Activity Activity Orig Rem % Predecessors Early Early DEC

17 18 19 20 21 22 23 24
ID Description Dur Dur Start Finish 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12

Hot Tap Work


Subtotal 151 151 0 17DEC10 23DEC10
01:00 07:59

Work Pack 010


Tie-in 200
Procurement
HT020 Hot tap material received 0 0 0 17DEC10 Hot tap material received
00:59*

Off Site Fabrication


HT010 Fabriate Hot tap split tee 8 8 0 HT020* 17DEC10 17DEC10 Fabriate Hot tap split tee
01:00 08:59
HT030 Blast & Paing Hot tap split tee 48 48 0 HT010* 17DEC10 19DEC10 Blast & Paing Hot tap split tee
09:00 08:59
HT320 Delivery to site 8 8 0 HT030* 19DEC10 19DEC10 Delivery to site
09:00 16:59

Preliminary Activities
HT040 Erect Spark Containment Habitat 2 2 0 18DEC10 18DEC10 Erect Spark Containment Habitat
02:00* 03:59
HT050 Perform lamination check/UT test 2 2 0 HT040* 18DEC10 18DEC10 Perform lamination check/UT test
04:00 05:59
HT060 Perform Ovality on hot tap location 8 8 0 HT050* 18DEC10 18DEC10 Perform Ovality on hot tap location
06:00 13:59
HT070 Submit UT Test/MPI result to consultant/client 8 8 0 HT060* 18DEC10 18DEC10 Submit UT Test/MPI result to consultant/client
14:00 21:59
HT080 Approve to weld on hot tap location 65 65 0 HT070* 18DEC10 21DEC10 Approve to weld on hot tap location
22:00 14:59
HT090 Hot work permit received 0 0 0 HT080* 21DEC10 Hot work permit received
14:59

Execution
HT110 Crane and welding machine into position 2 2 0 HT320* 21DEC10 21DEC10 Crane and welding machine into position
01:00 02:59
HT100 Operation line check/gas test 1 1 0 HT090* 21DEC10 21DEC10 Operation line check/gas test
15:00 15:59
HT120 Clamp split tee for 6" hot tap 1 1 0 HT100*, 21DEC10 21DEC10 Clamp split tee for 6" hot tap
HT110 16:00 16:59
HT130 Check with operation on flow parameter 1 1 0 HT120* 21DEC10 21DEC10 Check with operation on flow parameter
17:00 17:59
HT140 Fit-up/tack weld split tee on existing pipe 1 1 0 HT130* 21DEC10 21DEC10 Fit-up/tack weld split tee on existing pipe
18:00 18:59
HT150 Fit-up inspection(contractor/consultant/client) 1 1 0 HT140* 21DEC10 21DEC10 Fit-up inspection(contractor/consultant/client)
19:00 19:59
HT160 Welding(root run on branch section) 1 1 0 HT150* 21DEC10 21DEC10 Welding(root run on branch section)
20:00 20:59
HT170 Welding(root run on longitudinal section) 1 1 0 HT160* 21DEC10 21DEC10 Welding(root run on longitudinal section)
21:00 21:59
HT180 NDT for both roots (MPI) 2 2 0 HT170* 21DEC10 21DEC10 NDT for both roots (MPI)
22:00 23:59
HT190 Full fillet welding on circumstance existing pip 4 4 0 HT180* 22DEC10 22DEC10 Full fillet welding on circumstance existing pip
00:00 03:59
HT200 Cap butt welds 6 6 0 HT190* 22DEC10 22DEC10 Cap butt welds
04:00 09:59
HT210 Pneumatic test on comp pad 1 1 0 HT200* 22DEC10 22DEC10 Pneumatic test on comp pad
10:00 10:59
HT220 Install hot tap valve/blind for hydrotest 1 1 0 HT210* 22DEC10 22DEC10 Install hot tap valve/blind for hydrotest
11:00 11:59
HT230 Hydrotest split tee/valve 2 2 0 HT220* 22DEC10 22DEC10 Hydrotest split tee/valve
12:00 13:59
HT240 Inspect hot tap machine prior to drilling 1 1 0 HT230* 22DEC10 22DEC10 Inspect hot tap machine prior to drilling
14:00 14:59
HT250 Hot tap drilling by tapping contractor 2 2 0 HT240* 22DEC10 22DEC10 Hot tap drilling by tapping contractor
15:00 16:59
HT260 Close HT valve/Depressurise/drain the tapping 1 1 0 HT250* 22DEC10 22DEC10 Close HT valve/Depressurise/drain the tapping
17:00 17:59
HT270 Remove hot tap cutter 1 1 0 HT260* 22DEC10 22DEC10 Remove hot tap cutter
18:00 18:59
HT280 Install vent blind 1 1 0 HT270* 22DEC10 22DEC10 Install vent blind
19:00 19:59

Post Activities
HT290 1st PSSR-Contractor/Consult/Client clear punches 4 4 0 HT280* 22DEC10 22DEC10 1st PSSR-Contractor/Consult/Client clear punches
20:00 23:59
HT300 Touch-up paint on hot tap nozzle 4 4 0 HT290* 23DEC10 23DEC10 Touch-up paint on hot tap nozzle
00:00 03:59
HT310 House keeping 4 4 0 HT300* 23DEC10 23DEC10 House keeping
04:00 07:59

Start Date 17DEC10 00:00 HTAP Sheet 1 of 1


Early Bar
Finish Date 23DEC10 07:59 Date Revision Checked Approved
Float Bar
Data Date 17DEC10 00:00
Run Date 04JAN11 07:28 Progress Bar
Hot Tapping Work
Critical Activity

Classic Schedule Layout