD Technician 04 Mason* 05
Construction Manager 01 HSE Engineer 01 Operator* 13
Site Agent 01 Office boy 02 Pipe Fitter* 04
QS 01 Site Engineer* 04 Welder* 04
PRO 01 Foreman* 02 Carpenter* 03
Accountant 01 Safety Officer* 04 Steel Fixer* 00
QA/QC 01 Surveyor* 05 Laminator* 01
Planning Engineer 01 Chainman* 04 Watchman 06
Supervisor 01 Driver* 07 Others: (SOP) 08
Material Engineer 01 Labors* 83 Asst. Welder 01
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type Mod No. WG IL BD
Pick Up (3T) 04 04 Bob Cat 02 02
DC Pick Up 01 01 Dewatering Pumps:
Mini Bus (14 Seat)* Electrical Pumps 00 00
01 01 (Submersible)
Mini Bus (65 Seat)* 01 01 Diesel Pumps (6" & 17 17
Car (Salon) 04 04 Jetting Pumps 01 01
JCB 04 04 Overpumping Pumps:
Asphalt Cutter Elec’l Pumps 15 15
01 01 (Submersible)
Compressor Jack Hammer 01 01 Diesel Pumps (6" & 05 05
Excavator 05 05 Welding Machine 04 04
Plate Compactor 03 03 Shovel 00 00
Crane * 00 00 Jack Hammer Exc. 00 00
Tipper 02 02 Generator 00 00
Drill Excavator 01 01 Vibrator 00 00
Remarks: Common equipment with mark of “*” being utilized for the whole project.
For Contractor: Checked by (DC):

Date: Date: