You are on page 1of 13

Saudi Aramco

BI 10-00035
Increase Dhahran-Riyadh (DR-1) Product Pipeline Capacity Project
Contract No. 6600022340
Contractor : Gulf Consolidated Contractors Co. Ltd (GCC)

Minutes of Weekly Progress Meeting

Date : 15-Nov-11
Start Time : 9:00 AM
End Time : 12:00 PM
Location : Dhahran Tank Farm

Attendees
Names Organization Tel No e-mail ID
Ali Buhuligah ERDD 862-2957
Wesam ERDD 876-3886
Abdulhameed Alahanim ERDD 876-3886
Faisal Al sayari ERDD 876-3886
Ayyaz Akmal SAPID 0558977621 ayyaz.akmal@aramco.com
Sami Al Dossary SAPMT 872-6608 dossssig@aramco.com
Thamer Motailoq SAPMT 0568301002 motailtm@aramco.com
Abdul Mohsen Hejji SAPMT 872-6608 hijjah0@aramco.com
Richard Tabora SAPMT 872-6608 richard.tabora@aramco.com
Saju Chellapan GCC 802-6871 schellapan@gccksa.com
Jojo Tumbaga GCC 802-6871 jtumbaga@gccksa.com
Ramachandran Vattolli GCC 802-6871 rvattolli@gccksa.com
Ibrahim Quraishi GCC 802-6871 mquraishi@gccksa.com
Anthony Loria GCC 802-6871 aloria@gccksa.com
Minutes of Weekly Progress Meeting
November 15, 2011

Item No Items Discussed / Action required Issue date Action by

1 Construction Issues
1.1 Dhahran Bulk Plant

The vendor of the actuator for EIV valve in Dhahran


1.1.1 recommended to support the actuator. GCC advised SAPMT that it 14-Sep-11 SAPMT
will be an extra work. There is no final decision yet.

GCC followed up regarding the instruction of SAPMT where to


1.1.2 14-Sep-11 SAPMT
deliver the excess Aramco materials.

GCC informed SAPMT that foam system pumps and relief valves
1.1.3 were sent back to Dhahran.They must be formally retutned to 14-Sep-11 INFO
Operations.

GCC informed SAPMT regarding the workability issue in removing


1.1.4 the dead leg. GCC asked SAPMT to issue the required drawing for 14-Sep-11 SAPMT/GCC
new foundation which is required prior to removing the dead leg.

The sight glass for Pump A were installed.


The delivery date of sight glass for Pump B needs to be followed
up.
1.1.5 The SS spool for TCV is copleted. Needs gate pass to bring to 15-Nov-11 GCC/SAPMT
Halliburton for lube oil flushing.ETC is 10 days

The new ETC of destaging pum X14-G-100A is November 30, 2011

The fireproofing or structural frames of sprinkler system is still


1.1.6 11-Oct-11 INFO
disputed on scope of work.

GCC asked for the complete details and drawings to be able to


1.1.7 11-Oct-11 SAPMT
quote for the installation of sunshade for foam water skid.

Pump G-0961A/B has a product and lube oil leak. Aramco and
1.1.8 GCC are coordinatiing with Flowserve to resolve it. The ETA for 11-Oct-11 SAPMT
mechanical seal must be followed up.

GCC informed SAPMT that spare filters and other consumables for
1.1.9 HVAC must be brought by Aramco from Zamil.To be double 11-Oct-11 SAPMT
checked whose scope covers providing the consumables.

page 2 of 13
Item No Items Discussed / Action required Issue date Action by

GCC asked assistance from SAPMT to contact the RTU personnel


for MOV-10131 connection to the tank farm. The tag for jump
1.1.10 11-Oct-11 SAPMT
over line was seen as X14 which is not applicable in jump over.
GCC asked SAPMT to issue revised IFC drawing.

GCC asked permission to by-pass ESD system to terminate the fire


1.1.11 alarm cables inside cabinet at SIB. SAPMT will check the 15-Nov-11 SAPMT
possibility.

Operations asked for platform to make the newly installed


1.1.12 actuators accessible. GCC will be willing to install if SAPMT 15-Nov-11 INFO
instructed them and will be considered as change order.

GCC informed that the actuator of X14-ZV-2212 was sent to


1.1.13 SAECO for repair. SAPMT and Operations requested GCCfor 15-Nov-11 GCC
contact details of SAECO.

Operations raised a concern regarding the leak on the welding


boss of the strainer line of pump-G-0961B. GCC will send QC
1.1.14 15-Nov-11 SAPMT/GCC
personnel to investigate and to inform the result of investigation
to have an appropriate action.

1.2 Khurais Pump Station 2

GCC raised the issue regarding the mismatched between the filter
1.2.1 flange which is Class 150 and the suction line which is Class 600. 14-Sep-11 INFO
GCC is sourcing out for vendor, however, TBN 3 must be signed.

GCC and SAPMT discussed the works to be done prior to four hour
motor run test. The run test will not be done unless issues such as 15-Nov-11
1.2.2 SAPMT/GCC
relays coordination settings and study,multilin settings and other
engineering matters was resolved.

1.3 Riyadh Bulk Plant/Tank Farm

SAPMT handed over the CD of 12" line Surge Relief Line IFC. GCC
will study the workability but informed SAPMT that they will start
1.3.1 after the apporval of change order.GCC asked for assistance from 14-Sep-11 INFO
SAPMT to check from their stock for materials as another option
to minimize time of the procurement process.

page 3 of 13
Item No Items Discussed / Action required Issue date Action by

GCC asked SAPMT for the design on the support for the vertical
1.3.2 15-Nov-11 SAPMT/GCC
loop in the 12" Surge relief line in North Riyadh Tank Farm.

GCC is following SAPMT to coordinate with operations to allow to


1.3.3 unload the chemical detergent. GCC advised SAPMT that the 14-Sep-11 SAPMT
stand by cost shall be compensated by SAPMT.

GCC is following up approval of the proposed drawing related to


1.3.4 15-Nov-11 GCC
road sign and marking for chemical trucks.

1.4 Qassim Bulk Plant

GCC is following SAPMT to coordinate with operations to allow to


1.4.1 unload the chemical detergent. GCC advised SAPMT that the 14-Sep-11 SAPMT
stand by cost shall be compensated by SAPMT.

GCC is following up approval of the proposed drawing related to


1.4.2 15-Nov-11 GCC
road sign and marking for chemical trucks.

1.5 Abqaiq GOSP 5


GCC asked SAPMT for the approval of the work procedure in
removing the base plates of relocated pumps and motors. They
1.5.1 14-Sep-11 INFO
also asked if the foundation will be removed and requested them
to issue change order if ever.

page 4 of 13
Item No Items Discussed / Action required Issue date Action by

2 QA/QC Issues
GCC asked SAPMT for the availability of PDD cable crew for
2.1 termination of MV cable in Khurais.

GCC asked assistance form SAPMT for signing of loop folders or


2.2 inform GCC if there are any comments.

GCC asked assistance from SAPMT for RV numbers of PZVs. GCC


2.3 sent the 3099A forms already.

2.4 GCC asked for the data sheets for instruments for Khurais.

GCC informed SAPMT regarding the conflict of data between Data


2.5 sheet and NMR for Surge Relief Valve in Riyadh Tank Farm. GCC
asked formal instruction where to comply among the two data.

GCC informed SAPMT regarding the energization packages that


needs to be signed. It was agreed that GCC will first approach the
2.6 concerned personnel and will be assisted by SAPMT if there is a
need.

3 Change Order
SAPMT informed GCC that they will be notified for the schedule of
3.1 15-Nov-11 INFO
dropping of Bid for TBN 3 and COR 6

COR # 3 is negotiated and GCC is waiting for the copy of contract


3.2 15-Nov-11 INFO
change order.

GCC asked SAPMT for the approval of the change order for the
3.3 11-Oct-11 CLOSED
modification of block valves for detergent injection skids.

4 Other Issues

SAPMT informed GCC to clear the issued NCR. GCC is directly


4.1 14-Sep-11 GCC
coordinating with the vendor (ABB).

page 5 of 13
Item No Items Discussed / Action required Issue date Action by

GCC asked SAPMT for the elctronic copy of the native file for As
4.2 built activities. They informed SAPMT that making as built 11-Oct-11 GCC
drawings was awarded to a subcontractor (SASEC).

page 6 of 13
Item No Items Discussed / Action required Issue date Action by

GCC asked assistance from SAPMT to convince the concerned


departments to accept electronic files for Project Quality Records
(PQR). If the proposal was not accepted, GCC needs information
4.3 11-Oct-11 GCC
on what are the documents required and how many copies
each.SAPMT asked GCC to submit the list of documents which are
ready for submittal.

Prepared by Concurred by

Jojo Tumbaga
Project Manager, GCC

page 7 of 13
Weekly Progress Meeting
November 15, 2011

ETC REMARKS

page 8 of 13
ETC REMARKS

page 9 of 13
ETC REMARKS

page 10 of 13
ETC REMARKS

GCC to organize
25-Sep-11 meeting with
vendor

page 11 of 13
ETC REMARKS

page 12 of 13
ETC REMARKS

Gabgab I. Gabgab
Project Engineer, SAPMT

page 13 of 13