DIAPHRAGM WALL
A TECHNICAL REPORT SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS
FOR THE G EOTECHNICAL E NGINEERING GRADUATION PROJECT

Prepared by

Ahmed Saad El-Deen El-Sayed

Mahmoud Atta Ragab

Moustafa Atef Goda

Sabah El-Sayed Ahmed

2012

0
TABLE OF CONTENTS

CHAPTER1 INTRODUCTION .................................................................................................... 1

CHAPTER 2 SOIL RETENTION ................................................................................................. 2

2.1 BATTERED EXCAVATIONS .............................................................................................. 2

2.2 SLOPES IMPROVEMENT................................................................................................... 2

2.3 SOIL REINFORCEMENT .................................................................................................... 2

2.3.1 Types of Reinforcement .................................................................................... 2

2.3.1.1 Metal Strip Reinforcement ........................................................................ 2

2.3.1.2 Polymer Geogrids ...................................................................................... 3

CHAPTER 3 DIAPHRAGM WALL SYSTEMS .............................................................................. 4

3.1 SLURRY DIAPHRAGM WALLS ......................................................................................... 4

3.1.1 Ordinary Construction of Slurry Walls ............................................................. 4

3.1.1.1 Fixing of Alignment For Diaphragm Wall .................................................. 4

3.1.1.2 Construction of Guide Wall ............................................................................. 4

3.1.1.3 Construction of Diaphragm Wall .................................................................... 5

3.1.1.4 Safety Precaution.............................................................................................. 8

3.1.2 Ecofriendly Soil Cement Continuous Diaphragm Wall Method........................ 9

3.2 PRE-CAST DIAPHRAGM WALL ...................................................................................... 10

3.3 POST-TENSION DIAPHRAGM WALL ............................................................................. 13

3.4 SECANTPILES WALL ....................................................................................................... 15

3.4.1 Construction of Secant Piles ........................................................................... 15

3.5 THIN DIAPHRAGM WALLS ............................................................................................ 16

3.5.1 Thin diaphragm wall building materials ........................................................ 16

CHAPTER 4 OBSTACLES OF CONSTRUCTION ....................................................................... 17

4.1 TYPES of OBSTACLES................................................................................................................................17

I
4.1.1 The Guide Wall Construction .......................................................................... 17

4.1.1.1 Guide Wall Deformation ......................................................................... 17

4.1.1.2 Guide And Inner Wall Are Not Parallel To The Axis ............................... 17

4.1.1.3 Guide Wall Backfill. ................................................................................. 18

4.1.2 The Production of Steel Cage .......................................................................... 18

4.1.2.1 The Progress of Issues Affect the speed of the reinforcement cage

4.1.2.2 Welded Steel Cage ................................................................................... 18

4.1.3 Production and Control of Slurry ................................................................... 19

4.1.4 Diaphragm Wall Trench Construction ............................................................ 19

4.1.5 The Delegation of The Reinforcement Cage Lifting ........................................ 20

4.1.6 Pulling Locking Pipe ....................................................................................... 20

4.1.7 Leaks in Construction ..................................................................................... 20

CHAPTER 5 TYPES OF MACHINES ......................................................................................... 22

5.1 SERIES HYDRAULIC DIAPHRAGM WALL GRAB .......................................................... 22

5.1.1 Working Principle of hydraulic diaphragm wall grab ................................... 23

5.1.2 Features of hydraulic diaphragm wall grab ................................................... 23

5.2 SHELL GRAB (MECHANICAL GRAB APPLIED in OVERHEAD CRANE) ....................... 23

5.2.1 Features of Shell Grab ..................................................................................... 24

5.3 Diaphragm Wall Hydromill Grap ................................................................................. 25

CHAPTER 6 COLLAPSE OF SLURRY TRENCH DURING CONSTRUCTIONError! Bookmark not


defined.

6.1 SLURRY TRENCH STABILITY ........................................ Error! Bookmark not defined.

6.2 STABILITY ANALYSIS ..................................................... Error! Bookmark not defined.

6.2.1 Stability of UnsupportedTrenches..................... Error! Bookmark not defined.

6.2.2 Stability of Slurry- Filled Trenches in Clay ........ Error! Bookmark not defined.

6.2.3 Stability of Slurry- Filled Trenches in Dry Sand Error! Bookmark not defined.

6.2.4 Stability of Slurry-Field Trenches in Sand W/WaterError! Bookmark not defined.

II
6.3 MUD CAKE ....................................................................... Error! Bookmark not defined.

6.3.1 Effects of Mud (filter) Cake on Sand................... Error! Bookmark not defined.

6.4 Arching ................................................................................ Error! Bookmark not defined.

6.4.1 Arching Effect on Short Trenches in Sand ......... Error! Bookmark not defined.

CHAPTER 7 DESIGN OF DIAPHRAGM WALL ......................................................................... 32

7.1 EARTH PRESSURE .......................................................................................................... 32

7.1.1 Calculation of shear strength parameters (τ′, c′, φ′)...................................... 32

7.1.1.1 For cohesion soil ...................................................................................... 32

7.1.1.2 For cohesion less soil ..................................................................................... 33

7.1.1.3 For rocks ........................................................................................................... 33

7.1.2 Lateral earth pressure calculation ................................................................. 34

7.1.2.1 Lateral earth pressure based on long-term, drained, effective stress


values. ................................................................................................................................ 34

7.1.2.2 Lateral earth pressure based on short-term undrained stress values. .. 34

7.1.3 Water pressure ............................................................................................... 35

7.2 DESIGN OF DIAPHRAGM WALL.................................................................................... 35

7.2.1 Design of Cantilever Wall (Free Earth Support) ............................................ 36

7.2.2 Design of Hinged Single Anchored System .................................................... 37

7.2.3 Design of Fixed Single Anchored System ........................................................ 37

7.2.4 Design of Multi-prop System ........................................................................... 38

7.3.1 Overall Stability .............................................................................................. 42

7.3.2 Basal Heave Failure......................................................................................... 45

7.3.3 Hydraulic Failure ............................................................................................ 50

7.4.1 Deformation of Wall ........................................................................................ 54

7.4.2 Deformation of Soil Behind the Wall .............................................................. 54

7.5.1 Ground Anchors .............................................................................................. 56

7.5.2 Struts ............................................................................................................... 60

III
7.6.1 Factors Affecting Wall Movements ................................................................. 61

7.6.2 Instrumentation of Deep Excavations ............................................................ 63

7.7 FAILURE SHAPES OF DIAPHRAGM WALLS .................................................................. 64

CHAPTER 8 CASES OF STUDY ............................................................................................... 66

8.1 CASE STUDY 1 (QUAY WALL AT THE PORT OF CALAIS)............................................ 66

8.1.1 Introduction .................................................................................................... 66

8.1.2 Description of The Structure And Site ............................................................ 67

8.1.3 Geotechnical and Hydrological Context.......................................................... 68

8.1.4 Construction Phases........................................................................................ 69

8.1.5 Instrumentation and worksite monitoring .................................................... 70

8.2 CASE SYUDY 2 (MRT CHALOEM RATCHAMONGKHON LINE, BANGKOK) ................ 71

8.2.1 Introduction .................................................................................................... 71

8.2.2 Description of The Structure And Site ............................................................ 72

8.2.3 Construction phases........................................................................................ 73

8.2.3.1 Diaphragm wall construction .................................................................. 73

8.2.3.2 Sequence of construction ........................................................................ 74

8.2.3.3 Supporting fluid ....................................................................................... 74

8.2.3.4 Reinforcement ......................................................................................... 74

8.2.3.5 Concrete casting ...................................................................................... 75

8.2.4 Quality and Safety and Environmental Controls ............................................ 75

8.3 CASE STUDY 3 (El-Azhar Road tunnels project) .............................................................. 77

8.3.1 Introduction .................................................................................................... 77

8.3.2 Geotechnical Properties ................................................................................. 78

8.3.3 Construction Phasing ...................................................................................... 79

Chapter 9 ConclusionS ......................................................................................................... 80

APPENDIX : MULTI_ANCHORED DIAPHRAGM WALL ....................................................... 81

REFERENCES........................................................................................................................ 100
IV
WEB REFERENCES .............................................................................................................. 103

LIST OF FIGURES

Figure 2.1 Soil slope reinforcing .............................................................................................. 3


Figure 3.1 Typical guide wall ................................................................................................... 4
Figure 3.2 trenching ................................................................................................................. 6
Figure 3.3 End stops ................................................................................................................. 6
Figure 3.4 Cage reinforcement ................................................................................................. 7
Figure 3.5 Slurry wall ............................................................................................................... 8
Figure 3.6 construction of Ecofriendly Soil Cement Continuous Diaphragm Wall ............... 9
Figure 3.7 Constructed pre-cast diaphragm wall construction ............................................ 10
Figure 3.8 lifting a precast diaphragm panel ........................................................................ 11
Figure 3.8 horizontal cross section jointing detail ................................................................. 12
Figure3.9 Jointing details for Prefasil diaphragm wall panels ............................................. 12
Figure 3.10 Post-tensioned cantilever and single-propped diaphragm ................................ 13
Figure 3.11 Examples of post-tension .................................................................................... 14
Figure 3.12 secant pile wall .................................................................................................... 15
Figure 3.13 constructed secant pile wall ................................................................................ 15
Figure 3.14 thin diaphragm wall ............................................................................................ 16
Figure 4.1 Leaks in construction ............................................................................................ 21
Figure 5.1 SG series Hydraulic Diaphragm Wall Grab ........................................................ 22
Figure 5.2 shell grab ............................................................................................................... 24
Figure 5.3 Mechanical graps .................................................................................................. 24
Figure 5.4 Hydromill grap ..................................................................................................... 25
Figure 6.1 Stability of unsupported trenches ........................................................................ 28
Figure 6.2 Stability of slurry- filled trenches in clay ............................................................. 28
Figure 6.3 Stability of slurry- filled trenches in dry sand ..................................................... 28
Figure 6.4 Stability of slurry-field trenches in sand W/Water.............................................. 29
Figure 6.5 Effects of mud (filter) cake on sand ..................................................................... 30
Figure 7.1 trixial text .............................................................................................................. 33
Figure 7.2 Relationship between standard penetration resistance and φ′............................ 33
Figure 7.4 stresses affect on cantilevered diaphragm wall .................................................... 36
Figure 7.5 stresses affect on hinged single anchored diaphragm wall .................................. 37

V
Figure 7.6 stresses affect on fixed single anchored diaphragm wall ..................................... 38
Figure 7.7 Empirical method in sand soil .............................................................................. 39
Figure 7.8 Empirical method in soft to medium clays........................................................... 39
Figure 7.9 Empirical method in stiff clay .............................................................................. 40
Figure 7.10 for shallow or wide excavation with (H/B) <1 .................................................... 45
Figure 7.11 for deep excavation with (H/B)> 1 ...................................................................... 46
Figure7.12 Factor of safety against basal heave in cohesion less soils .................................. 47
Figure 7.13 Factor of safety against basal heave in cut in clay ............................................. 47
Figure 7.14 Factor of safety against basal heave in cuts in clay limited by hard stratum ... 48
Figure7.15 Stability of internally braced cut (circular arc method) ..................................... 49
Figure 7.16 Potential failure surfaces .................................................................................... 50
Figure7.17 the design charts for wall penetration ................................................................. 51
Figure 7.18 the design charts for wall penetration ................................................................ 52
Figure 7.19 the summary of the Japanese and Terzaghi methods ........................................ 53
Figure 7.20 the equilibrium between overburden pressure and pore water pressure ......... 54
Figure 7.21 Section of an anchored wall, details of anchors ................................................. 56
Figure 7.22 Anchorage section ............................................................................................... 58
Figure 7.23 Free length section .............................................................................................. 58
Figure 7.24 Tie rod force ........................................................................................................ 60
Figure 7.25 some examples for the geometry of strutted systems ......................................... 61
Figure 7.26 Embedded wall cantilever failure by forward rotation ..................................... 64
Figure 7.27 Bending moment failure of embedded wall ....................................................... 64
Figure 7.28 Failure of embedded wall by rotation about anchor ......................................... 65
Figure 7.29 failure of yield of anchor or tie ........................................................................... 65
Figure 7.30 Failure by rotation of soil mass .......................................................................... 65
Figure 7.31 Overturning of soil mass ..................................................................................... 65
Figure 8.1 the Port of Calais .................................................................................................. 66
Figure 8.2 plan of the Port of Calais ...................................................................................... 67
Figure 8.3 Typical section cut of the completed structure .................................................... 67
Figure 8.4 the Chaloem Ratchamongkhon line ..................................................................... 71
Figure 8.5 subsoil profile ........................................................................................................ 72
Figure 8.6 panel layout ........................................................................................................... 74
Figure 8.7 El-Azhar Road tunnels project ............................................................................. 77
Figure 8.8 Geological profile and longitudinal section .......................................................... 78

VI
Figure 8.9 Diaphragm wall for Attaba TBM arrival shaft being built under ...................... 79

LIST OF TABLES
Table7.1 Approximate values for the effective angle of shearing resistance of soft rocks ... 34
Table 7.2 Factors of safety for methods of analysis embedment (Padfield and Mair) ......... 44
Table7.3 Summary of limiting deformation .......................................................................... 55
Table 7.4 the minimum safety factors for design of individual anchors ............................... 59
Table 7.5 Maximum wall movements and vertical settlements behind walls ....................... 62
Table 7.6 Instrumentation of deep excavations ..................................................................... 63
Table 8.1: Layers and geotechnical parameters .................................................................... 78

VII
CHAPTER1
INTRODUCTION
The purpose of this research is to identify thediaphragm wall systems andits common
applications, construction processand design methods.

Diaphragm wallsare an underground concrete structural element commonly used for retention
systems, permanent foundation walls,permanent basement wall solution,deep groundwater
barriersand and add stability to landslides, highway cuts and deep building excavations.And also
Diaphragm walls were first introduced in the United States in the1960.

The wide use of the diaphragm wall is due to its advantages such as small deformations
with high loading, watertight to a large extent, gentle to the underground, economical,
space saving, little noise during construction, Water bar can be incorporated, Less joints
required than a piled wall, Top-down basement construction gives significant, Box outs
can be incorporated in diaphragm walls to facilitate easy connections for slabs, stairs, etc

But there were limitationsfor using diaphragm wall because of the extensive construction
supplies, separate disposal of admixed soil excavations, block-outs for crossing pipes, tubes are
often problematic to build.

1
CHAPTER 2

SOIL RETENTION
2.1 BATTERED EXCAVATIONS
The stability of a cut slope in granular soils can be determined simply from knowledge
of the angle of shearing resistance for the soil or the soil layers. In normally
consolidated cohesive soils, the stability can be assessed by a repetitive calculation of
disturbing and restoring moments for trial potential failure surfaces, the restoring force
being based on quick undrained shear strengths of the soil on the failure surface. Where
possible, it is usual to avoid the effects of disturbance on the measurement of clay
strengths by measuring in situ shear strengths with a vane apparatus rather than relying
on laboratory test values.

2.2 SLOPES IMPROVEMENT


There are six methods for improving the stability of a cut slope:

 Regarding the profile of the slope and, for example, weighting the toe of the
slope locally with a soil berm to reduce the disturbing movement.
 Using tensioned ground or rock anchors to increase the effective stress on the
potential failure surface, thereby improving soil strength.
 Intercepting potential failure surfaces with sheet piles or jet grouted columns
installed from the face or the top of the slope.
 Increasing the effective vertical stress on the potential failure surfaces by
reduction of pore-water pressure by drainage.
 Improving composite soil strength by regarding the slope and the inclusion of
reinforcement to intercept the potential failure surface, using reinforced soil.
 Driving soil nails through potential failure surfaces.

2.3 SOIL REINFORCEMENT

2.3.1 Types of Reinforcement

2.3.1.1 Metal Strip Reinforcement


The metallic reinforcing strip currently recommended is galvanized milled steel,
generally 5 mm thick and in standard widths of 40 or 60 mm. The surface of the strip
is ribbed to improve soil-reinforcement friction as shown in figure 2.1. The strip is

2
called high adherence strips. In permanent walls it is usual to allow a sacrificial
thickness of the metal to be lost due to corrosion (from 0.5 to 2 mm depending on
design life and exposure). It is also usual to place dummy strips through the wall face
on aggressive sites in order that strips can be jacked out occasionally to monitor the
rate of corrosion. The galvanized steel strip and precast concrete facing panel are
competitive for vertically-faced walls of medium to large height, due to the high
elastic modulus of mild steel and the low creep properties.

2.3.1.2 Polymer Geogrids


Tensergeogrids are high-strength polymer grids specifically made as tension-resistant
inclusions in soils. The manufacturing process begins with an extended sheet of
polyethylene or polypropylene which is punched with a regular pattern of circular
holes. This sheet is then stretched under controlled heat conditions so that randomly
long chain molecules are drawn into an aligned state. This process of stretching
increases the tensile strength and stiffness of the polymer. The resulting geogrid
structure of ribs and bars produces an effective means of transferring friction from
soil to geogrid. The prime disadvantages of using a polymer grid is the low elastic
modulus and high creep value compared with steel strip. The influence of long-term
strength has been the subject of vigorous research, and the influence of load capacity
on the design life of the geogrid can be predicted by extrapolation from laboratory
curves of strain against load with increasing time at various temperatures.

Figure 2.1 Soil slope reinforcing

3
CHAPTER 3

DIAPHRAGM WALL SYSTEMS


3.1 SLURRY DIAPHRAGM WALLS
A slurry wall is technique used to build reinforced-concrete walls in areas of soft earth close to open
water or with a high ground water table.

This technique is typically used to build diaphragm (cut-off) walls surrounding tunnels and open cuts,
and to lay foundations. A trench is excavated to create a form for each wall. The trench is kept with full
of slurry at all times.
The slurry prevents the trench from collapsing by providing outward pressure whichbalancesthe

inward hydraulic forces and prevents water flow into the trench. Then, rebar cage is lowered in and the
trench is filled with concrete, which displaces the slurry.

3.1.1 Ordinary Construction of Slurry Walls

3.1.1.1 Fixing of Alignment For Diaphragm Wall

Alignment of Diaphragm Wall shall be fixed on the ground with the help of total station as
per the relevant drawing. Proper alignment of Diaphragm Wall shall be maintained by
means of guide wall.

3.1.1.2 Construction of Guide Wall


Guide wall of 1.20 m depth shall be made of reinforced cement concrete As shown in
figure3.1. Distance between internal faces of guide wall shall be maintained 630mm.
Dimensions of guide wall, whether in filled area or in excavation shall be same as specified in
the above-referred drawing. Filled portion shall be compacted properly and then only
excavation activity for guide wall shall be started.

Figure 3.1 Typical guide wall

4
3.1.1.3 Construction of Diaphragm Wall
Construction of Diaphragm Wall shall be done by alternate panel method. In this method
primary panels shall be cast first leaving suitable gaps in between. Secondary panels &
closing panel shall then be cast in this gap. The length of panel may vary from one location
to another location depending upon the cut-off level and the termination depth. The changes
shall be intimated in advance. Two stop end tubes shall be used at the ends of
primary/secondary panels to support Cement Bentonite Slurry and to form suitable joints
with the adjacent panel. The shape of the secondary panel end shall be such as to form
proper joint with primary panel. 580 mm dia. MS hollow pipes shall be used as stop end
tube. The semicircular shape shall provide the proper joint between adjacent panels. Length
of panels shall be marked on the guide wall prior to start of trenching work.
a) Boring (Trenching)

Boring shall be carried out by wire rope grab As shown in Figure 3.2 operated by means of
suitable crane. The crane shall control the vertical motion of grab. Initially grabbing/ boring
shall be done from guide wall top up to water table level in dry conditions. After
completing the dry boring, the bentonite slurry of minimum density 1.04 gm/cc shall be
pumped to the partly excavated trench and bore shall be filled with bentonite slurry, and
further grabbing shall be continued up to specified depth as mentioned in the relevant
drawing. Continuous supply of bentonite slurry shall be maintained in bore during entire
trenching process to have a constant head above the ground water level. Sodium based
bentonite available at Bhuj/Bhavnagar shall be used for bentonite slurry. Necessary testing
like density, PH value, viscosity shall be carried out at site until a consistent working
pattern is established, taking into account the mixing process, blending of freshly mixed
bentonite with previously used slurry etc. Contaminated bentonite shall be removed from
site / bentonite tank by means of tankers / tractors and shall be disposed off at suitable
location shown by client / consultant. Usually panel width shall vary from 4.0 m to 6.0 m,
so that the entire trenching shall be completed in three cuts as per grab size. Panel width
may vary as per site conditions. During trenching operation adequate care shall be taken to
keep the bore vertical to such an extent so that it meets the permissible limits specified in
the technical specification. To maintain verticality of trench following measures shall be
adopted: Crane shall be placed on relatively firm and leveled ground and level of track
chain of crane shall be checked by means of sprit level. During trenching grab shall be
rotated by 180 degree after every three to four grabbing operation. To check the verticality

5
distance between grab rope and guide wall face shall be monitored. After completion of
boring up to specified depth, the boring equipment shall be shifted to another location.

Figure 3.2 trenching

b) Fixing of stop end tubes

Stop end pipes shall be lowered up to the bottom of trench maintaining pre specified distance
marked on the guide wall. The center of stop end tubes shall match with the panel markings on
Guide wall As shown in Figure 3.3Shutter release oil shall be applied on stop end tubes. During
placing of stop end pipes, verticality shall be monitored by means of plumb bob to make the same
vertical enough to meet the requirements specified in the technical specification.

Figure 3.3 End stops

6
c) Cleaning of excavated trench

After trenching is completed, for flushing tremmie pipe of 200 mm dia shall be lowered in
the trench keeping a gap of 300 mm to 500 mm from bottom of trench. Bentonite shall be
pumped through the tremmie pipe so as to clean the bottom of trench. Bentonite level shall
be maintained in trench by continuously pouring Bentonite from the Bentonite tank. Care
shall be taken to avoid Bentonite level from going below bottom of Guide wall. Flushing
shall be continued unless Bentonite density comes 1.15 gm/cc or below 1.15 gm/cc. For
checking purpose the suitable bentonite sampler shall be used for collecting sample from the
bottom of trench.

d) Trench Reinforcement

We put steel cage in side it, cage is fabricated on site as shown in Figure 3.4

Figure3.4 Cage reinforcement

e) Forming of cement-bentonite slurry diaphragm wall

After Flushing of Excavated trench re-circulation to be started for replacement by the


Cement bentonite slurry as shown in Figure 3.5 with the help of suitable capacity of
Vacseal/Electric Operated Pump s and Venture Mixer using high speed agitators. The
Pumping out of Bentonite Slurry is to be done from the bottom of the trench and the
Cement –Bentonite Slurry is to flow into trench by Gravity. Pumping out of the Slurry from

7
the excavated Trench to Mixing tank and flow back to Trench till continue and cement to be
added as per specifications. The Circulation of Cement Bentonite Slurry shall be continued
for homogeneous mixing but mixing to be finished before initial setting time of Cement
used and bulking time of Cement Bentonite Slurry.

Figure 3.5 Slurry wall

f) Bleeding of cement-bentonite slurry & top of trench

After one day Cement –Bentonite Slurry bleeding occurs which shall cause the top of the
slurry to settle down to be top up by additional Cement Bentonite Slurry with required
density to be pour to raised up to Cut-Off level.

g) Removal of stop end pipe

The end tubes shall be taken out gradually with the help of a Crane / Hydraulic Jacks.
Adequate care shall be taken during removal of stop end pipe so that no damage is caused to
the Slurry placed against them

3.1.1.4 Safety Precaution


Necessary safety precaution is the part of the job. All workers related with the construction
shall be provided with PPE. Periodical checking of cranes, wire shall be done. After boring,
the trench shall be covered with iron mesh till other activity starts. In the case of collapse of
excavated trench, the same shall be back filled immediately with lean concrete.

8
3.1.2 Ecofriendly Soil Cement Continuous Diaphragm Wall Method
Deep soil cement wall that can be excavated is built and up to 70 percent of the surplus soil
reused in order to standardize the technology, quality control and construction method of
continuous diaphragm wall methods, which recycle the surplus soil generated, as well as
aiming to increase use of the method as shown in Figure 3.6

Takenaka Corporation (Head Office: Osaka; President: Toichi: Takenaka), jointly with
Kajima Corporation and 11 other companies, has developed the "Continuous Diaphragm
Wall Method Using Excavated Soil (Reducing the Amount of Construction Surplus Soil by
Recycling the Excavated Soil)," and has received a Technical Inspection Certificate
recognized by the Minister for Construction.

Figure 3.6 construction of Ecofriendly Soil Cement Continuous Diaphragm Wall


.

9
This is an earth retaining method able to be used deep underground to build a continuous
diaphragm wall by reburying soil cement produced mainly with excavated soil (up to 70
percent recycling) into the groove excavated using stabilizing liquid by an excavator used in
RC continuous diaphragm wall methods . This method takes strong consideration of the
environment, and has superb quality, construction workability, safety and economic qualities
required in this day and age.

3.2 PRE-CAST DIAPHRAGM WALL


There are some advantages for this type such as:

 General appearance: no cutting back is required and the finished surface is agreeably clean.
 The shape of the diaphragm can be tailored to form an integral part of the final structure,
satisfying technical and economic consideration.
 Improved concrete quality and accuracy in placing reinforcement gives considerable
savings on materials; prefabricated diaphragms are generally 30 % thinner than
conventional diaphragm walls.
 The prefabricated diaphragm can be built and installed in the ground to finer tolerances,
and openings can be positioned more accurately.
 Watertightnees at the joints and in the wall itself is better than with conventional
diaphragms.
 The improved finished surface can be obtained as shown inFigure 3.7.

Figure 3.7 Constructed pre-cast diaphragm wall construction

10
Panel widths and lengths are limited to the capacity of mobile lifting equipment suitable for
operation on construction sites, and in practical terms this is of the order of 30 ton. The panels
are usually cast on site; some additional site area may be needed to do this although less space is
needed to store reinforcement since prefabrication of reinforcement cages is not necessary with
pre-casting. Panel being lifted as shown in Figure 3.8

Figure 3.8 lifting a precast diaphragm panel

There are two mechanical connections between panels and the timing of the use of
cementation slurry to surround the precast unit and support the subsoil:

 Soletanche's Pansol method:


The panel is dug under cementations slurry containing retarding and regulating additives, the
slurry being removed without difficulty from the smooth face of the wall during bulk
excavation of the site. Slurry between the rear face of the precast panel and the subsoil
remains permanently as an inert filler material between wall unit and subsoil, the final
strength of the set slurry being designed to exceed neighboring soil strength.
 Bachy's Prefasil method:
The panel is dug under a conventionalbentonite mud which is later displaced by the
introduction of a cementations grout just before the precast unit is positioned in the panel
excavation. It gives

11
flexibility in site operations, allows a wide range of grout strengths to be used, is particularly
convenient when large vertical loadsare being carried by the panels, and the process also avoid
risk of contamination of the grout bysoil during the excavation process.
The methods of panel connection for the Soletanche system are shown in Figure 3.8 where
types (a) and (b) are standard joints ; types (c) –(e) use temporary metal guides; types (f) and
(g) use preformed water bars (courtesy of Soletanche).

Figure 3.8 horizontal cross section jointing detail

The technique used by Bachy.Shown in Figure 3.9 where

Joint type (a) uses a preformed water bar, type (b) uses a reinforcing key, and type (c) uses
grout only (courtesy of Bachy)

Figure 3.9 Jointing details for Prefasildiaphragm wall panels

12
3.3 POST-TENSION DIAPHRAGM WALL
The feature of post-tension is that stressing of the panel is undertaken before bulk excavation
is carried out. Figure 3.11 shows examples of post-tensioned diaphragm wall
and while the wall panel is fully embedded. Tendon forces and eccentricities are calculated on
loading on the final structure with no tension across the concrete section, the panel movement
during stressing being minimized by the surrounding soil, the soil restrain varying between
full passive pressure and earth pressure at rest. The cable profiles for a cantilever wall and a
propped diaphragm wall are shown in Figure 3.10, shows earth pressure, bending moments
and stresses in a typical wall unit before removal of the surrounding soil, the applied to the
wall section by the prestressing force being effectively reduced by the soil stiffeners
preventing tension developing a cross the section due to pre-stress.

Figure 3.10 Post-tensioned cantilever and single-propped diaphragm

13
Site Type H (m) h (m) b (m) Max
prestress
(N/mm2)
Centrale PTT
Bellinzona A 7.0 2.7 60 3.6

Admiral
SA,Paradiso A 7.6 5.10 80 3.5
German
Embassy, London A 9.6 5.70 90 3.1

ETA-
WerkeGrenhen B 13.2 6.20 80 3.7
Propr.Fabriane,
Lugano C 11.6 4.60 60 3.6
Centrale TT ,
Moralto C 15.0 - 80 2.1

Figure 3.11 Examples of post-tension

14
3.4 SECANT PILES WALL
Secant piles wall can be both temporary and permanent wall for excavation. Usually secant piles
wall is used in stiff soil and lower water table. The advantages of secant piles wall are lower cost
and speed in construction for temporary or permanent wall where drilling conditions are
conducive as shown in figure3.12. The system has higher capacity to overcome obstructions like
rock compared to other system. However additional works are needed to form an acceptable
surface to the wall.

Figure 3.12 secant pile wall

3.4.1 Construction of Secant Piles


Secant pile walls are formed by constructing intersecting reinforced concrete piles as shown in
Figure 3.13.The piles are reinforced with either steel rebar or with steel beams and are
constructed by either drilling under mud or angering. Primary piles are installed first with
secondary piles constructed in between primary piles once the latter gain sufficient strength.
Pile overlap is typically in the order of 3 inches (8 cm). In a tangent pile wall, there is no pile
overlap as the piles are constructed flush to each other.

Figure 3.13 constructed secant pile wall

15
3.5 THIN DIAPHRAGM WALLS
This kind of diaphragm wall has been formed by ramming steel sheet panels into the soil as
shown in Figure 3.14.. The hollow cavity created when extracting the profiles is filled under
pressure with a special building material. The overlapping sequencing of these elements
creates a sealing barrier in the subsoil, as is often used in damming for flood protection.

Figure 3.14 thin diaphragm wall

3.5.1 Thin diaphragm wall building materials


Thin diaphragm wall building materials are mixes comprising cement, limestone filler
and bentonite. Due to the procedure, these materials are required to exhibit a very much
higher density (high specific gravity) by comparison with diaphragm wall building
materials. Thin diaphragm wall building materials are also available as ready-to-use dry
mixes.

16
CHAPTER 4
OBSTACLES OF CONSTRUCTION

Diaphragm wall construction is to use the Trench equipment on the ground, under the action
of the Slurry Wall, along the perimeter of deep excavation, excavation of a narrow groove,
placing the reinforcement cage in the tank and pouring concrete, building into a reinforced
concrete wall construction process.
Diaphragm Wall technology, complex, into the wall can be divided into by: pile row type,
tank plate, combined, according to excavation: The underground continuous wall,
underground cutoff wall. Underground continuous wall has many advantages, such as
stiffness, both retaining and retaining, the construction of no vibration, low noise, can be used
for the construction of any soil, but the construction of high cost and technical complexity.

4.1 TYPES of OBSTACLES


Diaphragm wall construction including: guide wall construction, steel cage production,
production and control of the mud, into the slot, the next locking pipes, reinforced steel
cage and lower cage dipping, pulling locking pipe and other PROCESSES.

4.1.1 The Guide Wall Construction

Guide wall construction of diaphragm wall construction is the first step, it is the role of
retaining walls, storage, mud, play a significant role on the chamfer. Guide wall
construction generally the following problems.
4.1.1.1 Guide Wall Deformation
The main reason this occurs is the guide wall did not increase after construction of the
vertical support; lateral stability deficiencies occurred guide wall guide wall deformation.
Solution

After form removal guide wall, 1m intervals along the vertical guide wall located two
Cricket support, will be supported by two guide wall up in the guide wall did not meet
the design strength of concrete before the heavy machinery in the guide wall against the
side of road, to prevent guide wall deformation.
4.1.1.2 Guide And Inner Wall Are Not Parallel To The Axis
Conduction within the wall of the diaphragm wall and not parallel to the axis of the wall
will cause the diaphragm wall does not meet the design requirements.

17
Solution

Be sure to ensure the guide wall centerline axis coincides with the underground
continuous wall, inside and outside the guide wall clearance should be equal to the design
of diaphragm wall plus the width of 50mm, spacing error is less than 5mm. Guide wall
and outside wall vertical.
4.1.1.3 Guide Wall Backfill.
Backfill easy to collapse, resulting in dorsal hollow guide wall, increasing the amount of
concrete square.
Solution
Use a small dug-based guide wall excavation, backfilling earthwork to reduce, and then
instead of using plain miscellaneous fill backfill soil.

4.1.2 The Production of Steel Cage

The production of steel cage construction of diaphragm wall is an important part of the
reinforcement cage making a direct impact on the speed of construction progress.
Reinforcement cage made of the following general problem.
4.1.2.1 The Progress of Issues
Affect the speed of the reinforcement cage made many factors, such as by site conditions,
construction site does not allow setting the two steel production platforms, and when
entering the rainy weather, the welding class can only stop the construction.

Solution
the construction site conditions can be set to alternate operation of two construction
platform. To ensure that one day one of the construction progress. When entering the
rainy days, you can use sub-erection of scaffolding and color steel shed, the welding in
the shed construction, to be reinforcement cage can be directly used to use when hanging
from the crane shed
4.1.2.2 Welded Steel Cage
As the heavy workload and lack of concentration and other workers, will cause steel joint
dislocation, and many joints after welding is still in the high-temperature weak state, in the
handling or stacking will not pay attention to, it will reinforced joints caused by stress and
deformation.
Solution

18
this problem is mainly caused by man-made, thus enhancing the technical management and
improve the quality of construction workers, the problem can be completely resolved.

4.1.3 Production and Control of Slurry


Mud production is the key to underground continuous wall if making bad mud, the surface of
the tank wall cannot form a layer of solid granular cements Ying (slurry) and loss of
adhesion. Slurry liquid column pressure will result in the same time, cannot Soil excavation
SLOT balance inside and outside wall of earth pressure and water pressure, leading to
instability in maintaining vessel wall, causing landslides.
Solution
According to hydro geological data, the use of bentonite, soda ash and other raw materials,
prepared by a certain percentage as mud. Slurry production process should also note the
following issues

 the use of mud slurry timely indicators of the state inspection. Slurry of recycled tests for
determining if time will cause deterioration in the quality mud
 Mud convergence of production and project as a whole. The new preparation of the
slurry should be placed in the pool fully fermented be put into use.
 The amount of slurry produced by the general to the specific side mixing amount of 1,5
times the theoretical side more appropriate

4.1.4 Diaphragm Wall Trench Construction


Diaphragm wall trench construction is an important part. Mainly into the slot machine
construction, slurry liquid level control, low clearance, brushes the wall and so on.

 Into a slot machine construction. Into a slot machine is the most important issue in the
construction bias problem.
 Liquid level control and ground lift mud. In the process into the slot and should be
carried out after the slurry liquid level control, when faced with rain and so the rapid
rise in the groundwater, the need to control the movements of underground water, if not
handled the wall will affect the quality of a good groove. or even collapse.
 The work of clearing at the end. Ching result of low sediment is not too much
time, will cause the concrete diaphragm wall reduces the strength, steel cage floating,
affecting its capacity as water seepage, it can lead piping. At the same time too much
sediment will affect the steel cage the sinking.

19
 Brush the wall. If the brush is not timely may result in the wall between the two walls
there are the earth, will have serious leakage, the integrity of underground continuous
wall.

Solution

The rapid rise in groundwater level, it can reduce some or all of the groundwater. Or raise
the mud surface, to at least 0.5-1.0 meters above the water table to ensure the vessel wall
stability. Moreover, you should do the work of technical tests , correct attitude towards the
construction workers, in a timely manner and brush the wall with low clearance work

4.1.5 The Delegation of The Reinforcement Cage Lifting


 Steel cage lifting. Steel cage in the dipping process, because the central lifting point
does not coincide with the trough section of center steel cage will deform.
 Decentralization of reinforcement cage. Tank requirements or substandard vertical
slurry leakage and other reasons, the reinforcement cage of concrete blocks in the lower
levels encountered, resulting in elevation of the reinforcement cage around
inconsistency or lateral

Solution

technical personnel to operate carefully, to ensure the absolute safety of lifting steel cage,
steel cage to the lower levels, to make the center line of the reinforcement cage and the
slot segment overlap as much as possible the vertical axis. In addition, make sure to
compact the backfill slurry leakage prevention.
4.1.6 Pulling Locking Pipe
Pulling locking pipe must to time, when the concrete did not freeze when operating, will
cause plasma leakage at the bottom of the wall, this time locking tube if not dense backfill,
concrete pipe will bypass the locking, the next one the construction of diaphragm wall caused
great obstacles.
Solution
Mastering the initial setting time of concrete, concrete at the conclusion of the use of
hydraulic jacking frame pulling locking pipe.

4.1.7 Leaks in Construction


When making underground structures using diaphragm walls, leaks can arise at the joints
between the diaphragm wall panels as shown in figure 4.1. Also in the diaphragm or wall

20
panels themselves, as a result of problems when casting the concrete there may be pockets of
gravel that can cause leaks in a construction pit. And after the diaphragm wall is completely
excavated and a floor has been cast then there may be leaks at the connection of the floor to
the wall as a result of the high water pressure.
B&W Grondinjectie has extensive experience in solving these problems using injection and
therefore also guarantees the solution to every type of leak in diaphragm walls.

Figure 4.1 Leaks in construction

21
CHAPTER 5
TYPES OF MACHINES

There are different types of machines will mention as follow:

5.1 SERIES HYDRAULIC DIAPHRAGM WALL GRAB


The Hydraulic Diaphragm Wall Grab which shown in figure 5.1 can be used in the deep pit
wall of subway, underground works, garage and street, as well as in underground
transformer substation and high building's basement.It especially can be used in deep pit
wall in dense buildings of cities.

Figure 5.1 SG series Hydraulic Diaphragm Wall Grab

22
5.1.1 Working Principle of hydraulic diaphragm wall grab
 Making guide wall.
 The machine digs along the guide wall; and at the same time, using inclinator to
measure the verticality.
 Adjust the grab verticality to keep the wall precision
 Slurry should be used to prevent wall collapse
 And finally clean the wall bottom, place the cage and then concrete the cement

5.1.2 Features of hydraulic diaphragm wall grab


 Low vibration and noise, so it can also work during night
 Electron detector, inclinometer and hydraulic push-plate are equipped to control the
depth and verticality.
 High wall strength: thus the walls can bear huge side pressure and avoid groundsill
sinking and landslip.
 Good penetration resistance.
 Cost Saving: functions like soil retaining, water stealing and weight bearing, etc are
all integrated.
 Can be used as the rigid foundation to replace shafts, and other foundation.

5.2 SHELL GRAB (MECHANICAL GRAB APPLIED in OVERHEAD CRANE)


Mechanical grabs are the best solution to excavate diaphragm walls in all soil conditions up
to soil hardness of 70 mPA as light chiseling work is possible. The SWG series of
diaphragm wall grabs is available with grab extensions for a total length of 10 or 12 m and
also with extra ballast to reach a total weight of up to 22550 kg for even the most demanding
projects.

Jaws may be rectangular or round shape. Jaws, ropes, pulleys and different teeth can be
quickly replaced on site without any problems As shown Figure 5.2. All rope and guide
pulleys have adequately dimensioned, maintenance-free bearings filled with grease.
We also supply hydraulic diaphragm wall grabs with inclination measuring and monitoring
systems to guarantee a verticality of the diaphragm wall of 1: 800. The recorded data of the
complete excavation procedure can be stored and printed out for further use.

23
The grab is widely used in ship, port, railway station, factory, mine and other transport
departments. It is an ideal tool in handling bulk cargo such as coal, ore powder, fertilizer
and sand.

Figure 5.2 shell grab

5.2.1 Features of Shell Grab


 Grab Advantages: Simple structure, good performance, high productivity.
 Grab's capacity 3 cbm to 30 cbmwith reducing capacity system.
 Supplied with removable spill plates, giving the capability to work light and
heavy cargos with the one grab.
For quotation of grab, there are detailed informations as following:

 Capacity and volume.


 Application.
 Handling Material
 Working Temperature..

Double Rope Clamshell Grab Single Rope Bulk Grab

Figure 5.3 Mechanical graps

24
5.3 Diaphragm Wall Hydromill Grap

The hydromill which shown in figure 5.4 is a hydraulically operated excavating machine
which operates on the principle of reverse circulation. The cutting chains are used to transfer
the power of the motors (positioned in the upper section of the Hydromill body) to the
cutting wheels.This system utilized exclusively by the CasagrandeHydromill, insures a
continuous cutting impact along the entire width of the excavation, increasing productivity,
especially, when excavating hard/very hard and difficult geological formations.
The Hydromill chain cutting system modified to form a key joint into the concrete (removed
from the primary panels), greatly improves the verticality control while insuring a more
efficient overlapping between panels.The “key joint” system may be used, if specified by
engineers and owner, as an extra requirement to insure a superior (structural and waterproof)
final wall result.

Figure 5.4 Hydromill grap

25
The submersible pump
A powerful submersible pump mounted above the mill wheels conveys the soil/rock cuttings
together with the trench support fluid to the surface and then to the desanding plant.

The long guide


A long guide frame is fitted on top of the cutting wheel assembly to steer the machine down
the diaphragm wall trench. The guide frame incorporates a series of trim plates (optional)
with which adjustments can be made to the machines inclination in order to maintain the
desired verticality. The guide frame also incorporates the electronic control instrumentation
and the descent control cylinder (optional) which enables the operator to vary the pressure
on the cutting teeth so as to optimize their efficiency in the different soils which are
encountered along the excavation.

The power pack


The hydro mill may be powered directly off the support crane’s hydraulic system if this has
sufficient capacity; alternatively it may be driven by an independent power pack, mounted to
the base carrier.

The instrumentation
Excavation with the hydromill is a continuous operation which is free of vibration; this
characteristic makes the machine ideal for instrumentation. The Casagrandehydro mills are
therefore fitted with a full set of instruments which measure and transmit to the operator or to
a remote station, parameters such as: the cutting wheel torques and speeds; the weight acting
on the cutting wheels, the performance of the fl using pump; the depth of the machine and its
inclination on two axes.

26
CHAPTER 6

COLLAPSE OF SLURRY TRENCH DURING CONSTRUCTION

Primarily, it is the fluid pressure of the slurry in combination with arching in the ground that
maintains trench stability in cohesion less soil. In addition, some local penetration into the
pervious, soil will impart cohesion to the soil and will prevent spalling. The bentonite slurry
in the trench is maintained at a higher elevation than the surrounding ground water table. By
a combination of hydrostatic pressure, osmotic pressure, and electrolytic properties of the
colloid, a membrane or “mud cake” forms against the walls of the trench. The effect of this
“mud cake” is to prevent fluid loss and to maintain the fluid pressure against the trench wall

6.1 SLURRY TRENCH STABILITY


 Fluid pressure + arching in the ground.
 Local penetration of the slurry into pervious soil imparts. Cohesion to the soil and
prevents spalling.
 Bentonite slurry is kept higher than the ground water table.
 Hydrostatic pressure, osmotic pressure, electrolytic properties of the colloid, membrane
or (mud cake) forms against the walls of the trench.
 Electro – osmotic phenomena, migration of colloidal particles to the trench wall by
electrical potential at the slurry, soil interface.
 Penetration of slurry into cohesion less soil, forming of the mud cake by seepage force
affected by the depth and permeability of the soil.

6.2 STABILITY ANALYSIS

 Fluid pressure + arching.


 Analysis mostly based on experience.

6.2.1 Stability of Unsupported Trenches


There are stability takes place in case of cut in clay soil due to cohesion properties
which it has by resisting earth pressure. Figure 6.1 shows (a) section through cut

(b) Horizontal earth-pressure diagram

27
Figure 6.1 Stability of unsupported trenches

6.2.2 Stability of Slurry- Filled Trenches in Clay


As shown in figure 6.2 Stability takes place between slurry pressure, earth-pressure
and soil cohesion in clay soil.

Figure 6.2 Stability of slurry- filled trenches in clay

6.2.3 Stability of Slurry- Filled Trenches in Dry Sand


As shown in figure 6.3 Stability takes place between slurry pressure and earth-
pressure in sand soil.

Figure 6.3 Stability of slurry- filled trenches in dry sand

28
6.2.4 Stability of Slurry-Field Trenches in Sand W/Water
As shown in figure 6.4 Stability takes place between slurry and earth-pressure in sand
W/water

Figure 6.4 Stability of slurry-field trenches in sand W/Water

6.3 MUD CAKE


The extent of fluid penetration into the soil voids depends upon the permeability of the soil
and the properties of the colloid. 'With very pervious soils such as sands and gravels, having
permeability greater than 10 Am/set, there could be free penetration of the slurry into the
soil without the formation of a “mud cake”. With soil shaving permeability between low2
and lb -1 cm/set, there may be some time lag associated with the development of an
impervious “mudcake”.With soils having permeability less than 1V2cm/sec, the depth of
penetration for formation of an impervious “mud cake” is minimal and there is essentially
no time lag (Hutchinson, 1974).
With impervious soils, such as clay, the bentonite need not form a “mud cake” because the
clay itself is essentially impermeable. In these cases the bentonite protects against fluid loss
through pervious seams that may be interbedded within the parent clay formation.

29
6.3.1 Effects of Mud (filter) Cake on Sand

Figure 6.5 Effects of mud (filter) cake on sand

6.4 Arching
In order to understand arching, the redistribution of stresses away from plane strain
conditions, two conditions must be examined:
 The strain conditions at great depth below the surface.
 The strain conditions near the surface.
At great depth, strain is essentially two-dimensional condition acting in the horizontal
plane outside the influence of Local conditions. Horizontal strain is less near the ends of
the panel thinner the center of the panel. As a result, load concentrates at tends of the
excavated panel, thus relieving the stress condition near the center and improving stability.
The very top of the trench is restrained by a guide wall which is used to align the
excavation and to introduce circulated slurry.
The guide wall is essentially rigid and therefore restrains lateral .movement

30
So that arching develops in the vertical plane. Arching also occurs in -the horizontal plane.
Experience has shown that a rigidly placed guide wall is an extremely important element in
maintaining the stability of the top part of the trench.

6.4.1 Arching Effect on Short Trenches in Sand

31
CHAPTER 7
DESIGN OF DIAPHRAGM WALL
This chapter addresses the key design items of earth and water pressure on a vertical wall
and the analysis of the wall to resist these pressures. Cantilevered, single anchored and
multi-anchored walls represent the different systems of diaphragm walls.

7.1 EARTH PRESSURE


Mohr's circle of stress can be used to illustrate graphically the horizontal soil pressures
which can be generated in active or passive states at either side of retaining wall.The
problem of assessing earth pressures can be solved using the coulomb equation for shear
strength

(τ′ = C′+ϭ′ tanφ′)

Where:
C′ represents effective soil cohesion.
ϭ′ represents effective vertical stress.
φ′ represents the angle of shearing resistance in terms of effective stress.
Mohr's circle is seen to touch the failure envelope to give values in the extremes of
minimum and maximum horizontal stresses. The active and passive earth pressure
according to horizontal stress is less than or greater than vertical stress.
Where:
Ϭ′ҥ=Ҡa* Ϭ′ѵ&Ϭ′ҥ=Ҡp* Ϭ′v

Ҡa =(1-sin φ′)/(1+sin φ′) &Ҡp =(1+sin φ′)/(1-sin φ′)

7.1.1 Calculation of shear strength parameters (τ′, c′, φ′)

7.1.1.1 For cohesion soil


The values of C′ and φ′ from drained triaxial tests or undrained tests with pore-water pressure
measurement as shown in fig 7.1.The effects of stress level, rate of strain for testing, the
degree of weathering and of sample swelling before the test, will all influence the test result.

32
Figure 7.1 trixial text

7.1.1.2 For cohesion less soil


The values of (φ′) based on in situ tests where possible. The relationship between standard
penetration resistance and (φ′) in shown in Fig7.2.

Figure7.2 Relationship between standard penetration resistance and φ′

7.1.1.3 for rocks


Table7.1 gives approximate values for the effective angle of shearing resistance of soft
rocks considered.

33
Table7.1 Approximate values for the effective angle of shearing resistance of soft
rocks

Stratum φ′

Chalk 35

Clayey marl 2

Sandy marl 33

Weak sandstone 42

Weak siltstone 35

Weak mudstone 2

7.1.2 Lateral earth pressure calculation

7.1.2.1 Lateral earth pressure based on long-term, drained, effective stress values.
Active and passive earth pressures acting on the wall at depth (Z) given by:

P'a=Ҡa* Ϭ′ѵ= Ҡa(γz+q-u)&P' p=Ҡ p * Ϭ′ѵ= Ҡ p (γz+q-u)

And for a soil with cohesion intercept

P'a=Ҡa*Ϭ′ѵ=Ҡa(γz+q-u) - 2 C′(Ҡa)0.5&P' p =Ҡ p*Ϭ′ѵ=Ҡ p (γz+q-u) +2 C′(Ҡp)0.5

Where:

γ is the bulk soil density.


q is the surcharge on ground surface.
U is pore-water pressure.
These values known as Rankin values.

The pore-water pressure is added to the effective lateral earth pressure to give the sum of
earth and water pressure

Pa = P'a+U&Pp = P' p + U

7.1.2.2 Lateral earth pressure based on short-term undrained stress values.


In terms of undrained conditions Active and passive earth pressures acting on the wall at
depth (Z) given by:

34
Pa=Ҡa* Ϭѵ = Ҡa(γz+q) &Pp=Ҡp* Ϭѵ = Ҡp (γz+q)

7.1.3 Water pressure

Average hydraulic pressure at toe (B):


U = (U1+U2)/2 > UB
HYDRAULIC PRESSURES:
U1 = (d-i)*γW
U2 = (h+d-j)*γW
Steady seepage:
In case of uniform dissipation of head difference along the flow path adjacent to the wall
UA = (2(d-i)(h-j+i))/(2d+h-j-i)
UB = (2(d-i) (d+h-j))/(2d+h-j-i)

7.2 DESIGN OF DIAPHRAGM WALL


In the design of earth retaining system for deep excavation, it requires both ultimate limit
states and serviceability limit states to be considered. An ultimate limit state of a structure
is seemed to have been reached when sufficient parts of the structure, the soil around it, or
both have yield to result in the formation of a failure mechanism in the ground or severe
damage in the principal structural components. A serviceability limit state of a structure is
seemed to have been reached with the onset of excessive deformation or deterioration.

35
7.2.1 Design of Cantilever Wall (Free Earth Support)
Fully fixity must be obtained to prevent a rotation and collapse of the wall .the penetration
depth is control the fixity. Certain simplifying assumptions are made due to the relative
complexity of the calculations.Fig7.4 shows an actual pressure diagram , shear, bending
moment and wall deflection diagrams.

Figure 7.4 stresses affect on cantilevered diaphragm wall

Design procedure

1) Ʃ Ma = zero to Find (Penetration depth).

2) Find Point of zero shears.

3) Find max bending moment (Mmax ) at point of zero shear

4) Actual penetration depth = 1.4*(calculated penetration depth).

36
7.2.2 Design of Hinged Single Anchored System
Fully fixity must be obtained to prevent a rotation and collapse of the wall .the penetration
depth anchored system is control the fixity.

Design procedure

1) Ʃ Ma = zero.

2) Ʃ H = zero EP+T- Ea=0.

3) From 1, 2 find D, T.

4) Find Point of zero shear.

5) Find max bending moment (Mmax ) at point of zero shear.

Fig 7.5 shows an actual pressure diagram and shear, bending moment and wall deflection
diagrams.

Figure7.5stresses affect on hinged single anchored diaphragm wall

7.2.3 Design of Fixed Single Anchored System


Design procedure

This structure can be subdivided into two parts (AB & BC).
AB part can be solved as cantilever.
BC part can be solved as single anchored free earth support

Fig 7.6 shows an actual pressure diagram and shear, bending moment and wall deflection
diagrams.

37
Figure7.6stresses affect on fixed single anchored diaphragm wall

7.2.4 Design of Multi-prop System


For deep excavation, usually the multi-anchored walls are used instead of cantilever or
singly supported walls. The design requirements and analyses for multi-anchored walls are
different from cantilever or singly supported wall. The earth pressures that act on multi-
level strutted walls or multi-level tied-back walls depend on the wall stiffness relative to
the soil, the support spacing and the acting pressure. The method of construction of these
walls is usually sequential, installing the wall and excavation in stages followed by
installation of support like anchor or prop at each installation stage. The available methods
for analysis and design of multi-level supported walls can be categorized as follows:
A. Empirical method

Usually based on strut load envelopes recommended by Terzaghi and peck (1967) or
peck(1969) for three categories of soil: sands, soft to medium clays and stiff clays.
a) For sand
Sands are assumed "drained". If no permeable wall is used, hydrostatically distributed
water pressure should be added to strut loads. Wall can be designed using the Coulomb
earth pressure distribution with hydrostatic water pressure except full drainage occurs
through the wall.

38
Pt = .65*Ka*γ*H2 → empirical value
pA = .5*Ka*γ*H2 → exact value
pt/pA = 1.3

Figure 7.7 Empirical method in sand soil

b) For soft to medium clays

Clay is assumed "undrained" and only considers total stresses.

Pt = . 75*γ*H2(1-4/N)

PA = .5*γ*H2(1-4/N)

Pt/PA =1.75

Figure 7.8 Empirical method in soft to medium clays

39
c) For stiff clays

Pt = .15*γ*H2 to .3*γ*H2

PA/N = 4 PA = 0

N4 PA4

Figure 7.9 Empirical method in stiff clay

Gue and Tan (1998) observe that for anchored diaphragm walls in Kenny Hill residual
soils in Kuala Lumpur, the apparent lateral earth pressures that were obtained from the
load cells indicated that for anchors at depths greater than 60% of the maximum excavation
depth of more than 20m, the apparent earth pressure obtained is larger than the values
suggested by Terzaghi& Peck (1967).

B. Beam spring approach (beam on elastic foundation)

The earth pressures are modeled with a series of independent spring supports similar to
Winkler elastic foundation model. At the start of the model, the springs are compressed to
create an initial load equal to represent a state of at-rest pressure. At each stage of
excavation or support system, the spring loads change as soil, water, and support system
loads are applied or removed and lateral wall displacement occurs. The soil springs load-
displacement relationship (modulus of subgrade reaction) is determined by the input soil
stiffness and governs the spring displacement until the limiting value of active or passive
pressure is reached.
The Winkler elastic foundation model approximates the wall-soil interaction with a one-
dimensional model instead of a two-dimensional model that includes the soil mass, and
hence doesn't include the effects of arching within the soil mass.
Typically, the required soil parameters include: unit weight; at-rest, active, and passive earth
pressure coefficients; and values for the modulus of subgrade reaction for the various soils
40
that may affect the system. The modulus of subgrade reaction is not a true soil property, but
rather depends on both the soil conditions and the geometry of the excavation being
modeled. To be representative, the modulus of subgrade reaction needs to be adjusted based
on the effective influence zone, which varies with the size of the loaded area.
Typically, the predicted wall displacements are much more sensitive to the values of sub
grade modulus used in the analysis than the predicted brace loads and wall bending
moments. Hence, conservative selection of the modulus of subgrade values should provide
conservative estimates of ground movements, without significantly increasing the structural
demand of the wall and bracing system.

C. Soil-structure interaction method (Finite Element method)

This method will be able to model wall and soil deformation and stress in realistic stages of
operations that follow actual construction sequence. Pre-judged failure modes are not
required in the analysis. This method can be carried out in two or three-dimensional
depending on the computer codes used. Usually two-dimensional is sufficient.

This method is particularly useful in predicting deformations of wall and soil for
serviceability checks especially there are deformation sensitive structures around the
excavation. Use of soil stiffness at low strain value is essential in this approach. Tan (1997)
has presented correlation to acquire the stiffness of Kenny Hill residual soils at low strain.

Some of the computer packages in this category include Finite Element program CRISP90
(Brittoand Gunn, 1987) and Plaxis, and the finite difference package FLAC (ITASCA,
1991).

Comparison of BEF and FE Results

For the United States Capital Visitor Center (Pearlman et.al. 2004 and Bonita (2005)), the
analyses for the structural design of the support system were performed using both BEF and
FE models The BEF program (WALLAP, 1997) was easier and quicker to run than FE
programs, so it was used for the structural design of the wall system by using the BEF
model, the design team could evaluate more design profiles FE models were run to verify
that the BEF model loadings and stresses were conservative and to provide ground
deformation predictions.

41
7.3 ULTIMATE LIMIT STATES

The check on the ultimate limit states of the wall includes check on the following:

A. Overall Stability the provision of sufficient embedment depth to prevent

overturning of the wall and overall slope stability.

B. Basal Failure the wall penetration depth must be sufficient to prevent basal

failure in front of the wall after excavation to formation level.

C. Hydraulic Failure the penetration of the wall must be sufficient to avoid piping or

blow out' in front of the wall after excavation to formation level

7.3.1 Overall Stability


The overall stability of both retaining walls is often evaluated using limit equilibrium
methods of analysis in which the conditions of failure are postulated, and a factor of safety is
applied to prevent its occurrence. There are a number of ways of applying the factor of
safety for the overall stability. They are:

a) Factor on embedment:

A factor of safety is applied to calculate embedment depth at limiting equilibrium. The


method is described in the US Steel Sheet Piling Design Manual (United States Steel
Corporation, 1975), the British Steel Corporation Pilling Handbook (1988) and by
Symons (1983).

b) Factor on moments of gross pressure:

This method applies a factor of safety to moments of gross pressure on the passive side only.
Water pressure is not factored. The method is described in NAVFAC Design Manual 7.2 by
US Navy (1982).

c) Factors on moments of net total pressure:

The net horizontal pressure distribution acting on the wall is calculated and the factor of
safety is defined as the ratio of moments of the net passive and active forces.

d) Factors on net passive resistance or Potts and Burland Method

Developed by Potts and Burland (1983) and is analogous to the calculation of the bearing
capacity for a strip load. This method defines the factor of safety as the ratio of the moment
of the net available passive resistance to the moment activated by the retained material

42
including water and surcharge.

e) Factors on shear strength on both active and passive sides:

Soil shear strengths are reduced by dividing c' and tanφ′ by factor of safety, and the active
and passive pressure diagrams are calculated using these reduced values. The reduced values
approximate to mobilized values. Bending moments and prop loads derived from the
calculation can be used for wall design if they are treated as ultimate limit state values. This
method is recommended in BS8002, 1994.

f) Factor on shear strength of passive side only:

The passive resistance is factored but no factor is applied to the active side.

Comparative studies show that there is no relationship between factors of safety applied to
methods listed. There are little that the preferred method is really defined by personal use
and experience, but some useful observations were made as follows:

 The factor on embedment is empirical and should be checked by applying a second


method (Factor on moments of gross pressure).
 The method of factoring moments on gross pressure may give excessive penetration at
low angles of shearing resistance (φ′ less than 20 ), so use varying factors for different
ranges of φ′ .
 The factoring of net passive pressure moments tends to give high penetration values.
 The factors on modified net passive resistance give consistent results in a reasonable
range of soils and wall dimensions.
Factors of safety recommended by Padfield and Mair for use in stiff clays with methods for
factoring embedment, moments of gross pressure, net passive resistance, shear strength on
both active and passive sides, are produced in table 7,2.

Two approaches are used:

 Approach A is based on moderately conservative parameters.

 Approach B uses worst credible soil parameters, geometry and loading in design .while
applying to stiff clays, the factors of safety listed can also be taken as indicative values
in granular soils.

43
Table 7.2 Factors of safety for methods of analysis embedment (Padfield and
Mair)

44
7.3.2 Basal Heave Failure

Usually base failure to an excavation by upward heave applies particularly in very soft and soft
clays and silty clays.Stiff soil less prone to encounter this problem. The basal heave failure is
analogous to a bearing capacity failure, only in reverse being that stresses in the ground are
relieved instead of increased.

There are many methods to examine the basal heave failure and may be broadly divided
according to basic concepts such as those based on bearing capacity formulae and those based
on examination of moment equilibrium. It is recommended that in the design, both methods are
to be used for basal heave check.

A) Method based on Bearing Capacity Formulae:

The first method based on bearing capacity formulae are presented by Terzaghi (1943) for
shallow and wide excavation shows in Fig 7.10.

The second method introduced by Bjerrum&Eide (1956) is suitable for deep and narrow
excavations shows in Fig 7.11.

Both methods neglect the effect of wall penetration below foundation level and results may be
conservative especially where stiffer clays exist with depth

Figure7.10 for shallow or wide excavation with (H/B) <1

45
Figure 7.11 for deep excavation with (H/B)> 1

The methods for calculating factors of safety against basal heave in cohesion less soils
shows in fig 7.12, cuts in clay of considerable depth shows in Fig 7.13 and cuts in clay
limited by hard stratum shows in Fig 7.14, as described in NAVFAC Design Manual 7.2

(1982).

a) Factors of safety against basal heave in cohesion less soils

Stability is independent of (H) & (B), but varies with (φ&γ) Factor of safety
Fs = 2Nγ * (Υ2/Υ1) Ҡa * tan φ1
Where: (Nγ) is the bearing capacity factor.
If groundwater is at depth of (B) or more below base of cut Υ2&Υ1 are taken as moist
unit weights.
If groundwater is static at base of cut Υ1 is the moist weight and Υ2 is the submerged
weight.
If seepage is moving upward to base of cut Υ2 = (saturated unit weight) – (uplift
pressure)

46
Figure 7.12 Factor of safety against basal heave in cohesion less soils

b) Factors of safety against basal heave in, cuts in clay of considerable depth.

If sheeting terminates at base of cut the factor of safety Fs =(C Nc/(Υ H +q))
Where
Ncis the bearing capacity factor which depends on dimensions of the excavation (B,
L&H)
C is undrained shear strength of clay in failure zone beneath and surrounding base of
cut.
Q is the surface surcharge
If safety factor is less than (1.5) sheeting must be carried below base of cut to insure
stability.

Figure 7.13 Factor of safety against basal heave in cut in clay

47
c) Factors of safety against basal heave in cuts in clay limited by hard stratum.

Continuous excavation Fs = (C NCD/ (Υ H +q))


Rectangular excavation Fs=(C NCR/ (Υ H +q))
NCD& NCR are the bearing capacity factors which depend on dimensions of the excavation (B,
L&H).
In general factor of safety must be more than (1.5).

Figure 7.14 Factor of safety against basal heave in cuts in clay limited by hard
stratum

d) Method based on Moment Equilibrium

The methods to evaluate basal heave failure based on examination of moment equilibrium
are described in Japanese Codes such as Architectural Institute of Japan (1988 Revision 1)
and Japan Society of Civil Engineers (1986 Revision 6). Figure 7.15 presents the summary
of the two moment equilibrium methods. In these methods, excavation width and excavation
length cannot be taking into consideration but it is possible to include variations of shear
strength in the direction of depth. With the moment equilibrium methods, the factor of safety
is generally required to be not less than 1.2.

48
Figure7.15 Stability of internally braced cut (circular arc method)

Moments around center of rotation


Forces to consider:
1) Weight of driving mass (WT)
2) Resisting strut loads (P1, P2) (Horizontal component of support load.)
3) Resisting shear capacity of wall (Hs) from competent soil layer.
4) Shear #strength of soil, frictional component (T). and
Cohesion, (c)

49
Figure7.16 Potential failure surfaces

7.3.3 Hydraulic Failure


For excavation at site with groundwater on the retained side exists above the base of the
excavation or under artesian pressure, analysis need to carried out to prevent hydraulic failure.
If the toe of the wall does not penetrate into an impermeable layer or to a sufficient depth,
instability of the base caused by piping occurs if the vertical seepage exit gradient at the base
of the excavation is equal to unity.
Figures 7.17 represent the design charts for wall penetration required for various safety factors
against heave or piping in isotropic sands.
Figures 7.18 represent the design charts for wall penetration required for various safety factors
against heave or piping in sands and in stratified soil.
At two types are recommended in NAVFAC Design Manual 7.2 (1982).

Usually a safety factor of 1.5 to 2.0 is provided to prevent piping.

50
Figure7.17 the design charts for wall penetration

51
Figure 7.18 the design charts for wall penetration

52
The boiling (piping) of the excavation base can also be checked using Terzaghi's method and
the critical hydraulic gradient method that mainly consider vertical flow in the vicinity of the
excavation bottom. Figure 7.19shows the summary of the above two methods. The Japanese
codes mostly suggest the use of Terzaghi's method with factor of safety ranges from 1.2 to 1.5
for temporary and permanent works respectively. For the critical hydraulic gradient method,
the suggested factor of safety is 2.0.

Figure 7.19 the summary of the Japanese and Terzaghi methods

53
To prevent heaving due to artesian pressure, the equilibrium between overburden
pressure and pore water pressure at the top surface of confined aquifer (bottom
surface of clayey soil) need to be evaluated as shown in Figure 7.20 and usually
factor of safety of 1.2 is sufficient.

Figure 7.20 the equilibrium between overburden pressure and pore water
pressure

7.4 SERVICEABILITY LIMIT STATES


Serviceability limit state check for retaining walls involves solution of soil-structures
interaction problems that require the use of deformation parameters and generally divided into
two major items:

7.4.1 Deformation of Wall


The acceptable limits of the wall deformation will depend on the purpose of the excavation
and whether the works are temporary, permanent and the permissible deformation of soil
behind the wall.

7.4.2 Deformation of Soil Behind the Wall

Settlement and lateral movements of the soil behind wall must not exceed the permitted

54
deformation of surrounding buildings and services. The guide on the limiting deformation of
framed buildings, reinforced and unreinforced load bearing walls are indicated in Table7.3.

Table7.3 Summary of limiting deformation

55
Primary factors influencing the deformation of the wall and the retained ground
are:

e) Type of ground
f) Depth and width of excavation
g) Stability of the bottom of excavation
h) Stiffness the support system and preload forces
i) Rigidity of the wall.
j) Construction technique.

7.5 SUPPORTING ELEMENTS

. 7.5.1 Ground Anchors

Ground anchor is a common type of supporting element used in the design and construction of
in-situ retaining walls. It is an installation that is capable of transmitting an applied tensile
load to a load bearing stratum which may be a soil or rock

Types and Capacity of Anchors


 Permanent anchors
 Design life of a permanent anchor is the same as the life of structure.
 Temporary anchors
 Design life of a temporary anchor is maximum two years.

Figure 7.21 Section of an anchored wall, details of anchors

56
57
Figure 7.22 Anchorage section

Figure 7.23 Free length section

58
Free length is a function of height of the wall. Fixed length is selected according to type of
soil and it varies between 3 m and 10 m fixed length is the tensile load bearing part of an
anchor in soil. There're different mechanisms of stress transfer from the fixed anchor zone
to surrounding ground. It is usually referenced as bond stress and depends on soil type and
grouting procedure.

Table 7.4 the minimum safety factors for design of individual anchors

Types of Ground/grout Tendon Grout/tendon


anchor interface encapsulation
interface

Temp anchor 2 1.6 2

Perm anchor 3 2 2

Capacity of anchors in cohesion less soils depends on average grain size (D50), uniformity
coefficient (CU), relative density (RD), fixed length, diameter of drill hole, method of grout
injection (primary/secondary) and grout pressure. Higher D50, CU, RD and grout pressure
result in higher capacities. Fixed lengths of 4 to 8 m are in use and 6 m seems to be a lower
limit of recommendation for fine to medium sand.

Capacity of anchors in clays is low compared to sandy and gravelly soils. Fixed anchor
lengths in design are usually 7-8 m. Application of low grouting pressure (less than 1 MPa)
and use of casing tubes may be beneficial to the capacity. Skin friction (tm) increases with
decreasing plasticity and increasing consistency.

 Planning of Anchors

Free length at each excavation stage and fixed length are selected. Fixed length in cohesion
less and cohesive soils has been discussed in the previous section It is usually kept constant in
a project. Fixed length has to be placed outside the active wedge behind wall.

The spacing between the ties rod usually between (1.5 & 2.5) in retaining structure but in case
of diaphragm walls the spacing is controlled by the panel width.

59
To get force in tie rod and moment in walling

Figure 7.24 Tie rod force

7.5.2 Struts
Strut is a compression member to provide temporary support to in-situ retaining walls in
deep excavations. It is mostly a steel beam of various sections or a pipe. Reinforced
concrete
beams are seldom used. Struts usually span the width of excavation and in cases of very
wide excavations vertical support is needed. It is an old support system compared to ground
anchor which has been used since mid- Seventies. Placement and removal of struts in
multi-level systems interfere with construction, and it is the major disadvantage. It is
relatively quicker compared to anchor support .
Experience gathered during the early metro construction activities in the U.S. and Europe
till 1970‟s still guides the present design principles. Apparent earth pressure envelopes
proposed by Terzaghi and Peck(1967) and Peck(1969) based on measurement of strut loads
in several projects are commonly used in the design of strutted support of excavations.

 Design of a strut support system includes:

A. Preliminary specification of strut pattern (geometrical lay-out, horizontal/vertical


spacing).
B. Estimation of loads in different soils by methods of analysis, and selection of length,
type, size and section of props.
C. Design of strut-waling connections and waling beams.

Design of a strutted retaining system is affected from several factors like sequence of
excavation and placement of supports and their stiffness and wall stiffness. If span width is
large steel strut section is generally preferred and in cases where depth of excavation is
comparable to width, reinforced concrete may be an alternative. Steel H sections and pipes
are common but availability and practical fabrication details govern the selection.

60
Simple end details for tight placement, minimum cutting requirements during removal and
least interference problems with construction activities are preferred. Short spans or trenches
are supported by proprietary struts easily which are also capable of applying preloads.
Preloads on stiff large sections may not be very effective.
Horizontal and vertical spacing of struts is related to construction activities and both of them
are kept as large as possible. 4 m to 5 m spacing is common but if side dimension or
diameter of support is considered net distance between struts is somewhat less. Geometry of
system depends on size and shape of excavation. Fig. 7.25 shows some examples.

Figure 7.25some examples for the geometry of strutted systems

Poor detailing and mistakes during removal of struts are sometimes reported as the reason
for damages and collapses. As far as unexpected (extra) movements of propped systems are
considered; depth of excavation to first prop level, over-excavation, delays in prop support,
loose installation are the common causes. Measurements on struts disclose that they are
structurally overdesigned in many cases. Buckling due to excessive loading or insufficient
capacity of section is not frequently encountered. Temperature changes cause increase or
decrease in strut loads but level of safety factors for struts allocated in design and earth
pressure envelopes usually compensate these changes
7.6 DISPLACEMENT of ADJACENT GROUND DUE TO DEEP EXCAVATIONS
When deep excavations are made and in-situ retaining walls are constructed horizontal and
vertical displacements occur around the excavation pit. They have to be kept at acceptable
limits otherwise damage to buildings, roads and underground facilities will occur. Large
number of excavation pits is opened every year worldwide and some of them are
instrumented. In this section expected displacements will be summarized in different soils.

7.6.1 Factors Affecting Wall Movements


 Soil condition.
 Groundwater condition.

61
 Changes in groundwater level.
 Depth and shape of excavation.
 Diaphragm wall stiffness.
 Supporting elements.
 Methods of construction.
 Surcharge loads.
There are Studies like Clough and O‟Rourke (1990) and Long (2001) show shows
maximum lateral wall movements and maximum vertical settlements behind walls
normalized by excavation height, soils are classified as soft soil or stiff soil, effect of the
factor of safety against base heave and the effect of the type of the supporting system is
also consideredAs shown in table 7.5

Table 7.5 Maximum wall movements and vertical settlements behind walls

62
7.6.2 Instrumentation of Deep Excavations
Deep excavations are instrumented before any excavation works start. They are needed for
controlling the behavior of wall and surrounding facilities. Displacements may not be detected
by visual inspection up to a certain level. There are many instruments that can be installed as
summarized in Table 7.7. Some of them are more frequently used in deep excavation projects.
These are inclinometers, horizontal and vertical extensometers, piezometers and surveying
methods to measure horizontal and vertical displacements of both wall and adjacent facilities.
Inclinometers may be placed in boreholes and/or in piles and diaphragm walls. An extra
number of instruments in each category must be allowed because damage occurs during
construction activities. Load cells on struts or anchor heads may be very useful in checking the
calculated project loads.

Table 7.6 Instrumentation of deep excavations

63
7.7 FAILURE SHAPES OF DIAPHRAGM WALLS
Cantilevered wall may be failure due to forward rotation as shown in Figure7.26.
Anchored walls due to excessive bending moment as shown in Figure7.27, rotation about
anchor shown in Figure7.28, yielding of anchor as shown in figure 7.29, rotation of soil
mass as shown in figure 7.30 and overturning of soil mass as shown in figure 7.31

Figure 7.26Embedded wall cantilever failure by forward rotation

Figure 7.27 Bending moment failure of embedded wall

64
Figure 7.28 Failure of embedded wall by rotation about anchor

Figure 7.29 failure of yield of anchor or tie

Figure 7.30 Failure by rotation of soil mass

Figure 7.31 Overturning of soil mass

65
CHAPTER 8
CASES OF STUDY

8.1 CASE STUDY 1 (QUAY WALL AT THE PORT OF CALAIS)

8.1.1 Introduction
The Port of Calais is situated on France's North Sea coast, at the point closest to England (22
nautical miles). Calais, together with the Port of Dover, provides the main maritime link between
the UK and Western Europe. The two ports find themselves in the unique global position of
taking first and second place in port classification in terms of passenger transport. Handling an
average of 65 car ferry departures per day and up to 20 million passengers per year, Calais is also
France's fourth largest mercantile port with 38 million metric tons of goods handled annually.
The opening of the Channel Tunnel in 1994-1995 prompted shipping companies to review their
operations in order to tackle this new competitor head-on: the frequency of crossings has been
increased and embankment procedures have been improved. The Port of Calais as shown in
Figure 8.1

Figure 8.1 the Port of Calais

66
8.1.2 Description of The Structure And Site
The structure under study is a retaining wall as shown in Figure 8.2, with a free height of 24
m and a length of 725 m, for use as a quay wall. The technical solution adopted is a variant of
that proposed and consists of a retaining wall built partially as a diaphragm wall in the ground
and partially in cased concrete, to be anchored by a passive system containing two layers of
tie rods and a sheet pile wall that serves as an anchorage block as shown in Figure 8.3.

Figure 8.2 plan of the Port of Calais

Figure 8.3 Typical section cut of the completed structure

67
8.1.3 Geotechnical and Hydrological Context
The soils encountered on site have been the focus of three reconnaissance surveys, whose
detaileddescription has been provided in Delattreet al. [1999]. The site is initially composed
of two formations:
 Flandrian sands between the ground surface to approximately a +5.00 reading on the
Marine Elevation Scale (CM) and a depth of –21.00 to –22.50 CM. These sands are
homocentric and fine-grained and were deposited during sea level movements during the
Quaternary Period.
 Flanders clay located beneath elevation readings –21.00 to –22.50 CM, with an
unrecognizable thickness. This clay is stiff and was deposited during the Eocene Period.
Table IV lists the soil parameter values extracted from the entire series of tests. Prior to
its installation, the site had been protected from sea level variations by means of an
enclosing dike. The new dock, on the contrary, is exposed to tidal conditions: the high
tide level during extreme tides can reach in the vicinity of +8.00 CM, while the low tide
level under extreme conditions lies around +0.30 CM. During the various construction
operations (March 1989 through November 1989), the water table was lowered to the –
8.00 level then rised back to –5.00 and then to –1.60 CM.

68
8.1.4 Construction Phases
The construction was carried out in nine stages, as briefly described below. For a more
detailed discussion, the interested reader is referred to the work by Delattre and Mespoulhe
[1999].

 Phase 1: A platform is built at an elevation of –4.50 CM, with the water table being
lowered to – 8.00 CM. The diaphragm wall (thickness: 1.33 m) is then cast from this
platform. Its base reaches an elevation of –29.00 CM, approximately 8 m beneath the
interface between the sands and the underlying Flanders clay layer. It is then scaled
back to an elevation of –5.50 CM.
 Phase 2: The diaphragm wall is extended between –5.50 and +7.00 CM by a cast in
place reinforced concrete superstructure. The lower layer of tie rods with diameter 90
mm and length 42 m, as well as the rear sheet pile wall, are installed.
 Phase 3: The sand embankments are built to the layer of upper tie rods at elevation
+4.00 CM along a 7-degree slope. The upper layer of tie rods is installed next. These are
passive tie rods with a diameter of 55 mm, grade T45 and spaced every 2 m. This layer
is then anchored to the same sheet pile wall as the lower layer.
 Phase 4: The ground is backfilled behind the diaphragm wall up to elevation +7.00 CM,
while the retaining wall is capped at elevation +9.00 CM by a longitudinal beam. A road
for worksite traffic is then installed 20 m in back of the retaining wall.
 Phase 5: Backfilling to elevation +8.70 CM. The water table rises to elevation –5.00
CM.
 Phases 6 and 7: Dredging to an elevation of –10.50 CM and then once again to
elevation –13.40 CM on the dock side.
 Phase 8: Termination of the level lowering: the water table rises to –1.60 CM on the
shore side and to –0.60 CM in the dock.
 Phase 9: The dock is set into place. The water level is variable at the dock (between
+0.30 and +8.00 CM) and the water table moves to an equilibrium position behind the
diaphragm wall (+4.50 CM).

69
8.1.5 Instrumentation and worksite monitoring
The implemented set of instrumentation comprised inclinometers within the diaphragm wall
and itsuperstructure, vibrating wire extensometers placed by pairs extensometer both on the
anchoring rods and in the diaphragm wall, and a high-precision topographical surveying
instrument at the head of the diaphragm wall. Around ten readings from various devices were
conducted during the construction process extending through service startup, between March
1989 and March 1991. For
further details on the measurement campaigns held; see Delattre and Mespoulhe [1999].

70
8.2 CASE SYUDY 2 (MRT CHALOEM RATCHAMONGKHON LINE,
BANGKOK)

8.2.1 Introduction
The Chaloem Ratchamongkhon line as shown in figure 8.4 is the first underground mass
rapid transit project in Bangkok, Thailand being constructed under the supervision of
Metropolitan Rapid Transit Authority (MRTA). The project involves the construction of
about 22km-long, twin bored, single track tunnels, 18 station boxes and cut and fills tunnels.

The station is one of the biggest stations and located on the Ratchadaphisek Road. The
station box is enclosed by principally 1.0m thick side walls and 1.20m thick end walls32.0-
42.0m deep. A Tunnel Boring Machine (TBM) launching shaft was included in the north
side of the station. To facilitate top down construction, 63 Barrettes (1.2mx3.0m) embedded
44.5-55.0m deep in conjunction with pre-placed stanchions at the top were used.

Three basement levels were planned for the station. The excavation depth inside the station
box was up to 24.5m for tunneling and basement slab construction. As deep excavation
required string in tolerances for the diaphragm walls and barrettes, a high level of quality
control was necessary.

Figure 8.4 the Chaloem Ratchamongkhon line

71
8.2.2 Description of The Structure And Site
The subsoil profile, as shown in Figure 8.5 consists of made-ground up to 2.5m thick for
pavement underlain by a series of clay and sand layers. Below the made ground is 12.0m
to 14.8m-thick Bangkok Soft Clay.
The first stiff clay layer occurs below 14.0m depth and extends to 21.0m, overlying the
first sand layer. The sand layer is about 20.0m thick at this location and has two thin
(about 2-4m thick) very stiff clay layers at the top. Below the sand layer is stiff to hard
clay layer which extends beyond 60.0m in depth. Within the clay layer, from 48.0m depth,
a 14m thick sand layer occurs in the north and lenses out to the south.

Figure 8.5 subsoil profile

72
8.2.3 Construction phases
Throughout the project, the main construction schedule for the station comprised several
interfacing and parallel work activities such as for utilities and traffic diversions, temporary
decking, substructure work for station box and the TBM driving shaft which other
subcontractors undertook. This meant that guide wall construction in particular needed to
follow utility diversion as the same area was to be excavated for relocation of the utilities,
removal of abandoned water pipes and construction of guide walls. The temporary
deckingand excavation for the TBM launching shaft followed the diaphragm wall
construction.

8.2.3.1 Diaphragm wall construction


Equipment and Plant
Mechanical rope-suspended grabs with crawler cranes (80tons) and service cranes (50-80tons)
were used as main construction equipment. Grabs, 1.0mx2.0-3.0m and 1.2mx3.0m were used
to cut the required dimensions of panel excavations. Bentonite slurry was used as supporting
fluid for panel and barrette excavation. Soils having a total of 300 c.m storage capacity and
de-sanding and de-silting units (80cu.m/hrcapacity) were used to supply the slurry required
for up to two-panel excavation at a time.
 Guide Walls
Generally 1.5m deep guide walls were used for panel excavation. In the location of
underground water pipes and duct banks, up to 3.0m-deep guide walls were used. Individual
panels were sized with the following considerations:
(1) Type of reinforcement.
(2) Size of grabs used.
(3) Thickness and depth of panels.
(4)Location of slab and wall openings for entrances and TBM.
(5) Stability of trench in connection with locationof underground utility.
(6) Location of public accesses and streets.
 Panel Layout
The walls were divided into 184 panels with horizontal lengths varying from 2.5m to 4.85m
as shown in Figure 8.6 L-shaped and T-shaped panels were used to form box structures of the
station and TBM launching shaft.

73
Figure 8.6 panel layout

8.2.3.2 Sequence of construction


Construction activities took place day and night. To maintain the traffic flow, comply with
local authority regulations, construction sequence and activities were planned to allow
concrete pouring and spoil removal to be done before and after rush hours, in most cases at
night. Generally panel excavation was carried out at least 6.0m away from the recently cast
panel or 16hrs after casting of the adjacent panels to avoid any damage induced by
excavation.

8.2.3.3 Supporting fluid


Locally available bentonite powder was used for preparation of slurry. This product had been
used for more than a dozen completed diaphragm wall projects. Approximately 496 tons of
bentonite.
Powder was consumed for excavation work. The last portion of slurry displaced by concrete
or contaminated with cement was usually discarded. Soil volumes of about 26,274cu.m and
10,740cu.m were excavated for diaphragm walls and barrettes respectively.

8.2.3.4 Reinforcement
Steel bars of SD50 were used for the main reinforcement bars. The reinforcement cages were
30.0m to42.2m long and up to 4.5m wide, with 4 levels of box-out for slab connections for
diaphragm wall panels. For barrettes, cages were 48.1 to 54.6m long. 4 to 5 cage sections with
lengths of 6-12m were joined to form one continuous cage for individual panels and barrettes.
The cage sections were fabricated off site and no more than two were joined for transporting
to the site. Cage sections were connected prior to and during lowering into the trench. In order

74
to place the box-out in position and to achieve an exact match of the cage sections, markings
were made on the main bars of each cage. U-shaped bolts were used for cage connections.
Couplers were generally used for slab connection and both couplers and bent-out bars were
used forbeam connections at the wall openings for entrances and slab openings. The large
panel cages weighed up to34.8 tons.

8.2.3.5 Concrete casting


Ready mixed concrete grades 40 (cube strength 40MPa at 28 days) and 35 (35MPa at 28days)
to BS5328were used for diaphragm walls and barrettes respectively. Two sets of termite pipes
were used in pouringconcrete for both diaphragm walls and barrettes. The largest single
concrete pour wasabout232cu.m for Lshapedpanels. Total concrete volumes of 27,480cu.m
and 6,611cu.m were poured for diaphragm walls andbarrettes respectively. Concrete over-
consumption in diaphragm wall caused by old, sand back-fill in thearea of abandoned water
pipes was estimated to be an average of 7.8% with a concretewastage ofup to38.0% occurring
in one panel. However, the average concrete wastage was 5.0%.
Forbarrettes, theaverageconcrete wastage was up to 14%. The high wastage compared to
building and elevated highwayprojects (upto 7%) was caused by overcasting of concrete well
above the cutoff level of 22m depthto ensurethat soundconcrete reached above the cutoff.
Aggregates were used to backfill the opentrench ofbarrettesabove theconcrete after casting.

8.2.4 Quality and Safety and Environmental Controls


As the alignment of diaphragm wall and barrettes is critical, every excavated panel and trench
waschecked with Kinden monitoring equipment. Monitoring was carried out after excavation
reached about22.0m (ie. at the levels of base slab and barrette cutoff) and toe levels.
Necessary corrections to trench verticallywere made during excavation if required. Panel
ends, especially for those panels with soft-eyes forTBM break-through were also checked to
achieve high levels of accuracy for positioning.
Duringexcavation, reference posts were used for checking the grab position and observing
rope position relative to thetrench sides at all times. Prior to lowering the reinforcement cage
into the trench, anymudcakebuilt-up onthe trench faces and panel joints was scraped off by a
grab to which brusheswere attached. Finally,anysediment or loose materials deposited at the
bottom of the trench were also removed by using the grab.

75
Reference bars attached to the top of reinforcement cage were extended above ground level to
check the position of the cage with survey equipment during installation of the cage into the
trench.
Delivered concrete was checked for slump and cohesiveness prior to casting. As per
specifications, adequate embedding length of termite pipes in the concrete and slurry
properties were maintained to achieve good-quality concrete casting. Plugging materials and
shutters were introduced in the termite pipes to separate first concrete pour and slurry in the
trench. Samples of reinforcement bars and concrete were taken as specified for testing in the
lab. 37 barrettes were provided with 6 steel tubes each for sonic logging to test the barrette
concrete quality. No significant anomalies were detected by sonic logging test, and integrity
and quality of barrette were found adequate.
As the site was in a busy public area, site and public accesses were kept clean all the time.
Flagmen were also provided for traffic control at each construction zone. All workers were
inducted in safety procedure prior to assuming duty. Construction activities were also
supervised by a full-time safety officer. The safety officer ensured that all labor used
mandatory personal protection equipment and observed the safety regulations. All heavy
equipment and cranes were checked for safety and certified for operation prior to use and for
regular maintenance. Additionally, regular safety patrol sand inspection were also conducted
by the main contractor and supervising engineers.

76
8.3 CASE STUDY 3 (El-Azhar Road tunnels project)

8.3.1 Introduction
El-Azhar Road tunnels project in Cairo as shown in Figure 8.7 is the first urban underground
road tunnel in Africa. It has four ventilation stations along 2.7-Km of the tunnels route. The
location of the third station was positioned at Port Said Street, west of an existing flyover and
CWO sewer tunnel. This station was the deepest one due to the crossing of the road tunnels
under the sewer tunnel. The total depth of the diaphragm walls of the station was 87.3 m while
the station was 37.3 m deep the thickness of the RC wall was 1.5 m. To reduce the lateral
deformations of the wall, RC horizontal slabs were adopted at different levels to be a monolithic
structure. The ground deformations associated with the construction of the diaphragm walls of
the underground stations can be divided into two components, one due to excavation and
installation of the diaphragm walls and the other due to wall movements. These deformations are
functions of many factors such as depth and shape of walls, soil properties, depth of excavation
around the walls, type and stiffness of supporting system, surrounding structures, surcharge loads
and time of construction. Hydro-phrase machine has been used for the construction of these
diaphragm panels, (Ramond and Guillien, 1999).

Figure 8.7 El-Azhar Road tunnels project

77
8.3.2 Geotechnical Properties
The geotechnical aspect of El-Azhar area and parameters are carried out and presented in the
geotechnical report of the project, (NAT soil report, 1999). The layers of soil in project area are
consisting mainly of fill, clay, sand and sandy gravel. The layers involved in the analysis of the
diaphragm walls of the ventilation station were depending on the minimum toe level necessary
to obtain the minimum safety factor 1.5 of passive mobilized pressure. The poor quality of
clayey layer required the wall to go deeper beyond this layer, into the underlying sand. The
ground water level was found to be at .3.00 m from the ground level. The geotechnical
parameters obtained from the geotechnical report are given in Table 1, (NAT soil report, 1999).
Figure 8.8 illustrates the cross-section of the geological profile and longitudinal section of the
ventilation station.

Table 8.1: Layers and geotechnical parameters

Figure 8.8 Geological profile and longitudinal section

78
8.3.3 Construction Phasing
 The excavation is carried out using a heavy self guided mechanical grab suspended from
the job of a large crawler crane
 The diaphragm walls were excavated and constructed in discrete panels of Between 2.8m
and 7.0m lengths, with a depth reaching 30m .
 As the excavation proceeds, support fluid was added into the excavation to maintain the
stability of the surrounding ground and to prevent a collapse This fluid is called “Bentonite”
which is a poser made of a special type of Soluble clay and is mixed at the mixing plant with
potable water.
 A heavy chisel may be used if an obstruction of hard strata is encountered, toBreak up the
obstruction for removal by the grab.
 When the excavation is completed, a submersible pump connected to tremie pipes will be
lowered into the panel excavation down to the toe level. This pumped the fluid down to the
toe level and then from the bottom of theExcavation back to a descending unit, in order to
separate the bentonite from The suspended particles contained in it. At the same time, fresh
fluid will be added to the top of the excavation to maintain the stability of the ground.

Figure 8.9 Diaphragm wall for Attaba TBM arrival shaft being built under

fly-over

79
Chapter 9

Conclusions
As we know the complexity of the interaction between the ground and the retaining diaphragm
wall structure that make it difficult to predict the behavior of a retaining diaphragm wall
structure in detail and accurately before the actual execution of the works .

The long term effect of a retaining diaphragm wall structure on the sub soil has a large role in
the analysis and design of the diaphragm wall.

The success of the design and construction of a diaphragm wall begin from well planed and
closely supervised subsurface investigation works including field and laboratory testing.

The design of retaining diaphragm wall structure should follow the appropriate standards,
specifications, guide lines and good practices.

The design step doesn’t stop by accomplishment of the diaphragm wall design but it still
continuous during construction to review the performance of the diaphragm wall, compare the
design requirements and prediction and take necessary action to prevent the occurrence of the
critical limit state.

The construction should also follows the approved method statement and have a check list on
supervision to prevent mistakes or carelessness in the execution of the works especially those
highlighted in this research.

Major consideration during construction as follows:

 Dilapidation survey of adjacent structures.


 Instrumentation and monitoring program.
 Supervision and construction control.

Quality assurance system should be implemented to ensure design and construction are carried
out systematically with the necessary check lists.

80
APPENDIX : MULTI_ANCHORED DIAPHRAGM WALL
1 PROFILE OF SOIL

Soil Profile

Soil and Interface Properties

81
2 PROPERTIES OF SUPPORTING ELEMENTS

Diaphragm wall properties

Anchor rod properties

Grout properties

3 PLAXIS MODEL

Geometry Model

82
4 CONSTRUCTION PHASES

PHASE 1:

Activate diaphragm wall and surface loads.

PHASE 2:

Cut upper cluster.

83
PHASE 3:

Activate upper tie-rods and grout.

PHASE 4:

Cut the second cluster and dwatering.

84
Flow field

Extreme velocity 285.86*10-3 m/day

Active pore pressure

Contoured active pore pressure

85
PHASE 5:

Activet the Lower tie-rods and grout.

PHASE 6:

Cut the third cluster and dewatering.

86
Flow field

Extreme velocity 520.22*10-3 m/day

Contoured active pore pressure

87
5 RESULTS

5.1 SOIL RESULTS

Deformed shape

Effective stresses -572.04 KN/m2

88
Extreme vertical displacement 67.04*10 -3 m

Shaded vertical displacement

89
Extreme horizontal diaplacement 79.87*10 -3 m

Shaded horizontal displacement

90
Total displacement

Shaded total displacement

91
92
5.2 DIAPHRAGHM WALLS RESULTS

5.2.1 LEFT ONE

93
Straining action on diaphragm wall

94
95
5.2.2 RIGHT ONE

96
Straining action on right diaphragm wall

97
98
5.3 ANCHOR-RODS RESULTS

99
REFERENCES

CIRIA.Special publication 95.The design and construction of sheet piled


cofferdams.Thomas Telford, london, 1993.

BS 8002 Earth retaining structures.British Standards Institutions, London, 1994.

Brooker E.W . and Ireland H.O.Earth pressures at rest related to stress history.

Canadian Geatech. J ., 1965, 11, feb.,1-15.

Caquot A. and kerisel J.Tables for the calculation of passive pressure, active
pressure and bearing capacity of foundations . Gauthier – villars, paris, 1948.

Civil engineering codes of practice No. 2.earth retaining structures.Civil


Engineering Codes of Practice Joint Committee, London, 1951.

Padfield C.J.and Mair R.J. Design of retaining walls embedded in stiff clay. CIRIA.

London, 1984, report 104.

Terzaghi K. and peck R.B. Soil mechanics in engineering practice. Wiley.New York,
1967 ,2nd edn.

Rowe P.W. Anchored sheet pile walls. Proc. Instn Civ. Engrs. Part 1. 1952.
1.Jan.27-70.

Design manual 7.2. Foundation and earth structures. US Navy, Washington.DC.

1982.

Goldberg D.T.Lateral support systems and underpinning. Vol. 1,design and


construction, Vol. 2,design fundamentals, Vol. 3, construction methods. Federal
Highway Administration, Washington, D.C. 1976, FAWA-RD-75, 128.

BS 6349 (PART 1)maritimes structures. British Standards Institution,London,1984.

Potts D.M.and Burland J.B.A parametric study of the stability of embedded earth
retaining structures. Transport and Road Reasearch

Symons,I.F.Assessing the stability of a propped in_situ retaining wall in over-


consolidated clay .Proc Instn Civ. Engrs,1983,75, dec., 617_633.

Piling handbook.British Steel Corporation, Scunthorpe,UK, 1988.

Sheet piling design manual.USS Steel, Pittsburgh, 1974.

Review of design methods for excavation in Hong Kong.Geotechnical Control


Office Hong Kong, 1990.

100
Lee D.H. Deep foundation and sheet piling. Concrete Pubications Ltd,London,
1961.

Blum H. Einspannungsverhaltnisse bei Bohlwerken. Ernst and sohn, Berlin, 1931.

Terzaghi K.Anchored bulkheads.Trans. ASCE, 1954,119. Paper 2720.1243_1324.

Rowe P.W.Atheoretical and experimental analysis of sheet pile walls. Proc. Instn
Civ. Engrs, 1955,4, Jan., 32_69.

Terzaghi K.Therectical soil mechanics. Wiley ,New York. 1943.

Bjerrum I.. and Eide O. Stability excavations in clay. Geotechnique,


1956,6,32_47.

Aas G. Stability problems in a deep excavation in clay.Norwegian Geotechnical


Institute. Oslo, 1985, publication 156.

Bjerrum L. Problems of soil mechanics and construction on soft clays.Proc. 8rh


Int. Conf. S.M.F.E., Moscow,1974, Vol. 3, 111_159.

BS8110 Structural use of concrete. British Standard Institution, London, 1985.

BS8007 Design of concrete structure for retaining acqueous liqids.British


Standards Institution, London, 1987.

Peck R.B. Deep excavation in soft ground.Proc. Int.Conf. S.M.F.E.,Mexico City,


1969,State-of-the-art vol.,225-290.

Papin J.W.et Numerical analysis of flexible retaining walls. Proc. Conf. Numerical
Methods, Swansea,1985,789_802.
Terzaghi, K. (1943),Theoretical soil mechanics. Wiley, New York.
Terzaghi, K. and Peck, R.B. (1967),Soil mechanics in engineering practice. Wiley,
New York, 2nd edn.
Potts, D.M. and Burland, J.B. (1983),A parametric study of the stability of
embedded earth retaining structures. Transport and Road Research Laboratory
report 813, Crowthorne, UK.
Peck, R.B. (1969), Advantages and limitations of the observational method in applied
soil mechanics.
Peck, R.B. (1969), Deep excavations and tunnelling in soft ground. Proc. r" Int.
Conf. S.M.F.E., Mexico City, State-of-the-art vol., 225-290.
Padfield, C.J. and Mair, R.J. (1984), Design of retaining walls embedded in stiff
clay. CIRIA Report No. 104, Construction Industry Research and Information

101
Association, London.
NAVFAC Design Manual 7.2 (1982), Foundation and earth structures. Department
of Navy, Naval Facilities Engineering Command, Washington, DC.
NAVFAC Design Manual 7.1 (1982), Soil Mechanics. Department of Navy, Naval
Facilities Engineering Command, Washington, DC.
Bjerrum, L. (1974), Problems of soil mechanis and construction on soft clays. Proc.
s" Int. Conf. S.M.F.E., Moscow, Vo1.3, 111-159.
Bjerrum, L. (1963), Discussion Proc. Eur. Cont. SM&FE, Wiesbaden, 2, p.135.
Bjerrum, L. and Eide, O. (1956), Stability of strutted excavations in clay.
Geotechnique, 6, 32-47.
Clough, G.W. &O'Rourke, T.D. (1990), Construction indued movements of in-situ
walls. Proc. ASCE Specialty Conference, Cornell. ASCE Geo Special Publication 25.
Clough, G.W., Smith, E.M. &Sweeney, B.P. (1989), Movement Control of
Excavation Support Systems by Iterative Design. Proc., ASCE, Foundation
Engineering: Current Principles and Practices, Vol. 2, 869-884.
Clough, G.W., Hansen, LA &Mana, A.1. (1979), Prediction of support excavation
movements under marginal stability conditions in clay. Proc. of the 3rd Int. Cont. on
Numerical Methods in Geomechanics, Aachen, VolA, 1485-1502.
GCO (1993), Guide to Site Investigation. Geotecnical Control Office, Geoguide 2,
Hong Kong.
GCO (1990), Review of design methods for excavations in Hong Kong. Geotechnical
Control Office, Publication No. 1/90, Hong Kong.
Gue, S.S. &Tan, Y.C. (1998), Performance of Anchored Diaphragm Walls for Deep
Basement in Kuala Lumpur, Malaysia, Proceedings of the 13th Southeast Asian
Geotechnical Conferences, Taipei. (accepted for publication in November, 1998)
Institution of Structural Engineers (1989), Soil-Structure Interaction - The Real
Behaviour of Structures. Institution of Structural Engineers, London, 120p.
Matsuo, M. and Kawamura, K. (1981), Predictions for the settlements around the
excavations. Proc. of the 26th Symposium of JSSMFE on comparing measurements
and predictions of ground deformation due to excavation or embankment, pp. 61-68
(in Japanese).

102
WEB REFERENCES

[1] http://eng.hi138.com/?i292432_Diaphragm-wall-construction-on-the-
Problems-and-Solution
[2] http://www.p3planningengineer.com/productivity/diaphragm%20wall/diaphra
gm%20wall.htm
[3] http://www.archiexpo.com/prod/keller-holding/reinforced-concrete-
diaphragm-walls-61321-345908.html
[4] http://www.modelco.com/en/foundation_equipment/diaphragm_wall/diaphr
agm_wall_implements/implements_flat_stop_end_pipes/water_stop_end_joi
nt_ws.asp
[5] http://www.nzta.govt.nz/projects/victoria-park-tunnel/gallery-2011.html
[6] http://www.thiess.com.au/smart-solutions/case-studies/out-of-harm-s-way
[7] http://www.brasfond.com.br/fundacoes/ingles/pdiafragma.html
[8] http://www.takenaka.co.jp/takenaka_e/news_e/pr0101/m0101_03.htm
[9] http://www.gps-bau.com/en/leistungen/schmalwande/schmalwand-
alpenrhein /
[10] http://www.cndrillingrig.com/1-SG.html
[11] http://zgzysq.en.made-in-china.com/product/HqgEGBKOEbpS/China-Shell-
Grab-Mechanical-Grab-Applied-in-Overhead-Crane-.html
[12] http://www.writeopinions.com/hydromill-trench-cutter