You are on page 1of 2

CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY REPORTS

CLIENT: Abu Dhabi Sewerage Services Company Date: 09 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sectors E19 & E19/01 , E10 , E14 and Sector E16-02
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
* Sector E19 – at Line 10: lowering excavation bet A to A8 ( 5 m Ongoing ) , backfilling and compaction bet A4 to A3 ( 3 Layers Done )
at Line 6 : Lowering Excavation at D22/13N/1 Ongoing . Asphalt reinstatement at Line 6 and Line 14 .
Manhole and Pipes Handing Over at Line 6 , Line 5 and Line 14

* sector E10 - Hand Excavation and Breaking of foot bath at Line 12 .

* sector E14 – Surveying works .

* Sector E16-01 – trial pit at Sector E16-02.

Manpower:

Staf No. Total Staf No. Total Staf No. Total


Construction Director 01 Secretary 01 Charge Hand* 02
Project Manager 01 Time keeper 01 Asst. Surveyor* 00
Dy. Project Manager 01 CAD Technician 04 Mason* 01
Construction Manager 01 HSE Engineer 01 Operator* 06
Site Agent 01 Office boy 02 Pipe Fitter* 02
QS 01 Site Engineer* 02 Welder* 01
PRO 01 Foreman* 02 Carpenter* 01
Accountant 01 Safety Officer* 01 Steel Fixer* 00
QA/QC 01 Surveyor* 01 Laminator* 01
Planning Engineer 01 Chainman* 01 Watchman* 03
Supervisor 01 Driver* 01 Asst. Safety* 01
Material Engineer 01 Labors* 35 Asst. Welder* 01
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type M No. WG IL BD
Pick Up (3T) 02 02 Bob Cat 01 01
DC Pick Up 01 01 Dewatering Pumps:
Mini Bus (14 Seat)* 01 01 Electrical Pumps 03 03
(Submersible)
Mini Bus (65 Seat)* 01 01 Diesel Pumps (6" & 4") 04 04
Car (Salon) 02 02 Jetting Pumps 00 00
JCB 02 02 Overpumping Pumps:
Asphalt Cutter 01 01 Elec’l Pumps 05 05
(Submersible)
Compressor Jack Hammer 01 01 Diesel Pumps (4”,6" & 08 08
8”)
Excavator 01 01 Welding Machine 01 01
Plate Compactor 01 01 Shovel 01 01
Crane * 00 00 Jack Hammer Exc. 01 01
Tipper 01 01 Generator 00 00
Drill Excavator 00 00 Mini Digger 01 01
Remarks: Common equipment with mark of “*” being utilized for the whole project.