You are on page 1of 12

PIPING ENGINEERING CELL

PLOT PLAN
T. N. GOPINATH

The selection of a project site is a of. Data to be collected before starting to


major corporate decision considering the evolve a plot plan can be classified as
various factors that make the plant follows.
technologically and economically viable.
The industrial policy of the government is a 1.0 BASIC DATA
major factor to be considered. Availability
of the various supporting facilities such as 1.1 Civil
power, water, effluent disposal, manpower
etc. have also to be taken into consideration 1.1.1 PLANE TABLE SURVEY MAP
along with the size and nature of the This document shows the extent of
industry. Once the site selection is done, the the plot with the overall area identifying all
next activity is to develop the plot plan. the existing constraints such as transmission
Plot plan is the master plan locating lines, structures, ponds, place of worship (if
each unit/facility within the plot boundary any) etc. The survey covers 20 to 30 metres
for a process plant belonging to industrial beyond the extent of the specified plot to
sectors such as the following. show the nearby roads, drains, etc. and
broad features of the neighbouring plots.
i) Refinery This will also show the geographical north
ii) Chemical / Agro Chemical / direction. The location of power and water
Petro-Chemical/ Organic Chemical / connections are also shown therein.
Inorganic Chemical (Ref. Fig. 1)
iii) Fertilizer
iv) Pharmaceutical 1.1.2 CONTOUR SURVEY MAP
v) Metallurgical Contour survey map shows the levels
vi) Electric Power Generation of the plot with respect to the Mean Sea
Level (MSL). These levels are taken at 10
The development of plot plan is a much metre grid so that the topography of the plot
involved job. While locating the various is well represented. This will establish the
units/facilities within the plot, consideration co-ordinates; normally North-South and
shall be given to the operation, maintenance East-West or it could be X-Y as well. The
and safety aspects related to the plant and to contour map will also show the benchmarks
that of the neighbour, fire hazards, location indicating the MSL to establish the level of
of power and water supply, expansion the plot. (Ref. Fig. 2)
facilities, man-material movements, etc. in a
balanced manner. 1.1.3 SOIL SURVEY
Soil survey is conducted to establish
Before the activity of development of the the load bearing capacity of the soil which
plot plan starts, there are a lot of data, will be required for the civil design. The
related to all disciplines of engineering, to nature of the soil is also tested to determine
be collected and analysed and/or made use the expansive nature, corrosion properties
etc.
1.2 Electrical

Plot Plan.doc 1
PIPING ENGINEERING CELL

The data related to electrical will 1.3.11 Fire Station


constitute the supply voltage levels, the
voltage levels required within the plant and 1.3.12 Weigh Bridge
fault levels to establish the power
distribution system, the location of supply 1.3.13 Staff Colony
point to decide the location of the receiving
station and the requirement of the state 1.4 Meteorological Data
electricity boards.
This data is required to arrive at the
1.3 Non Plant Facilities location of the process area, utility area
and the type of enclosure required for the
Necessary data is required to be building, basic design parameters, the
collected, to arrive at the block size of the drainage details, etc. The data includes:
following facilities, before the work is
started on the development of plot plan. The 1.4.1 Minimum, maximum and normal
user department should be consulted to temperatures during the year
arrive at the requirement and the allocation
should also be proportionate to the available 1.4.2 Rainfall
plot area and the effective process area.
1.4.3 Intensity and direction of the wind
1.3.1 Administrative Block (wind rose)

1.3.2 Canteen 1.4.4 Seismic zone

1.3.3 Workshop 1.4.5 Wet and Dry Bulb temperatures

1.3.4 R & D, QC (Quality Control) 1.4.6 Flood level


Laboratory and Pilot Plant
1.5 Process data
1.3.5 Gate House / Time Office
A lot of data related with the
1.3.6 Security Arrangements working of the process plant is also required
to develop a plot plan. The necessary data
1.3.7 Vehicle Parking includes:

1.3.8 Medical Centre 1.5.1 Size / capacity of the process unit to


work out the area to accommodate
1.3.9 Ware House the same.

i) Covered Area 1.5.2 Knowledge on the type of plant,


ii) Open Area whether it is to be located indoors or
iii) Solid Warehouse outdoors or the extent of enclosure
iv) Liquid Warehouse required.

1.3.10 Steel / Scrap Yard

Plot Plan.doc 2
PIPING ENGINEERING CELL

1.5.3 Sequence of process flow to locate Nitrogen, DM Water, Soft Water,


the process unit in the proper Cooling Water, Chilled Water,
manner. Brine, etc.
1.6.5 Capacities and the grouping
1.5.4 Hazardous nature of the plant to philosophy based on the nature of
keep proper inter-unit distances and utilities.
to work out the fire water storage
volume. 1.7 Statutory Requirements

1.5.5 The overall operating philosophy of Based on the location, nature and
the plant such as type of the plant, the requirements by the
i) Fully Automatic statutory authorities are well spelt out in any
ii) Partially Automatic country. Knowledge and application of these
iii) Manual are essential to develop the plot plan. These
iv) Batch / Continuous talk about the requirements of the Green
belt, Floor area occupation, (FSI) Floor
1.5.6 Raw material receipt and product Space Index, Width of the roads, Free area
despatch philosophy to be maintained along the plot boundary,
Height and tread of the steps, Floor to floor
1.5.7 Storage Philosophy such as the distances, requirements of distances to be
requirement of above ground and/or maintained between the units, requirements
underground storages, the nature of within the petroleum storages and gas
storage material etc. are required to storages, fire fighting requirements, height
decide on the block size. of chimneys, etc. These requirements are as
per the norms set by various government
1.5.8 Effluent plant capacity and discharge bodies in charge of industrial safety. In
points, incineration requirements, India, where the developers of this course
etc. hail from, a typical set of institutions and
bodies which are involved in granting
1.5.9 Type of hazard to decide fire hydrant permissions for the proposed activity are as
system. follows. This list for other nations will be
similar in spirit behind these permissions,
1.5.10 Number of flares. but different in nomenclature.
The following compilation does
1.6 Data on Utilities indeed have a strong India flavour. In a
course like this which is so popular all over
The following data on utilities are the world, it is a bit unfair. But, if you read
required to be gathered to size and locate the through the various rules and guidelines,
various utilities. you would certainly see through the basic
philosophy and pronounced safety concerns
1.6.1 Source and/or supply point of Raw which set the rules of the game. These are
water not different in different countries. The
1.6.2 Quality of water available differences in the guidelines will only be in
1.6.3 Water consumption for the process detail and not in the philosophy. Try to get
1.6.4 Requirement of different types of to these underlying philosophy and
utilities such as Steam, Air,

Plot Plan.doc 3
PIPING ENGINEERING CELL

overriding safety concerns in all the Based on the data collected as listed above,
specifics that follow. the following details shall be worked out so
that these can be used for the development
1.7.1 State Industrial Development of a plot plan.
Corporation (SIDC)
2.1 Block dimensions of the following
1.7.2 Central / State Environmental facilities:
Pollution Control Boards (PCBS) 2.1.1 Process plants considering the
1.7.3 Factory Inspectorate expansion philosophy

1.7.4 State Electricity Boards (SEB) 2.1.2 Utilities based on the grouping
philosophy and expansion
1.7.5 Chief Controller of Explosives
requirements
(CCOE)
2.1.3 Electrical receiving station and sub-
1.7.6 Static and Mobile Pressure Vessel station
Rules (SMPV)
2.1.4 Uncovered storage spaces
1.7.7 Tariff Advisory Committee (TAC)
2.1.5 Solid warehouses
1.7.8 Aviation Laws
1.7.9 Chief Inspector of Boilers (CIB) 2.1.6 Non explosive chemical storages/
Explosive chemical storages as per
1.7.10 Oil Industry Safety Directorate classification
(OISD)
2.1.7 Petroleum Storage as per
1.7.11 Food and Drug Administration classification
(FDA) 2.1.8 Fire water storage requirements
1.7.12 Ministry of Environment and Forest
(MoEF) 2.1.9 Acid / Alkali storage

1.8 Expansion Philosophy 2.1.10 Steel and scrap yard

The philosophy of expansion within 2.1.11 Raw material storage and treatment
the unit and additional units should be facilities
considered while developing a plot plan.
The expansion could be segregated as near 2.1.12 Contractor’s shed
future expansion and far future expansion
and both should reflect in the overall plot 2.1.13 Effluent treatment & Incinerator
plan. plants

2.0 DEVELOPMENT OF PLOT PLAN 2.1.14 Flare stacks

2.1.15 Control room

Plot Plan.doc 4
PIPING ENGINEERING CELL

3.5. Height of Boiler Chimney H (in m) =


2.1.16 Administrative buildings, workshop, 14 Q 1/3 where Q is the quantity of SO2
canteen, laboratories, pilot plant etc. generated in kg/hr.

2.2 Tentative details of Pipe rack/Sleepers


4.0 STEPS TO BE CONSIDERED
2.3 Inter unit distances based on the type WHILE DEVELOPING THE
and nature of the process. PLOT PLAN

2.4 Safety distances for the storages 4.1 Study the contour map and establish
based on the relevant statutory the grade levels/terraces.
regulations.
4.2 Establish the N-S and E-W (or X-Y)
3.0 POINTS TO NOTE grids, the plant north in relation to
geographical north.
3.1. Normally, Construction is permitted on
a maximum of 50% of the plot area 4.3 Establish the free area along the plot
with total built-up area equal to the boundary as per the statutory norms.
area of the plot (i.e. F.S.I. = 1
(Depending upon the regulation 4.4 Work out the area requirements for the
governing the area and the type of green belt, vehicle parking etc. as per
industry) the norms.
3.2. Area reserved for tree plantation shall
be 1/3 of the area occupied. 4.5 The process blocks shall be located in
3.3. Parking space – 10% of the plot area the sequential order of process flow so
3.4. Water storage capacity – 24 hr. that material handling (solid/liquid) is
minimum. minimum.

The following basics can be used to estimate 4.6 The blocks shall also be arranged
the water requirement. considering prevailing wind direction
so that flammable gases do not get
3.4.1 Domestic water - 100 litres per person carried to sources of ignition.
per day
4.7 Storage tanks shall be grouped
3.4.2 Water requirement for Boiler - Steam according to process classification.
rating x Working factor
4.8 Centralised control room shall be
3.4.3 Cooling tower – 1.25 % of capacity as located in safe area close to the
drift and blow down losses process plant.
3.4.4 Washing - 10-15 litres per day per 4.9 Two adjacent process units shall be
sq.ft. of floor area of the plant located based on annual shut down
philosophy so that hot work shall not
3.4.5 Gardening - 5 litres per day per sq.ft. affect the operation.
of garden area

Plot Plan.doc 5
PIPING ENGINEERING CELL

4.10 Process unit shall be located on higher


ground away from the unwanted 4.23 Administrative block, laboratories, etc.
traffic. shall be located closer to the man entry
gate.
4.11 Process units shall be serviced by
peripheral roads for easy approach. 4.24 Process unit can be separated within a
fencing providing additional gate.
4.12 Utility block shall be kept at safe area
close to process plants. 4.25 Consider recommendation from the
statutory authorities for inter unit
4.13 Electrical sub-stations shall be placed distances.
at the load centre to minimise cabling.
4.26 Residential colony shall be located
4.14 Receiving station shall be placed near away from the plant and relatively
the supply point. closer to the city limits.

4.15 Ware houses shall be located close to 5.0 POINTS TO CONSIDER WHILE
the material gate to avoid truck traffic DEVELOPING THE EXPLOSIVE
within the process area. TANK FARM WHICH REQUIRES
CCOE APPROVAL.
4.16 Flares, Furnaces/Heaters, cooling
towers, etc. shall be placed depending 5.1 Layout of Liquid Storage
on the wind direction.
5.1.1 CLASSIFICATION OF
4.17 Provision of future expansion shall be PETROLEUM PRODUCTS
considered.
i) Class-A - Liquids, which have flash
4.18 Raw water storage shall be placed point less than 23oC
closer to water source. Fire and raw
water tanks shall be located together. ii) Class-B - Liquids which have flash
point 23oC and above but
4.19 Fire stations shall be away from the below 65oC
hazardous area and nearer to main
gate. iii) Class-C - Liquids which have flash
point 65oC and above but
4.20 Effluent treatment plant shall be below 93oC
located away from the process and
utility area on the downwind direction. iv) Excluded
Petroleum: Liquids, which have flash
4.21 Workshop, contractor’s shed, storage point above 93oC
yard, etc. shall be at centralised
location serviced by peripheral roads. 5.1.2 REGULATORY QUANTITY
ABOVE WHICH LICENCE IS
4.22 Two gates are preferred, one for the NECESSARY
material entry with weigh bridge and
the other one for man entry. i) Petroleum Class A - 30 litres

Plot Plan.doc 6
PIPING ENGINEERING CELL

In case of motor conveyance or stationary vi) Tanks shall be arranged in two rows so
engines, capacity of fuel tank. that each tank is approachable from the
surrounding road.
ii) Petroleum Class B - 2500 litres
provided it is contained in a receptacle not vii) The tank height shall not exceed one
exceeding 1000 litres capacity and a half times the diameter of tank or
20 m, whichever is less.
iii) Petroleum Class C - 45000 litres
viii) Minimum distance between the tank
5.1.3 LAYOUT CONSIDERATIONS FOR shell and the inside of the dyke wall
EXPLOSIVE TANK FARM shall not be less than one half the
height of the tank. Height is
i) Petroleum storage tanks shall be considered from bottom to the top
located in dyked enclosures with roads curb angle.
all around the enclosure.
ix) It is better that the corner of the bund
ii) Dyked enclosure should be able to should be rounded and not at right
contain the complete contents of the angle as it is difficult to extinguish fire
largest tank in the tank farm in case of in a 900 angle corner because of the air
an emergency. Enclosure capacity compression effect.
shall be calculated after deducting the
volume of the tanks (other than the x) There should be a minimum of two
largest tank) upto the height of access points on opposite sides of the
enclosure. A free board of 200 mm bund to allow safe access/escape in all
shall be considered in fixing the height wind directions.
of the dyke.
xi) Distances to be observed around
In case of excluded petroleum, the facilities in an installation shall be as
capacity of the dyked enclosure could per the relevant chart furnished in the
be based on spill containment and not Petroleum Rules. (Refer Fig. 3 &
containment on tank rupture. relevant Table in the Petroleum Rules)

iii) The height of tank enclosure dyke 5.2 Layout of Gas Storage
shall be at least 1 m and shall not be
more than 2 m above average ground 5.2.1 Storage Vessels are not allowed
level inside. However, for excluded below the ground level. They are to
petroleum, it can be 600 mm. be installed above the ground level.
iv) Class A and/or Class B petroleum can
be stored in the same dyked enclosure. 5.2.2 Vessels shall be located in open.
When Class C is stored together, all
safety stipulations applicable to Class 5.2.3 Vessels are not to be installed above
A and Class B shall apply. one another.

v) Excluded petroleum shall not be stored 5.2.4 If vessels in the installation are more
in the same dyke. than one, the longitudinal axis of

Plot Plan.doc 7
PIPING ENGINEERING CELL

vessels should be parallel to each guidelines in SMPV, which are


other. reproduced in Table 1 & Table 2.
5.2.10 Notwithstanding anything contained
5.2.5 Top surfaces of vessels are required to in the sub rules above, the storage of
be made in one plane. LPG can be placed underground or
covered by earth in such a manner and
subject to such conditions as may be
5.2.6 Vessels installed with their dished specified by the notifications by the
ends facing each other shall have Central Government.
screen walls in between them. 5.2.11 Above ground vessel for storage of
corrosive flammable or toxic gas in
5.2.7 The distances to be observed between liquefied state shall be provided with
two vessels in one installation and enclosure wall all around the ground.
distance from building or a group of The minimum distance between vessel
buildings or line of adjoining property and enclosure wall shall be the
are given in Table 1 & Table 2. diameter of the vessel or five meters
whichever is less. Ground shall be
5.2.8 The area where vessels, pumping graded to form a slope away from
equipment, loading and unloading pumps, compressors or equipments.
facilities and direct fired vaporizers are The height of the enclosure shall be 30
provided shall be enclosed by an cm on the upper side and gradually
Industrial Type Fence at least 2 m high increasing to 60 cm on the lower side,
along the perimeter of Safety Zone. at the end of which, a shallow sump
for collection of spilled liquid if any,
5.2.9 The minimum distances to be observed shall be provided.
around installation shall be as per the

TABLE 1
Minimum Safety distances for flammable, corrosive & toxic gases

S. No. Water capacity of Vessels Minimum distance Minimum distance


( in litres ) from Building or between Pressure
Group of bldgs/line Vessels
of adjoining property

i Not above 2000 5 metres 1 metre

ii Above 2000 but not 10 metres 1 metre


above 10000

iii Above 10000 but not 15 metres 1.5 metres

Plot Plan.doc 8
PIPING ENGINEERING CELL

above 20000

iv Above 20000 but not 20 metres 2 metres


above 40000

v Above 40000 30 metres 2 metres

TABLE 2
Minimum Safety distances for non-toxic gases

Sl. No. Water Capacity of Vessels Minimum distance MinimumDdistan


( in litres ) from Building or ce between
Group of Bldgs/line Pressure Vessels
of adjoining
Property

i Not above 2000 3 metres 1 metre

ii Above 2000 but not 5 metres 1.5 metre


above 10000

iii Above 10000 but not 10 metres 2 metres


above 20000

iv Above 20000 15 metres Diameter of larger


vessel

Note: The distances specified above may be reduced by the Chief Controller in cases where
he/she is of the opinion that additional safety measures have been provided.

Plot Plan.doc 9
PIPING ENGINEERING CELL

TABLE - 3
Minimum Clearances to be considered in a Process Unit
(As per OISD guidelines)

1. Process units to flare 90M

2. Storage tanks class A/B 0.5D or 15M for Class


A/B, 6M for Class C

3. Storage tank to vehicle unloading 15M - Class A/B


3M - Class C

4. Vehicle unloading to boundary facing 15M - Class A/B


3M - Class C

5. Storage tank periphery to boundary facing 15M - Class A/B


4.5M - Class C

6. Electrical substation to process units 15M

7. Head room over main refinery roads 7.6M

8. Head room over main service roads 6M

9. Head room over secondary roads 4.5M - for cranes


3.6M - for trucks

Plot Plan.doc 10
PIPING ENGINEERING CELL

Fig. 1

Fig. 2

Plot Plan.doc 11
PIPING ENGINEERING CELL

Fig. 3

Fig. 4: EQUIPMENT LAYOUT - EXPLOSIVE TANK FARM

Plot Plan.doc 12

You might also like