JOB NO : 160028BDA1
P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR
P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR
TABLE OF CONTENTS
1. General
2. Construction Sequence
3. List of Equipment
4. List of Manpower
5. Construction Method
6. HSE Control
7. Quality Assurance
P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR
1. GENERAL
The purpose of construction method for cable work is to describe and explain sequence
of installation cable work. Another purpose is to record which equipment and material is
needed also who complete this work.
2. CONSTRUCTION SEQUENCE
Start
Installed Cable
Testing
Finish
P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR
3. LIST OF EQUIPMENT
Main equipment is in table as below:
No Equipment
1 Hydraulic Crimping Tools
2 Mechanical Crimping Tools
3 Cable Cutter
4 Cable Preparation Tools
5 Insulation Stripper
6 Clamp Meter
7 Pencilling Tools
8 Handy Talky
4. LIST OF MANPOWER
Main Manpower is in table as below:
No Description
1 Foreman
2 Electrician
3 Ass. Electrician
4 Helper
5. CONSTRUCTION METHOD
5.1. Preparation
a. The Material received from Vendor shall be stored in designated area of the
Store/storage facility for prevention from effects of weather and environment.
b. Material inspection will be carried out to ascertain that no damage has occurred
to the Cables.
c. Store material requisition shall be made.
d. The material shall be transported in their original packing to location.
e. The cable drums shall be off-loaded at the site locations as identified by the site
engineer.
P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR
6. HSE CONTROL
a. Personnel who involve in this work must use safety protective equipment such as
safety boots, hard hats, safety glove, etc.
b. Personnel who involve in this work must skilled and experienced.
c. All tools and equipment must be inspected first by Rekadaya
d. For higher place, personnel should use full body harness
7. QUALITY ASSURANCE
Quality of installation and materials will be ensured by Rekadaya team which is
consits of Project Manager, Project Enginner, Site Manager, QA/QC and Foreman.
P.T. R E K A D A Y A E L E K T R I K A