You are on page 1of 6

`

PT. REKADAYA ELEKTRIKA

CONSTRUCTION METHOD FOR


CABLING WORK

PROJECT : PLTU 1 NTB – BIMA (2 X 10 MW)

CLIENT : PT PLN (PERSERO)

LOCATION : BONTO, BIMA, NUSA TENGGARA BARAT

DOCUMENT NO. : 0028BDA1-C0-CP-508-R

JOB NO : 160028BDA1

0 ISSUE FOR PROPOSAL 27-10-2017 ALB RSY MZR

REV DESCRIPTION DATE PREPARED CHECKED APVD

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR

REVISION HISTORICAL SHEET

REV. DATE DESCRIPTION

0 27-10-2017 ISSUE FOR PROPOSAL

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR

TABLE OF CONTENTS

1. General
2. Construction Sequence
3. List of Equipment
4. List of Manpower
5. Construction Method
6. HSE Control
7. Quality Assurance

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR

1. GENERAL
The purpose of construction method for cable work is to describe and explain sequence
of installation cable work. Another purpose is to record which equipment and material is
needed also who complete this work.

2. CONSTRUCTION SEQUENCE

Start

Receive material, inspect, marking, storing

Install Cable Ladder,


Tray & Accessories

Installed Cable

Testing

Finish

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR

3. LIST OF EQUIPMENT
Main equipment is in table as below:
No Equipment
1 Hydraulic Crimping Tools
2 Mechanical Crimping Tools
3 Cable Cutter
4 Cable Preparation Tools
5 Insulation Stripper
6 Clamp Meter
7 Pencilling Tools
8 Handy Talky

4. LIST OF MANPOWER
Main Manpower is in table as below:
No Description
1 Foreman
2 Electrician
3 Ass. Electrician
4 Helper

5. CONSTRUCTION METHOD
5.1. Preparation
a. The Material received from Vendor shall be stored in designated area of the
Store/storage facility for prevention from effects of weather and environment.
b. Material inspection will be carried out to ascertain that no damage has occurred
to the Cables.
c. Store material requisition shall be made.
d. The material shall be transported in their original packing to location.
e. The cable drums shall be off-loaded at the site locations as identified by the site
engineer.

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-508-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
CABLING WORK
27-10-2017 ALB RSY MZR

f. It shall be ensured that there is no obstruction to movement of vehicles or any


hindrance to works of other companies.
5.2. Install Cable ladder, Tray & Accesories
Installation of Cable ladder, Tray & Accesories must be supervised by electrical
supervisor.
5.3. Installation Cable .
a. Cable work has to be supported with cable drawing that needs to faciliate the
installation.
b. Maximum allowable pulling tension shall not be exceeded, minimum bending
radii shall be adhered to as manufacturer recommendations.
c. At each joint or termination, a non-ferrous label shall be fixed to the cable giving
size and identification of the cable
d. All cable support bracket will firmly calmp the incoming cable at a suitable
distance from the termination
5.4. Cable Test
Hi Pot Test is Hipot Test is short name of high potential (high voltage) Test and it is
also known as Dielectric Withstand Test. A hipot test checks for “good isolation.”
Hipot test is connect one side of the supply to safety ground (Earth ground). The
other side of the supply is connected to the conductor being tested. With the supply
connected like this there are two places a given conductor can be connected: high
voltage or ground.

6. HSE CONTROL
a. Personnel who involve in this work must use safety protective equipment such as
safety boots, hard hats, safety glove, etc.
b. Personnel who involve in this work must skilled and experienced.
c. All tools and equipment must be inspected first by Rekadaya
d. For higher place, personnel should use full body harness

7. QUALITY ASSURANCE
Quality of installation and materials will be ensured by Rekadaya team which is
consits of Project Manager, Project Enginner, Site Manager, QA/QC and Foreman.

P.T. R E K A D A Y A E L E K T R I K A

You might also like